Professional Documents
Culture Documents
1. Foundation Slab
No. of sheets of mesh = 2
2. Headwalls:
No. of dowels = 24
Length = 9,600 mm = 2 No. x 6m Ø12mm bars
Length of horizontal bars = 10,400 mm = 2 No. x 6m Ø14mm bars
3. Wingwalls h 1,300mm
3.1 Main bars: d
Bar spacing = 150 mm 100mm
No. in one row = 26 3,700mm
Length of bars = 18,200 mm 18,411 18,411 h= 1200*d
18,411 3700
18,200 dact= 148
Total length of main reinforcement = 145,600 mm = 25 No. x 6m Ø16mm bars
4. Costs
1,3m
300mm
● Volume of concrete in headwalls = 2*0,15*1,3*0,2 = 0.078 m 3
3,7m
551971712.xls 10/24/2021 3
1.2 Estimate Shuttering
Area of shuttering:
Concrete surround = 21.32
Wingwalls = 19.24
Headwalls = 0.51
Total area = 41.07 m2
No. of 2,44x1,22m shutter boards = 14
Note: Assume that no shuttering is required for foundation slabs
1m3 mix-
Quantity Unit Cost US$ Transport
Total Unit Cost
Unit Cost US$
B25 Cost to Site US$
Cement No. 7 93 9 2 11 1,023.00
Stone m3 0.72 10 25 60 85 846.58
3
Sand m 0.65 9 17 5 22 197.81
Shutter Boards No. 14 3 2 5 70.00 *Ch
Sub-total 2,137.40
Steel Reinforcement Sum 465.71
Concrete Pipes No. 9 120 15 135 1,215.00
Total cost of materials 3,818.11
551971712.xls 10/24/2021 4
2. Labour
1 x Supervisor
8 x Labourers
Time required: Excavation - 1 day
Concreting - 1 day
Shuttering & Steel fixing - 1 day
Total time= 3 days
Working hours per day = 9 hrs
Labour Costs:
3. Equipment
551971712.xls 10/24/2021 5
5 Concrete Rate
(Concrete only, excluding reinforcement and pipes)
Output Unit Costs US$ Basic Rate $ Mark-up % Total Rate US$
1 Materials 13.174 m3 2,137.40 162.24 20% 194.69
2 Labour 13.174 m3 99.90 7.58 15% 8.72
3 Equipment 13.174 m3 1,170.00 88.81 20% 106.57
4 Tools & Accessories 13.174 m3 54.00 4.10 25% 5.12 Rate in MT at 35Mt to US$
Total Concrete Rate= 13.174 m3 3,461.30 262.73 20% 315.10 11,028.57
262.73 (includes risk)
Output Unit Costs US$ Basic Rate $ Mark-up % Total Rate US$
1 Materials 6.900 m 3,818.11 553.35 20% 664.02
2 Labour 6.900 m 99.90 14.48 15% 16.65
3 Equipment 6.900 m 1,170.00 169.57 20% 203.48
4 Tools & Accessories 6.900 m 54.00 7.83 25% 9.78 Rate in MT at 35Mt to US$
Total Concrete Rate= 6.900 m 3,461.30 745.22 20% 893.93 31,287.55
501.64 (includes risk)
551971712.xls 10/24/2021 6
TENDER RATES CALCULATIONS
A. BOQ ITEM BUILD-UP
Load, Haul, Dump, Water & Compact 150mm Base 1 layer, stabilised with 4% cement, to 98% Mod
AASHTO
Width of road = 10 m
Layer thickness = 75 mm w=6
Road side slope s (1:s) = 3
Working hours per day = 9.5 hrs Slope 1: s t = 0,15
551971712.xls 10/24/2021 7
1.2 Labour
1x Assistant at gravel pit
1x Dumping controller
Note: Operator costs included in equipment rates
1.3 Costs:
Resource Item No. Input Unit Rate $/unit Cost $
Loader 1 9.5 hr 156.00 1,482.00
Tippers 2 19 hr 1120.00 21,280.00
1.1 Total eqpt. Cost = 22,762.00
1.2 Labour 2 19 hr 4 76.00
Note: Fuel included in equipment rate
2 Spreading, mixing and compaction
2.1 Equipment
Compaction unit for a day's production is as listed in table below: grader, tractor, disc harrow, vibro roller
2.2 Labour
1x Gang leader
6x labourers to pick roots, spread cement bags etc.
