Professional Documents
Culture Documents
TENDER DOCUMENT
VOLUME – II
Civil approved methodology, QAP plan, EHS Documents and COVID-19 Manual
Sl. No. of
Description Page No.
No. Pages
Issue Status
Signat
Description Name Designation
ure
Prepared by Sr. Manager
Reviewed by DGM
Approved By GM
Page. 1 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
PURPOSE
The purpose of this methodology is to provide construction sequence, quality assurance and
quality control, safety measures adopted in all construction works.
REFERENCES:
RESPONSIBILITIES:
CONTENTS
Page. 2 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
SL NO. ITEMS PG.NO
Page. 3 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
SETTING OUT:
Prior to use, ensure that all survey equipment have valid calibration certificates.
Page. 4 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Establish TBM at site, either from a PBM taken by the land survey team with respect to
road or any permanent structure using auto level and staff.
Ensure that benchmark shall remain undisturbed till the completion of project.
Construct masonry pillars for the established benchmarks with embedded steel plates at
top. Plaster and finish the top surface neatly.
Drive 20 mm dia. rebar's to at least 1.50 m depth all around the pillars and barricade the
pillars to protect the pillars from displacement.
Measure existing site boundary and send it for preparation of setting out plan.
Plot detail survey plan showing site boundary, all reference points / pillar locations in
Auto-cad.
then give a setting out plan by incorporating the above with a baseline and diagonal
measurements for the fixing two corners of the structure.
Establish baseline by fixing two corner and closed traverses as per setting out plan with
the help of theodolite.
Page. 5 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
1. WORK PROCEDURE
Page. 6 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
pile will be worked out, tabulated, and submitted to the Engineer for review and
approval before commencement of piling. Pile point locations and elevations
shall be checked & record jointly. Two offsets will be positioned at suitable.
distances say at 2 to 3 m. points. R, L 's shall be marked near pile location on
rigid structure.
1.2 Barricading
The working area shall be properly barricaded as per the traffic diversion plan.
The barricading boards shall be properly anchored into the ground as per
approved drawing and solar reflectors shall be provided on barricaded boards.
Proper lighting arrangements shall be providing the inside the working area to
work in the night shift. Security arrangements shall be made to prevent.
unauthorized entry of men and machineries inside the working premise.
Page. 7 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
The loose soil produced by boring, mixes with water and comes up and is stored in the wash vat,
where the soil gets precipitated and the water is again usable. Taking out the DMC rods and
Chisel and Insertion of the reinforcement cage
After the boring is complete up to the desired depth, the DMC rods are removed one by one
using the DMC fork and the chisel is also removed. Then the steel reinforcement cage is inserted
and welded wherever there are joints.
2. LOWERING OF CAGE
Page. 8 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
The reinforcement shall be made into cages sufficiently rigid to withstand handling without
damage. In case the reinforcement case is made up of more than one segment, the same shall be
assembled by providing necessary laps or, preferably, by welding.
Stirrups to the main bars shall be tack welded.
Care shall be taken to ensure that the reinforcement bars do not move together before the cage is
lowered down the hole.
Proper cover and central placement of the reinforcement shall be ensuring by use of suitable
concrete spacers or rollers, case specifically for the purpose.
The reinforcement cage shall be shifted near to the pile bore, lifted using the piling rig
with a set of double sling ropes and lowered into the pile shaft casing till the required
depth of bore hole.
Cranes shall also be used to lifting the reinforcement cage. The details of the crane will
be submitted after 3rd party inspection and while submission of Safety methodology. The
approximate weight of the reinforcement cage to be lifted shall be 1.75MT and that of
caging is 0.05MT.
D- Shackles and slings of 25MT, l0MT, 5MT and 2MT capacity shall be used for lifting
the rebar cages and other equipment’s. The selection of D shackles and slings shall be as
per load lifted.
Only circular concrete cover blocks of 150mm diameter (having the same strength of pile
concrete) threaded onto the helix shall be used for encoring the cover.
All main longitudinal bars shall be welded at lapping zones using electrodes as specified.
The last circle of helical burs shall be welded to main longitudinal bars.
The projected length of the longitudinal bar beyond the cut off level of pile shall be 60
times bar diameter, or as specified in the GFC drawings /approved BBS.
3. CONCRETING:
The approved concrete mix having minimum cement content of 400kg/ cum & max. size
aggregate of 20mm shall be used for pile concreting.
The concrete shall be checked for consistency (slump 150-175mm) & cubes casted as per
the requirement.
The specific gravity of drilling mud at the base of bore shall be maintained as specified in
the corresponding tables given above before placing of concrete.
The hopper and attached tremie pipes shall be wetted with water before commencing the
concrete works.
The first charge of concrete shall be placed in the hopper over a stopper plate kept at the
neck of hopper.
By releasing the stopper plate, concrete will be discharged suddenly from the hopper into
the pipes in one continuous operation to ensure the flushing action to minimize mixing of
water or drilling mud and concrete.
Page. 9 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Tremie pipe shall be removed during pouring of concrete ensuring that tremie bottom is
embedded into the previously placed concrete for minimum depth of 2 meter below the
free rising surface of the concrete as a precaution against accidental withdrawal.
The rate of concrete pouring shall not be less than 6m (length of pile)/hour to ensure
compaction by hydraulic static head.
A record as enclosed in Annexure 4 shall be maintained for tremie pipes which comprises
of tremie length during lowering tremie pipe removed at stages and sounding of concrete.
The top of concrete in a pile shall be brought to 1.0 meter above the cut-off level to
remove all balance and week concrete to ensure good concrete at cut off level.
The casting height of concrete above cutoff level shall be agreed with GC before
commencing the concrete work and after some piles installation the concrete above cut
off level shall be jointly inspected and the depth of concrete above cutoff level shall be
mutually agreed.
The placing of concrete shall be done within 6 hours after completion of pile boring. If it
is delayed due to some unforeseen circumstances, the already laid concrete shall be
removed from the pile bore using cleaning bucket.
Tremie pipes and reinforcement cage shall be lifted from the pile bore and cleaned. Then
the cleaning bucket shall be used for removing the old concrete. After thorough cleaning
again the cage shall be lowered followed by the casing pipe and the concreting shall be
laid.
While concreting the pile, the overflowing drilling mud from pile shall be pumped out to
a watertight container / tank.
After completing the pile concrete, the hopper & the tremie pipes shall be removed and
cleaned properly.
After completion of pile concrete, casing shall be removed immediately or before initial
setting time by using a crane /piling rig.
When a casing is being extracted enough concrete shall be maintained within the bore to
avoid necking of the pile.
Bored muck shall be placed temporarily adjacent to the pile under construction &
subsequently disposed of in an environment friendly manner and as approved by the local
authorities (Pollution control board).
After each pile has been cast any empty bore shall be protected and carefully backfilled
as soon as possible with approved materials.
4. QUALITY ASSURANCE:
Page. 10 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Proper care shall be taken to ensure the correct implementation of the working
procedures described in this method statement.
5. TESTING:
Test cubes shall be made in accordance with IS 516 and all sampling and testing in
accordance with IS 1199 unless specified or instructed otherwise. At least one test shall
be Made for every 10 cum of concrete and not less than one test shall be made for any
one day's Concreting operation. Each test shall consist of 6 no. works test cubes cured
three cubes shall be tested at 7 days and other three at 28 days.
6. RECORDING OF DATA:
A competent supervisor shall be present to record the necessary information during the
installation of piles. The data to be recorded shall include:
The dimensions of the piles, including the reinforcement detail and the mark of the pile.
The type of boring employed.
The type of soil in which pile is constructed.
The depth bored.
The depth of water table.
When drilling mud is used, the specific gravity of the fresh supply and contaminated mud
in the borehole before concreting is taken up, in case of first few pi1es and subsequently
at suitable interval of piles.
The time taken for concreting.
The cut off level /working level and
The consumption of cement
Any other important observations.
Any deviation from the designed location, alignment of load carrying capacity of any pile shall
be noted and promptly reported to the Engineer-in- charge.
Page. 11 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
EQUIPMENT:
Earth moving machines and equipment, Survey instruments, Measuring tape, spade, crowbar,
thread, lime powder etc.,
CLEARING OF SITE:
The area to be Excavated / filled shall be cleared of fences, plants, logs, stumps, bush,
vegetation, rubbish, etc. If any roots or stumps of trees are met during excavation, they shall also
Page. 12 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
be removed. The material so removed shall be disposed of as directed by the
Architect/Construction Manager.
SURFACE PREPARATION:
All excavations shall be carried out to its minimum dimensions as required for safety and
working facility. Before starting the excavation, it shall be ensured no underground live cables /
pipes / drains are crossing the excavation area. Ensure safe access path to the excavation area
with the help of walkways / ladders etc. Vehicle positioning and stability shall be ensured.
EXCAVATION PROCEDURE:
The Contractor shall carry out the survey of the site before excavation and set properly all lines
with the Total Station Survey and establish proper bench marks, center lines of grids, center
lines of roads, etc.; as indicated in the drawings and as directed by the Engineer. All grid pillars
or control points shall be guarded and checked for any disturbances. Excavation plan with
necessary working space shall be prepared and the same shall be marked with line powder on the
ground. Block level shall be taken at 5m intervals maximum and recorded jointly before taking
up the excavation. Shoring and Strutting shall be provided wherever necessary for protecting the
sides of excavation and also barricades shall be provided around the excavated area for safety.
The face of the excavated earth shall be cut to slope or shored in order to hold the earth. Proper
barricades shall be provided around the excavated area. Rough excavation shall be carried out to
a depth of 150mm above final excavation level. The balance shall be removed with care. Soft
pockets if any found shall be removed even below the final level of excavation and the same
shall be filled as directed by the engineer in-charge.
DEWATERING:
All excavated pits shall be provided with proper dewatering arrangement. Arrangements to be
done so that surface water does not enter the foundation pit and the pit remains dry for
subsequent activities.
Excavated earth to be kept away from the edges of the foundation pits (Approx. 2.00m away
from the top edge) or to be properly stacked at the dump yard. Ensure availability of NOC for the
landowner if the dump yard / land is outside the site premise for unwanted earth/unusable earth.
Page. 13 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Page. 14 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
1. SCOPE:
This document enumerates the plan activities and execution activities for the
construction of Pile cap foundations for Anode Storage building within the EMAL
Projects.
2. APPLICABLE DOCUMENTS:
Page. 15 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
3. CONTROL MEASURES:
Page. 16 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
The surveyor will mark the foundation corners with coordinates and Underground
utilities shall be marked by total station equipment and the same will be subjected
to approval by Client / Consultant.
After approval for the location of foundations and underground utilities marking,
excavation will be commenced with the excavator within the outer limits of
marking for all the foundations. Care will be taken for the pile’s protection against
any damage and existing utilities.
Excavation within 5m radius of underground utilities by mechanical methods shall
be avoided, if not possible excavation shall be carried after approval from
concerned department. Exploration holes shall be done for locating the underground
utilities before mechanical excavation starts.
The excavation works will be carried out as per markings which were duly
approved by Client /Consultant for all the foundations. The exaction depth is
approximately 2.0 mt, so the excavation will be done by step cutting of 1.0 mt
vertical height with 1.0 mt horizontal set back and again 1.0 mt vertical height to
reach ground level for three sides only. 4th side due to space constraint on existing
conveyor side, excavation will be done by slope for available width only. Shoring
will be done, where space is constrained for slopping and stepping.
Once the excavation is completed up to the foundation level, pile head breaking
works will commence.
Marking will be made on each pile periphery at pile cut off level and a cut with
grinder will be made on the marking to prevent excess breaking of concrete below
cut off level. Pile chipping / breaking will be done with air compressor and
pneumatic concrete breaker from top of existing pile until cut off level. Suitable
scaffolding platforms shall be provided for breaking above 1m height.
All the loose concrete debris will be removed with the use of Excavator. Excavator
bucket will be kept at safe location and debris will be loaded into the bucket
manually where the work area is small and critical by means of adjacent services.
Special protection like hard covering for nearby services shall be provided.
The area will be fine leveled manually, and subbase will be compacted with plate
compactor / mini roller to the required degree of compaction. Will ensure 95% field
density.
Required formation levels and Compaction test will be subjected to Client /
Consultant inspection and upon approval will proceed to subsequent activity.
1000-gauge polythene sheet is laid in the foundation area. Blinding concrete will be
laid to a thickness as specified in approved drawing by pump or by suitable
methods.
Inspection will be raised for Blinding concrete for approval.
Concrete protection with bituminous paint shall be applied uniformly as per
Manufacturers recommendation over the blinding surface and will be subjected to
inspection and approval.
Page. 17 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Reinforcement steel will be transported and lowered in position. Fixing of
foundation reinforcement will be carried out as per the approved drawings.
Thereafter, Pedestal vertical reinforcement will be fixed as per the approved
drawings.
Prefabricated Doka shuttering sheets will be shifted and lowered by crane/boom
truck at locations wherever access is possible otherwise conventional shuttering will
be placed with adequate supports. The side shutters will be provided with adequate
supports in order to achieve the required shape and sizes of the foundations after the
concrete pour and shall be as per approved drawings.
Reinforcement and shuttering works are subjected to inspection before proceeding
to concrete works.
Upon approval of reinforcement & shuttering, concrete of required grade will be
transported to site from approved supplier and placed into form work. The concrete
compaction will be ensured with concrete vibrators and needles which will be made
available at site during the concrete pour.
The concrete will be laid up to the required levels and concrete surface will be
finished smooth as required. Concrete pump shall be used for pouring concrete
wherever applicable.
Curing will be commenced immediately after concrete is set and shall be
maintained for 4 days.
After the concrete is completely set, deshuttering will be carried out after a period
as specified in project specifications.
Immediately after deshuttering, if any finishing is required to be done on sides of
foundation, the same will be carried out with information to Client / Consultant. If
required, structural repair material shall be used wherever applicable.
The next day after completion of pile cap concrete, reinforcement steel fixing for
the pedestal works will be commenced as per the drawing.
Placing and fixing of Anchor down bolts will be done. Each anchor bolt will be
aligned and fixed in line and true level as per required coordinates. All the bolts will
be secured rigidly and ensure it will not be disturbed during subsequent concrete
pouring activity.
Shuttering of the pedestals will be fixed in line and level and rigid supports will be
ascertained to contain the concrete in required shape and size. Champers will be
provided on all four edges and on top.
Champers of 35 x 35 mm, inclined length 50mm will be fixed in vertical and
horizontal corners for the exposed concrete only, i.e. for pedestal only. If chambers
not provided before concreting, it shall be done by use of grinders on post
concreting.
Page. 18 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Inspection for reinforcement, anchor bolts and form work will be raised for
approval.
Upon approval concrete of required grade will be cast into pedestals and will ensure
proper compaction by concrete vibration needles. Concrete will be done with crane
bucket to prevent damage or disturbance to anchor bolts.
Curing works will commence after concrete is set and will continue for 4 days.
Form work will be stripped off after its stipulated time as per project specification.
Application of Concrete protection material (Bitumen paint) over the entire
concrete surface area of foundations and pedestals up to finished floor level is done
in accordance with the Manufacturer’s recommendation.
After the curing period, backfilling with the excavated soil will be laid in layers of
250mm loose with use of mechanical/manual methods, leveling and watering until
saturation and compacted to 200 mm thick to achieve 95% of proctor density. The
cycle will be repeated until required top levels are reached.
3.5 Deviation
The permissible Deviation Level/Tolerances for Finished concrete works shall be as
per Site Requirements / specifications / drawings.
4. QUALITY CONTROL:
The concrete work activities will be controlled using an Inspection Test Plan (ITP). The
ITP will be approved by the Consultants / Client and will include:
Hold points for Consultant / Client Inspections.
Frequency and Standard of Testing.
Test Points for Independent Testing Agencies.
Details of retained and non-retained documents.
Page. 19 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Shovels/spades
Scrapers & Pickaxe
Jack hammer (Electric & pneumatic)
6.3 P.P.E.
Hand gloves (Rubber, Cotton & Leather) & Safety goggles
Safety boots (Boots with steel toe)
Hard Hats
Coverall/uniform
Face shield
Ear plugs
6.4 Miscellaneous
Survey equipment - Auto Level and Total Station
Small tools (Trimming & Leveling works)
Fire Extinguishers
Banks man / Riggers
6. SAFETY
Site safety induction will be carried out as per EMAL EHS Rules and policy.
All operative will receive a method statement briefing and this will be maintained
as a site record.
All operative will maintain all the safety requirements for the project throughout the
work duration. This will include the wearing of Safety hats, High Visibility vests &
Safety boots and others as required for the job.
Trained and Skilled Operators shall be employed for operating heavy machineries
like excavator, dumpers, cranes, etc.
During Excavation process, a Signal Man shall be deployed in the surrounding area
of operating machineries to control the unauthorized access in the radius of
Machine Operating Zone.
Scaffolding platforms and Ladder will be used as a safe means for access and
egress.
Open excavations shall be barricaded by cordoned safety tape to secure the
excavating area and sufficient lighting arrangement shall be done in night to prevent
accidents and ensure safety.
The Excavation area will be inspected through the Site safety personnel deputed at
site.
7. DUST CONTROL
Page. 20 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Water Sprinkling shall be made to prevent flying of Dust and Polluting during the
Excavation activities.
All Labors working in the Vicinity shall be provided with Dust mask as a
precaution against dust pollution.
8. APPENDICES
APPENDIX-A
# I have been briefed of the contents of the above method statement, site safety and
Excavation, Backfill and Compaction and the entire sequence of construction of Pile cap
foundations work requirements. I fully understand all that has been said to me. I have also had
the opportunity to raise any queries relating to the work that is to be carried out.
EMPLOYER
NO. NAME (PRINT) SIGNATURE PAYROLL NO
(PRINT)
Page. 21 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
1
2
Page. 22 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
OBJECTIVE:
To carry out reinforced concrete work regarding quality, quantity, handling, storage of
ingredients, proportioning, batching, mixing, and testing of concrete. METHOD STATEMENT
covers the transportation of concrete mixer to the place of final deposit and placing, curing,
protecting, and finishing of concrete.
REFERENCE:
EQUIPMENTS:
1. Concrete batching plant, Concrete pump, Transit mixers, immersion vibrator needles, mason
tools- spade, mortar pan, Aluminum straight edge, wooden float, steel float, Auto level, etc.…
CONCRETE PREPARATION:
Page. 23 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Ensure all the materials are as per requirement / specification.
All reinforced concrete work shall be Design Mix Concrete as defined in IS: 456.Mix
proportioning shall be carried out in accordance with IS 10262, submitted and get approved by
the consultants.
Proportions of cement, coarse aggregate and fine aggregates shall be maintained during
subsequent concrete batching by means of weigh batchers. The different sizes of aggregates
shall be stacked at different stockpiles.
The concrete shall be produced only by weigh batching. The entire content of the drum shall be
discharged in one operation before the raw materials for the succeeding batches are fed into the
drum.
The accuracy of the weigh batcher shall be periodically checked. Each batch shall be mixed until
the concrete is uniform in color.
No concrete shall be placed on a water covered surface. Before leaving unattended, the work
shall be covered with tarpaulins immediately after the concrete has been placed and compacted
to safeguard against damages caused by rain.
PLACEMENT OF CONCRETE:
CURING:
Concrete surface continuously wet for a minimum period of 07 days from the date of placing the
concrete. The curing is preferred continuously by saturated coverings of sacks, canvas, hessian,
or other absorbent materials. No concrete shall be placed on a water covered surface. Before
leaving unattended, the work shall be covered with tarpaulins immediately after the concrete has
been placed and compacted to safeguard against damages caused by rain.
Page. 24 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Sl. No.
Procedure
Responsibility
Check By
Record
2 PLACEMENTS OF CONCRETE
2.1 Before placement of concrete the surface to be cleaned properly and leveled.
Site Engineer
QC Engineer
QAP/03
2.2 The leveled surface to be treated with Ant termite application as per the requirement.
Site Engineer
QC Engineer
QAP/03
2.3 Before the concrete is placed in position the insides of the formwork shall be inspected to see
that they have been cleaned and oiled. All embedment’s such to be cast in the concrete as indicated
in the drawings shall be correctly positioned and securely held in the forms to prevent
displacement during deposition and vibration of concrete.
Site Engineer
QC Engineer
QAP/03
All works shall be inspected and approved prior to the placement of the concrete.
Site Engineer
QC Engineer
QAP/03
All the equipment’s used for transport the concrete such as transit mixers, wheel
borrows shall be watertight. All equipment used for mixing, transportation and placing
shall be maintained in clean condition. All pans, buckets, hoppers, chutes, pipelines,
and other equipment shall be thoroughly cleaned after each period of placement.
Site Engineer
QAP/03
The concrete shall be compacted during placing with wooden rammers/equipment until
the concrete has been compacted properly.
Site Engineer
3 CURING
Curing shall be done by keeping the QC QC Engineer QF/CPC/01
Page. 25 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
fresh concrete surface continuously Engineer
wet for a minimum period of 07 days
from the date of placing the concrete.
The curing is preferred continuously by
saturated coverings of sacks, canvas,
hessian, or other absorbent materials.
Page. 26 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
OBJECTIVE:
Page. 27 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
To carry out reinforced concrete work in regard to quality, quantity, handling, storage of
ingredients, proportioning, batching, mixing and testing of concrete and also requirements in
regard to the quality, storage, cutting, bending and fixing of reinforcement in position. This also
covers the transportation of concrete mixer to the place of final deposit and placing, curing,
protecting and finishing of concrete.
REFERENCE:
EQUIPMENTS:
1. Concrete batching plant, Concrete pump, Transit mixers, immersion vibrator needles, mason
tools- spade, mortar pan, Aluminum straight edge, wooden float, steel float, Auto level, etc.…
CONCRETE PREPARATION:
Standard deviation of each grade of concrete shall be determined separately. The total
number of test results required constituting and acceptable record for calculation of
standard deviation shall be not less than 30.
QC Engineer
QC Engineer
QF/STD/01
Proportions of cement, coarse aggregate and fine aggregates shall be maintained during
subsequent concrete batching by means of weigh batchers. The different sizes of
aggregates shall be stacked at different stockpiles.
QC Engineer
QC Engineer
Page. 28 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
The concrete shall be produced only by weigh batching. The entire content of the drum
shall be discharged in one operation before the raw materials for the succeeding batches
are fed into the drum.
QC Engineer
QC Engineer
The accuracy of the weigh batcher shall be periodically checked. Each batch shall be
mixed until the concrete is uniform in color.
QC Engineer
QC Engineer
No concrete shall be placed on a water covered surface. Before leaving unattended, the work
shall be covered with tarpaulins immediately after the concrete has been placed and compacted
to safeguard against damages caused by rain.
Site Engineer
QC Engineer
All works shall be inspected and approved prior to the placement of the concrete.
Site Engineer
Sl. No.
Procedure
Responsibility
Check By
Record
2.1 Before the concrete is placed in position the insides of the formwork shall be inspected to see
that they have been cleaned and oiled. All embedment’s such to be cast in the concrete as
indicated in the drawings shall be correctly positioned and securely held in the forms to prevent
displacement during deposition and vibration of concrete. Slots, openings, holes, pockets, dowels
etc. shall be provided as indicated in the drawings. Reinforcements and other items to be cast in
concrete shall have clean surfaces that will not impair bond.
Site Engineer
QC Engineer
QAP/04
2.2 QAP/04
QC Engineer
QAP/04
All the equipment used for transporting the concrete such as transit mixers, wheel borrows shall
be watertight. All equipment used for mixing, transportation and placing shall be maintained in
Page. 29 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
clean condition. All pans, buckets, hoppers, chutes, pipelines, and other equipment shall be
thoroughly cleaned after each period of placement.
Site Engineer
Site Engineer
QAP/04
The concrete shall be compacted during placing with vibrating equipment until the concrete has
been consolidated to the maximum practicable density.
The use of vibrators shall be consistent with the concrete mix and caution is to be exercised not
to over vibrate the concrete to the point that segregation results. The immersion vibrator shall
penetrate the layer being placed and also penetrate the layer below while the under layer is still
plastic to ensure good bond and homogeneity between the two layers and prevent the formation
of cold joints. Immersion vibrators shall not be allowed to meet the reinforcement steel, forms,
and finished surfaces.
Site Engineer
Site Engineer
All laitance and loose stones shall be removed by hacking, wire brushing and surface wash. Just
before concreting the cleaned surface shall receive a thin layer of cement grout of specified
proportion. The new concrete shall be well worked against the prepared face before the grout
sets. Special care should be taken so that no segregation takes place along the joint plane.
Site Engineer
Site Engineer
QAP/04
5. FINISHING OF CONCRETE:
Floating or toweling of the finish shall be permitted only after all surface water has evaporated.
Finished surfaces shall present a uniform and smooth appearance.
Site Engineer
QC Engineer
QAP/04
Page. 30 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
The sample from fresh concrete shall be taken as per IS 1199, cubes shall be made, cured and
tested at 28 days in accordance with IS 516. The minimum frequency of sampling shall be in
accordance with the clause 15.2.2 of IS 456 2000. Slump test shall be carried out as required and
invariably from the same batch of concrete from which the test cubes are made. Slump test shall
be done immediately after sampling. Concrete of each grade shall be assessed separately.
QC Engineer
QC Engineer
QAP/04
7. CURING:
The curing of horizontal surface exposed to drying winds however shall begin immediately after
the concrete has hardened. For curing of concrete in pavements, floors, flat roofs or other level
surfaces, the ponding method of curing is preferred. For curing of vertical structural members
continuously saturated coverings of sacks, canvas, hessian, or other absorbent materials.
QC Engineer
QC Engineer
QAP/04
Curing shall be done by keeping the fresh concrete surface continuously wet for a minimum
period of 14 days from the date of placing the concrete.
Page. 31 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
OBJECTIVE:
The Formwork shall consist of shores, bracings, side of beams and columns, bottom of slabs, etc.
including ties, anchors, hangars, inserts, etc. complete which shall be properly designed and
planned for the works.
REFERENCE:
Page. 32 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
1.Inspection and Test Plan, Technical specification, BOQ, Relevant IS codes.
2. Client / Consultant Approved Drawings
1.DESIGN OF FORMWORK
1.1 The drawings and calculations for the design of the formwork for Footing, Column,
Slab, Tie beams, Plinth beams shall be submitted and get approval by the Client / Consultant.
Formwork Engineer
Site Engineer
1.2 The design shall take in to account all the loads vertical as well as lateral loads that
the forms will be carrying including live load and vibration loads.
Formwork Engineer
Site Engineer
1.3 Depending upon the height of the staging suitable vertical and horizontal cross
bracings shall be provided.
Site Engineer
Site Engineer
1.4 The concrete work of floor, beam, slab including roof slab shall be permitted after
inspection staging work.
Site Engineer
2 TYPE OF FORMWORK
Formwork may be of timber, plywood or metal. For special finishes the formwork may be lined
with smooth faced plywood, steel sheets, oil tempered hard board, etc. Sliding forms and slip
forms may be used. Approved formwork system shall be used.
Formwork Engineer
Site Engineer
3 FORMWORK REQUIREMENTS
Page. 33 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
3.1.1 Formwork system shall confirm to the shapes, lines, grades, levels and dimensions.
Ample studs, wailer braces, ties, straps, shores, etc. shall be used to hold the forms in proper
position. Form shall be strong enough to the use of immersion vibrator. The shuttering shall be
close boarded. Joints shall be sufficiently tight to prevent loss of water and fine material from
concrete.
Site Engineer
QA/QC Engineer
Sl. No.
Procedure
Responsibility
Check By
Record
3.1.2 Inside faces of forms for concrete surface, which are to be rubbed finished shall be
planned to remove irregularities or unevenness in the face. Formwork with lining will be
permitted.
Site Engineer
Site Engineer
a) 3.1.3 All formwork shall be maintained in a good condition with respect to shape,
strength, rigidity, water tightness, smoothness, and cleanliness of surfaces.
Formwork Engineer
Site Engineer
b) 3.1.4 Form work during any stage of construction showing signs of distortion or
disturbed to such a degree that the intended concrete work will not conform to the exact
contours indicated on the drawings shall be re-positioned and strengthened.
Formwork Engineer
QA/QC Engineer
3.1.5 Foam shall be provided at starters and 2nd lift of shuttering to avoid slurry leakage.
Site Engineer
Site Engineer
3.1.6 Formwork scheme & shuttering design to be attached with the method statement
(column, foundation, beams, wall & slab separately)
Formwork Engineer
Site Engineer
Page. 34 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Formwork Engineer
Site Engineer
3.1.9 The scaffolding, working platform and access shall be ensured as per JSA.
Site Engineer
Site Engineer
3.2.1 The reinforcement of Foundation, beams, columns, and walls shall be checked
including cover prior to placing the formwork from the Client/QC Engineer.
Site Engineer
Site Engineer
3.2.3 The tightening of tie rods & props shall be checked before concreting.
Site Engineer
Site Engineer
3.2.4 The formwork of slab shall be checked for line, level & dimension before placing
the reinforcement steel form the Client/QC Engineer.
Site Engineer
Site Engineer
1) 3.2.5 The rectification of shuttering board quality shall be checked and allowed by the
Construction Manager.
Site Engineer
Site Engineer
3.2.6 The top level of the concrete shall be marked on the shutters to ensure the uniform
level of the concrete.
Site Engineer
Site Engineer
Sl. No.
Procedure
Page. 35 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Responsibility
Check By
Record
4.1 Shuttering shall be braced, strutted, propped and so supported that it shall not deform
underweight and pressure of the concrete and also due the movement of men and other materials.
Site Engineer
Site Engineer
4.2 The shuttering for beams and slabs shall be so erected that the shuttering on the sides of the
beams and under the soffit of slab can be removed without disturbing the beam bottoms.
Site Engineer
Site Engineer
4.3 Re-propping of the beam shall not be done except when the props must be reinstalled to take
care of construction loads anticipated being in excess of the design load. Vertical props shall be
supported on wedges or other measures shall be taken whereby the props can be gently lowered
vertically while striking the shuttering.
Site Engineer
Site Engineer
5. FORM OIL
5.1 Form oil used as mould releasing agent to be used which shall not adversely affect the
concrete.
Site Engineer
Site Engineer
5.2
Care shall be taken that oil or such similar material is kept out of contact with the reinforcement.
Before treatment with oil, forms shall be thoroughly cleaned of dried splatter of concrete from
placement of previous lift.
Site Engineer
6
REUSE OF FORMS
6.1
Before reuse all forms shall be thoroughly scraped, cleaned, nails removed, holes that may leak
suitably plugged and joints examined and when necessary repaired and the inside retreated to
prevent adhesion to the satisfaction.
Page. 36 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Site Engineer
Site Engineer
7
REMOVAL OF FORMS
7.1
In normal circumstances where the ambient temperature does not fall below 15°C and where
Ordinary Portland Cement is used and adequate curing is done, the stripping time is to be
followed as specified in IS: 456-2000 i.e.
a) Vertical formwork to column, walls, beams – 16 to 24 hours.
b) Soffit to formwork to slabs (Props to be re fixed immediately after removal of formwork). - 3
days
c) Soffit formwork to beams (Props to be re fixed immediately after removal of formwork). - 7
days
d) Props to slab:
1) Spanning up to 4.5 m - 7 days
2)Spanning over 4.5m - 14days c) Props to beams and arches:
1) Spanning up to 6m - 14 days
2) Spanning over 6 m - 21 days
Site Engineer
Site Engineer
QF/CPC/01
7.2
Striking shall be done slowly with utmost care to avoid damage to corner and projections and
without shock or vibration by gently easing the wedges. If after removing the formwork, if it is
found that formwork has been embedded in the concrete, it shall be removed and made good as
specified earlier.
Site Engineer
Site Engineer
QF/CPC/01
7.3
No Concrete structure shall be loaded until the concrete is at least 21 days old and only then with
the approval of Client.
Site Engineer
Site Engineer
Site Engineer
Page. 37 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Page. 38 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Page. 39 Construction
Medothodology
ENGINEERING PROJECTS (INDIA) LIMITED
Page. 40 Construction
Medothodology
1
QUALITY ASSURANCE:- All those planned and systematic actions necessary to provide Confidence that an item or facility
will perform satisfactorily in service
QUALITY CONTROL - Those quality assurance actions that provide a means to control and measure against established
requirements the characteristics of an item, process, or
History of Revisions
Revision Revision Chapter / clause
No. Issue date no. & test affected Reason for revision
2
Note: These frequencies are indicative. In case of intermediate deviations or repairs, immediate calibration shall be undertaken
3
4
Quality
Assurance Plan
5
1.0 Engineering Projects (India) Ltd., (EPI) has developed its own quality system to meet required quality standard
and time schedule. In order to adhere to quality standards at every stage of construction activities, QUALITY
ASSURANCE PLAN is being introduced at site to ensure quality product
2.0 Quality Assurance plan consists of all the planned and systematic actions to be undertaken by EPI involved in
execution and acceptance of the works as per the contract. The plan shall define the operations to be performed, the
systematic and sequential progression of operations, the persons responsible for each activity and the measures
employed to assure the specific quality requirement. Thus, it is imperative to ensure that product and services are
inspected, checked and approved at all stages from commencement of work including receipt of material to its
completion in so far as utilization.
a) Pre-construction phase
b) During construction phase 1
c) Post Construction phase
During this phase various activities shall be undertaken and system shall be put in place and implemented in order to
ensure that:
a) All activities, at all locations begin as planned in time.
b) The support system is efficient enough to sustain the quality and progress of work as planned.
c) Quality and progress at all times during construction phase remain unaffected and unhindered.
6
3.1.1. MATERIAL:
It will be ensured that all materials going into the system have been inspected & material test certificates for each of the
material (MTC) (wherever applicable) is available. The untested materials are properly identified with a tag of 'material
under inspection' and rejected maternal shall be disposed.
In order to craft ‘out day to day testing of incoming materials, field laboratory shall be set up with calibrated instruments.
Lab assistant having practical experience and quality engineer having minimum diploma in civil engineering will operate
the Lab and they will report to lab in charge.
Utmost care shall be taken that necessary plant and equipment’s are well maintained and in working Condition prior to
being put into the use. Weigh batcher etc. shall be kept calibrated during commissioning and before operation. Well-
trained staff will control the operation and maintenance of all plant and machinery.
This is the most critical phase of quality control. This is ensured by allotting responsibilities to concerned engineers with
commensurate authority and supervisors with commensurate authority at execution and closely monitored by execution
in-charge and QA/QC Engineer to ensure a Total quality product at all times. This can be achieved as per specification
given by client.
Special products and works involving specialized agencies will be controlled by execution engineers and QA/QC Engineer
as per stipulated quality criteria.
7
After the process is completed, thorough inspection and testing shall be carried out to ensure that finished product is
conforming to specified standards. Required quality records shall be documented in prescribed documents to demonstrate
the achievements of specified quality and effectiveness of quality system.
A separate set of forms with detailed instructions are laid down for facilitating the audit of the quality assurance by an
independent unit of Regional /Corporate office at every 6 months periodical intervals.
4.0 SAFETY:
All quality measures relevant for the activity will be put in place to ensure that quality work is performed under the
supervision of the work leader. Training & daily pep talks on quality to all workmen will be conducted before start of the
activity.
8
Details of all the warranty/Guarantee documents of various work as applicable shall be recorded mentioning start of
warranty/guarantee period and the duration for which warrantee/guarantee is being given. Signature of the concerned
MSME / Consultants official with date shall be obtained on the hand over documents. One copy of the record of handover
copy shall be handed over to MSME and one copy shall be retained.
9
10
The following materials of construction shall be inspected, tested, and results documented and/or verified by agency
personnel in accordance with the following charts and Testing Frequency
SR IS
Internal / External Specification Level of
. Parameters reference Acceptance Norms
Laboratory test requirements Control
NO standard
11
1 Mark on steel
Tested for 3 no
TOR marking should be rolled on every
a) Tor steel On site Visual Inspection of bars
meter length
2 Pitch of twist of bar Ext Lab 8 to 12 times of Test certificate
nominal
3 Colour On site Steel gray Visual inspection
4 Weight per meter On site Theoretical weight Per lot
length
1. 6mm dia. Bar 0.22 kg/m
Practically actual
2. 8mm dia. Bar 0.39 kg/3
weight should not
3. 10mm dia. Bar 0.62 kg/3
vary more than 5%
4. 12mm dia. Bar 0.89 kg/3
5. 16mm dia. Bar 1.58 kg/3
6. 20mm dia. Bar 2.47 kg/3
12
Internal /
Sr. External IS reference standard Level of
Parameters Specified requirements
No. Laboratory Acceptance Norms control
test
13
14
16
M S Rolling Shutter
SR.N Paramet Internal I External Specified Level
O ers Laboratory test requirements IS ref. standard of
Acceptance Norms control
1 Type of the shutter Pull and push type 100%
2 Gauge of bottom lock Plate and Should be as per Dimn inspection- 100%
locking arrangement purchase order Vernier caliper &
3 Type of section used for laths with 16 / 18 120 gauge or Dims inspection - 100 %
gauge should be as per Vernier caliper &
purchase order Gauge
4 Check shutter laths in 30 cm. length 4 to 4 No. or as per Dimn inspection 100%
drawing
5 Top cover in the piece with center ally In one piece of 20 / 22 / Visual inspect= 100%
supported plate and its gauge 24
6 Diameter of ball bearing and spring Check no. and size as Dimensional inspection 100%
with their No. per order
7 M.S. pipe shaft diameter Generally 40 mm of 14 Dimensional inspection 100%
gauge or as per order
8 Bracket plates and guide rail As per Order Visual inspection 10C%
17
Aluminum Window
3 Section / accessories used for mullion tracks as mentioned in drawings Checking 100%
shutters interlocking
4 Fixing work Should be proper with Checking
Screws
5 Check for necessary Position and rubber / It should be located as per Checking 100%
P.V.C. Packing for glass drawing
18
9 Scratches I tend / cracks(if any ) Free from all detects Visual inspection 100%
10 Propert fixing in wall opening Side gap should not be Visual inspection 100%
there (if any . filled with
gap filler )
11 Provision of drain holes in window bottom Should be provided as per Visual inspection 100%
channel. drawings
19
20
GLAZED TILES
SR.NO Parameters Internal I Specified IS reference Level of
External requirements standardAcceptance control
Laboratory Norms
test
show no deterioration
21
Brand Steel Grey, Egyptian Blue, Cadbury Brown, Rolite Brown, Coffee Brown.
22
Water
23
ACC BLOCK
SR.No Parameters Internal /External Specified requirements IS reference Acceptance Level of control
Laboratory test standard Norms
24
Height+/-3mn IS-2185
part 3 Fig.3
25
26
2. Routine test: It will be carried out on a working pile/pile group to check capability of pile to take the working load
assigned to it without exceeding permissible limit, detection of any unusual performance and workmanship. Number of
test shall be 0.5% of the total number of piles subject to minimum one test for each type of loading (that is vertical,
lateral, pullout) for each diameter of pile and rated capacity of pile.
27
v) For pile test on a group of piles, caps shall be provided such that the requirement condition of actual use are full
filled.
vi) Deflection shall be measured preferably at the pile top. Datum bars should rest on firm ground.
a). Preparation of pile head: For carrying out the test pile head shall be chipped off to natural horizontal plane till
sound concrete is met. The projecting reinforcement shall be cut off or bent suitably and the top finished smooth &
made level with cement plaster. A bearing plate with a mark at the center shall be placed on the head of the piles for
the jacks to rest. Finished pile head level will be measured prior to and after the load test by suitable survey instrument.
b) Application of load: The test shall be carried out by applying a series of vertical downward incremental load each
increment being of about 20% of safe load on the pile.
c) Reaction: The reaction shall be obtained from kentledge placed on a platform supported clear of the test pile. The
center of gravity of the kentledge should coincide the axis of the piles and the load applied by the jack should be coaxial
with the pile.
The reaction for the test should be 25% more than the final test load proposed to the applied.
d) Settlement : Settlement shall be recorded with minimum four dial gauges of 0.01 mm sensitivity for both single
pile & group. The dial gauge shall be each positioned symmetrically at equal distance around the piles and held by
datum bars resting on immovable supports at a distance of 3D (subject to minimum of 2.0 meter) from the edge of
the piles, where D is the diameter of the piles.
28
e) The safe vertical load of single pile for the initial test shall be least of the following:
1. For piles upto and including 600mm diameter
i) 2/3 of the final load at which the total displacement attains a value of 12mm
ii) 50% of the final load at which the total displacement equals 7.5% of bulb diameter
F) Routine test shall be carried for a test load of at least 1.5 times the working load :
The maximum settlement at the test load been not greater than 12mm for piles diameter upto and including 600mm
and 18mm or 2% of the pile diameter whichever is less for piles of diameter more than 600mm.
The safe vertical load on group of piles for initial test shall be least of the following:
i) Final load at which the total displacement attains value of 25mm.
ii) 2/3 of the final load at which the total displacement attains value of 40mm.
iii) Routine test of group of piles shall be carried for a test load of atleast equal to the working load :
The maximum settlement of the test loading in position being not exceeding 25mm.
