OFC Cable Installation SOP
OFC Cable Installation SOP
10. Installation the Pole band (Cable termination of messenger wire with pole band)
11.Install the Suspension Clamp and Fixing the Cable (Including Sprial tube)
12.Stay wires and accessories Installation
13.Installation the earthing Material and test the earth resistance ( 2.18 Ohm)
14.Install for Dome Closure and ODB at inter media branching point and branching out splicing.
15.Prepare a reserve coil at the pole of dome closure installation.
16.ODB Installation at 3m high above the ground
17. Cable Headroom Clearance(H), 4.7 meters.
18. High Voltage Protection Installation at HT lines.