2.3 Costs:
Resource Item No. Input Unit Rate $/unit Cost $ 359.95
Grader 2 19 hr 360.00 6,840.00
Tractor 1 0 hr 25.00 -
Dozer 1 9.5 day 345.00 3,277.50
Vibro Roller 1 9.5 hr 156.00 1,482.00
2.1 Total eqpt. Cost = 11,599.50
Gang leader 1 9.5 hr 4 38.00
Labour 6 57 hr 3.5 199.50
2.2 Total labour cost = 237.50
551971712.xls 10/24/2021 8
Note: Peso de saibro= A*1950
3 Watering Peso/massa da Agua= w*A*1950 kg
3.1 Equipment Vol de água= Peso/Densidade de água (m3) *1000 litres = w*A*1950 kg
Wastage factor, β 5%
Compacted volume of gravel, A = 161 m3
Density of compacted layer = 1950 kg/m3
OMC, w = 9%
Volume of water required in section, V = A*w*Density of soil = 28,263 litres
Water haul distance, D = 10 km
Average bowser speed, S = 25 km/hr
Travel time,T =2*D*60÷S = 48 min
Loading time, L = 15 min
Watering time, W = 20 min
Cycle time, C = T+L+W = 83 min
Allowable compaction time, E (Due to limitations like heat, cement setting etc.) = 6 hrs
No. of loads in allowable compaction time,h =E*60÷C = 4.34
Say h = 5
Volume of bowser = 10,000 litres
Volume of water delivered by one bowser, I =B*(1-β)*h = 47,500
No. of bowsers, N =V÷I = 0.60
Say N= 1
3.2 Labour
1x Water pump attendant
3.3 Costs:
Resource Item No. Input Unit Rate $/unit Cost $
Water Bowser 1 9.5 hr 190.00 1,805.00
Water pump 1 9.5 hr 40.00 380.00
3.1 Total eqpt. Cost = 2,185.00
3.2 Labour 1 9.5 hr 4 38.00
551971712.xls 10/24/2021 9
4
551971712.xls 10/24/2021 10
PRELIMINARY AND GENERAL COSTS
I TIME RELATED COSTS
US $
1 LABOUR
Basic Rate/Mon %Charge to
No. Total
Rate/Mon incl. Allow. Job
Contract Manager 2000 3,200.00 1 33.00% 1,056.00
Site Agent/Manager 1500 2,400.00 1 100.00% 2,400.00
Foreman 800 1,280.00 1 100.00% 1,280.00
Surveyor 600 960.00 1 50.00% 480.00
Survey Assistants 250 400.00 1 50.00% 200.00
Clerk 200 320.00 1 100.00% 320.00
Mechanic 700 1,120.00 1 100.00% 1,120.00
Watchmen 150 240.00 2 100.00% 480.00
General Hands 60 96.00 20 100.00% 1,920.00
Total per month 29 9,256.00
551971712.xls 10/24/2021 11
Stationery 1.00 25.00 25.00
First Aid Reqirements 1.00 15.00 15.00
Total per month 40.00
2 Accommodation
Rate No. % Charge Cost
Wooden Huts $3,500.00 4 70% $9,800.00
Security Huts $3,500.00 1 70% $2,450.00
TOTAL $12,250.00
3 Transport Costs
Plant Requirement for the Job
Number L-Bed Self drive
Dozer 1 1
Excavator 1 1
Grader 1 1
Front End Loader 1 1
Tipper 2 2
Water Bowser 1 0 1
Pneumatic Roller 1 1
Vibro Roller 1
Tractor 1 1
Mobile Workshop 1 1
551971712.xls 10/24/2021 12
Light Vehicles 1 1
Total Plant 12
Total Trips 7 4
7 Furniture
a Office Number Cost Total
Computers 1 $1,500.00 $1,500.00
Printers 1 $800.00 $800.00
Desks 4 $150.00 $600.00
Chairs 10 $75.00 $750.00
Filing Cabinets 1 $200.00 $200.00
Shelves 1 $100.00 $100.00
Lock up cupboards 1 $100.00 $100.00
Tea Cups and other related items 1 $200.00 $200.00
Kettles 1 $75.00 $75.00
b Residetial
Nil
Total Cost $4,325.00
551971712.xls 10/24/2021 13
**PENDING