You are on page 1of 4

MATRIX PETROCHEM NIGERIA LTD

SOP for Blender : Lubricant Guidelines

Standard operating procedure of Blender used for blending in Lubricant


manufacturing.

1.0 OBJECTIVE
To lay down the cleaning and operation procedure for blender.

2.0 SCOPE
This procedure is applicable to blender used for blending.

3.0 RESPONSIBILITY
Blender/Officer Production
Executive Quality Assurance

4.0 ACCOUNTABILITY
Head Production

5.0 PROCEDURE
5.1 Cleaning procedure for product changeover
5.1.1 Ensure that 'To be Cleaned' label is put on the equipment
5.1.2 Ensure that the mains are switched 'OFF'.
5.1.3 Ensure that the bunker is transferred to respective OHCR room.
5.1.4 Clean the drive unit with moist clean duster followed by a dry clean duster.
5.1.5 Clean and ensure the cleanliness of the equipment surrounding the area.
5.1.6 After completion of compression, loosen the clamp and separate the Bunker
(Cage/mixing bowl) from material transfer gravity pipe.
5.1.5 Ensure that the bottom butterfly valve of the bunker is closed.
5.1.8 Take bunker and material transfer gravity pipe to the washing area.
5.1.9 Open the top lid of the bunker,
wash inside outside of the bunker, material transfer gravity pipe and top lid with
40 liters running potable water
followed by 2 liters of 2% non-ionic detergent solution using longhand hard nylon
bristle brush.
5.1.10 Rinse all above parts with 80 liters running potable water to remove
detergent.
5.1.11 Finally rinse all above parts with 80 liters Purified water.
5.1.12 Clean the material transfer system as per SOP under head cleaning procedure
for product changeover.
5.1.13 Visually ensure the cleanliness of the equipments.
5.1.14 Intimate QA to collect wash water sample and wait for approval.
5.1.15 On receipt of QA approval, dry all the parts using filtered compressed air/
hot air blower.
5.1.16 Remove ‘To be cleaned’ label and affix duly signed ‘Cleaned’ label.
Note:
The cleaning of the equipment remains valid for 48 hours. If the equipment is not
used within 48 hours then it should be re-cleaned as per
above procedure starting from step 5.1.4.
5.2 Cleaning procedure for a batch to batch changeover
5.2.1 Ensure that ‘To be Cleaned’ label is put on the equipment.
5.2.2 Ensure that the mains are switched ‘OFF ’.
5.2.3 Ensure that the bunker is transferred to the respective room.
5.2.4 Clean the drive unit with a dry clean duster.
5.2.5 Clean the material transfer system as per SOP under the head ‘Cleaning
procedure for a batch to batch changeover’.
Note: The cleaning of the equipment remains valid for 48 hours. If the equipment is
not used within 48 hours then it should be re-cleaned as
per
cleaning procedure for product changeover.
5.3 Operating procedure
5.3.1 Checks and precautions
5.3.1.1 Wear hand gloves, overcoat and nose mask during the sifting operation.
5.3.1.2 Ensure that safety railing is locked properly.
5.3.1.3 Ensure that the bottom butterfly valve of the bunker is closed.
5.4 Operating procedure
5.4.1 Remove ‘Clean’ label and affix it in the BMR.
5.4.2 Affix ‘Under Process’ label on the equipment.
5.4.3 Fix the bunker to drive unit with the fly nut. Ensure that the fly nuts are
properly locked.
5.4.4 Fix the material transfer system on the top open part (material charging
port) of the bunker.
5.4.5 Switch ‘ON’ the mains and operate the material transfer system as per SOP to
charge the material to be lubricated into the bunker.
https://www.pharmaguideline.com/2010/12/sop-for-for-cage-blender.html
6/24/2021
SOP for Cage Blender : Pharmaceutical Guidelines

5.4.6 After completion of the material charging, remove aside the pneumatic
conveying system.
5.4.5 Fix bunker lid in place of the material transfer system and lock with fly nut
Ensure that the lid is securely locked.
5.4.8 Lift the bunker by operating Push button marked `UP’.
5.4.9 Remove bunker trolley and lock the safety railing properly.
5.4.10 Set the timer for total blending time as per BMR.
5.4.11 Start the blender by operating push button marked `Blender ON’ to rotate the
bunker.
5.4.12 After completion of the blending cycle, bring the bunker in balanced
position by operating in inching mode.
5.4.13 Unlock the safety railing, insert bunker trolley and take down the bunker.
Restore it on the bunker trolley.
5.4.14 Unlock the fly nut and separate the bunker from the drive unit.
5.4.15 Weigh the bunker, note down the reading and transfer it to concerned room or
granules quarantine awaiting compression.
5.4.16 Remove `Under process’ label and affix ‘To be cleaned’ label.
6.0 ABBREVIATIONS
6.1 BMR - Batch Manufacturing Record
6.2 SOP - Standard Operating Procedure
Ankur Choudhary is India's first professional pharmaceutical blogger, author and
founder of Pharmaceutical Guidelines, a widely-read
pharmaceutical blog since 2008. Sign-up for the free email updates for your daily
dose of pharmaceutical tips.
Need Help: Ask Question

Copyright © 2008-2021
Pharmaceutical Guidelines
Setup

Terms of Use

FAQ

https://www.pharmaguideline.com/2010/12/sop-for-for-cage-blender.html

You might also like