Professional Documents
Culture Documents
Figure 1.2: Google image showing the specific location of the project site
Table 1.3
Other details of the Project
A. Cost Details
1 Total Cost for the Project 225.0 Crores
2 Cost for Environmental Management Plan Capital Cost: 45 Crores
Recurring Cost: 4.5 Crores/ annum
Source: Pre-feasibility Report
1.6 Requirements for the project
The project requirement such as area, raw material, fuel, water, steam, power, manpower with source of
supply is described in the section below:
1.6.1 Raw Material Requirement
Details regarding quantity of raw materials required, their source, storage and mode of transportation for
proposed project are given in the table below:
Table- 1.4
Raw Material Requirement, Source and Transportation
S. Particulars Total Storage facility and Distance from Source & mode of
No. Requirement Capacity Project Site transportation
1 Molasses 730 TPD 3 x 10000 Ton Upto 150 km From nearby sugar mills
Molasses Tanks by road
2 Chemicals
Caustic soda 200 kg/ day Packed in 50 kg Bags & 200-500 km Near-by Markets by road
Nutrients 150 kg/ day stored in Godown
Antifoam 200 kg/ day Packed in Cans & stored in
Agent Godowns
Yeast Own Propagation or 50 kg/day (dry yeast)
Source: Pre-feasibility Report
1.6.2 List of nearby Sugar mills for procurement of Molasses
Table 1.5
List of nearby sugar mills
s. Name of Sugar factory Crushing Mode of Estimated Molasses
No. Capacity Sugar Produced
(In TCD) Factory (In MT/annum)
1 Dwarikesh Sugar Industries Ltd, Bareilly 7500 Private 66500
2 DSM Sugar Mill, Meerganj (Bareilly) 5000 Private 41250
3 Kesar Enterprises Ltd, Baheri (Bareilly) 7200 Private 52950
4 Kisan Sahakari Chini Mills Ltd, Semikhera (Bareilly) 7200 Co-operative 0
5 Oswal Overseas Ltd, Sainthal (Bareilly) 3500 Private 12500
6 Bajaj Hindusthan Sugars Ltd, Maqsoodapur (Shahjahanpur) 7000 Private 59450
7 Dalmia Chini Mills, Nigohi (Shahjahanpur) 10000 Private 90000
8 Kisan Sahakari Chini Mills Ltd, Tilhar (Shahjahanpur) 2500 Co-operative 19000
9 Kisan Sahakari Chini Mills Ltd, Powayan (Shahjahanpur) 2125 Co-operative 18750
10 Oudh Sugar Energy Ltd, Rosa (Shahjahanpur) 4200 Private 40500
11 Kisan Sahakari Chini Mills Ltd, Bisalpur (Pilibhit) 2750 Co-operative 20000
12 Bajaj Hindusthan Sugars Ltd, Barkhera (Pilibhit) 7500 Private 55700
13 LH Sugar factory, Pilibhit 11500 Private 103900
14 Kisan Sahakari Chini Mills Ltd, Puranpur (Pilibhit) 2500 Co-operative 16000
1.6.3 Fuel Requirement
The fuel required for incineration boiler to generate steam & power is concentrated spent wash, bagasse
/biomass/coal. Details for incineration boiler fuel required, their source, storage and mode of transportation
for proposed project are given in the table below:
Table- 1.6
Fuel Requirement
S. Name of Material Requirement Storage facility and Source & mode of transportation
No. (TPD) capacity
1 Concentrated spent wash 595 TPD - Own plant through pipelines
2 Bagasse 340-350 TPD Covered Sheds with Nearby Sugar Mills by road
or storage capacity of 20
Coal or 135-140 TPD days Through local vendors by road
or
Rice Husk Biomass 175-180TPD Open market
Note: - The usage of fuel mix will be as per availability & technology.
1.6.4 Water Requirement
Total water requirement for the proposed project will be 1120 KLPD (1100 KLPD for distillery and 20 KLPD for
others) which will be sourced from Groundwater.
Application has been submitted to CGWA vide application number 21-4/8290/UP/IND/2019 dated 20th
October, 2019. Ground water permission application has been approved from CGWB and forwarded to AO,
CGWA NR dated 2nd March, 2020. Break-up of the water requirement is given below:
Table – 1.7 (A)
Total water input
S. No. Section Water quantity (KLPD)
1. Process water in fermentation 1100
2. Boiler feed water 280
3. DM water for distillation 200
4. Soft water for vaccum pump & others 100
5. Soft water for CT make up 1300
6. Fermenter washing & floor washing 100
7. Domestic consumption 20
Total water input 3100
Figure 1.4: Water Balance for 160 KLPD Molasses based distillery
Figure 1.5: Mass Balance for 160 KLPD Molasses based distillery
1.6.5 Steam Requirement
Steam generated from the boiler will be utilized in the generation of 7.0 MW Power which will be for the
own consumption and steam will be for boiler feed water heating and distillery process. Total steam
requirement for distillery is 55 TPH.
