Refinery Construction Waste Management Implementation Plan


Project Document Number: Rev.
Contract No.: Job No.: Date:
DRP001-OUF-PRO-Z-000-004 O2
CNT-1100-1000-007 JI-2037 12.11.2018

APPENDIX 4 WASTE ESTIMATION (CONSTRUCTION PHASE)

Approximate
Activity Anticipated
Sl. /location quantity
No Waste generating Waste Waste (in Kg per
. Type waste Characteristics Classification month) Remarks

Perishable items
+ food wastes Food waste Non- 29950 kg per
1 Semisolid from mess hall /garbage hazardous month  
Solid & Concrete wastes; 520.708 MT
2 inert Excavated soil Concrete Debris Nonhazardous per month  

Solid & 525.83 MT


3 inert Civil works Road Asphalt  Nonhazardous per month  
Construction
work/
Packaging 158.69 MT
4 Solid activities Wooden waste Nonhazardous per month  
Construction
work/
Packaging 682.5 kg per
5 Solid activities Papers/Cardboards Nonhazardous month  
Construction
work/
Packaging 310 kg per
6 Solid activities Plastic Waste Nonhazardous month  
Construction
work/
Packaging General Scrap- 60.189 MT
7 Solid activities (Metal Scrap) Nonhazardous per month  

Page 1 of 3
Duqm
Refinery Construction Environmental and Social Management Plan
Project Document Number: Rev.
Contract No.: CNT-1100- Job No.: Date: DRP001-OUF-PRO-Z-000-004 O2
1000-007 JI-2037 07.11.2018

Construction
work/
Packaging 492 kg per
8 Solid activities Vehicle tires Nonhazardous month  
Construction
work/ Uncontaminated Air
Packaging filter gloves , 440 kg per
9 Solid activities coverall, used PPE's Nonhazardous month  
Construction
work/
Packaging Wires/ Cables/ 2.8 MT per
10 Solid activities Conduits Nonhazardous month  
Construction
work/ E-waste
Packaging (Printer/Fax 12.5kg per
11 Solid activities Cartridge) Hazardous month  
Construction
work/
Packaging 320Kg
12 Semisolid activities Oily Sludge Hazardous permonth  
Construction
work/
Packaging Uncleaned Empty 4.1 MT per
13 Solid activities Containers Hazardous month  
Construction
work/
Packaging 2.5 MT per
14 Solid activities Insulation waste Hazardous month  

Page 2 of 3
Duqm
Refinery Construction Environmental and Social Management Plan
Project Document Number: Rev.
Contract No.: CNT-1100- Job No.: Date: DRP001-OUF-PRO-Z-000-004 O2
1000-007 JI-2037 07.11.2018

Construction work/ 13 MT per


15 Solid Packaging activities Oil contaminated soil Hazardous month  
Oily Contaminated
Wastes (e.g. gloves,
Construction disposal coverall,
/Packaging cotton, rags, used 1.6 MT per
16 Solid activities PPEs etc.): Hazardous month  
Construction
/Packaging Fluorescent Lamps / 11 kg per
17 Solid activities Bulbs Hazardous month  
Construction Used Welding
/Packaging Electrode Butts/ 4.3 MT per
18 Solid activities Grinding Wheels (MT) Hazardous month  
Varies
depending
upon the
Hydrotested waste *30000m3 scope of
19 liquid Hydrostatic testing water Hazardous total pipeline

Onsite Sewage 0.30 kg per


20 Drysolid Treatement Plant STP sludges Hazardous capita per day TBA
Domestic
Wastewater from
accomodation 320 litre per
21 Liquid camp Sewage Water Hazardous capita per day TBA

Page 3 of 3