Professional Documents
Culture Documents
PROJECT CONTRACTOR
RIYADH METRO
Package 3 (Lines 4)
Method Statement for Chemical Rebar
Anchor System-HILTI
M3-AZM-MST-CIV- 00000 Rev
FAST Organization:
Author Checked Reviewed Approved
Name Name Name Name
Role Role Role Role
Date & Signature Date & Signature Date & Signature Date & Signature
Riyadh Metro Package 3 (Lines 4)
Abbreviations
Abbr. Definition
FAST Main Contractor
KKIA King Khalid International Airport
ITP Inspection Test Plan
PQP Project Quality Plan
HSE Health, Safety and Environment
RAMPED Riyadh Advanced Metro Project Execution and Delivery
KSA Kingdom of Saudi Arabia
RFI Request for Inspection
QCI Quality Control Inspection
QCP Quality Control Procedures
QMS Quality Management System
ISO International Organization of Standardization
NCR Non-Conformance Report
TABLE OF CONTENTS
1 PURPOSE 5
2 SCOPE OF WORK 5
3 PERMIT AND LICENSE 5
4 STANDARDS AND SPECIFICATION 5
5 MACHINERY AND MANPOWER 6
6 METHODOLOGY 7
7 QA/QC PLAN 9
8 HSE PLAN 10
9 APPENDIX 10
1 PURPOSE
The purpose of this method statement is to provide a procedure and method for execution of Chemical Rebar
anchor system at 4G1 Station and Cut & Cover Tunnels Sides as required.
This document describes the execution of Chemical rebar anchorage system from HILTI with approved anchor
chemical material, at required location, depth, with dia of rebar and its testing. Making sure to comply with
the project specification and required standards. All concerned personnel must be familiarized with the
sequence of activities, utilization of resources, and execution of the works in compliance with applicable Safety
and Quality Procedures.
2 SCOPE OF WORK
This document covers the execution of Chemical rebar anchorage system from HILTI from Chainage 26+039
to Chainage 27+569 with approved anchor chemical material, in prescribed process from HILTI, at 4G1 and
Cut & Cover Tunnel wherever is required.
Necessary permits shall be provided by FAST from KKIA prior start of the Anchoring activity. Licenses of
all machineries and operators involved in Anchoring shall be visible for review and checking.
ID Description
ASTM A 615 Standard Specification for Deformed steel rebar for concrete reinforcement
ASTM C900-15 Standard for Test method of Pullout strength of Hardened concrete
ACI-318 Building code Requirements for structural concrete
ASTM C309-11 Standard Specification for Liquid Membrane-Forming Compounds for Curing
Concrete
Machinery List ‐
Serial No Description with Capacity Number of Machines
1. HILTI Drilling Machine with Bit 2 nos
2. Cleaning brush 4 nos
3. HILTI injectable Dispense 4 nos
4. Curing Agent Sprayer 1 nos
5. Ancillary equipments As required
Manpower List ‐
Manpower (Staff) Quantity
Project Manager 1
Cons. Manager 1
QA/QC Manager 1
Site Engineer 1
QC Inspector 1
Safety Officer 2
Senior Surveyor 0
Surveyor Aid 1
Foreman 1
Operators 2
Electrician 1
Manpower (Labour) Quantity
Gang Leader 2
Skilled Labour for Drilling and Installation 4
Skilled Labour for Cleaning and Preparation 2
Semi‐Skilled Labour Housekeeping 2
Flag Man 1
6 METHODOLOGY
Material quality
Part Material
rebar Geometry and mechanical properties according to DIN 488-2:1986 or
BSt 500 S E DIN 488-2:2006
Setting
Installation equipment
Anchor size Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø25 Ø28 Ø32
Rotary hammer TE 2 – TE 16 TE 40 – TE 70
Other tools compressed air gun or blow out pump, set of cleaning brushes, dispenser
Setting instruction
Drill Hole to the required embedment depth with a hammer drill set in
rotation-hammer mode using an appropriately sized carbide drill bit.
Bore hole cleaning Just before setting an anchor, the bore hole must be free of dust and debris.
Brush 4 times with the specified brush size by inserting the steel brush Hilti
HIT-RB to the back of the hole (if needed with extension) in a twisting
motion and removing it.
The brush must produce natural resistance as it enters the bore hole -- if
not the brush is too small and must be replaced with the proper brush
diameter.
Blow out again with manual pump at least 4 times until return air stream is
free of noticeable dust.
10 / 2012 547
AN-AC-D2147-2015-Rev 0
7
Hilti HIT-HY 200
with rebar
Brush 2 times with the specified brush size by inserting the steel brush Hilti
HIT-RB to the back of the hole (if needed with extension) in a twisting
motion and removing it.
The brush must produce natural resistance as it enters the bore hole -- if
not the brush is too small and must be replaced with the proper brush
diameter.
Blow again with compressed air 2 times until return air stream is free of
noticeable dust.
Injection preparation
Tightly attach new Hilti mixing nozzle HIT-RE-M to foil pack manifold (snug
fit). Do not modify the mixing nozzle. Observe the instruction for use of the
dispenser. Check foil pack holder for proper function. Do not use damaged
foil packs / holders. Swing foil pack holder with foil pack into HIT-
dispenser.
Inject adhesive from the back of the borehole without forming air voids
Inject the adhesive starting at the back of the hole, slowly withdrawing the
mixer with each trigger pull. Fill holes approximately 2/3 full, or as required
to ensure that the annular gap between the anchor and the concrete is
completely filled with adhesive along the embedment length.
Overhead installation and installation with embedment depth hef > 250mm.
For overhead installation the injection is only possible with the aid of
extensions and piston plugs. Assemble HIT-RE-M mixer, extension(s) and
appropriately sized piston plug. Insert piston plug to back of the hole and
inject adhesive. During injection the piston plug will be naturally extruded
out of the bore hole by the adhesive pressure.
548 10 / 2012
AN-AC-D2147-2015-Rev 0
8
Hilti HIT-HY 200
with rebar
For overhead installation use piston plugs and fix embedded parts with e.g.
wedges
For detailed information on installation see instruction for use given with the package of the product.
10 / 2012 549
AN-AC-D2147-2015-Rev 0
9
Hilti HIT-HY 200
with rebar
Approved PROFIS
Small edge Variable European
Tensile CE automatic Anchor
Concrete distance embedment Technical
zone conformity cleaning design
and spacing depth Approval
while drilling software
Approvals / certificates
Description Authority / Laboratory No. / date of issue
ETA-11/0493 / 2012-08-08
a) (Hilti HIT-HY 200-A)
European technical approval DIBt, Berlin
ETA-12/0084 / 2012-08-08
(Hilti HIT-HY 200-R)
a) All data given in this section according ETA-11/0493 and ETA-12/0084, issue 2012-08-08.
544 10 / 2012
AN-AC-D2147-2015-Rev 0
4
Hilti HIT-HY 200
with rebar
Embedment depth a) and base material thickness for the basic loading data.
Mean ultimate resistance, characteristic resistance, design resistance, recommended loads.
Data according ETA-11/0493 and ETA-12/0084, issue 2012-02-06
Anchor size Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø25 Ø28 Ø32
Typical embedment depth [mm] 80 90 110 125 145 170 210 270 300
Base material thickness [mm] 110 120 145 165 185 220 275 340 380
a) The allowed range of embedment depth is shown in the setting details. The corresponding load values can be
calculated according to the simplified design method.
Mean ultimate resistance: concrete C 20/25 – fck,cube = 25 N/mm², anchor rebar BSt 500S
Data according ETA-11/0493 and ETA-12/0084, issue 2012-02-06
Anchor size Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø25 Ø28 Ø32
Non cracked concrete
Tensile NRu,m BSt 500 S [kN] 29,4 45,0 65,1 87,6 116,1 148,6 204,0 297,4 348,4
Shear VRu,m BSt 500 S [kN] 14,7 23,1 32,6 44,1 57,8 90,3 141,8 177,5 232,1
Cracked concrete
Tensile NRu,m BSt 500 S [kN] - 18,8 38,5 51,1 67,7 99,3 145,4 212,0 248,3
Shear VRu,m BSt 500 S [kN] - 23,1 32,6 44,1 57,8 90,3 141,8 177,5 232,1
Characteristic resistance: concrete C 20/25 – fck,cube = 25 N/mm², anchor rebar BSt 500 S
Data according ETA-11/0493 and ETA-12/0084, issue 2012-02-06
Anchor size Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø25 Ø28 Ø32
Non cracked concrete
Tensile NRk BSt 500 S [kN] 24,1 33,9 49,8 66,0 87,5 111,9 153,7 224,0 262,4
Shear VRk BSt 500 S [kN] 14,0 22,0 31,0 42,0 55,0 86,0 135,0 169,0 221,0
Cracked concrete
Tensile NRk BSt 500 S [kN] - 14,1 29,0 38,5 51,0 74,8 109,6 159,7 187,1
Shear VRk BSt 500 S [kN] - 22,0 31,0 42,0 55,0 86,0 135,0 169,0 221,0
Design resistance: concrete C 20/25 – fck,cube = 25 N/mm², anchor rebar BSt 500 S
Data according ETA-11/0493 and ETA-12/0084, issue 2012-02-06
Anchor size Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø25 Ø28 Ø32
Non cracked concrete
Tensile NRd BSt 500 S [kN] 16,1 22,6 33,2 44,0 58,3 74,6 102,5 149,4 174,9
Shear VRd BSt 500 S [kN] 9,3 14,7 20,7 28,0 36,7 57,3 90,0 112,7 147,3
Cracked concrete
Tensile NRd BSt 500 S [kN] - 9,4 19,4 25,7 34,0 49,8 73,0 106,5 124,7
Shear VRd BSt 500 S [kN] - 14,7 20,7 28,0 36,7 57,3 90,0 112,7 147,3
10 / 2012 545
AN-AC-D2147-2015-Rev 0
5
Hilti HIT-HY 200
with rebar
Setting details
d0
550 10 / 2012
AN-AC-D2147-2015-Rev 0
10
Hilti HIT-HY 200
with rebar
Design concrete cone resistance NRd,c = N0Rd,c fB f1,N f2,N f3,N fh,N fre,N
Design splitting resistance a) NRd,sp = N0Rd,c fB f1,sp f2,sp f3,sp f h,N fre,N
Data according ETA-11/0493 and ETA-12/0084, issue 2012-02-06
Anchor size Ø8 Ø10 Ø12 Ø14 Ø16 Ø20 Ø25 Ø28 Ø32
0
N Rd,c Non cracked concrete [kN] 24,1 28,7 38,8 47,1 58,8 74,6 102,5 149,4 174,9
0
N Rd,c Cracked concrete [kN] - 20,5 27,7 33,5 41,9 53,2 73,0 106,5 124,7
a) Splitting resistance must only be considered for non-cracked concrete
Influencing factors
10 / 2012 553
AN-AC-D2147-2015-Rev 0
13
Riyadh Metro Package 3 (Lines 4)
7 QA/QC PLAN
a) The site shall follow the Inspection Test Plan (ITP) – Chemical rebar anchor attached with this Method
Statement.
b) Manufacture Recommendation regarding installation, application and Quality control will be
followed.
8 HSE PLAN
Risk Assessment Attached.
9 ANNEXES
A) Organizational Chart and Contact List
B) Inspection and Test Plan – Chemical Rebar Anchor System
C) Risk Assessment
D) Drawings
End of Document
DATE 8/24/2015
DOC NO
PROJECT MANAGER
ENG. FAISAL JARRAL
faisal.jarral@azmeel.com
0557874635
DOC. CONTROLLER
Mr. PAUL CANO
paul.cano@azmeel.com Sr. DOC. CONTROLLER PLANNING ENGINEER
0546254083 Mr. BOBBY FRANZA Sr. PLANNING ENGINEER Mr. AHMAD ALKHATIB
boby.franza@azmee.com Mr. MOHAMED EZZAT ahmed.alkhatib@azmeel.com
0581007179 0591539381
TIME KEEPER
Mr.AHMED MAHER
0597660774
TIME KEEPER MECHANICAL ENGINEER EQUIPMENT FOREMAN
