Risk Rating Matrix

Severity
Probability 5 - Catasthropic 4 - Critical 3 - Major 2- Moderate 1 - Minor
5 - Frequent 25 20 15 10 5
4 - Probable 20 16 12 8 4
3 - Occassional 15 12 9 6 3
2 - Remote 10 8 6 4 2
1 - Improbable 5 4 3 2 1

Risk Rating (Probability X Severity) Risk Acceptance Authority


1 to 4 (Low) Risk is tolerable (Manage by leadman and supervisor)

5 - 9 (Medium) Risk requires approval by supervisor, department head and safety officer

10 - 25 (High) Risk requires the approval of plant manager

Severity - Potenetial Consequences


Public
People Property Damage Environmental Impact
Image/Reputation
Offsite impact requiring Government
Catasthropic Fatality, Multiple Major Incidents > Php. 1,000, 000.00 remediation Intervention

> Php. 250,000.00 - Php. Onsite impact requiring


Critical Permanent impairment, long term injury/illness
1,000, 000.00 remediation
Media Intervention

> Php. 10,000.00 - Php. Release at/above reportable


Major Lost, Restricted work 250, 000.00 limit Owner Intervention

> Php. 1,000.00 - Release below reportable Community or local


Moderate Medical Treatment Php. 10, 000.00 limit attention
Php. 1,000.00 and Small chemical release
Minor First Aid below contained onsite Individual Complaint

Probability
Frequent Expected to occur during task/activity 9/10
Probable Likely to occur during task/activity 1/10
Occassional May occur during the task/activity 1/100
Remote Unlikely to occur during the task/activity 1/1,000
Improbable Highly unlikely to occur, but possible during task/activity 1/10,000