You are on page 1of 17

PRICE WITH OUT VAT

Location:- D/birhan
2013 First Quarter
Item
Description Unit D.birhan Price
No.
A. SUBSTRUCTURE
1. EXCAVATION & EARTH WORK
1.01 Site clearing and removing of the top 20 cm thick soil m2 32.74
1.02 Bulk excavation in ordinary soil to an average depth of 1500 mm from reduced level. m3 271.88
3
1.03 Ditto, but in soft rock m 580.50
3
1.04 Ditto but in boulder rock m 1,093.50
3
1.05 Ditto but in hardrock m 1,807.31
3
1.06 Pit excavation in ordinary soil to depth of 1500mm from reduced level m 192.57
1.07 Ditto , but in soft rock m3 734.28
1.08 Ditto , but in boulder rock m3 1,261.73
1.09 Ditto , but in hardrock m3 1,739.81
3
1.10 Pit excavation in ordinary soil over 1500mm but not exceeding 3000mm. m 376.44
3
1.11 Ditto, but in soft rock. m 964.85
3
1.12 Ditto , but in boulder rock . m 1,640.25
1.13 Ditto ,but in hardrock . m3 1,988.36
Trench excavation for masonry foundation wall to an average depth of 1000mm
1.14 m3 305.86
from reduced level in ordinary soil
1.15 Ditto, but in soft rock . m3 964.85
3
1.16 Ditto, but in boulder rock . m 1,093.50
3
1.17 Ditto, but in hardrock . m 1,988.36
1.18 Fill around foundation from granular material
imported from outside( from quarry) and
compact in layers not exceeding 20cm thick. m3 804.89
1.19 Ditto, but under hard core by sprinkling water
insure 95% modified AASHTO dry density . m3 804.89
1.20 Ditto as item no 1.18 ,but with selected excavated material from site for around foundation . m3 601.88
1.21 Ditto as item No. 1.19, but under hard core . m3 601.88
1.22 Load and cart away excavated material
as per engineers direction. m3 317.25
1.23 25cm thick basaltic or equivalent stone
hardcore, well rolled, consolidated and
blinded with crushed stone. m2 275.85
Item Description Unit D.birhan Price
No.
2. CONCRETE WORK
2.01 5cm lean concrete quality C-5 150kg of
cement/m3 : "type of cement to be PPC"under:
a) Footing m2 111.54
2
b) Grade Beams and ground floor slab m 111.54
2
c)Stone Masonry m 111.54
3
2.02 Ditto, but C-7 180 kg/m of cement under :
a) Footing m2 126.07
2
b) Grade Beams and ground floor slab m 126.07
2
c) Stone Masonry m 126.07
3
2.03 C-20 Concrete for lintel m 3,907.94
2
2.04 C-20 Concrete for 10 cm thick slab m 346.75
3
2.05 C-25Cyclopean Concrete under footing "Type of cement to be PPC " m 3,664.58
2.06 Reinforced concrete quality C-25
filled in to form work and vibrated
around rod reinforcement/ formwork and
reinforcement measured separately/ "Type of
cement to be PPC"
a) In footings. m3 3,664.58
3
b) In foundation columns. m 3,664.58
3
c) In grade beams. m 3,664.58
2
d) In 10cm thick ground floor slab. m 366.46
2.07 Provide, cut and fix in position sawn wooden
or steel formwork which ever appropriate.
a) To footings,subgradebeam & mat foundation m2 233.98
2
b) To subgrade column,grade beam,concrete wall & liftshaft m 260.57
2
c) To suspended slab. m 307.60
2.08 Mild steel reinforcement according to structural
drawings. Price includes cutting, Bending, Placing
in position and tying wires, chairs and spacers
a) Dia 6mm plain bar kg 84.07