Mr. SOHRAB ALI Mr. THAER HUSSAIN Mr. PRITHVIRAJ SAMY
0592650518 0597443019 0599585154
CONST'N MANAGER
Engr. QURBAN ALI BHATTI QA/QC MANAGER
PMP Engr. SACHIN YARDI QUANTITY SURVEYOR SAFETY MANAGER
qab_1414@yahoo.com sachin.yardi@azmeel.com Mr. MOHAMED SHAMEER SHEHADA MOHAMED
0599162347 0597442409 0598085982 0581006814
Sr. ENGINEER SITE ENGINEER QA/QC ENGINEER SAFETY OFFICER SAFETY OFFICER
Mr. EMAD AHMED MOHAMED Mr. FIRAS F. HABALTI Mr. JAIMYE ERMITANIO Mr.NARIO CASAS Mr. SHANA IMAM
0593101727 0598052736 0576421127 PROCUREMENT OFFICER 0507121786 0597442510
SITE ENGINEER SURVEYOR Mr. FEL IAN BONGOSIA
Mr. AHMED EMAD Mr. MAGRY IMTIAZ 0582323571
0564645844 0599519536
FOREMAN STEEL FIXER SITE ENGINEER QA/QC ENGINEER SAFETY OFFICER SAFETY OFFICER
Mr.MAKHLOUF FAROUK Mr.YAZAN AL-JALANI Mr. MOHAMMED ZUBAIR Mr.GUILUERMO CRUZAT Mr. MOHAMMED KHALID
0544678790 0592944062 0598871161 0599501468 0597442585
ASSISTANT ENG. STORE KEEPER
Mr. BASSAM HASSAN Mr. SHABAZ SHAFI
0544399634 0599585147
FOREMAN CARPENTER ELECTRICAL SUPERVISOR QA/QC INSPECTOR SAFETY OFFICER SAFETY OFFICER
FOREMAN.
Mr. ELGHAMRY SHAMS Mr. ZEESHAN UL-HAQ Mr. DONNEL AGUSTIN Mr. DANNY DUMALE Mr. SHAMSUDDIN ANSARI
Mr. IIJAZ SINDHU
0561816384 0563882946 0591008478 054172474 0598130865
SAFETY OFFICER
FOREMAN CIVIL
Mr. MAZHAR KHAN
Mr.MOHAMMED FAROOQ ELECTRICIAN
ELECTRICIAN ELECTRICIAN ELECTRICIAN ELECTRICIAN 0599753571
Mr.ABDUL KALAM
Mr. USMAN ALI Mr. MOHAMMED ALI Mr. SHRINIVAS SAHOO Mr. AKRAM HUSSAIN
0557984550
FOREMAN WORKSHOP
Mr.RICHARD ABASOLA
0596922006
SIGN
NAME 07
DATE
Document No. M3‐CJV‐ITP‐GQAQA‐T11‐000000
ITP ‐ Inspection and Test Plan for Chemical Anchoring System Application
Revision: 0
Page: 1 of 1
REF: Method Statement HILTI HIT‐HY 200
Date: 10‐Oct‐15
Inspection Level
Activity Description of Activity/Inspection Inspection and Testing Specific Acceptance QC Form / Verifying Responsible Inspection
Reference Documents
No. Item Method Criteria Ref: Record / Document Person Frequency S/C FAST RAMPED OTHER
1 General
* Approved shop drawing *
Subcontractor / QC
Approval of documents related to Prior to start of work Approved Method Statement * As per the reference Approved submittal / Prior to start the
1.1 Engineer / Site H H H
Chemical Anchoring System Application activities Chemical Anchoring System documents Documents work
Engineer
Application * Specs
* Approved shop drawing * Materials being used in
* Approved Material Subcontractor / QC
Visual Inspection / Approved Method Statement * permanent works are in Every delivery / every
1.2 Incomimg Materials / Receiving receiving inspection. * Engineer / Site H H W
Documents Review Chemical Anchoring System accordance to the approved lot
Delivery Note. MDS Engineer
Application * Specs material submittal.
2 Setting
Preparation ‐ Bore holes drilling to the
* Approved shop drawing * * As per approved MS *
required embeded depth with an Subcontractor / QC Only after the
Visual Inspection / Approved Method Statement * In accordance with
2.1 approprietly size carbide drill bit as per N/A Engineer / Site completion of each H I S
Measurement Chemical Anchoring System manufacturer's printed
anchor diameter, length and location Engineer activity
Application * Specs installation instruction
spacing.
