1.0 PURPOSE:
The purpose of this document is to explain the safe and effective Operation of the
electro chlorination plant.
2.0 RESPONSIBILITY:
The Electro chlorination plant is designed to prevent bio fouling in the condenser,
cooling tower and other facilities like Seawater intake, Pre-treatment Plant, CW
system and Potable water system. Sodium hypochlorite solution is used for the
chlorination / disinfection of the seawater circuit to prevent bio fouling growth of
marine organisms in the seawater facilities.
2. If SWRO system in running then open the ECP line inlet valve near MOV
(9GCB01AA051).
3. If SWRO system not in running condition then take any two PSF in rinse
mode with 60-70 m3/hr flow.
5. Open the Storage tank inlet valve (XSDV) and start blower.
7. The sea water fed to the electro chlorination plant at a pressure of 4.0 – 5.0
kg/cm2.
GPPC POWER PLANT,PIPAVAV
2X351MW Combined Cycle Power Plant
POMSP
L SOP
001
ECP Start up and shutdown SOP
GPPC POMSP
L
Revision Date Clau
Issue No Issue Date Revision
06.02.2018 se Page 2 of 5
001 Rev# 01
9. If the seawater supply pressure is ≤2.5 kg/cm 2, then the water is pumped by
means of seawater booster pumps (1 operating + 1 standby) to self-cleaning
filters to maintain pressure.
10. Ensure the service water line pressure near ECP plant above 3.00 kg/cm 2.
11. Open electrolyzer Inlet valve (XSDV002 for steam # A, XSDV003 for stream
# B, XSDV004for stream # C) and FCV (FCV001 for steam # A, FCV002 for
steam # B, FCV003 for steam # C) valve.
12. Establish the 27 m³/hr flow & set the flow valve in PLC SP box in auto mode
or give % valve in OP box in manual mode of respective stream.
13. Give the start command to rectifier from PLC after ensuring the following
steps.
14. Ensure all the starting parameters (feed flow, inlet pressure, Temp,) are well
within limits.
3. Ensure the storage tank blower in running condition for half an hour after
stopping the rectifier.
4. Flush the system with sea water to bring down temperature to room
temperature.
5. Stop the RO supply pump OR inlet vale near MOV 9GCB01AA051) which is
provided at seawater supply line.
6. Open the service water main isolation valve near the Hypo storage tank.
7. Open the electrolizer service water flushing inlet and outlet / drain valve and
let flush the system up to conductivity at both end are same.
The following conditions are incorporated towards automatic stop / trip of the
individual stream of electrolysers and its associated equipment’s
.
High High seawater inlet pressure
High seawater supply pressure
Low seawater flow at the inlet of Electrolyser stream
High differential pressure across electrolyser stream
High High solution temperature at the outlet of Electrolyzer stream
Seawater booster pumps trip
Low flow on the blower discharge header line occurs continuously.
High High Level in hypochlorite storage cum degassing tanks.
Loss of power, Transformer trip, Rectifier Failure.
The following conditions are incorporated towards automatic shutdown
of the complete plant.
H2 is 2.0% near hypochlorite storage cum degassing tanks and
Electrolysers.
Motor failure / stop of both the Air dilution blowers
Emergency plant shutdown by push button.
GPPC POWER PLANT,PIPAVAV
2X351MW Combined Cycle Power Plant
POMSP
L SOP
001
ECP Start up and shutdown SOP
GPPC POMSP
L
Revision Date Clau
Issue No Issue Date Revision
06.02.2018 se Page 4 of 5
001 Rev# 01
Flow switch provided at the inlet of each Electrolyzer stream will deliver
alarm and trip the respective Electrolyzer stream in case of low flow
and close the respective upstream ON-OFF valves with time delay.