b) Dia 8mm deformed bar . kg 67.13
c) Dia 10mm deformed bar. kg 66.22
d) Dia 12mm deformed bar . kg 66.22
e) Dia 14mm deformed bar . kg 66.22
f) Dia 16mm deformed bar . kg 68.06
g) Dia 20mm deformed bar. kg 75.57
h) Dia 24mm deformed bar . kg 75.57
2.09 Supply and install 0.5cm thick and 10cm high
styrofoam for the expansion joint in between
the grade beam and the ground floor slab. ml 27.50
3. STONE MASONRY WORK
3.01 50cm thick basaltic or equivalent stone masonry
wall bedded in cement sand mortar 1:4 below
natural ground level m3 2,073.23
3.02 Ditto, but above N.G.L m3 2,215.73
3.03 Retaining Maronry m3 2,444.63
3
3.04 One side dressed stone masonry steps bedded in cement sand mortar m 2,553.17
Item Description Unit D.birhan Price
B. SUPER STRUCTURE
1. CONCRET WORK
1.01 Reinforced concrete quality C-25
, filled into form work and vibrated
around rod reinforcement/ form work and
reinforcement measured separately/. "Type of
cement to be PPC" .
a) In elevation columns. m3 4,080.74
3
b) In suspended and floor beams. m 4,080.74
3
c) In roof beams. m 4,080.74
2
d) In 120mm Suspended slab . m 489.69
3
e) In staircase including landing . m 4,080.74
2
f) In 150mm thick staircase roof slab . m 612.11
g) In 280mm thick floor slab to be casted with
concrete in place of slab block. m2 1,142.61
1.02 Provide, cut and fix in position sawn wooden or
steel formwork which ever appropriate.
a) To elevation columns ,beams&lintels,concretewall& liftshaft m2 303.30
2
b)To Suspended slab . m 309.53
2
c) To side and belly of staircase including landing & parapet. m 331.80
2
d) To 150mm thick roof slab m 309.53
1.03 Eucalyptus props at mid and quarter point of pre
cast beams for 280mm thick floor ribbed slab m2 1,142.61
1.04 Mild steel reinforcement according to structural
drawings Price includes cutting, bending, placing
in position and tying wires, chairs and spacers .
a) Dia 6mm plain bar . kg 93.91
b) Dia 8mm deformed bar . kg 67.91
c) Dia 10mm deformed bar . kg 66.71
d) Dia 12mm deformed bar. kg 66.71
e) Dia 14mm deformed bar. kg 66.71
f) Dia 16mm deformed bar . kg 68.55
g) Dia 20mm deormed bar . kg 76.06
h) Dia 24mm deformed bar . kg 76.06
Item No. Description Unit D.birhan Price
2. BLOCK WORK
2.1 20 cm thick HCB wall class C m2 419.64
2
2.2 15 cm thick HCB wall class C m 391.28
2
2.3 10 cm thick HCB wall class C m 374.36
2
2.4 20 cm thick HCB wall class B m 495.58
2
2.5 15 cm thick HCB wall class B m 408.15
2
2.6 10 cm thick HCB wall class B m 374.36
2
2.7 20 cm thick HCB wall class A m 512.46
2
2.8 15 cm thick HCB wall class A m 475.65
2
2.9 10 cm thick HCB wall class A m 441.86
2
2.10 Agrostone wall m 260.14
2
2.11 12cm thick Brick wall m 1,186.88
2
2.12 25cm thick Brick wall m 2,280.02
3. Carpentery and joinery
3.1 5*7 Zigba purlin ml 61.41
3.2 Dia 10-12cm Eucaliptus truss upper & lower chord ml 158.48
3.3 Dia 8cm Eucaliptus truss Vertical & Diagonal ml 103.99
3.4 8mm chip wood Ceiling soffit m2 446.88
3.5 PVC Ceiling m2 453.96
2
3.6 Plywooden Door m 3,380.06
2
3.7 Wooden Window m 3,380.06
3.8 Facia board 25cm width ml 280.40

