Technical Alert

Page 1/3
Bit Depth Jump when creating Sidetrack

Case Histories & Lessons Learned


***INTERNAL COMMUNICATIONS ONLY***

From: Q&Ops
Introduction: Reminder to correct bit depth once sidetrack creation is complete.

Title

Problem: Bit Depth jumps to kick off depth while creating sidetrack even at surface. If unnoticed,
incorrect activity and data will occur if HKH moves and total depth increases.

Solution: If you need to create a sidetrack, it is recommended to do it when the bit is at


surface. When creating a sidetrack remember to move bit depth back to surface or to
correct depth.

In the following example a new wellbore has been added at a depth of 1855m. The bit
depth is 0.05m (on surface)

Kick off depth


New Wellbore

Issued by Verified by Approved by


Guy Nichols Remi Dalla-Barba Damodar Kumar
Revision 0 Issued on: December 2012 December 2012 December 2012
Technical Alert
Page 2/3
Bit Depth Jump when creating Sidetrack

Case Histories & Lessons Learned


***INTERNAL COMMUNICATIONS ONLY***
After the system is restarted and the setup panel is opened, the bit depth has jumped to
the kick off depth at 1855m.

Bit depth jumped to


KO depth.

Make sure to correct your bit depth. In this case, the bit was on surface so 0.05m was
entered.

Reset bit depth to


correct depth

Issued by Verified by Approved by


Guy Nichols Remi Dalla-Barba Damodar Kumar
Revision 0 Issued on: December 2012 December 2012 December 2012
Technical Alert
Page 3/3
Bit Depth Jump when creating Sidetrack

Case Histories & Lessons Learned


***INTERNAL COMMUNICATIONS ONLY***

To check that you have the correct wellbore in REAL TIME please
follow procedure documented in TICKET 5920152 .