02.15.4 For other than Dhaka, Ctg., Sylhet, Rajshahi, Barishal, Khulna metropolitan area and cum Tk.

cum Tk. 291.00


N'ganj district

02.16 Site Development/Improvement by carted earth or dredged sand, sandy silt (free
from any organic, foreign, environmental hazardous substances) carried by head or
truck or any other meansl in/c cost of cutting or by dredging of sand, sandy silt, all;
in/c local carrying, placing the earth/sand, sandy silt in the designated area,
maintaining slopes, breaking lumps, levelling and dressing in layers up to finished
level etc. all complete as per direction and accepted by the engineer in charge.

02.16.1 For Dhaka Metropolitan Area  

02.16.1.1 By Other than dredgeing cum Tk. 441.73

02.16.1.2 By Dredging including necessary systems there off cum Tk. 265.00

02.16.2 For Chittagong / Sylhet/ Narayanganj Area  

02.16.2.1 By Other than dredgeing cum Tk. 284.25

02.16.2.2 By Dredging cum Tk. 188.00

02.16.3 For Rajshahi / Barishal / Khulna metropolitan area  

02.16.3.1 By Other than dredgeing cum Tk. 250.70

02.16.3.2 By Dredging cum Tk. 164.00

02.16.4 For other than Dhaka, Ctg., Sylhet, Rajshahi, Barishal, Khulna metropolitan area and  
N'ganj district

02.16.4.1 By Other than dredgeing cum Tk. 217.16

02.16.4.2 By Dredging cum Tk. 140.00

02.17 Mechanical compaction of earth beyond plinth area, required for pre-approved cum Tk. 364.00
specific engineering purpose in 150mm layers including leveling, watering and
consolidation each layer with chain dozer, grader, roller etc. to achieve minimum dry
density of 90% with optimum moisture content (modified proctor test) up to finished
level all complete and accepted by the engineer subject to submission of the method
statement.

………………….. END OF DIVISION TWO …………………..


DIVISION 03 : BRICK SOLING, CC, DPC ETC.
Item No. Description of Item Unit Unit Rate

03.1 One layer of brick flat soling in foundation or in floor with first class or picked jhama sqm. Tk. 355.00
bricks including preparation of bed and filling the interstices with local sand, leveling
etc. complete and accepted by the Engineer.

03.2 One layer of Herring bone bond (HBB) brick soling in foundation or in floor with first sqm. Tk. 562.00
class or picked jhama bricks including preparation of bed and filling the interstices
with local sand, leveling including the supply of water,other charges, costs of tools
and plants etc. all complete and accepted by the Engineer.

03.3 Brick on end edging including preparation of bed and filling the interstices with local rm. Tk. 88.00
sand, leveling, maintaining alignment grid etc. all complete and accepted by the
Engineer.

03.4 Mass concrete (1:3:6) in foundation or floor with cement, sand (F.M. 1.2) and picked
jhama chips including breaking chips, screening, mixing, laying, compacting to levels
and curing for at least 7 days including the supply of water, electricity and other
charges and costs of tools and plants etc. all complete and accepted by the
Engineer. (Cement: CEM-II/A-M)

03.4.1 Mass concrete in foundation (1:3:6) with cement, brick chips and sand of F.M. 1.2 cum Tk. 6,319.00

03.4.2 Mass concrete in floor (1:3:6) with cement brick chips and sand of F.M. 1.2 cum Tk. 6,241.00

03.5 Mass concrete (1:2:4) in foundation or floor with cement, sand (F.M. 1.2) and picked
jhama chips including breaking chips, screening, mixing, laying, compacting to levels
and curing for at least 7 days including the supply of water, electricity and other
charges and costs of tools and plants etc. all complete and accepted by the
Engineer. (Cement: CEM-II/A-M)

03.5.1 Mass concrete in foundation (1:2:4) with brick chips and local sand of F.M. 1.2 cum Tk. 7,481.00

03.5.2 Mass concrete in floor (1:2:4) with brick chips and local sand of F.M. 1.2 cum Tk. 7,403.00
03.6 Damp proof course (DPC) (1:1.5:3) in cement concrete with cement, sand (F.M. 1.2)
and picked jhama or stone chips including breaking chips, screening, centering,
shuttering, casting, curing and finished with a coat of bitumen including the supply of
water, electricity and other charges and costs of tools and plants etc. all complete
and accepted by the Engineer. (Cement: CEM-II/A-M)

03.6.1 75 mm or 3" thick damp proof course (1:1.5:3) with brick chips and 50% Sylhet sand sqm. Tk. 1,002.00
(F.M. 2.2) and 50% local sand (F.M. 1.2)

03.6.2 75 mm or 3" thick damp proof course (1:1.5:3) with Sylhet sand (F.M. 2.2) and stone sqm. Tk. 1,174.00
chips.

03.6.3 150 mm or 6" thick damp proof course (1:1.5:3) with Sylhet sand (F.M. 2.2) stone cum Tk. 12,711.00
chips and water-proofing admixture/agent approved by the Engineer.

03.7 Supplying and laying of single layer polythene sheet weighing one kilogram per 6.5 sqm. Tk. 34.00
square meter in floor or any where below cement concrete complete in all respect
and accepted by the Engineer.

You might also like