4. STEEL STRUCTURE & Metal Work


Fix steel roof truss made out of RHS
and fixed in position as shown in detail ST-
drawing. Erection work includes anchorage plates
to beam/column, welding and all associated works on Price includes cleaning , wire
brushing and finally two coats of antirust paint .The Employer shall suply all
material that will incorporate into the work except anti -rust paint .
4.01 RHS Lattice purlin
a) 25 x 25 x 2.5mm RHS & Diameter 16mm Rein bar ml 181.91
b) 25 x 25 x 2.5mm lattice purlin kg 124.78
c) 30 x 30 x 2mm kg 124.78
d) 40 x 40 x 2.5mm kg 124.78
e)40 x 40 x 3mm kg 124.78
4.02 Connection plate, price includes bolt & nut, welding
to lattice purlin & two coats of antirust.
Size 75 x 50 x 3mm No 35.89
4.03 Angle iron anchored to concrete beam using 8mm
diameter reinforcement bar and eventually connected
to lattice purlin by M10 bolt.Price includes two coats of anti -rust.
Size :50x50x3mm,L= 50mm No 116.02
4.04 0.9*2.1m Metal Door pcs 4,498.40
4.05 1*1.2m Metal Window pcs 3,584.99
Aluminium window & Door of 1.8mm thick Aluminium Profiles with 5mm glass
4.06 m2 5,795.60
and aluminum Grill
4.07 Aluminium handrail of 1.8mm thick profiles ml 5,161.87
2
4.08 Wiremesh with 20*20*2.5 RHS fram with anti rust m 941.09
4.09 Wiremesh with 5*7zegba purline fram with anti rust m2 920.01
Metal window grill made of Φ10mm plain bar c/c 100mm on 20*20*1.5mm
4.09 m2 560.81
RHS fram welded .price included one coat of Anti rust and synthetic enamil paint.
Item Description Unit D.birhan Price
No.
5. LINTEL WORK
5.01 Reinforced concrete quality C-20
"Type of cement to be PPC" m3 3,907.94
5.02 Provide, cut & fix in position sawn wooden or
steel form work which ever appropriate. m2 303.30
5.03 Mild steel reinforcement according to
structural drawings. Price includes cutting,
bending, placing in position and tying
wires, chairs & spacers.
a) 6mm plain bar kg 93.91
b) 10mm deformed bar kg 76.06

