Professional Documents
Culture Documents
Challenges:
Solution:
Result:
350 bbl of FlexSTONE HT NS batch mixed (good dry blend flowability and
slurry density achieved as per design). 3 x 150 bbl batch mixers used in
series (6 compartment tanks in total)
Cementing job pumped and displaced under MPD scenario, minor losses
Top Plug bumped and ZXP packer set as per plan
Cement liner cap was drilled showing hard cement proving good cement
quality and low contamination.
Jose Salazar
Schlumberger-Private
Slurry presents minor incompatibility with OBM, optimizing the rig operation
to handle returns and successfully engage the dummy seal assembly into the
PBR at the first attempt.
FlexSTONE HT NS
Jose Salazar
Schlumberger-Private
CemSTRESS* Simulation
CemSTRESS software was used to analyze the stress environment and confirmed
the FlexSTONE HT NS* mechanical properties meets the requirements for proper
zonal isolation of TOR limestone formation under HTHP high stress environment.
The cement job was performed as per program without any HSE or Quality incident:
The slurry mixability in batch mixer was excellent giving an average mixing time of
approximately 25 minutes per 60bbl of slurry. CemNET fibers were added to the
slurry at a concentration of 1.5 lb/bbl to mitigate the risk of losses.
The bulk flow was smooth and contributed to trouble free mixing without stoppages.
Jose Salazar
Schlumberger-Private
During the slurry placement approximately 40 bbl of Versatherm mud were lost to
the formation, however no losses were recorded after cement and spacer were
pumped in the annulus.
Most of the job has been pumped at 4 bbl/min with the exception of the last 300bbl
of displacement when the rate was limited to 3 bbl/min and then 2 bbl/min to reduce
the impact of the higher pressure induced by the cement and minimize the risk of
losses.
The cement job was performed under managed pressure cementing. The return line
was chocked during the entire cement job operation to maintain the well under
control with the added ECD provided by the surface equipment. The surface back
pressure was gradually backed off towards the end of the displacement to
compensate for the pressure increase generated by the raise of the cement in the
annulus. The following chart shows the profile of the actual back pressure versus
time applied during the cement job.
Jose Salazar
Schlumberger-Private
950
900
850
During the pumping operations the job was monitored with Invizion Real Time
software. Invizion RT has proven to be a valuable tool for a better understanding of
the job parameters and the experience accumulated in this field trial will greatly
contribute to the improvement of the future versions of the software for managed
pressure cementing operations.
Cement Evaluation
The cement job has been a complete success from every perspective. The new
cement system has been mixed and placed as per plan. There was no loss of
cement to the formation which is a great success in itself considering the very
critical conditions with the extremely narrow window between pore and frac.
Hard cement was tagged and drilled out above the expected top of cement
indicating that the open hole was close to the nominal 12 1/4in value. This is also in
line with the good agreement between the post job simulation and the acquired
pumping pressure as shown in the figure below.
Indication from the cement logs performed with Schlumberger Isolation Scanner
tool have shown good cement coverage and good zonal isolation of high pressure
Hod Mass anomaly gas zone.
Jose Salazar
Schlumberger-Private