29
3. Vertical load in group of piles shall be continue till one of the following takes place:
a) Incase of initial load test:
i) Applied load reaches 2.5 times the safe estimated load or
ii) Maximum settlement of piles exceed a value of 40mm
b) Incase of routine load test:
i) Applied load reaches the working load or
ii) Maximum settlement of pile exceed a value of 25mm
.
B) Lateral load test on piles:
i) The test will be carried out by introducing a hydraulic jack with gauge between two piles or pile groups and the full
load imposed by jack shall be taken in as the lateral resistance of each pile of group.
The loading shall be applied in increments of about 20% of the estimated safe load.
ii) The next increment shall be applied after the rate of displacement is less than or equal to 0.1mm per 30 minutes
subject to minimum of 30 minutes.
iii) Displacement shall be recorded by using dial gauge of 0.01mm sensitivity. Placed diametrically opposite to the jack.
iv) The safe lateral load on the pile shall be taken as the least of the following:
a) 50% of the final load at which the total displacement increases to 12mm
b) Final load at which the total displacement corresponds to 5mm
v) Routine lateral test shall be carried out for a test load equal to the working load; the maximum deflection of test
loading in position shall not exceed 5 mm.
C) Pullout Test:
30
iv) The initial test shall be carried out up to 2.5 times the estimated safe uplift load or until the load displacement
curve show the downward trend.
v) Routine test shall be carried out to 1½ times the working load or 12mm total displacement for piles diameter up to
and including 600mm and 18mm or maximum of 2% of pile diameter whichever is less for piles of diameter more than
600mm, whichever is earlier.
Recording of data:
The pile test data will be recorded for the test under consideration and recorded in a tabular form along with the
information about the pile. The data will consist of load, displacement and time.
31
Freshness Test:
Smoothing Test:
Open the cement bag from one corner and take some dry cement in the finger and rub, feel the touch. It should
feel silky n smooth while rubbing.
Floating Test:
Lump Test:
32
Take any cement bag at random and test it for presence of lump
Good fresh cement should be in powder form only and lump formation must not be there
Any cement bag with lumps should be rejected Steel
Hardness Test:
Take 1m length of each diameter of bar from different lots by holding both ends of the bar in two hands apply
pressure for bending
Observe the bend portion, bend should be smooth
If steel ins not good then it may break of develop the crack on bending surface, such steel should be rejected
Sand
33
Metal
After unloading of metal, collect small quantity of metal from different parts of the heap
Mix the different parts and take exact 2kg of metal in container
34
35
SIEVE Analysis
SIEVE ANALYASIS
For coarse aggregate
Weight
Cumulative Weight Retained Cumulative % Cumulative %
I.S.SIEVE Retained
(kg) Retained Passing
(KG)
80mm W1 A=W1 A1=A/W*100 %=100-A1
63mm W2 B=A+W2 B1=B/W*100 % =100-B1
40mm W3 C=B+W3 C1=C/W*100 %=100-C1
25mm W4 D=C+W4 D1=D/W*100 %=100-D1
20mm W5 E=D+W5 E1=E/W*100 %=100-D1
16mm W6 F=E+W6 F1=F/W*100 %=100-E1
12.5mm W7 G=F+W7 G1=G/W*100 %=100-G1
10mm W8 H=G+W8 H1=H/W*100 %=100-H1
Total Weight
Total (P)= %=100-W1
(W)=
36
Take the weight of coarse aggregate which is used for sieve analysis (W)
Pass it through I.S. recommended sieves and take the weight of retained aggregate at each sieve as W1,W2,W3….
Respectively
Calculate the cumulative weight retained and note down in reading book by using the procedure as given in table
Calculate the cumulative percentage retained using the procedure as given in table
Calculate the cumulative percentage passing using the procedure as given in table.
Note :- For fine aggregate calculate the fineness modulus by using the formula F.M.=P/100
Procedure :
Precautions:-
Remove the mold after 24 hours & submerge the concrete cube in clean & fresh water
The water in which the cube are submerged shall be replaced every 7days
Cubes shall not be allowed to dry out at any time before testing
37
38
1.0 CEMENT
39
e) After filling the mould place it on the base plate of the vicat apparatus with glass plate, for making it level with
the top of the mould.
f) Then slightly shake the mould to expel the air.
g) Now lower the plunger just near the top surface of the cement paste & realize quickly it to sink into the paste.
h) The above operation should be carried out immediately after filling the mould.
i) Continue the same process with the varying percentage of water in the range, until the desired limit is achieved.
1.1.5 RECORDS :
This test is done for determining the initial and final setting time of cement of given consistency.
a) Prepare a neat cement paste by gauging the cement with 0.85 times the water required to give a paste of
standard consistency. The paste shall be gauged for 3 to 5 minutes.
40
b) Fill the mould completely and smooth off the surface of the paste making it level with the top of the mould.
A) Place the test block under the vacate apparatus. Lower the needle gently until it comes in contact with the
surface of the test block and quickly release, allowing it to penetrate into the test block.
B) In the beginning, the needle will completely pierce the test block. Repeat this procedure until the needle, when
brought in contact with the test block and released as described above, fail to pierce the block beyond 5.0+
0.5mm measured from the bottom of the mould.
C) The period elapsing between the time when water is added to the cement and the time at which the needle fails
to pierce the test block to a point 5.0+ 0.5mm measured from the bottom of the mould shall be the initial
setting time.
a) Replace the initial setting needle of the Vicat apparatus by the final setting needle. The cement shall be
considered as finally set when, upon applying the needle gently to the surface of the test block, the needle
makes an impression thereon, while the attachment fails to do so.
b) The period elapsing between the time when water is added to the cement and the time at which the needle
makes an impression on the surface of test block while the attachment fails to do so shall be the final setting
tile.
c) The result of initial and final setting the shall be reported to the nearest five minutes.
1.2.5 RECORDS :
41
a) Take a flask which shall be filled with kerosene to a point on the stem between the zero and the1-ml mark.
b) The inside of the flask above the level of the liquid shall be dried. The first reading shall be recorded.
c) A Weighed quantity of cement (about 65g for Portland cement ) shall then be introduced in small amounts at
the same temperature as the liquid.
d) Care shall be taken to avoid splashing and to see that the cement does not adhere to the inside of the flask
above the liquid.
e) After all the cement has been introduced, the stopper shall be placed in the flack and the flask rolled in an
inclined position of gently whirled in a horizontal circle, so as to free the cement from air until no further air
bubbles rise to the surface of the liquid.
f) If a proper amount of cement has been added, the level of the liquid will be in its final position at some point of
the upper series of graduations. The final reading shall be taken.
g) The difference between the first and the final readings represents the volume of liquid displaced by the mass of
cement used in the test. The specific gravity shall be calculated as follows to the second place of decimal.
42
1.3.5 RECORDS:
The result should be record in the relevant format.
.
1.4 TEST PROCEDURE FOR DETERMINATION OF FINENESS OF CEMENT BY DRY SIEVING
1.4.1 PURPOSE OF TESTING :
This test is done for determining the fineness of cement in %.
1.4.6 CACULATIONS :
Fineness of the cement F= B X100 (%)
A
1.4.6 RECORDS:
The result should be record in the relevant format.
.
2.0 TEST PROCEDURE FOR DETERMINATION OF DRY DENSITY OF FINE, MEDIUM & COARESE GRAINED
SOILS BY SAND REPLACEMENT METHOD
43
This test is done for determining of the dry density (in g/cm3) of fine, medium & coarse- grained soils by sand
replacement method.
44
c) Then excavate a hole using the hole on the tray as the pattern, to the depth of the layer to be tested up
to a maximum of 250mm.
d) Collect carefully the soil sample from the hole & keep the soil sample in a poly pack for further moisture testing.
e) Remove the metals tray & place the pouring cylinder just over the excavated hole.
f) First Pour a known wt of sand into the cylinder & measure the wt of sand & cylinder before pouring.
g) Then open the shutter & allow to running out the sand into the hole.
h) Close the shutter when no further movement of sand takes place.
i) Continue this process at least twice more.
2.6 TEST PROCEDURE:
a) First weight the soil sample collects from the hole (Ww).
b) Measure the wt sand+ cylinder after pouring.
c) Check the moisture content (Wm) by thermostatically hot air oven.
2.7 CALCULATIONS :
a) Weight of wet soil from the hole (Ww), in gm.
b) Weight of sand (+ cylinder) before pouring (W1), in gm.
c) Weight of sand (+cylinder) after poring (W4), in gm.
d) Weight of sand in hole (Ws) =W1-W4-W2, in gm.
e) Bulk density Bd= (Ww/Ws) X Bds, in kg/m3
f) Water content container No.
g) Weight of soil for water content determination (Wa), in gm.
h) Weight of oven dried soil (Wb), in gm.
i) Water content w = Wa – Wb X 100 (%)
Wa
j) Water content w = 100Bd kg/cum
100+w
2.8 RECORDS:
The result should be record in the relevant format.
3.0 TEST PROCEDURE FOR DETERMINATION OF DRY DENSITY OF SOIL BY CORE CUTTER METHOD
45
a) Cylinder core cutter: Seamless steel tube of 130mm long, 100mm internal dia & 3mm thick with bottom end open
& cutting edge at bottom.
b) Steel dolly: 25mm high, 100mm dia & 10cm thickness
c) Steel rammer: 140mm dia & 75mm height base connected with 900mm length stuff of having dia 25mm, weight
of these whole arrangement approx 9kg.
d) Weight balance accurate to 1 gm.
e) Hot air oven accurate to 10 C / moisture meter to check the moisture content of the sample.
f) One non-absorbent tray.
g) Steel rule for remove sample from the core..
h) Steel straight edge.
46
3.6 CALCULATIONS:
The bulk density is calculated as Bd = Ws-Wc in g/cm3
Vc
The dry density is calculated as Db = 100-Bd in g/cm3
Vc
Where,
Ws= weight of core –cutter + soil in gm.
Wc= weight of empty core-cutter
Vc= volume of empty core
3.7 RECORDS:
The result should be record in the relevant format.
4.0 Procedure for material Testing of concrete Ingredient- aggregate (Coarse & Fine)
4.1 PURPOSE:
This procedure covers the test method for the determination of Physical & Mechanical Properties of fine & coarse of
Normal.
Is 383:1970 Specification for coarse and fine aggregates from natural sources for concrete
IS 460 Part 1 : 1985 Specification for Test Sieves : Part 1- Wire Cloth Test Sieves
IS 460 Part 2 : 1985 Specification for Test Sieves : Part 2 – Perforated Plate test Sieves
IS 460 Part 3 : 1985 Specification for Test Sieves : Part 3 – Methods of Examination of Apertures of
Test Sieves
IS 2386 Part 1 : 1963 Methods of Test for Aggregates for Concrete – Part I : Particle Size and Shape.
47
IS 2386 Part 3 : 1963 Methods of Test for Aggregates for Concrete – Part 3 Specific gravity, density,
voids, absorption and bulking.
IS 2386 Part 4 : 1963 Methods of Test for Aggregates for Concrete – Part 4 Mechanical properties
a) Sieve: Sieves conforming to IS 460 shall be used for determining particle size distribution. Following sieves
shall be taken for determining the grading of coarse and fine aggregates.
b) Balance: A balance accurate to 0.1 % of the weight of the sample to the taken shall be used.
c) Oven: A well ventilated oven thermostatically controlled to maintain temperature of 100 to 1100 C.
d) Basket: A wire basket of not more than 6.3 mm mesh or a perforated container of convenient size, preferably
chromium plated and polished, with wire hangers not thicker than one millimeter for suspending it from the
balance.
e) Metal Gauge: The length gauge confirming to IS 2386 Part 1 shall be used as shown in figure. The tolerance
on dimensions shall be + 0.20 mm for dimensions shall equal to or more than 50mm and + 0.10 mm for
dimensions less than 50mm.
f) Impact testing machine: as per IS specifications.
g) Tamping Rod: A straight metal Tamping rod of circular cross-section 10mm in diameter and 230 mm long.
Rounded at one end.
h) Cylinder Cell: Open ended 150 mm cylindrical cell with appropriate base plate and plunger, metal measure
and tamping rod.
i) Compression Testing Machine: Compression testing machine capable of applying a load of 40 Tones is not
more than 10 minutes at a uniform rate of loading.
48
GUIDANCE
DOCUMENT
ENGINEERING PROJECTS(INDIA)LTD
(A Govt. of India Enterprise)
Prepared by
Reviewed &
Date Rev Description of Change Prepared by
Approved by
Page 2 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
Table of Contents
1. Introduction … 4
2. Scope … 5
3. Responsibilities … 6
4. Preparedness – Prior to start of activity … 7
4.1 Communication … 7
4.2 Area Disinfection … 8
4.3 Safety Inspection of Machineries & Critical equipment … 9
4.4 Inspection of Facilities … 9
4.5 Basic screening & orientation of workmen before engaging … 9
5 Initiating/ Resumption of Normal Working … 10
5.1 Identification of Hazards, Risk Classification & control measures … 10
6 Reporting … 11
7 General Precautionary Measures … 11
8 Returning or New worker & staff joining to the project … 12
8.1 Procedure for Recruiting New Staff/ Workers … 12
8.2 Procedure for Returning existing staff/ workers … 12
9 Actions to be taken COVID-19 Positive case if identified … 13
10 Annexures … 12
Page 3 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
1. Introduction
1.1 This Guideline is prepared to carry out the construction activities at Construction
of New Technology Centre at Vallam-Vadagal, Sriperumbudur, Tamil Nadu after
the lockdown period due to COVID-19 outbreak, 2020.
1.2 All precautionary measures need to be ensured at TCSP establishments so that all
stakeholders e.g. Employees / Vendors / Suppliers / Customers / Contract
workers / Consultants / Visitors etc. feel safe and secure at workplace.
1.3 Disclaimer: This document is intended to facilitate safe startup and continuation
of construction works during COVID-19 pandemic situation. Any of the
recommendations contradicting with the existing / future notifications of the
Government / Local authorities shall be considered void. All concerned are
advised to consider that the instructions from the Government, will supersede any
/ all the guidelines mentioned in this document.
Page 4 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
2. Scope
This Guideline applies to the following activities / facilities of TCSP Project
Page 5 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
3. Responsibilities
Page 6 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
Page 7 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
4.2.2 Appropriate protective equipment like Face Masks, Goggles, Gloves, Aprons,
Shoes including appropriate disinfecting equipment like sprayer, brush,
sanitizer, soaps etc. shall be made available in adequate quantities, in addition
to Disinfection Chambers / areas at all identified places.
Page 8 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
4.3.1 As all the major & Critical equipment like Pilling machine, excavator, Crane,
transportation vehicle, bar bending machine, concrete pump, Associated tools
and tackles, suspended work platforms, man-lifters etc., shall be disinfected to
prior to start of daily activity at worksite.
Page 9 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
Page 10 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
6. Reporting
The following reports must be submitted by the contractors on daily basis to
Client/ Owner who will further scrutinize, compile and forward to local
authorities (if required).
1. Emergency Preparedness & Response report (Annexure 4)
2. Photographic evidence of containment and welfare initiatives with location,
Page 11 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
Page 12 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
Page 13 of 14
FORMAT NO.
ENGINEERING PROJECT (INDIA) LIMITED HSE/GID/001
Guidance Document ISSUE NO. 01
REV NO. 00 , DATE: 09.11.2020
10. Annexures
Annexure-1: Guidelines for Cleaning and Disinfection etc.
Annexure-2: Risk Assessment
Annexure-3: Checks to Ensure Before Work Start
Annexure-4: Emergency Preparedness & Response
Annexure-5: Self-declaration for New Workmen/ Staff Joining During Covid-19
Outbreak
Annexure-6: Resumption of works Self-declaration form
Annexure-7: Flow Chart - For Deployment of New/ Returning staff & Worker to
project work
Annexure-8: Flow Chart – Action to be taken if any COVID-19 positive case
identified at Workplace/ Site office
Page 14 of 14
PORJECT ESHSE
MANAGEMENT
STRATEGIES &
IMPLANTATION PLAN
Rev.02
Date of Rev.: 08/11/2020
PREPARED BY
Mr. XXXXXX – Health & Safety Specialists
CHECKED BY
Mr. XXXXXX – Chief Engineer (or xxxxxxx)
APPROVED BY
Mr. XXXXXX – Project Director/ Project Manager
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
CLIENT :
CONSULTANT :
Reviewed by Approved by P a g e 1 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 2 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 3 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 4 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
1. SCOPE
This specification establishes the ESHSE Management Strategies & Implementation
requirement to be complied during construction activity.
This specification is not intended to replace the necessary professional judgment needed to
design & implement an effective ESHSE system for construction activities Requirements
stipulated in this specification shall supplement the requirements of HSE Management given
in relevant Act(s)/legislations, General Conditions of Contract (GCC), Particular Conditions of
Contract (PCC) and Contract Forms.
2. LEGAL & OTHER REFERENCES
In order to facilitate the better understanding on the various provisions of the
Act and Rules, a tabulated information highlighting the Sections/Rules applicable to the
legislation and Indian statutory requirements listed below but not limiting to:
i. Workmen Liabilities
a. Workman Compensation Act 1923
b. Payment of Gratuity Act 1972
c. Employees P.F. and Miscellaneous Provision Act 1952
d. Maternity Benefit Act 1951
e. Contract Labour (Regulation & Abolition) Act 1970
f. Minimum Wage Act 1948
g. Payment of Wages Act 1936
h. Equal Remuneration Act 1979
i. Payment of Bonus Act 1965
j. Industrial Disputes act 1947
k. Industrial Employment (Standing Order) Act 1946
l. Trade Unions Act 1926
m. Child Labour (Prohibition & Regulation) Act 1986
n. Inter-State Migrant workmen’s (Regulation of Employment & Conditions of Service)
Act 1979
o. Weekly Holidays Act -1942
ii. Health & Safety
a. The Building and Other Construction works (Regulation of Employment and Conditions
of Service) Act 1996 and the Cess Act of 1996
b. TN Building and Other Construction Workers (Regulation of Employment and
Conditions of Service) Rules
c. Indian Electricity Act 2003 and Rules 1956
d. Motor Vehicles Act as amended in 1994 and The Central Motor Vehicles Rules, 1989
e. The Motor Transport Workers Act 1961 & Rules
f. Indian Road Congress Code IRC: SP: 55-2001
g. The Petroleum Act, 1934 and Rules 1976
h. Gas Cylinder Rules, 2003
i. Indian Explosives Act, 1884, along with the Explosives substance Act 1908 and the
j. Explosives Rules 1983
Reviewed by Approved by P a g e 5 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 6 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
3. OUR POLICIES
a. HEALTH & SAFETY POLICY
Reviewed by Approved by P a g e 7 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
b. ENVIRONMENT POLICY
ENVIRONMENT POLICY
Reviewed by Approved by P a g e 8 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Conduct operations with high standards for personal integrity and ethical
behavior
Respect the laws and regulations of the government with whom we work and
the beliefs and values of communities.
Promote equal opportunity for employment regardless of gender.
Provide a means for open exchange of information that is clear and relevant
among communities, leaders, affected parties and EPIL.
Communicate expectations regarding community relations to all our employees
and contractors;
Implement Corporate Social Responsibility programs that directly benefit the
local communities; and
Routinely review the effectiveness of our community relations programs.
Reviewed by Approved by P a g e 9 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Site In-
Charge
Mr. XXXX
Safety Steward
Mr. XXXXX
Reviewed by Approved by P a g e 10 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Give precise instruction to the workers as the requirement for correct work method.
Coordinate with his worker’s to avoid any confusion about areas of responsibility.
Make sure that suitable personnel protective equipment is available and in use
Assure that new workers properly instructed precautions to taken before they are
allowed to start work.
Report all safety defects, and /usage practices to Site In-charge and Safety
supervisor.
Ensure for orientation and safety standards required & requirements for corrective
work methods.
7. ESHSE COMMITTEE
Site ESHSE Committee meeting shall be conducted at least once in a month with the
minimum members listed below:
ESHSE Committee Members Designation Site Designation
Reviewed by Approved by P a g e 14 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 15 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 16 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reports of all accidents (fatal / injury) and dangerous occurrences shall also be sent within 24
hours as per approved format.
No accident / dangerous occurrences is exempted from reporting to the Client/ Owner.
13. EMERGENCY PREPAREDNESS PLAN
An Emergency Response Plan for all work sites as required under Rule 36 of BOCWR will
be submitted as part of HSE plan.
Arrangements will be made for emergency medical treatment and evacuation of the victim in
the event of an accident or dangerous incident occurring, the chain of command and the
Reviewed by Approved by P a g e 17 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
responsible persons with the telephone numbers and addresses for quick communication will
be adequately publicized and conspicuously displayed in the workplace.
13.1 Fire
Shout for help.
Turn off the electricity to the building from the mains.
Call the fire brigade. Inform them of the nature of fire (solid / Liquid / gas)
And location of the accident with any prominent landmark.