Source: 65 TPH Incineration Boiler.
The steam requirement for different purposes is given below:
Table – 1.8
Steam requirement
S. No. Purpose Steam Required (TPH)
1. Distillation Section 21.5
2. MEE Section 13.5
3. Molecular Sieve Dehydration unit 4.0
4. Steam Coil Air Pre-Heaters 6.0
5. De-aerator 5.0
6. Misc. 5.0
Total 55 TPH
Activity Months
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Appointment of 3
consultant, basic
engineering and
issue of tender
enquiries and
main machinery
order placement
for units
Civil 9
construction
Fabrication and 11
mechanical work
Electrical and 3
instrumentation
erection
Refractory works 2
Trial runs and 2
commissioning
Dilute alcohol water mixture from rectifier feed tank is pumped by rectifier feed pump through rectifier feed
pre-heater in to rectifying column. Rectifier and its associated equipment work under pressure so that these
vapors can supply the necessary heat for generating the vapors.
The condensate from analyzer column reboiler is then pumped as Reflux to rectifying column. Rich alcohol
vapors at a concentrating of 95.5 % v/v from top of rectifying column are condensed first in Analyzer reboiler
and then in Reflux vent condenser. The liquid is then collected in Rectifier Reflux Tank. Part of the liquid from
vent condenser may be drawn off as impure spirit. The impure spirit cut will be maintained as little as
possible to maintain aldehyde levels to meet the required limits in Absolute Alcohol.
Liquid from the rectifier reflux tank is pumped bye product pump partly as product and partly as reflux to the
top of the Rectifying column. The necessary rectifying vapors to rectifying column are generated by boiling
the bottom liquid in Rectifier column Re-boiler by using medium pressure steam, some side streams are
drawn from rectifier column as light and heavy fractions of higher alcohols called fusel oils and cooled in
fusel oil coolers. These are mixed with water and allowed to separate out in fusel oil separator. All vents from
condensers are connected to Vent Gas Absorber where the vent gases are scrubbed with water to recover
entrained alcohol. The scrubber water is used for washing the fusel oils in fusel oil separator to recover
alcohol from the fusel oil fractions. The absorber vent is connected to vacuum pump which is used to create
vacuum in the respective columns.
The plant will have high level of automation to get consistent output at required concentration.
Cooling water from cooling water is used in the surface condensers for condensing the vapors.
b) Incineration boiler along with the turbine generator:
The concentrated spent wash will be mixed with bagasse/biomass/coal and fired into especially designed
incineration boiler to generate high pressure steam and power.
air pre heaters flue gases pass through ESP where the dust particles are collected. The dust is collected in
closed system with dense phase technology for final disposal.
High pressure superheated steam from incineration boiler is passed through a steam turbine, which is used
for distillery process operations. While passing through the turbine, the high pressure and temperature
steam rotates the turbine rotor and an electric alternator mounted on the same shaft. Electric power is
generated by the alternator. This electric power generated is consumed in house i.e. for running the distillery
and utilities like incineration boiler’s auxiliaries etc.
1.8.3 Distillery Effluent Treatment Scheme –RO based Process condensate Treatment Plant
5) Biofilter
Molder will be present at the bottom which helps the sludge and solid particles to settle and clear water
flows through the sparging pipe having holes to the top.
6) Tube Settler Clarifier
Media will be added to filter the waste water from the contaminants and then passed to AT-1 (Aeration tank-
1)
7) Conventional Aeration Tank-1
In this section aeration and agitation will be done. The purpose of aeration is
To provide oxygen to bacteria so that it does not get deactivated.
To increase the chemical oxygen demand, this will further help in aerobic degradation.
Allow the biological matter to settle.
Biological treatment uses micro organisms which will be already present in waste water to degrade the
organic matter.
3 pumps will be present in AT-1:
i. 6 inches – tube settler pump.
ii. 2 inches – recycle from the clarifier
8) Clarifier -1
Sludge separator will be provided to separate waste water from solid particle. Water will be sent further to
AT-2 by gravity and sludge is passed to sludge tank and rest is sent back to AT-1.
pH is 8.2 and COD is 600 mg/l
9) Extended Aeration Tank-2
It withdraws feed from the clarifier-1. Two aerators will be provided for efficient aeration.
10) Clarifier-2
In this clarifier pH is 8.3 and COD level is 40 mg/l.
Water will be passed to Clarifier-3 and sludge back to AT-2. Poly-alum will be added after the sludge
separation which will be metered automatically. It clears the water.
11) Clarifier -3
Clear water from Clarifier-3 will be sent to R.O system by gravity.
