You are on page 1of 4

MAPÚA INSTITUTE OF TECHNOLOGY

Muralla St. Intramuros, Manila


School of Civil, Environmental and Geological Engineering

FIELD WORK NO. 7


DIFFERENTIAL LEVELING

COURSE AND SECTION: CE 120-0F/B7

SUBMITTED BY:

SN:

NAME: Pineda, Jose Jeffrey Zoilo F. STUDENT NUMBER: 2014100720

GROUP NO: 7 CHIEF OF PARTY: Cezanne Chan Talosig

DATE OF FIELDWORK: February 4, 2016

DATE OF SUBMISSION: February 11, 2016

SUBMITTED TO:
GRADE
PROFESSOR: ENGR. BIENVENIDO CERVANTES
FINAL DATA SHEET

FIELD WORK 7 (DIFFERENTIAL/PROFILE LEVELING)

DATE: February 4, 2016 GROUP NO. 7


TIME: 12 P.M. – 4:30 P.M. LOCATION: Intramuros wall
WEATHER: Sunny PROFESSOR: Engr. Cervantes

STATION B.S H.I. F.S. I.F.S. ELEV REMARKS


BM1 1.4m 201.4m - - 200m
00+010 - - 3.81m 197.59m
00+020 - - 3.85m 197.55m
00+030 - - 3.83m 197.59m
00+040 - - 3.85m 197.55m
00+050 - - 2.50m 198.90m Ramp
00+060 - - 1.27m 201.13m
00+070 - - 1.26m 200.14m
00+080 - - 1.27m 201.13m
00+090 - - 2.38m 199.02m
00+100 - - 2.40m 199m
00+110 - - 2.39m 199.01m
00+120 - - 2.42m 198.98m

SAMPLE COMPUTATION FOR THE RESULTS:

FOR ALL POINTS

H.I. = ASSUMED ELEVATION + B.S.

ELEVATION = H.I. – F.S.

FOR H.I.

H.I. = 200m + 1.40m

H.I. = 201.40m

FOR ELEVATION OF 00+010

ELEVATION = 201.4m – 3.81m

ELEVATION = 197.59m
A sample illustration, using AutoCAD, of the group’s set up during the field work

CONCLUSION

With the aid of a Precise level, we were able determine the elevation
of a specific path easily. By using the leveling rod and precise level
instrument, we were able to record the back sight and the foresight, from a
position where our precise level is fixed, for every 10 meter point inside the
120 meters span.

Precise level is the most useful instrument in getting the elevation of


a specific path/lot and also the right instrument to be used in differential
leveling that will give you the most precise results (disregarding the human
error). It will help you in future constructions for you may know the elevation
of a specific lot where you want to build your structure.

RECOMMENDATION

The next group that would survey inside the Intramuros wall must ask
for a permit first at least from their professor and give it to the ones who are
guarding the wall for they may interrupt your field work constantly. And if
there are no permits given to you by the prof, get the permit at the main
office of the Intramuros.
DOCUMENTATION

The picture on the left indicates that the group is


getting the IFS on the road that has a 120 meters
span.

The picture on the right shows that


the instrument man is getting the
IFS of a specific point.

The picture on the left shows


the office of Palacio Del
Gobernador where our group
got the permit for surveying
inside the walls of Intramuros,
Manila.