In the event of small fire, attempt to put off the fire with minor fire appliances, water,
sand or any other available facility.
Call the nearest hospital and inform them of the condition of the injured if any.
Request for ambulance if needed and rush victims to the nearest hospital.
Inform Site In-Charge and HSE Department at the earliest.
Provide all help to the District authorities.
13.2 Fall from Height
Shout for help
Call the fire brigade. Inform them the nature and location of the accident with any
prominent landmark.
In the event of a minor injury provide immediate first aid to the victim.
In the event of a major injury do not move the victim, as there could be possibility of a
fracture or dislocation.
Call the nearest hospital and inform them of the condition of the injured if any.
Request for ambulance if needed and rush victims to the nearest hospital.
Inform Site In-Charge and HSE Department at the earliest.
Provide all help to the District authorities.
13.3 Electrocution
Stay away the victim. Do not touch the person or anything he is holding with bare hands,
since there is every possibility that the person any still be in touch with the source of
electricity. Touch the victim if you have to with a wooden rod or with gloves on.
Remove plug of the connected electrical equipment from socket.
Turn off the electricity to the building from the mains.
Shout for help and do not let anyone to get close to the victim.
Do not give anything to the victim to eat or drink.
Loosen clothes and start artificial respiration if necessary.
Call the fire brigade. Inform them the nature and location of the accident with any
prominent landmark.
Call the nearest hospital and inform them of the condition of the injured if any.
Request for ambulance if needed and rush victims to the nearest hospital.
Do not permit use of water at the site under any circumstances.
Don’t touch burns, burst blisters or remove burnt clothing.
Inform Site In-Charge and HSE department at the earliest
Provide all help to the District authorities.
Reviewed by Approved by P a g e 18 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 19 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
addressed by started OSHA standards. They give specific requirements for the maximum
load, when to use scaffolding, bracing and the use of guardrails.
13.6 Riot
Riots
Sound siren / blow whistle and assemble all personnel at a safe place within the site
premises.
Inform all personnel about the situation and appeal for calm.
Address the personnel on the need for applying self-restraint.
In the event of any unforeseen event at the work site, segregate warring groups and
appeal for self-restraint.
Call the nearest police station / PCR if the situation goes out of hand.
Provide first aid to the injured if any.
In the event of any major injury call the nearest hospital and inform them of the condition
of the injured if any.
Request for ambulance if needed and rush victims to the nearest hospital.
Inform Site In-Charge and HSE Department at the earliest.
Provide all help to the District authorities.
13.7 Flood
If Flood Surrounded in work area immediately you should move to elevated place and
Inform to Client/ Owner
Inform to the National disaster Management Team
13.8 Mock Drill
Will follow and participate in the main contractor’s mock drill at site by all the employees
and subcontractors.
Mock drill on different scenario have been conducted and made aware to the workers
After each mock drill the lesson learnt is informed among the project team.
Effectiveness and response of everyone is monitored.
14. PERSONNEL PROTECTIVE EQUIPMENTS
Following PPEs will be provided to workmen to protect against safety and health hazards.
Safety Purpose of
Item Location Compliance
Equipment Use
PN501
1 Safety Helmet In construction sites. Head protection
EN 397
Type: -PN352
Full Body Wear at sites when Personal Fall
4 EN355:2002
Harness working in heights or Protection
EN361:2002
Reviewed by Approved by P a g e 20 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
inside scaffolding or
any
Works which may
have the potential of
falling. (above 1.8mts
or where
more than 300 mm
gap)
Wear at sites during
welding, grinding,
drilling,
hammering works or
5 Goggles Eye protection Local
any
works which may
cause
injury to eyes
Wear at sites when
handling material with
6 Gloves Hand Protection Local
sharp edges or
chemicals
Wear at sites in dusty Respiratory
7 Dust mask PS400S
environment Protection
Wear at sites when
working in noisy
location
particularly at
atmosphere
with high frequency
8 Ear Plugs Noise Protection EP01 & EP02
noise
level (exceeding 85
dB)
such as grinding
works,
hammering
Hazard spotting
Protect from hazards
A planned system of housekeeping will cover every feature of the workplace.
Points to be checked to ensure good housekeeping in the work environment.
Maintain the walkways and stairways clear of materials. This will help to prevent
accidents due to slip, trip and falls.
Keep walkways and stairways free from electrical cables and wires.
Keep tools and equipment away from walkways and in locations where there is no
chance of fall from height.
Keep the materials and tools in storeroom. Have only tools that are essential for work
with you.
Store combustible and flammable materials away from ignition source.
Ensure adequate lighting and ventilation in working environment.
Maintain cleanliness and orderliness in the working environment.
Water stagnation should be avoided by providing proper draining system in the working
environment.
Assign place of storage for all equipment.
Keep the material after use in its place. Do not misplace it.
Stack the materials in an orderly way.
Floor openings should be properly covered.
Cable trenches should always be covered.
Remove trash, dirt and junk materials from the work area.
Keep waste or dust bins in the work area and put the wastes in that bin only.
Do not store materials or tools on window ledges.
Do not keep lifting tackles on floors. Provide proper stands to hang them.
Fire can be prevented by proper storage or disposal of flammable liquids, paper trash’s
and rags.
Eliminate the practice of keeping excessive materials.
Do not allow exits to be blocked.
Keep all electrical control boxes free from stored items.
The following steps have been identified and will be taken for proper housekeeping
during the execution of the Project.
All workers and site supervisors will be trained and instructed to keep the area clean by
removing the unwanted / dangerous materials out from the workplace.
Waste bins will be provided in sites in the area of work and daily disposal regime will be
established and implemented.
The Site Engineers will inspect the site for Housekeeping.
There will be signage provided in the area to keep workers aware of the importance.
16.2 Welding and Cutting
Gas Cylinders used should be in upright position and handled only with trolleys.
All gas cylinders shall be fixed with pressure regulator and dial gauges.
Reviewed by Approved by P a g e 22 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
DCP or CO2 type Fire Extinguisher not less than 5 kg shall be fixed at or near to welding
process zone in an easily accessible location. Fire Extinguisher should confirm to IS 2190:
1992.
Welding grounds and returns should be securely attached to the work by cable lugs, by
clamps in the case of stranded conductors, or by bolts for strip conductors. The ground
cable will not be attached to equipment or existing installations or apparatus.
Avoid being in contact with water or wet floors when welding. Use duckboards or rubber
protection
16.3 Machine/Equipment Guarding
All potentially hazardous parts are required to be effectively guarded from accidental
or incidental contact. The following items, for example, are considered potentially
hazardous:
Sheaves, pulleys and wire winders
Chain/sprocket and slew ring and drives.
Rollers and pulley drives
16.4 Hoisting and Rigging
Rigging practices shall conform to the standards approved in the country of use. If no
rigging practices exist, they should be developed with the assistance of a licensed
professional engineer. Safe practices shall include but are not limited to the following:
Machines/Hoisting devices (e.g. gasoline powered, electric winches, chain falls, etc.)
must be used and maintained in accordance with manufacturer recommendations.
Manufacturer recommended load capacities on rigging hardware (e.g. turnbuckles,
shackles, hooks, eyebolts, wire rope clips/clamps) - shall not be exceeded. Application
of these devices must be in accordance with manufacturer recommendations (e.g.
thimbles must be used in the eyes of all rope, slings shall not be shortened with knots
or other devices, slings shall be padded or protected from sharp edges or 90 degree or
greater bends).
Wire rope clips shall not be used. If unforeseen circumstances require deviation from a
Standard Work Process, before wire rope clips can be used, a documented Risk
Assessment (RA) must be submitted for review and approval to the Client of the project.
Deviations can only use double saddle clips (or other approved mistake-proof
alternative), and they must be used and installed according to manufacturer’s
recommendations. Pre-formed slings are certified slings made by a specialized
manufacturer for hoisting applications that require no modification for use.
Reeving must be done so that the hoisting strain comes on the centre of the blocks and
they are prevented from toppling, twisting and causing injury to the rope by cutting
across the edges of the reeve block.
16.4.1 Test and periodical examination of lifting appliances and gears
All lifting appliances including all parts and gears thereof, whether fixed or movable shall
be thoroughly tested and examined by a competent person once at least in every six
months or after it has undergone any alterations or repairs liable to affect its strength
Reviewed by Approved by P a g e 23 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
or stability. Within the validity, if the lifting appliances are shifted to a new site, re-
examination by the same competent person for ensuring its safety shall also be done.
EPI will utilize the services of any competent person as defined in Factories Act, 1948
and approved by Chief Inspector of Factories with the permission of the Client/ Owner.
All alarms and signals like automatic safe load indicators (SLI), boom angle indicators,
boom extension indicators, over lift boom alarm, swing alarm, hydraulic safety valves,
mechanical radius indicators, load moment indicators etc. shall be periodically
examined and maintained always in working condition
16.4.2 Automatic safe load indicators
As stipulated in relevant Rule of BOCWR 2007, no lifting appliances gear or any other
material handling appliance is used, if:
The Inspector having jurisdiction is not satisfied with reference to a certification of test
or examination or to an authenticated record maintain as provided under these rules;
And in the view of such Inspector, the lifting appliance, lifting gear or any other material
handling appliance is not safe for use in building or other construction work;
And no pulley block is used in building or other construction work unless the safe
working load and its identification are clearly marked on such block.
16.4.3 Qualification of operator of lifting appliances and of signaller etc.
The Contractor shall not employ any person to drive or operate a lifting machine-like
crane, hydra etc. whether driven by mechanical power or otherwise or to give signals to
work as an operator of a rigger or derricks unless he:
Is above twenty-one years of age and possesses a valid heavy transport vehicle driving
license as per Motor Vehicle Act and Rules.
is absolutely competent and reliable
Possesses the knowledge of the inherent risks involved in the operation of lifting
appliances by undergoing a formal training at any institution of national importance
acceptable to client.
Is medically examined periodically as specified in Schedule VII of BOCW Rules
16.4.4 General
Responsible personnel (i.e. mechanic-in-charge, lead person, foreman, etc.) will be
instructed regarding safety standards and proper application of all rigging and lifting
equipment.
A system of communication (e.g. hand signals) must be established and used for all
hoisting/lifting operations.
All rigging and lifting equipment (including hoists, ropes, hooks, etc.) shall be inspected
initially before the equipment is placed in service and at least once each year thereafter.
Inspections shall only be made by responsible personnel who are trained and
competent to perform such inspections. Written records of initial and periodic
inspections must be maintained, and the equipment must be marked to indicate the
last inspection date.
All rigging and lifting equipment shall be visually inspected before each use for defects
and deformation. Defective devices shall be immediately removed from service
Reviewed by Approved by P a g e 24 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 25 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
unless it is cleaned off or covered or sanded or saw dusted or make it safe with any
suitable material.
When workers are exposed to areas where fall into water is possible, the Contractor
shall provide suitable and adequate equipment for saving the workers from drowning
and rescuing from such hazard. If the Client/ Owner considers, the Contractor shall
provide well-equipped boat or launch, manned with trained personnel at the workplace.
Open side or opening where worker, equipment, vehicle or lifting appliance may fall at
a building or outside shall be guarded suitably except in places of free access by reasons
of nature of work.
Suitable safety net shall be provided at places of material / man falling is possible in
accordance with national standards.
The collapse of formwork in the construction industry has the potential for severe injury
and death. The four stages of the use of formwork (erection, adjustment, concrete
placement and dismantling) all need to be managed in a risk assessment framework.
Implementing suitable control measures can eliminate or reduce the potential for
events such as the collapse of formwork. Suitable control measures include:
Keeping the documentation for the formwork at the workplace;
Following the formwork documentation;
Planning to ensure that all elements of the process are conducted in a safe manner
– e.g. ensuring operators such as crane operators, concrete placers are suitably
licensed and trained, appropriate personal protective equipment is used etc.
Erecting the formwork on foundations which will support the loads to be imposed on
the formwork;
Not erecting formwork near excavation;
Ensuring materials used in the erection of formwork are not defective;
Securing loose material which may be dislodged as a result of inclement weather;
Inspecting the formwork assembly before and during the placement of concrete;
Not attaching equipment to the formwork assembly unless specifically designed for
this purpose; and not using a stripping process which may cause damage to the
permanent structure.
16.7 Site electricity and Hazards
Electricity in one of the greatest hazards to people either at work or at home. Power
line workers, electricians and electrical engineers work continuously and can face
exposure to this hazard on a daily basis. At the construction site, the best way to prevent
this kind of hazard is for the power line workers to be safe working to be safe working
distance away from the power lines. Other precautionary measures include guarding
and insulating of the vehicle from which they might work. This would help prevent
electrical hazards from injuring them while working.
EPI have assess the size and location of the electrical loads and the manner in which
they vary with time during the currency of the project.
They have elaborated as to how the total supply is to be obtained / generated. The
details of the source of electricity, earthing requirement, substation / panel boards,
Reviewed by Approved by P a g e 26 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
distribution system shall be prepared and necessary approval from client obtained
before proceeding of the execution of the job.
EPI will submit electrical single line diagram, schematic diagram and the details of the
equipment for all temporary electrical installation and these diagrams together with
temporary electrical equipment have submitted to the client and necessary approval
have been obtained.
EPI will provided distribution system for control and distribution of electricity from a
main AC supply of 50Hz for typical appliances:
Fixed plant - 400V 3 phase
Movable plant fed via trailing cable over 3.75 kW- 400V 3 phase
Installation in site building - 230V Single Phase
Fixed flood lighting - 230V single phase
Portable and hand tools - 115V single phase
Site lighting - 115V single phase
Portable hand lamps - 115V single phase
Enough ELCBs (maintain sensitivity 30 mA) / RCCBs for all the equipments (including
Potable equipments), electrical switchboards, distribution panels etc. to prevent
electrical shocks to the workers.
Cables were selected after full consideration of the condition to which they have
exposed and the duties for which they are required. Supply cable up to 3.3 kV shall be
in accordance with BS 6346.
For supplies to mobile or transportable equipment where operating of the equipment
subjects the cable to flexing, the cable shall conform to any of these codes BS 6007 / BS
6500 / BS 7375.
Flexible cords with a conductor cross sectional area smaller than 1.5 mm2 shall not be
used and insulated flexible cable shall conform to BS 6500 and BS 7375.
Where low voltage cables are to be used, reference have made to BS 7375. The
following standards shall also be referred to particularly for underground cables BS 6346
and BS 6708.
Plugs, socket-outlets, and couplers available in the construction site as “Splash Proof”.
The minimum degree of ingress protection was IP44 in accordance with BS EN 60529.
Only plugs and fittings of the weatherproof type shall be used, and they should be color
in accordance with the internationally recognized standards for example as detailed as
followed:
110 volts: Yellow
240 volts: Blue
415 volts: Red
All electrical equipment has permanently numbered and a record kept of the date of
issue, date of last inspection and recommended inspection period.
Fixed installation has been inspected at least at three months interval: routine
maintenance being carried out in accordance with equipment manufactures
recommendations.
Reviewed by Approved by P a g e 27 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
16.8 Lighting
Enough site lighting, of the right type and at the right place was properly effective.
Lighting ought not to introduce the risk of electric shock. Therefore, 230V supplies
should be used for those fittings, which are robustly installed, and well out of reach e.g.
flood lighting or high-pressure discharge lamps.
Selection of Luminaries
The selection of luminaries was as per the area requirement indicated below:
Type of Area of
S. No Luminaries
Lighting Requirement
Shovel type: non-
Workmen and symmetrical
Area
1 vehicles to move Symmetrical or non-
Lighting
about in safely. symmetrical tungsten
halogen
Portable flood light (Conical
Concentrated light
beam) Wide angle flood (fan
Beam flood over an area from a
2 shaped beam)
lighting relatively great
Medium or narrow angle
distance.
flood (Conical beam)
Dispersive (Mercury
Dispersive
3 Lighting for indoor florescent) Cargo cluster
lighting
florescent trough
Lighting for stairways, Well glass unit
Walkway ladder, corridors, Bulkhead unit (tungsten
4
lighting scaffold access routes, filament) Bulkhead unit
etc. (Florescent)
PAR (Parabolic Aluminized
Lighting on sites and Reflector) lamp cluster
Local fittings are generally Festoons (with or without
5
lighting accessible to shades) Adjustable florescent
operatives work lamp Portable flood
lamp
Luminaries have always been placed so that no person is required to work in their own
shadow and so that the local light for one person is not a source of glare for the others.
Strongly made clamps should be available for attaching luminaries to poles and other
convenient supports.
Luminaries should be robust, resistant to corrosion and rain proof especially at the
point of the cable entry.
The correct type of lamp for each luminaries should always be used and when lamps
need to be replaced if shall be in accordance with the supply voltage.
Lamp holders not fitted with a lamp should be capped off.
Reviewed by Approved by P a g e 28 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
All hand tools and power tools had sufficient grip and the design specification on par
with national / international standards on anthropometrics.
16.9.2 Hand tools
Hand tools shall include saws, chisels, axes and hatches, hammers, hand planes, screw
drivers, crow bars, and nail pullers.
The EPI will ensure that,
i. For crosscutting of hardwood, saws with larger teeth points (no. of points per
inch) have been preferred to avoid the saw jumping out of the job.
ii. Mushroom headed chisels was not be used in the worksite where the
fragments of the head may cause injury.
iii. Unless hatchet has a striking face, it was be used as a hammer.
iv. Only knives of retractable blades have been used in the worksite.
v. No screwdrivers have been used for scraping, chiseling or punching holes.
vi. A pilot hole was always be driven before driving a screw.
vii. Wherever necessary, usage of proper PPEs was used by their employees.
16.9.3 Power tools
Power tools include drills, planes, routers, saws, jackhammers, grinder, and sprayer,
chipping hammers, air nozzles and drills.
The EPI will ensure that,
i. Electric tools are properly grounded or / and double insulated.
ii. GFCIs/ RCCBs was used with all portable electric tool operated especially
outdoors or in wet condition.
iii. Before making any adjustments or changing attachments, their workers have
disconnected the tool from the power source.
iv. When operating in confined spaces or for prolonged periods, hearing
protection shall be required. The same shall also apply to working with
equipment’s, which gives out more noise.
v. Tool is held firmly, and the material was properly secured before turning on the
tool.
vi. All drills had suitable attachments respective of the operations and powerful
for ease of operation.
vii. When any work / operation needs to be performed repeatedly or continuously,
tools specifically designed for that work was used. The same is applicable to
detachable tool bit also.
viii. Size of the drill have been determined by the maximum opening of the chuck
in case of drill bit.
ix. Attachments such as speed reducing screwdrivers and buffers have been
provided to prevent fatigue and undue muscle strain to his workers.
x. Stock should be clamped or otherwise secured firmly to prevent it from moving.
xi. Workers shall never stand on the top of the ladder to drill holes in walls/
ceilings, which can be hazardous, instead standing on the fourth or fifth rung
shall be recommended.
Reviewed by Approved by P a g e 30 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
xii. Electric plane shall not be operated with loose clothing or long scarf or open
jacket.
xiii. Safety guards used on right angle head or vertical portable grinders must cover
a minimum of 180° of the wheels and the spindle / wheel specifications shall be
checked.
xiv. All power tools / hand tools shall have guards at their nip points.
xv. Low profile safety chain shall be used in case of wood working machines and
the saw shall run at high rpm when cutting and correct chain tension shall be
ensured to avoid “Kick Back”.
xvi. Leather aprons and gloves shall be used as an additional personal protection
auxiliary to withstand kickback.
xvii. Push sticks shall be provided and properly used to hold the job down on the
table while the heels move the stock forward and thus preventing kickbacks.
xviii. Air pressure is set at a suitable level for air actuated tool or equipment being
used. Before changing or adjusting pneumatic tools, air pressure shall be turned
off.
xix. Only trained employees shall use explosive actuated tools and the tool shall
also be unloaded when not in use.
xx. Usage of such explosive actuated tools shall be avoided in case of places where
explosive/flammable vapors or gases may be present.
xxi. Explosive actuated tools and their explosives shall be stored separately and be
taken out and loaded only before the time of immediate use.
xxii. Misfired cartridges of explosive actuated tools must be placed in a container of
water and be removed safely from the project.
xxiii. No worker shall point any power operated / hand tool to any other person
especially during loading / unloading.
16.10 Welding, Gouging and Cutting
Gas cylinders in use shall be kept upright on a custom-built stand or trolley fitted with
a bracket to accommodate the hoses and equipment or otherwise secured. The metal
cap shall be kept in place to protect the valve when the cylinder is not connected for
use.
Hose clamp or clip shall be used to connect hoses firmly in both sides of cylinders and
torches.
All gas cylinders shall be fixed with pressure regulator and dial gauges
Non-return valve and Flashback arrester shall be fixed at both end of cylinder and
torch.
Domestic LPG cylinders shall not be used for Gas welding and cutting purpose.
DCP or CO2 type Fire Extinguisher not less than 5 kg shall be fixed at or near to welding
process zone in an easily accessible location. Fire Extinguisher should confirm to IS
2190: 1992.
Use firewatchers if there is a possibility of ignition unobserved by the operator (e.g.
on the other side of bulkheads).
Reviewed by Approved by P a g e 31 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Oxygen cylinders and flammable gas cylinders shall be stored separately, at least 6.6
meters (20 feet) apart or separated by a fireproof, 1.5 meters (5 feet) high partition.
Flammable substances shall not be stored within 15 meters of cylinder storage areas.
Transformer used for electrical arc welding shall be fixed with Ammeter and Voltmeter
and fixed with separate main power switch.
Welding grounds and returns should be securely attached to the work by cable lugs,
by clamps in the case of stranded conductors, or by bolts for strip conductors. The
ground cable will not be attached to equipment or existing installations or apparatus.
Use a low voltage open circuit relay device if welding with alternating current in
constricted or damp places.
Take precautions against the risk of increased fume hazards when welding with
chrome containing fluxed consumables or high current metal inert gas (MIG) or
tungsten inert gas (TIG) processes.
Avoid being in contact with water or wet floors when welding. Use duckboards or
rubber protection.
All electrical installations shall meet the IS: 5571: 1997 and NFPA 70 for gas cylinder
storage area and other hazardous areas.
The current for Electric arc welding shall not exceed 300A on a hand welding
operation.
16.11 Fire Prevention, Protection and Fighting System
The EPI shall ensure that construction site is provided with fire extinguishing
equipment sufficient to extinguish any probable fire at construction site. An adequate
water supply is provided at ample pressure as per national standard.
Recharging of fire extinguishers and their proper maintenance should be ensured and
as a minimum should meet Indian National Standards
All drivers of vehicles, foreman, supervisors and managers shall be trained on
operating the fire extinguishers and fire-fighting equipment.
The Contractor shall also give consideration to the provision of adequate fire-fighting
arrangements within the underground and tunneling operations including the
provision of Fire Service compatible hose connections and emergency lighting.
As per the TNBOCW Rules “all lifting appliance” driver cabin should be provided with
a suitable portable fire extinguisher.
Combustible scrap and other construction debris should be disposed of site on a
regular basis. If scrap is to be burnt on site, the burning site should be specified and
located at a distance no less than 12metres from any construction work or any other
combustible material.
Emergency plans and Fire Evacuation plans shall be prepared and issued. Mock drills
should be held on a regular basis to ensure the effectiveness of the arrangements and
as a part of the Programme, the Telephone Number of the local fire brigade should be
prominently displayed near each telephone on site.
Reviewed by Approved by P a g e 32 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
16.12 Excavation
EPI will ensure that:
Where any construction building worker engaged in excavation is exposed to hazard
of falling or sliding material or article from any bank or side of such excavation which
is more than one 1.5 m above his footing, such worker is protected by adequate piling
and bracing against such bank or side.
Where banks of an excavation are undercut, adequate shoring is provided to support
the material or article overhanging such bank.
Excavated material is not stored at least 0.65 m from the edge of an open excavation
or trench and banks of such excavation or trench are stripped of loose rocks and the
banks of such excavation or trench are stripped of loose rocks and other materials
which may slide, roll or fall upon a construction building worker working below such
bank.
Metal ladders and staircases or ramps are provided, as the case may be, for safe access
to and egress from excavation where, the depth of such excavation exceeds 1.5 m and
such ladders, staircases or ramps comply with the IS 3696 Part 1&2 and other relevant
national standards.
Trench and excavation are protected against falling of a person by suitable measures
if the depth of such trench or excavation exceeds 1.5 m and such protection is an
improved protection in accordance with the design and drawing of a professional
engineer, where such depth exceeds 4m.
16.12.1 Piling (if Required)
General Precautions
There are certain hazards which are common to all types of piling, and the following
precautions are necessary:
Prior to piling, all underground services should be located and made safe. A check
should be made to ensure there are no cellars, underground water courses or ground
conditions which might cause hazards; there should be a firm level base for the crane,
or crane mats provided;
when working on piling operations one must wear a safety helmet, and ear and eye
protection where necessary;
All cranes, lifting appliances and lifting gear must have appropriate certificates of
testing and thorough examination, and should be large enough for the job.
Particular attention should be paid to the risk of damage to lifting gear from sharp
edges;
Cranes used for raising or lowering workers must be fitted with a dead man’ handle
and lowering should be done under power; you must be carried in properly
constructed cages which cannot spin or tip;
Piling contractors should be asked to provide a written method statement setting out
the precautions relevant to the type of piling they are to employ;
Induction training and information for you as supervisor or operative should be
specifically related to the method statement.
Reviewed by Approved by P a g e 33 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
A Work Permit authorization form shall be completed with the maximum duration
period not exceeding 12 hours.
A copy of each Permit-to-Work shall be displayed, during its validity, in a conspicuous
location near the actual works location to which it applies.
16.14 Traffic Management
The basic objective of the following guidelines is to lay down procedures to be adopted
by Contractor to ensure the safe and efficient movement of traffic and to ensure the
safety of workmen at construction sites.
All construction workers should be provided with high visibility jackets with reflective
tapes if they are deployed at vehicle movement area. The conspicuity of workmen
always shall be increased to protect from speeding vehicular traffic.
The guiding principles to be adopted for safety in construction zone are to:
i. Warn the road user clearly and sufficiently in advance.
ii. Provide safe and clearly marked lanes for guiding road users.
iii. Provide safe and clearly marked buffer and work zones
iv. Provide adequate measures that control driver behavior through construction
zones.
16.14.1 Legal permission
In all cases, the EPI shall ensure proper precautions. Wherever operations
undertaken are likely to interfere with public traffic, specific traffic management
plans shall be drawn up and implemented by the Contractor in consultation with
the approval of local police authorities and/or the concerned metropolitan / civil
authorities as the case may be.
Such traffic management plans shall include provision for traffic diversion and
selection of alternative routes for transport of equipment. If necessary, the
Contractor shall carry out road widening before commencement of works to
accommodate the extra load.
The primary traffic control devices used in work zones shall include signs,
delineators, barricades, cones, pylons, pavement markings and flashing lights.
The road construction and maintenance signs which fall into the same three major
categories as do other traffic signs, that are Regulatory Signs, Warning Signs and
Direction (or guidelines) Signs shall only be used. The IRC: 67 (Code of Practice for
Road Signs) provide a list of traffic signs. The size, colors and placement of sign
shall confirm to IRC: 67.
16.14.2
Regulatory signs
Regulatory signs impose legal restriction on all traffic. It is essential, therefore, that
they are used only after consulting the local police and traffic authorities.
Warning signs
Warning signs in the traffic control zone shall be utilized to warn the drivers of
specific hazards that may be encountered.
The EPI shall place detour signage at strategic locations and install appropriate
warning signs. In order to minimize disruption of access to residences and business,
Reviewed by Approved by P a g e 35 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
the Contractor shall maintain at least one entrance to a property where multiple
entrances exist.
A warning sign need to be installed at all secondary road which merges with the
primary road where the construction work is in progress at enough distance before
it merges with the primary road to alert the road
Materials hanging over / protruded from the chassis / body of any vehicle especially
during material handling shall be indicated by red indicator (red light/flag) to
indicate the caution to the road users.
16.14.3 Delineators
The delineators are the elements of a total system of traffic control and have two
distinct purposes:
i. To delineate and guide the driver to and along a safe path
ii. As a taper to move traffic from one lane to another.
These channelizing devices such as cones, traffic cylinders, tapes and drums shall
be placed in or adjacent to the roadway to control the flow of traffic. These should
normally be retro- reflectors complying with IRC: 79 - Recommended Practice for
Road Delineators.
16.14.4 Traffic cones and cylinders
Traffic cones of 500mm, 750mm and 1000mm high and 300mm to 500mm in
diameter or in square shape at base and are often made of plastic or rubber and
normally have retro- reflectorized red and white band shall be used wherever
required.
16.14.5 Drums
Drums about 800mm to 1000mm high and 300mm in diameter can be used either
as channelizing or warning devices. These are highly visible, give the appearance of
being formidable objects and therefore command the respect of drivers.
16.14.6 Boundary marking/ Restricting access to site
Temporary/ permanent work shall be protected by Caution tapes to avoid
unauthorized entry to the work site and to prevent the working area from the risk
of accidents. Same to protect the road users from the danger due to construction
equipment and other temporary structures.
Work area boundary shall be marked and identified on wooden pegs clearly.
Work related hazards shall be displayed using sign boards to inform/ caution/
communicate the unauthorized personnel accessing nearby.
Site entry register shall be maintained for the all the person including Client/
Visitors/ suppliers etc. entering the work area.
.
Reviewed by Approved by P a g e 36 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
be made for the stability of the machine. The loading shovels should always be
lowered to the ground to stabilize the machine when the backhoe is employed.
The netting operation of the skip wagons should be carried out prior to lifting the
skip to reduce the risks of working on the rear platform.
If a tractor dozer is employed on clearing scrub or felling trees, it shall be provided
with adequate driver protection.
When two or more scrapers are working on the same job, a minimum distance of
at least 25m shall be kept between them.
In case of hydraulic breakers, hydraulic rams and hoses shall be in good working
condition.
All wood working machines shall be fitted with suitable guards and devices such
as top guard, riving knife, and push stick, guards for drive belts and chains, and
emergency stop switch easily accessible by the operator.
16.14.12 Requirements related to use of Bulldozers
Be careful when working near the edge of banks, ditches, cuts or fills, or near
Overhanging material. The vibration and weight of the machine may cause the edge
to give way or overhanging material to fall.
Before starting work, ensure that an observer is present when plant is required to
work in water where the depth may endanger the operator.
Avoid obstacles such as rocks or logs. If forced to cross them, use extreme caution
and change to the lowest gear.
Ease up to the balance point and ease down to minimize the jolt on contact with
the other side.
When receiving a wire rope on a drum or through Sheaves, operators should
disengage the master clutch, idle the engine, and lock the brakes.
16.14.13 Clearing Operations
(When clearing trees, watch out for dead branches in treetops.
(Dozer operators should make sure that all persons are standing clear before
pushing over trees, dozing rocks or rolling logs.
(A long rope should be used to pull over large dead trees. (Make sure in advance
that a falling tree will clear the machine and operator).
In excavation work, operators should be alert to dangers from overhanging dirt
and rocks. In such cases, dozers should be equipped with the relevant overhead
protection.
(Watch boom clearance when travelling. Uneven ground may cause the boom to
weave and collide with obstructions.
Avoid jerky slewing or sudden braking. These can make the machine unstable and
overload machine components.
Ensure the operator has the appropriate restricted operator’s license if the
excavator is to be used in the crane mode.
When an excavator is used in the crane mode, check that the lifting weight is well
within the approved lifting capacity for the machine. This lifting capacity shall be
clearly and permanently marked on each machine.
Only operate attachments while stationary, as operation during travelling may
starve one of the track drive motors and result in an unintended turn.
Consider implementing a “Permit to work” system, particularly when working near
power lines or underground power for example: - that the height of power lines is
known; - that the underground location is known; and - visible measure, such as
tiger tails, are put in place.
16.14.15 Requirements related to use of Trucks
Driver defensively
Obey road signs
Never race with other vehicles
When following another vehicle, always allow enough distance to stop safely.
One truck length for every 10 km per hour of truck speed should be the minimum
distance between vehicles.
Reversing is the most hazardous truck operation. Reversing alarm which are fitted
on truck are effective in warning person of the danger. Reverse truck only when
they are under the direction of a signalman or when satisfied that the way is clear
and will remain clear.
Be cautious of spillage from loaded units and any hazards the spillage might
present to people on the ground and to the tires of other plant
Use a protective beam or timber baulk or back under the control of a signalman in
order to avoid this happening.
Where ground conditions are soft, or the tip head is likely to subside, dump loads
back from the edge and have a dozer move the material over the edge.
Watch for and avoid other vehicles, personnel and rock outcrops on entering or
leaving the loading area.
Stay a safe distance from trucks ahead at the loading point, and follow the
directions of the signalman or loader operator before moving into the loading
position.
Where material is to be transported on a public road, maintain a distance of 1.2
meter or more beyond the front or rear of the vehicle, or 150 mm on either side,
shall have a visible red flag or object fastened to the projecting end.
Truck operators are responsible for giving load placement requirements to crane
operators before loading operations begin.
Reviewed by Approved by P a g e 39 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
The load should be placed so that it will remain stable during loading, unloading
and travelling.
Lower truck bodies before leaving the dump area.
Only raise truck bodies to unload materials on surfaces where the vehicle will
remain stable and upright.
Never raise truck bodies to within a specified distance of overhead power line.
Take special care when tipping a load or spreading screenings on a road.
With the tray up, trucks are less stable and are more likely to roll over, particularly
on hilly sections or roads with surface irregularities or steep shoulders.
Check that the raised tray will not foul overhead power lines or telephone wires.
Never place part of your body under a raised truck body unless the truck body is
securely propped.
Trucks shall not be used to transport personnel unless they are specifically
designed to do so.
Where a bus is employed for the transportation of personnel, the bus shall: -be
enclosed; have seats which are attached to the vehicle; have a safe means of
access and exit; and, have two means of exit in case of emergency.
16.15 Manual Lifting And Carrying Of Excessive Weight
The Contractor shall ensure at his construction site of a building or other construction
work that no building worker lifts by hand or carries overhead or over his back or
shoulders any material, article, tool or appliances exceeding in weight as said below
as per Rule 38 of BOCWR, unless aided by another building worker or device.
Gender Person Maximum weight in kg
Adult man 55 Adult man 55
Adult woman 30 Adult woman 30
No building worker aided by other building worker shall lift or carry weight higher than
or exceeding the sum of total of maximum limits set out for each building worker
separately as mentioned in the table above
Reviewed by Approved by P a g e 40 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
The EPI will arrange a medical examination of all his employees including his sub-
contractor employees employed as drivers, operators of lifting appliances and
transport equipment before employing, after illness or injury, if it appears that
the illness or injury might have affected his fitness and, thereafter, once in every
two years up to the age of 40 and once in a year, thereafter.
Maintain the confidential records of medical examination or the physician
authorized by the Client/ Owner.
No building or other construction worker is charged for the medical examination
and the cost of such examination is borne by EPI employing such building worker.
The medical examination shall include:
i. Full medical and occupational history
ii. Clinical examination with particular reference to
iii. General Physique;
iv. Vision: Total visual performance using standard orthorator like Tetanus’s
Vision Tester should be estimated and suitability for placement
ascertained in accordance with the prescribed job standards.
v. Hearing: Persons with normal must be able to hear a forced whisper at
twenty-four feet. Persons using hearing aids must be able to hear a
warning shout under noisy working conditions.
vi. Breathing: Peak flow rate using standard peak flow meter and the average
peak flow rate determined out of these readings of the test performed.
The results recorded at pre-placement medical examination could be used
as a standard for the same individual at the same altitude for reference
during subsequent examination
vii. Upper Limbs: Adequate arm function and grip
viii. Spine: Adequately flexible for the job concerned.
ix. Lower Limbs: Adequate leg and foot concerned
x. General: Mental alertness and stability with good eye, hand and foot
coordination.
xi. Any other tests which the examining doctor considers necessary
If they fail to get the medical examination conducted as mentioned above, the
client has the right to get the same conducted by through an agency with
intimation to the Contractor and deduct the cost and overhead charges.
Reviewed by Approved by P a g e 41 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 42 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
It is suggested to the Contractor that due care should be taken to select the peer
educators from among the group of workmen so that they remain with the
Contractor throughout the contract period.
16.16.9 Prevention of mosquito breeding
Measures shall be taken to prevent mosquito breeding at site. The measures to
be taken shall include:
Empty cans, oil drums, packing and other receptacles, which may retain water
shall be deposited at a collection point and shall be removed from the site
regularly.
There should not be accumulation of still water at any site, In case of still water,
it should be covered by earth and levelled.
Equipment and other items on the site, which may retain water, shall be stored,
covered or treated in such a manner that water could not be retained.
Water storage tanks shall be provided.
At periodic interval shall arrange to prevent mosquito breeding by fumigation /
spraying of insecticides. Most effective insecticides shall include SOLFAC WP 10 or
Baytex, The Ideal Larvicide etc.
16.16.10 Alcohol and drugs
The Contractor shall ensure at all times that no employee is working under the
influence of alcohol / drugs which are punishable under Government regulations.
Smoking at public worksite by any employee is also prohibited as per Government
17. ENVIRONMENTAL MANAGEMENT
17.1 Air Quality
All necessary precautions to minimize fugitive dust emissions from operations involving
excavation, grading, and clearing of land and disposal of waste. He shall not allow
emissions of fugitive dust from any transport, handling, construction or storage activity
to remain visible in atmosphere beyond the property line of emission source for any
prolonged period without notification to the client.
Use construction equipment designed and equipped to minimize or control air
pollution. He shall maintain evidence of such design and equipment and make these
available for inspection by client
Establish and maintain records of routine maintenance program for internal combustion
engine powered vehicles and equipment used on this project. We shall keep records
available for inspection by Client/ owner.
Cover loads of dust generating materials like debris and soil being transported from
construction sites. All trucks carrying loose material should be covered and loaded with
sufficient free- board to avoid spills through the tailboard or sideboards.
Promptly transport all excavation disposal materials of whatever kind so as not to delay
work on the project. Stockpiling of materials will only be allowed at sites designated by
the Client/ Owner. The Contractor shall place excavation materials in the dumping /
disposal areas designated in the plans as given in the specifications.
Reviewed by Approved by P a g e 43 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
The temporary dumping areas shall always be maintained by the EPI until excavate is
re-utilised for backfilling or as directed by Client/ Owner. Dust control activities shall
continue even during any work stoppage.
Place material in a manner that will minimize dust production. Material shall be
minimized each day and wetted, to minimize dust production. During dry weather, dust
control methods must be used daily especially on windy, dry days to prevent any dust
from blowing across the site perimeter.
Water down construction sites as required to suppress dust, during handling of
excavation soil or debris or during demolition. The EPI will make water sprinklers, water
supply and water delivering equipment available at any time that it is required for dust
control use. Dust screens will be used, as feasible when additional dust control
measures are needed especially where the work is near sensitive receptors
Provide a wash pit or a wheel washing and/or vehicle cleaning facility at the exits from
work sites such as construction depots and batching plants. At such facility, high-
pressure water jets will be directed at the wheels of vehicles to remove all spoil and dirt.
To submit to the Client/ Owner an Air Monitoring and Control Plan (AMCP) under
contract specific Site Environmental Plan to guide construction activity insofar as it
relates to monitoring, controlling and mitigating air pollution.
17.2 Air Monitoring
Construction activities that will generate dust impacts include excavation (including
related activities), material handling and stockpiling, vehicular movement, and wind
erosion of unpaved work areas.
The impact of fugitive dust on ambient air pollution depends on the quantity generated,
as well as the drift potential of the dust particles injected into the atmosphere. Large
dust particles will settle out near the source and smaller particles are likely to undergo
dispersal over greater distance from the sources and impeded settling. SPM levels will
be monitored to evaluate the dust impact during the construction phase of the Project.
The Air Quality Monitoring and Control Plan (AMCP) in contract-specific Site
Environmental Plan prepared by the EPI shall establish procedures to monitor impact
air quality and measures to control air pollution including dust suppression due to
construction activities at work sites. This plan shall contain description of activities that
will cause degradation in air quality, environmental procedures to manage pollutants to
minimize the air pollution, monitoring program, record keeping and reporting.
existing stream courses and drains within or adjacent to the site. In the event of any
spoil or debris from construction works being deposited or any silt washed down to any
area, then all such spoil, debris or material and silt shall be immediately removed and
the affected land and areas restored to their natural state by the EPI to the satisfaction
of the Client.
Mud slurry from drilling, excavation, wall construction or grouting etc. shall not be
discharged into the drainage system unless treatment is carried out that will remove
silt, mud particles, bentonite etc. The EPI shall provide treatment facilities as necessary
to prevent the discharge of contaminated ground water.
Discharge wastewater arising out of site office, canteen or toilet facilities constructed
by him into sewers after obtaining prior approval of agency controlling the system. A
wastewater drainage system shall be provided to drain wastewater into the sewerage
system.
The bentonite mixing, treatment and handling system shall be established by the EPI
giving due regard to its environmental impacts. The disposal of redundant bentonite
shall be carefully considered whether in bulk or liquid form. The disposal location will
be advised and agreed with the relevant authorities.
