Department of Public Works and Highways (DPWH) : Instructions For Completeting The Summary of Bid Prices
Department of Public Works and Highways (DPWH) : Instructions For Completeting The Summary of Bid Prices
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera,
Talomo District, Davao City
ABC: Php 9,800,000.00
Location of the Contract : Davao City
B.5 15,307.66
Project Billbord/Signboard (2-4'x8' DPWH Billboard, 1-8'x8' COA Billboard)
B.7(2) Occupational Safety and Health Program 523,345.18
B.8(1) Traffic Management 113,400.00
B.9 Mobilization/Demobilization 15,763.13
PART C EARTHWORKS
Nine Million Seven Hundred Thousand Four Hundred Thirty Seven Pesos and 13/100.
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo District,
Davao City
Location of the Contract : Davao City
BILL OF QUANTITIES
Part No. Part Description :
Section Scope of Work Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART B OTHER GENERAL REQUIREMENTS
In Words In Words
Twenrt Four Thousand Six Hundred Six Thousand Two Hundred Fourteen
B.4(1) Construction Survey and Staking Kilometer 0.252 Sixty Pesos. Pesos and 32/100.
In Words
Sub-Total for this Page: Six Hundred Seventy Four Thousand
Thirty Pesos and 28/100.
In Figures 674,030.28
Submitted by:
In Words
Sub-Total for this Page: Two Million Seven Hundred Ninety Nine
Thousand Three Hundred Forty Pesos
and 38/100.
In Figures 2,799,340.38
Submitted by:
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo District,
Davao City
Location of the Contract : Davao City
BILL OF QUANTITIES
Part No. Part Description :
Section Scope of Work Unit Quantity Quantity Bid Price
No. (Pesos) (Pesos)
(1) (2) (3) (4) (5) (6)
PART F BRIDGE CONSTRUCTION (BOX CULVERT)
In Words In Words
Sixty Eight Pesos and 55/100. Two Million One Hunded Fifteen Thousand
404(1)a Reinforcing Steel, Grade 40 Kilogram 30,865.00
Seven Hundred Sixty Pesos and 50/100.
In Figures 68.55 In Figures 2,115,760.50
In Words In Words
Seven Thousand Nine Hundred Two Million Three Hundred Ten Thousand
Structural Concrete (27.58 Mpa,
Cubic Meter 291.60 Twenty Three Pesos and 39/100. Four Hundred Fifty Nine Pesos
405(1)b2 Class A, 14 days)
and 23/100.
In Figures 7,923.39 In Figures 2,310,459.23
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
In Words In Words
Thirty Five Thousand Seven Hundred One Hundred Forty Two Thousand
502(5) Metal Frames and Gratings Pair 4.00 Six Pesos and 90/100. Eight Hundred Twenty Seven Pesos
and 61/100.
In Figures 35,706.90 In Figures 142,827.61
In Words In Words
Two Thousand Four Hundred Fifty One Million Six Hundred Fifty Eight
505(2)a Grouted Riprap (Class A) Cubic Meter 675.22 Five Pesos and 52/100. Thousand Eight Hundred Twenty Seven
Pesos and 61/100.
In Figures 2,455.52 In Figures 1,658,019.13
In Words
Sub-Total for this Page: Six Million Two Hundred Twenty Seven
Thousand Sixty Six Pesos and 47/100.
In Figures 6,227,066.47
Submitted by:
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera,
Talomo District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
No. of Qty. Description Rate per Day No. of Days COST (ADD)
1 Construction Foreman 650.00 1 650.00
2 Instrumentman 475.00 1 950.00
4 Surveyman 475.00 1 1,900.00
3 Laborer 350.00 1 1,050.00
SUB-TOTAL 4,550.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 4,550.00
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera,
Talomo District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 1,475.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 1,475.00
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 175,417.55
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 175,417.55
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 21,400.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 21,400.00
Total Direct Cost P 100,000.00
O.C.M. P -
Profit P 8,000.00
TAX P 5,400.00
Total Indirect Cost P 13,400.00
Total Cost P 113,400.00
Unit Cost P 28,854.96
Department of Public Works and Highways (DPWH)
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL -
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P -
Total Direct Cost P 15,012.50
O.C.M. P -
Profit P -
TAX P 750.63
Total Indirect Cost P 750.63
Total Cost P 15,763.13
Unit Cost P 15,763.13
Department of Public Works and Highways (DPWH)
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 1,350.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 1,350.00
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 135,850.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 135,850.00
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 10,700.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 10,700.00
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 53,500.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 53,500.00
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo
District, Davao City
Location Of Contract Davao City
DETAILED ESTIMATES
I. EQUIPMENT RENTAL/MATERIALS:
SUB-TOTAL 6,000.00
Plus % Fringe Benefits -
TOTAL Direct Labor Cost P 6,000.00
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 11.82 trips/day
Total DT travel time 38.07
say 11.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 11.82 trips/day
Total DT travel time 38.07
say 11.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
No. of trips per day = 7.5 hrs./day x 60min./hr. = 450 = 6.41 trips/day
Total DT travel time 70.21
say 6.00 trips/day
=
No. of days to complete hauling = #REF! cu.m. #REF! days
Loader Requirement:
Equipments Required:
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 sq.m/day
No.of days required: #REF! / 420.00 = #REF! days say #REF! days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days
Equipments Required:
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 sq.m/day
No.of days required: #REF! / 420.00 = #REF! days say #REF! days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days
BACK-UP COMPUTATION
5b/8
Equipments Required :
GRADER: for spreading 1 unit
Capacity: 60 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 60 x 7 = 420.00 cu.m/day
No. of days required: #REF! / 420 = #REF! days say #REF! days
COMPACTOR: 1 unit
Capacity: 30 cu.m/hr 7 hrs/day
Capacity/day: 1 unit x 30 x 7 = 210.00 cu.m/day
No. of days required: #REF! / 210.00 = #REF! days say #REF! days
BACK - UP COMPUTATION
506 Riprap
Quantity:
Volume Multiplier
Cement = #REF! x 3.5 = #REF! bags say #REF! bags
Sand = #REF! x 0.51 = #REF! say #REF! cu.m.
Boulders = #REF! x 1.05 = #REF! say #REF! cu.m.
Quantity:
Volume Multiplier
Cement = #REF! x 4.25 = #REF! bags say #REF! bags
Sand = #REF! x 0.62 = #REF! say #REF! cu.m.
Boulders = #REF! x 1.05 = #REF! say #REF! cu.m.
Quantity:
Volume Multiplier
Cement = #REF! x 4 = #REF! bags say #REF! bags
Sand = #REF! x 0.605 = #REF! say #REF! cu.m.
Boulders = #REF! x 1.05 = #REF! say #REF! cu.m.
Department of Public Works and Highways (DPWH)
Contract ID : 20LB0183
Contract Name : Construction of Drainage Along Davao – Cotabato Old Rd. K1520+745 –
K1520+750, Davao City
Location of the Contract : Davao City
MANPOWER
Project Engineer 1,000.00 / day
C & M Foreman / Eng'ng Assistant 650.00 / day
Laborer / T&C Helper 350.00 / day
Mason/ Steelman/ Carpenter/ Painter 475.00 / day
Welder/Eletrician 420.00 / day
H.E.O. (Bulldozer/Excavator/Loader/Grader/Crane/Prime Mover) 550.00 / day
Driver (Dumptruck/Water Truck) 475.00 / day
L.E.O. (Compactor, Vibrator, Mixer) 425.00 / day
Crane 80.00 lit. / day 21,250.00 / day
Bulldozer 80.00 lit. / day 15,780.00 / day
Back hoe 60.00 lit. / day 8,800.00 / day
Dump Truck 50.00 lit. / day 7,250.00 / day
Water Truck 35.00 lit. / day 5,725.00 / day
Road Grader 50.00 lit. / day 8,250.00 / day
Road Roller 40.00 lit. / day 6,700.00 / day
Pay Loader 50.00 lit. / day 11,550.00 / day
Transit Mixer 40.00 lit. / day 7,250.00 / day
PRIME MOVER/ LOW BED TRAILER 60.00 lit. / day 9,300.00 / day
Single Bagger Concrete Mixer 6.00 lit. / day 1,670.00 / day
Concrete Vibrator 6.00 lit. / day 1,030.00 / day
PLATE COMPACTOR 5.00 lit. / day 1,000.00 / day
Chainsaw Operated 2,400.00 / day
Concrete Cutter Operated 1,250.00 / day
BAR CUTTER /BAR SHEAR Operated 1,750.00 / day
BAR BENDER Operated 1,100.00 / day
Concrete Batch Plant 14,100.00 / day
Concrete Screeder 4,360.00 / day
Concrete Saw 260.00 / day
DIESEL 50.00 / liter
GASOLINE 60.00 / liter
Submitted by:
MATERIALS
Portland Cement 258.00 / bags
Reinforcing Deformed bars 44.00 / kg.
Asphalt cement 60/70 Hot poured 44.00 / liter
Plastic Canvass (12 ft. wide) 141.60 / mtrs
Hacksaw blade (Heavy duty) 82.00 / pcs
Deformed bars/RSB (Grade 40) 42.00 / kgs.
Assorted CW Nails 76.00 / kgs.
Tarpauline - as per design 25.00 / sq.ft.
Ordinary plywood, 10mm thk. x 4' x 8' 714.00 / pc/s
Marine plywood, 5mm thk. x 4' x 8' 714.00 / pc/s
Coco Lumber 18.00 / bdft.
Coco Net 120.00 sq.m.
Coco Log 390.00 ln.m.
Vegitation 81.00 sq.m.
Tie Wire, G.I # 16 80.00 / kgs.
4" CWN 70.00 / kgs.
Boulders Extraction 50.00 / cu.m.
CHB 4" 20.00 / pcs
REINFORCING STEEL 44.10 / kgs.
TIE WIRE # 16 76.00 / kgs.
HACKSAW BLADE 70.00 / pcs
WASHED GRAVEL 800.00 / cu.m.
WASHED GRAVEL Y-Y 700.00 / cu.m.
WASHED SAND 700.00 / cu.m.
AGGREGATE BASE COARSE 500.00 / cu.m.
AGGREGATE SUB-BASE COARSE 500.00 / cu.m.
BOULDERS 1,000.00 / cu.m.
GOODMIX 600.00 / cu.m.
Submitted by:
Contract ID : 20LB0183
Contract Name : Construction of Drainage Along Davao – Cotabato Old Rd. K1520+745 –
K1520+750, Davao City
Location of the Contract : Davao City
Submitted by:
Contract ID : 21LB0302
Contract Name : Construction of Drainage System at Libby Bridge, Purok 6, Bago Gallera, Talomo District, Davao City
Location of the Contract : Davao City
ABC :
YEAR
PARTICULAR TOTAL
FIRST QUARTER SECOND QUARTER THIRD QUARTER FOURTH QUARTER
Percentage Accomplishment 100.00% 5.95% 7.99% 11.34% 74.72%
AMOUNT 576,917.50 775,374.88 1,100,262.67 7,247,882.09
Cumulative Percentage Accomplishment 100.00% 5.95% 13.94% 25.28% 100.00%
AMOUNT 576,917.50 1,352,292.37 2,452,555.05 9,700,437.13
Submitted by: