Qatar Liquefied Gas Company Limited

JOB SAFETY ANALYSIS FORM


JSA Number:DS/QG/SD-1014 NEW REVISED Page No 1 of 4
Job being analysed: Pulling / Pushing Tube Bundle.

Department/Section doing JSA: Descon Planning JSA members: Alamdar Shah,Umar Niazi
Job Area/Location: Process & SRU Area Job performers: Descon Plant Services
NORMAL APPROVALS: POSITION Name Staff No Signature Date General Job Requirements/ Common PPE
JSA by: - Coveralls (Nomex Delta C).
Job Supervisor: - Safety Helmet (No older then 3 years
EXTRA ORDINARY APPROVALS (ONLY IN VERY SPECIAL CASES REFERRED BY A JOB SUPERVISOR): from date of issue).
Discipline Superintendent - Safety Shoes (Sole must not be smooth).
Safety Representative - Safety Glasses (Dark & Clear with carry
Any Other Approving Authority Case).
- Hearing Protection.
- Safety Glove (Rigger Gloves).
- 1 Gas Alert Clip per group.
- Barricade/Sign the area.
- Pre-Start Safety Toolbox Talk.

Sequence of Basic Job Steps Potential Hazards Risk Recommended safe working practices /procedures/
(Number them with description, write duration) Hazard Control methods/ PPE
Rank
1. Pneumatic connections to Bundle Puller. 1.1 Release of pressure. H 1.1.1 Use only well maintained hoses.
1.2 Personal injury. H 1.2.1 Secure fitting properly.
1.3 Manual handling injury. L 1.3.1 Maintain manual handling techniques.
1.4 Slip / Trips / Falls. H 1.4.1 Good House Keeping (a place for everything and
everything in its place always).

PULLING/PUSHING TUBE BUNDLE-- Rev 00


2. Clamping the Bundle Puller to the exchanger. 2.1 Trapping Fingers. M 2.1.1 Use Proper tools for all works.
2.2 Falling Objects. H 2.2.1 Ensure all tools tied up with lanyard / Use tools
Bag or Basket.
2.2.2 Use only QG Certificate / Colour Coded lifting
gear.
2.2.3 Only qualified Riggers to carry out work.
2.3.1 Good House Keeping (a place for everything and
2.3 Slip / Trips / Falls. H everything in its place always).
3. Balancing of the Bundle Puller. 3.1 Falling Objects. H 3.1.1 Secure tools and tickle on the machine.
3.2 Slip / Trips / Falls. H 3.2.1 Good House Keeping (a place for everything and
everything in its place always).
3.3.1 Maintain manual handling techniques.
3.3 Manual handling injury. L
4. Puller / Pushing the Bundle. 4.1 Personal injury. H 4.1.1 Only qualified Riggers to carry out work.
4.2 Flying materials. H 4.2.1 Use only certified and colour coded lifting gear.
4.3 Slip / Trips / Falls. H 4.3.1 Good House Keeping (a place for everything and
everything in its place always).
4.4 Release of hazardous material residue. H
4.4.1 Dilute the drained contaminated liquid.
4.5 Manual handling injury. L
4.5.1 Maintain manual handling techniques.
5. De-Clamping the Bundle Puller from the 5.1 Trapping Fingers. M 5.1.1 Use proper tools for all work.
exchanger.
5.2 Falling Objects. H 5.2.1 Ensure all tools tied up with lanyard / Use tools
Bag or Basket.
5.2.2 Use only QG Certificate / Colour Coded lifting
gear.
5.2.3 Only qualified Riggers to carry out work.
5.3 Slip / Trips / Falls. H
5.3.1 Good House Keeping (a place for everything and
everything in its place always).
5.4 Manual handling injury. L 5.4.1 Maintain manual handling techniques.
6. Area cleaning. 6.1 Slip / Trips / Falls. H 6.1.1 Ongoing at all times as you work, the area shall
be cleaning and unwanted materials to be removed.
Note: 1) If any of the tasks involves biological, physical or chemical hazards, then Industrial Hygienist must also sign this Form, against “Any Other Approving Authority” above.
2) If steps in a job are more than the space provided above, use a photocopy of this sheet to continue on the next page.
3) Details on safety (PPE, Hazard etc) and environmental requirements can be found in Safety & Environment Procedures available from the Intranet/Documents & Standards.
Qatar Liquefied Gas Company Limited
JOB SAFETY ANALYSIS RISK SUMMARY SHEET

HIGH RISK HAZARD DESCRIPTION RISK DESCRIPTION CONTROL MEASURE


1 Pneumatic connections to Release of pressure. Use only well maintained hoses.
Bundle Puller,

5 Pneumatic connections to Personal injury. Secure fitting properly, Only qualified


Bundle Puller, Puller / Pushing Riggers to carry out work.
the Bundle

6 Pneumatic connections to Slip / Trips / Falls. Good House Keeping (a place for
Bundle Puller, Balancing of the everything and everything in its place
Bundle Puller, Puller / Pushing always).
the Bundle, De-Clamping the
Bundle Puller from the
exchanger, Area cleaning
7 Clamping the Bundle Puller to Falling Objects. Ensure all tools tied up with lanyard /
the exchanger, Balancing of Use tools Bag or Basket, Use only
the Bundle Puller, De- QG Certificate / Colour Coded lifting
Clamping the Bundle Puller gear, Only qualified Riggers to carry
from the exchanger out work.
8 Puller / Pushing the Bundle Flying materials. Use only certified and colour coded
lifting gear.
9 Puller / Pushing the Bundle Release of hazardous material Dilute the drained contaminated
residue. liquid.

MEDIUM RISK 1 Clamping the Bundle Puller to Trapping Fingers. Use Proper tools for all works.
the exchanger, De-Clamping
the Bundle Puller from the
exchanger

LOW RISK 1 Clamping the Bundle Puller to Manual handling injury. Maintain manual handling techniques.
the exchanger, De-Clamping
the Bundle Puller from the

PULLING/PUSHING TUBE BUNDLE-- Rev 00


exchanger