Project Job Ref.

Section Sheet no./rev.


1
Calc. by Date Chk'd by Date App'd by Date
D 04-04-2021

DEAD LOAD CONSTRUCTION

External wall construction

Material Thickness γ Weight


3
(in) (lb/ft ) (lb/ft2)
Cement render; 0.591; 146.4; 7.2
Blockwork solid; 3.937; 140.0; 45.9
Cavity; 1.969; ; 0.0
Blockwork solid; 3.937; 140.0; 45.9
Plaster; 0.591; 57.3; 2.8
Totals; 11.024; 101.9

Internal load bearing wall construction

Material Thickness γ Weight


3
(in) (lb/ft ) (lb/ft2)
Plaster; 0.591; 57.3; 2.8
Blockwork solid; 3.937; 140.0; 45.9
Plaster; 0.591; 57.3; 2.8
Totals; 5.118; 51.6

Party wall construction

Material Thickness γ Weight


3
(in) (lb/ft ) (lb/ft2)
Plaster; 0.591; 57.3; 2.8
Blockwork solid; 3.937; 140.0; 45.9
Cavity; 1.969; ; 0.0
Blockwork solid; 3.937; 140.0; 45.9
Plaster; 0.591; 57.3; 2.8
Totals; 11.024; 97.5

Solid concrete ground floor construction

Material Thickness γ Weight


(in) (lb/ft3) (lb/ft2)
T&G Chipboard flooring; 0.866; 50.9; 3.7
Polystyrene insulation; 1.969; 12.7; 2.1
Concrete slab; 3.937; 152.8; 50.1
DPM; 0.000; ; 0.0
Sand blinding; 1.969; 121.0; 19.8
Compacted fill; 5.906; 121.0; 59.5
Totals; 14.646; 135.3

Timber upper floor construction

Material Thickness γ Weight


(in) (lb/ft3) (lb/ft2)
T&G Chipboard flooring; 0.866; 50.9; 3.7
Project Job Ref.

Section Sheet no./rev.


2
Calc. by Date Chk'd by Date App'd by Date
D 04-04-2021

Softwood 50 x 200 C16 joists at 600 centres ; 7.874; 3.2; 2.1


with insulation in between
Plasterboard; 0.492; 57.3; 2.3
Totals; 9.232; 8.1