After bore holes
* Approved shop drawing * * As per approved MS * In
Subcontractor / QC drilling prior to
Approved Method Statement * accordance with
2.2 Cleaning ‐ Hole must be free of dust Visual Inspection N/A Engineer / Site inspection of hole H W S
Chemical Anchoring System manufacturer's printed
Engineer depth and diameter
Application * Specs installation instruction
size.
* As per approved MS * In
accordance with
* Approved shop drawing *
manufacturer's printed Subcontractor / QC
Application ‐ Prepare HILTI Adhesive and Visual Inspection / Approved Method Statement * During application
2.3 installation instruction. * N/A Engineer / Site H I S
inject starting at the back of the hole. Documents Review Chemical Anchoring System activity
Check Adhesive Engineer
Application * Specs
identification and expiration
date
* Approved shop drawing * * As per approved MS *
Anchoring ‐ Setting the element as per Subcontractor / QC
Visual Inspection / Approved Method Statement * In accordance with After installation of
2.4 working time period in which anchor can N/A Engineer / Site H W S
Documents Review Chemical Anchoring System manufacturer's printed anchoring
be inserted and adjusted. Engineer
Application * Specs installation instruction
* As per approved MS * Once only after
Subcontractor / QC
Visual Inspection / In accordance with curing period is done
2.5 Curing time ‐ before anchor can be loaded * Manufacturer Data Sheet N/A Engineer / Site H W S
Documents Review manufacturer's printed in every composite
Engineer
installation instruction activity
Legend: Key for Inspection Levels
Prepared By: Signature: Date:
H = Hold Point: Contractor must not proceed without approval
R = Review Point: Responsible for reviewing documentation
Approved By: Signature: Date:
I = Inspection: Responsible for carrying out inspection or test
S = Surveillance Point: Responsible for carrying out random
surveillance of inspection or test
(*): To be specified case by case. E.g. Independent Laboratory
Project Name:
Riyadh Metro 4G1
Station - Riyadh
RISK ASSESSMENT
FOR CHEMICAL
Prepared By: REBAR ANCHOR
Aamir Naveed Abbasi SYSTEM
AZMEEL – Sr. Safety Supervisor
It is fact that all risks can’t be eliminated, but we are required to protect people as far as is
‘reasonably practicable’. This guide tells us how to achieve that with minimum fuss for our
chemical rebar anchor system activity.
A risk assessment is simply a careful examination of what, in our work, could cause harm to
people, so that we can weigh up whether we have taken enough precautions or should do
more to prevent harm. Workers and others have a right to be protected from harm caused by
a failure to take reasonable control measures. We are required to assess the risks in our
workplace so that we put in place a plan to control the risks. Below is our risk assessment plan
to control the potential risks involved in chemical rebar anchor system work.
A hazard is anything that may cause harm, such as chemicals, electricity, working from
ladders, an open drawer, etc.; and
The risk is the chance, high or low, that somebody could be harmed by these and other
hazards, together with an indication of how serious the harm could be.
Power Tools
Chemical Handling
8. Lake of available High incidence General The required personal PM
personal safety of unsafe site safety equipment and
equipment conditions workers personal protective
General equipment shall be
site staff provided.
Site Make sure all persons wear
visitors 5 5
25
proper PPE’s.
PPE’s shall be maintained
5 1
05
and replaced if damaged.
Specific hand gloves and
mask shall be wears at all
time during spraying the
chemical.
Welfare Facilities
11. Personal Health Heat Stress General Provide drinking water. PM
Eyes Problem site Provide rest area.
Body workers Take regular rest.
Protection General Provide tightly sealed
site staff
Site
4 3
12
safety glasses.
Eye washout area shall be
4 1
04
visitors provided on site.
Provide protective work
clothing (coverall).