Measures to prevent discharge of oil and grease during spillage from reaching drainage
system or any water body. Oil removal / interceptors shall be provided to treat oil waste
from workshop areas etc.
17.4 Waste
Required to develop, institute and maintain a Waste Management Programme (WMP)
during the construction of the project for his works, which may include:
Identification of disposal sites
Identification of quantities to be excavated and disposed off
Identification of split between waste and inert material
Identification of amounts intended to be stored temporarily on-site location of such
storage.
Identification of intended transport means and route.
Obtaining permission, where required, for disposal.
Such a mechanism is intended to ensure that the designation of areas for the
segregation and temporary storage of reusable and recyclable materials are incorporate
into the WMP. The WMP should be prepared and submitted to the Engineer for
approval.
Handle waste in a manner that ensures they are held securely without loss or leakage
thus minimizing potential for pollution. The EPI shall maintain and clean waste storage
areas regularly.
17.5 Energy Management
Use and maintain equipment to conserve energy and shall be able
Measures to conserve energy include but not limited to the following:
Use of energy efficient motors and pumps
Use of energy efficient lighting, which uses energy efficient luminaries
Reviewed by Approved by P a g e 45 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Adequate and uniform illumination level at construction sites suitable for the task
Proper size and length of cables and wires to match the rating of equipment
Use of energy efficient air conditioners
Design site offices maximum daylight and minimum heat gain. The rooms shall be well
insulated to enhance the efficiency of air conditioners and the use of solar films on
windows may be used where feasible.
17.6 Noise
EPI shall consider noise as an environmental constraint in his design, planning request.
The EPI shall, at his own expense, take all appropriate measures to ensure that work
carried out by the EPI and by his sub-Contractors, whether on or off the Site, will not
cause any unnecessary or excessive noise which may disturb the occupants of any
nearby dwellings, schools, hospitals, or premises with similar sensitivity to noise.
Without prejudice to the generality of the foregoing, noise level reduction measures
shall include the following:
The EPI shall ensure that all powered mechanical equipment used in the Works
shall be effectively sound-reduced using the most modern techniques available
including but not limited to silencers and mufflers.
The EPI shall construct acoustic screens or enclosures around any parts of the
Works from which excessive noise may be generated.
EPI shall ensure that noise generated by work carried out by the EPI and sub-contractor
during the daytime and night time shall not exceed the maximum permissible noise
limit, whether continuously or intermittently. The same may be varied from time to time
by and at the sole discretion of the Client/ Owner. In the relevant of a breach of this
requirement, the EPI shall immediately re-deploy or adjust the relevant equipment or
take other appropriate measures to reduce the noise levels and thereafter maintain
them at levels which do not exceed the said limits. Such measures may include without
limitation the temporary or permanent cessation of use of certain items of equipments.
The noise monitoring requirements are given in the project SHE Manual and the
monitoring locations shall be identified.
17.7 Noise Monitoring
The activities which are expected to cause noise during the construction of Project,
include noise from construction equipment, construction activities such as portal
construction, boring for piling, earthwork excavation, concreting, viaduct construction
and removal of spoil and movement of construction vehicles and delivery vehicle
travelling to and from the construction and disposal sites.
The level of impact of these noise sources depends upon the noise characteristics of the
equipment and activities involved the construction schedule, and the distance from
noise sensitive receptors.
If the measured noise levels exceed the noise limits, the noise levels shall be reduced
by appropriate abatement measures.
Reviewed by Approved by P a g e 46 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
In no case shall the EPI expose the public to construction noise levels exceeding 90 dBA
(slow) or to impulsive noise levels with a peak sound pressure level exceeding 140 dB as
measured on an impulse sound level meter.
Limit for construction noise is based on the existing ambient noise levels in areas
adjoining the construction sites.
The noise levels emanating from any source during construction, shall not exceed 5 dBA
or more above existing ambient pre-construction noise levels. The same may be varied
from time to time and at the sole discretion of the Client/ owner.
Where there are no ambient noise measurements, the construction activities shall be
limited to levels at a distance of 200 feet from the construction limits or at the nearest
affected building, whichever is closer,
Maximum Noise Level Lmax dBA
Land Use
Day Time Night Time
Residential 75 65
Commercial (all time) 85
Industrial (all time) 90
When Diesel Generator (DG) Sets are used for operation of equipment and machinery,
then Environment (Protection) Act, 1986 shall apply.
The EPI shall inform the Client/ owner of all steps taken to investigate cause of
exceedance and immediate action taken to avoid further exceedance through written
reports and proposals for action under an Event Contingency Plan.
17.8 Vibration Level
In locations where the alignment is close to historical / heritage structures, the EPI shall
prepare a monitoring scheme prior to construction at such locations. This scheme for
monitoring vibration level at such historical / heritage sites shall be submitted to Client/
owner for his approval. This scheme shall include:
Monitoring requirements for vibrations at regular intervals throughout the
construction period;
Pre-construction structural integrity inspections of historic and sensitive
structures in project activity;
Information dissemination about the construction method, probable effects,
quality control measures and precautions to be used;
The vibration level limits at work sites adjacent to the alignment shall conform
to the permitted values.
18. WATER RESOURCE PROTECTION
Water source protection involves the protection of surface water sources (e.g. lakes,
rivers, man-made reservoirs) and groundwater sources (e.g. spring protection, dug well
protection, and drilled well protection) to avoid water pollution (see also pathogens and
contaminants).
While surface water sources and springs are directly exposed to human activities,
groundwater sources are often protected through overlaying soil layers. However, accessing
Reviewed by Approved by P a g e 47 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
groundwater sources through dug or drilled wells allows contaminants to enter aquifers,
polluting the well itself and the water in nearby lakes, rivers, or neighboring wells, which
consequently threatens both public health and the environment.
In the past, the need for water source protection has often been neglected. As a consequence,
many drinking water sources have become contaminated making water purification measures
indispensable. The very slow flow of groundwater makes rehabilitation of contaminated
aquifers both costly and time-intensive. While removal of pathogenic contamination through
disinfection is more likely to be successful, some metals and chemical substances will
permanently remain in the soil.
Recently, establishing adequate water source protection has been recognized as the most
suitable and cost-effective method to keep contaminants out of drinking water and making
costly water purification measures and construction of new wells. This holds both for
industrialized and developing countries.
Implementing water source protection requires a legal framework. This usually involves a
protection plan, which formulates responsibilities, specific protection measures and basic
rules that apply to all community members and water source users.
18.1 Surface Water Source Protection Measures
As many surface water sources are used for drinking water purposes, protection is vital.
Generally, three basic strategies exist for protection.
Prevention: No discharge of waste, pollutants or untreated water from domestic,
industrial or agricultural use; optimized water use and practices in agriculture in order
to stop nutrients from entering aquatic systems (e.g. establishing buffer zones).
Treatment: treatment of polluted water prior to discharge; storm water management:
ensuring that run-off cannot transport pollutants into water bodies.
Restore ecosystems: Enable or support natural rehabilitation processes.
18.2 Groundwater Source Protection Measures
Numerous simple preventative measures can be applied to protect springs, wells and
aquifers from contamination. They are presented in the following five steps.
Step 1: Location / Site Selection of the Water Source - Never Close to Pollutant Sources
Before the drilling of a well or construction of a spring tapping starts, an appropriate
site has to be found. Villagers or landowners are a good source of information and
mostly point out a suitable location for them as users. However, several other
important aspects have to be kept in mind when selecting the optimal site for a water
source
18.3 A water point of any kind or source should be:
Situated above the (seasonal) flood level of any nearby river or lake;
In a location, which guarantees easy access for all water users all year round. This
refers to physical access but also to legal access.
In proximity to the actual point of water use;
In an area allowing the rapid dispersal of spilt water;
Reviewed by Approved by P a g e 48 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
In a sunny area without shade to guarantee that the immediate well surroundings
remain dry, so as to prevent bacteria, algae, etc. to evolve.
In a location where the level of the water table is at a depth of at least two meters
all year round (for wells);
In distance from agricultural activities of any kind; particularly if pesticides or
fertilizers are applied.
In an area not susceptible to erosion;
In safe distance to saltwater and any source of pollution such as a pit latrine, abattoir,
dumping site, fertilizer or pesticide store, etc.
18.4 Set up Rules for all Community Members
Any protection plan rises and falls with the behaviour of the community members, their
attitude towards the plan and their knowledge. Besides the installation of constructional
measures, simple rules should be set up and communicated by a local caretaker.
Such rules can include:
Don’t defecate close to the well,
Don’t let your animals graze close to the well,
Don’t throw any garbage into the well, etc.
No sewer line will be connected to the water resource.
No person/ workmen will be allowed for bathing, fishing at water resource area.
Adequate site security shall be deployed for monitoring the same.
All personnel will be restricted to water resource area by installing adequate fences
if required.
19. HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL PROCEDURE
This is the procedure of identifying hazards, assessing the risk level and applying control
measure on each activities or process of the entire section to bring it to tolerable level so
as to carry out work in safe and healthy manner.
This is applicable for entire division. Overall responsibility for procedure implementation
lies with the Site in-charge While Site engineer responsibility for procedure
implementation lies with the respective sectional heads.
Description; Identification of Hazard associated with the activities carried out in the
division is done on
Routine and non –routine activities
Activities of all personnel having access to the workplace.
Activities carried out during Abnormal and Emergency situations.
Start up and Shut down.
Human behaviors, capabilities and other human factors.
Identified hazards originating outside the workplace capable of adversely affecting
the health and safety of person under the control of the organization within the
workplace,
Hazards created in the vicinity of the workplace by work related activities under the
control of the organization.
Reviewed by Approved by P a g e 49 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 50 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Review
HSE Specialist will review HIRA every year and suggests necessary corrective actions, if any.
It can be reviewed after internal & external audits also.
Reviewed by Approved by P a g e 52 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 53 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 54 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
_______________________________________________________________________________
CAUSE OF ACCIDENT
_______________________________________________________________________________
NATURE OF INJURY /DAMAGE
_______________________________________________________________________________
Medical aid Provided / Actions Taken
_______________________________________________________________________________
Intimation To Local Authorities
_______________________________________________________________________________
DATE: SIGNATURE OF CONTRACTOR
WITH SEAL
Reviewed by Approved by P a g e 55 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 56 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Inspection By _________________________
Reviewed by Approved by P a g e 57 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 58 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
8. WORKING AT HEIGHT
a) Erection plan and work permit obtained
b) Safety nets
Reviewed by Approved by P a g e 59 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 60 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 61 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
10. All persons provided with proper safety belt & helmet
Reviewed by Approved by P a g e 62 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
A. Following Personal protective equipment are provided [mark] and use as relevant
.Safety Helmet Gloves Goggles / Face shield / life line/Safety belt / Safety
harness.
B. This permit shall be available at the work site at all times.
C. Permit shall be issued for maximum one week only [Monday to Sunday]
D. This shall be applicable in non-operations areas.
E. After completion of the work used permit shall be preserved for record purposes.
F. Additional precaution, if any;
Reviewed by Approved by P a g e 63 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
PERMIT EXTENSION
Sl. No. Validity period Work Time Initiators (SO site In Signature
(--------- To---------) From- (His). (Supervisor of charge Of the PMC
To (Hrs). the Contractor) Contractor)
1.
2.
3.
4.
5.
6.
7.
Note: - Name of the person & their gate pass nos. permitted to work at height shall be entered daily
on separate sheet & shall be available along with the permit.
Reviewed by Approved by P a g e 64 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Name of Contractor:
Date of Inspection:
(Safety officer)
Contractor:
Reviewed by Approved by P a g e 67 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 68 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Equipment make:
Equipment Model:
Equipment S. No:
Above portable electric grinder found ( ) suitable ( ) not suitable for use at
Construction site
Name: Name:
Signature: Signature:
Reviewed by Approved by P a g e 69 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Equipment make:
Equipment Model:
Equipment S.No:
S. No. Item Status Remarks
1. All body cover /electrical
insulation in sound condition
2. Electrical Cable without joint
3. Cable including welding and
ground cables with wron-out or
crack insulation
4. Condition of Welding Holder and
its insulation
5. Conditions of Electrical Switches
6. Earthing arrangement proper
7. Availability of proper face shield
and leather hand gloves for
welder
8. Other remarks
Reviewed by Approved by P a g e 70 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Equipment make:
Equipment Model:
Equipment S. No:
S. No. Item Status Remarks
1. All body cover /electrical
insulation in sound condition
2. Electrical Cable without joint
3. Cable including welding and
ground cables with worn-out or
crack insulation
4. Condition of Welding Holder and
its insulation
5. Conditions of Electrical Switches
6. Earthing arrangement proper
7. Availability of proper face shield
and leather hand gloves for
welder
8. Other remarks
Name: Name :
Signature Signature:
Reviewed by Approved by P a g e 71 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Equipment make:
Equipment Model:
Equipment S. No:
S. No. Item Status Remarks
1. Proper Wheel Guard Provided
2. All body covers/ electrical
insulation in sound conditions
3. Three core electrical cable
provided
4. Electrical plug top provided
5. Provision of earthing
6. Cable without joints and in sound
condition
7. Wheel RPM matches with
machine RPM
8. Availability of Face Shield &
Gloves for Grinder
9. Other Items, If any
Name : Name :
Signature Signature:
Reviewed by Approved by P a g e 72 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Equipment make:
Equipment Model:
Equipment S. No:
Item Status Remarks
Gas cylinders colour as per code
Flesh back arrester Provided
Cylinder valves are ISI marked
Valve key available
Both hoses free form joints, burns
& cracks
Colour of hoses proper:
Oxygen Black Acetylene: Red
Length of both hoses should be
equal
Proper goggles and leather hand
gloves available for use
Other remarks
Above portable electric grinder found ( ) suitable ( ) not suitable for use
Name : Name :
Signature Signature:
Reviewed by Approved by P a g e 73 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Equipment make:
Equipment Model:
Equipment S. No:
S. no. Item Status Remarks
1 Proper
& valid load test certificate available form
authorized reprehensive of chief inspector
of factories
2. Max. safe load displayed on equip. in kg
3. All guard such as guard over gears, rotating
shaft etc are in place
4. Wire rope without kinks/ loose or broken
strands / excessive wear.
5. Chain / hook without physical damage.
6. Date of last test done
7. Next Testing test done
8. Other remarks
Above portable electric grinder found ( ) suitable ( ) not suitable for use
Contractor Safety Engineer Contractor Site Engineer
Name: Name :
Signature Signature:
Reviewed by Approved by P a g e 74 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Contractor:
Topics:
S. No Name of Designation Company Sex Date of Blood Gate pass Signature
worker birth group no
Reviewed by Approved by P a g e 75 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
DESCRIPTION
S. No. QUANTITY
Reviewed by Approved by P a g e 76 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 77 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
HOSPITALS :
KGH PBX
ESI Hospital-
ESI Hospital- Industrial Estate
Reviewed by Approved by P a g e 78 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 79 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 80 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 81 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Reviewed by Approved by P a g e 82 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Name & Sign. Of the Safety Engineer. (EPI) Name & Sign. Of the Site Engineer. (EPI)
Reviewed by Approved by P a g e 83 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Signature:…………………. Signature:………………….
Reviewed by Approved by P a g e 84 | 86
ENGINEERING PROJECTS(INDIA)LTD FORMAT NO.
(A Govt. of India Enterprise) EPI/ENGG/PMD/001
ISSUE NO. 01, DATE: 02.06.14
Project ESHSE Management REV NO. 02 , DATE: 08.11.20
Strategies & Implementation Plan
Signature of Site-in-charge
Reviewed by Approved by P a g e 85 | 86
GEOTECHNICAL INVESTIGATION REPORT
for proposed MSME buildings at SIPCOT Industrial Park, Vallam,
Vadagal, Kanchipuram, Tamilnadu.
EXECUTIVE SUMMARY
M/s. TATA Consulting Engineers Limited., Pune are associated in construction of MSME
buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
The site for the proposed project is situated on northern and western side of road at
SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu. The site is almost
rectangular in shape and approximately measures 7.5acres. The site is open on all sides
and is undulating. The site is below the existing road level by about 1.5m Vegetation in
the form of grass, bushes and trees were observed at the site during the period of field
investigations. There is a water body existing on the western side of the site (adjacent to
site). There is a high tension line on the southern side of the site in east-west direction
(adjacent to site).
The proposed project comprises of MSME buildings comprising of Ground floor and 4/5
upper floors.
Geotechnical investigations have been undertaken at the site as per the scope of
investigations, stipulated by the client, which consisted of total Five boreholes down to
the required depth along with 3 electrical resistivity tests and 10 trial pits. The coordinates
of the test location are provided belwo:
G(C)9289
Page 1 of 136
Test Number Easting Northing
TP 2 382916 1426094
TP 3 382892 1426123
TP 4 382836 1426103
TP 5 382791 1426144
TP 6 382672 1426060
TP 7 382677 1426136
TP 8 382693 1426197
TP 9 382825 1426201
TP 10 382925 1426180
ERT 1 382680 1426145
ERT 2 382802 1426122
ERT 3 382889 1426152
The soil strata consists of clay silt sand with gravels with varying proportions. The subsoil
strata is reflective of gradually improving conditions with upper layers indicating medium
to stiff consistency and indicating very dense conditions beyond 12m depth.
During the investigations on completion of boreholes, water table was allowed to stabilise
for 24hrs. Ground water table had been encountered between 7.5 and 12.5m depth in the
borehole during the period of field investigations.
In view of the observed subsoil strata conditions the proposed structure can be supported
on Isolated/strip foundations. The allowable bearing pressure at different depths for
different widths for various settlement are given below:
G(C)9289
Page 2 of 136
Net Allowable Bearing Pressure for
Depth of Foundation Settlement different foundation width (t/m²)
from E G L (m) (mm)
1 2 3 4 5 $6m
75 11 11.5 11.5 12 12.5 13
50 8.5 9 11 12 12.5 13
2
40 7 7 9 10 12 13.5
25 4 4.5 5.5 6.5 7.5 8.5
75 11.5 12 12 12.5 13 14
50 9 10 11.5 13 13 14
3
40 8 8 11 12 13 14
25 4.5 5 5.5 6.5 8.5 10
75 18 18.5 19 19.5 20 21
50 13.5 14.5 15 16.5 18 21
6
40 12 13 14.5 16 17.5 21
25 7 8.5 9 9 12 13
G(C)9289
Page 3 of 136
If load transfer by structures is more than the bearing pressure recommended above; then
Pile foundation may be adopted. The Load Carrying Capacity of different diameter piles
is given below:
The excavated soil is fine grained and exhibits medium expansivity. It is therefore not
recommended for use as foundation backfill (refer para 7.10.1).
For excavation for the foundations, the excavation may be done with a slope of 1.5-
2vertical to 1horizontal upto a depth of 3m. Excavations beyond 3m should have suitable
benches as per IS 10386 (Part 8).
Stiff Tie-beams connecting the columns in both directions may be provided which will
render additional rigidity to the structure.
The site must have proper slopes and drainage system to drain out any pilferage of water/
rain water to avoid moisture water movement towards the foundation / underneath the
G(C)9289
Page 4 of 136
structures.
Is the site is being filled with external soil and for any filling; the filling may be done in
layers using non swelling soil. The filling may be done in layers of 25-30cm thick duly
compacted to >95% of modified proctor density.
It is suggested the load capacity of the pile be confirmed by a load test.
After reaching the required depth, care should be taken that the slush formed at the bottom
is minimum. The bentonite being used during piling should be as per IS 2911.
G(C)9289
Page 5 of 136
REPORT ON GEOTECHNICAL INVESTIGATION FOR
1.0 INTRODUCTION
1.1 Overview
1.1.1 The geotechnical investigation has been done to ascertain the soil properties and to aid
1.1.2 M/s. TATA Consulting Engineers Limited., Pune are associated in construction of MSME
1.2 Authority
1.2.1 A comprehensive soil investigation programme has been conducted as per the
authorisation by M/s. TATA Consulting Engineers Limited, Pune vide their P.O.No.
2.1.1 The site for the proposed project is situated on northern and western side of road at
SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu. The key map
2.2.1 The site is almost rectangular in shape and approximately measures 7.5acres. The site is
open on all sides and is undulating. The site is below the existing road level by about
1.5m Vegetation in the form of grass, bushes and trees were observed at the site during
the period of field investigations. There is a water body existing on the western side of the
G(C)9289
Page 6 of 136
site (adjacent to site). There is a high tension line on the southern side of the site in east-
2.3 Geology
2.3.1 The proposed site is located in the south eastern part of India and in northern part of
Tamil Nadu. It is bounded by Bay of Bengal on the east, Andhra Pradesh state in the north
2.3.2 The area of tamilnadu have extensive khondalites, charnockites and migmatitic rocks are
traced. The eastern coastal tract is characterized by Phanerozoic sedimentary cover. The
sedimentary deposits were deposited at various stages ranging from the Recent to Upper
Gondwana.
