Professional Documents
Culture Documents
Sensitivity: Internal & Restricted
Sensitivity: Internal & Restricted
4 Value is always defined from the perspective of the a. Customer b. Project c. Product
d. All of the above Hide Answer Answer : Customer
5 ______________ is a Visual Control device in the work area indicating a process or quality
problem a. Andon Board b. SMED c. Both 1 and 2 d. None Hide Answer Answer : Andon
Board
6 ______________ is the rate (time per unit of value) at which work should proceed
through a Value Stream a. Cycle Time b. Activity Time c. Takt Time d. All the above Hide
Answer Answer : Takt Time
7 This technique can be used to conduct root cause analysis a. 5 Why b. Fishbone
diagram c. Cause and Effect diagram d. All the above Hide Answer Answer : All the
above
16 Which of the following is not a root cause analysis technique a. Pareto diagram b. 5
Why c. Fish Bone Diagram d. Mistake Proofing Hide Answer Answer : Mistake Proofing
18 Identifying the necessary and removing unwanted one in any workplace is called a.
Straighten b. Automation c. Mistake proofing d. Sort Hide Answer Answer : Sort
19 What is the typical first step towards identifying the area of waste elimination in a
project a. Root Cause Analysis b. 5S c. Mistake proofing d. Value Stream Mapping Hide
Answer Answer : Value Stream Mapping
20 Kaizen applied with the right approach helps in achieving a. Quantum improvement
b. Incremental improvement c. Sustains the performance d. Marginal improvement
Hide Answer Answer : Incremental improvement
21 ‘Value’ in Lean terms is a deliverable to the client which is usable. Identify which
statements below qualify for this Value definition a. Value for a recruitment group is
each human resource made available to the project teams b. Value for a Maintenan ce
project is the Bugs serviced per release c. Value for a Conversion project is every web
page converted d. All of the above Hide Answer Answer : All of the above
22 Identify Type 2 “Waste” in these scenarios a. Waiting and searching for resources in
the lab during reproduction and testing b. Capturing relevant information in defect
tracker c. Updating knowledge base d. Frequent build cycles, frequent code reviews and
early testing Hide Answer Answer : Waiting and searching for resources in the lab
during reproduction and testing
26 During which phase of the project can Lean be implemented? a. Requirement phase
b. Design phase c. CUT & ST phases d. All of the above Hide Answer Answer : All of the
above
27 The delivery team uses white boards to monitor the status of the tickets, automates
routine jobs, maintains checklist and implements learning from previous releases. The
team does not have a knowledge of Lean and has never attended any Lean training
sessions. Is Lean being practiced in the project a. Yes b. No c. Can’t answer d. None of
the above Hide Answer Answer : Yes
29 Which of the following are two key pillars of the Toyota Production System? a. Just-in-
Time and Waste Elimination b. Jidoka and Just in Time c. Visual Management and Kaizen
d. Standardisation and Leveled Production Hide Answer Answer : Jidoka and Just in Time
30 The culture of stopping when there is a quality problem is called a. Waste elimination
b. Standardisation c. Jidoka d. None of the above Hide Answer Answer : Jidoka
32 The roots of Lean thinking can be traced back to a. Harvard b. GE c. Honda d. Toyota
Hide Answer Answer : Toyota
41 To reduce test setup change-over time, you considered SMED technique. Which of
the following principles can help? a. Displace b. Eliminiate c. Standardize d. All of the
above Hide Answer Answer : All of the above
42 Customer expects the team to test 10 features in 20 working days. What is the takt
time? a. 10 features/month b. 2 days/feature c. 0.5 features/day d. None of above Hide
Answer Answer : 2 days/feature
45 An effective way to make team memebrs aware of progress made and currents
status is through a. Visual Boards b. Poka – yoke c. Mura d. Muri Hide Answer Answer :
Visual Boards
46 Mistake proofing is a. Andon b. Poka – yoke c. Mura d. Muri Hide Answer Answer :
Poka – yoke
47 Over production is avoided by using ___________ a. Pull system b. Poka – yoke c. Mura
d. Push system Hide Answer Answer : Pull system
48 How many Lean principles are there according to Jeffrey Liker as presented in “The
Toyoto Way” a. 5 b. 10 c. 14 d. None of the above Hide Answer Answer : 14
49 How many categories of wastes can be identified as per the Toyota Production
System? a. 7 b. 10 c. 100 d. 20 Hide Answer Answer : 7
54 A tool in the work area giving the current status of the work a. Visual Control Board
b. SMED c. Both 1 and 2 d. None Hide Answer Answer : Visual Control Board
57 In TPS, high levels of quality is achieved by the principles of a. Jidoka b. Poka Yoke c.
Both 1 and 2 d. None Hide Answer Answer : Both 1 and 2
60 Problems identified are displayed for everyone’s attention rather than covering up a.
Make the problem visibile b. Make it fast c. Make it beautiful d. None Hide Answer
Answer : Make the problem visibile
61 Any activity that consumes resources, but does not create value is _______________ a.
Muda b. Mura c. Muri d. All the above Hide Answer Answer : Muda
62 Tasks with clear specification on the input, process, time and output are
_______________ a. Fixed b. standardized c. Designed d. All the above Hide Answer Answer
: standardized
63 Identification of all activities occuring along the life cycle of the product is _________ a.
Value Creation b. Value Stream Mapping c. Customer Value d. None Hide Answer
Answer : Value Stream Mapping
66 In the 5 Why analysis, if the root cause is not identified at the 5th Why, one should
_______________ a. Stop b. Start afresh c. Continue d. None Hide Answer Answer :
Continue
68 What is the ongoing process/philosophy of doing things better, faster and lower
cost? a. Continuous Processs b. Continuous Engineering c. Continuous Improvement d.
