Professional Documents
Culture Documents
Ceng 125 Learning Hand Out 2 PDF
Ceng 125 Learning Hand Out 2 PDF
Lesson 2
Detailed Quantity Survey
Learning Objectives:
Upon completion of the lesson, the learners will be able to:
1. Discuss the methods in determining the quantities of materials needed per scope of
work/elements.
2. Apply techniques in computing for quantities of materials
An estimator must know how to compute the length of lines, areas of plain figures and volume
of solids which may represent parts of building for which quantities of materials are to be
estimated. (Tagayun, 2002). It is to take note that consistency in using dimensions is a must. One
can adopt the metric system (meter, centimeter, millimeter). When computing, see to it that the
considered measurements are in just a single unit. Conversions can be made as needed by using
conversion tables (refer to Fajardo. Simplified Construction Estimate, Charter 1-3. Latest Ed.)
In estimating quantities of materials, center line measurements are advisable. Other
references consider inside dimensions. Allowances for wastage may be added to computed
quantities.
Earthwork in excavation and backfilling of soil up to required depth is required for construction
of foundation and trenches. Excavation and backfilling of soil is a very important part of
construction process, and care must be taken. Correct measurement of excavation and backfilling
is required because excavation cost is major part of the foundation construction .
(https://theconstructor.org/practical-guide)
VOLUME OF EXCAVATION:
Volumes are computed from cross-section measurements by the average end area
method.
By the Average-End-Area method: Volume = L x (A1+A2)/2
Also, where not practical to measure material by the cross-section method due to erratic
location of isolated deposits, acceptable methods involving three dimensional measurements may
be used to measure material in the original position. Equations for these measurements are:
Volume (m3) = Length x Width x Depth
(http://www.state.in.us/indot/files/Earthworks_Chapter_06.pdf)
1
Measurements for volume are nothing more than applying basic distance and elevation
measurements to determine the locations and elevations of points where the volume is to be
determined. The key to volume calculation is the determination of area. Most volume calculation
formulas contain within them the formula for an area, which is simply multiplied by the height to
determine the volume. For instance, the area of a circle is pi times the radius squared. The volume
of a cylinder is the area of the circle times the height of the cylinder. If an area can be determined,
it is generally easy to determine the volume. (https://civilblog.org/)
VOLUME OF EARTHFILL
To estimate the quantity of earth fill needed to fill up hollow spaces in the building, compute
its volume and multiply by 1.25. The 25% is added as allowance for compaction of the loose soil
to be delivered. That is,
Volume of earth fill required = volume of space to be filled x 1.25
The volume method is generally used and can be applied in estimating the materials for all
concrete members employed in a construction project. The concrete volume is being multiplied
by factors appropriate for a specified class of concrete mixture in order to obtain the estimated
quantities of cement, sand and gravel.
To use tables from the text book and other references, the estimated quantities of cement,
sand and gravel can be computed. However, this is only limited to concrete members with sizes
specified on tables.
In concrete proportioning, from Simplified Construction Estimate by Max B. Fajardo, the
following table is suggested.
Table 1. Concrete proportioning
Note: the current common available cement in the market is 40 kgs/ bag
2
By volume method:
3
3. After that, compute the total length of bars which is equal to the number of required bars
multiply by the length of one bar. If the same size of bars is used in both direction, then
you can sum up both quantity of the bars
4
Sample Problem 1:
Determine the number of 12mm diameter steel bars including tie wire in kilograms if there are
30 pieces of 1.15m x 1.15m independent square footing.
Figure 2. Plan and elevation (from Simplified Construction Estimate by Max Fajardo
Solution:
5
The quantity of the materials needed for a certain masonry work made of concrete hollow
blocks generally comprises of the following items:
Concrete hollow blocks.
Cement and sand for block laying.
Cement, sand and gravel filler for the hollow core or cell.
Cement and fine sand for plastering.
Cement and fine sand and gravel for foundation or footing.
Reinforcing steel bars and
Tie wires
Note: The size of concrete hollow block 1.) 0.20m; 2.) 0.40m; & 3.) varies from 0.10m, 0.125m, 0.15m, 0.20m
Sample Problem 2:
A concrete hollow block wall has a general dimension of 3.00 meters high by 4.00 meters
long. Determine the number of CHB, cement and sand required to construct the wall.
6
Solution:
By Fundamental Method
1. Divide the height of the fence by the height of one block
3 / 0.20 = 15 layers
2. Divide the length of the fence by the length of one block
4 / 0.40 = 10 pieces
3. Multiply the result of step 1 by step 2.
15 x 10 = 150 pieces CHB
By Area Method
Note:
To establish how many pieces of CHB can cover up one square meter:
Area of one CHB = 0.20m x 0.40m = 0.08 square meter
Number of CHB per square meter = 1 / 0.08 =12. 5 pieces
Therefore,
There are 12.5 pieces CHB for every one square meter
Table 2-1 from Simplified Construction Estimate by Max Fajardo is useful in computing for mortar
and plaster of concrete CHB wall.
Also, the following tabulated values are useful in finding the cement mortar of concrete hollow
blocks (CHB) which can be done in three ways.
a. By volume method (using table 2-1)
b. By the area method (using table 2-2)
c. By per hundred block method (using table 2-3)
7
Table 2-2 QUANTITY OF CEMENT AND SAND FOR CHB MORTAR
PER SQUARE METER
Size of Cement in bags, 40 kg
CHB Mixture Sand
(cm) A B C D (cu.m.)
10x20x40 0.792 0.522 0.394 0.328 0.0435
15x20x40 1.526 1.018 0.763 0.633 0.0844
20x20x40 2.26 1.5 1.125 0.938 0.125
From Simplified Construction Estimate by Max Fajardo
Table 2-3 QUANTITY OF CEMENT AND SAND PER ONE
HUNDRED BLOCKS
Size of Cement in bags, 40 kg
CHB Mixture Sand
(cm) A B C D (cu.m.)
10x20x40 6.336 4.176 3.152 2.624 0.348
15x20x40 12.150 8.104 6.072 5.064 0.675
20x20x40 18.072 12.000 9.000 7.504 1.000
From Simplified Construction Estimate by Max Fajardo
Sample Problem 3:
Continuing sample problem 2, determine how many bags of cement and sand needed to
install the 10 x 20 x 40 cm CHB using class B mortar.
8
Sample Problem 4:
From sample problem 3, list down the cement and sand necessary to plaster the two faces
of the wall at an average thickness of 0.016 mm class B mixture.
9
Sample Problem 5:
From figure 3-6, sample problem 2, determine the number of:
a) 10 x 20 x 40 cm CHB
b) Vertical reinforcement 10 mmφ spaced at 80cm
c) Horizontal reinforcement 10 mmφ at every 3 layers
Sample Problem 6:
Continuing the solution of sample problem 5, find the required tie wire in kilograms if the
reinforcements are spaced at:
1. Vertical bars spaced 0.80 and one horizontal bar after 3 layers of the block
2. Tie wire in kilograms
Solution
1. Solve for the wall area.
Area = Length x Height
A = 3 x 4 = 12 square meters
2. Refer to Table 3-6, tie wire is at 30 cm long
12 m2 x 0.024 = 0.29 kg. say order 0.50 kg #16 GI wire
10
Feedback Activity
1. Solve Problem Exercise on pages 35, 36 & 37, 1 to 5…….Simplified Construction Estimate
by Max Fajardo.
2. If the natural grade line of soil of Figure 1-19/page 35 is 2.0 m from the bottom of the
footing, solve for the total concrete materials (class A) needed to support Figure 1-20.
Solve also for the total volume of excavation.
Note:
A. In solving for concrete:
use volume method only
use 40 kgs of cement/bag
B. All answers should be handwritten(Arial 12)…picture/scan then send to
concosteng51@gmail.com . Deadline of submission October 19, 2020 6:00 pm.
11