Operator Snag (Level UB,B1,B2,B3) Outstanding Comments

Checklist Comment Responsible


SI NO Level Snag issued Date No. No COMMENT Contractor STATUS

1 UB 24-Mar-21 101 4.2 Window seal is missing REA Not done


4 UB 24-Mar-21 105 2.6 Door paint damage TGC Not done
UB 2.6 Door paint damage TGC Not done
5 24-Mar-21 109 Ceiling iron beam several places paint damage and joint
UB 3.1
rusty TGC Not done

UB 1.1 At several place floor paint damage need to redo TGC Not done
7 UB 24-Mar-21 114 2.1 At several place wall paint damage need to redo TGC Not done
UB 3.1 At several place Ceiling paint is damage and stain on it. TGC Not done
AT several place floor paint damage and stain on it need
UB 1.1 TGC Not done
to redo.
8 UB 24-Mar-21 115 2.1 At several place wall paint damage need to redo TGC Not done
UB 2.2 Wall skirting paint damage need to redo TGC Not done
UB 2.3 Wall acrylic sheet stain mark on it TGC Not done
10 UB 24-Mar-21 117 1.2 Railing paint damage and need to redo TGC Not done
UB 1.1 At several place floor paint is damage TGC Not done
UB 1.2 At several place paint and glue stain TGC Not done
12 24-Mar-21 120
UB 2.1 There several stain on the wall TGC Not done
UB 2.2 Wall skirting paint damage TGC Not done
UB 1.1 At several place floor paint is damage TGC Not done
13 24-Mar-21 121
UB 1.2 At several place paint and glue stain TGC Not done
UB 1.1 At several place floor paint is damage TGC Not done
14 UB 24-Mar-21 122 1.2 At several place paint and glue stain TGC Not done
UB 2.3 Door and door frame paint damage TGC Not done
UB 2.6 Door and door frame paint damage TGC Not done
15 UB 24-Mar-21 125 2.8 Fire extinguishing cabinet singage is missing TGC Not done
UB 2.14 Wall hole to be close near the hand wash sink TGC Not done
16 UB 24-Mar-21 126 2.2 Door key cylinder is missing TGC Not done
17 UB 24-Mar-21 129 1.1 At several place floor paint is damage and stain on it TGC Not done
18 UB 24-Mar-21 130 3.2 Several ceiling tiles have yellow and black stain on it. TGC not done
Ceiling paint is pending and cable tray plastic sheet to
19 UB 24-Mar-21 131 3.1 TGC Not done
remove
20 UB 24-Mar-21 133 2.1 Door paint is damage and scratch mark on it. TGC Not done
21 UB 24-Mar-21 134 2.1 Door paint is damage and paint mark on it. TGC Not done
23 UB 24-Mar-21 136 2.1 Door paint is damage and paint mark on it. TGC Not done
Main Door, Compressor Rm door and frame paint
24 B1 15-Mar-21 5 2.2 TGC Not done
damaged
25 B1 15-Mar 6 2.4 Office all walls wall paper gap visible TGC Not done
26 B1 15-Mar 7 2.2 Office area wall paper joint gap visible TGC Not done
27 B1 15-Mar 8 2.2 Office area wall paper joint gap visible TGC Not done
28 B1 15-Mar 9 2.2 Office area wall paper joint gap visible TGC Not done
29 B1 15-Mar 10 2.3 Office all walls wall paper gap visible TGC Not done
30 B1 15-Mar 11 2.4 Office all walls wall paper gap visible TGC Not done
31 B1 15-Mar 12 2.2 Wall paper joints gap visible TGC Not done
32 B1 15-Mar 13 4.1 Door key cylinder is missing TGC Not done
33 B1 15-Mar 14 2.2 All the Wall paper joints gap visible TGC Not done
34 B1 15-Mar 15 2.2 All the Wall paper joints gap visible TGC Not done
B1 2.1 Door key cylinder is missing TGC Not done
35 15-Mar 16
B1 2.2 All the Wall paper joints gap visible TGC Not done
B1 15-Mar 17 2.2 All the Wall paper joints gap visible TGC Not done
36
B1 15-Mar 18 2.2 All the Wall paper joints gap visible TGC Not done
37 B1 15-Mar 19 2.2 All the Wall paper joints gap visible TGC Not done
39 B1 15-Mar 21 2.1 From inside door is damage TGC Not done
B1 1.2 Scratches on the floor tile TGC Not done
40 15-Mar 22
B1 2.1 door paint is damage TGC Not done
41 B1 15-Mar 25 4.6 Rolling shutter is not yet installed TGC Not done

B1 2.1
At some places of Wall paint damage, Door and door TGC Not done
44 15-Mar 35 frame paint damage
B1 2.4 Door Warning sign of extinguish agent is damage TGC Not done
45 B1 15-Mar 36 2.4 Ramp hand rail paint damage TGC Not done
46 B1 15-Mar 42 4.3 Window seal beading is not installed REA Not done
47 B2 43 2.1 All the wall paper joints gap visible TGC Not Done
B2 2.1 All the wall paper joints gap visible TGC Not Done
48 16-Mar-21 44
48 16-Mar-21 44
B2 3.5 Finishing with the wall paper edges with ceiling is not good TGC Not Done
49 B2 16-Mar-21 45 2.1 All the wall paper joints gap visible TGC Not Done
B2 1.1 Near the entrance door floor paint damage TGC Not Done
50 16-Mar-21 50
B2 2.2 Both entrance door and door frame paint damage has a paint TGC Not Done
51 B2 16-Mar-21 52 2.2 Both entrance door and door frame paint damage has a paint TGC Not Done
53 B2 16-Mar-21 55 2.1 Door freme paint is damage and paint mark on it. TGC Not done
B2 1.1 several Part of floor paint damage need to redo TGC Not Done
B2 2.1 Wall paint not yet started TGC Not Done
55 16-Mar-21 59
B2 2.3 Door key cylinder is missing TGC Not Done
B2 3.1 Ceiling paint not yet started , holes & conduit box cover to be TGC Not Done
B2 1.1 several Part of floor paint damage need to redo TGC Not Done
56 16-Mar-21 61
B2 1.2 On the floor joint paint damage TGC Not Done
58 B2 16-Mar-21 66 2.2 Door is damage from the bottom and stain on it TGC Not Done
B2 1.1 At some places paint stain & scratch mark on it TGC Not Done
59 16-Mar-21 67
B2 2.2 There is scratch mark on the door TGC Not Done
60 B2 16-Mar-21 68 2.4 Door frame paint damage TGC Not Done
61 B2 16-Mar-21 70 2.4 Door paint damage and scratch mark TGC Not Done
B2 2.1 At several place scratch and stain mark on it TGC Not Done
62 17-Mar-21 71
B2 2.4 Door paint damage and scratch mark TGC Not Done
63 B2 17-Mar-21 72 2.1 At several place scratch and stain mark on it TGC Not Done
B2 1.2 Gap between sliding door frame and floor ro be sealed TGC Not Done
65 B2 17-Mar-21 74 3.1 Several ceiling tile have damaged and black &yellow stain on i TGC Not Done
B2 3.3 Several dirty ceiling tile to be clean properly TGC Not Done
B3 1.1 Entire floor paint is damage needs to redo TGC Not Done
B3 1.2 Main hole cover is rusty need to color it TGC Not Done
B3 2.2 Wall skirting missing and conduit pipe box to be cover TGC Not Done
66 21-Mar-21 75
B3 2.9 Water tank access door not yet fixed TGC Not Done
B3 2.12 Door key cylinder is missing TGC Not Done
B3 3.4 At several places ceiling paiting is not done TGC Not Done
B3 2.3 Door and door frame paint damage TGC Not done
67 B3 21-Mar-21 76 2.1 Above the skirting there is several stain on the wall TGC Not done
B3 1.2 At several place floor paint is damage and scratch on it TGC Not done
B3 2.3 Entrance and Staircase Door and door frame paint is damage TGC Not done
68 77
B3 2.4 Door key cylinder is missing TGC Not done
69 B3 21-Mar-21 79 2.2 Door and door frame paint is damage TGC Not Done
B3 1.2 At several place floor paint is damage TGC Not Done
B3 2.5 Chiller room steel stairs painting not done TGC Not Done
B3 2.6 Water tank wall steel mesh damage TGC Not Done
70 21-Mar-21 81
B3 2.7 Water tank access door not yet fixed TGC Not Done
B3 2.1 Door key cylinder is missing TGC Not Done
B3 3.1 At several place ceiling mesh is damage TGC Not Done
B3 2.1 There is several stain mark on the wall TGC Not Done
71 B3 82 2.2 Near the skirting wall paint is damage TGC Not Done
B3 2.4 Wall skirting area paint is damage and stain on it TGC Not Done
B3 1.2 Gap between sliding door frame and floor ro be sealed TGC Not done
B3 2.6 Plastic sheet on elevator door to be removed TGC Not done
72 21-Mar-21 83
B3 3.1 Several ceiling tile have damaged and black &yellow stain on i TGC Not done
B3 3.3 Several dirty ceiling tile to be clean properly TGC Not done
B3 1.1 Floor is covered with the plastic sheet TGC Not done
B3 2.1 Entire wall paint is damage TGC Not done
B3 2.2 Several black and yellow stain on it TGC Not done
B3 2.3 Door and door frame paint is damage TGC Not done
73 B3 21-Mar-21 85 2.6 Wall corner guard is missing TGC Not done
B3 3.1 Several ceiling tile is damage TGC Not done
B3 3.2 There is several black and yellow stain on the ceiling tile. TGC Not done
B3 3.4 Ceiling frame is damage and ceiling tile is missing TGC Not done
B3 4.3 Wall corner guard is missing TGC Not done
74 B3 21-Mar-21 86 2.3 Door and door frame paint is damage TGC Not done
75 B3 21-Mar-21 88 2.3 Door and door frame paint is damage TGC Not Done
76 B3 89 2.3 Door and door frame paint is damage TGC Not Done
B3 1.2 several stains markson the floor TGC Not Done
B3 2.1 Service lift lobby entire wall paint damage TGC Not Done
77 B3 90 2.3 Wall acrylic protection sheet and corner guard to be fix. TGC Not Done
B3 2.4 Both door and door frame paint is damage TGC Not Done
B3 3.1 Lift lobby area several ceiling tiles are damage and frame gap TGC Not Done
B3 1.1 At several place floor paint damage needs to redo TGC Not Done

B3 TGC Not Done


78 21-Mar-21 92 1.2 At several place paint and putty stain on the floor
B3 TGC Not Done
1.5 Main hole cover is rusty