Location:- D/birhan
2013 First Quarter
Item
Description Unit D.birhan Price
No.
A. SUBSTRUCTURE
1. EXCAVATION & EARTH WORK
1.01 Site clearing and removing of the top 20 cm thick soil m2 32.74
1.02 Bulk excavation in ordinary soil to an average depth of 1500 mm from reduced level. m3 271.88
3
1.03 Ditto, but in soft rock m 580.50
3
1.04 Ditto but in boulder rock m 1,093.50
3
1.05 Ditto but in hardrock m 1,807.31
3
1.06 Pit excavation in ordinary soil to depth of 1500mm from reduced level m 192.57
1.07 Ditto , but in soft rock m3 734.28
1.08 Ditto , but in boulder rock m3 1,261.73
1.09 Ditto , but in hardrock m3 1,739.81
3
1.10 Pit excavation in ordinary soil over 1500mm but not exceeding 3000mm. m 376.44
3
1.11 Ditto, but in soft rock. m 964.85
3
1.12 Ditto , but in boulder rock . m 1,640.25
1.13 Ditto ,but in hardrock . m3 1,988.36
Trench excavation for masonry foundation wall to an average depth of 1000mm
1.14 m3 305.86
from reduced level in ordinary soil
1.15 Ditto, but in soft rock . m3 964.85
3
1.16 Ditto, but in boulder rock . m 1,093.50
3
1.17 Ditto, but in hardrock . m 1,988.36
1.18 Fill around foundation from granular material
imported from outside( from quarry) and
compact in layers not exceeding 20cm thick. m3 804.89
1.19 Ditto, but under hard core by sprinkling water
insure 95% modified AASHTO dry density . m3 804.89
1.20 Ditto as item no 1.18 ,but with selected excavated material from site for around foundation . m3 601.88
1.21 Ditto as item No. 1.19, but under hard core . m3 601.88
1.22 Load and cart away excavated material
as per engineers direction. m3 317.25
1.23 25cm thick basaltic or equivalent stone
hardcore, well rolled, consolidated and
blinded with crushed stone. m2 275.85
Item Description Unit D.birhan Price
No.
2. CONCRETE WORK
2.01 5cm lean concrete quality C-5 150kg of
cement/m3 : "type of cement to be PPC"under:
a) Footing m2 111.54
2
b) Grade Beams and ground floor slab m 111.54
2
c)Stone Masonry m 111.54
3
2.02 Ditto, but C-7 180 kg/m of cement under :
a) Footing m2 126.07
2
b) Grade Beams and ground floor slab m 126.07
2
c) Stone Masonry m 126.07
3
2.03 C-20 Concrete for lintel m 3,907.94
2
2.04 C-20 Concrete for 10 cm thick slab m 346.75
3
2.05 C-25Cyclopean Concrete under footing "Type of cement to be PPC " m 3,664.58
2.06 Reinforced concrete quality C-25
filled in to form work and vibrated
around rod reinforcement/ formwork and
reinforcement measured separately/ "Type of
cement to be PPC"
a) In footings. m3 3,664.58
3
b) In foundation columns. m 3,664.58
3
c) In grade beams. m 3,664.58
2
d) In 10cm thick ground floor slab. m 366.46
2.07 Provide, cut and fix in position sawn wooden
or steel formwork which ever appropriate.
a) To footings,subgradebeam & mat foundation m2 233.98
2
b) To subgrade column,grade beam,concrete wall & liftshaft m 260.57
2
c) To suspended slab. m 307.60
2.08 Mild steel reinforcement according to structural
drawings. Price includes cutting, Bending, Placing
in position and tying wires, chairs and spacers
a) Dia 6mm plain bar kg 84.07
b) Dia 8mm deformed bar . kg 67.13
c) Dia 10mm deformed bar. kg 66.22
d) Dia 12mm deformed bar . kg 66.22
e) Dia 14mm deformed bar . kg 66.22
f) Dia 16mm deformed bar . kg 68.06
g) Dia 20mm deformed bar. kg 75.57
h) Dia 24mm deformed bar . kg 75.57
2.09 Supply and install 0.5cm thick and 10cm high
styrofoam for the expansion joint in between
the grade beam and the ground floor slab. ml 27.50
3. STONE MASONRY WORK
3.01 50cm thick basaltic or equivalent stone masonry
wall bedded in cement sand mortar 1:4 below
natural ground level m3 2,073.23
3.02 Ditto, but above N.G.L m3 2,215.73
3.03 Retaining Maronry m3 2,444.63
3
3.04 One side dressed stone masonry steps bedded in cement sand mortar m 2,553.17
Item Description Unit D.birhan Price
B. SUPER STRUCTURE
1. CONCRET WORK
1.01 Reinforced concrete quality C-25
, filled into form work and vibrated
around rod reinforcement/ form work and
reinforcement measured separately/. "Type of
cement to be PPC" .
a) In elevation columns. m3 4,080.74
3
b) In suspended and floor beams. m 4,080.74
3
c) In roof beams. m 4,080.74
2
d) In 120mm Suspended slab . m 489.69
3
e) In staircase including landing . m 4,080.74
2
f) In 150mm thick staircase roof slab . m 612.11
g) In 280mm thick floor slab to be casted with
concrete in place of slab block. m2 1,142.61
1.02 Provide, cut and fix in position sawn wooden or
steel formwork which ever appropriate.
a) To elevation columns ,beams&lintels,concretewall& liftshaft m2 303.30
2
b)To Suspended slab . m 309.53
2
c) To side and belly of staircase including landing & parapet. m 331.80
2
d) To 150mm thick roof slab m 309.53
1.03 Eucalyptus props at mid and quarter point of pre
cast beams for 280mm thick floor ribbed slab m2 1,142.61
1.04 Mild steel reinforcement according to structural
drawings Price includes cutting, bending, placing
in position and tying wires, chairs and spacers .
a) Dia 6mm plain bar . kg 93.91
b) Dia 8mm deformed bar . kg 67.91
c) Dia 10mm deformed bar . kg 66.71
d) Dia 12mm deformed bar. kg 66.71
e) Dia 14mm deformed bar. kg 66.71
f) Dia 16mm deformed bar . kg 68.55
g) Dia 20mm deormed bar . kg 76.06
h) Dia 24mm deformed bar . kg 76.06
Item No. Description Unit D.birhan Price
2. BLOCK WORK
2.1 20 cm thick HCB wall class C m2 419.64
2
2.2 15 cm thick HCB wall class C m 391.28
2
2.3 10 cm thick HCB wall class C m 374.36
2
2.4 20 cm thick HCB wall class B m 495.58
2
2.5 15 cm thick HCB wall class B m 408.15
2
2.6 10 cm thick HCB wall class B m 374.36
2
2.7 20 cm thick HCB wall class A m 512.46
2
2.8 15 cm thick HCB wall class A m 475.65
2
2.9 10 cm thick HCB wall class A m 441.86
2
2.10 Agrostone wall m 260.14
2
2.11 12cm thick Brick wall m 1,186.88
2
2.12 25cm thick Brick wall m 2,280.02
3. Carpentery and joinery
3.1 5*7 Zigba purlin ml 61.41
3.2 Dia 10-12cm Eucaliptus truss upper & lower chord ml 158.48
3.3 Dia 8cm Eucaliptus truss Vertical & Diagonal ml 103.99
3.4 8mm chip wood Ceiling soffit m2 446.88
3.5 PVC Ceiling m2 453.96
2
3.6 Plywooden Door m 3,380.06
2
3.7 Wooden Window m 3,380.06
3.8 Facia board 25cm width ml 280.40