Mechanical and Plumbing Works General Notes For All Mechanical and Plumbing Works
Mechanical and Plumbing Works General Notes For All Mechanical and Plumbing Works
Supplying of materials shall not be done before obtain approval on the materials type, Brand , Color
4 also the contractor should provide certificate of origin and tests result certificate for the supplied
materials
The Contractor should Submit Builder Drawing, Shop Drawing , Coordination Drawings and Obtain
8 approval on it before start any Works in the site.
9 The Contractor should submit as built Drawings for all the works
The Contractor should Submit Material Submit for all the items mentioned in the BoQ , and Obtain
approval on it before supplying any materials , and materials submittal shall include all technical
10 data sheet , Compliance statement to Iraqi standard , specifications .
The Final Location , color , brand of All Equipment's should be coordinate and approved by
11 Engineer
Supply, install, test and commission on the following items including connection to ductworks,
refrigeration pipes, electrical connection, thermostats, controls , drain pipes, fixing in position,
complete with all needed.
The Contractor should submit ESP calculations for approval for All HAVC Units ( Ducted Concealed ,
Package Unit , Fans , Energy Recovery Units , Pressurization Fans ,…etc. .) and shall not start any
supplying for any item without approval on these Calculations.
HVAC Ductwork complete with, Volume control damper For all branch ,turning vanes, stiffeners,
splitter dampers, test holes, branch, openings, etc.
All air Outlets and Dampers should be Flowtech - UAE origin ( Grill , Diffusers, Volume control
damper , fire Damper , Motorized Damper , Slot linear diffuser , Bar grill, Louver , sand trap ,..etc. .)
Page 1 of 3
Mechanical BoQ.
Supply, install, test and commission Decorative split Invertor AC units and shall be reversible cycle
(heat pump) Split units Systems with Capacities as mentioned below , Tosot , complete with all
connection to refrigeration pipes, electrical connection, thermostats, controls , drain pipes, fixing in
position, flexible connection to duct,..etc.. , the Ducting size , air Outlet ,... etc. should be design
according to ASHARE and SMACNA Instruction , and the final color and shape and location of the
Air Outlet should as per Site Engineer's instructions.
1.1 Indoor /outdoor AC unit 18 MBH - Decorative split - Wall Mounted 5.0 No.
1.2 Indoor /outdoor AC unit 24 MBH - Decorative split - Wall Mounted 2.0 No.
1.3 Indoor /outdoor AC unit 24 MBH - Decorative split - Cassette type 1.0 No.
1.4 Indoor /outdoor AC unit 36 MBH - Decorative split - Cassette type 4.0 No.
1.5 Indoor /outdoor AC unit36MBH - Decorative split -Ducted type for swimming pool 1.0 No.
Dehumidefire for swimming Pool , the work include submit calculation for Dehumidifier and obtain
1.6 approval from engineer before start any supplying or work. 1.0 No.
Ventilation
Supply and install fans as specifications and as shown in the drawings and complete with all
needed. 0
Plumbing Works
Packaged cold water lifting pump set 32 IMP.GPM @ 25 M Head comprising one duty and one
standby pumps including all pipework, interconnections, valves, drains and electrical connections
1 as detailed in the specification and shown on drawings. 1.0 Set
Supply and install Insulated Pressed Sectional GI tanks 3.0X1.0X1.0 With insulation 20-30 MM as
specification and Site engineer instructions and shown on the drawings ,complete with all
2 connection, inlet, outlet, vent and cover, shaded, , etc. … all as specification and shown on the 1.0 No.
drawings .
Supply, install, connect and test for Booster Pump Set ( 1.4 l/s @ 20 M head ) one duty and one
stand by ,complete with piping system, valves ,strainer, electrical panel and electrical connections,
3 steal base plate and Alum. Louvered box for pump protection, complete as specification and 1.0 Set
drawings.
Supply, install, connect and test Hot Water Circulation Pump Set (0.35 l/s @ 15 m head) one duty
and one stand by ,complete with piping system, valves ,strainer, electrical panel and electrical
4 connections, steal base plate as specification and drawings. 1.0 Set
Supply, install, connect and test Electrical Heater (400 liter , 3kw ) according to standard
specification ,complete with piping system, Safety valve s, valves ,strainer, electrical panel and
5 electrical connections, steal base as specification and drawings. 1.0 No.
Supply, install, connect, insolate and test PPR for cold and hot water system including all fittings
and valves , Insulations according to the Standard Specifications , accessoieries and support 0
Water meter as shown in the drawing complete with water meter chamber , valve , accessories
12 ,..etc. 1.0 no.
Page 2 of 3
Mechanical BoQ.
Drainage System
Construct solid blocks Sewerage manhole complete with waterproofing and 40x40 cm Heavy duty
1 cover 40x40 cm as shown on the drawings. 1.0 no
Construct solid blocks Sewerage manhole complete with waterproofing and 60x60 cm Heavy duty
2 cover 60x60 as shown on the drawings. 4.0 no
Construct Gully trap manhole complete with waterproofing and 30x30 cm Heavy duty cover 30x30
3 as shown on the drawings. 2.0 no
Construct Pressure manhole complete with waterproofing and 60x60 cm Heavy duty cover 60x60
4 cm as shown on the drawings. 1.0 no
Construct solid block cesspol according to muncipilaty's Instructions complete with all connection,
5 inlet, outlet, vent and cover, etc … with dimesnions as shown in the drawings 1.0 No.
supply,install,connect and test internal drainage system (soil, waste ,vent) from UPVC pipes and
fittings from all sanitary fixtures upto manholes including all pipes and fittings as specified and as
shown on drawings.
Supply ,install ,connect and test rain water outlet RWO 200x200 x 4inch with chrome platted, brass
14 cover & strainer with all needed clean out points as specified and as shown on the drawings. 2.0 No.
Supply ,install ,connect and test rain water outlet RWO 100x100 x 3inch with chrome platted, brass
15 cover & strainer with all needed clean out points as specified and as shown on the drawings. 1.0 No.
Fixture :
Install ,connect and test the below mentioned fixture complete with all required works and
accessories , Mixer , angle valves , flexible pipe , bottle trape , pipes,...etc , to connect it to the
water supply and drainage networks and as specified and as shown on the drawings.
The Fixtures and Mixers should be Supplied By Owner , the Contractor to supply all required
accessories , Piping , Valves ,..etc.
Page 3 of 3