Professional Documents
Culture Documents
Apron Drain BOQ
Apron Drain BOQ
Summary
Price Amount
No Description Specification Unit Quantity
(Kyats) (Kyats)
1 Earth work
Manual 16080 64000
1-1 Excavation soil Sud 3.98
Incl. Transport and stockpile
Gravel or Crushed stone under foundation 30000 47700
1-2 Sub-grade with compaction Sud 1.59
t=4in thk:
Subtotal 111700
2 Concrete works
Pouring of Blinding concrete 408000
Lean concrete for drain base & apron
2-1 including material Sud 1.87 218182
with slump test(1:3:6) (Rivershingle)
Pouring of Blinding concrete including 260866 195650
Dain cover (2'-0" x1'-6")
2-2 material Sud 0.75
with slump test(1:2:4) (Rivershingle)
Subtotal 603650
3 Re-bar works
Placing of Re-bar incl. fabrication & 850000 25500
3-1 For Drain Cover (6mm Ø) ton 0.03
erection
Subtotal 25500
4 Formworks
4-1 Drain Cover (2'x -0"x1'-6") Formwork include material Sqft 75.00 1000 75000
Subtotal 75000
5 Masonry work
5-1 Brick work t=4.5", (1:3) cement motor, for drain Cuft 500.06 2279 1139650
5-2 Plastering work t=1/2", (1:3) cement motor, for drain Sqft 539.12 367 197750
Subtotal 1337400
Subtotal 2,153,250
Transportation Charge 2.5 % 53,831
1
2
3
Remarks