CONTRACT # 4400003961

TOWER CHECKING MARKING


Twr No End I I-4
PROJECT: Portion 2
Twr Type HA HA
DIMENSIONS (m)
SAGGING SECTION

Tower No. End I I-4


Tower Type HA HA

SAGGING SPAN
Tower No. End I
Tower Type HA
Checking Side
Body Ext.
Leg Ext.
Tower No. I-4
Tower Type HA
Marking Side
Body Ext. 6
Leg Ext. 6
Span Length 198.7
Intial Sag At 44 ⁰C D (mts) = 3.44
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 3.44 (m)

( 3.74 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No I-4 I-3
PROJECT: Portion 2
Twr Type HA MA
DIMENSIONS (m)
SAGGING SECTION

Tower No. I-3 I-4


Tower Type MA HA

SAGGING SPAN
Tower No. I-4
Tower Type HA
Checking Side
Body Ext. 6
Leg Ext. 6
Tower No. I-3
Tower Type MA
Marking Side
Body Ext. -
Leg Ext. 4.5
Span Length 370.2
Intial Sag At 40 ⁰C D (mts) = 11.47
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 11.47 (m)

( 11.77 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No I-3 I-2
PROJECT: Portion 2
Twr Type MA LA
DIMENSIONS (m)
SAGGING SECTION

Tower No. I-3 I-2


Tower Type MA LA

SAGGING SPAN
Tower No. I-3
Tower Type MA
Checking Side
Body Ext. 0
Leg Ext. 4.5
Tower No. I-2
Tower Type LA
Marking Side
Body Ext. -
Leg Ext. 1.5
Span Length 291.4
Intial Sag At 38 ⁰C D (mts) = 6.92
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 6.92 (m)

( 7.22 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No I-1 I-2
PROJECT: Portion 2
Twr Type AT LA
DIMENSIONS (m)
SAGGING SECTION

Tower No. I-1 I-2


Tower Type AT LA

SAGGING SPAN
Tower No. I-1
Tower Type AT
Checking Side
Body Ext. 0
Leg Ext. 1.5
Tower No. I-2
Tower Type LA
Marking Side
Body Ext. -
Leg Ext. 1.5
Span Length 321.8
Intial Sag At 38 ⁰C D (mts) = 8.54
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 8.54 (m)

( 8.84 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No BSE 15 BSE 14
PROJECT: Portion 2
Twr Type AT AT
DIMENSIONS (m)
SAGGING SECTION

Tower No. BSE 15 BSE 14


Tower Type AT AT

SAGGING SPAN
Tower No. BSE 15
Tower Type AT
Checking Side
Body Ext. 0
Leg Ext. 9
Tower No. BSE 14
Tower Type AT
Marking Side
Body Ext. 0
Leg Ext. 1.5
Span Length 160
Intial Sag At 36 ⁰C D (mts) = 5.81
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 5.81 (m)

( 6.11 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No I-1 JRSD GT
PROJECT: Portion 2
Twr Type AT Gantry
DIMENSIONS (m)
SAGGING SECTION

Tower No. I-1 JRSD GT


Tower Type AT Gantry

SAGGING SPAN
Tower No. I-1
Tower Type AT
Checking Side
Body Ext.
Leg Ext.
Tower No. JRSD GT
Tower Type Gantry
Marking Side
Body Ext. -
Leg Ext. -
Span Length 88
Intial Sag At 36 ⁰C D (mts) = 1.32
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 1.32 (m)

( 1.62 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No BK 11 End I
PROJECT: Portion 2
Twr Type TT
DIMENSIONS (m)
SAGGING SECTION

Tower No. BK 11 End I


Tower Type TT

SAGGING SPAN
Tower No. BK 11
Tower Type TT
Checking Side
Body Ext. -
Leg Ext. -
Tower No. End I
Tower Type
Marking Side
Body Ext. -
Leg Ext.
Span Length 349
Intial Sag At 36 ⁰C D (mts) = 10.36
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 10.36 (m)

( 10.66 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No BNJ 1 BK2
PROJECT: Portion 2
Twr Type Monopole TT
DIMENSIONS (m)
SAGGING SECTION

Tower No. BNJ 1 BK2


Tower Type Monopole TT

SAGGING SPAN
Tower No. BK2
Tower Type TT
Checking Side
Body Ext. -
Leg Ext. -
Tower No. BNJ 1A, B, C
Tower Type Monopole
Marking Side
Body Ext. -
Leg Ext. -
Span Length 270
Intial Sag At 36 ⁰C D (mts) = 5.81
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 5.81 (m)

( 6.11 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No Gantry G1
PROJECT: Portion 2
Twr Type Gantry AT
DIMENSIONS (m)
SAGGING SECTION

Tower No. Gantry G1


Tower Type Gantry AT

SAGGING SPAN
Tower No. Gantry
Tower Type Gantry
Checking Side
Body Ext. -
Leg Ext. -
Tower No. G1
Tower Type AT
Marking Side
Body Ext. -
Leg Ext. 1.5
Span Length 86.47
Intial Sag At 34 ⁰C D (mts) = 3.59
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 3.59 (m)

( 3.89 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No Gantry G1
PROJECT: Portion 2
Twr Type Gantry AT
DIMENSIONS (m)
SAGGING SECTION

Tower No. Gantry G1


Tower Type Gantry AT

SAGGING SPAN
Tower No. Gantry
Tower Type Gantry
Checking Side
Body Ext. -
Leg Ext. -
Tower No. G1
Tower Type AT
Marking Side
Body Ext. -
Leg Ext. 1.5
Span Length 86.47
Intial Sag At 34 ⁰C D (mts) = 3.59
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 3.59 (m)

( 3.89 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No G6A BSE 14
PROJECT: Portion 2
Twr Type MASH25 AT
DIMENSIONS (m)
SAGGING SECTION

Tower No. G6A BSE 14


Tower Type MASH25 AT

SAGGING SPAN
Tower No. G6A
Tower Type MASH25
Checking Side
Body Ext. -
Leg Ext. -
Tower No. BSE 14
Tower Type AT
Marking Side
Body Ext. -
Leg Ext. 1.5
Span Length 120.2
Intial Sag At 36 ⁰C D (mts) = 5.17
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 5.17 (m)

( 5.47 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No G7A BSE 14
PROJECT: Portion 2
Twr Type MASH25 AT
DIMENSIONS (m)
SAGGING SECTION

Tower No. G7A BSE 14


Tower Type MASH25 AT

SAGGING SPAN
Tower No. G7A
Tower Type MASH25
Checking Side
Body Ext. -
Leg Ext. -
Tower No. BSE 14
Tower Type AT
Marking Side
Body Ext. -
Leg Ext. 1.5
Span Length 105.38
Intial Sag At 36 ⁰C D (mts) = 2.71
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 2.71 (m)

( 3.01 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No G6A G5/1
PROJECT: Portion 2
Twr Type MASH25 MHA-SC45
DIMENSIONS (m)
SAGGING SECTION

Tower No. G6A G5/1


Tower Type MASH25 MHA-SC45

SAGGING SPAN
Tower No. G6A
Tower Type MASH25
Checking Side
Body Ext. -
Leg Ext. -
Tower No. G5/1
Tower Type MHA-SC45
Marking Side
Body Ext. -
Leg Ext. -
Span Length 57.1
Intial Sag At 36 ⁰C D (mts) = 1.66
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 1.66 (m)

( 1.96 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No G5 G5/1
PROJECT: Portion 2
Twr Type LA MHA-SC45
DIMENSIONS (m)
SAGGING SECTION

Tower No. G5 G5/1


Tower Type LA MHA-SC45

SAGGING SPAN
Tower No. G5
Tower Type LA
Checking Side
Body Ext. 12
Leg Ext. 3
Tower No. G5/1
Tower Type MHA-SC45
Marking Side
Body Ext. -
Leg Ext. -
Span Length 290.37
Intial Sag At 36 ⁰C D (mts) = 6.79
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 6.79 (m)

( 7.09 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No G1 G2
PROJECT: Portion 2
Twr Type AT HA
DIMENSIONS (m)
SAGGING SECTION

Tower No. G1 G2
Tower Type AT HA

SAGGING SPAN
Tower No. G1
Tower Type AT
Checking Side
Body Ext. -
Leg Ext. 1.5
Tower No. G2
Tower Type HA
Marking Side
Body Ext. 6
Leg Ext. 9
Span Length 277.89
Intial Sag At 34 ⁰C D (mts) = 6.01
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 6.01 (m)

( 6.31 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No G3 G2
PROJECT: Portion 2
Twr Type MA HA
DIMENSIONS (m)
SAGGING SECTION

Tower No. G3 G2
Tower Type MA HA

SAGGING SPAN
Tower No. G3
Tower Type MA
Checking Side
Body Ext. -
Leg Ext. 9
Tower No. G2
Tower Type HA
Marking Side
Body Ext. 6
Leg Ext. 9
Span Length 336.07
Intial Sag At 32 ⁰C D (mts) = 9.01
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 9.01 (m)

( 9.31 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No G4 G5
PROJECT: Portion 2
Twr Type MA LA
DIMENSIONS (m)
SAGGING SECTION

Tower No. G4 G5
Tower Type MA LA

SAGGING SPAN
Tower No. G4
Tower Type MA
Checking Side
Body Ext. -
Leg Ext. 6
Tower No. G5
Tower Type LA
Marking Side
Body Ext. 12
Leg Ext. 3
Span Length 211.96
Intial Sag At 34 ⁰C D (mts) = 3.59
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 3.59 (m)

( 3.89 )m
D2 =

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No 71 72
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type TT TT
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No. 65 77
Tower Type HA TT 2.00

SAGGING SPAN 1.5


Tower No. 71 2.4

Tower Type TT
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 72 2.30

Tower Type TT
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length 429.9 (m)
Intial Sag At 24 ⁰C D= 10.61 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 10.61 (m)

D2 = ( 10.91 ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No 71 72
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type TT TT
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No. 65 77
Tower Type HA TT 2.00

SAGGING SPAN 1.5


Tower No. 71 2.4

Tower Type TT
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 72 2.30

Tower Type TT
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length 429.9 (m)
Intial Sag At 24 ⁰C D= 10.61 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 10.61 (m)

D2 = ( 10.91 ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No 92 107
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type TT TT
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No. 92 107
Tower Type TT TT 2.00

SAGGING SPAN 1.5


Tower No. 97 2.4

Tower Type TT
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 98 2.30

Tower Type TT
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length 363.9 (m)
Intial Sag At 29 ⁰C D= 7.48 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 7.48 (m)

D2 = ( 7.78 ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No 101 102
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type TT TT
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No. 92 107
Tower Type TT TT 2.00

SAGGING SPAN 1.5


Tower No. 102 2.4

Tower Type TT
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 101 2.30

Tower Type TT
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length 351.9 (m)
Intial Sag At 29 ⁰C D= 7.0 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 7.0 (m)

D2 = ( 7.3 ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No 113 112
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type TT TT
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No. 107 123
Tower Type TT TT 2.00

SAGGING SPAN 1.5


Tower No. 113 2.4

Tower Type TT
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 112 2.30

Tower Type TT
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length 303.8 (m)
Intial Sag At 29 ⁰C D= 5.17 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 5.17 (m)

D2 = ( 5.47 ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No.
Tower Type 2.00

SAGGING SPAN 1.5


Tower No. 2.4

Tower Type
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 2.30

Tower Type
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length (m)
Intial Sag At ⁰C D= 6.92 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + (m)

D2 = ( ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No 119 120
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type TT TT
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No. 107 123
Tower Type TT TT 2.00

SAGGING SPAN 1.5


Tower No. 119 2.4

Tower Type TT
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 120 2.30

Tower Type TT
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length 349.9 (m)
Intial Sag At 29 ⁰C D= 6.86 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 5.17 (m)

D2 = ( 5.47 ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No 119 120
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type TT TT
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No. 123 138
Tower Type TT HA 2.00

SAGGING SPAN 1.5


Tower No. 128 2.4

Tower Type TT
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 129 2.30

Tower Type TT
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length 350 (m)
Intial Sag At 29 ⁰C D= 6.92 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 6.92 (m)

D2 = ( 7.22 ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No 119 120
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type TT TT
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No. 123 138
Tower Type TT HA 2.00

SAGGING SPAN 1.5


Tower No. 133 2.4

Tower Type TT
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 134 2.30

Tower Type TT
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length 350 (m)
Intial Sag At 29 ⁰C D= 6.92 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 6.92 (m)

D2 = ( 7.22 ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No.
Tower Type 2.00

SAGGING SPAN 1.5


Tower No. 2.4

Tower Type
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 2.30

Tower Type
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length (m)
Intial Sag At ⁰C D= 6.92 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + (m)

D2 = ( ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No 3 4
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type HA TT
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No. 3 7
Tower Type HA HA 2.00

SAGGING SPAN 1.5


Tower No. 3 2.4

Tower Type HA
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. 4 2.30

Tower Type HA
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length 300 (m)
Intial Sag At 34 ⁰C D= 5.24 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 5.24 (m)

D2 = ( 5.54 ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant


CONTRACT # 4400003961
TOWER CHECKING MARKING
Twr No 7 T#GJSE 65
PROJECT: Portion 2, Scope M, 230 KV Jubail Southeast to SWCC1
Twr Type HA HA
DIMENSIONS (m)
SAGGING SECTION
1.97
Tower No. 7 T#GJSE 65
Tower Type HA HA 2.00

SAGGING SPAN 1.5


Tower No. 7 2.4

Tower Type HA
Checking Side
Body Ext. 2.40

Leg Ext. 1.70

Tower No. T#GJSE 65 2.30

Tower Type HA
Marking Side
Body Ext. 2.30
1.50
Leg Ext.
Span Length 280 (m)
Intial Sag At 34 ⁰C D= 4.56 (m)
SAG VARIATION /1⁰C (m)

SAG ADJUSTMENT AT
CHECKING SIDE (m)
VARIATION /1 ⁰C
+0 m +18m Common Body

+0 m +18 m Body Extension

+3 m +8 m
+4 m +9 m
+5 m +10 m
Leg Extension
+6 m
+7 m

Actual Sag Measurement


= Length from Peak to Sheave Roller Groove + Initial Sag
(from Peak Cross Arm)

= D1 + D (m)
D2

D2 = 0.3 + 4.56 (m)

D2 = ( 4.86 ) m

Prepared By Checked By Approved By

Al-Sharif KEC Al-Sharif KEC SEC Consultant