You are on page 1of 1

RATE ANALYSIS

(Based on MSR 2015)

Sl. Quan
Description Unit Rate Amount Remark
No. tity
1 Earth work in excavation in foundation trenches or drains including dressing of sides and ramming of
bottoms lift upto 1.5 metres including getting out the excavated soil and disposal of surplus excavated
soil as directed within a lead of 50 metres
a) Hard/Dense
Cost Soil.
for 1.00 cum. Rs. 140.10

2 Providing and laying cement concrete in foundation and plinth excluding the cost of centering and
Cost for 1.00 m3 Rs. 5,243.40
Carriage of material by mechanical transport
(A) Stone metal 40mm and above.
3 3
0.89 m @ Rs.769.60 /m = Rs. 684.94
3 3
(B) Sand 0.47 m @ Rs.657.62 /m = Rs. 309.08
(C) Cement 0.156 MT @ Rs.289.52 /MT = Rs. 45.17
Rs. 6,282.59

3 Cement concrete 1:3:6 mix with stone aggregate 20 mm nominal size mechanically mixed and
Cost for 1.00 m3 = Rs. 5,949.30
Carriage of material by mechanical transport
(A) Stone metal 40mm and above.
3 3
0.89 m @ Rs.769.60 /m = Rs. 684.94
3 3
(B) Sand 0.47 m @ Rs.657.62 /m = Rs. 309.08
(C) Cement 0.22 MT @ Rs.289.52 /MT = Rs. 63.69
Rs. 7,007.02