12. Lack of Welfare and Food / drinking General Site welfare facilities shall PM
Medical Facilities water
contamination
site
workers
4 4
16 be established. Sufficient
toilets, washing facilities,
4 1
04
Severity (S) Frequency (F) Risk Rating (RR) Very High High Medium Low
R=SxF 15-25 8-12 4-6 1-3
1 Minor Injury 1 Improbable
2 Major Single Injury 2 Possible Unacceptability Limits S 5 4 3 2 1 F
3 Major Multiple Injuries 3 Occasional More than 5 is unacceptable re-assess task 5 25 20 15 10 5
4 Single Death 4 Frequent and preventative actions. 4 20 16 12 8 4
5 Multiple Deaths 5 Regular 3 15 12 9 6 3
S = 0 is deemed to be the limit of practicability 2 10 8 6 4 2
of control measures. 1 5 4 3 2 1
www.hilti.sa sa.tso@hilti.com
AN-AC-D2147-2015-Rev 0
20
Page 1/7
Safety data sheet
according to 1907/2006/EC, Article 31 / ISO 11014
Printing date 26.07.2011 Version number 1 Revision: 26.07.2011
2 Hazards identification
· Classification of the substance or mixture
· Classification according to Regulation (EC) No 1272/2008
GHS07
GHS07
AN-AC-D2147-2015-Rev 0
21
DR
Page 2/7
Safety data sheet
according to 1907/2006/EC, Article 31 / ISO 11014
Printing date 26.07.2011 Version number 1 Revision: 26.07.2011
(Contd. of page 1)
· Other hazards
· Results of PBT and vPvB assessment
· PBT: Not applicable.
· vPvB: Not applicable.
· Additional information:
Hilti HIT
3 Composition/information on ingredients
· Chemical characterization: Mixtures
· Description:
2-Component-foilpack, contains:
Component A: Urethane methacrylate resin, inorganic filler
Component B: Dibenzoyl peroxide, phlegmatized
AN-AC-D2147-2015-Rev 0
22
DR
Page 3/7
Safety data sheet
according to 1907/2006/EC, Article 31 / ISO 11014
Printing date 26.07.2011 Version number 1 Revision: 26.07.2011
(Contd. of page 2)
5 Firefighting measures
· Extinguishing media
· Suitable extinguishing agents
Water spray, carbon dioxide (CO2), carbon dioxide blanket, foam, or dry powder.
Sand
· For safety reasons unsuitable extinguishing agents Water with full jet.
· Special hazards arising from the substance or mixture
Can be released in case of fire
Carbon monoxide (CO)
Carbon dioxide (CO2)
Nitrogen oxides (NOx)
Under certain fire conditions, traces of other toxic gases cannot be excluded.
· Advice for firefighters
· Protective equipment: In the event of fire, wear self contained breathing apparatus
AN-AC-D2147-2015-Rev 0
23
DR
Page 4/7
Safety data sheet
according to 1907/2006/EC, Article 31 / ISO 11014
Printing date 26.07.2011 Version number 1 Revision: 26.07.2011
(Contd. of page 3)
· Protection of hands:
Protective gloves
Avoid direct contact with the chemical/ the product/ the preparation by organizational measures.
Use gloves of stable material (e.g. Nitrile) - if necessary tricoted to improve the wearability.
· Material of gloves Nitrile rubber, NBR
· Penetration time of glove material
The exact break trough time has to be found out by the manufacturer of the protective gloves and has to be observed.
· Not suitable are gloves made of the following materials:
Natural rubber, NR
Leather gloves
Strong gloves
· Eye protection: Tightly sealed safety glasses.
· Body protection: Protective work clothing.
AN-AC-D2147-2015-Rev 0
24
DR
Page 5/7
Safety data sheet
according to 1907/2006/EC, Article 31 / ISO 11014
Printing date 26.07.2011 Version number 1 Revision: 26.07.2011
(Contd. of page 4)
· Hazardous decomposition products: No dangerous decomposition products known
11 Toxicological information
· Information on toxicological effects
· Acute toxicity:
· Primary irritant effect:
· on the skin: Irritant to skin and mucous membranes.
· on the eye: Irritant effect.
· Sensitization: Sensitization possible by skin contact.
· Additional toxicological information:
The product shows the following dangers according to the calculation method of the General EC Classification Guidelines for Preparations
as issued in the latest version:
Irritant
12 Ecological information
· Toxicity
· Acquatic toxicity: No further relevant information available.
· Persistence and degradability No further relevant information available.
· Behaviour in environmental systems:
· Bioaccumulative potential No further relevant information available.
· Mobility in soil No further relevant information available.
· Additional ecological information:
· According to recipe contains the following heavy metals and compounds according to EC guideline NO. 76/464 EC: None
· General notes: The product does not contain organically bounded halogens (AOX-free).
· Results of PBT and vPvB assessment
· PBT: Not applicable.
· vPvB: Not applicable.
