Professional Documents
Culture Documents
Week (04)
A building has the following U values and surface areas for various components of a building’s fabric:
Element Area (m2) U value (W/m2K)
Floor 324 0.45
Roof 324 0.28
Glazing 60 4.5
External Door 8 2.0
External walls 378 0.75
Assume the following: The building experiences 3 air changes per hour, the building volume = 2268
m3, the internal design temperature is 21⁰C, and the external design temperature is -3 ⁰C. For the
building, use a heavy weight building according to Lebanese Building Guideline. Also, use Bekaa
climate degree day provided in the posted climatic zoning of Lebanon if needed.
U value Temperature
Element Area (m2) Heat Loss (W)
(W/m2K) Difference (°C)
2. Determine the heating plant output for an internal design dry resultant temperature of 21°C for
the following building heating systems:
b- Using the following equations for option b- LTHW panel radiator system:
c- Using the following equations for option c- High Temperature radiant strip system:
The required output of the high temperature radiant strip system is about considerably lower (about
22KW) than that of forced warm air system with radiator system in middle.
The simple method based on indoor air temperature produces a plant output close in magnitude to
that required for the LTHW panel radiator system (with 3Kw difference).
The simple ‘air temperature’ method is acceptable for sizing standard wall radiator heating systems.
‘F1 and F2’ method should be used when designing systems which are either 100% convective or
almost 100% radiative.
a- Continuous Operation:
E=73,232.16 /24 x 2354 x 24 x 1 / 0.85 = 202,810,005.45 KWH
b- Week day operation for 12 hours:
Correction factor for length of working week= 1.00
Correction factor for length of working day= 1.02
Correction factor for response of building and plant= 0.85
E=73,232.16 /24 x 2354 x 24 x 1.0 x 0.85 x 1.02 / 0.85 = 175,836,274.73 KWH.
Question-02:
2- The sensible chilled ceiling ratio R=50%, the DV supply temperature 19-20 (°C), the chilled
ceiling temperature 16.5 (°C) and supply mass flow rate = 75x30/8/1000 =0.28125 kg/s.