Professional Documents
Culture Documents
CONTRACT NAME : NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS, MALABANG-DOBLESTON-
TUKURAN ROAD
ABC : 2,445,500.00
CD : 26
BID BULLETIN / 0
SUPPLEMENT:
WEB POSTING MARCH 04 to 10, 2021
ISSUANCE OF BID DOCS MARCH 04 to 10, 2021
PREBID MARCH 11, 2021
OPENING MARCH 23, 2021
B.5 PROJECT BILLBOARD / SIGNBOARD 2.000 EA. 8,168.36 16,336.72 -3% (525.36)
B.7 OCCUPATIONAL SAFETY ANG HEALTH PROGRAM 0.870 MOS. 13,022.22 11,329.33 -3% (364.33)
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTION 1.000 L.S. 17,673.95 17,673.95 -3% (568.37)
100(3)a2 INDIVIDUAL REMOVAL OF TREES, SMALL b, 301-500 mm dia. 1.000 EA. 5,754.74 5,754.74 -3% (185.06)
102(2) SURPLUS COMMON EXCAVATION 176.640 CU.M. 251.13 44,359.60 -3% (1,427.25)
104(1)a EMBANKMENT FROM ROADWAY EXCAVATION 65.620 CU.M. 453.23 29,740.95 -3% (956.74)
200(1) AGGREGATE SUBBASE COURSE 269.940 CU.M. 3,177.53 857,742.45 -3% (27,582.47)
311(1)e1 PCC PAVEMENT, UNREINFORCED, 0.28m thk. 442.200 SQ.M. 2,675.72 1,183,203.38 -3% (38,051.31)
606(1)b1 PAVEMENT MARKINGS, REFLECTORIZED THERMOPLASTIC, WHITE 26.400 SQ.M. 1,831.11 48,341.30 -3% (1,554.70)
606(1)b2 PAVEMENT MARKINGS, REFLECTORIZED THERMOPLASTIC, YELLOW 3.000 SQ.M. 7,670.20 23,010.60 -3% (739.98)
1,697.610 GRAND TOTAL 2,369,712.60