· Other adverse effects No further relevant information available.
13 Disposal considerations
· Waste treatment methods
· Recommendation
After curing, the product can be disposed of with household waste.
Full or only partially emptied cartridges must be disposed of as special waste in accordance with official regulations.
· European waste catalogue
08 00 00 WASTES FROM THE MANUFACTURE, FORMULATION, SUPPLY AND USE (MFSU) OF COATINGS (PAINTS,
VARNISHES AND VITREOUS ENAMELS), ADHESIVES, SEALANTS AND PRINTING INKS
08 04 00 wastes from MFSU of adhesives and sealants (including waterproofing products)
08 04 09* waste adhesives and sealants containing organic solvents or other dangerous substances
20 00 00 MUNICIPAL WASTES (HOUSEHOLD WASTE AND SIMILAR COMMERCIAL, INDUSTRIAL AND INSTITUTIONAL
WASTES) INCLUDING SEPARATELY COLLECTED FRACTIONS
20 01 00 separately collected fractions (except 15 01)
20 01 27* paint, inks, adhesives and resins containing dangerous substances
· Uncleaned packagings:
· Recommendation:
Empty packs: May be disposed via the local Green Dot collecting system or EAK waste material code 150102 (plastic packaging materials)
14 Transport information
· UN-Number
· ADR, ADN, IMDG, IATA Void
· UN proper shipping name
· ADR Void
· ADN, IMDG, IATA Void
· Transport hazard class(es)
· ADR, ADN, IMDG, IATA
· Class Void
· Packing group
· ADR, IMDG, IATA Void
· Environmental hazards:
· Marine pollutant: No
(Contd. on page 6)
LIE
AN-AC-D2147-2015-Rev 0
25
DR
Page 6/7
Safety data sheet
according to 1907/2006/EC, Article 31 / ISO 11014
Printing date 26.07.2011 Version number 1 Revision: 26.07.2011
(Contd. of page 5)
· Special precautions for user Not applicable.
· Transport in bulk according to Annex II of MARPOL73/78 and
the IBC Code Not applicable.
· Transport/Additional information: Not dangerous according to the above specifications.
· UN "Model Regulation": -
· HS-Code: 3214 10 10: Glaziers' putty, grafting putty, resin cements, caulking
compounds and other mastics
15 Regulatory information
· Safety, health and environmental regulations/legislation specific for the substance or mixture
· Labelling according to Regulation (EC) No 1272/2008 The product is classified and labelled according to the CLP regulation.
· Hazard pictograms
GHS07
16 Other information
These data are based on our present knowledge. However, they shall not constitute a guarantee for any specific product features and shall
not establish a legally valid contractual relationship.
· Relevant phrases
H241 Heating may cause a fire or explosion.
H315 Causes skin irritation.
H317 May cause an allergic skin reaction.
H319 Causes serious eye irritation.
R3 Extreme risk of explosion by shock, friction, fire or other sources of ignition.
R36 Irritating to eyes.
R36/38 Irritating to eyes and skin.
R43 May cause sensitisation by skin contact.
R7 May cause fire.
· Department issuing data specification sheet:
Hilti Entwicklungsgesellschaft mbH
Hiltistrasse 6
D-86916 Kaufering
Tel.: +49 8191 906310
Fax: +49 8191 906826
e-mail: monika.moench@hilti.com
· Contact: Monika Mönch
(Contd. on page 7)
LIE
AN-AC-D2147-2015-Rev 0
26
DR
Page 7/7
Safety data sheet
according to 1907/2006/EC, Article 31 / ISO 11014
Printing date 26.07.2011 Version number 1 Revision: 26.07.2011
(Contd. of page 6)
· Abbreviations and acronyms:
ADR: Accord européen sur le transport des marchandises dangereuses par Route (European Agreement concerning the International Carriage of Dangerous Goods by Road)
RID: Règlement international concernant le transport des marchandises dangereuses par chemin de fer (Regulations Concerning the International Transport of Dangerous Goods by Rail)
IMDG: International Maritime Code for Dangerous Goods
IATA: International Air Transport Association
ICAO: International Civil Aviation Organization
GHS: Globally Harmonized System of Classification and Labelling of Chemicals
LIE
AN-AC-D2147-2015-Rev 0
27
DR