2.3.3 The Alluvium consists of sand, silts and clays. The thickness of alluvium varies from
place to place. The tertiary sandstones are reddish brown to greyish white and white in
colour. The sandstones are available above the eroded Gondwana formations and or
overlain by river alluvium. This formation is of terrestrial origin. The Gondwana deposit
is located in a small area on the north western corner south of the tertiary formation. In
the coastal Gondwana deposit, the presence of plant fossils and marine incursion during
2.3.4 Kanchipuram area consists of soil underlayed by crystalline hard rocks with varying depth
to the basement rocks (mostly charnockite with some gneissic/granite zones). Lineament
features like fractures, joints, faults, dykes are common in the region. The predominant
geomorphological features that are found in this area are buried pediment, inselbergs,
residual hills and mud flats. The general sequence of lithounits in this area comprises
G(C)9289
Page 7 of 136
thick layer of soil, weathered charnockite and the basement rock.
2.4.1 As per the client’s information, the proposed project comprises of MSME buildings
2.5.1 Site for the proposed project is situated at Vallam, Vadagal, Kanchipuram near Chennai
which falls under Seismic Zone III as per IS 1893 (Part 1) - 2016.
a) Latitude : 12<53'
b) Longitude : 79<55'
3.1 For designing the foundation system of the proposed structures, the following data are
required:
b) Depth below the ground level at which the foundation system is to be laid.
a) The sub soil profile indicating thickness of the various soil strata, to a depth down
G(C)9289
Page 8 of 136
3.3 The object of conducting field and laboratory investigations and analysis is to get data for
N>100) and further drilling in refusal/rock strata by minimum 7.5m (i,e 5 SPT
c) Recovering undisturbed soil samples from various levels of the sub soil strata.
i) Conducting relevant laboratory tests on soil samples and water samples were
recovered/collected.
j) Preparation and submission of a technical report containing the details of the tests
carried out, their analysis and recommendations regarding the foundation system
Weather was dry and clear during field investigations which was carried out on second
G(C)9289
Page 9 of 136
week of February 2019.
5.1.2.1 The location of the boreholes were shown at site by the client. A Schematic site plan
showing the location of the test points marked by the client is given in fig. 1.
5.1.2.2 Few photographs taken during the test are provided in fig 23 to 36.
5.2 Boreholes
5.2.1 The boreholes were progressed by mechanically operated rotary core drill method using
5.2.2 The boreholes were terminated after drilling a minimum of 7.5m (i,e 5 SPT in N>100 at
1.5m intervals) in refusal/rock strata. The refusal strata encountered is in the form of Hard
clay. The N value in this strata is >100. The termination depth of boreholes and depth of
water table encountered in the boreholes during the period of field investigations are given
5.2.3 Standard penetration tests were conducted at 1.5m intervals. Disturbed soil samples
recovered from split spoon samples were packed in polythene bags, labelled and retained
5.2.4 Undisturbed soil samples were recovered by thin walled tubes conforming to IS 2132.
G(C)9289
10
Page 10 of 136
These tubes had an area ratio of less than 10-15%. The diameter of soil samples were
90mm and its length was 45cm. The ends of sample tubes were sealed by wax to prevent
5.3.1 Ground water table had been encountered between 7.5 and 12.5m depth in the borehole
5.4.1 Electrical resistivity tests (ERT1 to ERT3) had been carried out at the specified locations.
The tests have been conducted using Wenners' four electrode method as per IS : 3043.
Co-ordinates
ERT No
Easting Northing
1 382680 1426145
2 382802 1426122
3 382889 1426152
5.4.2 In this test, four electrodes had been driven into the ground surface along a straight line
at equal intervals/ spacings. The tests involves the passing of a current through the outer
two electrodes called the current electrodes and the measurement of the voltage difference
between the two inner electrodes called the potential electrodes. The ratio of the voltage
difference measured to the current passed gives the resistance. An electrical megger had
been used to determine the resistance directly, at the site. The resistance had been so
5.4.3 In the present case, the depth of electrodes had been maintained at 20cms. The spacings
G(C)9289
11
Page 11 of 136
5.4.4 The above procedure had been repeated for eight different directions at every selected
5.4.5 The electrical resistivity of the soil which is a function of the resistance determined is
calculated for each electrode spacing used. A plot of electrical resistivity vs distance is
then prepared which invariably indicates an average constant value of the electrical
resistivity at larger electrode spacings. This average constant value of the electrical
5.4.6 The electrical resistivity so determined for each direction is plotted on a polar plot to
obtain a closed curve. The representative electrical resistivity for the test location is then
determined as the radius of the circle having an area equivalent to the enclosed area within
5.4.7 The electrical resistivity of the soil/rock depends on the density, water content, grain size
distribution etc. of the soil and mineral composition and grain structure of the parent rock.
5.5.1 Three trial pit were excavated at the specified locations. The coordinates of the tests are
given below:
Co-ordinates
TP No
Easting Northing
1 382953 1426156
2 382916 1426094
3 382892 1426123
4 382836 1426103
5 382791 1426144
6 382672 1426060
G(C)9289
12
Page 12 of 136
Co-ordinates
TP No
Easting Northing
7 382677 1426136
8 382693 1426197
9 382825 1426201
10 382925 1426180
5.5.3 Samples were collected at regular depth from the pits that were excavated.
5.6.1 Field permeability tests had been conducted as per IS: 5529 (Part I) - 1985 by the open
ended cased borehole method. The permeability tests had been conducted by falling head
5.6.2 In this method, the borehole had been drilled down to the level of 3m at which test had
been performed. The casing had been simultaneously sunk down to the full drilled depth
of the borehole as the drilling or boring of the borehole was in progress. After the required
level had been reached, the borehole had been properly cleaned.
5.6.3 After the borehole had been cleaned, the borehole had been filled with water up to a level
6.1 The disturbed and undisturbed soil samples brought to the laboratory were used for the
tests, as appropriate.
6.2 The soil samples were subjected to various tests to determine the following properties
b) Consistency limits
G(C)9289
13
Page 13 of 136
c) Natural density
f) Swell Pressure
g) Consolidation properties
i) Lab CBR
6.3 In order to determine the above properties listed in 6.2, the following tests were
conducted.
f) Specific Gravity
i) Consolidation tests
G(C)9289
14
Page 14 of 136
7.0 RESULTS OF INVESTIGATION AND ANALYSIS
7.1.1 The results of borehole investigations and of the laboratory investigations conducted on
the soil samples collected from the boreholes have been presented in the form of tables.
e) Atterberg limits
7.2.1 A perusal of the data presented in the soil profile tables indicate the presence of the
following strata.
7.2.2 The thicknesses in each borehole of each strata described in 7.2.1 is given in the table
below:
G(C)9289
15
Page 15 of 136
depth (m) : from - to
BH. NO.
Stratum I Stratum II
3 0.0 - 13.5 13.5 - 19.5
4 0.0 - 13.5 13.5 - 19.5
5 0.0 - 13.5 13.5 - 21
7.3.1 The grain size distribution of the soil samples at various depths, as determined in the
laboratory have been presented in the form of grain size analysis curves, as fig. 3, 3a to
7.3.2 The variations in the grain size distribution - strata wise across the boreholes are as
follows:
G(C)9289
16
Page 16 of 136
7.3.3 The above results indicate that :
a) Stratum I consists of about 14 - 23% of sand, 29 - 37% silt and 38 - 57% of clay.
b) Stratum II consists of about 20 - 27% of sand, 33 - 37% silt and 37 - 46% of clay.
7.4.1 The In-situ bulk density of the sub soil stratum varies between 1.77 and 1.94g/cm3, water
content varies between 11.46 and 22.16% and In-situ dry density of the sub soil stratum
7.5.1 The Atterberg Limits in Stratum I (Brownish grey sandy silty clay) are given below:
G(C)9289
17
Page 17 of 136
BH No Liquid Limit (%) Plastic Limit (%) Plasticity Index (%)
1 47 - 59 20 - 26 27 - 33
2 46 - 62 20 - 27 26 - 35
3 50 - 59 21 - 23 29 - 36
4 45 - 61 19 - 27 26 - 34
5 47 - 66 20 - 28 27 - 38
7.5.2 The Atterberg Limits in Stratum II (Hard clay) are given below:
7.6.1 Standard Penetration Test values (N-values observed) are presented in the soil profile
table no 1 to 5. The curve showing relation N - values (observed) vs depth is shown in fig.
7.7.1 The cohesion obtained from consolidated drained triaxial compression test at varies
between 0.23 to 0.33kg/cm² and the angle of shearing resistance k of the soil varies
7.8.1 The specific gravity of the soil particles are given below:
G(C)9289
18
Page 18 of 136
Specific Gravity at Depth (m)
BH NO
1.5 3
1 2.55 2.56
2 2.54 2.56
3 2.56 2.57
4 2.54 2.55
5 2.54 2.56
7.9.1 The free swell index of the soil particles are given below:
7.9.2 The above results indicate that the soil is medium swelling nature. Hence, the excavated
G(C)9289
19
Page 19 of 136
Swelling Pressure (kg/cm²)
BH No Depth (m)
At Dry State At Natural Water Content
10 0.33 0.25
2 0.89 0.82
4 0.83 0.76
2
7 0.51 0.48
10 0.31 0.24
2 0.86 0.77
3 4 0.79 0.71
7 0.53 0.45
2 0.89 0.81
4 4 0.82 0.73
7 0.41 0.39
2 0.92 0.83
5 4 0.84 0.78
7 0.63 0.52
G(C)9289
20
Page 20 of 136
BH No Depth (m) Cc av (cm²/kg) mv (cm²/kg)
4 0.183 0.048 0.0222
7 0.109 0.024 0.0151
2 0.226 0.049 0.0256
4 4 0.185 0.040 0.0224
7 0.091 0.020 0.0130
2 0.234 0.051 0.0262
5 4 0.181 0.039 0.0220
7 0.082 0.018 0.0120
7.11.2 Graph of e log p curve is given in fig 6 to 22, settlement of square root of time is given
in fig 6a to 22a and e vs applied pressure in normal scale is given in fig 6b to 22b.
7.12.1 An overview of the results and their analysis has been presented in the form of soil profile
in fig. 2.
7.13.2 Presently the ground water samples can be used for construction purpose as per IS 456-
2000.
7.14.2 As the sulphate content is less than 0.2% Ordinary Portland Cement may be used for
7.15.1 The results of the Electrical Resistivity Tests (ERT1 to ERT3 ) has been analysed as given
below.
G(C)9289
21
Page 21 of 136
7.15.2 The electrical resistivity is calculated using the following expression :
2 S R
S = spacing of electrodes in m
7.15.3 The polar plot of the electrical resistivity vs measured in eight directions have been given
7.15.4 The resistivity measured (in ohm) at various spacings are given in Appendix D.
7.15.5 The values of electrical resistivity obtained from the polar plot are given below :
7.15.6 The above soil resistivity ranges between 25-50ohm-m. Hence, the soil is moderately
7.16.1 Laboratory CBR tests were conducted on the soil samples (about 30-50cm below the
ground level) collected from the site and conducted at maximum dry density obtained
from Modified Proctor density. The CBR tests were conducted under soaked state with
a surcharge weight of 5, 10 and 12.5kg. The results of tests are given below.
G(C)9289
22
Page 22 of 136
% CBR for Penetration with the
Modified Proctor Density surcharge weight of
test
Location
5kg 10kg 12.5kg
Maximum Optimum
Dry Moisture 2.5 5.0 2.5 5.0 2.5 5.0
Density Content mm mm mm mm mm mm
(g/cm3) (%)
7.17.1 Samples were collected form regular depths in the excavated trial pits. The laboratory test
7.18.1 The permeability by falling head method is obtained from the following relation
.r H
k log e 1
55. (t 2 t 1) H2
k = coefficient of permeability(cm/s)
G(C)9289
23
Page 23 of 136
H1 = Piezometric head at time t1
7.18.2 The coefficient of permeability ‘k’ determined at 3m depths at different boreholes has
7.19 Liquefaction
7.19.1 Liquefaction is a condition in sandy soil strata which occurs when the inherent shear
strength in the strata is reduced and the strata behaves like a liquid. This condition arises
mainly when the strata is subjected to accelerations during vibrations. Under vibrations,
the individual particles loose contact with each other and reach a weightless (Levitation)
state. Consequently, the shear strength of the strata reduces. When the strata is saturated,
the pore water pressure increases due to the acceleration and reduces the effective shear
strength. The magnitude of reduction in both cases depends upon the intensity of
acceleration and also on the insitu density. The above phenomena occur during
7.19.2 Normally, if the fines content (silt and clay fraction) of the soil is more than 35%,
liquefaction does not occur when the N values are more than 15.
7.19.3 At the present site, the corrected N values in the soil strata are generally in excess of 15
G(C)9289
24
Page 24 of 136
7.19.4 Such subsoil conditions are generally considered to be not susceptible to liquefaction.
7.19.5 Hence, the soil at the present site is not susceptible to liquefaction.
8.1.1 The parameters required for the design of foundation system for the proposed structure
are:
capacity of piles.
8.1.2 On the basis of the analysis of the results of investigations, the required design parameters
have been arrived at and these are given in paras 8.2 to 8.4.
b) Type of structure
8.2.2 As per the client’s information, the proposed project comprises of MSME buildings
8.2.3 For the above conditions, Isolated/Strip/Raft foundations can be adopted for the proposed
projects. If load transfer by structures is more than the bearing pressure recommended;
G(C)9289
25
Page 25 of 136
8.3 Isolated/Strip/Raft Foundations
8.3.1.1 The depth at which foundations should be laid will be governed by the following criteria.
c) Soil below the level of footings/foundations should have the requisite strength to
support the anticipated bearing pressures on the foundations without allowing the
8.3.2 Net allowable bearing pressure at 2, 3, 4, 5 and 6m depth from exising ground level are
provided.
8.3.3.1 An allowable settlement of 25/40/50/75mm has been considered to evaluate the allowable
8.3.3.5 The allowable bearing pressure at different depth for various widths and settlements are
G(C)9289
26
Page 26 of 136
given in the para 9.1.2.c.
8.4.1.1 The piles may be bored cast insitu piles. The boring may be done using augering (using
8.4.2.1 The load carrying capacity of different diameter piles are given in para 9.1.3.b.
8.4.2.2 As per Is 2911-2010, if L<2T; then the piles considered as short piles. The stiffness
factor (T) for various pile diameters vary between 2.63 to 3.96 and minimum length
of piles is 12 to 18m. Hence, the piles will primarily behave like long piles.
9.0 RECOMMENDATIONS
c) Allowable bearing pressure : for different depth and widths are given
below
G(C)9289
27
Page 27 of 136
Net Allowable Bearing Pressure for
Depth of Foundation Settlement different foundation width (t/m²)
from E G L (m) (mm)
1 2 3 4 5 $6m
75 11.5 12 12 12.5 13 14
50 9 10 11.5 13 13 14
3
40 8 8 11 12 13 14
25 4.5 5 5.5 6.5 8.5 10
75 18 18.5 19 19.5 20 21
50 13.5 14.5 15 16.5 18 21
6
40 12 13 14.5 16 17.5 21
25 7 8.5 9 9 12 13
G(C)9289
28
Page 28 of 136
Effective Diameter Load Uplift Depth of Lateral
length of Pile of Pile Carrying Capacity Fixity (m) Capacity (t)
(m) (mm) Capacity (t) (t)
Free Fixed Free Fixed
head head head head
Factor of safety (multiplier) can be taken as 2.5 for computing ultimate modulus
9.3 Note
9.3.1 The recommendations given in this report have been arrived at on the basis of design
parameters which have been judiciously adopted by giving due consideration to the results
decades in working in various types of soil and rock conditions all over India.
10.1 The soil of each strata has been described with name, colour etc. During excavation
any variation in the nature of the soil and its condition from those given in this Report
10.2 The excavated soil is fine grained and exhibits medium expansivity. It is therefore not
G(C)9289
29
Page 29 of 136
recommended for use as foundation backfill (refer para 7.10.1).
10.3 For excavation for the foundations, the excavation may be done with a slope of 1.5-
2vertical to 1horizontal upto a depth of 3m. Excavations beyond 3m should have suitable
10.4 Stiff Tie-beams connecting the columns in both directions may be provided which will
10.5 The site must have proper slopes and drainage system to drain out any pilferage of water/
rain water to avoid moisture water movement towards the foundation / underneath the
structures.
10.6 Is the site is being filled with external soil and for any filling; the filling may be done in
layers using non swelling soil. The filling may be done in layers of 25-30cm thick duly
10.7 It is suggested the load capacity of the pile be confirmed by a load test.
10.8 After reaching the required depth, care should be taken that the slush formed at the
bottom is minimum. The bentonite being used during piling should be as per IS 2911.
11.0 REFERENCES
11.1 A list of IS codes referred for providing the recommendations and that which might be
12.0 LIMITATIONS
12.1 This Geotechnical investigation has been carried out at locations in the site chosen by
the client as representing the entire site. The recommendations provided in this Report
are hence valid only for those test locations. However, if there is any change in sub-
soil conditions and properties at places between or beyond the chosen test locations,
Nagadi may be contacted for further actions. Fresh investigations will have to be
G(C)9289
30
Page 30 of 136
carried out at such locations.
M L SHANKAR
G(C)9289
31
Page 31 of 136
Appendix A
ANALYSIS FOR ALLOWABLE BEARING PRESSURE
Data
(i) Soil Properties :
c (kg/cm2) = 0.33 N = 13< ( (g/cm3) = 1.77
(ii) Depth of Foundation, D (m) = 200
(iii) Allowable Settlement, s (mm) = 75/50/40/25
B (m) 1 2 3 4 5 $6m
qs (t/m2) 11.2 11.5 11.8 12.1 12.4 13.0
From Settlement Criterion
as per IS 6403 q = 0.554 (N-3) {B+0.3/2B}²x Rw’ for 40mm settlement
N(Corrected Weighted) 9 11 14 16 19 21
B (m) 1 2 3 4 5 $6m
2
qs (t/m ) 7.01 7.3 9.14 10.3 12.4 13.7
The lower of the above must be adopted:
G(C)9289
32
Page 32 of 136
SETTLEMENT CALCULATION BASED ON CONSOLIDATION TEST
The total settlement of the foundation due to underlying compressible stratum (as Is 8009) is
given by:
S = {Cc / (1 + eo)} H. log10 {(Po +> P) /Po }
Where:
S = Settlement
Cc = Compression index
H = Thickness of compressible strata
Po = Original intensity of pressure acting at mid height of compressible stratum
>P = Increment in pressure due to the additional load imposed through
Foundation
eo = Original Void Ratio
Data
Depth of foundation = 200cm
Dimension of footing (assumed) = 200 x 200cm
Bulk density = 1.86gm/cc
Compression index Cc = 0.143
Initial void ratio eo = 0.57
Compressible strata (H) = 300cms
Po (1.8 x 350) = 0.459g/cm2
>P = {(qa (B x L)}/{(B+Z)(L+Z)}
Where:
qa = Allowable bearing pressure = 4.5t/m² = 0.45kg/cm²
B&L = Dimension of footing = 200 x 200cm
Z = depth below foundation level of mid height of compressible
stratum = 350cm
>P = 0.1469g/cm2
substituting the values in the above equation, we get
S = 32.92cm
Therefore, The calculated settlement for an allowable bearing pressure of 4.5t/m² is about
24mm which is less than 25mm. Hence, Safe.
G(C)9289
33
Page 33 of 136
CALCULATION FOR LOAD CARRYING CAPACITY OF PILE
Typical calculations for the pile capacity has been given hereunder for a pile of diameter 500mm.
For piles of other diameters, a similar procedure has been used to arrive at the recommended pile
capacities.
As per IS 2911 (Part 1/Sec 2) the Ultimate Pile Capacity is given by
Qu = End bearing + Skin friction = Ap Nc Cp + 3 " C As
where Ap = area of pile = 0.1953 m²
Nc = bearing capacity factor = 9
Cp = average cohesion at pile tip = 3kg/cm²
"= Adhesion factor in ith layer depending on the consistency of soil = 1upto 10m
depth, 0.435 upto 13m depth and 0.25 upto 16m depth
C= average cohesion for the ith layer = 0.3kg/cm² upto 10m depth, 1kg/cm² upto 13m
depth and 3kg/cm² upto 16m depth
As = surface area of pile in the ith layer = 14.139m² upto 10m depth (afer deducting 1m
as pile cap), 4.713m² upto 13m depth and 4.713m² upto 16m depth
substituting the values in the equation, we get
Qu = 53.02 + 42.42 + 20.03 + 35.35
= 150.82t
considering a FOS of 2.5
Qs = Qu / FOS = 150.82/2.5 = 60.33t
Therefore Adopt Qs = 60t
Uplift Capacity
Uplift Capacity is skin friction with a Factor of safety
Skin friction = 42.42 + 20.03 + 35.35
= 97.79t
considering a FOS of 3 we get
Uplift Capacity = 97.97/3 = 32.65t
Therefore adopt 30t
LATERAL PILE LOAD CAPACITY
G(C)9289
34
Page 34 of 136
A.1 Methodology
A.1.1 A typical calculation for the lateral pile load capacity has been given hereunder for a pile
of diameter ‘d’ = 500mm.
