Project Owner Dau Tieng Tay Ninh Energy Joint Stock Company Power Plant in Vietnam Area RFI No. Date QA&QC-DT- Element Format No. Page No. FRMC-021 ITP No. DWG No.
The following items have been checked and cleared YES NO N/A
1 CABLE TRAY MATERIAL
1.1 Checking mill test certificate 1.2 Visual inspection of galavanize coatings for damage 1.3 Checking the thickness of galvanized coatings 1.4 Dimensional check for all components, holes, overall length, markings MATERIAL DESCRIPTION Width Thickness Galvanizing Name Specification Material (mm) (mm) (μm) Design Actual Design Actual Design Actual