None Hide Answer Answer : Continuous Improvement
70 Lean practices optimizes the a. Cost b. Qualitty c. Schedule d. All the above Hide
Answer Answer : All the above
75 An engineer fixes a bug request from the customer. The customer value here is
_______________ a. Fixed Bug b. No side effect c. Both 1 and 2 d. None Hide Answer
Answer : Both 1 and 2
77 According to Lean thinking, leaders should work with first hand information from
_______________ by direct observation. a. Customers b. Workplace c. Both 1 and 2 d. None
Hide Answer Answer : Workplace
79 In a maintenance project with a 3 month release cycle, the team idles during the first
six weeks due to lack of clarity. The customer expects team to work as per the planned
efforts in the remaining 6 weeks. This will lead to _______________ a. Task switching b.
Overload c. Poor quality d. Both 2 and 3 Hide Answer Answer : Both 2 and 3
81 _______________ is the time taken for those activities that actually transform the
product/service in a way that the customer is willing to pay for a. Takt Time b. Activity
Time c. Cycle Time d. Value Added Time Hide Answer Answer : Value Added Time
82 Those activities that are not mandatory to provide what customer wants are
_______________ a. Important b. Non Value Add c. Both 1 and 2 d. None Hide Answer
Answer : Non Value Add
84 Mechanisms (other than inspection at a work place) to achi eve in-station quality by
prevention is an example of _______________ a. Jidoka b. Heijunka c. Poka Yoke d. All the
above Hide Answer Answer : Poka Yoke
87 Standardized work and environment are the basis for a. Continuous improvement b.
Defect prevention c. Both 1 and 2 d. None Hide Answer Answer : Continous
Improvement
92 Automatically stopping the process when something is wrong and then fixing the
problems on the line itself as they occur is called _______________ a. Heijunka b. Jidoka c.
Kaizen d. Kanban Hide Answer Answer : Jidoka
93 Which of the following are examples of Muda (waste) in the process which should be
eliminated? a. Doing work manually when it can be automated b. Equipment not
working c. Spending efforts in processing repetitive issues d. All of the above Hide
Answer Answer : All of the above
95 Lean is not _______________ a. Short term gain b. Problem Solver c. Action Oriented d.
Continous Improvement Hide Answer Answer : Short term gain
100 The PM defines the coding standard for a new technology before the development
starts. Based on these guidelines, he also reconfigures the code review tool. Choose the
Lean tenets PM has applied a. Standardization & Mistake proofing b. Standardization &
Statistical Analysis c. Only Standardization d. 5S and Mistake proofing Hide Answer
Answer : Standardization & Mistake proofing
101 What are the 5 STEPS of 5S? a. Shine, Solve, Sustain, Sort, Standardize b. Sustain,
Sort, Standardize, Set, Shine c. Sort, Straighten, Shine, Standardize, Sustain d. Sort,
Sustain, Sushi, Shine, Standardize Hide Answer Answer : Sort, Straighten, Shine,
Standardize, Sustain
102 Which statements defines “VALUE”? a. The customer has to be willing to pay for the
activity b. The activity must “directly transform” the item or person flowing through the
process into what the customer is willing to pay for. c. The activity must meet all
expected requirements on the first attempt d. All of the above Hide Answer Answer : All
of the above
104 What is the first step in the VSM? a. Draw the Value stream mapping(As -IS) b.
Identify the customer Value deliverable c. Remove the wastes d. Identify the Value
added and Non value added activities Hide Answer Answer : Identify the customer Value
deliverable
106 Which of the following tenets is used for work place management? a. SMED b. 5S c.
VSM d. DSM Hide Answer Answer : 5S
107 Which of the following Lean methodologies can be used to identify the waste in the
process? a. DSM b. 5S c. VSM d. CMMI Hide Answer Answer : VSM Also Read : The best
apps to gather followers on Instagram: InstaTags, Follower Insight
108 Identify the applicable tenet used for identifying the root cause of the problem a. 5S
b. Statistical Analysis c. 5WHY d. PDCA Hide Answer Answer : 5 WHY
109 In an application maintenance project, the team was following the practice of
placing a Red flag in front of the engineer who was stuck up with a problem related to
resolving the incident. This is an example of _______________ a. Standardization b. Kanban
c. Andon d. None of the above Hide Answer Answer : Andon
110 How many guiding principles does Lean have? a. 11 b. 7 c. 12 d. 14 Hide Answer
Answer : 14
111 _____________ provides a complete visibility of all work items and status in the team
a. Standardization b. Mistake Proofing c. Visual Control d. ecube Hide Answer Answer :
Visual Control
113 Which of the following is not part of 5S? a. Sort b. Sustain c. Shine d. Sequence Hide
Answer Answer : Sequence
115 Which of these are not a core Lean principle according to Womack a. Pull b. Flow c.
Value d. Push Hide Answer Answer : Push
116 The principle of flow emphasizes on __________ a. reduction in batch size b. Moving
to next phase as quickly as possible c. Individual productivity d. Customer satisfaction
Hide Answer Answer : reduction in batch size