00 30-Jun-18
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Review of Relief Valve Authorization SAIC-J-2005 24-Jul-18 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
The Originating Engineer enters the data into the corporate SAP system
using the Transaction Code IE01 (Create Equipment). At this stage of the
process, the RV is assigned a permanent number which should be kept in
SAEP- 319 , Para
A2 a permanent RV data records having “CRTD” Created mode in User
6.1.2
Status. Once all required RV data records are entered, then the Originator
should select “Awaiting Approval” mode in User Status field of the SAP
system.
The relief valve has been assigned an RV number,. Follow the SAP SAEP-319
A4
approval Process as in Appendix A SAEP-319 Appendix A
Workflow shall be sent to the Project inspection supervisor through SAP SAEP-319
A8
for review and approval. Sec. Appendix A
REMARKS:
ATTACHMENTS:
ATTACHMENT 1 - SAEP-319 FLOWCHART FOR RVs 2 July 2017
REFERENCE DOCUMENTS: 1. SAEP-319, Inspection and Testing Requirements for Pressure Relief Devices,2 July 2017
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified