Annexure - H

DETAIL DESIGN AND CONSTRUCTION SUPERVISION OF WATER SUPPLY SYSTEM,GUJRAT

SCHEDULE OF ACTIVITIES

DESIGN STAGE
Sr. MONTHS
Activity
No. 1 2 3 4 5 6 7 8

Preparation of Detail Cost


1
Estimate for Technical sanction.

Preparation, Quality Assurance


2 and submission of Draft Tender
Documents for vetting by Client.
3 Preparation, Quality Assurance
and Submission of Final Tender
Documents.

LEGEND:

Full time Activity Submission


Annexure - H

DETAIL DESIGN AND CONSTRUCTION SUPERVISION OF WATER SUPPLY SYSTEM, GUJRAT

SCHEDULE OF ACTIVITIES
( For work to be done)
SUPERVISION STAGE

MONTHS
Sr.
Activity
No.
Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17

1 Re-mobilization of Consultant at site.

2 Installation of Tube Wells

i Tubewell Electrical works

ii Installation of Pumping Equipment's

3 Rehabilitation of Existing Tubewells

4 Constriction of New OHR

5 Rehabilitation of Existing OHR

6 Raising Mains and Distribution


System
i Main Lines (Part-II)

ii Distribution Tertiary Lines (Part-II)

7 Providing and Fixing of Hypo


Chlorinator
8 NOC from Railway, NHA, Provisional
Highway and District Highway

i) Schedule of activities is for balance works.


ii) The time period is considered for balance works from the date of demobilization of Consultants i.e. August, 2014.

LEGEND:

Full time Activity Part Time Activity

2
Annexure - I

DETAIL DESIGN AND CONSTRUCTION SUPERVISION OF WATER SUPPLY SYSTEM, GUJRAT

SCHEDULE OF ACTIVITIES
( For work to be done)
SUPERVISION STAGE
Sr. MONTHS
Activity
No. Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17

1 Re-mobilization of Consultant at site.

2 Checking site boundaries and setting


out of works

3 Checking construction plans, work


schedule and shop drawings
submitted by contractor

4
Construction supervision

5 Progress monitoring and progress


report

6 Testing of construction materials and


works

7 Quality control including inspection


and tests

8 Final testing and commisioning


9 Review and submission of as-built
drawings and completion report

LEGEND:

Full time Activity Part Time Activity