Weekly Progress Report #30
Weekly Progress Report #30
Approved
PERTAMINA EP
Approved
Rev. Date Description Prepare By Checked By
By
CONTRACTOR
PO NO. 4500196323
PROJECT PROGRESS REPORT PERIOD #30
FROM DATE 11 Oct 2021
PENGADAAN POMPA RECIPROCATING API 674 UNTUK AREA UNTIL DATE 15 Oct 2021
SPU-E DAN SPU-F SANGASANGA FIELD NO. OF PAGES 2
1. EXECUTIVE SUMMARY
PO from Pertamina EP Asset 5: 16 December 2020
Kick Off Meeting: 17 December 2020
Current Status: Pump Only Stage
2. PROGRESS SUMMARY
Progress Report
Period Report : 11 Oct – 15 Oct 2021
Progress Plan Accumulative: 88.33%
Progress Actual Accumulative: 86.11%
Deviasi : -2.22%
3. ACTIVITIES THIS PERIOD
2.1 Unit Engineering and Design 10.00% 15 100% 10.00% 10.00% 0.00%
2.2 Drawing 10.00% 45 100% 10.00% 10.00% 0.00%
6. AREA CONCERNS
1. Dokumentasi untuk beberapa Part terlampir.
7. ATTACHMENT
1. S-Curve
2. Berikut Dokumentasi untuk Unit Assembly Stage
S-Curve
100,00%
90,00%
80,00%
70,00%
60,00%
PROGRESS
50,00%
40,00%
30,00%
20,00%
10,00%
0,00%
W-2 W-3 W-4 W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4 W-5 W-1 W-2 W-3 W-4 W-1 W-2 W-3 W-4
Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21
TIME