A.1.2 For determining the lateral pile load capacity, the depth of fixity of the piles or in other
words, the equivalent cantilever length of the pile, has to be first determined. The depth
of fixity is determined based on the modulus of horizontal subgrade reaction 0h value
which in turn is considered based on the relative density of the soil as observed in the
boreholes conducted, as per table 3 of appendix C of the BIS code IS:2911.
A.1.3 For evaluation of the modulus of horizontal subgrade reaction, the soil along the top
length of the pile has been considered on an average to be in a loose state based on the
range of N-values recorded within this length/depth.
A.1.4 The lateral pile load capacity is then determined as the horizontal force required for
causing the allowable horizontal deflection of the pile head when considering the pile as
a cantilever.
A.1.5 For calculation purposes, the concrete of pile has been considered to be of M25 grade.
A.1.6 For the determination of the lateral pile load capacity, the allowable horizontal deflection
of the pile head has been considered as 5mm based on the provisions of clause 7.4 of BIS
code IS:2911 (Part4) - 1985.
A.2 Evaluation of Depth of Fixity
A.2.1 Considering that the soil in the top of the pile is in a loose state (due to N values ranging
between 4 to 9), the modulus of horizontal subgrade reaction can be taken as 0.08kg/cm3
applicable for submerged conditions, as per table 3 of appendix C of the BIS code
IS:2911.
A.2.2 The stiffness factor is calculated using the following formula:
T = 5% (E . I /0h)
Where E is the elastic modulus and I is the moment of inertia of the pile section that has
to be determined by taking into account the flexural rigidity provided by the concrete.
A.2.3 The elastic modulus of concrete is determined as :
E 5000 f ck
G(C)9289
35
Page 35 of 136
Hence, E = 25,000 N/mm2 or 250,000kg/cm2
A.2.4 The moment of inertia of the pile section is determined as :
d4
I
64
Hence, I = 306796.16 cm4
A.2.5 For the above value of the modulus of horizontal subgrade reaction and flexural rigidity
of the concrete, the stiffness factor (T) works out to 2.49m. As per fig.2 of the Appendix
C of IS 2911 the depth of Fixity works out to
Zf = 4.76m (for free head condition)
Zf = 5.43m (for fixed head condition).
A.3 Determination of Lateral Pile Load Capacity
A.3.1 The horizontal deflection of the pile head, is determined by the following equations :
QL Z 3f
y (for free head condition)
3 E I
Ql Z 3f
y (for fixed head condition)
12 E I
A.3.2 Considering an allowable horizontal deflection of the pile head of 5mm, the lateral pile
load capacity works out to be :
QL = 1.07tons (for free head condition)
Ql = 2.87tons (for fixed head condition)
Therefore Adopt
QL = 1.05 tons (for free head condition)
Ql = 2.85 tons (for fixed head condition)
Note : The above calculation has been carried out by neglecting the contribution of the
reinforcement to the flexural rigidity of the pile, which will increase when the
contribution of the reinforcement is considered and can be further increased by
increasing the area of reinforcement provided in the pile. An increased flexural rigidity
implies a greater lateral pile load carrying capacity for the same allowable deflection.
G(C)9289
36
Page 36 of 136
Appendix B
G(C)9289
37
Page 37 of 136
Appendix C
G(C)9289
38
Page 38 of 136
Appendix D
ERT - 1
ERT - 2
ERT - 3
G(C)9289
39
Page 39 of 136
Appendix E
LIST OF IS CODES
Field Investigation
1. IS : 1498 - 1970 : Classification and identification of soils for general engineering
purposes (First Revision) (Amendment 2)
2. IS : 1892 - 1979 : Code of practice for sub surface investigations for foundations
(First revision)
3. IS : 2131 - 1981 : Method of Standard Penetration Tests for soils (First revision)
4. IS : 2132 - 1986 : Code of practice for thin walled tube sampling of soils (Second
revision)
Laboratory Tests
1. IS : 2720 - 1983 (Part 1) : Methods of test for soils: Preparation of dry soil samples
for various tests (Second revision)
2. IS : 2720 - 1980 (Part 2) : Method of test for soils: Determination of water content
(Second revision) Amendment 1
3. IS : 2720 - 1980 (Part 3/Sec 1) : Method of test for soils : Determination of
Specific Gravity : Fine grained soils. (First
revision)
4. IS : 2720 - 1980 (Part 3/Sec 2) : Method of test for soils : Determination of
Specific Gravity : Fine, Medium & Coarse
grained soils. (First revision).
5. IS : 2720 - 1985 (Part 4) : Method of test for soils : Grain size analysis (Second
revision)
6. IS : 2720 - 1985 (Part 5) : Method of test for soils : Determination of liquid and
plastic limit (Second revision)
7. IS : 2720 - 1977 (Part 40) : Methods of tests for soils: Determination of free swell
index of soils.
8. IS:2720(Part XVI):1979 : Methods of test for soils (Part XVI) Laboratory
determination of CBR
Foundation Construction
1. IS : 1080 - 1986 : Code of practice for design and construction of shallow
foundations on soils (other than raft, ring and shell) (Second
revision)
2. IS : 1904 - 1986 : Code of practice for design and construction of foundation in
soils: General requirements (Third revision)
3. IS 6403 - 1981 : Code of practice for determination of bearing capacity of
shallow foundations : First revision (Amendment 1)
4. IS 8009 - 1976 (Part 1) : Code of practice for calculation of settlements of
foundations : Shallow foundations subject to
symmetrical static vertical loads (Amendment 2)
5. IS 2911 (Part I to IV) : Design and construction of pile foundations.
G(C)9289
40
Page 40 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: 7.5m Term. Depth : 25.5m B.H. No. : 1
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 41 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: 7.5m Term. Depth : 25.5m B.H. No. : 1A
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
41 10.5 Brownish grey sandy silty clay
Page 42 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: 11.5m Term. Depth : 25.5m B.H. No. : 2
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 43 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: 11.5m Term. Depth : 25.5m B.H. No. : 2A
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
>100 13.5 Hard clay
(81/23cm)
>100 15.0 Hard clay 0 20 34 46 51 23
(99/20cm)
>100 16.5 Hard clay
(107/17cm)
>100 18.0 Hard clay
(50/12cm)
>100
(50/7cm) 19.5 Hard clay 0 24 32 44 51 22
>100
(50/14cm) 21.0 Hard clay
>100
(50/10cm) 22.5 Hard clay
>100
(50/6cm) 24.0 Hard clay 0 27 35 38 44 19
>100
(50/3cm)
25.5 Hard clay
*-Natural Bulk Density # -N Values (Observed)
G(C)9289
2A
Page 44 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: 12.5m Term. Depth : 19.5m B.H. No. : 3
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 45 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: 12.5m Term. Depth : 19.5m B.H. No. : 3A
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
>100 13.5 Hard clay 0 20 35 45 52 22
(95/23cm)
>100 15.0 Hard clay
(50/5cm)
>100 16.5 Hard clay 0 22 37 41 47 20
(50/3cm)
>100 18.0 Hard clay
(50/5cm)
>100
(50/2cm) 19.5 Hard clay 0 26 37 37 43 18
*-Natural Bulk Density # -N Values (Observed)
G(C)9289
3A
Page 46 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: 11.0m Term. Depth : 19.5m B.H. No. : 4
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 47 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: 11.0m Term. Depth : 19.5m B.H. No. : 4A
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
>100 13.5 Hard clay
(102/19cm)
>100 15.0 Hard clay 0 22 34 44 50 22
(121/19cm)
>100 16.5 Hard clay
(50/5cm)
>100 18.0 Hard clay 0 25 36 39 46 20
(50/10cm)
>100
(50/3cm) 19.5 Hard clay
*-Natural Bulk Density # -N Values (Observed)
G(C)9289
4A
Page 48 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: 8.0m Term. Depth : 21.0m B.H. No. : 5
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 49 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: 8.0m Term. Depth : 21.0m B.H. No. : 5A
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
>100 13.5 Hard clay 0 22 33 45 52 22
(89/25cm)
>100 15.0 Hard clay
(89/25cm)
>100 16.5 Hard clay 0 25 35 40 47 20
(89/25cm)
>100 18.0 Hard clay
(89/25cm)
>100
(89/25cm) 19.5 Hard clay 0 27 36 37 42 18
>100
(89/25cm) 21.0 Hard clay
Page 50 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: Not met Term. Depth : 3.0m T.P. No. : 1
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m) Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 51 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: Not met Term. Depth : 3.0m T.P. No. : 2
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m)
Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 52 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: Not met Term. Depth : 3.0m T.P. No. : 3
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m)
Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 53 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: Not met Term. Depth : 3.0m T.P. No. : 4
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m)
Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 54 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: Not met Term. Depth : 3.0m T.P. No. : 5
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m)
Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 55 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: Not met Term. Depth : 3.0m T.P. No. : 6
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m)
Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 56 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: Not met Term. Depth : 3.0m T.P. No. : 7
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m)
Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 57 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: Not met Term. Depth : 3.0m T.P. No. : 8
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m)
Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 58 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: Not met Term. Depth : 3.0m T.P. No. : 9
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m)
Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 59 of 136
Project: MSME buildings at SIPCOT Industrial Park, Vallam, Vadagal, Kanchipuram, Tamilnadu.
SOIL PROFILE
B. H. Location: Water Table: Not met Term. Depth : 3.0m T.P. No. : 10
N - Value# Atterberg In-situ Triaxial Test
Grain Size Analysis
Depth (m)
Soil Description
(%)
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
(%)
Plastic
(g/cm3)
Density
Cont (%)
Type
(kg/cm2)
c
(O)
N
Water
*
0.0 Ground level
Page 60 of 136
Page 61 of 136
BH 1 BH 2 BH 3 BH 4 BH 5
E.G.L
1 -7 2 -5 3 -7 4 -5 5 -4
2 U
1
U
1
U
1
U
1
U
1
-8 -7 -9 -9 -7
1 2 3 4 5
4 U
2 -16
U
2 -23
U
2 -24
U
2 -26
U
2 -24
24 ->100 ->100
(50/7cm) (50/6cm)
->100 ->100
26 (50/4cm) (50/3cm)
KEY
G(C)9289
Page 62 of 136
& '
!
" # $ !% " !%
Page 63 of 136
& '
!
" # $ !% " !%
Page 64 of 136
& '
!
" # $ !% " !%
Page 65 of 136
& '
!
" # $ !% " !%
Page 66 of 136
& '
!
" # $ !% " !%
Page 67 of 136
Page 68 of 136
Page 69 of 136
!
Page 70 of 136
!
Page 71 of 136
0.75
0.73
0.71
0.69
0.67
0.65
Void Ratio 'e'
0.63
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH1
Depth - 2m
Cc = 0.221
G(C) 9289
Page 72 of 136
0.1 kg/sq.cm
0.2 kg/sq.cm
0.4 kg/sq.cm
0.8 kg/sq.cm
1.6 kg/sq.cm
3.2 kg/sq.cm
6.4 kg/sq.cm
0.2
0.4
0.6
Settlement (mm)
0.8
1.2
1.4
1.6
1.8
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
6a
Page 73 of 136
0.74
0.72
0.70
0.68
0.64
Void Ratio 'e'
0.62
0.60
0.58
0.56
0.54
0.52
0.50
0 1 2 3 4 5 6 7
G(C) 9289
6b
Page 74 of 136
0.75
0.73
0.71
0.69
0.67
0.65
Void Ratio 'e'
0.63
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH1
Depth - 4m
Cc = 0.197
G(C) 9289
Page 75 of 136
0.1 kg/sq.cm
0.2 kg/sq.cm
0.4 kg/sq.cm
0.8 kg/sq.cm
1.6 kg/sq.cm
3.2 kg/sq.cm
6.4 kg/sq.cm
0.2
0.4
0.6
Settlement (mm)
0.8
1.2
1.4
1.6
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
7a
Page 76 of 136
0.75
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
7b
Page 77 of 136
0.69
0.67
0.65
0.63
0.61
Void Ratio 'e'
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH1
Depth - 7m
Cc = 0.099
G(C) 9289
Page 78 of 136
0.1 kg/sq.cm
0.2 kg/sq.cm
0.4 kg/sq.cm
0.8 kg/sq.cm
1.6 kg/sq.cm
3.2 kg/sq.cm
6.4 kg/sq.cm
0.2
0.4
Settlement (mm)
0.6
0.8
1.2
1.4
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
8a
Page 79 of 136
0.75
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
8b
Page 80 of 136
0.69
0.67
0.65
0.63
0.61
Void Ratio 'e'
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH1
Depth - 10m
Cc = 0.072
G(C) 9289
Page 81 of 136
0.1 kg/sq.cm
0.2 kg/sq.cm
0.4 kg/sq.cm
0.8 kg/sq.cm
1.6 kg/sq.cm
3.2 kg/sq.cm
6.4 kg/sq.cm
0.1
0.2
0.3
0.4
Settlement (mm)
0.5
0.6
0.7
0.8
0.9
1
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
9a
Page 82 of 136
0.75
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
9b
Page 83 of 136
0.75
0.73
0.71
0.69
0.67
0.65
Void Ratio 'e'
0.63
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH2
Depth - 2m
Cc = 0.227
G(C) 9289
10
Page 84 of 136
0.1 kg/sq.cm
0.2 kg/sq.cm
0.4 kg/sq.cm
0.8 kg/sq.cm
1.6 kg/sq.cm
3.2 kg/sq.cm
6.4 kg/sq.cm
0.2
0.4
0.6
Settlement (mm)
0.8
1.2
1.4
1.6
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
10a
Page 85 of 136
0.74
0.72
0.70
0.66
0.64
Void Ratio 'e'
0.62
0.60
0.58
0.56
0.54
0.52
0.50
0 1 2 3 4 5 6 7
G(C) 9289
10b
Page 86 of 136
0.73
0.71
0.69
0.67
0.65
Void Ratio 'e'
0.63
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
2
Applied Pressure 'p' (kg/cm )
Soil Sample Details
Borehole - BH2
Depth - 4m
Cc = 0.176
G(C) 9289
11
Page 87 of 136
0.1 kg/sq.cm
0.2 kg/sq.cm
0.4 kg/sq.cm
0.8 kg/sq.cm
1.6 kg/sq.cm
3.2 kg/sq.cm
6.4 kg/sq.cm
0.2
0.4
0.6
Settlement (mm)
0.8
1.2
1.4
1.6
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
11a
Page 88 of 136
0.75
0.73
0.71
0.69
0.67
0.65
0.63
av = 0.038 cm 2/kg
Void Ratio 'e'
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0 1 2 3 4 5 6 7
2
Applied Pressure 'p' (kg/cm )
Soil Sample Details
Borehole - BH2
Depth - 4m
G(C) 9289
11b
Page 89 of 136
0.69
0.67
0.65
0.63
0.61
Void Ratio 'e'
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH2
Depth - 7m
Cc = 0.103
G(C) 9289
12
Page 90 of 136
0.1 kg/sq.cm
0.2 kg/sq.cm
0.4 kg/sq.cm
0.8 kg/sq.cm
1.6 kg/sq.cm
3.2 kg/sq.cm
6.4 kg/sq.cm
0.2
0.4
0.6
Settlement (mm)
0.8
1.2
1.4
1.6
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
12a
Page 91 of 136
0.75
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
12b
Page 92 of 136
0.69
0.67
0.65
0.63
0.61
Void Ratio 'e'
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH2
Depth - 10m
Cc = 0.076
G(C) 9289
13
Page 93 of 136
0.1 kg/sq.cm
0.2 kg/sq.cm
0.4 kg/sq.cm
0.8 kg/sq.cm
1.6 kg/sq.cm
3.2 kg/sq.cm
6.4 kg/sq.cm
0.1
0.2
0.3
0.4
Settlement (mm)
0.5
0.6
0.7
0.8
0.9
1
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
13a
Page 94 of 136
0.75
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
13b
Page 95 of 136
0.75
0.73
0.71
0.69
0.67
0.65
Void Ratio 'e'
0.63
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH3
Depth - 2m
Cc = 0.224
G(C) 9289
14
Page 96 of 136
0.1 kg/sq.cm
0.2 kg/sq.cm
0.4 kg/sq.cm
0.8 kg/sq.cm
1.6 kg/sq.cm
3.2 kg/sq.cm
6.4 kg/sq.cm
0.2
0.4
0.6
Settlement (mm)
0.8
1.2
1.4
1.6
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
14a
Page 97 of 136
0.75
0.73
0.71
0.69
0.67
0.63
Void Ratio 'e'
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0 1 2 3 4 5 6 7
G(C) 9289
14b
Page 98 of 136
0.73
0.71
0.69
0.67
0.65
Void Ratio 'e'
0.63
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
2
Applied Pressure 'p' (kg/cm )
Soil Sample Details
Borehole - BH3
Depth - 4m
Cc = 0.183
G(C) 9289
15
Page 99 of 136
0.1 kg/sq.cm
0.2 kg/sq.cm
0.4 kg/sq.cm
0.8 kg/sq.cm
1.6 kg/sq.cm
3.2 kg/sq.cm
6.4 kg/sq.cm
0.2
0.4
0.6
Settlement (mm)
0.8
1.2
1.4
1.6
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
15a
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
15b
0.67
0.65
0.63
0.61
Void Ratio 'e'
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH3
Depth - 7m
Cc = 0.109
G(C) 9289
16
0.2
0.4
Settlement (mm)
0.6
0.8
1.2
1.4
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
16a
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
16b
0.73
0.71
0.69
0.67
0.65
Void Ratio 'e'
0.63
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH4
Depth - 2m
Cc = 0.226
G(C) 9289
17
0.2
0.4
0.6
Settlement (mm)
0.8
1.2
1.4
1.6
1.8
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
17a
0.73
0.71
0.69
0.67
0.65
av = 0.049 cm 2/kg
0.63
Void Ratio 'e'
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0 1 2 3 4 5 6 7
2
Applied Pressure 'p' (kg/cm )
Soil Sample Details
Borehole - BH4
Depth - 2m
G(C) 9289
17b
0.71
0.69
0.67
0.65
Void Ratio 'e'
0.63
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
2
Applied Pressure 'p' (kg/cm )
Soil Sample Details
Borehole - BH4
Depth - 4m
Cc = 0.185
G(C) 9289
18
0.2
0.4
Settlement (mm)
0.6
0.8
1.2
1.4
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
18a
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
18b
0.67
0.65
0.63
0.61
Void Ratio 'e'
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH4
Depth - 7m
Cc = 0.091
G(C) 9289
19
0.2
0.4
Settlement (mm)
0.6
0.8
1.2
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
19a
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
19b
0.71
0.69
0.67
0.65
Void Ratio 'e'
0.63
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
2
Applied Pressure 'p' (kg/cm )
Soil Sample Details
Borehole - BH5
Depth - 2.0m
Cc = 0.234
G(C) 9289
20
0.2
0.4
Settlement (mm)
0.6
0.8
1.2
1.4
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
20a
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
20b
0.71
0.69
0.67
0.65
Void Ratio 'e'
0.63
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
2
Applied Pressure 'p' (kg/cm )
Soil Sample Details
Borehole - BH5
Depth - 4m
Cc = 0.181
G(C) 9289
21
0.2
0.4
0.6
Settlement (mm)
0.8
1.2
1.4
1.6
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
21a
0.73
0.71
0.69
0.67
0.65
0.61
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0 1 2 3 4 5 6 7
2
Applied Pressure 'p' (kg/cm )
Soil Sample Details
Borehole - BH5
Depth - 4m
G(C) 9289
21b
0.67
0.65
0.63
0.61
Void Ratio 'e'
0.59
0.57
0.55
0.53
0.51
0.49
0.47
0.45
0.1 1 10
Applied Pressure 'p' (kg/cm 2)
Soil Sample Details
Borehole - BH5
Depth - 7m
Cc = 0.082
G(C) 9289
22
0.2
0.4
0.6
Settlement (mm)
0.8
1.2
1.4
1.6
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0 18.0 20.0
G(C) 9289
22a
0.73
0.71
0.69
0.65
0.63
0.61
0.59
0.57
0.55
0 1 2 3 4 5 6 7
G(C) 9289
22b
23
24
25
26
27
28
29
30
31
32
33
34
35
36