COD is 0.1 mg/l
12) Sludge Tank / Bed
There will be 6 sludge tanks. Sludge will be filtered to remove the remaining water and then dried. It can be
further used as fuel.
During filter, 60% of the sand will be used as a filter media and 40% water will be added to increase
efficiency. After filtration the water will be passed to AT-1 and sludge to drier.
13) Multi Grade filter
Effluent will be passed through multi layers of filter media consisting of fine and coarse sand supported by
layers of pebbles and gravels with adequate pore size. This media will capture the small and large suspended
particles and undissolved impurities. The captured particles will be effectively removed by backwashing. The
filtered water will pass at the bottom of the tank from where it will be sent to Activated carbon filter.
14) Activated carbon filtration
Activated carbon filter uses a bed of activated carbon/charcoal that provides a larger surface area, allowing
maximum possible exposure to contaminants with the active sites in the filter media. It works on the basis of
adsorption whereby organic compounds in the water received from MGF are trapped inside the pore
structure of the carbon substrate. They effectively remove chlorine, sediment, volatile organic compounds,
taste and odour.
15) Multi membrane RO system
The reverse osmosis occurs when pressure, greater than the osmotic pressure, is applied to the water
recovered from ACF. Treated water is forced to flow from the concentrated to the diluted side, and solutes
are retained by the membrane. The membranes will allow the selective movement of solvent while rejecting
the solutes, such as salts or low molecular weight organic materials against its osmotic pressure difference. It
will effectively remove almost all the inorganic compounds, contaminant ions and most dissolved non-ions.
The permeate generated from the multi membrane RO system will be passed through the permeate RO
system for further removal of dissolve solid. The system comprises of two pressure vessels containing four
elements each configured in series. As the feed water will flow through the first membrane from feed to
reject end the pure water permeates through the membranes & will be collected in the permeate header.
The concentrated water will be collected in Reject header & then passes through the second pressure vessel.
The permeate generated from the system will be collected on the permeate RO product tank and recycled in
cooling tower whereas the final reject will be used as ash spray.
Table – 1.12
Characteristics of Untreated and treated effluent
S. Parameters Untreated Effluent Treated effluent
No. Evaporation process condensate Cooling tower blow down
Figure 1.8: Process Flow Chart for Distillery Effluent Treatment Scheme
Blow down: Waste water generated from cooling tower blow down, boiler blow down, vacuum pump
and sealing will be recycled in the process itself after proper treatment in CPU.
Domestic sewage- Will be treated in proposed sewage treatment plant and used for greenbelt
development.
1.9.3 Noise pollution
Acoustic enclosure will be provided to DG sets for controlling noise pollution.
Greenbelt will be developed around plant boundary to prevent noise problems outside plant
boundary.
Noise generating equipment like pump, motors, compressors, blower, turbine/engines, power
generator sets/ engines etc. will be mounted on sturdy concrete foundations with proper & suitable
rubber padding to reduce vibrations & thereby noise generation. Pumps, fans, compressor, etc. will be
statically and dynamically balanced.
The major noise producing equipment such as turbine will be provided with sound proof container,
where ever possible. Acoustic enclosure for DG set and similar provision like noise attenuator
wherever suitable/possible.
1.9.4 Solid and hazardous waste pollution
The ash will be used as manure due to rich potash content (biomass ash) or supplied to brick
manufacturers (coal ash).
Spent wash will be concentrated in Multi-effect evaporator and then used as fuel in boiler.
Sludge generated will be used as manure.
Used oil & grease generated from plant machinery/gear boxes as hazardous waste will be burnt
completely in incinerator boiler or sold to authorized vendors.
1.9.5 Soil pollution
No discharge of effluent or solid waste outside or inside plant premises will be done.
Strict disposal rules will be implemented inside and outside plant premises.
Solid and hazardous waste will be handled as per MSIHC rules so no dumping on soil environment.
Greenbelt will be developed and deforestation will be prevented.
No construction waste will be dumped on soil and proper bins will be constructed at designated areas
where dump will be collected and disposed according to their type.
The mitigation measures which will be incorporated by the project proponent for maintaining the prescribed
standards as directed by EPA, 1986, MOEFCC guidelines and CPCB guidelines have been given above. The
Company will implement all the mitigation measures compulsorily after obtaining EC during construction as
well as operation phase.
1.10 ASSESSMENT OF NEW & UNTESTED TECHNOLOGY FOR THE RISK OF TECHNOLOGICAL FAILURE
For this proposed project using different grades of Molasses and Cane Juice Syrup, only proven technologies
will be selected. No new or untested technology will be used. The Process will be based on proven
technologies i.e. HIFERM-Fermentation, Multi Pressure Distillation with integrated/SA Evaporation followed
by Incineration.