6. PLASTERING & pointing (In PPC Cement)


m2
6.01 Third Fine coats of lime plaster in cement mortar (1:3) for internal,external wall ,beam &column 95.13
6.02 Third Fine coats of cement plaster in cement
6.03 mortar (1:3) for internal,external wall ,beam &column m2 59.25
6.04 Third (fine) coat of Gypsum plaster m2 128.19
2
6.05 Gypsum board ceiling m 566.51
6.06 armstrong Ceiling m2 1,096.14
2
6.07 Apply one coat of Rendering to external wall m 101.96
2
6.08 Apply three coats of plaster in cement mortar Inter & Exte. Surface m 184.17
2
6.09 Apply three coats of plaster in cement mortar Vertical sur. & Soffit m 288.23
2
6.10 Apply three coats of Compomortar Inter & Exte surface m 169.37
2
6.11 Apply two coats of plaster cement mortar Inter & Exte surface m 106.88
2
6.12 Apply two coats of plaster cement mortar concrete Vertical sur.&soffit m 269.86
2
6.13 Apply two coats of Compomortar Inter & Exte surface m 153.11
6.14 Pointing to stone masonry wall in cement
mortar (1:3) mix. m2 67.45
2
6.15 pointing to stone H.C.B wall in cement mortar (1:3) mix. m 67.16
2
6.16 pointing to brick wall cement mortar (1:3) mix. m 113.91
7. Finshing Work
7.1 5cm thick Cement screed 1:3 m2 213.92
2
7.2 3cm thick Cement screed 1:3 m 154.82
2
7.3 cement floor tile m 519.33
2
7.4 PVC tile m 448.86
2
7.5 Terrazzo tile gray m 530.34
2
7.6 Terrazzo tile coulerfull m 537.23
2
7.7 Marble floor tile m 2,148.88
2
7.8 60*60*1cm Dubai pourcelling floor tile m 1,098.63
2
7.9 80*80*0.8 Dubai pourcelling floor tile m 1,088.56
2
7.10 60*60*1cm Granite floor tile m 3,213.33
2
7.11 Ceramic floor tile (500*500*8)mm m 670.01
2
7.12 Ceramic wall tile(150*150*6)mm m 576.63
2
7.13 Ceramic floor tile (450*450*9.5)mm m 703.30
2
7.14 Ceramic floor tile (300*300*8)mm m 634.45
2
7.15 Ceramic wall tile(200*300*8)mm m 739.44
2
7.16 20*30 Dubai pourcellin wall tile m 766.98
7.17 30*45 Dubai pourcellin wall tile m2 623.88
2
7.18 Mozic m 9,220.34
2
7.19 clinker wall tile (60*240)mm m 3,495.21
7.20 PVC skrting ml 81.07
7.21 Terrazzo skirting ml 132.34
7.22 Marble skirting ml 191.19
7.23 Ceramic skirting ml 155.03
7.24 Porcilen skirting ml 165.59
7.25 Wooden skirting ml 109.72
7.26 C-25 60*60*15 manhole No 195.56
7.27 300mm half ditch concrete pipe ml 204.64
7.28 Stone paving rough dressed m2 357.59
7.29 Stone paving dressed m2 456.55
7.30 terrazo window sill width 27 cm ml 344.94
7.31 Marble window sill width 27 cm ml 664.89
7.32 Marble Copping ml 560.11
7.33 marble steps m2 2,231.91
7.34 marble Risers m2 1,885.23
2
7.35 Granite steps m 3,465.69
2
7.36 Granite Riser m 3,053.19
7.37 Granite threshold width 25cm ml 1,162.90
Item Description Unit D.birhan Price
No. 8.PAINTING WORK
Apply three coats of plastic paint to plasterd vertical
8.01 m2 56.03
surfaces,beams & columns.
8.02 Ditto, but to sofit Surfaces & renderd wall surfaces m2 83.56
8.03 Apply three coat of synthetic enamel paint to plastered Vertical .
surfaces,beams & columns. m2 78.47
2
8.04 Ditto, but to sofit Surfaces & renderd wall surfaces m 84.42
8.05 Apply three coat of Oil paint to plastered Vertical .
surfaces,beams & columns. m2 107.87
2
8.06 Ditto, but to sofit Surfaces & renderd wall surfaces m 113.81
8.07 Apply two coat of plastic emulsion paint to plastered Vertical .
surfaces,beams & columns. m2 71.82
8.08 Ditto, but to sofit Surfaces & renderd wall surfaces m2 77.77
8.09 Apply two coat of synthetic enamel paint to plastered Vertical .
surfaces,beams & columns. m2 71.42
8.10 Ditto, but to sofit Surfaces & renderd wall surfaces m2 77.36
8.11 Apply two coat of Oil paint to plastered Vertical .
surfaces,beams & columns. m2 93.29
8.12 Ditto, but to sofit Surfaces & renderd wall surfaces m2 99.23
8.13 Apply three coat of varnish paint to wooden surface m2 92.58
8.14 Apply three coat of Anti rust paint m2 122.46
8.15 Apply Quartize paint m2 236.23
9. ROOF WORK
9.1 Galvanized,Corrugated steel sheet G-35 m2 268.34
2
9.2 Ditto but toG-32 m 344.27
9.3 Ditto but toG-30 m2 337.71
9.4 Ditto but to G-28 m2 487.15
9.5 110 PVC Down pipes ml 109.49
9.6 100mm development length G_28 flat sheet Gutter ml 304.75
9.7 90mm development length G_28 flat sheet Gutter ml 282.47
9.8 100mm development length G_28 flat sheet Down pipe ml 319.12
9.9 100 mm diametere Down pipes ml 109.49
9.10 80 mm diametere Down pipes ml 82.42
9.11 40cm width G-28 coping ml 282.54
9.12 Roof ridge caps ml 269.88
9.13 Galvanized EGA ribbed sheet Guge 28 300mm thick with color roofing m2 601.63
9.14 Ditto but 400mm m2 586.55
2
9.15 Ditto but 500mm m 554.15
2
9.16 Ditto but 400mm with color roofing m 554.15
2
9.17 EGA 400 ribbed sheet clading m 557.09
9.18 Flashing ml 288.28
9.19 4mm thick Roof tretment memberane m2 407.25
9.20 Xypex water profing m2 410.85
10. GLAZING WORK
10.1 Clear glass 3mm thick m2 464.85
2
10.2 Clear glass 4mm thick m 539.10
2
10.3 Froasted galss 4mm thick m 553.95
2
10.4 Clear glass 5mm thick m 479.70
2
10.5 Colored glass 5mm m 509.40
2
10.6 6mm Colored glass m 836.10

You might also like