Professional Documents
Culture Documents
MANPOWER
No. Name Rate Position No.of Days Total Amount
1 DANILO PESINO 500.00 Lead Man 2 1000.00
2 DELFIN IBANA 500.00 Skilled Painter 6 3000.00
3 KEVIN DIAZ 500.00 Skilled Painter 6 3000.00
Total Amount 7,000.00
Materials Needed:
1 liter Maple Enamel
4 gal Megacryl Flat Latex White
2 gal Sun and Rain Tinge of Gray
5 pcs Sand Paper #120
2 pcs Roller Refill
2 gal Megacryl Moonlight
Prepared by:
ELLEN-ZYRA R. CAPILLAS
Office Engineer
Checked by:
MANPOWER
No. Name Rate Position No.of Days Total Amount
1 DELFIN IBANA 600.00 Plumber/Painter/Tilesetter 6 3,600.00
2 RENE RAMPAS 600.00 Plumber/Painter/Tilesetter 6 3,600.00
Total Amount 7,200.00
SCOPE OF WORKS:
SECOND FLOOR COMMON TOILET CHECKING AND REPAIR
a. Re-checking of Plumbing and Sanitary Lines 2 days 2 Manpower
b. Dismantling of Ceiling along Laundry Area 1 day 1 Manpower
c. Dismantling of Floor Tiles (30x30) 1 day 1 Manpower
d. Flood Test 1 day 2 Manpower
e. Re-piping of Plumbing/Sanitary Line 3 days 2 Manpower
f. Re-checking/Flood Test 1 day 1 Manpower
g. Installation of Tiles 1 day 1 Manpower
f. Testing 1 day 1 Manpower
10 days Max.
Prepared by:
ELLEN-ZYRA R. CAPILLAS
Office Engineer
Checked by: