DAFTAR HARGA SATUAN BAHAN

PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK


LOKASI : JAKARTA

NO JENIS MATERIAL/BAHAN HARGA SATUAN

Bata ringan ex Powerblock / setara Rp. 567,610.00 / m3


Pasir urug Rp. 217,030.00 / m3
Pasir Pasang Rp. 233,720.00 / m3
Batu pecah Rp. 217,030.00 / m3
Split 2/3 . Rp. 272,670.00 / m3
Beton Fc 15 Mpa Slump 14 +/- 2 cm Rp. 688,920.00 / m3
Beton K 125 Slump 12 +/- 2 cm Rp. 612,130.00 / m3
Beton K 350 Slump 12 +/- 2 cm Rp. 723,420.00 / m3
Beton K 300 Slump 12 +/- 2 cm Rp. 701,160.00 / m3
Beton K 450 Slump 12 +/- 2 cm Rp. 812,460.00 / m3
Beton K 500 Slump 12 +/- 2 cm Rp. 834,720.00 / m3
Besi Beton Rp. 7,570.00 / kg
Wire mesh M 6 ( 150 x 150 mm ) Rp. 24,700.00 / m2
Wire mesh M 8 ( 150 x 150 mm ) Rp. 49,170.00 / m2
Wire mesh M 10 ( 150 x 150 mm ) Rp. 68,892.00 / m2
Homogeneous tile Niro Granite 40 x 40 cm Rp. 200,330.00 / m2
Homogeneous tile Niro Granite 40 x 40 cm, EX Indogress White Onyx Rp. 267,110.00 / m2
Homogeneous tile Niro Granite 40 x 40 cm, EX Indogress Zincronium Rp. 220,370.00 / m2
Homogeneous tile Niro Granite 60 x 60 cm, EX Indogress Bianco damasco Rp. 220,370.00 / m2
Homogeneous tile Niro Granite 60 x 60 cm, EX Indogress white onyx Rp. 394,250.00 / m2
Homogeneous tile Niro Granit 60 x 60 cm DORATO ANTICO LAPATTO polish Rp. 257,090.00 / m2
Homogeneous tile Niro Granit 60 x 60 cm unpolish Rp. 252,420.00 / m2
Homogeneous tile Niro Granit 1200 x 600 mm polish Rp. 552,920.00 / m2
Homogeneous tile Indogres 1200 x 600 mm polish Rp. 557,590.00 / m2
Homogeneous tile Niro Granit 800 x 800 mm polish Rp. 890,370.00 / m2
Homogeneous tile Niro Granit 600 x 600 mm polish Rp. 341,370.00 / m2
Homogeneous tile Indogress 800 x 800 mm polish type Zicornium Rp. 375,020.00 / m2
Homogeneous tile Indogress 100 x 800 mm polish type topaz Rp. 180,300.00 / m2
Homogeneous tile Indogress 60 x 60 cm unpolish type topaz Rp. 278,860.00 / m2
Granit hitam nero 800 x 1000 Rp. 1,193,090.00 / m2
Keramik lantai ex Mulia (GOL C) 300 x 300 mm Rp. 85,140.00 / m2
Keramik lantai ex Mulia 400 x 400 mm, digital glossy murble premium Rp. 65,110.00 / m2
Keramik lantai ex Mulia 200 x 200 mm, matt white Rp. 64,550.00 / m2
Keramik lantai ex Mulia 600 x 600 mm MATT RUSTIC Rp. 141,740.00 / m2
Stepnosing keramik 10 x 20 cm ex Roman Rp. 11,130.00 / bh
Marmer ex Ujung Pandang ( type Tuscany Cream ) Rp. 667,770.00 / m2
Batu Andesit polos 40 x 40 cm, tebal 18 mm Rp. 170,280.00 / m2
Karpet ex Balance Rp. 550,910.00 / m2
Thinbed PMT 101 ex Pratama Mortar Rp. 63,440.00 / 50 kg
Grouting nat PMG 700 ex Pratama Mortar Rp. 11,130.00 / 1 kg
Kanstin Car Stopper uk 60 x 30 x 15 cm (K-300) Rp. 61,210.00 / bh
UPAH KERJA

NO JENIS MATERIAL/BAHAN HARGA SATUAN (Rp) HSAT RC (Rp.)

A TANAH & STRUKTUR :


Pembersihan site + buangan keluar 2,230.00 / m2 2,000
Galian tanah s/d kedalaman 150 cm 55,650.00 / m3 50,000
Galian tanah kedalaman 150 s/d 300 cm 36,730.00 / m3 33,000
Galian tanah manual 38,950.00 / m3 35,000
Galian tanah kedalaman 300 s/d 450 cm 41,180.00 / m3 37,000
Galian tanah kedalaman 450 s/d 600 cm + buang 50,080.00 / m3 45,000
Urugan tanah bekas galian 22,260.00 / m3 20,000
Buangan tanah keluar site 11,130.00 / m3 10,000
Urugan tanah bekas galian 5,560.00 / m3 5,000
Upah pancang mini pile 25 x 25 cm 12,240.00 / m3 11,000
Upah pancang Spun ø 45 cm 45,630.00 / m' 41,000
Pasang Bouwplank 2,780.00 / m' 2,500
Urugan tanah bekas galian + pemadatan 16,690.00 / m3 15,000
Pemadatan tanah (stamper) 9,740.00 / m3 8,750
Pemadatan tanah (stamper) 13,360.00 / m2 12,000
Pemadatan pasir 3,340.00 / m3 3,000
Pemadatan batu pecah, tebal 20 cm 16,690.00 / m3 15,000
Pemadatan batu pecah, tebal 10 cm 33,390.00 / m3 30,000
Pemadatan batu pecah, tebal 10 cm 66,780.00 / m3 60,000
Potong tiang pancang 450 x 450 mm 84,100.00 / bh 75,563
Potong tiang pancang ø 30 cm 19,480.00 / bh 17,500
Potong tiang pancang ø 50 cm 33,390.00 / bh 30,000
Bobok kepala tiang bor pile dia 50 cm 82,530.00 / bh 74,156
Bobok kepala tiang bor pile dia 60 cm 115,290.00 / bh 103,585
Bobok kepala tiang bor pile dia 80 cm 195,000.00 / bh 175,360
Bobok kepala tiang bor pile dia 110 cm 518,850.00 / bh 466,194
Bobok kepala tiang bor pile dia 120 cm 605,340.00 / bh 543,900
Potong tiang pancang 45 x 45 cm 44,520.00 / bh 40,000
Potong tiang pancang 20 x 20 cm 27,820.00 / bh 25,000
Bobok beton 417,360.00 / m3 375,000
Gelar wire mesh (1 lapis) 1,390.00 / m2 1,250
Gelar wire mesh (2 lapis), M6 3,670.00 / m2 3,300
Gelar wire mesh M 6 (1 lapis) 1,670.00 / m2 1,500
Gelar wire mesh M 8 (1 lapis) 2,340.00 / m2 2,100
Besi beton ø 16 s/d 32 mm - / kg
Besi beton ø 8 s/d 13 mm 420.00 / kg 375
Pasang Bouwplank 2,780.00 / m' 2,500
Pasang angkur & grouting 13,360.00 / bh 12,000
Bekisting tie beam (batako) 10,020.00 / m2 9,000
Bekisting Praktis 3,900.00 / m' 3,500
Bekisting kolom (persegi) 16,690.00 / m2 15,000
Bekisting kolom exposed (persegi) 23,370.00 / m2 21,000
Bekisting kolom (bulat) 28,940.00 / m2 26,000
Bekisting balok 17,250.00 / m2 15,500
Bekisting balok exposed 21,700.00 / m2 19,500
Bekisting plat 16,140.00 / m2 14,500
Bekisting plat exposed 19,480.00 / m2 17,500
Bekisting shear wall/ retaining wall 18,360.00 / m2 16,500
Bekisting shear wall/ retaining wall exposed 21,700.00 / m2 19,500
Bekisting tangga 19,200.00 / m2 17,250
Bekisting anak tangga 8,350.00 / m' 7,500
Bekisting leher kolom 30,610.00 / m2 27,500
Bekisting list plank 25,600.00 / m2 23,000
Cor kolom (dgn TC) 19,480.00 / m3 17,500
Cor pile cap & tie beam (dgn TC) 13,910.00 / m3 12,500
Cor plat (dgn pompa) 16,690.00 / m3 15,000
Cor balok (dgn pompa) 16,690.00 / m3 15,000
Cor Pondasi Besar (50 m3 ke atas) 13,910.00 / m3 12,500

Cor Bored Pile 66,780.00 / m3 60,000


UPAH KERJA

NO JENIS MATERIAL/BAHAN HARGA SATUAN (Rp) HSAT RC (Rp.)


Cor beton lantai kerja 44,520.00 / m3 40,000
Cor beton site mix (klm & blk praktis) 87,920.00 / m3 79,000
Membuat talang cor 8,350.00 / m' 7,500
Adukan beton site mix 77,910.00 / m3 70,000
Site clearing 2,780.00 / m2 2,500
Bongkar bangunan existing 111,300.00 / m2 100,000
Pengukuran 2,780.00 / m' 2,500
Striping tanah 20 cm 5,560.00 / m2 5,000
Buang tanah ke luar site 11,130.00 / m3 10,000
Galian tanah pile cap/ tie beam 7,790.00 / m3 7,000
Galian basement 16,690.00 / m3 15,000
Bongkar sub base parkir 16,690.00 / m2 15,000
Urugan tebar pasir/ sirtu 9,740.00 / m3 8,750
Pasang pondasi batu kali kosong 33,390.00 / m3 30,000
Pasangan batu kali 44,520.00 / m3 40,000
Pasang Expantion joint 16,690.00 / m' 15,000
Alat bantu Expantion joint 2,780.00 / m' 2,500

B PEKERJAAN FINISHING

Pasang pondasi batu kali 38,950.00 / m3 35,000


Pasang lantai batu alam 22,260.00 / m2 20,000
Pasang lantai batu alam (kombinasi) 38,950.00 / m2 35,000
Pasang lantai granito 8,350.00 / m2 7,500
Pasang lantai marmer 60 x 120 cm termasuk poles 166,940.00 / m2 150,000
Pasang lantai granit 60 x 120 cm termasuk poles 194,770.00 / m2 175,000
Pasang lantai keramik 20 x 20 cm 22,260.00 / m2 20,000
Pasang lantai keramik 45 x 45 cm 22,260.00 / m2 20,000
Pasang lantai Homogeneus 60 x 60 cm 38,950.00 / m2 35,000
Pasang lantai Mosaic 20,030.00 / m2 18,000
Pasang lantai Homogeneus 40 x 40 cm 16,690.00 / m2 15,000
Pasang lantai keramik 30 x 30 cm 16,690.00 / m2 15,000
Pasang lantai keramik 40 x 40 cm 24,490.00 / m2 22,000
Pasang lantai keramik tangga 23,370.00 / m2 21,000
Pasang paving block (lengkap) 14,470.00 / m2 13,000
Perataan tanah u/ paving block 2,780.00 / m2 2,500
Pasang conblock 8,350.00 / m2 7,500
Pasang grass block 8,350.00 / m2 7,500
Pasang paving block 8,350.00 / m2 7,500
pemadatan conblock 3,340.00 / m2 3,000
pemadatan grass block 3,340.00 / m2 3,000
pemadatan paving block 3,340.00 / m2 3,000
Pasang lantai parquet 72,340.00 / m2 65,000
Trowel lantai 5,560.00 / m2 5,000
Screed lantai 8,070.00 / m2 7,250
Screed lantai tangga 8,350.00 / m2 7,500
Pasang natural stone 33,390.00 / m2 30,000
Buat gutter 50 x 100 mm 11,130.00 / m' 10,000
Pasang border lantai marmer + poles 33,390.00 / m' 30,000
Pasang border batu alam 8,900.00 / m' 8,000
Pasang nosing granit tangga + poles 13,910.00 / m' 12,500
Grouve nosing granit 11,130.00 / m' 10,000
Pinggulan marmer 27,820.00 / m' 25,000
Pasang plint marmer 13,910.00 / m' 12,500
Benangan (sudutan) 8,350.00 / m' 7,500
Bevel kaca cermin 16,690.00 / m' 15,000
Pasang plint + tali air 6,680.00 / m' 6,000
Pasang step nosing keramik 10 x 30 cm 8,900.00 / m' 8,000
Buat plint skonengan 2,230.00 / m' 2,000
Pasang joint filler + sealant 5,840.00 / m' 5,250
Pasang screed dinding 8,010.00 / m2 7,200
UPAH KERJA

NO JENIS MATERIAL/BAHAN HARGA SATUAN (Rp) HSAT RC (Rp.)


Acian dinding bata termasuk sudutan 6,680.00 / m2 6,000
Plester dinding + acian 18,920.00 / m2 17,000
Sudutan 8,350.00 / m2 7,500
Pasangan dinding bata 1batu 20,030.00 / m2 18,000
Pasangan dinding bata 1/2 batu 17,810.00 / m2 12,500
Pasangan rooster termasuk perapihan nat 23,370.00 / m2 21,000
Pasangan glassblock 14,470.00 / m2 13,000
Pasangan dinding keramik 20 x 20 cm 33,390.00 / m2 30,000
Pasangan dinding keramik 30 x 30 cm 27,820.00 / m2 25,000
Pasangan dinding marmer/ granit sistem basah 217,030.00 / m2 195,000
Pasangan dinding marmer/ granit sistem kering 306,060.00 / m2 275,000
Pasangan dinding batu alam 30,050.00 / m2 27,000
Pasangan cermin + bor kaca + gosok 27,820.00 / m2 25,000
Lubang wastafel 55,650.00 / bh 50,000
Perapihan plafond exposed 11,130.00 / m2 10,000
Pasang rangka atap 11,130.00 / m2 10,000
Pasang gelombang atap 13,360.00 / m2 12,000
Pasang genteng keramik 11,130.00 / m2 10,000
Pasang lapisan seng/ aluminium foil 1,110.00 / m2 1,000
Pasang plafond tripleks + rangka 11,130.00 / m2 10,000
Pasang kusen + daun pintu 27,820.00 / m2 25,000
Pasang listplank kayu 7,790.00 / m' 7,000
Plint Keramik 8,350.00 / m' 7,500
Pasang nok genteng keramik 13,910.00 / m' 12,500
Pasang talang jurai 5,560.00 / m' 5,000
Pasang flashing metal 5,560.00 / m' 5,000
Pasang saluran buis beton ø 30 cm 38,950.00 / m' 35,000
tali air kusen 8,350.00 / m' 7,500

C PEKERJAAN JALAN
Pemadatan jalan dengan vibro 2,780.00 / m2 2,500
Tebar sirtu tebal 10 cm 2,230.00 / m2 2,000
Tebar abu batu pengisi tebal 3 cm 3,060.00 / m2 2,750
Pasang macadam tebal 30 cm 5,010.00 / m2 4,500
Aspal hotmix padat (bahan + upah) 1 cm 13,360.00 / m2 12,000
ATB padat (bahan + upah) 1 cm 11,690.00 / m2 10,500
Pemadatan sirtu/ macadam 4,170.00 / m2 3,750
Pemadatan batu pengisi 1,110.00 / m2 1,000
Pasang kanstein beton 6,680.00 / m' 6,000

D LAIN - LAIN
Bongkar dinding, Kusen & Pintu 11,980.00 / m2 10,760
Bongkar keramik lantai 14,970.00 / m2 13,450
Bongkar plafond 11,320.00 / m2 10,170
Bongkar Atap 31,800.00 / m2 28,571
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

1 M2 WIRE MESH M 8 (1 LAYER)


Wire Mesh M 8 1.100 m2 41,700 45,870
Kawat beton 0.050 kg 13,360 668
Alat bantu 1.000 ls - -
Upah Gelar wire mesh M 6 - k atas (1 lapis) 1.000 m2 6,678 6,678
SUB TOTAL 46,538 6,678
PROFIT - -
PPH - -
JUMLAH 46,538 6,678
PEMBULATAN 53,220

1 M2 WIRE MESH M 9 (1 LAYER)


Wire Mesh M 9 1.100 m2 53,400 58,740
Kawat beton 0.050 kg 13,360 668
Alat bantu 1.000 ls - -
Upah Gelar wire mesh M 6 - k atas (1 lapis) 1.000 m2 6,678 6,678
SUB TOTAL 59,408 6,678
PROFIT - -
PPH - -
JUMLAH 59,408 6,678
PEMBULATAN 66,090

1 M2 WIRE MESH M 9 (2 LAYER)


Wire Mesh M 9 2.200 m2 53,400 117,480
Kawat beton 0.050 kg 13,360 668
Alat bantu 1.000 ls - -
Upah Gelar wire mesh M 6 - k atas (1 lapis) 1.000 m2 6,678 6,678
SUB TOTAL 118,148 6,678
PROFIT - -
PPH - -
JUMLAH 118,148 6,678
PEMBULATAN 124,830

1 M2 WIRE MESH M 6 (1 LAYER)


Wire Mesh M 6 1.100 m2 23,400 25,740
Kawat beton 0.050 kg 13,360 668
Alat bantu 1.000 ls - -
Upah Gelar wire mesh M 6 - k atas (1 lapis) 1.000 m2 6,678 6,678
SUB TOTAL 26,408 6,678
PROFIT - -
PPH - -
JUMLAH 26,408 6,678
PEMBULATAN 33,090

1 M3 LANTAI KERJA BETON B0


Beton ready mix m³ 1.030 634,390 653,422
Alat bantu / talang cor m³ 1.000 5,560 5,560
Upah cor m³ 1.000 61,210 61,210
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

Sub Jumlah 720,192


Profit -
Jumlah 720,192
Dibulatkan 720,190

1 M3 PAS BATU KALI 1 : 5


PC m³ 2.700 70,820 191,214
Batu belah m³ 1.200 217,030 260,436
Pasir pasang m³ 0.400 233,720 93,488
Upah cor m³ 1.000 66,780 66,780
Sub Jumlah 611,918
Profit -
Jumlah 611,918
Dibulatkan 611,910

1 M3 PAS Anstamping 1 : 5
Batu belah m³ 1.200 217,030 260,436
Pasir pasang m³ 0.400 233,720 93,488
Upah cor m³ 1.000 44,520 44,520
Sub Jumlah 398,444
Profit -
Jumlah 398,444
Dibulatkan 398,440

1 M3 BETON READY Fc 30 Mpa


Beton ready mix m³ 1.030 779,070 802,442
Alat bantu m³ 1.000 - -
Upah cor m³ 1.000 33,390 33,390
Sub Jumlah 835,832
Profit -
Jumlah 835,832
Dibulatkan 835,830

1 Kg BETON READY MIX K 125


Beton ready mix m³ 1.030 612,130 630,494
Curring ls 1.000 3,900 3,900
Alat bantu m³ 1.000 - -
Upah cor m³ 1.000 33,390 33,390
Sub Jumlah 667,784
Profit -
Jumlah 667,784
Dibulatkan 667,780

1 Kg BETON READY MIX K 300


Beton ready mix m³ 1.030 701,160 722,195
Curring ls 1.000 3,900 3,900
Alat bantu m³ 1.000 - -
Upah cor m³ 1.000 33,390 33,390
Sub Jumlah 759,485
Profit -
Jumlah 759,485
Dibulatkan 759,480

1 Kg BETON READY MIX K 350


Beton ready mix m³ 1.030 723,420 745,123
Curring ls 1.000 3,900 3,900
Alat bantu m³ 1.000 - -
Upah cor m³ 1.000 33,390 33,390
Sub Jumlah 782,413
Profit -
Jumlah 782,413
Dibulatkan 782,410

1 M3 BETON READY MIX K 450


Beton ready mix m³ 1.030 812,460 836,834
Curring ls 1.000 3,900 3,900
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

Alat bantu m³ 1.000 - -


Upah cor m³ 1.000 33,390 33,390
Sub Jumlah 874,124
Profit -
Jumlah 874,124
Dibulatkan 874,120

1 M3 BETON READY MIX K 500


Beton ready mix m³ 1.030 834,720 859,762
Curring ls 1.000 3,900 3,900
Alat bantu m³ 1.000 - -
Upah cor m³ 1.000 33,390 33,390
Sub Jumlah 897,052
Profit -
Jumlah 897,052
Dibulatkan 897,050

1 KG BESI BETON
Besi Beton kg 1.035 7,570 7,835
Kawat Beton kg 0.010 13,360 134
Alat bantu lot 1.000 - -
Upah kg 1.000 890 890
Kaki ayam kg 0.010 - -
Sub Jumlah 8,859
Profit -
Jumlah 8,859
Dibulatkan 8,859

1 M2 BEKISTING BATACO
Batako bh 15.000 3,170 47,550
PC zak 0.175 70,820 12,394
Pasir Pasang m³ 0.023 233,720 5,376
Upah m² 1.000 19,480 19,480
Sub Jumlah 84,799
Profit -
Jumlah 84,799
Dibulatkan 84,790

1 M² BEKISTING KOLOM
Multipleks poly film 1 muka 4' x 8', tebal 18 mm lbr 0.082 328,320 26,800
Minyak bekisting ltr 0.150 16,690 2,504
Hollow 50 x 50 x 600 mm Ls 1.000 26,580 26,580
Stell prop Ls 1.000 3,250 3,250
Waller Beam / klem UNP 100 x 50 ls 1.000 15,790 15,790
Material bantu ls 1.000 - -
Upah m² 1.000 55,000 55,000
Sub Jumlah 129,923
Profit -
Jumlah 129,923
Dibulatkan 129,920

1 M² BEKISTING BALOK
Multipleks poly film 1 muka 4' x 8', tebal 15 mm lb 0.102 278,240 28,390
Minyak bekisting ltr 0.150 16,690 2,504
Hollow 50 x 50 x 2000 mm Ls 1.000 14,960 14,960
Hollow 50 x 100 x 6000 mm Ls 1.000 13,630 13,630
Material bantu ls 1.000 - -
Upah m² 1.000 44,520 44,520
Sub Jumlah 104,003
Profit -
Jumlah 104,003
Dibulatkan 104,000
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

1 M2 BEKISTING PELAT LANTAI


Multipleks poly film 1 muka 4' x 8', tebal 15 mm lb 0.204 245,410 50,080
Minyak bekisting ltr 0.150 16,690 2,504
Hollow 50 x 50 x 6000 mm Ls 1.000 5,560 5,560
Hollow 50 x 100 x 6000 mm Ls 1.000 3,480 3,480
Material bantu Ls 1.000 - -
Upah m2 1.000 38,950 38,950
Sub Jumlah 100,574
Profit -
Jumlah 100,574
Dibulatkan 100,570

1 M2 BEKISTING TANGGA
Multipleks poly film 1 muka 4' x 8', tebal 15 mm lb 0.113 245,410 27,822
Minyak bekisting ltr 0.150 16,690 2,504
Rangka Besi Hollow 50 x 50 x 6000 mm Ls 1.000 14,610 14,610.00
Rangka Besi Hollow 50 x 100 x 6000 mm Ls 1.000 18,260 18,260.00
Material bantu Ls 1.000 - -
Upah m² 1.000 100,170 100,170
Sub Jumlah 163,366
Profit -
Jumlah 163,366
Dibulatkan 163,360

1 M² BEKISTING DINDING
Multipleks phenolic 1 sisi 4' x 8', tebal 18 mm lbr 0.102 328,320 33,500
Minyak bekisting ltr 0.150 16,690 2,504
Rangka Besi Hollow 80 x 40 x 3 mm Ls 1.000 19,140 19,140
Stell prop Ls 1.000 3,250 3,250
Waller Beam UNP 100 x 50 Ls 1.000 20,260 20,260
Material bantu Ls 1.000 - -
Upah m² 1.000 33,390 33,390
Sub Jumlah 112,043
Profit -
Jumlah 112,043
Dibulatkan 112,040

1 M2 SCREED PELINDUNG TEBAL 5 CM


Wire Mesh M6 m² 1.100 24,700 27,170
PC zak 0.500 70,820 35,410
Pasir pasang m³ 0.053 233,720 12,270
Upah m² 1.000 22,260 22,260
Sub Jumlah 97,110
Profit -
Jumlah 97,110
Dibulatkan 97,110

1 M' KOLOM PRAKTIS K 175


PC zak 6.154 70,820 435,815
Pasir beton m³ 0.467 250,420 116,863
Split m³ 0.650 217,030 141,070
Besi KP 6 m' 83.000 15,020 1,246,660
Stek & grout Ls 1.000 115,470 115,470
Bekisting + upah m' 83.000 11,130 923,790
Upah cor m' 83.000 13,360 1,108,880
Jumlah 4,088,548
Profit -
Jumlah 4,088,548
Dibulatkan 4,088,540
Harga / m' 49,060

1 M2 PAS. DINDING BATA RINGAN TBL 10 CM


Bata ringan m³ 0.103 567,610 58,464
Thinbed zak 0.088 63,440 5,583
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

Kolom Praktis m' 0.350 49,060 17,171


Alat bantu ls 1.000 - -
Upah m² 1.000 22,260 22,260
Sub Jumlah 103,478
Profit -
Jumlah 103,478
Dibulatkan 103,480

1 M2 PAS. DINDING BATA RINGAN TBL 7,5 CM


Bata ringan m³ 0.077 567,610 43,848
Thinbed zak 0.066 63,440 4,187
Kolom Praktis m' 0.350 49,060 17,171
Alat / material bantu ( stek ) ls 1.000 - -
Upah m² 1.000 22,260 22,260
Sub Jumlah 87,466
Profit -
Jumlah 87,466
Dibulatkan 87,470

1 M2 PLESTERAN + ACIAN DALAM DINDING BATA RINGAN TBL 15 mm


Plesteran zak 0.6346 41,180 26,133
Acian zak 0.0880 54,530 4,799
Alat bantu ls 1.0000 - -
Upah m² 1.0000 30,610 30,610
Sub Jumlah 61,542
Profit -
Jumlah 61,542
Dibulatkan 61,540

1 M2 SKIMCOAT DINDING & KOLOM BETON


Skimcoat zak 0.0720 85,140 6,130
Alat bantu ls 1.0000 - -
Upah m² 1.0000 27,820 27,820
Sub Jumlah 33,950
Profit -
Jumlah 33,950
Dibulatkan 33,950

1 M2 DINDING KERAMIK 20 x 20 cm
Keramik exMulia m² 1.100 64,550 71,005
PC zak 0.150 70,820 10,623
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 102,470 11,272
Grouting nat kg 0.379 11,130 4,222
Upah m² 1.000 38,950 38,950
Sub Jumlah 139,753
Profit -
Jumlah 139,753
Dibulatkan 139,750

1 M2 DINDING KERAMIK 30 x 30 cm
Keramik ex Mulia m² 1.100 85,140 93,654
PC zak 0.150 75,880 11,382
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.379 11,130 4,222
Upah m² 1.000 38,950 38,950
Sub Jumlah 161,560
Profit -
Jumlah 161,560
Dibulatkan 161,560
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

1 M2 DINDING KERAMIK 30 x 30 cm
Keramik ex Mulia m² 1.100 65,110 71,621
PC zak 0.150 75,880 11,382
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.379 11,130 4,222
Upah m² 1.000 38,950 38,950
Sub Jumlah 139,527
Profit -
Jumlah 139,527
Dibulatkan 139,520

1 M2 DINDING HOMOGENEOUS TILE NIRO GRANITE 60 x 60 Cm


Homogeneous tile m² 1.100 257,090 282,799
PC zak 0.150 70,820 10,623
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 72,340 7,957
Grouting nat kg 0.362 11,130 4,030
Upah m² 1.000 38,950 38,950
Sub Jumlah 348,040
Profit -
Jumlah 348,040
Dibulatkan 348,040

1 M2 DINDING HOMOGENEOUS TILE INDOGRESS 60 x 60 Cm Bianco damasco


Homogeneous tile m² 1.100 257,090 282,799
PC zak 0.150 70,820 10,623
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 11,130 1,224
Grouting nat kg 0.362 11,130 4,030
Upah m² 1.000 40,070 40,070
Sub Jumlah 342,427
Profit -
Jumlah 342,427
Dibulatkan 342,420

1 M2 DINDING HOMOGENEOUS TILE NIRO GRANITE 40 x 40 Cm


Homogeneous tile m² 1.100 200,330 220,363
PC zak 0.150 70,820 10,623
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.362 11,130 4,030
Upah m² 1.000 40,070 40,070
Sub Jumlah 288,438
Profit -
Jumlah 288,438
Dibulatkan 288,430

1 M2 DINDING HOMOGENEOUS TILE INDOGRESS 40 x 40 Cm White Onyx


Homogeneous tile m² 1.100 267,110 293,821
PC zak 0.150 70,820 10,623
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.362 11,130 4,030
Upah m² 1.000 40,070 40,070
Sub Jumlah 361,896
Profit -
Jumlah 361,896
Dibulatkan 361,890

1 M2 DINDING HOMOGENEOUS TILE INDOGRESS 40 x 40 Cm Zincronium


Homogeneous tile m² 1.100 220,370 242,407
PC zak 0.150 70,820 10,623
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.362 11,130 4,030
Upah m² 1.000 40,070 40,070
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

Sub Jumlah 310,482


Profit -
Jumlah 310,482
Dibulatkan 310,480

1 M2 DINDING HOMOGENEOUS TILE NERO CEMENTO 30 x 60 Cm


Homogeneous tile m² 1.100 228,160 250,976
PC zak 0.150 70,820 10,623
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 11,130 1,224
Grouting nat kg 0.362 11,130 4,030
Upah m² 1.000 50,080 50,080
Sub Jumlah 320,614
Profit -
Jumlah 320,614
Dibulatkan 320,610

1 M2 LANTAI ANDESIT
Screed lantai m² 1.000 43,380 43,380
Batu alam andesit ukuran 20 x 20 cm m² 0.525 170,280 89,397
Granit 30 x 60 cm m² 0.525 1,193,090 626,372
Pasir Pasang zak 0.131 233,720 30,676
Coating anti jamur m² - - -
Upah m² 1.000 38,950 38,950
Sub Jumlah 828,775
Profit -
Jumlah 828,775
Dibulatkan 828,770

1 M2 LANTAI KERAMIK 30 x 30 cm
Screed lantai m² 1.000 43,380 43,380
Keramik lantai m² 1.100 85,140 93,654
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.386 11,130 4,296
Upah m² 1.000 22,260 22,260
Sub Jumlah 173,261
Profit -
Jumlah 173,261
Dibulatkan 173,260

1 M2 LANTAI KERAMIK 20 x 20 cm
Screed lantai m² 1.000 43,380 43,380
Keramik lantai m² 1.100 64,550 71,005
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.386 11,130 4,296
Upah m² 1.000 22,260 22,260
Sub Jumlah 150,612
Profit -
Jumlah 150,612
Dibulatkan 150,610
1 M2 LANTAI KERAMIK 40 x 40 cm
Screed lantai m² 1.000 43,385 43,385
Keramik lantai m² 1.100 46,190 50,809
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.386 11,130 4,296
Upah m² 1.000 22,260 22,260
Sub Jumlah 130,421
Profit -
Jumlah 130,421
Dibulatkan 130,420

1 M2 koral silikat
koral m² 1.100 43,406 47,747
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.386 11,130 4,296
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

Upah m² 1.000 22,260 22,260


Sub Jumlah 83,974
Profit -
Jumlah 83,974
Dibulatkan 83,970

1 M2 LANTAI KERAMIK 60 x 60 CM
Screed lantai m² 1.000 43,380 43,380
Keramik lantai m² 1.100 141,740 155,914
Perekat keramik zak 0.138 87,920 12,089
Grouting nat kg 0.286 11,130 3,180
Upah m² 1.000 27,820 27,820
Sub Jumlah 242,383
Profit -
Jumlah 242,383
Dibulatkan 242,380

1 M2 LANTAI HOMOGENEOUS TILE Polish 60 x 60 mm


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Niro granite m² 1.100 257,090 282,799
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 377,325
Profit -
Jumlah 377,325
Dibulatkan 377,320

1 M2 DINDING HOMOGENEOUS TILE INDOGRESS 40 x 40 Cm White Onyx


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile m² 1.100 267,110 293,821
Perekat keramik zak 0.110 257,090 28,280
Grouting nat kg 0.362 11,130 4,030
Upah m² 1.000 50,080 50,080
Sub Jumlah 376,211
Profit -
Jumlah 376,211
Dibulatkan 376,210

1 M2 LANTAI HOMOGENEOUS TILE UnPolish 60 x 60


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Niro granite m² 1.100 252,420 277,662
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 372,188
Profit -
Jumlah 372,188
Dibulatkan 372,180

1 M2 LANTAI HOMOGENEOUS TILE Polish 1200 x 60


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Niro granite m² 0.792 552,920 437,913
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 532,438
Profit -
Jumlah 532,438
Dibulatkan 532,430

1 M2 LANTAI HOMOGENEOUS TILE Polish 600 x 600


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Niro granite white onyx m² 1.100 394,250 433,675
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 528,201
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

Profit -
Jumlah 528,201
Dibulatkan 528,200

1 M2 LANTAI HOMOGENEOUS TILE Polish 40 x 40


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Niro granite m² 1.100 267,110 293,821
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 388,347
Profit -
Jumlah 388,347
Dibulatkan 388,340

1 M2 LANTAI HOMOGENEOUS TILE UnPolish 40 x 40


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Indogress m² 1.100 278,860 306,746
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 401,272
Profit -
Jumlah 401,272
Dibulatkan 401,270

1 M2 LANTAI HOMOGENEOUS TILE Polish 80 x 80


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Niro granite m² 1.100 890,370 979,407
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 1,073,933
Profit -
Jumlah 1,073,933
Dibulatkan 1,073,930

1 M2 LANTAI HOMOGENEOUS TILE 80 x 80 mm type topaz Indogress


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Niro granite m² 1.100 375,020 412,522
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 507,048
Profit -
Jumlah 507,048
Dibulatkan 507,040

1 M2 LANTAI HOMOGENEOUS TILE 100 x 800 mm type topaz Indogress


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Indogress m² 1.100 180,300 198,330
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 292,856
Profit -
Jumlah 292,856
Dibulatkan 292,850

1 M2 LANTAI HOMOGENEOUS TILE 1200 x 600 mm Indogress


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Indogress m² 1.100 557,590 613,349
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 707,875
Profit -
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

Jumlah 707,875
Dibulatkan 707,870

1 M2 LANTAI HOMOGENEOUS TILE 800 x 800 mm Indogress Zincornium


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Indogress m² 1.100 375,020 412,522
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 507,048
Profit -
Jumlah 507,048
Dibulatkan 507,040

1 M2 LANTAI HOMOGENEOUS TILE 600 x 600 mm Indogress Zincornium


Screed lantai m² 1.000 43,380 43,380
Homogeneous tile EX, Indogress m² 1.100 341,370 375,507
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.227 11,130 2,524
Upah m² 1.000 38,950 38,950
Sub Jumlah 470,033
Profit -
Jumlah 470,033
Dibulatkan 470,030

1 M' STEPNOSING KERAMIK


Screed lantai m' 0.100 43,385 4,338
Stepnosing keramik 10 x 20 bh 5.000 11,130 55,650
Perekat keramik lantai zak 0.012 87,920 1,055
Grouting nat kg 0.013 11,130 147
Upah m' 1.000 18,920 18,920
Sub Jumlah 80,110
Profit -
Jumlah 80,110
Dibulatkan 80,110

1 M' STEPNOSING HT
Screed lantai m' 0.100 43,385 4,338
Stepnosing keramik 60 x 20 bh 0.360 252,420 90,871
Perekat keramik lantai zak 0.012 87,920 1,055
Grouting nat kg 0.013 11,130 147
Upah m' 1.000 18,920 18,920
Sub Jumlah 115,332
Profit -
Jumlah 115,332
Dibulatkan 115,330

1 M' TALANG METAL


Fixing Strap ls 1.000 14,190 14,190
Talang datar m' 0.051 213,330 10,878
Isolasi atap m2 1.000 109,240 109,240
Dudukan talang m' 1.000 83,470 83,470
Upah m² 1.000 38,950 38,950
Sub Jumlah 256,728
Profit -
Jumlah 256,728
Dibulatkan 256,720

1 BUAH MEJA LAVATORY UK. 1050X500 MM FIN KERAMIK EX MULIA


P L
1.05 0.50
Meja beton 1.000 Unit 150,249 150,249
keramik 30 x 60 cm 0.525 m2 141,740 74,414
keramik 30 x 60 cm 0.308 m2 141,740 43,585
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

Material bantu 1.000 Ls 50,080 50,080


Alat bantu 1.000 LS 2,230 2,230
Upah pinggulan 0.308 m' 22,260 6,845
Upah pasang 1.000 m' 139,120 139,120
SUB TOTAL 320,558 145,965
PROFIT - -
PPH - -
JUMLAH 320,558 145,965
PEMBULATAN 466,520

1 BUAH MEJA LAVATORY UK. 800X665 MM FIN Granit


P L
0.80 0.67
Meja beton 1.000 Unit 161,067 161,067
Black granit 0.532 m2 890,370 473,677
Black granit 0.320 m2 890,370 284,473
Material bantu 1.000 Ls 50,080 50,080
Alat bantu 1.000 LS 2,230 2,230
Upah pinggulan 0.320 m' 22,260 7,112
Upah pasang 1.000 m' 139,120 139,120
SUB TOTAL 971,527 146,232
PROFIT - -
PPH - -
JUMLAH 971,527 146,232
PEMBULATAN 1,117,760

1 BUAH MEJA LAVATORY UK. 1000X665 MM FIN GRANIT


P L
1.00 0.67
Meja beton 1.000 Unit 201,334 201,334
Black granit 0.665 m2 890,370 592,096
Black granit 0.350 m2 890,370 311,184
Material bantu 1.000 Ls 50,080 50,080
Alat bantu 1.000 LS 2,230 2,230
Upah pinggulan 0.350 m' 22,260 7,780
Upah pasang 1.000 m' 139,120 139,120
SUB TOTAL 1,156,924 146,900
PROFIT - -
PPH - -
JUMLAH 1,156,924 146,900
PEMBULATAN 1,303,820

1 BUAH MEJA LAVATORY UK. 2250X890 MM FIN GRANIT


P L
2.25 0.89
Meja beton 1.000 Unit 601,748 601,748
Black granit 2.003 m2 890,370 1,782,966
Black granit 0.605 m2 890,370 538,229
Material bantu 1.000 Ls 50,080 50,080
Alat bantu 1.000 LS 2,230 2,230
Upah pinggulan 0.605 m' 22,260 13,456
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

Upah pasang 1.000 m' 139,120 139,120


SUB TOTAL 2,975,253 152,576
PROFIT - -
PPH - -
JUMLAH 2,975,253 152,576
PEMBULATAN 3,127,830
1 BUAH MEJA LAVATORY UK. 2250X890 MM FIN GRANIT
P L
2.25 0.89
Meja beton 1.000 Unit 601,748 601,748
Black granit 2.003 m2 890,370 1,782,966
Black granit 0.605 m2 890,370 538,229
Material bantu 1.000 Ls 50,080 50,080
Alat bantu 1.000 LS 2,230 2,230
Upah pinggulan 0.605 m' 22,260 13,456
Upah pasang 1.000 m' 139,120 139,120
SUB TOTAL 2,975,253 152,576
PROFIT - -
PPH - -
JUMLAH 2,975,253 152,576
PEMBULATAN 3,127,830
1 BUAH MEJA LAVATORY UK. 900X600 MM FIN MARBLE EX LOKAL
P L
1.96 1.00
Meja beton 1.000 Unit 588,977 588,977
Marmer 30 x 60 cm 1.960 m2 667,770 1,308,829
Marmer 30 x 60 cm 0.594 m2 667,770 396,655
Material bantu 1.000 Ls 50,080 50,080
Alat bantu 1.000 LS 2,230 2,230
Upah pinggulan 0.594 m' 22,260 13,222
Upah pasang 1.000 m' 139,120 139,120
SUB TOTAL 2,346,772 152,342
PROFIT - -
PPH - -
JUMLAH 2,346,772 152,342
PEMBULATAN 2,499,110

1 BUAH MEJA LAVATORY UK. 2740X1000 MM FIN MARBLE EX LOKAL


P L
2.74 1.00
Meja beton 1.000 Unit 823,366 823,366
Marmer 30 x 60 cm 2.740 m2 667,770 1,829,690
Marmer 30 x 60 cm 0.711 m2 667,770 474,784
Material bantu 1.000 Ls 50,080 50,080
Alat bantu 1.000 LS 2,230 2,230
Upah pinggulan 0.711 m' 22,260 15,827
Upah pasang 1.000 m' 139,120 139,120
SUB TOTAL 3,180,150 154,947
PROFIT - -
PPH - -
JUMLAH 3,180,150 154,947
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

PEMBULATAN 3,335,100

1 BUAH MEJA LAVATORY UK. 2740X1000 MM FIN MARBLE EX LOKAL


P L
3.45 1.00
Meja beton 1.000 Unit 1,036,720 1,036,720
Marmer 30 x 60 cm 3.450 m2 667,770 2,303,807
Marmer 30 x 60 cm 0.818 m2 667,770 545,902
Material bantu 1.000 Ls 50,080 50,080
Alat bantu 1.000 LS 2,230 2,230
Upah pinggulan 0.818 m' 22,260 18,198
Upah pasang 1.000 m' 139,120 139,120
SUB TOTAL 3,938,738 157,318
PROFIT - -
PPH - -
JUMLAH 3,938,738 157,318
PEMBULATAN 4,096,060

1 BUAH MEJA LAVATORY UK. 1000X478 MM FIN MARBLE EX LOKAL


P L
1.00 0.48
Meja beton 1.000 Unit 144,239 144,239
Keramik 0.480 m2 85,140 40,867
Keramik 0.294 m2 85,140 25,031
Material bantu 1.000 Ls 50,080 50,080
Alat bantu 1.000 LS 2,230 2,230
Upah pinggulan 0.294 m' 22,260 6,544
Upah pasang 1.000 m' 139,120 139,120
SUB TOTAL 262,448 145,664
PROFIT - -
PPH - -
JUMLAH 262,448 145,664
PEMBULATAN 408,110

PLINT KERAMIK 10/30


Screed 1:5 m2 0.100 48,210 4,821
Tile adhesive (40 Kg/zak) sak 0.013 91,260 1,198
Dry mix pengisi tile (24 Kg/zak) Kg 0.021 5,230 110
Plint keramik m' 0.150 14,090 2,114
Alat bantu m2 1.000 - -
Upah pasang stepnosing / plint keramik bh 1.000 14,470 14,470
Sub Jumlah 22,712
Profit -
Jumlah 22,712
Dibulatkan 22,710

1 M2 KONST JALAN ASPAL


Penyiapan badan jalan & pemadatan m² 1.000 8,350 8,350
Lapisan sirtu tebal 30 cm m² 1.000 103,650 103,650
Lapisan batu pecah tebal 20 cm m² 1.000 103,650 103,650
Prime coat 1,5 ltr / m2 m² 1.000 20,870 20,870
Lapisan ATB tebal 5 cm m² 1.000 153,590 153,590
Sub Jumlah 390,110
Profit -
Jumlah 390,110
Dibulatkan 390,110
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

1 M2 PAVING BLOCK TEBAL 8 CM


Penyiapan badan jalan & pemadatan m² 1.000 5,565 5,565
Lapisan sirtu tebal 10 cm m² 1.000 40,115 40,115
Urugan pasir tebal 4 cm m3 0.044 217,030 9,549
Pavingblock tebal 8 cm m² 1.000 165,552 165,552
Upah pasang m² 1.000 27,824 27,824
Sub Jumlah 248,605
Profit -
Jumlah 248,605
Dibulatkan 248,600

1 M' KANSTEIN BETON T 20 CM (type 1)


Penyiapan jalur kanstein m' 1.000 2,230 2,230
Screed tebal 3 cm m' 1.000 10,820 10,820
Kanstein beton m' 1.000 105,170 105,170
Upah pasang m' 1.000 22,260 22,260
Sub Jumlah 140,480
Profit -
Jumlah 140,480
Dibulatkan 140,480

1 M' KANSTEIN BETON T 30 CM (type 2)


Penyiapan jalur kanstein m' 1.000 2,230 2,230
Screed tebal 3 cm m' 1.000 10,820 10,820
Kanstein beton m' 1.000 100,170 100,170
Upah pasang m' 1.000 22,260 22,260
Sub Jumlah 135,480
Profit -
Jumlah 135,480
Dibulatkan 135,480

1 M' KANSTEIN BETON T 30 CM (type 3)


Penyiapan jalur kanstein m' 1.000 2,230 2,230
Screed tebal 3 cm m' 1.000 10,820 10,820
Kanstein beton m' 1.000 103,510 103,510
Upah pasang m' 1.000 22,260 22,260
Sub Jumlah 138,820
Profit -
Jumlah 138,820
Dibulatkan 138,820
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

1 M' TANGGULAN DG PAS. BATA RINGAN LEBAR 60 CM TEBAL 20 CM FIN KERAMIK 400X400 CM EX. PLATINUM
Bata ringan Ex Jaya Celcon 0.126 m3 567,610 71,519
Thinbed 111 (perekat bata ringan t = 3-8 mm) Ex. Drymix 0.100 zak 63,440 6,344
Tile Adhesive Standar (HT, Dinding, Lantai) Ex. Drymix 0.150 zak 82,359 12,354
Tile Grout Ex. Drymix 0.210 kg 7,791 1,636
Lexus Cream, Grey 1.050 m2 68,981 72,430
Keramik mulia 400 x 400 1.100 m2 65,110 71,621
Angkur 1.000 ls 556 556
Alat bantu 1.000 ls 1,669 1,669
Upah Pasang dinding bata ringan dinding dalam 1.000 m2 25,042 25,042
Upah Pasang lantai keramik 1.000 m2 41,736 41,736
SUB TOTAL 238,130 66,777
PROFIT - -
PPH - -
JUMLAH 238,130 66,777
PEMBULATAN 304,910

1 M2 PAS. BATA PLANTER BOX


Batu bata 80 bh 670 53,600
MU - 380 0.066 zak 85,140 5,587
MU - 301 0.404 zak 87,920 35,506
Alat bantu 1.000 m³ - -
Upah Pasang dinding bata ringan dinding dalam 1.000 m2 25,042 25,042
SUB TOTAL 94,693 25,042
PROFIT - -
PPH - -
JUMLAH 94,693 25,042
PEMBULATAN 119,740

1 M' KANSTEEN BETON


Kanstein beton 15 x 30 x 60 cm ex Conblock Cisangkan bh 1.660 66,221 109,927
Groutingan / perekat ls 1.000 11,130 11,130
Upah pasang m' 1.000 22,259 22,259
Sub Jumlah 143,316
Profit -
Jumlah 143,316
Dibulatkan 143,310

1 M' GROOVE ALUMINIUM U


Aluminium U 10 1.100 m' 8,570 9,427
Alat bantu 1.000 m' - -
Upah Tali air - Fasade 1.000 m' 16,694 16,694
SUB TOTAL 9,427 16,694
PROFIT - -
PPH - -
JUMLAH 9,427 16,694
PEMBULATAN 26,120

1 M' SALURAN (GUTTER) PERIMETER


Ukuran L H TEB.
0.40 0.20 0.05
Beton mutu K-175 terpasang m3 0.042 688,920 28,935
Besi beton terpasang kg 3.780 8,859 33,485
Beksiting m2 1.680 100,570 168,958
Waterproofing coating Brushbond Grey, 2x coating m2 0.800 44,520 35,616
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA

ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SAT. KOEFISIEN HARGA SAT JUMLAH HARGA

Upah Bekisting Praktis m' 1.680 3,895 6,544


Upah Pasang m' 1.000 66,777 66,777
Alat bantu m³ 1.000 -
Sub Jumlah 340,315
Profit -
Jumlah 340,315
Dibulatkan 340,310

1 BH CAR STOPPER
Kanstin Car Stopper uk 60 x 30 x 15 cm (K-400) bh 1.000 61,210 61,210
Angkur dia. 12 mm bh 1.000 24,485 24,485
Cat Minyak Ex Gardex Premium Jotun m2 0.284 33,390 9,483
Upah pasang m' 1.000 5,565 5,565
Sub Jumlah 100,743
Profit -
Jumlah 100,743
Dibulatkan 100,740
Rp

DAFTAR No. 1 PEK. PERSIAPAN, PRASARANA DAN PENUNJANG ( Preliminaries )

1.0. Catatan harga :

1. Kontrak ini bersifat Harga Tetap (Lump Sum Fix Price), kecuali
dimana dicantumkan Provisional atau "Provisional Sum".
Kontraktor wajib menghitung kembali volume pekerjaan dan
memeriksa satuannya yang dibuat oleh Quantity Surveyor dan jika
menurut perhitungan Kontraktor volume dan atau satuannya tidak
sesuai atau terdapat item pekerjaan yang belum tercantum, maka
Kontraktor dapat merubah atau menambahkan pada lampiran
khusus yang dibuat untuk pekerjaan tambah atau kurang.

2. Dalam mengajukan harga pekerjaan ini Kontraktor harus sudah


mempertimbangkan untuk memasukkan semua biaya pengeluaran
pekerjaan dan tidak ada tuntutan di kemudian hari terhadap
Pemberi Tugas, bila daftar uraian pekerjaan ini dipandang tidak
lengkap.

3. Semua hal yang tidak tercantum disini dianggap sudah termasuk


dalam penawaran dan semua resiko baik mengenai eskalasi harga,
salah hitung terhadap volume maupun harga yang diajukan menjadi
tanggung jawab Kontraktor.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-1 ( 21 ) SAMEP


Rp

DAFTAR No. 1 PEK. PERSIAPAN, PRASARANA DAN PENUNJANG ( Preliminaries )

1 Manajemen Proyek dan Biaya Administrasi Lapangan ls 1.00 3,000,000,000 3,000,000,000

Pemborong harus menyediakan biaya-biaya yang dikeluarkan


untuk mengadakan tenaga teknis dan tenaga pimpinan
proyek di lapangan yang kompeten, cakap, menguasai bidang
pekerjaan dengan baik dan berpengalaman, yang akan
mengelola pelaksanaan pekerjaan dan mengurus segala hal
yang berhubungan dengan tanggung jawabnya terhadap
kontrak ini, termasuk semua biaya administrasi yang
diperlukan selama pelaksanaan proyek (Kontraktor di minta
melampirkan rinciannya)

2 Mobilisasi dan demobilisasi peralatan ls 1.00 310,560,000 310,560,000

Biaya mobilisasi dan demobilisasi termasuk biaya ijin


pemasukan peralatan dan perlengkapan kerja kedalam lokasi
proyek dan pemindahan dari satu tempat ke tempat lainnya
didalam lokasi pekerjaan termasuk pemakaiannya Tower
Crane dan Alimax oleh pemborong lain, serta
mengeluarkannya setelah penyelesaian pekerjaan. Atau
apabila diperlukan berkaitan dengan metoda kerja (surat
kalibrasi alat). Kontraktor di minta melampirkan rinciannya

3 Alat-alat Keselamatan Kerja ls 1.00 721,000,000 721,000,000

Pemborong bertanggung jawab atas pengadaan alat-alat


keselamatan kerja seperti helm, sepatu lapangan, jas hujan,
sabuk pengaman, handy talky, dan lain-lain sebanyak yang
diperlukan untuk keperluan Pemberi Tugas, QS, Konsultan
Pengawas, Pekerja dan Staff Pemborong, serta terhadap
pihak lain didalam lokasi proyek. Pengadaan pelatihan
keselamatan kerja secara berkala untuk tenaga - tenaga kerja
dan pihak - pihak terkait lain. Serta penyediaan tenaga -
tenaga khusus K3 yang mencukupi selama pelaksanaan
proyek.

4 Rapat Proyek ls 1.00 50,000,000 50,000,000


Pemborong harus menyediakan fasilitas yang diperlukan
termasuk akomodasi dan konsumsi (snack) untuk
pelaksanaan rapat rutin di proyek dengan Pemberi Tugas,
Pimpinan Proyek, para Konsultan dan para Pemborong paket
lain (jika ada).

5 Keamanan Proyek ls 1.00 150,000,000 150,000,000


Pemborong bertanggung jawab atas penjagaan dan
perlindungan terhadap pekerjaan yang dianggap penting
selama pelaksanaan kontrak siang dan malam Pemberi
Tugas tidak bertanggung jawab terhadap Pemborong atas
kehilangan atau kerusakan bahan-bahan bangunan atau
peralatan atau pekerjaan yang sedang dalam pelaksanaan.

Pemborong wajib menempatkan tenaga Satpam yang terlatih


dan mencukupi selama 24 jam untuk penjagaan keamanan
terhadap pencurian dan oknum-oknum yang mengganggu
ketertiban termasuk kerjasama dengan satuan Polri setempat.
DAN KEAMANAN LINGKUNGAN SETEMPAT.

6 Laporan Bulanan Dan Photo - Photo Kemajuan Pekerjaan ls 1.00 57,000,000 57,000,000
Pemborong wajib membuat Laporan harian, mingguan dan
bulanan, laporan progress pekerjaan serta laporan lainnya.
Pemborong berkewajiban untuk membuat photo- photo atas
kemajuan pekerjaan sebanyak 4 (empat) set untuk
diserahkan setiap bulan hingga masa penyerahan pertama,
serta setiap tahap pengajuan pembayaran (penagihan)
prestasi.

7 Biaya pembuatan dan pencetakan Dokumen Kontrak ls 1.00 15,000,000 15,000,000


Biaya pembuatan dan pencetakan Dokumen Kontrak rangkap
5 (lima) lengkap dengan gambar- gambar yang sehubungan
dengannya (seperti biaya meterai).

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-1 ( 22 ) SAMEP


Rp

DAFTAR No. 1 PEK. PERSIAPAN, PRASARANA DAN PENUNJANG ( Preliminaries )

8 Pengadaan Gambar informasi (For Construction) ls 1.00 10,000,000 10,000,000


Pengadaan gambar informasi (for construction) untuk
pelaksanaan (design intent) sebanyak yang diperlukan untuk
keperluan kerja dilapangan termasuk 2 (dua) set keperluan
pengawasan.

9 Pembuatan Gambar kerja (Shop drawing) ls 1.00 10,000,000 10,000,000

Pembuatan gambar kerja (shop drawing) berikut perhitungan


atau kalkulasi yang terinci sebanyak 3 (tiga) set, hingga
disetujui Manajemen Konstruksi dan atau Pemberi Tugas.

10 Pembuatan gambar terlaksana (As Built Drawing) ls 1.00 15,000,000 15,000,000


Pembuatan gambar-gambar terlaksana (as built drawing)
sebanyak 1 (satu) set kalkir dan 4 (empat) set blue print.
Termasuk CD

11 Contoh-contoh Bahan, Brosur dan Pengujian ls 1.00 50,000,000 50,000,000


Pengadaan contoh-contoh bahan dan brosur yang
dikehendaki oleh Pemberi Tugas harus segera disediakan
tanpa kelambatan, atas biaya Pemborong.

Contoh-contoh yang diajukan tersebut harus sesuai dengan


standard dan Syarat-syarat Teknis Pelaksanaan dan diambil
dengan jalan atau cara sedemikian rupa sehingga dapat
dianggap bahwa bahan atau pekerjaan tersebutlah yang akan
dipakai dalam pelaksanaan pekerjaan nanti.

12 Pemeriksaan dan Pengujian Bahan ls 1.00 50,000,000 50,000,000


Dalam pengajuan penawarannya, Pemborong harus
meperhitungkan segala biaya-biaya pengujian berbagai
bahan dan pekerjaan. Pemborong tetap bertanggung jawab
pula atas biaya-biaya pengujian kembali dari bahan dan
pekerjaan yang tidak memenuhi syarat yang dikehendaki.

13 Kantor Konsultan di Lapangan ls 1.00 140,000,000 140,000,000


Pembuatan Kantor sementara untuk Konsultan dan Konsultan
lainnya di lapangan berikut semua fasilitas yang diperlukan
seperti Listrik, Air, Telepon, Air Conditioning, Toilet, Meja,
Kursi, Filing Cabinet, dan perlengkapan penunjang lainnya
termasuk biaya-biaya yang dikeluarkan untuk pemakaian
listrik dan telepon selama proyek berlangsung, berikut
pemeliharaan selama proyek berlangsung, dan memindahkan
ke tempat lainnya di dalam lokasi pekerjaan bila ada perintah,
membongkar setelah penyelesaian pekerjaan dan
memperbaiki/merapihkan sekitar lokasi kantor tersebut
(Spesifikasi sesuai penjelasan dalam Aanwijzing).

14 Pembuatan Kantor sementara Pemborong di lapangan berikut ls 1.00 40,000,000 40,000,000


semua fasilitas yang diperlukan termasuk toilet untuk para
pekerja dan berikut pemeliharaan selama pelaksanaan
pekerjaan dan memindah-mindahkan dalam lokasi pekerjaan
bila ada perintah membongkar setelah penyelesaian
pekerjaan dan memperbaiki/ merapihkan bekas lokasinya
(termasuk partisi triplek, apabila suatu saat kantor harus
dipindah ke dalam bangunan yang telah selesai).

15 P3K dan Keselamatan Kerja ls 1.00 40,000,000 40,000,000

Pengadaan perlengkapan P3K dan peralatan pencegahan


terhadap bahaya kebakaran (fire extinguisher) yang
melindungi semua area proyek yang sesuai dengan anjuran
perusahaan asuransi terhadap pekerjaan dan Instansi
Pemerintah yang berwenang, menyediakan tenaga-tenaga
yang terlatih untuk maksud di atas selama masa pelaksanaan
proyek dengan pelatihan dari DPK minimal 3x selama proyek,
dan kerjasama dengan rumah sakit setempat.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-1 ( 23 ) SAMEP


Rp

DAFTAR No. 1 PEK. PERSIAPAN, PRASARANA DAN PENUNJANG ( Preliminaries )

16 Listrik kerja dan penerangan malam hari ls 1.00 300,000,000 300,000,000

Pemborong harus menyediakan pembangkit tenaga listrik


sementara atau penerangan buatan untuk keperluan kerja
dan penerangan malam hari termasuk pemasangan kabel-
kabel dan meteran yang dipergunakan untuk pekerjaan atau
pengambilan daya dari sumber PLN yang sudah ada yang
dipergunakan untuk keperluannya. Semua biaya pemakaian
daya selama pelaksanaan proyek termasuk izin-izin yang
diperlukan serta perapihan setelah pekerjaan selesai. Besar
daya agar diperhitungkan pula untuk kontraktor - kontraktor
lain (sub kontraktor, NSC, dan sebagainya).

17 Penerangan Malam Hari ls 1.00 50,000,000 50,000,000


Pemasangan lampu TL 20 W berikut tiang termasuk instalasi
kabel dan lain-lain, pada tempat-tempat strategis sepanjang
sisi dalam pagar proyek

18 Air kerja dan keperluan sanitasi/toilet sementara. ls 1.00 291,400,000 291,400,000

Pemborong harus menyediakan air kerja untuk keperluannya


yang didapat dari sumber yang ada di lokasi tersebut a.l.
sumur pantek jet pump, atau sumur dalam (deep well), dlsb.
Pemborong harus membuat sambungan-sambungan
sementara yang diperlukan atau cara lain untuk mengalirkan
air dan mencabutnya kembali pada waktu pekerjaan selesai
dan membetulkan segala pekerjaan yang terganggu.
Penyediaan sumber air bersih tersebut harus dapat untuk
melayani seluruh Pemborong lain yang terkait pada proyek
ini, termasuk keperluan pekerjaan dan buruhnya, selama
masa pembangunan proyek dan air harus layak dipakai untuk
konstruksi dan kegiatan lainnnya

19 Telepon ls 1.00 22,000,000 22,000,000


Pemborong atas biaya sendiri harus menyediakan fasilitas
telephone aiphone yang akan digunakan di dalam proyek ini
termasuk telepon yang akan digunakan oleh Konsultan.

20 Papan Nama ls 1.00 44,000,000 44,000,000

Pemborong harus mengadakan dan memasang Papan Nama


Proyek yang menunjukkan Nama Proyek, Pemberi Tugas,
Konsultan-konsultan yang terkait, No. Izin, dan termasuk
biaya untuk membongkar kembali setelah proyek selesai
pembongkarannya menjadi beban dari Pemborong, termasuk
pembayaran retribusi reklame kepada Pemda (bila ada),
selama masa pembangunan.

21 Kebersihan
a) Pemborong harus menyediakan fasilitas yang dibutuhkan ls 1.00 200,000,000 200,000,000
untuk memelihara kondisi lapangan serta lingkungan
sekitarnya agar tetap bersih, termasuk pembersihan ban
kendaraan yang keluar masuk proyek.
b) Pemborong harus mengangkut dan membuang keluar proyek ls 1.00 105,000,000 105,000,000
semua sampah, puing-puing, dan bahan-bahan yang tidak
terpakai secara teratur selama pelaksanaan dan pada waktu
penyelesaian pekerjaan keadaan lokasi harus bersih dan
rapih termasuk penyediaan sarana-sarana yang diperlukan
untuk maksud tersebut. (Catatan : sampah dibersihkan setiap
hari dan dalam pengangkutan keluar proyek tidak mengotori
jalan umum).

22 Jalan Masuk Tempat Pekerjaan dan Jalan Sementara ls 1.00 50,000,000 50,000,000

Jalan masuk ke empat pekerjaan harus diadakan oleh


Pemborong bilamana diperlukan disesuaikan dengan
kebutuhan dan kepentingan lokasi proyek tersebut ( jalan
masuk dicor beton sementara ) . Selama masa pembangunan
pihak pemborong harus mengadakan dan memelihara
seluruh jalan - jalan semetara, jembatan -jembatan, dsb yang
mungkin diperlukan untuk memasuki bagian pekerjaan dan
menyingkirkan
JAKARTA INTERNATIONAL / membersihkan
EQUESTRIAN PARK kembali pada waktu Daf-1 ( 24 ) SAMEP
penyelesaian atau jika diperintahkan juga memeperbaiki
segala kerusakan yang diakibatkannya
Jalan masuk ke empat pekerjaan harus diadakan oleh
Pemborong bilamana diperlukan disesuaikan dengan Rp
kebutuhan dan kepentingan lokasi proyek tersebut ( jalan
masukNo.
DAFTAR dicor1 beton
PEK.sementara ) . Selama
PERSIAPAN, masa pembangunan
PRASARANA DAN PENUNJANG ( Preliminaries )
pihak pemborong harus mengadakan dan memelihara
seluruh jalan - jalan semetara, jembatan -jembatan, dsb yang
mungkin diperlukan untuk memasuki bagian pekerjaan dan
menyingkirkan / membersihkan kembali pada waktu
penyelesaian atau jika diperintahkan juga memeperbaiki
segala kerusakan yang diakibatkannya

23 Pengukuran dan Bouwplank (Setting Out) ls 1.00 31,500,000 31,500,000

Pemborong harus menyediakan perlatan yang diperlukan


seperti alat ukur optik, waterpass, theodolite, dll, dan juru ukur
yang berpengalaman yang sewaktu-waktu dapat ditugaskan
untuk pengukuran as-as bangunan (vertikal dan horizontal)
serta untuk pembuatan peta kontur tanah di lapangan.

24 Pagar Proyek Sementara ls 1.00 225,000,000 225,000,000


Pagar Proyek Sementara berikut pintu-pintu tinggi 180 cm
terbuat dari seng gelombang BJLS 30 dipasang dengan
rangka dan skur kayu borneo termasuk pengecatan dan
pembongkarannya setelah tidak diperlukan lagi.

25 Kerusakan/Kerugian Terhadap Bangunan Lain ls 1.00 3,374,873,691 3,374,873,691


Semua kerusakan/kerugian terhadap bangunan / jaringan
instalasi di sekitarnya maupun jaringan- jaringan instalasi
yang sudah ada dari PLN, PAM, Perumtel, PU, dsb. di lokasi
proyek dalam waktu pelaksanaan menjadi tanggung jawab
sepenuh-nya oleh Pemborong.

Pemborong harus membebaskan Pemberi Tugas dari


tuntutan Pihak Ketiga terhadap kerugian dan pembayaran
ganti rugi atas segala kehilangan-kehilangan, gangguan-
gangguan yang diakibatkan oleh getaran, suara, debu, dan
lain-lain, dan kerusakan-kerusakan yang timbul sebagai
konsekwensi dari pelaksanaan pembangunan.

Pemborong juga bertanggung jawab atas terhentinya


kegiatan pelaksanaan yang diakibatkan dan semua biaya
yang timbul menjadi beban Pemborong bersangkutan.

26 Pemindahan jaringan-jaringan instalasi ls 1.00 1,000,000,000 1,000,000,000


Pemindahan jaringan-jaringan instalasi tersebut di atas juga
menjadi tanggung jawab Pemborong jika jaringan tersebut
mengganggu dalam pelaksanaan proyek tersebut termasuk
pengurusan izin-izin pada instansi yang bersangkutan.

27 Asuransi CAR dan TPL


Pemborong harus menutup seluruh biaya asuransi serta biaya-
biaya lain yang sehubungan dengan asuransi :
a) Asuransi pekerjaan Construction All Risk ( CAR ), Third Party ls 1.00 224,000,000 224,000,000
Liability ('TPL) dan Personal Accident (PA)
b) Biaya deductible dari asuransi CAR dan TPL (jika CAR dan ls 1.00 286,000,000 286,000,000
TPL ditutup oleh Pemberi Tugas) ditanggung oleh Pemborong
c) ls 1.00 40,000,000 40,000,000
Asuransi tenaga kerja (ASTEK) untuk pekerja dan staff
pemborong yang bekerja di dalam proyek ini sesuai ketentuan
dari Undang- Undang Kecelakaan bagi para pekerja.

d) Asuransi peralatan yang dimilikinya yang digunakan dalam ls 1.00 545,000,000 545,000,000
proyek ini.

28 Biaya Testing dan Commissioning


Termasuk operasi lengkap dengan Instalasi dan
pengabelan dari Panel (sumber daya) sampai ke alat
(mesin) yang mau ditest termasuk pengadaan air dan
penunjang lainnya, serta melatih personel dan
menyediakan buku petunjuk yang merupakan tanggung
jawab kontraktor dan sesuai kondisi didalam Dokumen
Tender untuk lingkup pekerjaan, sebagai berikut :
(1). MEKANIKAL & ELEKTRIKAL Jumlah 1.00 100,000,000 100,000,000

29 Biaya Service Dan Pemeliharaan


Biaya Service dan pemeliharaan setahun lengkap dengan
peralatan atau perkakas dan alat - alat bantu, sesuai

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-1 ( 25 ) SAMEP


Rp

DAFTAR No. 1 PEK. PERSIAPAN, PRASARANA DAN PENUNJANG ( Preliminaries )

dengan spesifikasi service dan pemeliharaan untuk


pekerjaan sebagai berikut :
(1). MEKANIKAL & ELEKTRIKAL Jumlah 1.00 100,000,000 100,000,000

11,647,333,691

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-1 ( 26 ) SAMEP


DAFTAR No. II.1 - PEKERJAAN STRUKTUR SPECTATOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. II.1.1 - PEKERJAAN PONDASI BORPILE

Catatan Harga ( Pricing Notes ) :

I Harga satuan Bored piles sudah termasuk :


- Pencatatan setiap tiang sesuai spesifikasi teknis.
- Platform alat boring, casing, dll.
- Alat-alat bantu yang diperlukan

II Harga satuan untuk pengeboran ( boring ) dan buang tanah sudah harus
diperhitungkan kemungkinan resiko longsor, pengeboran yang terkena pondasi
dan / atau konstruksi bangunan existing yang masih tertanam pembuangan sisa-
sisa akar tanaman.

III
Harga satuan beton sudah termasukoverbreak beton,semua
yang diperlukan seperti kubus beton, penyiraman, sambungan-
sambungan perhentian beton, pembuatan parit-parit, dsb.

IV Harga satuan untuk pembesian termasuk juga semua yang


diperlukan seperti besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat dan bendraad.

V
Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk
diameter yang sama menjadi tanggung jawab kontraktor

VI Tabel berat yang dipakai dalam menghitung berat besi dalam


daftar ini, adalah :
Diameter Kg/m
8 mm 0,395
10 mm 0,617
13 mm 1,042
16 mm 1,578
19 mm 2,226
22 mm 2,985
25 mm 3,853
29 mm 5,185
32 mm 6,315

VII Harus sesuai gambar dan syarat-syarat teknis pelaksanaan.


VIII Volume galian, urugan, buangan dihitung netto, tidak ada
ekstra untuk tempat kerja.

IX Harga satuan pekerjaan buang tanah lumpur harus sudah


diperhitungkan pekerjaan urugan kembali tiang bor sementara,
sesuai petunjuk MK atau Project manager

X Pembuangan tanah di lokasi proyek (jika ada) sudah termasuk


biaya kebersihan pada area pengeboran.

XI Harga satuan pekerjaan keseluruhan sudah termasuk biaya pemasangan


(ongkos kerja).

2.1 Pengeboran sampai level permukaan, pada :

Pondasi Bored piles :

A Pengeboran Pondasi Bored piles , Ø = 600 mm


Kedalaman pengeboran = 14 m,boredpile =124 titik m' 1,736 - 222,591 386,418,729 -

2.2 Buang tanah + lumpur dari pengeboran ke luar lokasi proyek


( Out site )
( Volume dihitung netto ) pada :

1.Pondasi Bored piles :

A Tanah Ex Pengeboran Pondasi Bored piles , Ø = 600 mm


Kedalaman = 14 m,boredpile =124 titik m3 5,113 - 38,950 199,139,860 -

2.3 Beton mutu ( K-500 ) dengan slump 12cm - 14 cm pada :


1.Pondasi Bored piles :

B Pondasi Bored piles , Ø = 600 mm


Kedalaman = 14 m,boredpile =124 titik m3 491 - 897,050 440,086,989 -

2.4 Pembesian / BJTD 40 / BJTP 24 / pada Bored piles :


1.Pondasi Bored piles :

C Pondasi Bored piles , Ø = 600 mm


Kedalaman = 14 m,boredpile =124 titik kg 39,099 - 8,859 346,354,351 -

3.1 Pekerjaan Pengeboran sampai level permukaan, pada :

1.Contingeous piles :
A Pengeboran Contingeous piles , Ø = 600 mm
Kedalaman pengeboran = …. m, Contingeous pile = …. Unit m' - Exclude - -

3.2 Pekerjaan Buang tanah + lumpur dari pengeboran ke luar lokasi proyek
( Out site ) ( Volume dihitung netto ) pada :

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-II.1.1 ( 27 ) PONDASI


DAFTAR No. II.1 - PEKERJAAN STRUKTUR SPECTATOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
Contingeous piles :

C Contingeous piles , Ø = 600 mm


Kedalaman = …. m, Contingeous pile = ... Unit m3 - Exclude - -

3.3 Pekerjaan Beton mutu ( K-500 ) dengan slump 12cm - 14 cm pada :

1.Contingeous piles :
E Pengeboran Contingeous piles , Ø = 600 mm
Kedalaman pengeboran = …. m, Contingeous pile = …. Unit m3 - Exclude - -

3.4 Pekerjaan Pembesian / BJTD 40 / BJTP 24 / pada :

1.Contingeous piles :
G Contingeous piles , Ø = 600 mm
Kedalaman = …. m, Contingeous pile = ... Unit kg - Exclude - -

3.5 Potong Kepala Tiang borepile termasuk buang puing keluar site
I Contingeous piles , Ø = 600 mm = …. Bh bh - by Others - -

4.1 Pile Test : ( USE PILE )

Axial Loading Test (Test Reaksi), 250% x Design Axial Load ( Beban = 250% x
A Bh 1.00 - 37,840,544 37,840,544 -
400 T = 1000 T ) - Diameter 600mm

B Mobilisasi/demobilisasi untuk peralatan test reaksi Bh 1.00 - 429,601,467 429,601,467 -

C PDA Test Bh 2.00 - 7,790,700 15,581,400 -

D Mobilisasi/demobilisasi untuk peralatan test PDA Bh 1.00 - 8,903,657 8,903,657 -

D PIT Test Bh 1.00 - 38,953,501 38,953,501 -

D Mobilisasi/demobilisasi untuk peralatan test PIT Bh 1.00 - termasuk - -

DAFTAR No. II.1.1 - PEKERJAAN PONDASI BORPILE


Dipindahkan ke Penjumlahan Total 1,902,880,498 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-II.1.1 ( 28 ) PONDASI


DAFTAR No. II.1 - PEKERJAAN STRUKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR No. II.1.2 - PEKERJAAN TANAH

II.1.2.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko longsoran,
volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah


termasuk kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi dan
tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan sesuai
gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-II.1.2 ( 29 ) TANAH


DAFTAR No. II.1 - PEKERJAAN STRUKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp
A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan ls Exclude - -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan) untuk
urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pile Cap m3 737.78 - 55,640 41,050,301 -
- Pile Cap (area spectator tribune) m3 138.89 - 55,640 7,728,062 -
- Tie beam (area spectator tribune) m3 18.90 - 55,640 1,051,854 -
- Pit lift (area spectator tribune) m3 95.78 - 55,640 5,329,458 -
- Tangga (area spectator tribune) m3 16.88 - 55,640 938,925 -
- Bio Tank Tribun Utara m3 42.70 55,640 2,375,828 -
- Bio Tank Tribun Selatan m3 42.70 55,640 2,375,828 -

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu berikut
peralatan perlengkapan sesuai spesifikasi dan gambar
- Pile Cap m3 35.86 - 272,340 9,766,943 -
- Pile Cap (area spectator tribune) m3 8.67 - 272,340 2,361,392 -
- Tie beam (area spectator tribune) m3 2.93 - 272,340 798,779 -
- Pit lift (area spectator tribune) m3 4.46 - 272,340 1,213,302 -
- Tangga (area spectator tribune) m3 1.13 - 272,340 306,383 -

Urugan tanah untuk mencapai level yang diinginkan, termasuk pemadatan,


dengan memaksimalkan tanah dipakai dari bekas galian serta tanah dari luar
site jika diperlukan sesuai spek dan gambar
- Pile Cap m3 701.92 - 55,648 39,060,396 -
- Pile Cap (area spectator tribune) m3 114.30 - 55,648 6,360,439 -
- Tangga (area spectator tribune) m3 13.50 - 55,648 751,246 -

D Pek. Lain - Lain


D.1 Pek. Bobok kepala tiang Pondasi Pancang

Bobok kepala Borpile, termasuk buang keluar lokasi proyek sesuai spesifikasi
dan gambar

- Borpile diameter 600 mm ttk 124.00 - 83,472 10,350,502 -


D.2 Pekerjaan Anti rayap
Anti rayap pada Lantai, termasuk alat - alat bantu, peralatan perlengkapan m2 269.23 - 16,690 4,493,416 -
sesuai spesifikasi dan gambar

D.3 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan
sesuai spesifikasi dan gambar (Kontraktor diminta untuk melampirkan
breakdown harganya) Ls 1.00 - Exclude - -

DAFTAR No. II.1.2 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 136,313,053 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-II.1.2 ( 30 ) TANAH


DAFTAR No. II.1 - PEKERJAAN STRUKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.1.3 - PEKERJAAN STRUKTUR BETON

II.1.3.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- II.1.3 ( 31 ) BETON


DAFTAR No. II.1 - PEKERJAAN STRUKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.1.3 - PEKERJAAN STRUKTUR BETON

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Dibawah Tie beam (area spectator tribune) m3 1.47 - 667,780 979,306 -
2) Pile cap m3 358.63 - 667,780 239,486,283 -
3) Pile Cap (area spectator tribune) m3 4.34 - 667,780 2,895,077 -
4) Pit lift (area spectator tribune) m3 2.23 - 667,780 1,487,513 -
5) Pondasi Tangga (area spectator tribune) m3 0.56 - 667,780 375,626 -
6) Bio Tank Tribun Utara m3 1.66 667,780.00 1,108,515 -
7) Bio Tank Tribun Selatan m3 1.66 667,780.00 1,108,515 -

B Beton mutu K-300 :


1) Pile cap m3 625.97 - 759,480 475,408,226 -
2) Pile Cap (area spectator tribune) m3 28.12 - 759,480 21,355,059 -
3) Tie beam (area spectator tribune) m3 14.42 - 759,480 10,953,676 -
4) Bio Tank Tribun Utara m3 15.41 759,480.00 11,702,068
5) Bio Tank Tribun Selatan m3 15.41 759,480.00 11,702,068

C Beton mutu K-350 :


4) Pelat (area spectator tribune), pada:
- Lantai 2 m3 8.99 - 782,410 7,033,147 -
- Lantai 3 m3 8.99 - 782,410 7,033,147 -
- Lantai 4 m3 31.48 - 782,410 24,634,093 -

5) Balok (area spectator tribune), pada:


- Lantai 2 m3 1.28 - 782,410 1,001,487 -
- Lantai 3 m3 1.28 - 782,410 1,001,487 -
- Lantai 4 m3 0.78 - 782,410 608,959 -

6) Kolom (area spectator tribune), pada:


- Lantai 1 m3 6.88 (0.30) 782,410 5,386,365 (238,107)
- Lantai 2 m3 4.57 (0.51) 782,410 3,576,298 (399,714)
- Lantai 3 m3 3.88 (0.07) 782,410 3,037,609 (51,619)

7) Pit lift (area spectator tribune), pada:


- Lantai 1 m3 31.97 - 782,410 25,016,230 -

8) Pondasi Tangga (area spectator tribune)


- Lantai 1 m3 8.35 - 782,410 6,536,058 -

9) Tangga (area spectator tribune)


- Lantai 1 m3 14.33 - 782,410 11,213,745 -
- Lantai 2 m3 14.64 - 782,410 11,450,811 -
- Lantai 3 m3 8.85 - 782,410 6,926,995 -

PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M9-150
1) Pelat, pada:
- Lantai 4 m2 189.16 - 66,090 12,501,861 -

B Wiremesh 2 lapis M9-150


1) Pelat, pada:
- Lantai 2 m2 59.93 - 124,830 7,480,714 -
- Lantai 3 m2 59.93 - 124,830 7,480,714 -
- Lantai 4 m2 83.79 - 124,830 10,459,483 -

A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:


1) Pile cap kg 69,199.58 - 8,859 613,004,436 -
2) Pile Cap (area spectator tribune) kg 4,656.90 - 8,859 41,253,189 -
3) Tie beam (area spectator tribune) kg 3,041.43 - 8,859 26,942,489 -

4) Pelat (area spectator tribune), pada:


- Lantai 2 kg 93.28 - 8,859 826,351 -
- Lantai 3 kg 93.28 - 8,859 826,351 -
- Lantai 4 kg 126.11 - 8,859 1,117,102 -

5) Balok (area spectator tribune), pada:


- Lantai 2 kg 632.82 - 8,859 5,605,845 -
- Lantai 3 kg 632.82 - 8,859 5,605,845 -
- Lantai 4 kg 374.04 - 8,859 3,313,459 -

A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40: - lanjutan

6) Kolom, pada:
- Lantai 1 kg 2,012.74 (518.22) 8,859 17,829,841 (4,590,681)
- Lantai 2 kg 1,255.57 (414.20) 8,859 11,122,463 (3,669,174)
- Lantai 3 kg 909.33 (183.39) 8,859 8,055,323 (1,624,519)

7) Pit lift (area spectator tribune), pada:

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- II.1.3 ( 32 ) BETON


DAFTAR No. II.1 - PEKERJAAN STRUKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.1.3 - PEKERJAAN STRUKTUR BETON

- Lantai 1 kg 6,422.52 - 8,859 56,893,906 -

8) Pondasi Tangga (area spectator tribune)


- Lantai 1 kg 1,756.94 - 8,859 15,563,866 -

9) Tangga (area spectator tribune)


- Lantai 1 kg 2,947.40 - 8,859 26,109,574 -
- Lantai 2 kg 3,000.67 - 8,859 26,581,460 -
- Lantai 3 kg 1,748.36 - 8,859 15,487,877 -
10) Bio Tank
- Bio Tank Tribun Utara kg 2,311.00 8,858.50 20,471,994
- Bio Tank Tribun Selatan kg 2,311.00 8,858.50 20,471,994

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap m2 524.29 - 84,790 44,454,743 -
2) Tie beam (area spectator tribune) m2 98.28 - 84,790 8,333,500 -
3) Sisi tegak pile cap (area spectator tribune) m2 99.51 - 84,790 8,437,453 -

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada:
- Lantai 2 (Bawah pelat, bawah balok dan sisi tegak) m2 69.19 - 134,520 9,306,908 -
- Lantai 3 (Bawah pelat, bawah balok dan sisi tegak) m2 69.19 - 134,520 9,306,908 -
- Lantai 4 (Bawah pelat, bawah balok dan sisi tegak) m2 299.63 - 134,520 40,305,627 -

2) Kolom, pada:
- Lantai 1 m2 121.37 (5.37) 163,870 19,888,083 (879,163)
- Lantai 2 m2 76.50 (10.90) 163,870 12,536,055 (1,786,183)
- Lantai 3 m2 62.73 (1.07) 163,870 10,279,565 (174,685)

3) Balok (area spectator tribune), pada:


- Lantai 2 m2 17.07 - 163,870 2,796,720 -
- Lantai 3 m2 17.07 - 163,870 2,796,720 -
- Lantai 4 m2 10.38 - 163,870 1,700,561 -

4) Pit lift (area spectator tribune), pada:


- Lantai 1 m2 200.04 - 163,870 32,780,883 -

5) Pondasi Tangga (area spectator tribune)


- Lantai 1 m2 64.84 - 163,360 10,591,446 -

9) Tangga (area spectator tribune)


- Lantai 1 m2 129.25 - 163,360 21,115,037 -
- Lantai 2 m2 132.72 - 163,360 21,680,375 -
- Lantai 3 m2 80.63 - 163,360 13,171,156 -

10) Bio Tank


- Bio Tank Tribun Utara m2 108.24 163,360.00 17,681,335
- Bio Tank Tribun Selatan m2 108.24 163,360.00 17,681,335 -

PEKERJAAN LAIN-LAIN (Provisional)


Perkuatan carbon fiber sesuai dengan gambar dan spesifikasi,
A
pada :
1) Balok
- Lantai 2 m2 894.99 - 779,070 697,256,398 -
- Lantai 3 m2 575.63 - 779,070 448,452,179 -
- Lantai 4 m2 626.54 - 779,070 488,118,084 -
2) Kolom
- Lantai 1 m2 319.33 - 779,070 248,781,987 -
- Lantai 2 m2 305.55 - 779,070 238,044,844 -
- Lantai 3 m2 248.85 - 779,070 193,871,574 -

Peninggian elevasi sesuai dengan gambar dan spesifikasi,


B
pada :
1) Beton 6,5 cm
- Beton m3 1.54 - 667,780 1,028,611 -
- Bekesting m2 3.86 - 163,870 632,745 -

2) Bata ringan tinggi 22,5 cm m2 28.49 - 87,470 2,491,985 -

E Water Stop sesuai dengan gambar dan spesifikasi, pada :


1) Pit lift m' 47.48 - 94,600 4,491,608 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- II.1.3 ( 33 ) BETON


DAFTAR No. II.1 - PEKERJAAN STRUKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.1.3 - PEKERJAAN STRUKTUR BETON

DAFTAR NO. II.1.3 - PEKERJAAN STRUKTUR BETON


Dipindahkan ke Penjumlahan Total 4,476,038,921 (13,413,845)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- II.1.3 ( 34 ) BETON


DAFTAR No. II.1 - PEKERJAAN STRUKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.1.4 - PEKERJAAN STRUKTUR BAJA

II.1.4.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-
lubang baut, perapihan dengan gerinda, penyediaan
peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi


dan pengiriman ke lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi

I Kolom baja
1) WF 500 x 200 x 12 x 19 Kg 34,006.48 18,364 624,487,969 -
2) WF 400 x 200 x 8 x 13 Kg 22,139.04 18,364 406,556,754 -
3) WF 300 x 300 x 10 x 15 Kg 245,385.12 18,364 4,506,201,619 -
4) WF 300 x 150 x 6,5 x 9 Kg 19,488.80 18,364 357,888,313 -
5) WF 250 x 250 x 9 x 14 Kg 35,910.40 18,364 659,451,162 -
6) WF 250 x 125 x 6 x 9 Kg 8,317.01 18,364 152,731,816 -
7) WF 200 x 200 x 8 x 12 Kg 27,642.60 18,364 507,623,066 -
8) WF 200 x 150 x 6 x 9 Kg 3,938.83 18,364 72,331,897 -
9) WF 200 x 100 x 5,5 x 8 Kg 22,333.12 18,364 410,120,825 -
10) WF 200 x 100 x 5,5 x 8 Kg 22,333.12 18,364 410,120,825 -
11) CNP 150 x 50 x 20 x 2,3 Kg 10,198.00 18,364 187,273,964 -
12) L 150 x 150 x 15 Kg 49,929.51 18,364 916,895,158 -
13) L 120 x 120 x 12 Kg 75,961.15 18,364 1,394,934,893 -
14) L 100 x 100 x 10 Kg 56,158.71 18,364 1,031,286,978 -
15) L 90 x 90 x 10 Kg 10,400.60 18,364 190,994,468 -
16) L 90 x 90 x 7 Kg 2,938.38 18,364 53,959,729 -
17) L 80 x 80 x 6 Kg 22,367.58 18,364 410,753,571 -
18) L 70 x 70 x 6 Kg 5,716.48 18,364 104,976,257 -
19) L 60 x 60 x 6 Kg 20,171.45 18,364 370,424,301 -
20) L 60 x 60 x 5 Kg 9,913.27 18,364 182,045,186 -
21) L 50 x 50 x 5 Kg 17,394.37 18,364 319,426,630 -
22) L 50 x 50 x 4 Kg 1,367.98 18,364 25,121,375 -
23) L 40 x 40 x 4 Kg 1,136.82 18,364 20,876,313 -
24) baut 2 m12 bh 21,320.00 31,163 664,390,912 -
25) baut m12 (provisional) bh 4,040.00 31,163 125,897,715 -
26) plat t=5mm kg 461.45 17,807 8,217,197 -
27) L 40x40x4 @400mm kg 2,968.78 18,364 54,518,036 -
28) plat t=6mm kg 787.74 17,807 14,027,607 -
29) plat t=7mm kg 454.19 17,807 8,087,988 -
30) baut 2 m20 bh 9,520.00 17,807 169,525,636 -
31) plat t=8mm kg 3,095.09 17,807 55,115,160 -
32) plat t=9mm kg 2,543.69 17,807 45,296,257 -
33) baut 2 m16 bh 4,008.00 31,163 124,900,505 -
34) plat t=10mm kg 1,478.94 17,807 26,335,950 -
35) plat t=12mm kg 16,460.16 17,807 293,111,300 -
36) baut 3 m25 bh 2,016.00 31,163 62,824,206 -
37) plat t=15mm kg 8,969.58 17,807 159,724,148 -
38) plat t=16mm kg 8,862.34 17,807 157,814,406 -
39) plat t=18mm kg 7,536.82 17,807 134,210,444 -
40) plat t=5mm (Provisional) kg 2,423.30 17,807 43,152,377 -
41) plat t=8mm (Provisional) kg 2,631.95 17,807 46,867,926 -
42) Stifner t=8mm kg 1,032.43 17,807 18,384,842 -
44) Stifner t=9mm kg 254.34 17,807 4,529,112 -
45) Stifner t=12mm kg 4,755.22 17,807 84,677,628 -
46) Box 400x200x6,3 Kg 32,967.74 18,364 605,412,726 -
45) Box 300x200x6,3 Kg 10,273.83 18,364 188,666,512 -
46) Box 200x100x6,3 Kg 2,515.42 18,364 46,192,701 -

II Kolom baja-Lanjutan

47) Box 180x100x6,3 Kg 2,734.66 18,364 50,218,812 -


48) HB 300 x 300 x 10 x 15 Kg 8,422.40 18,364 154,667,213 -
49) Siku 2L 120 x 120 x 12 Kg 2,426.70 18,364 44,563,491 -
50) Stiffner Plate 12mm Kg 82.29 17,807 1,465,419 -
51) Plate 6mm Kg 82.43 17,807 1,467,768 -
52) Angkur Baut M16, L = 500mm Bh 112.00 222,591 24,930,241 -
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- II.1.4 ( 35 ) BAJA
DAFTAR No. II.1 - PEKERJAAN STRUKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
53) Baut dia 22 (HTB A325) Bh 56.00 31,163 1,745,117 -
54) Non Shrink Grout, t = 25mm titik 28.00 50,083 1,402,326 -
55) Shear Stud M22 @120, panjang 75 mm Bh 2,016.00 83,472 168,279,124 -
56) Shear Stud M16 @50, panjang 50 mm Bh 784.00 66,777 52,353,505 -
57) Beton (Kolom Pedestal) m3 0.61 759,480 465,182 -
58) Besi (Kolom Pedestal) kg 9.80 8,859 86,813 -
59) Bekisting (Kolom Pedestal) m2 357.09 129,920 46,392,956 -
60) Cat Dasar Kg 849,380.11 3,339 2,835,971,042 -

III Balok area Spectator tribune


Lantai 2
1) WF 250 x 125 x 6 x 9 Kg 475.08 18,364 8,724,271 -
2) WF 300 x 150 x 6,5 x 9 Kg 1,541.77 18,364 28,312,690 -
3) WF 350 x 175 x 7 x 11 Kg 2,232.00 18,364 40,987,987 -
4) Plate T=10mm Kg 301.15 17,807 5,362,595 -
5) Anchourage M16 Bh 390.00 222,591 86,810,659 -
6) Baut M16 Bh 84.00 31,163 2,617,675 -
7) Shear Connector 2 dia19 - 175mm Kg 124.19 18,364 2,280,536 -
8) Cat Dasar Kg 4,674.18 3,339 15,606,484 -

Lantai 3
1) WF 250 x 125 x 6 x 9 Kg 375.92 18,364 6,903,317 -
2) WF 300 x 150 x 6,5 x 9 Kg 1,000.44 18,364 18,371,910 -
3) WF 350 x 175 x 7 x 11 Kg 2,232.00 18,364 40,987,987 -
4) Plate T=10mm Kg 260.33 17,807 4,635,700 -
5) Anchourage M16 Bh 318.00 222,591 70,784,076 -
6) Baut M16 Bh 84.00 31,163 2,617,675 -
7) Shear Connector 2 dia19 - 175mm Kg 99.71 18,364 1,830,968 -
8) Cat Dasar Kg 3,968.39 3,339 13,249,954 -

Lantai 4
1) WF 250 x 125 x 6 x 9 Kg 375.92 18,364 6,903,317 -
2) WF 300 x 150 x 6,5 x 9 Kg 1,307.80 18,364 24,016,251 -
3) WF 350 x 175 x 7 x 11 Kg 2,232.00 18,364 40,987,987 -
4) UNP 200 x 80 x 7,5 Kg 7,291.44 18,364 133,898,497 -
5) UNP 150 x 75 x 6,5 Kg 1,307.12 18,364 24,003,681 -
6) Plate T=10mm Kg 274.85 17,807 4,894,307 -
7) Anchourage M16 Bh 336.00 222,591 74,790,722 -
8) Baut M16 Bh 90.00 31,163 2,804,652 -
9) Shear Connector 2 dia19 - 175mm Kg 110.83 18,364 2,035,317 -
10) Cat Dasar Kg 12,899.97 3,339 43,071,328 -

IV Kolom area Spectator tribune


Lantai 1, lantai 2 dan Lantai 3
1) kolom H Beam kg 5,550.88 18,364 101,935,139 -
2) Plate t=12mm uk 30 cm x 30 cm kg 76.30 17,807 1,358,734 -
3) Angkur 4 M16, tinggi 30cm bh 36.00 222,591 8,013,292 -
4) Plate t=20mm uk 25 cm x 25 cm kg 441.56 17,807 7,863,042 -
5) Angkur 4 M19, tinggi 30cm bh 180.00 222,591 40,066,458 -
6) Cat Dasar kg 6,068.74 3,339 20,262,745 -
7) Cat Finish kg 292.30 3,339 975,959 -

IV separator beam
1) WF 300 x 150 x 6,5 x 9 Kg 4,903.12 18,364 90,039,882 -
2) Plate T=10mm Kg 489.84 17,807 8,722,735 -
3) Anchourage M16 Bh 624.00 222,591 138,897,055 -
4) Cat Dasar kg 5,392.96 3,339 18,006,400 -
7) Cat Finish kg 5,527.12 3,339 18,454,343 -

DAFTAR NO. II.1.4 - PEKERJAAN STRUKTUR BAJA 21,004,459,698 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- II.1.4 ( 36 ) BAJA


DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.1. - PEKERJAAN DINDING

II.2.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah


termasuk adukan biasa atau drymix, kolom praktis, ringbalk,
angkur, sparing dan semua pekerjaan bantu yang berhubungan
dengan pekerjaan dinding tersebut.

II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton maupun
bata , kawat ayam (jika diperlukan) dan semua pekerjaan bantu
yang berhubungan dengan plesteran. Volume plesteran dan
acian sudah ditambahkan 10cm di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit,


marmer, keramik, porselin) sudah termasuk adukan, cor
beton,perekat (calbond), angkur, kawat pengikat alumunium
fixing pada dinding dengan ketinggian lebih dari 2m,
pemotongan, pinggulan, adu manis, naad, dan alat bantu
lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk


dinding kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian


cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi.

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. primacon,


termasuk dinding penebalan,urinoir, perekat, adukan kering
kolom
- Lantaidan
1 balok praktis sesuai spesifikasi dan gambar : m2 1,961.01 24.78 103,480 202,925,347 2,564,400
- Lantai 2 m2 1,170.33 0.20 103,480 121,105,413 20,812
- Lantai 3 m2 1,297.95 (89.06) 103,480 134,312,166 (9,216,237)
- Lantai 4 m2 1,424.09 (58.17) 103,480 147,364,811 (6,019,357)

II PEK. PELAPIS DINDING

A Plesteran dan Acian, Plesteran halus berikut acian halus,


termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :
- Lantai 1 m2 2,178.41 (374.15) 61,540 134,059,647 (23,025,464)
- Lantai 2 m2 1,383.57 281.69 61,540 85,144,742 17,335,236
- Lantai 3 m2 1,454.01 (165.58) 61,540 89,480,038 (10,189,869)
- Lantai 4 m2 2,277.85 - 61,540 140,179,165 -
- Area Exterior m2 1,320.67 (370.22) 61,540 81,273,810 (22,783,117)
Homogenus Tile 600x600 ex Setara Niro granite / Essenza
B
(Polished), sesuai spesifikasi dan gambar ;
- Lantai 1
Lobby Lift Service m2 4.07 0.59 348,040 1,415,479 206,388
Male Toilet Athelete Room m2 40.78 (1.02) 348,040 14,193,767 (355,697)
Female Toilet Athelete Room m2 40.46 3.78 348,040 14,081,698 1,315,591
Male Toilet As. 1-A m2 48.11 (0.23) 348,040 16,745,040 (80,884)
Female Toilet As. 1-A m2 32.56 0.95 348,040 11,333,575 331,334
Disable Toilet As. 1-A m2 21.33 0.25 348,040 7,425,225 85,479
Janitor As. 1-A m2 14.79 (0.23) 348,040 5,148,904 (78,657)
Male Toilet Musholla m2 70.26 (31.62) 348,040 24,452,455 (11,004,190)
Female Toilet Musholla m2 46.44 (0.12) 348,040 16,163,813 (42,600)
Disable Toilet Musholla m2 25.26 0.27 348,040 8,790,516 94,249
Janitor Musholla m2 16.18 (0.24) 348,040 5,631,287 (83,530)
Ablution m2 33.60 (0.14) 348,040 11,694,144 (48,726)
Homogenus Tile 600x600 ex Setara Niro granite / Essenza
B
(Polished), sesuai spesifikasi dan gambar ;-Lanjutan
- Lantai 2
Male Toilet As. 8-D m2 48.53 6.05 348,040 16,891,773 2,104,250
Female Toilet As. 8-D m2 46.01 5.85 348,040 16,014,713 2,036,034
Janitor As. 8-D m2 20.02 2.50 348,040 6,966,369 871,492
Lobby Lift Service m2 4.07 0.59 348,040 1,415,479 206,388

- Lantai 3
Lobby Lift Service m2 4.07 0.59 348,040 1,415,479 206,388
Male Toilet As. 1-D m2 48.53 8.45 348,040 16,891,773 2,939,546
Female Toilet As. 1-D m2 46.01 8.25 348,040 16,014,713 2,871,330
Janitor As. 1-D m2 20.02 4.90 348,040 6,966,369 1,706,788
Male Toilet As. 8-D m2 37.11 19.87 348,040 12,917,157 6,914,163
Female Toilet As. 8-D m2 26.79 27.48 348,040 9,323,156 9,562,886
Janitor As. 8-D m2 20.02 4.90 348,040 6,966,369 1,706,788

- Lantai 4
Male Toilet As. 1-D m2 55.11 (6.39) 348,040 19,181,877 (2,222,583)
Female Toilet As. 1-D m2 40.17 14.69 348,040 13,979,932 5,113,543
Janitor As. 1-D m2 21.30 (0.18) 348,040 7,413,670 (63,065)
Men Ablution m2 17.88 0.46 348,040 6,222,955 158,706
Women Ablution m2 18.66 0.46 348,040 6,494,844 159,681
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.1. - PEKERJAAN DINDING


Lobby Lift Service m2 4.07 0.59 348,040 1,415,479 206,388
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.1. - PEKERJAAN DINDING

C Pengecatan dengan fin. cat Acrylic emulsion paint ex.setara ICI /


Jotun tipe ambience majestic, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :

- Lantai 1
Steward m2 87.90 0.33 18,360 1,613,807 6,096
Office m2 68.76 0.36 18,360 1,262,470 6,573
Secretariat Office m2 119.35 6.32 18,360 2,191,229 116,072
Retail 1 m2 56.86 1.76 18,360 1,044,014 32,282
Retail 2 m2 53.11 (1.73) 18,360 975,026 (31,800)
Retail 3 m2 53.11 (1.73) 18,360 975,026 (31,800)
Retail 4 m2 55.36 (2.32) 18,360 1,016,419 (42,531)
Retail 5 m2 71.64 2.40 18,360 1,315,365 44,152
Lobby As. 3-D m2 50.25 (1.39) 18,360 922,590 (25,520)
Lobby As. 6-D m2 39.53 (3.06) 18,360 725,679 (56,090)
Lobby Lift Service m2 28.21 1.14 18,360 517,899 21,004
Coridor Toilet Athelete Room m2 43.91 (4.49) 18,360 806,243 (82,491)
Athelete Room m2 124.57 1.91 18,360 2,287,078 35,095
Coridor Toilet As. 1-A m2 114.94 (14.29) 18,360 2,110,360 (262,426)
Coridor Toilet Musholla m2 104.03 12.90 18,360 1,910,080 236,791
Male Toilet Musholla m2 7.87 (0.03) 18,360 144,456 (514)
Musholla m2 94.27 (22.62) 18,360 1,730,886 (415,355)
Meeting Room m2 146.50 (146.50) 18,360 2,689,740 (2,689,740)
Lounge Waiting Room m2 81.62 75.19 18,360 1,498,626 1,380,461
Security Office m2 44.19 0.05 18,360 811,417 977
VIP Lobby & Lobby Lift m2 134.17 (61.39) 18,360 2,463,422 (1,127,108)
Public Hall m2 209.44 (111.51) 18,360 3,845,303 (2,047,368)
Stairs As. 3-D m2 50.89 37.12 18,360 934,304 681,523
Stairs As. 5-D m2 56.40 (4.26) 18,360 1,035,504 (78,214)

- Lantai 2
Multipurpose - 1 m2 106.05 10.24 18,360 1,947,078 188,006
Multipurpose - 2 m2 114.69 68.76 18,360 2,105,708 1,262,434
Multipurpose - 3 m2 244.51 18.15 18,360 4,489,240 333,289
Office Room - 1 m2 61.95 1.44 18,360 1,137,402 26,438
Office Room - 2 m2 45.98 0.62 18,360 844,101 11,291
Office Room - 3 m2 45.98 0.62 18,360 844,101 11,291
Control Room /IT Room m2 66.54 157.78 18,360 1,221,674 2,896,841
Coridor Toilet As. 8-D m2 36.00 9.21 18,360 660,960 169,004
Lobby Lift Service m2 23.03 4.15 18,360 422,794 76,139
OB Counter m2 65.22 (8.64) 18,360 1,197,347 (158,539)
Stairs As. 3-D m2 63.80 14.60 18,360 1,171,368 268,093
Stairs As. 5-D m2 56.40 (4.26) 18,360 1,035,504 (78,214)
C Pengecatan dengan fin. cat Acrylic emulsion paint ex.setara ICI /
Jotun tipe ambience majestic, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada : - lanjutan

- Lantai 3
Lobby Lift m2 24.22 0.39 18,360 444,700 7,174
Coridor m2 250.31 4.04 18,360 4,595,609 74,140
Room As. 1-B m2 67.88 0.53 18,360 1,246,185 9,639
Meeting Room As. 1'-B m2 66.74 0.02 18,360 1,225,255 275
Meeting Room As. 3-D m2 66.97 (7.90) 18,360 1,229,551 (145,026)
Meeting Room As. 4-D m2 49.85 9.26 18,360 915,154 169,922
Meeting Room As. 6-D m2 56.83 (6.22) 18,360 1,043,353 (114,153)
Meeting Room As. 7-D m2 35.03 15.17 18,360 643,059 278,429
VIP Room m2 67.68 6.56 18,360 1,242,605 120,350
Office m2 74.52 (0.15) 18,360 1,368,187 (2,754)
Press Conference Room m2 91.72 (0.28) 18,360 1,683,961 (5,122)
Announcer Box m2 32.18 (32.18) 18,360 590,733 (590,733)
Judges Room m2 43.32 2.07 18,360 795,355 38,005
Fei & Aef Room m2 56.61 (17.38) 18,360 1,039,360 (319,078)
Broadcast Room m2 56.61 (35.87) 18,360 1,039,360 (658,536)
Reporter Room m2 74.99 (13.21) 18,360 1,376,725 (242,471)
Lobby Lift Service m2 23.03 1.75 18,360 422,794 32,167
Coridor Toilet As. 1-D m2 36.00 1.32 18,360 660,960 24,235
Coridor Toilet As. 8-D m2 36.00 1.32 18,360 660,960 24,235
Female Toilet As. 8-D m2 5.29 0.65 18,360 97,058 11,927
OB Counter m2 56.64 (0.06) 18,360 1,039,910 (1,102)
Stairs As. 3-D m2 63.80 (3.23) 18,360 1,171,368 (59,266)
Stairs As. 5-D m2 56.40 (4.26) 18,360 1,035,504 (78,214)

- Lantai 4
Pre-Function Room & Lobby Lift m2 381.80 71.21 18,360 7,009,832 1,307,384
Function Room m2 647.71 120.80 18,360 11,891,999 2,217,942
Coridor Function Room m2 344.05 64.17 18,360 6,316,719 1,178,113
Coridor Toilet m2 77.05 14.37 18,360 1,414,702 263,852
Stairs As. 3-D m2 63.80 (3.23) 18,360 1,171,368 (59,266)
Athlete Dining m2 202.26 (56.58) 18,360 3,713,521 (1,038,744)
VIP Room m2 116.75 (48.83) 18,360 2,143,504 (896,493)
Coridor Toilet As. 1-D m2 40.83 8.47 18,360 749,694 155,454
Musholla m2 62.76 (3.12) 18,360 1,152,274 (57,283)
Lobby Lift Service m2 22.07 3.91 18,360 405,168 71,824
Storage As. C-8 m2 47.75 13.16 18,360 876,741 241,566
Storage As. C'-8 m2 68.10 18.58 18,360 1,250,367 341,169

D Pengecatan dengan fin. Washable paint (A.E.P) ex. Setara ICI /


Jotun tipe Easy clean majestic, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. dengan


Pengecatan II.2.1. - PEKERJAAN
fin. Washable DINDING
paint (A.E.P) ex. Setara ICI /
Jotun tipe Easy clean majestic, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
Pengecatan dengan fin. Washable paint (A.E.P) ex. Setara ICI /
Jotun tipe
DAFTAR Easy
NO. clean
II.2.1. majestic, termasuk
- PEKERJAAN peralatan dan
DINDING
perlengkapan sesuai spesifikasi dan gambar pada :

- Lantai 1
Panel Room m2 32.32 (3.72) 18,920 611,494 (70,382)
Fire Stairs As. 1-D m2 97.36 (6.37) 18,920 1,842,051 (120,566)
Fire Stairs As. 9-D m2 71.20 (6.07) 18,920 1,347,028 (114,825)
Male Toilet Athelete Room m2 18.64 0.28 18,920 352,631 5,335
Female Toilet Athelete Room m2 10.42 (0.06) 18,920 197,146 (1,135)
Male Toilet As. 1-A m2 12.02 0.06 18,920 227,335 1,218
Female Toilet As. 1-A m2 13.10 0.22 18,920 247,829 4,185
Male Toilet Musholla m2 21.52 (0.26) 18,920 407,204 (4,965)

- Lantai 2
Smoke Lobby m2 37.88 (9.08) 18,920 716,661 (171,765)
Fire Stairs As. 1-D m2 75.16 (0.79) 18,920 1,422,027 (15,022)
Fire Stairs As. 9-D m2 76.76 (9.05) 18,920 1,452,224 (171,150)
Room As. 1-B m2 47.75 0.41 18,920 903,335 7,663
Room As. 9-B m2 37.02 (0.60) 18,920 700,362 (11,295)

- Lantai 3
Smoke Lobby m2 28.32 0.48 18,920 535,814 9,082
Fire Stairs As. 1-D m2 75.16 (3.65) 18,920 1,422,027 (69,058)
Fire Stairs As. 9-D m2 69.56 3.09 18,920 1,316,075 58,463

E Pengecatan dengan fin. Washable paint (A.E.P) ex. Setara ICI /


Jotun tipe Easy clean majestic, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada : - Lanjutan

- Lantai 4
Smoke Lobby m2 28.29 (2.49) 18,920 535,247 (47,111)
Fire Stairs As. 1-D m2 75.20 (3.69) 18,920 1,422,784 (69,815)
Fire Stairs As. 9-D m2 76.76 (4.11) 18,920 1,452,224 (77,686)

F CAT WEATHERSHIELD
Pengecatan dengan fin. Weathershield ex.setara ICI/ Jotun tipe
Weathershield Jotashield, termasuk peralatan dan perlengkapan
sesuai spesifikasi dan gambar pada :

- Lantai 2
Tribune m2 229.79 503.58 29,490 6,776,521 14,850,502

- Lantai 3
Male Toilet As. 8-D m2 11.42 (11.42) 29,490 336,776 (336,776)
Female Toilet As. 8-D m2 13.94 (13.94) 29,490 411,091 (411,091)

- Lantai 4
Female Toilet As. 1-D m2 8.72 (8.72) 29,490 257,047 (257,047)

G Skim coat pada permukaan kolom beton, termasuk peralatan


dan perlengkapan sesuai spesifikasi dan gambar pada :
- Lantai 1 m2 64.64 168.66 33,950 2,194,562 5,726,014
- Lantai 2 m2 80.91 106.28 33,950 2,746,895 3,608,308
- Lantai 3 m2 193.10 0.40 33,950 6,555,742 13,617

H Penambahan pasir untuk lapisan carbon fiber pada permukaan


kolom beton, termasuk peralatan dan perlengkapan sesuai
spesifikasi dan gambar pada :(Provisional)

- Lantai 1 m2 64.64 - 779,070 50,359,865 -


- Lantai 2 m2 80.91 - 779,070 63,034,555 -
- Lantai 3 m2 193.10 - 779,070 150,438,350 -
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.1. - PEKERJAAN DINDING


DAFTAR NO. II.2.1. - PEKERJAAN DINDING 1,855,203,863 (1,185,713)
Dipindahkan ke Penjumlahan Total
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.2.2 - PEKERJAAN PINTU dan JENDELA

II.2.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis sekeliling
pintu & jendela, dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU BAJA

Pintu Baja SD1 terdiri dari 2 daun pintu, ukuran overall pintu
1500mm lebar x 2400mm , Fire rated 2 hour, kusen steel duco paint
finish termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Lift Lobby
- Lantai 1 unit 1.00 - 10,183,558 10,183,558 -
- Lantai 4 unit 1.00 - 10,183,558 10,183,558 -

Hardware :
Lockset Wilka Art-8379/855 HF BBKSS set 1.00 - Include
- Lockcase Namef art-1769.35/65 SS
- Cylinder Wilka art-1410.40 Nickel
- Panic bar aart-379 /855 BKSS
Hinges Gracia BB 4,5"x4x3 mm SS bh 6.00 - Include
Automatic Flush bolt art-375 MJ SS bh 2.00 - Include
Door selector art-N250 SS bh 1.00 - Include
Door closer dorma TS 300 EN 4 RA silver bh 2.00 - Include

Pintu Baja SD2 terdiri dari 1 daun pintu, ukuran overall pintu
1000mm lebar x 2400mm , Fire rated 2 hour, kusen steel duco paint
finish termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Fire stair
- Lantai 1 unit 2.00 - 6,469,064 12,938,127 -
- Lantai 2 unit 4.00 - 6,469,064 25,876,254 -
- Lantai 3 unit 4.00 - 6,469,064 25,876,254 -
- Lantai 4 unit 3.00 - 6,469,064 19,407,191 -

Hardware :
Lockset Wilka Art-8379/855 HF BBKSS set 1.00 - Include
- Lockcase Namef art-1769.35/65 SS
- Cylinder Wilka art-1410.40 Nickel
- Panic bar aart-379 /855 BKSS
Hinges Gracia BB 4,5"x4x3 mm SS bh 3.00 - Include
Door cleser dorma TS 300 EN 4 RA silver bh 1.00 - Include

Pintu Baja SD3 terdiri dari 1 daun pintu, ukuran overall pintu
1000mm lebar x 2400mm , Fire rated 2 hour, kusen steel duco paint
finish termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Panel room
- Lantai 1 unit 1.00 - 6,302,120 6,302,120 -

Hardware :
Lever handle art-306 SS psg 1.00 - Include
Lockcase Wilka art-1490.55 SS bh 1.00 - Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 - Include
Hinges Gracia B 4"x3"x3 mm SS bh 3.00 - Include
Door cleser dorma TS 300 EN 4 RA silver bh 1.00 - Include

Pintu Baja SD4 terdiri dari 2 pintu dan 4 daun pintu, ukuran overall
pintu 2480mm lebar x 2400mm , Non Fire rated, kusen steel duco
paint finish termasuk hardware dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
Electrical shaft
- Lantai 4 unit 1.00 - 9,474,048 9,474,048 -
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.2.2 - PEKERJAAN PINTU dan JENDELA


Hardware :
Ring handle art-8-3 SS bh 4.00 - Include
Shaft door art-542 Nickel bh 4.00 - Include
Anak kunci shaft door art-543 Nickel bh 4.00 - Include
Hinges Gracia B 4"x3"x3 mm SS bh 12.00 - Include

B PINTU KAYU
Pintu Kayu WD1 terdiri dari 1 daun pintu ukuran overall pintu
1100mm lebar x 2400mm,solid wood engineering T= 40 mm fin.
HPL wood grain finished ,kusen Alumunium 50/100 powder coating
finish termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Disable toilet
- Lantai 1 unit 2.00 - 3,812,435 7,624,870 -

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - Include
Door Closer DKS DCL 300 NHO NA set 1.00 - Include

B PINTU KAYU - Lanjutan

Pintu Kayu WD2 terdiri dari 1 daun pintu,solid wood engineering T=


40 mm fin. HPL wood grain finished ukuran overall pintu 900mm
lebar x 2400mm ,kusen Alumunium 50/100 powder coating finish
termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Toilet
- Lantai 1 unit 2.00 - 3,546,160 7,092,320 -
- Lantai 2 unit 2.00 - 3,546,160 7,092,320 -
- Lantai 3 unit 4.00 - 3,546,160 14,184,639 -
- Lantai 4 unit 2.00 - 3,546,160 7,092,320 -

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include

Pintu Kayu WD3 terdiri dari 1 daun pintu,solid wood engineering T=


40 mm fin. HPL wood grain finished ukuran overall pintu 900mm
lebar x 2400mm ,kusen Alumunium 50/100 powder coating finish
termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Janitor
- Lantai 1 unit 2.00 - 3,546,160 7,092,320 -
- Lantai 2 unit 1.00 - 3,546,160 3,546,160 -
- Lantai 3 unit 2.00 - 3,546,160 7,092,320 -
- Lantai 4 unit 1.00 - 3,546,160 3,546,160 -

Storage
- Lantai 2 unit 1.00 (1.00) 3,546,160 3,546,160 (3,546,160)
Pantry
- Lantai 3 unit 1.00 (1.00) 3,546,160 3,546,160 (3,546,160)
Service corridor
- Lantai 4 unit 1.00 (1.00) 3,546,160 3,546,160 (3,546,160)

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include

Pintu Kayu WD4 terdiri dari 1 daun pintu,solid wood engineering T=


40 mm fin. HPL wood grain finished ukuran overall pintu 1000mm
lebar x 2400mm ,kusen Alumunium 50/100 powder coating finish
termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Steward
- Lantai 1 unit 1.00 - 3,662,742 3,662,742 -
Office
- Lantai 1 unit 1.00 - 3,662,742 3,662,742 -
- Lantai 3 unit 2.00 (1.00) 3,662,742 7,325,484 (3,662,742)
VIP room
- Lantai 3 unit 1.00 - 3,662,742 3,662,742 -
Toilet
- Lantai 4 unit 1.00 (1.00) 3,662,742 3,662,742 (3,662,742)

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.2.2 - PEKERJAAN PINTU dan JENDELA


Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include

Pintu Kayu WD5 terdiri dari 1 pintu dan 2 daun pintu,solid wood
engineering T= 40 mm fin. HPL wood grain finished ukuran overall
pintu 1600mm lebar x 2400mm ,kusen Alumunium 50/100 powder
coating finish termasuk hardware dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
Secretariat office
- Lantai 1 unit 1.00 - 7,935,385 7,935,385 -
Athlete room
- Lantai 1 unit 1.00 - 7,935,385 7,935,385 -
Storage
- Lantai 4 unit 2.00 - 7,935,385 15,870,769 -
Function room
- Lantai 4 unit 3.00 7,935,385 23,806,154 -
VIP room
- Lantai 4 unit 1.00 1.00 7,935,385 7,935,385 7,935,385
Toilet
- Lantai 4 unit 1.00 7,935,385 7,935,385 -
Control room
- Lantai 4 unit 1.00 7,935,385 7,935,385 -

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include

B PINTU KAYU - Lanjutan

Pintu Kayu WD6 terdiri dari 1 daun pintu,solid wood engineering T=


40 mm fin. HPL wood grain finished ukuran overall pintu 1000mm
lebar x 2400mm ,kusen Alumunium 50/100 powder coating finish
termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Office
- Lantai 3 unit 1.00 - 3,662,742 3,662,742 -
- Lantai 4 unit 4.00 3,662,742 14,650,968 -

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include

Pintu Kayu WD7 terdiri dari 1 pintu dan 2 daun pintu,solid wood
engineering T= 40 mm fin. HPL wood grain finished ukuran overall
pintu 1600mm lebar x 2400mm ,kusen Alumunium 50/100 powder
coating finish termasuk hardware dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
VIP room
- Lantai 3 unit 1.00 - 7,935,385 7,935,385 -

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include

Pintu Kayu WD8 terdiri dari 1 pintu dan 2 daun pintu,solid wood
engineering T= 40 mm fin. HPL wood grain finished ukuran overall
pintu 2500mm lebar x 3000mm ,kusen Alumunium 50/100 powder
coating finish termasuk hardware dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
Function room
- Lantai 4 unit 3.00 - 7,848,296 23,544,887 -

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include

C PINTU KACA
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.2.2 - PEKERJAAN PINTU dan JENDELA

Pintu Kaca GD1, ukuran overall 7400x3000 mm dari kaca tempered


tinted glass tebal 12mm, lengkap terpasang termasuk kusen IWF
250x125 stailess steel (hairline finish), hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
Main Entrance
- Lantai 1 unit 4.00 - 118,620,266 474,481,064 -

Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include

Pintu Kaca GD2, ukuran overall 3575x3000 mm dari kaca tempered


clear tebal 12mm frameless, lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Lounge room

- Lantai 1 unit 1.00 - 19,263,079 19,263,079 -


Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include

Pintu Kaca GD3, ukuran overall 3575x2400 mm dari kaca tempered


clear tebal 12mm frameless, lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Lounge room
- Lantai 1 unit 2.00 15,017,323 30,034,645 -

Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.21 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include

Pintu Kaca GD4, ukuran overall 2450x2400 mm dari kaca tempered


clear tebal 12mm frameless, lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Acces to Tribune lantai 2
- Lantai 1 unit 1.00 (1.00) 13,962,077 13,962,077 (13,962,077)
- Lantai 2 unit 1.00 - 13,962,077 13,962,077 -

Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include

Pintu Kaca GD5, ukuran overall 2450x2400 mm dari kaca tempered


clear tebal 12mm frameless, lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Press conference
- Lantai 3 unit 1.00 - 13,962,077 13,962,077 -
Meeting room
- Lantai 3 unit 2.00 - 13,962,077 27,924,153 -

Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include

C PINTU KACA - Lanjutan

Pintu Kaca GD6, ukuran overall 7850x2400 mm dari kaca tempered


clear tebal 12mm frameless, lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Announcer room
- Lantai 3 unit 1.00 - 30,598,053 30,598,053 -
FEI & AEF room
- Lantai 3 unit 1.00 - 30,598,053 30,598,053 -
Broadcast room
- Lantai 3 unit 1.00 - 30,598,053 30,598,053 -
Reporter room
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.2.2 - PEKERJAAN PINTU dan JENDELA


- Lantai 3 unit 1.00 (1.00) 30,598,053 30,598,053 (30,598,053)
Appeal room
- Lantai 3 unit 1.00 - 30,598,053 30,598,053 -

Meeting room
- Lantai 3 unit 1.00 - 30,598,053 30,598,053 -

Hardware :
Pull handle art-243/600 mm SS psg 1.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 1.00 - include
Patch fitting dorma PT.21 bh 1.00 - include
Floor hinges dorma BTS 84 T/complete SS set 1.00 - include

Pintu Kaca GD7, ukuran overall 5400x2400 mm dari kaca tempered


clear tebal 12mm frameless, lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Acces to Tribune lantai 2
- Lantai 2 unit 1.00 - 27,784,192 27,784,192 -

Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include

Pintu Kaca GD8, ukuran overall 1800x2400 mm dari kaca tempered


clear tebal 12mm frameless, lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Acces to Tribune lantai 2
- Lantai 2 unit 1.00 - 19,666,033 19,666,033 -

Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include

Pintu Kaca AD1, ukuran overall 1000x2400 mm dari kaca clear tebal
8mm, kusen Alumunium 50/100 powder coating finish, lengkap
terpasang termasuk hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada:
Security
- Lantai 1 unit 1.00 - 4,826,448 4,826,448 -

Hardware :
Lever handle art-352 SS psg 1.00 - include
Lockcase Wilka art-1438.30 SN + striking plate bh 1.00 - include
Cylinder Wilka art-1400.60 Nickel bh 1.00 - include
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 - include
Door closer dorma TS 68 RA silver bh 1.00 - include

D JENDELA KACA

Jendela Kaca G1, ukuran overall 1800x3000 mm lengkap terpasang


termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
Mushola
- Lantai 4 unit 1.00 - 7,480,848 7,480,848 -

Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 - include
Rambuncis art - 118 silver bh 1.00 - include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 - include

DAFTAR NO. II.2.2 - PEKERJAAN PINTU dan JENDELA 1,183,302,306 (54,588,708)


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.3 - PEKERJAAN LANTAI

II.2.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

HOMOGENEOUS TILE
Homogeneous Tile (polished) uk 600 x 600 mm ex. Setara
Niro granite / Essenza, berikut adukan mortar, additiv,
grouting nat termasuk alat-alat bantu lainnya dengan
peralatan perlengkapan sesuai spesifikasi dan gambar pada :

Lantai 1
- Lift Lobby m2 10.87 0.05 377,320 4,102,028 19,551
- Security office m2 15.47 0.00 377,320 5,836,774 706
- Stair #2 m2 45.56 (0.10) 377,320 17,190,699 (38,713)
- Stair #3 m2 25.35 24.19 377,320 9,565,628 9,127,333
- Teras VIP lobby m2 116.31 11.85 377,320 43,884,326 4,470,892
- Teras Public Hall m2 125.52 31.81 377,320 47,360,810 12,002,795
- Ramp Teras lobby m2 20.83 7.47 377,320 7,858,652 2,819,851

Lantai 2
- Lift Lobby m2 9.40 (0.08) 377,320 3,546,808 (31,318)
- Stair #2 m2 18.63 6.44 377,320 7,029,472 2,430,507
- Stair #3 m2 25.35 6.35 377,320 9,565,628 2,396,359

Lantai 3
- Lift Lobby m2 9.52 (0.10) 377,320 3,592,086 (38,864)
- Stair #2 m2 18.63 6.65 377,320 7,029,472 2,510,650
- Stair #3 m2 22.95 2.49 377,320 8,659,494 940,281

Lantai 4
- Lift Lobby m2 9.28 (0.15) 377,320 3,500,747 (55,174)
- Storage 1 m2 14.09 0.00 377,320 5,318,106 1,880
- Storage 2 m2 30.91 0.03 377,320 11,663,729 11,382

Homogeneous Tile (unpolished) uk 600 x 600 mm ex.setara


Niro granite / Essenza, berikut adukan mortar, additiv,
grouting nat termasuk alat-alat bantu lainnya dengan
peralatan perlengkapan sesuai spesifikasi dan gambar pada :

Lantai 1
Detail toilet 1
- Toilet Female m2 28.15 7.42 372,180 10,477,555 2,761,669
- Toilet Male m2 30.37 1.71 372,180 11,302,837 636,623
- Janitor m2 2.31 0.01 372,180 860,890 3,684
- Toilet difable m2 4.77 (0.01) 372,180 1,774,516 (3,721)
Detail toilet 2
Toilet Female m2 15.24 (0.12) 372,180 5,673,748 (43,706)
- Toilet Male m2 18.85 (0.06) 372,180 7,014,995 (21,844)
- Janitor m2 2.73 0.01 372,180 1,017,443 4,005
- Toilet difable m2 6.12 (0.03) 372,180 2,276,835 (12,715)
- Ablution m2 9.78 0.02 372,180 3,640,386 8,393

Lantai 2
Detail toilet 3
- Toilet Female m2 12.46 0.02 372,180 4,637,363 8,709
- Toilet Male m2 12.89 (0.01) 372,180 4,797,400 (2,717)
- Janitor m2 3.15 (0.01) 372,180 1,172,367 (4,355)

Homogeneous Tile (unpolished) uk 600 x 600 mm ex.setara


Niro granite / Essenza, berikut adukan mortar, additiv,
grouting nat termasuk alat-alat bantu lainnya dengan
peralatan perlengkapan sesuai spesifikasi dan gambar
pada :-Lanjutan

Lantai 3
Detail toilet 3
- Toilet Female m2 25.06 (0.18) 372,180 9,326,831 (66,174)
- Toilet Male m2 25.93 (0.25) 372,180 9,650,627 (92,003)
- Janitor m2 6.29 (0.01) 372,180 2,339,151 (3,201)

Lantai 4
Detail toilet 4
- Toilet Female m2 13.73 0.01 372,180 5,110,201 3,739
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.3 - PEKERJAAN LANTAI


- Toilet Male m2 15.17 0.01 372,180 5,646,112 3,618
- Janitor m2 4.34 (0.15) 372,180 1,615,233 (57,473)
- Ablution m2 8.15 3.37 372,180 3,033,217 1,255,376
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.3 - PEKERJAAN LANTAI

CERAMIC TILE
Ceramic Tile uk. 600 x 600 mm ex setara Roman berikut
adukan mortar, additiv, grouting nat termasuk alat-alat bantu
lainnya dengan peralatan perlengkapan sesuai spesifikasi
dan gambar pada :

Lantai 1
- Panel room m2 9.32 0.03 242,380 2,260,193 7,708

Lantai 2
- Panel room m2 7.24 0.75 242,380 1,754,831 181,833

Lantai 3
- Panel room m2 7.44 (0.05) 242,380 1,803,307 (12,652)

Lantai 4
- Panel room m2 7.44 (1.84) 242,380 1,803,307 (445,252)

FLOOR HARDENER
Floor Hardener 5kg/m2, termasuk alat alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :

Lantai 1
- Security office m2 15.48 (15.48) 41,740 646,135 (646,135)
- Stair #1 m2 35.16 0.23 41,740 1,467,578 9,588
- Stair #4 m2 38.50 (0.54) 41,740 1,606,990 (22,702)
- Stair #5 m2 64.97 5.84 41,740 2,711,848 243,795
- Teras samping m2 162.10 5.82 41,740 6,766,054 242,868
- Tangga ke public hall m2 21.18 17.83 41,740 883,845 744,082
- Tangga ke VIP lobby m2 21.18 24.90 41,740 883,845 1,039,380

Lantai 2
- Pedestrian m2 150.42 8.49 41,740 6,278,531 354,498
- Tribune m2 669.28 18.57 41,740 27,935,747 775,229
- Stair #1 m2 25.99 0.79 41,740 1,084,823 33,004
- Stair #4 m2 26.49 0.55 41,740 1,105,693 23,082
- Teras samping m2 39.91 (39.91) 41,740 1,665,843 (1,665,843)

Lantai 3
- Stair #1 m2 25.69 1.09 41,740 1,072,301 45,522
- Stair #4 m2 26.26 0.70 41,740 1,096,092 29,410

PLINT HOMOGENOUS TILE


Homogeneous Tile (polished) uk 100 x 600 mm ex.setara
Niro granite / Essenza, berikut adukan mortar, additiv,
grouting nat termasuk alat-alat bantu lainnya dengan
peralatan perlengkapan sesuai spesifikasi dan gambar pada :

Lantai 1
- Lift Lobby m' 12.22 0.02 20,601 251,749 396
- Security office m' 15.64 0.02 20,601 322,226 369
- Teras VIP lobby m' 27.66 2.13 20,601 569,834 43,881
- Teras Public Hall m' 30.06 0.44 20,601 619,277 9,065

PLINT HOMOGENOUS TILE -Lanjutan

Homogeneous Tile (polished) uk 100 x 600 mm ex.setara


Niro granite / Essenza, berikut adukan mortar, additiv,
grouting nat termasuk alat-alat bantu lainnya dengan
peralatan perlengkapan sesuai spesifikasi dan gambar pada :

Lantai 2
- Lift Lobby m' 11.88 11.86 20,601 244,744 244,283

Lantai 3
- Lift Lobby m' 11.88 (1.41) 20,601 244,744 (29,003)

Lantai 4
- Lift Lobby m' 11.37 (0.88) 20,601 234,155 (18,224)

PLINT CERAMIC TILE


Ceramic Tile uk. 100 x 600 mm ex setara Roman berikut
adukan mortar, additiv, grouting nat termasuk alat-alat bantu
lainnya dengan peralatan perlengkapan sesuai spesifikasi
dan gambar pada :
Lantai 1
- Panel room m' 11.40 0.02 11,358 129,482 267

Lantai 2
- Panel room m' 11.21 0.03 11,358 127,324 310

Lantai 3
- Panel room m' 10.44 (0.24) 11,358 118,578 (2,715)
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.3 - PEKERJAAN LANTAI

Lantai 4
- Panel room m' 9.09 1.12 11,358 103,245 12,741

SKIRTING
Homogeneous Tile (polished) uk 100 x 600 mm ex.setara
Niro granite / Essenza, berikut adukan mortar, additiv,
grouting nat termasuk alat-alat bantu lainnya dengan
peralatan perlengkapan sesuai spesifikasi dan gambar
pada :-Provisional
Lantai 1
- Stair #2 m' 16.37 - 20,601 337,244 -
- Stair #3 m' 17.48 - 20,601 360,112 -

Lantai 2
- Stair #2 m' 16.37 - 20,601 337,244 -
- Stair #3 m' 17.48 - 20,601 360,112 -

Lantai 3
- Stair #2 m' 16.37 - 20,601 337,244 -

STEP NOSING

Keramik Tile uk. 100 x 200mm ex setara ROMAN berikut


adukan mortar, additiv, grouting nat termasuk alat-alat bantu
lainnya dengan peralatan perlengkapan sesuai spesifikasi
dan gambar pada :

Lantai 1
- Stair #1 m' 30.80 (0.00) 80,110 2,467,388 (0)
- Stair #4 m' 31.90 (1.10) 80,110 2,555,509 (88,121)

Lantai 2
- Stair #1 m' 32.20 (1.40) 80,110 2,579,542 (112,154)
- Stair #4 m' 33.35 (2.55) 80,110 2,671,669 (204,281)

Lantai 3
- Stair #1 m' 32.20 (1.40) 80,110 2,579,542 (112,154)
- Stair #4 m' 33.35 (2.55) 80,110 2,671,669 (204,281)

WATERPROOFING

Continuous Waterproofing Coating, termasuk pada dinding


setinggi 300mm terpasang sesuai dengan spesifikasi dan
gambar pada : (Provisional)
Lantai 1
- Toilet Female m2 42.56 - 44,520 1,894,771 -
- Toilet Male m2 51.17 - 44,520 2,278,088 -
- Janitor m2 4.92 - 44,520 219,038 -
- Toilet difable m2 10.74 - 44,520 478,145 -
- Ablution m2 9.79 - 44,520 435,851 -

Lantai 2
- Toilet Female m2 12.46 - 44,520 554,719 -
- Toilet Male m2 12.89 - 44,520 573,863 -
- Janitor m2 3.15 - 44,520 140,238 -

Lantai 3
- Toilet Female m2 24.79 - 44,520 1,103,651 -
- Toilet Male m2 25.66 - 44,520 1,142,383 -
- Janitor m2 6.06 - 44,520 269,791 -

Lantai 4
- Toilet Female m2 15.16 - 44,520 674,923 -
- Toilet Male m2 13.73 - 44,520 611,260 -
- Janitor m2 4.19 - 44,520 186,539 -
- Ablution m2 8.15 - 44,520 362,838 -
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.3 - PEKERJAAN LANTAI

DAFTAR NO. II.2.3 - PEKERJAAN LANTAI 381,047,859 41,423,819


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.4 - PEKERJAAN PLAFOND

II.2.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A Plafond Gypsumboard tebal 9 mm rangka metal furing hollow setara ex.


Jayaboard, finishing cat Acrylic Emulsion paint setara ex.ICI, termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :

Lantai 1
- Lift Lobby m2 10.65 0.05 124,090 1,321,122 6,430
- Security office m2 15.32 0.00 124,090 1,900,938 232
- Teras VIP lobby m2 116.31 11.85 124,090 14,432,328 1,470,351
- Teras Public Hall m2 125.52 31.81 124,090 15,575,646 3,947,384

Lantai 2
- Lift Lobby m2 8.70 0.47 124,090 1,079,583 57,950

Lantai 3
- Lift Lobby m2 9.37 (0.25) 124,090 1,162,723 (31,395)

Lantai 4
- Lift Lobby m2 9.11 0.02 124,090 1,130,823 2,330
- Storage 1 m2 14.09 0.00 124,090 1,748,976 618
- Storage 2 m2 30.91 0.03 124,090 3,835,874 3,743

B Plafond Gypsum Water resistant tebal 12 mm rangka metal furing hollow


setara ex. Jayaboard, finishing cat Acrylic Emulsion paint setara ex.ICI,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :

Lantai 1
Detail toilet 1
- Toilet Female m2 28.15 7.42 168,610 4,746,683 1,251,129
- Toilet Male m2 30.37 1.71 168,610 5,120,564 288,411
- Janitor m2 2.18 (0.01) 168,610 367,250 (860)
- Toilet difable m2 4.62 (0.01) 168,610 778,624 (1,686)

Detail toilet 2
- Toilet Female m2 15.09 0.03 168,610 2,545,106 5,491
- Toilet Male m2 18.70 0.09 168,610 3,152,736 15,395
- Janitor m2 2.60 (0.00) 168,610 438,173 (715)
- Toilet difable m2 5.97 (0.03) 168,610 1,006,191 (5,760)
- Ablution m2 9.78 (0.20) 168,610 1,649,217 (34,135)
B Plafond Gypsum Water resistant tebal 12 mm rangka metal furing hollow
ex. Jayaboard, finishing cat Acrylic Emulsion paint ex.ICI, termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :-Lanjutan

Lantai 2
Detail toilet 3
- Toilet Female m2 12.30 0.03 168,610 2,073,903 5,632
- Toilet Male m2 12.73 0.00 168,610 2,146,405 455
- Janitor m2 3.01 (0.02) 168,610 507,516 (3,659)

Lantai 3
Detail toilet 3
- Toilet Female m2 24.79 (0.21) 168,610 4,179,842 (35,037)
- Toilet Male m2 25.66 (0.28) 168,610 4,326,533 (46,739)
- Janitor m2 6.06 (0.08) 168,610 1,021,777 (14,096)

Lantai 4
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.2.4 - PEKERJAAN PLAFOND


Detail toilet 3
- Toilet Female m2 13.73 0.01 168,610 2,315,092 1,694
- Toilet Male m2 15.17 0.01 168,610 2,557,878 1,639
- Ablution m2 8.15 3.37 168,610 1,374,149 568,727
- Janitor m2 4.19 (0.00) 168,610 706,463 (746)

C Beton exposed skim coat, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai dengan spesifikasi dan gambar pada :
- Lantai 1
- Ruang panel m2 9.17 1.87 33,950 311,491 63,594
- Stair #1 m2 18.63 (3.83) 33,950 632,422 (130,132)
- Stair #2 m2 15.67 (1.42) 33,950 531,827 (48,209)
- Stair #3 m2 18.72 2.26 33,950 635,595 76,798
- Stair #4 m2 19.98 1.35 33,950 678,197 45,695

- Lantai 2
- Ruang panel m2 7.23 2.00 33,950 245,459 67,840
- Stair #1 m2 18.94 4.26 33,950 642,897 144,585
- Stair #2 m2 16.09 5.12 33,950 546,105 173,739
- Stair #3 m2 18.72 7.95 33,950 635,595 270,040
- Stair #4 m2 10.89 12.59 33,950 369,846 427,432

- Lantai 3
- Ruang panel m2 7.22 1.47 33,950 245,119 49,749
- Stair #1 m2 18.94 6.37 33,950 642,897 216,171
- Stair #2 m2 16.09 7.30 33,950 546,105 247,832
- Stair #3 m2 22.95 (1.36) 33,950 779,153 (46,240)
- Stair #4 m2 10.89 14.63 33,950 369,846 496,718

- Lantai 4
- Ruang panel m2 5.58 1.14 33,950 189,441 38,825
- Stair #1 m2 21.06 0.14 33,950 714,987 4,814
- Stair #2 m2 21.06 (1.57) 33,950 714,987 (53,366)
- Stair #4 m2 21.30 (0.07) 33,950 722,999 (2,329)

D Metal Ceiling type Custom ex. Durlum atau setara, termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
Lantai 2
- Pedestrian m2 150.42 8.49 444,627 66,880,718 3,776,213
- Tribune m2 669.28 18.57 444,627 297,579,624 8,257,959

DAFTAR NO. II.2.4 - PEKERJAAN PLAFOND 457,817,424 21,530,514


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp

DAFTAR NO. II.2.5. - PEKERJAAN SANITARY

II.2.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan


kelengkapan material bantu (adukan, plesteran, acian, nad, sealan,
grouting, bahan bantu pengubung (doble niple) yang berhubungan
dengan instalasi ME dan lainnya berikut pemasangan dan
perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Sanitary by Interior

DAFTAR NO. II.2.5. - PEKERJAAN SANITARY -


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. II.2.6. - PEKERJAAN LAIN-LAIN

II.2.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai


gambar dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Railing
Railing Tangga steel Pipe dia. 50 W/OP dan dia. 38 W/OP with paint
finish welded & grind smooth tinggi 1100 mm, termasuk Hand Railing dan
alat-alat bantu lainnya dengan peralatan perlengkapan terpasang Sesuai
spesifikasi dan gambar pada :
Lantai 1
- Stair #1 m' 16.51 (7.96) 723,422 11,947,011 (5,761,752)
- Stair #2 m' 11.00 (2.27) 723,422 7,954,939 (1,639,463)
- Stair #3 m' 11.39 1.03 723,422 8,236,623 746,833
- Stair #4 m' 21.72 (13.02) 723,422 15,715,454 (9,421,681)
Lantai 2
- Stair #1 m' 22.87 (13.67) 723,422 16,543,500 (9,888,016)
- Stair #2 m' 11.30 (2.35) 723,422 8,171,966 (1,697,337)
- Stair #3 m' 14.79 (1.59) 723,422 10,696,259 (1,147,086)
- Stair #4 m' 22.52 (13.32) 723,422 16,294,192 (9,638,708)
Lantai 3
- Stair #1 m' 26.67 (16.67) 723,422 19,292,504 (12,058,282)
- Stair #2 m' 13.00 (3.11) 723,422 9,401,783 (2,247,138)
- Stair #4 m' 26.22 (16.12) 723,422 18,970,854 (11,664,290)

2 Handrailing
Hand Railing steel Pipe dia.38mm W/OP with paint finish, termasuk alat-
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
Lantai 1
- Stair #1 m' 16.21 (2.91) 278,239 4,510,472 (809,889)
- Stair #2 m' 16.10 (2.52) 278,239 4,478,612 (700,123)
- Stair #3 m' 17.99 (1.51) 278,239 5,004,311 (420,041)
- Stair #4 m' 15.59 (2.02) 278,239 4,338,595 (562,888)
Lantai 2
- Stair #1 m' 16.21 (2.26) 278,239 4,510,472 (629,034)
- Stair #2 m' 16.10 (2.52) 278,239 4,478,612 (700,123)
- Stair #3 m' 17.99 (1.51) 278,239 5,004,311 (420,041)
- Stair #4 m' 15.59 (2.02) 278,239 4,338,595 (562,888)
Lantai 3
- Stair #1 m' 16.21 (2.26) 278,239 4,510,472 (629,034)
- Stair #2 m' 16.10 (2.52) 278,239 4,478,612 (700,123)
- Stair #4 m' 15.59 (2.02) 278,239 4,338,595 (562,888)

3 Railling Kaca
Railling Kaca Tempered 12mm dan Railing stainless steel 20mm x 60mm
(custom) + Hand Railling Stainless Steel 40mm x 80mm with paint finish
welded & grind smooth tinggi 1100 mm , termasuk angkur baut, sealant
dan kelengkapan lainnya sesuai gambar dan spesifikasi pada :
- Lantai 2
- Stair #5 m' 114.17 0.23 3,199,752 365,315,670 735,943

4 Cermin
Kaca cermin tebal 6mm, lengkap dengan bevel bagian pinggir, berikut
lapisan belakang dari multiplek tebal 12 mm, berikut sealant, bracket, dll
termasuk alat-alat bantu lainnya dengan peralatan dan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :
Lantai 1
Detail toilet 1
- Female toilet 1 (uk. 1960x1000 mm) unit 1.00 - 1,590,601 1,590,601 -
- Male toilet 1 (uk. 1960x1000 mm) unit 1.00 - 1,590,601 1,590,601 -
- Female toilet 2 (uk. 2740x1000 mm) unit 1.00 - 2,223,596 2,223,596 -
- Male toilet 2 (uk. 3450x1000 mm) unit 1.00 - 2,799,783 2,799,783 -

Detail toilet 2
- Female toilet (uk. 2740x1000 mm) unit 1.00 - 2,223,596 2,223,596 -
- Male toilet (uk. 2810x1000 mm) unit 1.00 - 2,272,288 2,272,288 -

Lantai 2
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. II.2.6. - PEKERJAAN LAIN-LAIN


Detail toilet 3
- Female toilet (uk. 2690x1000 mm) unit 1.00 - 2,183,019 2,183,019 -
- Male toilet (uk. 2085x1000 mm) unit 1.00 - 1,687,985 1,687,985 -

Lantai 3
Detail toilet 3
- Female toilet (uk. 2690x1000 mm) unit 2.00 - 2,183,019 4,366,038 -
- Male toilet (uk. 2085x1000 mm) unit 2.00 - 1,687,985 3,375,970 -

Lantai 4
Detail toilet 4
- Female toilet (uk. 3590x1000 mm) unit 1.00 - 2,913,397 2,913,397 -
- Male toilet (uk. 1885x1000 mm) unit 1.00 - 1,525,679 1,525,679 -

5 Cove lampu cermin


Lapisan belakang dari multiplek tebal 12 mm lebar 90mm dan
penambahan finishing Homogeneous tile 300x600 mm termasuk alat-alat
bantu lainnya dengan peralatan dan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
Lantai 1
Detail toilet 2
- Female toilet (uk. 2740x1000 mm) m' 2.74 - 343,107 940,114 -
- Male toilet (uk. 2810x1000 mm) m' 2.81 - 343,107 964,131 -

Lantai 2
Detail toilet 3
- Female toilet (uk. 2690x1000 mm) m' 2.69 - 343,107 922,958 -
- Male toilet (uk. 2085x1000 mm) m' 2.08 - 343,107 713,663 -

Lantai 3
Detail toilet 3
- Female toilet (uk. 2690x1000 mm) m' 2.69 - 343,107 922,958 -
- Male toilet (uk. 2085x1000 mm) m' 2.08 - 343,107 713,663 -

Lantai 4
Detail toilet 4
- Female toilet (uk. 3590x1000 mm) m' 3.59 - 343,107 1,231,755 -
- Male toilet (uk. 1885x1000 mm) m' 1.89 0.00 343,107 646,757 1,716

6 Meja Lavatory
Meja Lavatory granite hitam nero absolute (rangka besi), termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
Lantai 1
Detail toilet 1
- Female toilet 1 (uk. 1960x1000 mm) unit 1.00 - 2,499,110 2,499,110 -
- Male toilet 1 (uk. 1960x1000 mm) unit 1.00 - 2,499,110 2,499,110 -
- Female toilet 2 (uk. 2740x1000 mm) unit 1.00 - 3,335,100 3,335,100 -
- Male toilet 2 (uk. 3450x1000 mm) unit 1.00 - 4,096,060 4,096,060 -

Meja Lavatory granite hitam nero absolute (rangka besi), termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :-Lanjutan
Lantai 1
Detail toilet 2
- Female toilet (uk. 2740x1000 mm) unit 1.00 - 3,335,100 3,335,100 -
- Male toilet (uk. 2810x1000 mm) unit 1.00 - 3,335,100 3,335,100 -

Lantai 2
Detail toilet 3
- Female toilet (uk. 2690x1000 mm) unit 1.00 - 3,335,100 3,335,100 -
- Male toilet (uk. 2085x1000 mm) unit 1.00 - 3,335,100 3,335,100 -

Lantai 3
Detail toilet 3
- Female toilet (uk. 2690x1000 mm) unit 2.00 - 3,335,100 6,670,200 -
- Male toilet (uk. 2085x1000 mm) unit 2.00 - 3,335,100 6,670,200 -

Lantai 4
Detail toilet 4
- Female toilet (uk. 3590x1000 mm) unit 1.00 - 4,096,060 4,096,060 -
- Male toilet (uk. 1885x1000 mm) unit 1.00 - 2,499,110 2,499,110 -

Tanggulan tinggi 400 mm, tebal 150 mm lapis keramik ex. Roman
7 termasuk adukan perekat, material bantu dan perlengkapan lainnya sesuai
gambar dan spesifikasi pada : (Provisional)

Lantai 1
Detail toilet 1
- Janitor m' 1.18 - 304,910 358,879 -
Detail toilet 2
- Janitor m' 1.35 - 304,910 411,629 -

Lantai 2
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. II.2.6. - PEKERJAAN LAIN-LAIN


Detail toilet 3
- Janitor m' 0.81 - 304,910 246,977 -

Lantai 3
Detail toilet 3
- Janitor m' 1.62 - 304,910 493,954 -

Lantai 4
Detail toilet 4
- Janitor m' 1.65 - 304,910 503,102 -

Tanggulan tinggi 200 mm, tebal 150 mm lapis keramik ex. Roman
8 termasuk adukan perekat, material bantu dan perlengkapan lainnya sesuai
gambar dan spesifikasi pada : (Provisional)

Lantai 1
Detail toilet 1
- Janitor m' 1.18 - 152,455 179,440 -
Detail toilet 2
- Janitor m' 1.35 - 152,455 205,814 -

Lantai 2
Detail toilet 3
- Janitor m' 0.81 - 152,455 123,489 -

Lantai 3
Detail toilet 3
- Janitor m' 1.62 - 152,455 246,977 -

Lantai 4
Detail toilet 4
- Janitor m' 1.65 - 152,455 251,551 -

Tanggulan tinggi 300 mm, tebal 150 mm lapis batu alam termasuk adukan
9 perekat, material bantu dan perlengkapan lainnya sesuai gambar dan
spesifikasi pada : (Provisional)

Lantai 1
Detail toilet 2
- Ablution m' 4.60 - 160,078 736,358 -

Lantai 4
Detail toilet 4
- Ablution m' 3.30 - 160,078 528,257 -

Tanggulan tinggi 150 mm, tebal 300 mm lapis keramik ex. Roman
10 termasuk adukan perekat, material bantu dan perlengkapan lainnya sesuai
gambar dan spesifikasi pada : (Provisional)

Lantai 1
Detail toilet 2
- Ablution m' 4.60 - 152,455 701,293 -

Lantai 4
Detail toilet 4
- Ablution m' 3.30 - 152,455 503,102 -

Tanggulan Urinoir tinggi 1050 mm, tebal 200 mm lapis granit, sesuai
11
gambar dan spesifikasi pada :

Lantai 1
Detail toilet 1
- Male toilet 1 (uk. 1960x1000 mm) m' 2.74 - 457,365 1,253,180 -

Tanggulan Urinoir tinggi 1250 mm, tebal 450 mm lapis granit, sesuai
12
gambar dan spesifikasi pada :

Lantai 1
Detail toilet 2
- Male toilet (uk. 2810x1000 mm) m' 2.14 - 457,365 978,761 -

Tanggulan Urinoir dan closet tinggi 1200 mm, tebal 100 mm lapis granit,
13 sesuai gambar dan spesifikasi pada :

Lantai 4
Detail toilet 4
- Male toilet (uk. 1885x1000 mm) m' 3.59 - 457,365 1,641,940 -
- Female toilet (uk. 3590x1000 mm) m' 3.59 - 457,365 1,641,940 -

14 Fire Stop (Provisional)


DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. II.2.6. - PEKERJAAN LAIN-LAIN


Fire Stop termasuk plat untuk dudukan dan glasswool, insulasi, rangka,
angkur, sealant, material bantu dan perlengkapan lainnya sesuai gambar
dan spesifikasi pada:
Area shaft
- Lantai 1 m2 3.28 - 556,479 1,823,855 -
- Lantai 2 m2 3.09 - 556,479 1,718,124 -
- Lantai 3 m2 3.57 - 556,479 1,989,406 -
- Lantai 4 m2 3.09 - 556,479 1,718,124 -

15 Grating
Grating ukuran 300 mm (6x25mm stailess steel) termasuk sesuai gambar
dan spesifikasi (Provisional)
Lantai 1
Detail toilet 2
- Ablution m' 4.60 - 560,040 2,576,184 -

Lantai 4
Detail toilet 4
- Ablution m' 3.30 - 560,040 1,848,132 -
16 Planter Box
Planter Box, dari pasangan bata ringan, finish plester+cat, termasuk
material bantu dan perlengkapan lainnya sesuai gambar dan spesifikasi
pada : (PROVISIONAL)
- Lantai 1 m2 195.94 - 149,230 29,240,126 -

17 Concrete Curb / Kansteen


Concrete Curb / Kansteen tinggi 100mm, lebar 100mm termasuk galv
steel dowel 12mm, material dan alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
- Lantai 1 m' 218.02 63.58 143,310 31,244,160 9,111,936

18 Groove
Cutter Grove uk. 10x10 mm pada tepi kansteen terpasang sesuai gambar
dan spesifikasi pada :
- Lantai 1 m' 218.02 63.58 26,120 5,694,630 1,660,762

19 Gutter (Provisional)
Gutter with steel grate sesuai spesifikasi dan gambar pada :
Lantai 1
- Outdoor ramp (Gutter uk 400x200mm) m' 14.80 - 340,310 5,036,588 -
- Outdoor stair bawah tribune (Gutter uk 400x200mm) m' 9.20 - 340,310 3,130,852 -

20 Jamb Lift
Wide jamb stainless steel hairline (ex local) sesuai spesifikasi dan gambar
pada :
Lantai 1
- VIP lift m' 12.20 0.40 389,535 4,752,327 155,814
- Public area lift m' 6.00 0.30 389,535 2,337,210 116,861
Lantai 2
- VIP lift m' 12.20 0.40 389,535 4,752,327 155,814
- Public area lift m' 6.00 0.30 389,535 2,337,210 116,861
- Service lift m' 6.00 0.30 389,535 2,337,210 116,861
Lantai 3
- VIP lift m' 12.20 0.40 389,535 4,752,327 155,814
- Public area lift m' 6.00 0.30 389,535 2,337,210 116,861
- Service lift m' 6.00 0.30 389,535 2,337,210 116,861
Lantai 4
- VIP lift m' 12.20 0.40 389,535 4,752,327 155,814
- Service lift m' 6.00 0.30 389,535 2,337,210 116,861

21 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material bantu
dan kelengkapan lainnya, sesuai spesifkasi & gambar pada: (Provisional)
- Lantai Atap m2 1,629.17 - 198,663 323,655,563 -

DAFTAR No. II.2.6. - PEKERJAAN LAIN-LAIN 1,093,761,269 (58,279,214)


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. II.2.6. - PEKERJAAN LAIN-LAIN


DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. II.2.7. - PEKERJAAN ATAP CANOPY

II.2.7.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari


konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Atap Canopy
Atap Canopy termasuk kaca laminated tebal 10.75mm, rangka
alumunium, metal roof sandwich panel + insulasi berikut alat bantu
dengan peralatan perlengkapan sesuai dengan spesifikasi dan
gambar pada :
Roof top Baja masuk Struktur Pekerjaan Baja
- Tribune m2 634.40 20.79 1,669,436 1,059,090,042 34,712,578

2 Atap Canopy dan Kolom Canopy


Atap Canopy termasuk (ACP) alumunium composit panel setara
Alucobon, termasuk rangka alumunium berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar
pada :
Roof top Baja masuk Struktur Pekerjaan Baja
- Tribune m2 12,522.34 60.09 855,200 10,709,105,168 51,387,258

3 Atap Sanwich Metal

Atap Sanwich metal, termasuk rangka alumunium berikut alat bantu


dengan peralatan perlengkapan sesuai dengan spesifikasi dan
gambar pada :

Roof top Baja masuk Struktur Pekerjaan Baja


- Tribune m2 3,007.95 355.09 681,690 2,050,489,436 242,060,620

4 Talang air

Talang metal, termasuk rangka, berikut alat bantu dengan peralatan


perlengkapan sesuai dengan spesifikasi dan gambar pada :

Roof top Baja masuk Struktur Pekerjaan Baja


- Tribune m' 75.00 9.79 256,720 19,254,000 2,513,289

DAFTAR No. II.2.7. - PEKERJAAN ATAP CANOPY 13,837,938,645 330,673,744


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.2.9 - PEKERJAAN FAÇADE

II.2.9.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber

gasket (sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci
& alat-alat penggantung, perlengkapan yang dibutuhkan seperti
mur, baut, handle, engsel, kait angin, sealant, dan
kelengkapannya., rubber gasket (sealant), neoprene, penyetelan
dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di


dalam daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk


alat penggantung (ironmongery sets) dan sistem kunci (keying
system) dan pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan


sketch detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari
peserta tender, seperti merk dan jenis kunci ataupun alat-alat
penggantung, dll..

A CAT WEATHERSHIELD
Pengecatan dengan fin. Weathershield ex.ICI/ Jotun tipe
Weathershield Jotashield, termasuk peralatan dan perlengkapan
sesuai spesifikasi dan gambar pada :
- Lantai 1
Eksterior m2 576.15 65.50 29,490 16,990,557 1,931,524
- Lantai 2
Eksterior m2 226.76 72.19 29,490 6,687,129 2,128,759
- Lantai 3
Eksterior m2 280.63 4.74 29,490 8,275,767 139,653
- Lantai 4
Eksterior m2 237.13 31.52 29,490 6,992,999 929,478

B CURTAIN WALL
Curtain wall Tinted Tempered Glass 8mm, ex. Asahimas, termasuk
rangka mullion system, plate st.steel 8mm, firestop, transom,
sunshade bracket alumunium extrude, sesuai spesifikasi dan gambar
pada :
TAMPAK UTARA
- Lantai 1 (Provisional) m2 47.55 - 1,391,196 66,151,392 -
- Lantai 3 m2 193.26 170.43 1,391,196 268,857,063 237,102,169
TAMPAK SELATAN
- Lantai 1 (Provisional) m2 101.07 - 1,391,196 140,604,053 -
- Lantai 3 (Provisional) m2 119.36 - 1,391,196 166,053,210 -
- Lantai 4 m2 136.88 85.30 1,391,196 190,431,493 118,673,440

Curtain wall tinted tempered laminated glass t: 11.14mm, ex.


Asahimas, terdiri dari tinted tempered and pvb, termasuk rangka
alumunium mullion, firestop, transom, sunshade bracket alumunium
extrude, sesuai spesifikasi dan gambar pada :

TAMPAK UTARA
- Lantai 4 m2 499.10 60.53 1,391,196 694,346,154 84,205,226
TAMPAK SELATAN
- Lantai 2 (Provisional) m2 119.36 - 1,391,196 166,053,210 -
TAMPAK TIMUR
- Lantai 4 m2 50.05 3.92 1,391,196 69,629,383 5,458,359
TAMPAK BARAT
- Lantai 4 m2 50.05 3.92 1,391,196 69,629,383 5,458,359
C SPANDREL
Spandrel 12 mm calcium cilicate board painted finish, sesuai
spesifikasi dan gambar pada :

TAMPAK UTARA
- Lantai 3 m2 70.23 0.43 180,300 12,662,559 77,439

TAMPAK TIMUR
- Lantai 3 m2 7.04 - 180,300 1,269,808 -

TAMPAK BARAT
- Lantai 3 m2 7.04 - 180,300 1,269,808 -

D RAILING
Tempered Glass Railing h: 900mm and hollow stainless steel
25x50mm hairline finish, Handle stainless steel d. 50mm, 10 mm
temperred glass ex. Asahimas terpasang sesuai dengan gambar dan
spesifikasi pada : (Provisional)
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.2.9 - PEKERJAAN FAÇADE


TAMPAK UTARA
- Lantai 2 m' 125.57 7.06 2,392,858 300,463,192 16,891,982
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. II.2.9 - PEKERJAAN FAÇADE


E ALUMUNIUM LOUVRE
Alumunium Louvre Shading, ex. …. atau setara, termasuk powder
coating, rangka, perkuatan, pemasangan serta perapihan, sesuai
spesifikasi dan gambar pada :

TAMPAK SELATAN
- Lantai 1 - Lantai 2 m2 47.34 3.52 1,224,253 57,961,414 4,304,088

TAMPAK TIMUR
- Lantai 1 - Lantai 2 m2 21.35 0.00 1,224,253 26,133,155 4,644

TAMPAK BARAT
- Lantai 1 - Lantai 2 m2 21.35 0.00 1,224,253 26,133,155 4,644

F METAL LASER CUTTING


Metal Sheet (Laser Cut) t 18mm, ex. …. atau setara, finish coating
termasuk rangka, perkuatan, pemasangan serta perapihan, sesuai
spesifikasi dan gambar pada :

TAMPAK SELATAN
- Lantai 1 - Lantai 4 m2 1,002.01 110.03 2,337,210 2,341,903,804 257,167,266

TAMPAK TIMUR
- Lantai 1 - Lantai 4 m2 394.50 36.15 2,337,210 922,029,365 84,490,145

TAMPAK BARAT
- Lantai 1 - Lantai 4 m2 394.59 36.06 2,337,210 922,240,020 84,279,490

Catwalk Baja , terdiri dari WF, steel angle 50x50x5mm duco finish,
grill strip plate 40x4mm welded system, finish coating termasuk
rangka, perkuatan, pemasangan serta perapihan, sesuai spesifikasi
dan gambar pada :

TAMPAK TIMUR
- Lantai 1 m' 22.65 1.43 946,014 21,425,316 1,354,691
- Lantai 2 m' 22.32 1.76 946,014 21,115,969 1,664,038
- Lantai 3 m' 18.92 0.91 946,014 17,900,469 858,980
- Lantai 4 m' 18.92 0.91 946,014 17,900,469 858,980
TAMPAK BARAT
- Lantai 1 m' 22.65 1.43 946,014 21,425,316 1,354,691
- Lantai 2 m' 22.32 1.76 946,014 21,115,969 1,664,038
- Lantai 3 m' 18.92 0.91 946,014 17,900,469 858,980
- Lantai 4 m' 18.92 0.91 946,014 17,900,469 858,980

DAFTAR NO. II.2.9 - PEKERJAAN FAÇADE 6,639,452,519 912,720,046


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.1. - PEKERJAAN DINDING

II.3.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon


sudah termasuk adukan biasa atau drymix, kolom
praktis, ringbalk, angkur, sparing dan semua
pekerjaan bantu yang berhubungan dengan pekerjaan
dinding tersebut.

II Harga satuan plesteran biasa atau drymix sudah


termasuk acian, skonengan, tali air , ketrikan atau
bobokan beton maupun bata , kawat ayam (jika
diperlukan) dan semua pekerjaan bantu yang
berhubungan dengan plesteran.

III Harga satuan pekerjaan pelapis dinding (seperti :


granit, marmer, keramik, porselin) sudah termasuk
adukan, cor beton,perekat (calbond), angkur, kawat
pengikat alumunium fixing pada dinding dengan
ketinggian lebih dari 2m, pemotongan, pinggulan, adu
manis, naad, dan alat bantu lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk


untuk dinding kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk


pengertian cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat


yang diperlukan dan sesuai spesifikasi.

I PEK. PASANG DINDING

Pasangan Bata ringan tebal 100 mm, setara ex.


Optima/ LeitchBrick, termasuk dinding
penebalan,urinoir,
- Lantai 1 perekat, adukan kering kolom dan m2 - by architect
- Lantai 2 m2 - by architect
- Lantai 3 m2 - by architect
- Lantai 4 m2 - by architect

II PEK. PELAPIS DINDING

1 Plesteran dan Acian, Plesteran halus berikut acian


halus, termasuk peralatan dan perlengkapan sesuai
spesifikasi dan gambar pada :
- Lantai 1 m2 - by architect
- Lantai 2 m2 - by architect
- Lantai 3 m2 - by architect
- Lantai 4 m2 - by architect

2 Pengecatan dengan fin. cat Interior setara ex.ICI /


Jotun tipe standar, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :

- Lantai 1 m2 - by architect
- Lantai 2 m2 - by architect
- Lantai 3 m2 - by architect
- Lantai 4 m2 - by architect

3 Cat eksterior setara ex.ICI / Jotun Tipe standar,


termasuk peralatan dan perlengkapan sesuai
spesifikasi
Eksterior dan gambar pada :
- Lantai 1 m2 - by architect
- Lantai 2 m2 - by architect
- Lantai 3 m2 - by architect
- Lantai 4 m2 - by architect

4 Cat minyak tipe standar, termasuk peralatan dan


perlengkapan sesuai spesifikasi dan gambar pada :
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.1.


Cat minyak tipe- PEKERJAAN DINDING
standar, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :
Eksterior

- Lantai 1
Fire Stairs As. 00-01 m2 - by architect
Fire Stairs As. 16-17 m2 - by architect
- Lantai 2
Fire Stairs As. 00-01 m2 - by architect
Fire Stairs As. 16-17 m2 - by architect
- Lantai 3
Fire Stairs As. 00-01 m2 - by architect
Fire Stairs As. 16-17 m2 - by architect
- Lantai 4
Fire Stairs As. 00-01 m2 - by architect
Fire Stairs As. 16-17 m2 - by architect

5 Wallpaper (WP) setara ex. Art Design, terpasang


termasuk perekat, perapihan, peralatan &
perlengkapan lainnya, sesuai dengan gambar dan
spesifikasi pada:
- Lantai 1
Musholla m2 69.97 1.68 111,296 7,787,695 186,866
- Lantai 3
Meeting Room 1 m2 66.93 (0.18) 111,296 7,449,022 (20,033)
VIP Room m2 33.27 3.72 111,296 3,702,809 413,464
Press Conference Room m2 85.29 6.15 111,296 9,492,412 684,469
Meeting Room 2 m2 58.65 0.42 111,296 6,527,494 46,744
Meeting Room 3 m2 58.80 0.30 111,296 6,544,188 33,389
- Lantai 4
VIP Room m2 112.22 (44.30) 111,296 12,489,820 (4,930,615)
Musholla m2 63.42 (3.78) 111,296 7,058,374 (420,698)
Function Room (VIP Lounge) m2 122.17 - 111,296 13,596,580 -

6 Veener (VN) setara ex. Abadi Indorona, terpasang


termasuk perekat, perapihan, peralatan &
perlengkapan lainnya, sesuai dengan gambar dan
spesifikasi pada:
- Lantai 4
Pre-Function & Lobby Lift m2 224.26 - 445,183 99,838,713 -
Function Room (VIP Lounge) m2 95.54 - 445,183 42,532,771 -
Coridor VIP Lounge m2 9.70 - 445,183 4,320,166 -

7 HPL (HPL) setara ex. Arborite, terpasang termasuk


perekat, perapihan, peralatan & perlengkapan lainnya,
sesuai dengan gambar dan spesifikasi pada:

- Lantai 1
VIP Lobby m2 25.99 (6.09) 500,831 13,014,187 (3,047,655)
- Lantai 2
Multi Purpose 2 m2 23.40 31.85 500,831 11,719,439 15,950,457
- Lantai 3
VIP Room m2 34.53 2.72 500,831 17,293,685 1,362,260
Coridor m2 68.72 (0.55) 500,831 34,417,588 (273,557)
Lobby Lift m2 51.81 (0.41) 500,831 25,948,040 (206,239)

8 Homogenous tile type topaz setara ex. Indogress uk.


600 x 600 mm , berikut adukan mortar, additiv,
grouting nat termasuk alat alat bantu lainnya dgn
peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar
- Lantai 1
Lounge Waiting Room m2 43.91 (43.91) 348,040 15,283,481 (15,283,481)

9 Tali air 20x20, termasuk peralatan dan perlengkapan


sesuai spesifikasi dan gambar pada :
Eksterior
- Lantai 1 m' - by architect
- Lantai 2 m' - by architect
- Lantai 3 m' - by architect
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.1. - PEKERJAAN DINDING


- Lantai 4 m' - by architect

10 Fin.kamprot , termasuk peralatan dan perlengkapan


sesuai spesifikasi dan gambar pada :
Eksterior
- Lantai 1 m2 - by architect
- Lantai 2 m2 - by architect
- Lantai 3 m2 - by architect
- Lantai 4 m2 - by architect
m2 -

11 Skim coat pada permukaan kolom beton, termasuk


peralatan dan perlengkapan sesuai spesifikasi dan
gambar
- Lantai 1pada : m2 - by architect
- Lantai 2 m2 - by architect
- Lantai 3 m2 - by architect
m2 - by architect

DAFTAR NO. II.3.1. - PEKERJAAN DINDING 339,016,464 (5,504,630)


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.1. - PEKERJAAN DINDING


DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.2 - PEKERJAAN PINTU dan JENDELA

II.3.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk


angkur, sealant, karet, kaca, pengelasan, pemasangan kolom
praktis sekeliling pintu & jendela, dan peralatan bantu yang
diperlukan dan bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU KACA
Pintu & Jendela kaca 1 daun Type GD1 ukuran overall 2700 x
3625 mm, terdiri dari tempered clear glass 12 mm thick setara
ex. Asahimas with patch fitting termasuk pemasangan, door seal,
hardware setara ex. Dekkson, kusen plywood fin.HPL dan
aksessories, sesuai dengan gambar dan spesifikasi, pada:

Lantai 1
- Retail 1 unit 1.00 (1.00) 17,038,261 17,038,261 (17,038,261)

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include

Pintu & Jendela kaca 1 daun Type GD1 ukuran overall 2700 x
3850 mm, terdiri dari tempered clear glass 12 mm thick setara
ex. Asahimas with patch fitting termasuk pemasangan, door seal,
hardware setara ex. Dekkson, kusen plywood fin.HPL dan
aksessories, sesuai dengan gambar dan spesifikasi, pada:

Lantai 1
- Retail 2 unit 1.00 17,984,831 17,984,831 -
- Retail 3 unit 1.00 17,984,831 17,984,831 -

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include
-

Pintu & Jendela kaca 1 daun Type GD1 ukuran overall 2700 x
4075 mm, terdiri dari tempered clear glass 12 mm thick setara
ex. Asahimas with patch fitting termasuk pemasangan, door seal,
hardware setara ex. Dekkson, kusen plywood fin.HPL dan
aksessories, sesuai dengan gambar dan spesifikasi, pada:

Lantai 1
- Retail 4 unit 1.00 19,404,686 19,404,686 -
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.2 - PEKERJAAN PINTU dan JENDELA


-
Pintu & Jendela kaca 1 daun Type GD1 ukuran overall 2700 x
6600 mm, terdiri dari tempered clear glass 12 mm thick setara
ex. Asahimas with patch fitting termasuk pemasangan, door seal,
hardware setara ex. Dekkson, kusen plywood fin.HPL dan
aksessories, sesuai dengan gambar dan spesifikasi, pada:

Lantai 1
- Retail 5 unit 1.00 31,236,812 31,236,812 -

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include
-
Pintu kaca Frameless 1 daun Type GD2 ukuran overall 2700 x
1400 mm, terdiri dari tempered clear glass 12 mm thick setara
ex. Asahimas with patch fitting termasuk pemasangan, door seal,
hardware setara ex. Dekkson dan aksessories, sesuai dengan
gambar dan spesifikasi, pada:

Lantai 2
- Multi Purpose 2 unit 1.00 6,625,991 6,625,991 -

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include
-
B PINTU KAYU

Pintu Kayu PD5 Daun pintu Honeycomb, Kusen alumunium 40


mm powder coating finish setara ex. Alexindo, termasuk
hardware setara ex. Dekkson sesuai spesifikasi dan gambar,
pada :

Lantai 2
- Office Room 1 unit 1.00 2,893,689 2,893,689 -
- Control Room/IT-Room unit 1.00 2,893,689 2,893,689 -
- Office Room 2 unit 1.00 2,893,689 2,893,689 -
- Office Room 3 unit 1.00 2,893,689 2,893,689 -

Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include

Moveable Partition ukuran overall 3000 x 6163 mm, setara ex


Sandei termasuk, hardware, door seal, perkuatan rail gantung,
rockwool density 50kg/m3, peralatan & perlengkapan

Lantai 3
- FEI & AEF Room unit 1.00 38,953,501 38,953,501 -
- Broadcast Room unit 1.00 38,953,501 38,953,501 -

C JENDELA KACA

Jendela kaca Type PD5 ukuran overall 3000 x 7400 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:

Lantai 2
- Office Room 1 unit 1.00 22,298,653 22,298,653 -
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.2 - PEKERJAAN PINTU dan JENDELA


Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 Include
Rambuncis art - 118 silver bh 1.00 Include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 Include

Jendela kaca Type PD5 ukuran overall 3000 x 2950 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:

Lantai 2
- Office Room 1 unit 1.00 8,889,328 8,889,328 -

Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 Include
Rambuncis art - 118 silver bh 1.00 Include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 Include

Jendela kaca Type PD5 ukuran overall 3000 x 1000 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:

Lantai 2
- Control Room/IT-Room unit 1.00 3,013,332 3,013,332 -
- Office Room 2 unit 1.00 3,013,332 3,013,332 -
- Office Room 3 unit 1.00 3,013,332 3,013,332 -

Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 Include
Rambuncis art - 118 silver bh 1.00 Include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 Include

Jendela kaca Type PD5 ukuran overall 3000 x 4560 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:

Lantai 2
- Control Room/IT-Room unit 1.00 13,740,792 13,740,792 -

Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 Include
Rambuncis art - 118 silver bh 1.00 Include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 Include

Jendela kaca Type PD5 ukuran overall 3000 x 5960 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:

Lantai 2
- Control Room/IT-Room unit 1.00 17,959,456 17,959,456 -

Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 Include
Rambuncis art - 118 silver bh 1.00 Include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 Include

C JENDELA KACA (Lanjutan)

Jendela kaca Type PD5 ukuran overall 3000 x 6000 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:

Lantai 2
- Office Room 2 unit 1.00 18,079,989 18,079,989 -
- Office Room 3 unit 1.00 18,079,989 18,079,989 -

Hardware :
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.2 - PEKERJAAN PINTU dan JENDELA


Hinges gracia BB 4"x3"x2 mm SS bh 3.00 Include
Rambuncis art - 118 silver bh 1.00 Include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 Include

DAFTAR NO. II.3.2 - PEKERJAAN PINTU dan JENDELA 307,845,372 (17,038,261)


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.3. - PEKERJAAN LANTAI

II.3.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

A Homogenous Tile

Homogenous tile (polished) type white onyx setara ex.


Indogress uk. 1200 x 600 mm , berikut adukan mortar, additiv,
grouting nat termasuk alat alat bantu lainnya dgn peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar, pada :

- Lantai 1
Public Hall m2 398.17 (76) 532,430 211,999,104 (40,681,925)
VIP Lobby m2 145.19 15 532,430 77,301,282 8,242,702

Homogenous tile (polished) type white onyx setara ex.


Indogress uk. 800 x 800 mm , berikut adukan mortar, additiv,
grouting nat termasuk alat alat bantu lainnya dgn peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar, pada :

- Lantai 1
Steward m2 4.60 44 1,073,930 4,943,023 47,147,737
Office m2 32.74 0 1,073,930 35,157,774 116,853
Coridor VIP Toilet m2 33.12 22 1,073,930 35,565,035 23,364,297
Athelete Room m2 74.43 1 1,073,930 79,936,408 664,723
Coridor Toilet Athelete Room m2 8.42 0 1,073,930 9,045,242 8,525
Secretariat Office m2 129.06 2 1,073,930 138,601,413 1,947,994
Retail 1 m2 23.53 (0) 1,073,930 25,270,915 (128,496)
Retail 2 m2 22.42 0 1,073,930 24,074,826 16,968
Retail 3 m2 22.42 0 1,073,930 24,074,826 24,593
Retail 4 m2 23.60 0 1,073,930 25,343,406 77,269
Retail 5 m2 51.99 (0) 1,073,930 55,828,373 (133,182)
Coridor Musholla m2 41.24 - 1,073,930 44,285,896 -
Lounge Waiting Room m2 77.45 23 1,073,930 83,173,865 24,353,651
Meeting Room m2 144.18 42 1,073,930 154,844,582 45,339,132

- Lantai 2
Multi Purpose 1 m2 130.11 1 1,073,930 139,734,396 967,652
Multi Purpose 2 m2 134.65 11 1,073,930 144,600,082 11,327,419
Multi Purpose 3 m2 342.44 (3) 1,073,930 367,760,421 (3,683,188)
Coridor toilet m2 9.42 (0) 1,073,930 10,116,421 (56,704)

- Lantai 3
Room As. B1 m2 39.74 1 1,073,930 42,676,636 549,584
Meeting Room 1 m2 50.76 0 1,073,930 54,512,687 192,126
VIP Room m2 43.10 0 1,073,930 46,283,689 151,863
Announcer BOX m2 3.34 1 1,073,930 3,585,473 582,986
Judges Room m2 3.34 1 1,073,930 3,585,210 583,249
FEI & AEF Room m2 5.34 (1) 1,073,930 5,735,011 (633,199)
Broadcast Room m2 5.38 (1) 1,073,930 5,774,913 (642,816)
Reporter Room m2 5.19 (0) 1,073,930 5,574,457 (462,764)
Office m2 46.30 0 1,073,930 49,722,940 508,096
Meeting Room 4 m2 11.04 (1) 1,073,930 11,856,396 (675,389)
Appeal Room m2 11.04 (1) 1,073,930 11,856,397 (675,389)
Lobby Lift m2 44.97 (45) 1,073,930 48,299,062 (48,299,062)
Coridor m2 169.88 (65) 1,073,930 182,444,355 (70,118,580)
Coridor toilet m2 18.84 (19) 1,073,930 20,232,841 (20,232,841)
Homogenous tile (polished) type white onyx setara ex.
Indogress uk. 800 x 800 mm , berikut adukan mortar, additiv,
grouting nat termasuk alat alat bantu lainnya dgn peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar, pada :
(Lanjutan)

- Lantai 4
Athlete Dining m2 194.36 (194) 1,073,930 208,732,061 (208,732,061)
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.3. - PEKERJAAN LANTAI


VIP Room m2 53.09 (53) 1,073,930 57,013,715 (57,013,715)
Pre-Function & Lobby Lift m2 143.43 (143) 1,073,930 154,033,301 (154,033,301)
Coridor VIP Lounge m2 25.32 (1) 1,073,930 27,187,389 (1,183,892)
Coridor Toilet m2 53.05 (1) 1,073,930 56,973,304 (664,469)
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.3. - PEKERJAAN LANTAI

Homogenous tile type topaz ex. Indogress atau setara uk. 800
x 800 mm , berikut adukan mortar, additiv, grouting nat
termasuk alat alat bantu lainnya dgn peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar, pada :-Lanjutan
- Lantai 2
Multi Purpose 1 m2 7.62 0 507,040 3,863,645 26,755
Multi Purpose 2 m2 8.38 1 507,040 4,246,967 332,691
Multi Purpose 3 m2 8.88 (0) 507,040 4,502,516 (45,094)
Office Room 1 m2 90.50 1 507,040 45,887,120 428,145
Control Room/IT-Room m2 110.75 (13) 507,040 56,154,680 (6,542,946)
Office Room 2 m2 55.50 1 507,040 28,140,086 266,576
Office Room 3 m2 55.50 1 507,040 28,140,086 266,576

B Carpet

Carpet roll type odyssey setara ex. Classic, berikut perekat,


termasuk alat alat bantu lainnya dgn peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar

- Lantai 1
Musholla (Provisional) m2 37.89 - 228,156 8,644,908 -

Carpet tile type Abstract series setara ex. Balance ukuran 500
x 500 mm, berikut perekat, termasuk alat alat bantu lainnya
dgn peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar
- Lantai 3
Press Conference Room m2 79.49 1 155,814 12,386,248 165,287
Announcer BOX m2 20.63 (0) 155,814 3,214,264 (16,509)
Judges Room m2 20.04 0 155,814 3,122,567 75,188
Judges Room m2 59.21 - 155,814 9,226,300 -
FEI & AEF Room m2 59.18 1 155,814 9,220,510 129,685
Broadcast Room m2 76.11 (15) 155,814 11,859,478 (2,387,825)
Reporter Room m2 49.56 29 155,814 7,722,662 4,443,622
Meeting Room 2 m2 49.56 1 155,814 7,722,662 177,030
Meeting Room 3 m2 45.05 (0) 155,814 7,019,001 (609)
Meeting Room 4 m2 45.05 (0) 155,814 7,019,001 (608)

- Lantai 4
Function Room (VIP Lounge) m2 795.32 35 155,814 123,921,763 5,531,190
Coridor VIP Lounge m2 69.46 3 155,814 10,823,333 483,094
Musholla m2 29.22 (0) 155,814 4,553,278 (23,235)

C Plint Homogenous Tile

Plint Homogenous tile type white onyx setara ex. Indogress uk.
100 x 1200 mm , berikut adukan mortar, additiv, grouting nat
termasuk alat alat bantu lainnya dgn peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar, pada :

- Lantai 1
Public Hall m' 60.06 (23) 73,845 4,435,214 (1,722,837)
VIP Lobby m' 37.40 20 73,845 2,761,661 1,490,852

Plint Homogenous tile type white onyx setara ex. Indogress uk.
100 x 800 mm , berikut adukan mortar, additiv, grouting nat
termasuk alat alat bantu lainnya dgn peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar, pada :

- Lantai 1
Steward m' 29.20 (1) 73,845 2,156,278 (86,879)
Office m' 22.80 0 73,845 1,683,669 864
Coridor VIP Toilet m' 32.23 25 73,845 2,379,734 1,809,457
Athelete Room m' 41.05 0 73,845 3,031,344 9,334
Coridor Toilet Athelete Room m' 12.05 3 73,845 889,834 235,219
Secretariat Office m' 39.60 (1) 73,845 2,924,268 (94,138)
Retail 1 m' 17.03 1 73,845 1,257,214 96,065
Retail 2 m' 15.90 0 73,845 1,174,138 1,086
Retail 3 m' 15.90 (0) 73,845 1,174,138 (650)
Retail 4 m' 16.58 0 73,845 1,223,983 3,611
Retail 5 m' 21.45 1 73,845 1,583,979 58,855
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.3. - PEKERJAAN LANTAI


Coridor Musholla m' 28.85 - 73,845 2,130,728 -
Lounge Waiting Room m' 25.93 2 73,845 1,914,436 133,297
Meeting Room m' 41.85 3 73,845 3,090,420 215,178
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.3. - PEKERJAAN LANTAI


Plint Homogenous tile type white onyx ex. Indogress atau
setara uk. 100 x 800 mm , berikut adukan mortar, additiv,
grouting nat termasuk alat alat bantu lainnya dgn peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar,
pada :- Lanjutan
- Lantai 2
Multi Purpose 1 m' 34.05 (2) 73,845 2,514,427 (125,773)
Multi Purpose 2 m' 37.57 14 73,845 2,774,362 1,070,614
Multi Purpose 3 m' 79.89 1 73,845 5,899,563 93,458

- Lantai 3
Room As. B1 m' 22.43 (2) 73,845 1,655,978 (148,252)
Meeting Room 1 m' 21.93 2 73,845 1,619,055 119,134
VIP Room m' 22.04 3 73,845 1,627,547 214,934
Office m' 24.64 4 73,845 1,819,545 324,564
Lobby Lift m' 22.13 31 73,845 1,633,824 2,302,049
Coridor m' 24.64 96 73,845 1,819,545 7,076,603

- Lantai 4
Athlete Dining m' 33.22 (33) 73,845 2,452,914 (2,452,914)
VIP Room m' 19.07 (19) 73,845 1,408,375 (1,408,375)
Pre-Function & Lobby Lift m' 60.91 (61) 73,845 4,498,167 (4,498,167)
Coridor VIP Lounge m' 23.54 1 73,845 1,738,647 88,710
Coridor Toilet m' 23.54 21 73,845 1,738,647 1,527,908

Plint Homogenous tile type topaz ex. Indogress atau setara uk.
100 x 800 mm , berikut adukan mortar, additiv, grouting nat
termasuk alat alat bantu lainnya dgn peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar
- Lantai 2
Office Room 1 m' 20.65 1 292,850 6,047,353 274,635
Control Room/IT-Room m' 22.18 55 292,850 6,495,413 15,971,483
Office Room 2 m' 15.33 0 292,850 4,487,926 47,149
Office Room 3 m' 15.33 0 292,850 4,487,926 35,435

Plint Carpet roll type odyssey setara ex. Classic custom,


berikut perekat, termasuk alat alat bantu lainnya dgn peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar

- Lantai 1
Musholla (Provisional) m' 28.23 - 228,156 6,439,937 -

Plint Carpet tile type Abstract series setara ex. Balance ukuran
500 x 500 mm, berikut perekat, termasuk alat alat bantu
lainnya dgn peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar
- Lantai 3
Press Conference Room m' 30.21 5 46,744 1,412,283 224,732
Announcer BOX m' 10.05 - 46,744 469,779 -
Judges Room m' 15.20 - 46,744 710,512 -
Judges Room m' 17.30 - 46,744 808,675 -
FEI & AEF Room m' 17.30 1 46,744 808,675 33,777
Broadcast Room m' 23.43 (6) 46,744 1,094,983 (264,684)
Reporter Room m' 21.96 1 46,744 1,026,643 30,543
Meeting Room 2 m' 16.26 7 46,744 759,827 340,751
Meeting Room 3 m' 18.70 5 46,744 874,117 226,162
Meeting Room 4 m' 11.05 19 46,744 516,523 900,097

- Lantai 4
Function Room (VIP Lounge) m' 110.02 - 46,744 5,142,890 -
Coridor VIP Lounge m' 57.62 - 46,744 2,693,602 -
Musholla m' 20.52 2 46,744 959,191 93,376
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.3. - PEKERJAAN LANTAI

DAFTAR NO. II.3.3. - PEKERJAAN LANTAI 3,197,376,090 (414,327,276)


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.4 - PEKERJAAN PLAFOND

II.3.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A Plafond Gypsumboard tebal .9 mm setara ex. Jayaboard, finishing cat


interior warna putih setara ex Pentalite, Dulux-ICI , termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :

Lantai 1
- Public Hall m2 263.29 (126.79) 124,090 32,671,342 (15,733,653)
- VIP Lobby m2 100.80 6.37 124,090 12,508,075 790,576
- Steward m2 4.53 43.83 124,090 561,848 5,438,500
- Office m2 32.66 0.03 124,090 4,053,089 4,195
- Coridor VIP Toilet m2 32.54 21.85 124,090 4,038,257 2,711,321
- Athelete Room m2 74.20 0.63 124,090 9,207,607 77,738
- Coridor Toilet Athelete Room m2 8.13 0.15 124,090 1,008,859 18,668
- Secretariat Office m2 128.94 1.71 124,090 16,000,165 212,057
- Retail 1 m2 23.53 (0.12) 124,090 2,919,993 (14,847)
- Retail 2 m2 22.42 0.02 124,090 2,781,788 1,961
- Retail 3 m2 22.42 0.02 124,090 2,781,788 2,842
- Retail 4 m2 23.60 0.07 124,090 2,928,369 8,928
- Retail 5 m2 51.99 (0.12) 124,090 6,450,833 (15,389)
- Coridor Musholla m2 40.53 - 124,090 5,029,412 -
- Lounge Waiting Room m2 76.51 23.07 124,090 9,493,971 2,862,140
- Meeting Room m2 143.65 43.31 124,090 17,825,372 5,373,802
- Musholla m2 37.89 (2.78) 124,090 4,701,807 (344,685)

Lantai 2
- Multi Purpose 1 m2 137.73 0.95 124,090 17,091,535 118,358
- Multi Purpose 2 m2 143.02 11.20 124,090 17,747,566 1,390,277
- Multi Purpose 3 m2 351.19 (3.38) 124,090 43,578,990 (419,867)
- Office Room 1 m2 90.50 0.84 124,090 11,230,145 104,782
- Control Room/IT-Room m2 110.75 (13.65) 124,090 13,742,968 (1,694,350)
- Office Room 2 m2 55.50 0.53 124,090 6,886,840 65,240
- Office Room 3 m2 55.50 0.53 124,090 6,886,840 65,240

Lantai 3
- Room As. B1 m2 39.66 0.44 124,090 4,921,875 54,196
- Meeting Room 1 m2 50.64 0.07 124,090 6,283,918 9,170
- VIP Room m2 42.90 0.19 124,090 5,323,770 23,131
- Press Conference Room m2 79.36 1.20 124,090 9,847,634 148,386
- Announcer BOX m2 23.38 1.03 124,090 2,901,069 127,273
- Judges Room m2 23.38 1.03 124,090 2,901,069 127,273
- FEI & AEF Room m2 63.97 0.79 124,090 7,937,418 98,564
- Broadcast Room m2 63.97 1.60 124,090 7,937,418 198,791
A Plafond Gypsumboard tebal .9 mm setara ex. Jayaboard, finishing cat
interior warna putih setara ex Pentalite, Dulux-ICI , termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :-Lanjutan
Lantai 3
- Reporter Room m2 80.72 2.13 124,090 10,015,924 263,927
- Office m2 46.22 0.55 124,090 5,736,058 68,016
- Meeting Room 2 m2 49.43 1.27 124,090 6,133,563 157,738
- Meeting Room 3 m2 49.43 1.29 124,090 6,133,563 159,525
- Meeting Room 4 m2 51.73 3.72 124,090 6,419,641 461,733
- Appeal Room m2 51.73 3.72 124,090 6,419,641 461,733
- Lobby Lift m2 44.97 41.83 124,090 5,580,839 5,191,116
- Coridor m2 183.80 (42.11) 124,090 22,808,334 (5,225,129)

Lantai 4
- Athlete Dining m2 194.05 (13.31) 124,090 24,079,394 (1,651,938)
- VIP Room m2 52.97 (0.65) 124,090 6,572,905 (80,355)
- Pre-Function & Lobby Lift m2 81.22 (13.85) 124,090 10,078,224 (1,718,827)
- Function Room (VIP Lounge) m2 281.79 (5.73) 124,090 34,967,758 (711,423)
- Coridor VIP Lounge m2 45.09 - 124,090 5,595,088 -
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.4 - PEKERJAAN PLAFOND


- Coridor Toilet m2 52.38 0.06 124,090 6,499,366 6,983
- Musholla m2 29.07 0.00 124,090 3,607,609 109
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.4 - PEKERJAAN PLAFOND

B Membrane Ceiling type customized setara ex. Intrino atau setara, black
glossy paint finish termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Public Hall m2 133.78 51.49 1,214,878 162,520,673 62,559,250
- VIP Lobby m2 43.28 10.22 1,214,878 52,576,778 12,416,425

C Metal Ceiling type baffle setara setara ex. Durlum, termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
Lantai 3
- Meeting Room 4 m2 3.77 0.03 458,813 1,727,431 14,177
- Appeal Room m2 3.77 0.03 458,813 1,727,431 14,177

D Metal Ceiling type Custom setara ex. Durlum, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :

Lantai 4
- Function Room (VIP Lounge) m2 358.60 (358.60) 444,627 159,443,063 (159,443,063)
- Coridor VIP Lounge m2 18.80 (18.80) 444,627 8,358,978 (8,358,978)

E Metal Ceiling type linear setara ex. Durlum, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :

Lantai 4
- Pre-Function & Lobby Lift m2 61.80 (61.80) 425,706 26,308,600 (26,308,600)
- Function Room (VIP Lounge) m2 154.70 (154.70) 425,706 65,856,641 (65,856,641)
- Coridor VIP Lounge m2 30.50 (30.50) 425,706 12,984,018 (12,984,018)

F Drop Ceiling Gypsumboard h: 50mm tebal .9 mm setara ex. Jayaboard,


finishing cat interior warna putih termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Public Hall m' 130.01 (34.20) 44,518 5,787,733 (1,522,352)
- VIP Lobby m' 55.26 21.26 44,518 2,460,170 946,659
- Steward m' 26.40 (0.02) 44,518 1,175,283 (681)
- Office m' 20.80 0.56 44,518 925,980 24,930

G Drop Ceiling Gypsumboard h: 50mm tebal .9 mm setara ex. Jayaboard,


finishing cat interior warna putih termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :-
Lanjutan

Lantai 1
- Coridor VIP Toilet m' 29.10 0.16 44,518 1,295,482 7,123
- Athelete Room m' 37.80 (0.09) 44,518 1,682,791 (4,042)
- Secretariat Office m' 50.10 2.71 44,518 2,230,366 120,645
- Coridor Musholla m' 36.50 - 44,518 1,624,917 -
- Musholla m' 15.85 (15.85) 44,518 705,659 (705,659)

H Drop Ceiling Gypsumboard h: 150mm tebal .9 mm setara ex. Jayaboard,


finishing cat interior warna putih termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :

Lantai 2
- Multi Purpose 1 m' 138.90 (11.56) 44,518 6,183,590 (514,631)
- Multi Purpose 2 m' 146.32 (1.74) 44,518 6,513,916 (77,462)
- Multi Purpose 3 m' 337.78 - 44,518 15,037,387 -

Lantai 3
- Meeting Room 1 m' 58.51 6.79 44,518 2,604,745 302,299
- VIP Room m' 47.95 10.28 44,518 2,134,682 457,440
- Press Conference Room m' 97.76 0.50 44,518 4,351,940 22,351
- Announcer Box & Judges Room m' 214.65 1.13 44,518 9,555,850 50,395
- FEI & AEF Room m' 75.33 (0.20) 44,518 3,353,340 (8,764)
- Broadcast Room m' 75.38 (1.46) 44,518 3,355,788 (64,943)
- Reporter Room m' 59.65 14.27 44,518 2,655,737 635,109
- Office m' 39.00 0.18 44,518 1,736,213 8,013
- Meeting Room 2 m' 65.78 0.29 44,518 2,928,206 12,894
- Meeting Room 3 m' 65.78 0.29 44,518 2,928,206 12,894
- Meeting Room 4 m' 46.25 (7.25) 44,518 2,058,971 (322,758)
- Appeal Room m' 46.25 (7.25) 44,518 2,058,971 (322,758)
- Lobby Lift m' 29.96 (0.30) 44,518 1,333,625 (13,212)
- Coridor m' 245.76 3.83 44,518 10,940,694 170,625

Lantai 4
- Athlete Dining m' 44.74 0.22 44,518 1,991,953 9,701
- VIP Room m' 7.74 0.05 44,518 344,623 2,054
- Coridor Toilet m' 33.05 0.01 44,518 1,471,327 625

I Drop Ceiling Gypsumboard h: 250mm tebal .9 mm setara ex. Jayaboard,


finishing cat interior warna putih, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.4


Drop Ceiling - PEKERJAAN
Gypsumboard PLAFOND
h: 250mm tebal .9 mm setara ex. Jayaboard,
finishing cat interior warna putih, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.4 - PEKERJAAN PLAFOND


Lantai 2
- Office Room 1 m' 5.20 (0.01) 44,518 231,495 (445)
- Office Room 2 m' 5.20 (0.01) 44,518 231,495 (445)
- Office Room 3 m' 5.20 (0.01) 44,518 231,495 (445)

Lantai 3
- FEI & AEF Room m' 6.40 (0.02) 44,518 284,917 (745)
- Broadcast Room m' 6.40 (0.02) 44,518 284,917 (745)
- Reporter Room m' 6.40 (0.02) 44,518 284,917 (745)

J Drop Ceiling Gypsumboard h: 490mm tebal .9 mm setara ex. Jayaboard,


finishing cat interior warna putih, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Retail 5 m' 7.40 (0.04) 44,518 329,435 (2,003)

DAFTAR NO. II.3.4 - PEKERJAAN PLAFOND 1,055,639,965 (199,532,524)


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.5. - PEKERJAAN SANITARY

II.3.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan


kelengkapan material bantu (adukan, plesteran, acian, nad, sealan,
grouting, bahan bantu pengubung (doble niple) yang berhubungan
dengan instalasi ME dan lainnya berikut pemasangan dan
perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Lantai 1

Male Public Toilet As. A1


- Wastafel Set setara ex TOTO LW549J bh 3.00 - 3,644,970 10,934,910 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 3.00 - 3,385,100 10,155,300 -
- Floor Drain setara ex. TOTO TX 1 BN bh 2.00 - 385,700 771,400 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 3.00 - 267,820 803,460 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -
- Faucet setara ex. TOTO TX 108LDN bh 3.00 - 1,301,490 3,904,470 -
- Urinoir setara ex. TOTO UW 930 JM bh 3.00 - 3,483,960 10,451,880 -
- Urinoir Divider setara ex. TOTO AW 115 J bh 2.00 - 3,483,960 6,967,920 -

- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Female Public Toilet As. A1


- Wastafel Set setara ex TOTO LW549J bh 3.00 - 3,644,970 10,934,910 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 3.00 - 3,385,100 10,155,300 -
- Floor Drain setara ex. TOTO TX 1 BN bh 2.00 - 385,700 771,400 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 3.00 - 267,820 803,460 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -
- Faucet setara ex. TOTO TX 108LDN bh 3.00 - 1,301,490 3,904,470 -
- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Disable Toilet As. A1


- Wastafel Set setara ex TOTO LW549J bh 1.00 - 3,644,970 3,644,970 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 1.00 - 3,385,100 3,385,100 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 1.00 - 267,820 267,820 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 1.00 - 581,660 581,660 -
- Faucet setara ex. TOTO TX 108LDN bh 1.00 - 1,301,490 1,301,490 -
- Robe Hook setara ex TOTO (Provisional) bh 1.00 - 186,400 186,400 -

Male Athlete Toilet


- Wastafel Set setara ex TOTO LW549J bh 2.00 - 3,644,970 7,289,940 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 2.00 - 3,385,100 6,770,200 -
- Floor Drain setara ex. TOTO TX 1 BN bh 4.00 - 385,700 1,542,800 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 2.00 - 267,820 535,640 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 2.00 - 581,660 1,163,320 -
- Faucet setara ex. TOTO TX 108LDN bh 2.00 - 1,301,490 2,602,980 -
- Sliding Rail (638 mm) setara ex. TOTO TX721AN bh 1.00 - 392,850 392,850 -
- Shower Set setara ex. TOTO TX432SHBR bh 1.00 - 2,122,450 2,122,450 -

- Urinoir setara ex. TOTO UW 930 JM bh 3.00 - 3,483,960 10,451,880 -


- Urinoir Divider setara ex. TOTO AW 115 J bh 2.00 - 3,483,960 6,967,920 -

- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Female Athlete Toilet


- Wastafel Set setara ex TOTO LW549J bh 2.00 - 3,644,970 7,289,940 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 2.00 - 3,385,100 6,770,200 -
- Floor Drain setara ex. TOTO TX 1 BN bh 3.00 - 385,700 1,157,100 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 2.00 - 267,820 535,640 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 2.00 - 581,660 1,163,320 -
- Faucet setara ex. TOTO TX 108LDN bh 2.00 - 1,301,490 2,602,980 -
- Sliding Rail (638 mm) setara ex. TOTO TX721AN bh 1.00 - 392,850 392,850 -

Female Athlete Toilet - Lanjutan


- Shower Set setara ex. TOTO TX432SHBR bh 1.00 - 2,122,450 2,122,450 -

- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Male Public Toilet As. A7


- Wastafel Set setara ex TOTO LW549J bh 3.00 - 3,644,970 10,934,910 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 3.00 - 3,385,100 10,155,300 -
- Floor Drain setara ex. TOTO TX 1 BN bh 4.00 - 385,700 1,542,800 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 3.00 - 267,820 803,460 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -
- Faucet setara ex. TOTO TX 108LDN bh 3.00 - 1,301,490 3,904,470 -
- Urinoir setara ex. TOTO UW 930 JM bh 3.00 - 3,483,960 10,451,880 -
- Urinoir Divider setara ex. TOTO AW 115 J bh 2.00 - 3,483,960 6,967,920 -
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.5. - PEKERJAAN SANITARY


- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Female Public Toilet As. A7


- Wastafel Set setara ex TOTO LW549J bh 3.00 - 3,644,970 10,934,910 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 4.00 - 3,385,100 13,540,400 -
- Floor Drain setara ex. TOTO TX 1 BN bh 3.00 - 385,700 1,157,100 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 4.00 - 267,820 1,071,280 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 4.00 - 581,660 2,326,640 -
- Faucet setara ex. TOTO TX 108LDN bh 3.00 - 1,301,490 3,904,470 -
- Robe Hook setara ex TOTO (Provisional) bh 4.00 - 186,400 745,600 -

Disable Toilet As. A1


- Wastafel Set setara ex TOTO LW549J bh 1.00 - 3,644,970 3,644,970 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 1.00 - 3,385,100 3,385,100 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 1.00 - 267,820 267,820 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 1.00 - 581,660 581,660 -
- Faucet setara ex. TOTO TX 108LDN bh 1.00 - 1,301,490 1,301,490 -
- Robe Hook setara ex TOTO (Provisional) bh 1.00 - 186,400 186,400 -

Janitor
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 1.00 - 229,660 229,660 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -

Ablution
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 4.00 - 229,660 918,640 -
- Floor Drain setara ex. TOTO TX 1 BN bh 2.00 - 385,700 771,400 -

2 Lantai 2

Male Public Toilet As. D9


- Wastafel Set setara ex TOTO LW549J bh 2.00 - 3,644,970 7,289,940 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 3.00 - 3,385,100 10,155,300 -
- Floor Drain setara ex. TOTO TX 1 BN bh 4.00 - 385,700 1,542,800 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 3.00 - 267,820 803,460 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -
- Faucet setara ex. TOTO TX 108LDN bh 2.00 - 1,301,490 2,602,980 -
- Urinoir setara ex. TOTO UW 930 JM bh 2.00 - 3,483,960 6,967,920 -
- Urinoir Divider setara ex. TOTO AW 115 J bh 1.00 - 3,483,960 3,483,960 -

- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Female Public Toilet As. D9


- Wastafel Set setara ex TOTO LW549J bh 3.00 - 3,644,970 10,934,910 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 3.00 - 3,385,100 10,155,300 -
- Floor Drain setara ex. TOTO TX 1 BN bh 3.00 - 385,700 1,157,100 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 3.00 - 267,820 803,460 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -
- Faucet setara ex. TOTO TX 108LDN bh 3.00 - 1,301,490 3,904,470 -
- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Janitor
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 1.00 - 229,660 229,660 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -

3 Lantai 3

Male Public Toilet As. D9


- Wastafel Set setara ex TOTO LW549J bh 2.00 - 3,644,970 7,289,940 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 3.00 - 3,385,100 10,155,300 -
- Floor Drain setara ex. TOTO TX 1 BN bh 4.00 1.00 385,700 1,542,800 385,700
- Paper Holder setara ex.TOTO TX 720 ACRB bh 3.00 - 267,820 803,460 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -
- Faucet setara ex. TOTO TX 108LDN bh 2.00 - 1,301,490 2,602,980 -
- Urinoir setara ex. TOTO UW 930 JM bh 2.00 - 3,483,960 6,967,920 -
- Urinoir Divider setara ex. TOTO AW 115 J bh 1.00 - 3,483,960 3,483,960 -

- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Female Public Toilet As. D9


- Wastafel Set setara ex TOTO LW549J bh 3.00 - 3,644,970 10,934,910 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 3.00 - 3,385,100 10,155,300 -
- Floor Drain setara ex. TOTO TX 1 BN bh 3.00 1.00 385,700 1,157,100 385,700
- Paper Holder setara ex.TOTO TX 720 ACRB bh 3.00 - 267,820 803,460 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -
- Faucet setara ex. TOTO TX 108LDN bh 3.00 - 1,301,490 3,904,470 -
- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Janitor As. D9
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 1.00 - 229,660 229,660 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -

Male VIP Toilet As. D1


- Wastafel Set setara ex TOTO LW549J bh 2.00 - 3,644,970 7,289,940 -
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.5. - PEKERJAAN SANITARY


- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 3.00 - 3,385,100 10,155,300 -
- Floor Drain setara ex. TOTO TX 1 BN bh 4.00 1.00 385,700 1,542,800 385,700
- Paper Holder setara ex.TOTO TX 720 ACRB bh 3.00 - 267,820 803,460 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -
- Faucet setara ex. TOTO TX 108LDN bh 2.00 - 1,301,490 2,602,980 -
- Urinoir setara ex. TOTO UW 930 JM bh 2.00 - 3,483,960 6,967,920 -
- Urinoir Divider setara ex. TOTO AW 115 J bh 1.00 - 3,483,960 3,483,960 -

- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Female VIP Toilet As. D1


- Wastafel Set setara ex TOTO LW549J bh 3.00 - 3,644,970 10,934,910 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 3.00 - 3,385,100 10,155,300 -
- Floor Drain setara ex. TOTO TX 1 BN bh 3.00 1.00 385,700 1,157,100 385,700
- Paper Holder setara ex.TOTO TX 720 ACRB bh 3.00 - 267,820 803,460 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -
- Faucet setara ex. TOTO TX 108LDN bh 3.00 - 1,301,490 3,904,470 -
- Robe Hook setara ex TOTO (Provisional) bh 3.00 - 186,400 559,200 -

Janitor As. D1
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 1.00 - 229,660 229,660 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -

4 Lantai 4

Male VVIP Toilet As. D1


- Wastafel Set setara ex TOTO LW549J bh 2.00 - 3,644,970 7,289,940 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 2.00 - 3,385,100 6,770,200 -
- Floor Drain setara ex. TOTO TX 1 BN bh 3.00 - 385,700 1,157,100 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 2.00 - 267,820 535,640 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 2.00 - 581,660 1,163,320 -
- Faucet setara ex. TOTO TX 108LDN bh 2.00 - 1,301,490 2,602,980 -
- Urinoir setara ex. TOTO UW 930 JM bh 4.00 - 3,483,960 13,935,840 -
Male VVIP Toilet As. D1 - Lanjutan
- Urinoir Divider setara ex. TOTO AW 115 J bh 3.00 - 3,483,960 10,451,880 -

- Robe Hook setara ex TOTO (Provisional) bh 2.00 - 186,400 372,800 -

Female VVIP Toilet As. D1


- Wastafel Set setara ex TOTO LW549J bh 4.00 - 3,644,970 14,579,880 -
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 4.00 - 3,385,100 13,540,400 -
- Floor Drain setara ex. TOTO TX 1 BN bh 3.00 - 385,700 1,157,100 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 4.00 - 267,820 1,071,280 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 4.00 - 581,660 2,326,640 -
- Faucet setara ex. TOTO TX 108LDN bh 4.00 - 1,301,490 5,205,960 -
- Robe Hook setara ex TOTO (Provisional) bh 4.00 - 186,400 745,600 -

Janitor As. D1
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 1.00 - 229,660 229,660 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -

Male Ablution
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 2.00 - 229,660 459,320 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -

Female Ablution
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 2.00 - 229,660 459,320 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.5. - PEKERJAAN SANITARY

DAFTAR NO. II.3.5. - PEKERJAAN SANITARY 521,005,020 1,542,800


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp

DAFTAR NO. II.3.6. - PEKERJAAN FIX FURNITURE

II.3.6.0. Catatan Harga

I Harga satuan pekerjaan sudah termasuk fitting, accessories, alat


bantu, perlengkapan dan peralatan yang diperlukan

II Harga satuan Backdrop dinding panel HPL sudah termasuk


rangka, penyesuaian pola permukaan, bahan terbuang, biaya
pengeringan kayu, anti rayap, penyambungan dan finishing

III Harga satuan pada pekerjaan Movable Partition sudah termasuk


biaya untuk rangka, perkuatan struktur penggantung, sound
berrier, siap cat harus sudah termasuk biaya fabrikasi, handling
dan pemasangan, angkur-angkur, bracket, sealant dan back of
rod pada celah-celah horisontal dan vertikal untuk mencegah
kebocoran udara, air dan suara.

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat

V Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste)

VI Harga satuan sesuai dengan gambar dan spesifikasi teknis

DAFTAR NO. II.3.6. - PEKERJAAN FIX FURNITURE -


Dipindahkan ke Penjumlahan Total
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.7. - PEKERJAAN LOOSE FURNITURE

II.3.7.0. Catatan Harga

I Harga satuan pekerjaan furniture sudah termasuk fitting,


accessories, alat bantu, perlengkapan dan peralatan yang
diperlukan

II Harga satuan sudah termasuk lampu, kabel, fitting dan sparing-


sparing sesuai gambar dari konsultan terkait

III Harga satuan Backdrop dinding panel HPL sudah termasuk


rangka, penyesuaian pola permukaan, bahan terbuang, biaya
pengeringan kayu, anti rayap, penyambungan dan finishing

IV Harga satuan pada pekerjaan Movable Partition sudah termasuk


biaya untuk rangka, perkuatan struktur penggantung, sound
berrier, siap cat harus sudah termasuk biaya fabrikasi, handling
dan pemasangan, angkur-angkur, bracket, sealant dan back of
rod pada celah-celah horisontal dan vertikal untuk mencegah
kebocoran udara, air dan suara.

V Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

VI Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste)

VII Harga satuan sesuai dengan gambar dan spesifikasi teknis

A. TRIBUNE

L, Locker & Storage, uk panjang 600mm x lebar 500mm x


tinggi 2500mm, Plywood 18mm finish HPl ex. Arborite atau
setara vinyl edging, fitting & accessoris ex. Setara Hafelle,
termasuk Alumunium extrusi handle dan alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :
1 - Lantai 1 unit 24.00 - 3,130,192 75,124,609 -
2 - Lantai 3 unit 11.00 - 3,130,192 34,432,112 -

Cermin 8mm, uk lebar 3300mm x tinggi 1142mm, termasuk


alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :

Lantai 1
3 - VIP Male Toilet unit 1.00 (1.00) 3,010,413 3,010,413 (3,010,413)

Cermin 8mm, uk lebar 2610mm x tinggi 1142mm, termasuk


alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-
1104/1204 )
Lantai 1
4 - Male Toilet unit 1.00 (1.00) 2,371,841 2,371,841 (2,371,841)

Cermin 8mm, uk lebar 2600mm x tinggi 1142mm, termasuk


alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-
1104/1204 )
Lantai 1
5 - Female Toilet unit 1.00 (1.00) 2,371,841 2,371,841 (2,371,841)

Cermin 8mm, uk lebar 2490mm x tinggi 1142mm, termasuk


alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-
1104/1204 )
Lantai 1
6 - VIP Female Toilet unit 1.00 (1.00) 2,271,494 2,271,494 (2,271,494)
Lantai 2
7 - Female Toilet unit 1.00 (1.00) 2,271,494 2,271,494 (2,271,494)
Lantai 3
8 - Female Toilet unit 2.00 (2.00) 2,271,494 4,542,987 (4,542,987)

Cermin 8mm, uk lebar 1805mm x tinggi 1142mm, termasuk


alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-
1104/1204 )
Lantai 1
9 - Athlete Male Toilet unit 1.00 (1.00) 1,649,494 1,649,494 (1,649,494)
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.7. - PEKERJAAN LOOSE FURNITURE


10 - Athlete Female Toilet unit 1.00 (1.00) 1,649,494 1,649,494 (1,649,494)

Cermin 8mm, uk lebar 1805mm x tinggi 1142mm, termasuk


alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-
1104/1204 )- Lanjutan
Lantai 2
11 - Male Toilet unit 1.00 (1.00) 1,649,494 1,649,494 (1,649,494)
Lantai 3
12 - Male Toilet unit 2.00 (2.00) 1,649,494 3,298,987 (3,298,987)

Cermin 8mm, uk lebar 1797mm x tinggi 1142mm, termasuk


alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-
1104/1204 )
Lantai 4
13 - VIP Male Toilet unit 1.00 (1.00) 1,642,183 1,642,183 (1,642,183)

Cermin 8mm, uk lebar 3390mm x tinggi 1142mm, termasuk


alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-
1104/1204 )
Lantai 4
14 - VIP Female Toilet unit 1.00 (1.00) 3,097,941 3,097,941 (3,097,941)

Tribune Chair type... ex. …. uk panjang ...mm x lebar ...mm x


tinggi ...mm, kursi tribune termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (Reff.gbr : INT-1104/1204 )
15 - Lantai 2 unit 920.00 - 206,554 190,029,423 -

BD1, Backdrop 1, uk panjang 5900mm x tinggi 2250mm,


Plywood tebal 9mm finish HPL ex. Arborite with Alumunium
Edging, Rangka Hollow 4x4 & accessoris ex. Hafelle, Painted
Glass 8mm on Plywood 12mm ,dinding finishing Wallpaper,naad
2mm, termasuk hardware dan alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :

16 - Lantai 2 unit 3.00 - 9,603,429 28,810,288 -


17 - Lantai 3 unit 4.00 - 9,603,429 38,413,717 -

BD2, Backdrop 2, uk panjang 4000mm x tinggi 2150mm,


Plywood tebal 9mm finish HPL ex. Arborite with Alumunium
Edging, Rangka Hollow 4x4 & accessoris ex. Hafelle, Painted
Glass 8mm on Plywood 12mm ,dinding finishing Wallpaper,naad
2mm, termasuk hardware dan alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
18 - Lantai 3 unit 2.00 - 6,221,431 12,442,861 -

BD3, Backdrop 3, uk panjang 3875mm x tinggi 2150mm,


Plywood tebal 9mm finish HPL ex. Arborite with Alumunium
Edging, Rangka Hollow 4x4 & accessoris ex. Hafelle, Painted
Glass 8mm on Plywood 12mm ,dinding finishing Wallpaper,naad
2mm, termasuk hardware dan alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :

19 - Lantai 3 unit 2.00 (1.00) 6,027,011 12,054,022 (6,027,011)

BD4, Backdrop 4, uk panjang 5775mm x tinggi 2150 mm,


Plywood finish HPl ex. Arborite, Alumunium edging rangka
hollow 40x40mm, fitting & accessoris ex. Hafelle, painted glass
8mm, termasuk hardware dan alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
19 - Lantai 3 unit 1.00 - 8,982,190 8,982,190 -

C1, Chair 1 Paso AL.Beleza series ex. Morelli uk panjang


600mm x lebar 490mm x tinggi 630mm, kursi kerja termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
20 - Lantai 1 unit 1.00 2.00 3,784,054 3,784,054 7,568,109

C2, Chair 2 Paso Beleza series ex. Morelli uk panjang 500mm


x lebar 450mm x tinggi 633mm, kursi kerja termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
21 - Lantai 1 unit 19.00 - 2,989,403 56,798,656 -
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.7. - PEKERJAAN LOOSE FURNITURE


22 - Lantai 2 unit 55.00 - 2,989,403 164,417,163 -
23 - Lantai 3 unit 43.00 (17.00) 2,989,403 128,544,327 (50,819,850)

C3, Chair 3 Paso AL.Beleza series ex. Morelli uk panjang


600mm x lebar 490mm x tinggi 630mm, kursi kerja termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
24 - Lantai 1 unit 24.00 - 3,784,054 90,817,305 -
25 - Lantai 3 unit 123.00 20.00 3,784,054 465,438,688 75,681,087

C4, Chair 4 Paso CL.Beleza series ex. Morelli uk panjang


580mm x lebar 450mm x tinggi 630mm, kursi kerja termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
26 - Lantai 1 unit 10.00 2.00 3,784,054 37,840,544 7,568,109

C5, Chair 5 Elizabeth ex. Ikons uk panjang 550mm x lebar


450mm x tinggi 800mm, kursi makan termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
27 - Lantai 1 unit 9.00 1.00 1,400,100 12,600,901 1,400,100
28 - Lantai 4 unit 365.00 - 1,400,100 511,036,543 -

S1, Soffa 1 Seat Poppy ex. Ikons uk panjang 720mm x lebar


730mm x tinggi 633mm, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
29 - Lantai 1 unit 5.00 (1.00) 5,342,194 26,710,972 (5,342,194)
30 - Lantai 3 unit 2.00 - 5,342,194 10,684,389 -

S2, Soffa 1 Seat Maya ex. Vivere uk panjang 720mm x lebar


730mm x tinggi 700mm, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
31 - Lantai 4 unit 2.00 - 5,342,194 10,684,389 -

S3, Soffa 3 Seat Maya ex. Vivere uk panjang 1300mm x lebar


730mm x tinggi 700mm, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
32 - Lantai 1 unit 3.00 - 9,794,023 29,382,069 -
33 - Lantai 3 unit 2.00 - 9,794,023 19,588,046 -

S4, Soffa 2 Seat Masimo Modular ex. Vivere uk panjang


2700mm x lebar 1830mm x tinggi 850mm, termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :

34 - Lantai 4 unit 4.00 - 8,013,292 32,053,166 -

WS1, Work Station Table, uk panjang 1600mm x lebar 750mm


x tinggi ...mm, Plywood finish HPl ex. Arborite, vinyl edging,
metal chromed foot base, cable system, fitting & accessoris ex.
Hafelle, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

35 - Lantai 1 unit 1.00 1.00 3,516,945 3,516,945 3,516,945

WS2, Work Station Table, uk panjang 1400mm x lebar 800mm


x tinggi ...mm, Plywood finish HPl ex. Arborite, vinyl edging,
metal chromed foot base, cable system, fitting & accessoris ex.
Hafelle, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

36 - Lantai 1 unit 19.00 - 5,464,175 103,819,316 -

WS4, Work Station Table, uk panjang 1400mm x lebar 800mm


x tinggi ...mm, Plywood finish HPl ex. Arborite, vinyl edging,
metal chromed foot base, cable system, fitting & accessoris ex.
Hafelle, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

37 - Lantai 3 unit 9.00 - 5,005,128 45,046,150 -


DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.7. - PEKERJAAN LOOSE FURNITURE

T1, Discussion Table, uk diameter 900mm x tinggi 750 mm,


Plywood finish HPl ex. Arborite, vinyl edging, fitting & accessoris
ex. Hafelle, powder coated steel pipe 2", termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :

38 - Lantai 1 unit 2.00 - 2,763,950 5,527,900 -

T2, Coffe Table, uk diameter 600mm x tinggi 600mm, Plywood


finish HPl ex. Arborite, vinyl edging, aluminum extrusion
footbase, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

39 - Lantai 1 unit 10.00 - 1,678,339 16,783,394 -


40 - Lantai 3 unit 3.00 (1.00) 1,678,339 5,035,018 (1,678,339)

T3, Meeting Table, uk panjang 3400mm x lebar 1600mm x


tinggi 750mm, Top Table PB HPl Walnut Woodgran/Solid White,
termasuk accessoris & alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

41 - Lantai 1 unit 2.00 - 4,053,072 8,106,144 -

T4, Coffe Table, uk diameter 600mmx tinggi 600mm, Plywood


6mm & Top Table PB HPl Walnut Woodgran/Solid White, Partisi
Gypsum 12mm fin. cat ,termasuk accessoris & alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
42 - Lantai 1 unit 1.00 - 1,541,605 1,541,605 -

T5, Dinning Table, uk panjang 1200mm x lebar 500mm x tinggi


1000mm, Top Table PB HPl Walnut Woodgran/Solid White,
Partisi Gypsum 12mm fin. cat ,termasuk accessoris & alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
43 - Lantai 1 unit 4.00 - 1,809,986 7,239,945 -

T6, Dinning Table, uk panjang 3300mm x lebar 500mm x tinggi


1000mm, Top Table PB HPl Walnut Woodgran/Solid White,
termasuk accessoris & alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

44 - Lantai 1 unit 1.00 - 2,429,681 2,429,681 -

T7, Meeting Table, uk panjang 1700mm x lebar 700mm x tinggi


700mm, Top Table PB HPl Walnut Woodgran/Solid White with
edging, kaki meja d=30mm, Alumunum Ekstrusi fin Powder
Coating ,termasuk accessoris & alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
45 - Lantai 2 unit 28.00 - 4,053,072 113,486,020 -
46 - Lantai 3 unit 50.00 - 4,053,072 202,653,607 -

T8, Dinning Table, uk diameter 1000mm x tinggi 702mm, Top


Table PB HPl Walnut Woodgran/Solid White with edging, kaki
meja d=30mm, Alumunum Ekstrusi fin Powder
Coating ,termasuk accessoris & alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
47 - Lantai 4 unit 9.00 - 2,802,108 25,218,975 -

T9, Dinning Table, uk diameter 1600mm x tinggi 702mm, Top


Table PB HPl Walnut Woodgran/Solid White with edging, kaki
meja d=30mm, Alumunum Ekstrusi fin Powder
Coating ,termasuk accessoris & alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
48 - Lantai 4 unit 28.00 - 2,802,108 78,459,032 -

T10, Dinning Table, uk diameter 900mm x tinggi 702mm, Top


Table PB HPl Walnut Woodgran/Solid White with edging, kaki
meja d=100mm, Alumunum Ekstrusi fin Powder
Coating ,termasuk accessoris & alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
49 - Lantai 4 unit 28.00 - 2,802,108 78,459,032 -
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.7. - PEKERJAAN LOOSE FURNITURE


T11, Meeting Table, uk panjang 4808mm x lebar 2200mm x
tinggi 710mm, Plywood 9mm lapis veneer fin. Melamic, vinyl
edging, cable tray, kaki meja d=30mm fin. Powder Coating
fitting & accessoris ex. Hafelle, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :
50 - Lantai 3 unit 1.00 - 4,053,072 4,053,072 -

T12, Meeting Table, uk panjang 3925mm x lebar 800mm x


tinggi 70mm, Top Table PB HPl Walnut Woodgran/Solid White
with edging, kaki meja d=30mm fin. Powder Coating fitting &
accessoris ex. Hafelle, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
51 - Lantai 3 unit 4.00 (2.00) 4,053,072 16,212,289 (8,106,144)

BF1, Buffet Table, uk panjang 4000mm x lebar 600mm x tinggi


800mm, Plywood 18mm finish HPl ex. Arborite, vinyl edging,
kaki solid wood fin.melamic, cable system, fitting & accessoris
ex. Hafelle, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

50 - Lantai 4 unit 2.00 - 4,320,690 8,641,381 -

CR1, Credenza 1, uk panjang 1500mm x 500mm x tinggi


1530mm, Plywood 18mm finish HPl ex. Arborite, vinyl edging,
kaki solid wood fin.melamic, cable system, fitting & accessoris
ex. Hafelle, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

50 - Lantai 1 unit 1.00 (1.00) 2,543,902 2,543,902 (2,543,902)

CR2, Credenza 2, uk panjang 1200mm x 450mm x tinggi


800mm, Top Table PB HPl Walnut woodgrain + body PB HPl
Walnut woodgrain ex. Arborite, Alumunium edging, fitting &
accessoris ex. Hafelle, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
51 - Lantai 1 unit 4.00 (2.00) 3,815,853 15,263,412 (7,631,706)

CR3, Credenza 3, uk diameter 1400mm x 200mm x tinggi 1000


mm, Plywood finish HPl ex. Arborite, vinyl edging, fitting &
accessoris ex. Hafelle, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
52 - Lantai 1 unit 2.00 - 3,815,853 7,631,706 -

CR5, Credenza 5, uk Panjang 2700mm x 550mm x tinggi 1530


mm, Plywood finish HPl ex. Arborite, Alumunium Extrusi handle,
bagian dalam plywood 18mm finish melaminto, fitting &
accessoris ex. Hafelle, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
53 - Lantai 3 unit 3.00 - 4,477,267 13,431,802 -

CR6. 1, Credenza 6, uk diameter 3953mm x 400mm x tinggi


1000 mm, Plywood finish HPl ex. Arborite, vinyl edging, fitting &
accessoris ex. Hafelle, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
54 - Lantai 4 unit 1.00 - 10,175,608 10,175,608 -

CR6 . 2, Credenza 6, uk diameter 4000mm x 400mm x tinggi


1000mm, Plywood finish HPl ex. Arborite, vinyl edging, fitting &
accessoris ex. Hafelle, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
55 - Lantai 4 unit 1.00 - 10,175,608 10,175,608 -

DP, uk diameter 4000mm x 400mm x tinggi 1000mm, Plywood


finish HPl ex. Arborite, vinyl edging, fitting & accessoris ex.
Hafelle, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

56 - Lantai 4 unit 1.00 (1.00) 10,175,608 10,175,608 (10,175,608)


DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. II.3.7. - PEKERJAAN LOOSE FURNITURE

DAFTAR NO. II.3.7. - PEKERJAAN LOOSE FURNITURE 2,826,125,248 (26,418,068)


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.1.B - PEKERJAAN STRUKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.1.B.1 - PEKERJAAN TANAH

III.1.B.1.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko longsoran,
volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah


termasuk kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi


dan tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-III.1.A.2 ( 96 ) TANAH


DAFTAR No. III.1.B - PEKERJAAN STRUKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.1.B.1 - PEKERJAAN TANAH


A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan m2 544.50 - 11,130 6,060,052 -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 171.86 - 55,640 9,562,513 -
- Pile Cap m3 62.01 (52.61) 55,640 3,450,069 (2,927,332)
- Tie Beam m3 12.87 7.95 55,640 716,270 442,121

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu berikut
peralatan perlengkapan sesuai spesifikasi dan gambar

- Dibawah plat lantai inc Tie Beam m3 3.90 - 272,340 1,062,398 -


- Pondasi Batu kali m3 15.62 - 272,340 4,255,040 -
- Pile Cap m3 2.74 - 272,340 746,756 -

Urugan tanah untuk mencapai level yang diinginkan, termasuk pemadatan,


dengan memaksimalkan tanah dipakai dari bekas galian serta tanah dari luar
site jika diperlukan sesuai spek dan gambar
- Pile Cap m3 53.12 - 55,648 2,955,903 -

D Pek. Lain - Lain


D.1 Pek. Bobok kepala tiang Pondasi Pancang

Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar

- Mini Pile diameter 25 cm ttk - exclude - -


D.2 Pekerjaan Anti rayap
Anti rayap pada Lantai, termasuk alat - alat bantu, peralatan perlengkapan m2 544.50 - 16,690 9,087,705 -
sesuai spesifikasi dan gambar

D.3 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan
sesuai spesifikasi dan gambar (Kontraktor diminta untuk melampirkan
breakdown harganya) Ls 1.00 - Exclude - -

DAFTAR No. III.1.B.1 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 37,896,707 (2,485,211)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-III.1.A.2 ( 97 ) TANAH


DAFTAR No. III.1.B - PEKERJAAN STRUKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.1.B.2 - PEKERJAAN STRUKTUR BETON

III.1.B.2.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam m3 1.95 - 667,780 1,302,505 -
2) Pile cap m3 1.37 - 667,780 915,526 -

B Beton mutu K-300 :


1) Pile cap m3 8.89 (2.03) 759,480 6,751,018 (1,544,782)
2) Tie beam m3 6.69 (1.07) 759,480 5,078,643 (810,054)

C Beton mutu K-350 :


3) Pelat, pada:
- Lantai dasar m3 63.43 (0.76) 782,410 49,627,953 (597,680)
4) Balok, pada:
- Lantai dasar m3 16.81 (0.00) 782,410 13,150,747 (0)
5) Kolom, pada:
- Lantai dasar m3 7.20 2.70 782,410 5,633,352 2,112,507

PEKERJAAN PEMBESIAN
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- III.1.A.3 ( 98 ) BETON
DAFTAR No. III.1.B - PEKERJAAN STRUKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.1.B.2 - PEKERJAAN STRUKTUR BETON

A Wiremesh 1 lapis M8-150


1) Pelat, pada:
- Lantai 1 m2 528.58 (6.37) 53,220 28,131,028 (338,788)

A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:


1) Pile cap kg 1,017.97 (400.48) 8,859 9,017,691 (3,547,688)
2) Tie beam kg 1,566.28 (142.35) 8,859 13,874,899 (1,261,007)
3) Pelat, pada:
- Lantai dasar kg - 8,859 - -
4) Balok, pada:
- Lantai dasar kg 2,189.48 155.82 8,859 19,395,527 1,380,334
5) Kolom, pada:
- Lantai dasar kg 1,152.36 508.39 8,859 10,208,145 4,503,543

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap m2 50.52 (27.12) 84,790 4,283,591 (2,299,505)
2) Sisi tegak Tie Beam m2 66.87 (10.67) 84,790 5,669,907 (904,362)

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada:
- Lantai dasar (Bawah pelat, bawah balok dan sisi tegak) m2 14.42 0.78 100,570 1,450,622 78,203
2) Kolom, pada:
- Lantai dasar m2 96.00 36.00 100,570 9,654,720 3,620,520
3) Balok (sisi tegak), pada:
- Lantai dasar m2 127.12 (0.00) 104,000 13,220,480 (0)

PEKERJAAN LAIN-LAIN (Provisional)


Water Proofing Integral termasuk sesuai dengan gambar dan
A
spesifikasi, pada :
1) Pelat lantai 1 m3 63.43 - 100,170 6,353,743 -
2) Pile Cap m3 8.89 - 100,170 890,411 -

B Pondasi Batu Kali


1) Pondasi Batu Kali m3 70.31 - 611,910 43,022,168 -
2) Pasangan Aanstamping t=15cm m3 31.25 - 398,440 12,450,453 -
3) Beton tumbuk m3 14.06 - 720,190 10,127,024 -
4) Angkur D13-500 kg 163.20 - 18,920 3,087,805 -

DAFTAR NO. III.1.B.2 - PEKERJAAN STRUKTUR BETON


Dipindahkan ke Penjumlahan Total 273,297,958 391,242

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- III.1.A.3 ( 99 ) BETON


DAFTAR No. III.1.B - PEKERJAAN STRUKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.1.A.4 - PEKERJAAN STRUKTUR BAJA

III.1.A.4.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang diperlukan, seperti :
pengelasan, pembuatan lubang-lubang baut, perapihan dengan gerinda,
penyediaan peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi dan pengiriman ke


lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan


sesuai spesifikasi

I Canopy Atap
1) WF 250 x 125 x 6 x 9 Kg 4,475.52 18,364 82,187,524 -
2) HB 200 x 200 x 8 x 12 Kg 359.28 18,364 6,597,744 -
3) Gording CNP 150 x 50 x 20 x 2,3 Kg 3,960.00 18,364 72,720,621 -
4) Plate 6 mm Kg 235.01 18,364 4,315,678 -
5) Plate 12 mm Kg 378.88 18,364 6,957,707 -
6) Stifner 8 mm Kg 105.98 18,364 1,946,103 -
7) Stifner 12 mm Kg 116.06 18,364 2,131,372 -
8) Trekstang dia 10mm Kg 163.50 17,807 2,911,421 -
9) Bracing dia 16mm Kg 358.58 18,920 6,784,358 -
10) Spanskrup Kg 64.00 18,920 1,210,897 -
10) Angkur M20 L = 660mm bh 72.00 222,591 16,026,583 -
11) Baut M12 bh 576.00 31,163 17,949,773 -
12) Baut M 16 bh 360.00 31,163 11,218,608 -
13) Nonshrink Grout, T = 25 mm, Uk 300 x 300mm Kg 18.00 50,083 901,495 -
14) Cat Dasar (Zincromate) bh 10,234.80 3,339 34,172,691 -
15) Cat Finish bh 10,234.80 3,339 34,172,691 -

DAFTAR NO. III.1.A.4 - PEKERJAAN STRUKTUR BAJA 302,205,268 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- IV.1.4 ( 100 ) SAMEP


DAFTAR No. III.1 - PEKERJAAN STRUKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.1.1 - PEKERJAAN PONDASI TIANG PANCANG

III.1.1.0. Catatan Harga

Catatan Harga (Pricing Notes)


I Harga satuan tiang pancang sudah termasuk :

- harga tukang, alat dan material untuk pemancangan lengkap


termasuk waste

- keperluan galian tanah insidentil termasuk buangan tanah

penggantian tiang pancang yang rusak atau tiang pancang yang


- meleset atau tiang pancang yang gagal test

- topi pondasi dan sepatu pondasi tiang pancang

perbaikan tiang pancang yang menyimpang dari as bagian


- bawah atau atas

- biaya test sudah termasuk pengadaan balok beton pemindahan


balok beton dan hal - hal lain

- pondasi tiang diperhitungkan net tidak ada biaya untuk


tambahan panjang tiang pada pie head

Kedalaman pemancangan dihitung dari muka tanah asli (peil +/-


2
0.000 pada gambar lokasi).

Harga satuan untuk pemancangan dan galian tanah sudah harus


diperhitungkan kemungkinan resiko longsor, pembuangan sisa-sisa
3
akar tanaman, sisa konstruksi bangunan lama yang masih
tertanam, pembersihan lumpur (wash boring), dan lain-lain.

Perbedaan berat yang dikeluarkan oleh pabrik yang satu dengan


4 pabrik yang lainnya untuk diameter yang sama menjadi tanggung
jawab pemborong.

Tabel berat yang dipakai dalam menghitung berat besi dalam


5
Daftar ini, adalah :
Diameter Ø Kg/m (polos)

6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.186
32 mm 6.313

Monitoring lapangan :

harga sudah termasuk observasi lapangan, test lapangan dan


-
test laboratorium

- harga sudah termasuk penyediaan contoh, analisa tanah,


termasuk persiapan test

- harga sudah termasuk penyelesaian laporan yang diperlukan


untuk pekerjaan tersebut diatas

- pengukuran dilokasi tiang sebelum dan sesudah pemancangan

- pembersihan lapangan, jalan sementara, lantai kerja, jalan


masuk yang mungkin diperlukan untuk pelaksanan
pemancangan

VOLUME PROVISIONAL (HARGA SATUAN TETAP)

A PENGADAAN TIANG PANCANG

Pengadaan Tiang Pancang untuk pemancangan, sesuai spesifikasi


dan gambar
Ukuran 250 x 250 mm, 4D13 U-40, stirup Ø5 -75 pada atas dan
bawah, stirup Ø5 -150 pada tengah
kedalaman pemancangan = 11 m' m' exclude - -
Jumlah titik pemancangan = 372 titik

B PEMANCANGAN TIANG PANCANG

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-III.1.A.1 ( 101 ) PONDASI


DAFTAR No. III.1 - PEKERJAAN STRUKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.1.1 - PEKERJAAN PONDASI TIANG PANCANG

Pemancangan Tiang Pancang dengan drop hammer 1500 kg untuk


Test Pile dan Reaction Pile (used pile), sesuai spesifikasi dan
gambar
Ukuran 250 x 250 mm, 4D13 U-40, stirup Ø5 -75 pada atas dan
bawah, stirup Ø5 -150 pada tengah
kedalaman pemancangan = 11 m' m' exclude - -
Jumlah titik pemancangan = 372 titik

C PEK. SAMBUNGAN T. PANCANG


Pekerjaan sambungan tiang pancang beton ukuran 250 x 250
mm lengkap dgn alat - alat bantu berikut dgn pengelasan
terpasang sesuai spesifikasi dan gambar

Sambungan tiang pancang ukuran 250 x 250 mm nos


exclude - -
Note : Kedalaman tiang pancang 11 m'

D PEK. DOLLY

Pekerjaan Dolly tiang pancang ukuran 250 x 250 mm, dengan titik
exclude - -
kedalaman = 2 ~ 3 m'

E PEK. TEST PONDASI TIANG PANCANG (USE PILE)

Test beban pendahuluan reaction pile pada tiang pancang dengan


bh
beban sebesar 44 ton exclude - -

Test beban pancang + PDA (Pile Driving Analysis) test ttk


exclude - -

F PEKERJAAN LAIN - LAIN

Mobilisasi dan demobilisasi blok2 beton dan peralatan loading test


lainnya (2 x 75 ton) ls
exclude - -
Loading test 2 x 75 ton titik
exclude - -

DAFTAR No. III.1.1 - PEKERJAAN PONDASI TIANG PANCANG


Dipindahkan ke Penjumlahan Total - -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-III.1.A.1 ( 102 ) PONDASI


DAFTAR No. III.1 - PEKERJAAN STRUKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.1.A.2 - PEKERJAAN TANAH

III.1.A.2.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko longsoran,
volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah


termasuk kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi dan
tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan sesuai
gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-III.1.A.2 ( 103 ) TANAH


DAFTAR No. III.1 - PEKERJAAN STRUKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.1.A.2 - PEKERJAAN TANAH


A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan m2 240.00 - 11,130 2,671,097 -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 94.73 - 55,640 5,270,777 -
- Pile Cap m3 122.75 - 55,640 6,829,810 -
- Tie Beam m3 93.66 37.88 55,640 5,211,242 2,107,629
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 1 m3 51.60 55,640 2,871,024 -
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 2 m3 51.60 55,640 2,871,024 -
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 3 m3 51.60 55,640 2,871,024 -
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 4 m3 51.60 55,640 2,871,024 -
- Bio Tank Vol 5 m3 Pada Equipment & Equine Clinic m3 28.64 55,640 1,593,619 -
- Bio Tank Vol 5 m3 Pada Pordasi Office m3 28.64 55,640 1,593,619 -

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu berikut
peralatan perlengkapan sesuai spesifikasi dan gambar

- Dibawah plat lantai inc Tie Beam m3 156.87 - 272,340 42,721,976 -


- Pondasi Batu kali m3 8.61 - 272,340 2,344,847 -
- Pile Cap m3 6.32 0.21 272,340 1,721,189 56,647
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 1 m3 0.83 272,340 226,029 -
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 2 m3 0.83 272,340 226,029 -
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 3 m3 0.83 272,340 226,029 -
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 4 m3 0.83 272,340 226,029 -
- Bio Tank Vol 5 m3 Pada Equipment & Equine Clinic m3 0.60 272,340 162,424 -
- Bio Tank Vol 5 m3 Pada Pordasi Office m3 0.60 272,340 162,424 -

Urugan tanah untuk mencapai level yang diinginkan, termasuk pemadatan,


dengan memaksimalkan tanah dipakai dari bekas galian serta tanah dari luar
site jika diperlukan sesuai spek dan gambar
- Pile Cap m3 106.11 - 55,648 5,904,794 -

D Pek. Lain - Lain

D.1 Pekerjaan Anti rayap


Anti rayap pada Lantai dan dinding basement , termasuk alat - alat bantu, m2 240.00 - 16,690 4,005,600 -
peralatan perlengkapan sesuai spesifikasi dan gambar

D.2 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan
sesuai spesifikasi dan gambar (Kontraktor diminta untuk melampirkan
breakdown harganya) Ls 1.00 - Exclude - -

DAFTAR No. III.1.A.2 - PEKERJAAN TANAH


JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-III.1.A.2 ( 104 ) TANAH
DAFTAR No. III.1 - PEKERJAAN STRUKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.1.A.2 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 92,581,628 2,164,276

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-III.1.A.2 ( 105 ) TANAH


DAFTAR No. III.1 - PEKERJAAN STRUKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.1.A.3 - PEKERJAAN STRUKTUR BETON

III.1.A.3.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam m3 32.39 - 667,780 21,629,394 -
2) Pile cap m3 3.16 0.10 667,780 2,110,185 69,449
3) Bio Tank Vol 15 m3 Pada Horse Stable Zone 1 m3 1.66 667,780 1,108,448 -
4) Bio Tank Vol 15 m3 Pada Horse Stable Zone 2 m3 1.66 667,780 1,108,448 -
5) Bio Tank Vol 15 m3 Pada Horse Stable Zone 3 m3 1.66 667,780 1,108,448 -
6) Bio Tank Vol 15 m3 Pada Horse Stable Zone 4 m3 1.66 667,780 1,108,448 -
7) Bio Tank Vol 5 m3 Pada Equipment & Equine Clinic m3 1.19 667,780 796,528 -
8) Bio Tank Vol 5 m3 Pada Pordasi Office m3 1.19 667,780 796,528 -

B Beton mutu K-300 :


1) Pile cap m3 27.44 (11.12) 759,480 20,840,131 (8,445,418)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- III.1.A.3 ( 106 ) BETON


DAFTAR No. III.1 - PEKERJAAN STRUKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.1.A.3 - PEKERJAAN STRUKTUR BETON

2) Tie beam m3 60.87 18.05 759,480 46,229,548 13,711,538


3) Pelat, pada:
- Lantai 1 m3 147.62 (56.49) 759,480 112,114,438 (42,900,124)
4) Bio Tank Pada Horse Stable Zone 1 m3 16.54 759,480 12,558,944 -
5) Bio Tank Pada Horse Stable Zone 2 m3 16.54 759,480 12,558,944 -
6) Bio Tank Pada Horse Stable Zone 3 m3 16.54 759,480 12,558,944 -
7) Bio Tank Pada Horse Stable Zone 4 m3 16.54 759,480 12,558,944 -
8) Bio Tank Vol 5 m3 Pada Equipment & Equine Clinic m3 11.16 759,480 8,479,442 -
9) Bio Tank Vol 5 m3 Pada Pordasi Office m3 11.16 759,480 8,479,442 -

C Beton mutu K-350 :


10) Pelat, pada:
- Lantai 2 m3 78.88 12.25 782,410 61,716,501 9,587,511
- Ramp Baru m3 59.27 50.63 782,410 46,373,441 39,616,298
- Perbaikan Ramp Existing m3 12.00 782,410 9,388,920 -

11) Balok, pada:


- Lantai 2 m3 55.64 (0.82) 782,410 43,533,292 (638,720)
- Ramp m3 30.73 (3.80) 782,410 24,043,459 (2,969,559)

12) Kolom, pada:


- Lantai 1 m3 29.89 11.42 782,410 23,386,235 8,935,122
- Ramp m3 4.58 5.32 782,410 3,583,438 4,160,704

PEKERJAAN PEMBESIAN
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pile cap kg 4,140.21 (1,735.56) 8,859 36,676,050 (15,374,494)
2) Tie beam kg 9,727.33 (218.44) 8,859 86,169,553 (1,935,064)
3) Bio Tank Pada Horse Stable Zone 1 kg 2,480.44 8,859 21,972,942 -
4) Bio Tank Pada Horse Stable Zone 2 kg 2,480.44 8,859 21,972,942 -
5) Bio Tank Pada Horse Stable Zone 3 kg 2,480.44 8,859 21,972,942 -
6) Bio Tank Pada Horse Stable Zone 4 kg 2,480.44 8,859 21,972,942 -
7) Bio Tank Vol 5 m3 Pada Equipment & Equine Clinic kg 1,674.72 8,859 14,835,507 -
8) Bio Tank Vol 5 m3 Pada Pordasi Office kg 1,674.72 8,859 14,835,507 -

10) Pelat, pada:


- Lantai 1 kg 12,755.27 - 8,859 112,992,559 -
- Lantai 2 kg 7,925.02 181.72 8,859 70,203,790 1,609,792
- Ramp Baru kg 5,188.30 4,588.10 8,859 45,960,556 40,643,703
- Perbaikan Ramp Existing kg 1,974.00 8,859 17,486,679 -

Balok, pada:
11) - Lantai 2 kg 9,688.70 1,928.78 8,859 85,827,349 17,086,095
- Ramp kg 5,247.32 63.61 8,859 46,483,384 563,501

Kolom, pada:
12) - Lantai 1 kg 4,853.11 2,034.99 8,859 42,991,275 18,026,987
- Ramp kg 817.32 834.52 8,859 7,240,229 7,392,621

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap m2 225.12 (143.52) 84,790 19,087,925 (12,169,061)
2) Sisi tegak Tie Beam m2 405.77 120.39 84,790 34,405,238 10,207,783
3) Bio Tank Pada Horse Stable Zone 1 m2 7.34 84,790 622,359 -
4) Bio Tank Pada Horse Stable Zone 2 m2 7.34 84,790 622,359 -
5) Bio Tank Pada Horse Stable Zone 3 m2 7.34 84,790 622,359 -
6) Bio Tank Pada Horse Stable Zone 4 m2 7.34 84,790 622,359 -
7) Bio Tank Vol 5 m3 Pada Equipment & Equine Clinic m2 6.22 84,790 527,394 -
8) Bio Tank Vol 5 m3 Pada Pordasi Office m2 6.22 84,790 527,394 -

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada:
- Lantai 1 (Bawah pelat, bawah balok dan sisi tegak) m2 58.87 (15.95) 100,570 5,920,556 (1,604,498)
- Lantai 2 (Bawah pelat, bawah balok dan sisi tegak) m2 646.04 4.43 100,570 64,972,243 446,004
- Ramp Baru m2 422.48 360.48 100,570 42,488,814 36,253,393
- Perbaikan Ramp Existing m2 100.00 100,570.00 10,057,000 -

2) Kolom, pada:
- Lantai 1 m2 398.54 152.26 129,920 51,778,317 19,781,619
- Ramp m2 61.06 70.91 129,920 7,932,915 9,212,722

3) Balok (sisi tegak), pada:


- Lantai 2 m2 370.91 (5.42) 104,000 38,574,640 (563,576)
- Ramp m2 204.83 51.69 104,000 21,302,320 5,375,760

4) Bio Tank Pada Horse Stable Zone 1 m2 60.62 100,570 6,096,553 -


5) Bio Tank Pada Horse Stable Zone 2 m2 60.62 100,570 6,096,553 -
6) Bio Tank Pada Horse Stable Zone 3 m2 60.62 100,570 6,096,553 -
7) Bio Tank Pada Horse Stable Zone 4 m2 60.62 100,570 6,096,553 -
7) Bio Tank Vol 5 m3 Pada Equipment & Equine Clinic m2 69.80 100,570 7,020,188 -
8) Bio Tank Vol 5 m3 Pada Pordasi Office m2 69.80 100,570 7,020,188 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- III.1.A.3 ( 107 ) BETON


DAFTAR No. III.1 - PEKERJAAN STRUKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.1.A.3 - PEKERJAAN STRUKTUR BETON

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- III.1.A.3 ( 108 ) BETON


DAFTAR No. III.1 - PEKERJAAN STRUKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.1.A.3 - PEKERJAAN STRUKTUR BETON

PEKERJAAN LAIN-LAIN (Provisional)

Waterproofing membrane termasuk screed tebal rata-rata 50


A mm + wire mesh M6 termasuk peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar: (Provisional)

1) lantai atap
- Atap m2 646.04 - 127,690 82,492,848 -

Water Proofing Integral termasuk sesuai dengan gambar dan


B
spesifikasi, pada :
1) Pelat lantai 1 m3 147.62 - 100,170 14,787,095 -
2) Pile Cap m3 27.44 - 100,170 2,748,665 -

Perkuatan carbon fiber sesuai dengan gambar dan spesifikasi,


A
pada :
1) Balok
- Kolom KP.1 m2 97.40 779,070 75,881,420 -
- Kolom KP.2 m2 292.28 779,070.02 227,702,690 -

1) Balok
- Balok BP.1 m2 43.20 779,070.02 33,655,825 -
- Balok BP.2 m2 129.60 779,070.02 100,967,474 -
- Balok BP.3 & BP.4 m2 200.64 779,070.02 156,312,608 -

DAFTAR NO. III.1.A.3 - PEKERJAAN STRUKTUR BETON


Dipindahkan ke Penjumlahan Total 2,190,804,100 156,080,089

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- III.1.A.3 ( 109 ) BETON


DAFTAR No. III.1 - PEKERJAAN STRUKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.1.A.4 - PEKERJAAN STRUKTUR BAJA

III.1.A.4.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-lubang
baut, perapihan dengan gerinda, penyediaan peralatan bantu
untuk pemasangan dan mendirikan atap+rangka serta sisa
terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi dan


pengiriman ke lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi

I Pekerjaan Baja Atap Monitor


2) Pipa Baja Hitam 4", tebal 4,5mm Kg 20,041.50 23,372 468,411,953 -
6) Plate T=8mm Kg 1,162.87 17,807 20,707,506 -
7) Cat Dasar Baja Existing & Baja Atap Monitor Kg 74,528.43 3,339 248,840,839 -
8) Cat Finish Baja Existing & Baja Atap Monitor Kg 74,528.43 3,339 248,840,839 -

DAFTAR NO. III.1.A.4 - PEKERJAAN STRUKTUR BAJA 1,257,063,375 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- IV.1.4 ( 110 ) SAMEP


DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.2.A. - PEKERJAAN DINDING

III.2.A.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah termasuk


adukan biasa atau drymix, kolom praktis, ringbalk, angkur, sparing dan
semua pekerjaan bantu yang berhubungan dengan pekerjaan dinding
tersebut.

II
Harga satuan plesteran biasa atau drymix sudah termasuk acian,
skonengan, tali air , ketrikan atau bobokan beton maupun bata , kawat
ayam (jika diperlukan) dan semua pekerjaan bantu yang berhubungan
dengan plesteran. Volume plesteran dan acian sudah ditambahkan 10cm
di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit, marmer,


keramik, porselin) sudah termasuk adukan, cor beton,perekat (calbond),
angkur, kawat pengikat alumunium fixing pada dinding dengan ketinggian
lebih dari 2m, pemotongan, pinggulan, adu manis, naad, dan alat bantu
lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk dinding kedap


air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian cat dasar
(meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan


sesuai spesifikasi.

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. Optima/ LeitchBrick,
termasuk dinding penebalan,urinoir, perekat, adukan kering kolom dan
balok praktis
- Lantai 1 sesuai spesifikasi dan gambar : m2 2,589.74 284.87 103,480 267,986,258 29,478,488
- Lantai 2 m2 2,019.40 222.13 103,480 208,967,882 22,986,467

II PEK. PELAPIS DINDING

A Plesteran dan Acian, Plesteran halus berikut acian halus, termasuk


peralatan dan perlengkapan sesuai spesifikasi dan gambar pada :

- Lantai 1 m2 5,019.29 557.45 61,540 308,887,236 34,305,673


- Lantai 2 m2 4,988.84 615.00 61,540 307,013,293 37,847,324
- Area Exterior m2 751.24 706.17 61,540 46,231,482 43,457,593

Keramik Roman 300x300 setara ex Roman/Mulia tipe standar, sesuai


B
spesifikasi dan gambar ;
- Lantai 1
Female Shower Room m2 - by Interior
Male Shower Room m2 - by Interior
Male Toilet m2 74.05 (74.05) 161,560 11,963,922 (11,963,922)
Female Toilet m2 62.37 (62.37) 161,560 10,075,770 (10,075,770)
Difable Toilet m2 29.33 (29.33) 161,560 4,738,393 (4,738,393)
- Lantai 2
Female Shower Room m2 - by Interior
Male Shower Room m2 - by Interior
Male Toilet m2 74.05 (74.05) 161,560 11,963,922 (11,963,922)
Female Toilet m2 62.37 (62.37) 161,560 10,075,770 (10,075,770)
Difable Toilet m2 29.33 (29.33) 161,560 4,738,393 (4,738,393)

C Pengecatan dengan fin. cat Interior setara ex.Jotun tipe standar,


termasuk peralatan dan perlengkapan sesuai spesifikasi dan gambar
pada :

- Lantai 1
Steward Office m2 - by Interior
Dining & Lounge m2 - by Interior
Preparation Pantry m2 - by Interior
Female Shower Room
-Locker Area m2 - by Interior
-Changing Room m2 - by Interior
C Pengecatan dengan fin. cat Interior setara ex.Jotun tipe standar,
termasuk peralatan dan perlengkapan sesuai spesifikasi dan gambar
pada :- Lanjutan

- Lantai 1
Male Shower Room
-Locker Area m2 - by Interior
-Changing Room m2 - by Interior
Security Office m2 48.95 (48.95) 18,920 926,157 (926,157)
Security Bedroom m2 39.50 (39.50) 18,920 747,294 (747,294)
R. Pengelola m2 80.57 (29.39) 18,920 1,524,470 (556,049)
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.2.A. - PEKERJAAN DINDING


R. Drawing m2 290.72 (197.77) 18,920 5,500,379 (3,741,765)
Stairs m2 53.32 (25.17) 18,920 1,008,809 (476,211)

D Pengecatan dengan fin. cat Acrylic Emultion ex setara jotun tipe standar
+ Rubber, termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :

- Lantai 1
Horse Box Type A m2 723.67 (723.67) 18,360 13,286,616 (13,286,616)
Horse Box Type B m2 723.67 (723.67) 18,360 13,286,616 (13,286,616)
Horse Box Type C m2 681.21 (681.21) 18,360 12,506,977 (12,506,977)
Tack Room m2 439.98 (439.98) 18,360 8,078,105 (8,078,105)
Horse Bath/ Cleaning m2 443.41 (443.41) 18,360 8,140,970 (8,140,970)
Female Shower Room m2 27.63 (27.63) 18,360 507,362 (507,362)
Male Shower Room m2 27.63 (27.63) 18,360 507,362 (507,362)
Eksterior Horse Box m2 393.24 (393.24) 18,360 7,219,886 (7,219,886)
- Lantai 2
Horse Box Type A m2 1,709.26 (1,709.26) 18,360 31,382,014 (31,382,014)
Horse Box Type B m2 256.18 (256.18) 18,360 4,703,465 (4,703,465)
Tack Room m2 354.04 (354.04) 18,360 6,500,174 (6,500,174)
Horse Bath/ Cleaning m2 362.06 (362.06) 18,360 6,647,348 (6,647,348)
Stairs m2 53.09 (53.09) 18,360 974,687 (974,687)
Eksterior Stairs m2 56.17 (56.17) 18,360 1,031,281 (1,031,281)
Coridor Horse Box m2 703.86 (703.86) 18,360 12,922,943 (12,922,943)
Eksterior Horse Box m2 1,494.18 (1,494.18) 18,360 27,433,214 (27,433,214)

E Skim coat pada permukaan kolom beton, termasuk peralatan dan


perlengkapan sesuai spesifikasi dan gambar pada :
- Lantai 1 m2 1,662.39 (2.32) 33,950 56,438,141 (78,594)
- Lantai 2 m2 1,071.45 0.35 33,950 36,375,728 11,882

DAFTAR NO. III.2.A. - PEKERJAAN DINDING 1,450,292,318 (47,123,833)


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.2.A.2 - PEKERJAAN PINTU dan JENDELA

III.2.A.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis sekeliling
pintu & jendela, dan peralatan bantu yang diperlukan dan bahan yang
terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling pintu &
jendela , dan peralatan bantu yang diperlukan dan bahan yang terbuang
(waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis sekeliling
pintu & jendela, dan peralatan bantu yang diperlukan dan bahan yang
terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik


pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU KAYU
Pintu Kayu P1 Terdiri dari 1 pintu dan 2 daun pintu dengan kusen/frame
alumunium ukuran 2628x2400 mm, Plywood, kaca 5 mmTHK. lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :
Main Entrance
- Lantai 1 unit 3.00 (1.00) 7,545,850 22,637,549 (7,545,850)
- Lantai 2 unit 8.00 2.00 7,545,850 60,366,797 15,091,699

Pintu Kayu P2 Terdiri dari 1 pintu dan 2 dengan kusen/frame alumunium


ukuran 930x2400 mm , Plywood, kaca 5 mmTHK + Sunblast. lengkap
terpasang
- Lantai 1 termasuk, hardware, accesories dan perlengkapan bantu unit 6.00 - 3,238,705 19,432,232 -

Pintu Kayu P3 Terdiri dari 1 pintu dan 2 daun pintu dengan kusen/frame
alumunium ukuran 1807x2400 mm, Plywood, kaca 5 mmTHK +
Sunblast. lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 2.00 (2.00) 6,533,059 13,066,117 (13,066,117)

Pintu Kayu P4 Terdiri dari 1 pintu dan 2 daun pintu dengan kusen/frame
alumunium ukuran 1700x2400 mm , Plywood, kaca 5 mmTHK +
Sunblast. lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 1.00 (1.00) 3,584,418 3,584,418 (3,584,418)

Pintu Kayu P5 Terdiri 1 daun pintu dengan kusen alumunium ukuran 40


mm Clear anodized, kaca clear 5 mm, daun jendela alumunium, daun
pintu double teakwood 3 mm,plywood 4 mm, lapis formica. lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :
Toilet
- Lantai 1 unit 3.00 - 2,803,956 8,411,869 -
- Lantai 2 unit 3.00 (1.00) 2,803,956 8,411,869 (2,803,956)

A PINTU KAYU -Lanjutan

Pintu Kayu PJ1 ukuran 3350x2400 mm lengkap terpasang termasuk,


hardware, accesories dan perlengkapan bantu lainnya sesuai spesifikasi
dan gambar pada :
- Lantai 1 unit 64.00 37.00 6,624,043 423,938,741 245,089,585
- Lantai 2 unit 68.00 28.00 6,624,043 450,434,912 185,473,199

Pintu Kayu PJ2 ukuran 3350x2400 mm lengkap terpasang termasuk,


hardware, accesories dan perlengkapan bantu lainnya sesuai spesifikasi
dan gambar pada :
- Lantai 1 unit 8.00 4.00 6,624,043 52,992,343 26,496,171
- Lantai 2 unit 8.00 4.00 6,624,043 52,992,343 26,496,171

Pintu Kayu PJ3 ukuran 2368x2400 mm lengkap terpasang termasuk,


hardware, accesories dan perlengkapan bantu lainnya sesuai spesifikasi
dan gambar pada :
- Lantai 1 unit 2.00 (2.00) 5,154,060 10,308,120 (10,308,120)

B JENDELA

Jendela J1 ukuran 1500x920 mm Kusen Alumunium 40 mm Clear


Anodized, besi bulat 1.5 lengkap terpasang termasuk, hardware,
accesories dan perlengkapan bantu lainnya sesuai spesifikasi dan
gambar pada :
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)
Jendela J1 ukuran 1500x920 mm Kusen Alumunium 40 mm Clear
DAFTAR
Anodized,NO. III.2.A.2
besi - PEKERJAAN
bulat 1.5 PINTU dan
lengkap terpasang JENDELA
termasuk, hardware,
accesories dan perlengkapan bantu lainnya sesuai spesifikasi dan
gambar pada :
- Lantai 1 unit 56.00 37.00 1,309,266 73,318,903 48,442,846
- Lantai 2 unit 48.00 36.00 1,309,266 62,844,774 47,133,580

Jendela J2 Kusen Alumunium ukuran 2000x2400 mm, frame beton,


kaca 5 mmThk lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 2.00 (2.00) 4,553,969 9,107,938 (9,107,938)

Jendela J3 Kusen Alumunium ukuran 4700x2400 , frame beton, kaca 5


mmTHK lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 3.00 - 10,701,827 32,105,482 -

Jendela J4 Kusen Alumunium ukuran 2843x2400 mm , frame beton,


kaca 5 mmTHK lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 3.00 (3.00) 6,473,467 19,420,401 (19,420,401)

Jendela J5 Kusen Alumunium ukuran 1443x2400 mm , frame beton,


kaca 5 mmTHK lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 1.00 (1.00) 3,285,689 3,285,689 (3,285,689)

Jendela J6 Kusen Alumunium ukuran 730x2800 mm , kaca 5 mmTHK


lengkap terpasang termasuk, hardware, accesories dan perlengkapan
bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 34.00 (28.00) 1,939,232 65,933,883 (54,298,492)

Jendela J7 Kusen Alumunium louvre ukuran 4150x1264 mm lengkap


terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 1.00 (1.00) 4,976,729 4,976,729 (4,976,729)
- Lantai 2 unit 8.00 4.00 4,976,729 39,813,834 19,906,917

DAFTAR NO. III.2.A.2 - PEKERJAAN PINTU dan JENDELA 1,437,384,943 485,732,459


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.2.A.3 - PEKERJAAN LANTAI

III.2.A.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)

II Harga satuan sudah termasuk levelling (sloping) mortarmix


sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

CERAMIC TILE

Ceramic Tile uk. 300 x 300 mm setara ex Roman berikut


adukan mortar, additiv, grouting nat termasuk alat-alat bantu
lainnya dengan peralatan perlengkapan sesuai spesifikasi
dan gambar pada :

Lantai 1
- Toilet Pria m2 18.41 (18.41) 173,260 3,188,962 (3,188,962)
- Toilet Wanita m2 16.91 (16.91) 173,260 2,929,938 (2,929,938)
- Toilet Difable m2 3.59 (3.59) 173,260 621,791 (621,791)
- Selasar samping as 20-23/A-L (Provisional) m2 180.23 - 173,260 31,226,650 -
Lantai 2
- Toilet Pria m2 18.41 (18.41) 173,260 3,188,962 (3,188,962)
- Toilet Wanita m2 16.91 (16.91) 173,260 2,929,938 (2,929,938)
- Toilet Difable m2 3.59 (3.59) 173,260 621,791 (621,791)

PAVING BLOCK

Paving Block Tebal 80 mm setara Ex. Conblock ,termasuk


alat-alat bantu lainnya dengan peralatan terpasang sesuai
spesifikasi dan gambar

Lantai 1
- Koridor m2 3,233.89 499.91 248,600 803,945,054 124,277,626
- Jalur kuda eksternal m2 548.32 720.38 248,600 136,312,352 179,086,468
- Horse box m2 1,027.84 512.96 248,600 255,521,024 127,521,856
- Tack room m2 123.60 68.40 248,600 30,726,960 17,004,240
- Horse bath m2 129.12 66.48 248,600 32,099,232 16,526,928

FLOOR HARDENER

Floor Hardener 3kg/m2,setara ex Fosroc / Sika/MU termasuk


alat alat bantu lainnya dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Ramp Horse Box m2 172.80 178.32 33,390 5,769,792 5,954,105
- Ramp Horse Bath m2 57.68 31.42 33,390 1,925,935 1,049,114
- Ramp Koridor m2 189.19 751.01 33,390 6,317,196 25,076,082

Lantai 2
- Koridor m2 1,522.01 (601.01) 33,390 50,819,914 (20,067,724)
- Jalur kuda eksternal m2 612.44 1,211.16 33,390 20,449,372 40,440,632
- Horse box m2 998.40 532.80 33,390 33,336,576 17,790,192
- Tack room m2 124.96 65.84 33,390 4,172,414 2,198,398
- Horse bath m2 128.48 67.12 33,390 4,289,947 2,241,137

PLINT CERAMIC TILE


Ceramic Tile uk. 100 x 300 mm setara ex Roman berikut
adukan mortar, additiv, grouting nat termasuk alat-alat bantu
lainnya dengan peralatan perlengkapan sesuai spesifikasi
dan gambar pada :

Lantai 1
- Selasar samping as 20-23/A-L (Provisional) m' 56.20 - 2,843 159,761 -

WATERPROOFING

Continuous Waterproofing Coating, termasuk pada dinding


setinggi 300mm terpasang sesuai dengan spesifikasi dan
gambar pada : (Provisional)
Lantai 1
- Toilet Pria m2 18.96 - 44,520 844,002 -
- Toilet Wanita m2 17.42 - 44,520 775,448 -
- Toilet Difable m2 3.70 - 44,520 164,565 -
- Selasar samping as 20-23/A-L (Provisional) m2 185.64 - 44,520 8,264,555 -
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.2.A.3 - PEKERJAAN LANTAI

PENAMBAHAN SCREED BETON T=5CM (Provisional)

Beton tanpa tulangan termasuk alat bantu lainnya dengan


perlengkapan terpasang sesuai spesifikasi dan gambar
pada :
Lantai 1
- Koridor m2 3,233.89 - 97,110 314,043,058 -
- Jalur kuda eksternal m2 548.32 - 97,110 53,247,355 -
- Horse box m2 1,027.84 - 97,110 99,813,542 -
- Tack room m2 123.60 - 97,110 12,002,796 -
- Horse bath m2 129.12 - 97,110 12,538,843 -
- Ramp Horse Box m2 172.80 - 97,110 16,780,608 -
- Ramp Horse Bath m2 57.68 - 97,110 5,601,305 -
- Ramp Koridor m2 189.19 - 97,110 18,372,654 -
Lantai 2
- Koridor m2 1,522.01 - 97,110 147,802,391 -
- Jalur kuda eksternal m2 612.44 - 97,110 59,474,048 -
- Horse box m2 998.40 - 97,110 96,954,624 -
- Tack room m2 124.96 - 97,110 12,134,866 -
- Horse bath m2 128.48 - 97,110 12,476,693 -

PENGUPASAN LAHAN (Provisional)

Lantai 1
- Koridor m2 3,233.89 - 22,259 71,983,621 -
- Jalur kuda eksternal m2 548.32 - 22,259 12,205,133 -
- Horse box m2 1,027.84 - 22,259 22,878,838 -
- Tack room m2 123.60 - 22,259 2,751,230 -
- Horse bath m2 129.12 - 22,259 2,874,101 -
- Ramp Horse Box m2 172.80 - 22,259 3,846,380 -
- Ramp Horse Bath m2 57.68 - 22,259 1,283,907 -
- Ramp Koridor m2 189.19 - 22,259 4,211,302 -

Lantai 2
- Koridor m2 1,522.01 - 22,259 33,878,639 -
- Jalur kuda eksternal m2 612.44 - 22,259 13,632,390 -
- Horse box m2 998.40 - 22,259 22,223,529 -
- Tack room m2 124.96 - 22,259 2,781,503 -
- Horse bath m2 128.48 - 22,259 2,859,855 -

DAFTAR NO. III.2.A.3 - PEKERJAAN LANTAI 2,499,255,342 525,617,670


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.2.A.4 - PEKERJAAN PLAFOND

III.2.A.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A Plafond Gypsum Water resistant tebal 12 mm rangka metal furing hollow


setara ex. Jayaboard, finishing cat Acrylic Emulsion paint setara ex.ICI,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :

Lantai 1
- Toilet Pria m2 18.41 0.29 144,680 2,662,929.09 42,586.91
- Toilet Wanita m2 16.91 (2.01) 144,680 2,446,631.93 (290,899.93)
- Toilet Difable m2 3.59 0.21 144,680 519,223.84 30,560.16
Lantai 2
- Toilet Pria m2 18.41 (11.71) 144,680 2,662,929.09 (1,693,573.09)
- Toilet Wanita m2 16.91 (12.61) 144,680 2,446,631.93 (1,824,507.93)
- Toilet Difable m2 3.59 (3.59) 144,680 519,223.84 (519,223.84)

B Beton exposed (rangka atap), termasuk alat bantu lainnya dengan


peralatan perlengkapan terpasang sesuai dengan spesifikasi dan gambar
pada :
- Lantai 1
- Koridor m2 3,233.89 499.91 52,310 169,164,785.90 26,150,292.10
- Jalur Kuda Eksternal m2 548.32 720.38 52,310 28,682,619.20 37,683,077.80
- Horse Box m2 1,027.84 512.96 52,310 53,766,310.40 26,832,937.60
- Tack Room m2 123.60 68.40 52,310 6,465,516.00 3,578,004.00
- Horse Bath m2 129.12 66.48 52,310 6,754,267.20 3,477,568.80
- Selasar samping as 20-23/A-L (Provisional) m2 180.23 - 52,310 9,427,831.30 -

- Lantai 2
- Koridor m2 1,522.01 (0.01) 52,310 79,616,343.10 (523.10)
- Jalur Kuda Eksternal m2 612.44 (612.44) 52,310 32,036,736.40 (32,036,736.40)
- Horse Box m2 998.40 532.80 52,310 52,226,304.00 27,870,768.00
- Tack Room m2 124.96 65.84 52,310 6,536,657.60 3,444,090.40
- Horse Bath m2 128.48 67.12 52,310 6,720,788.80 3,511,047.20

DAFTAR NO. III.2.A.4 - PEKERJAAN PLAFOND 462,655,730 96,255,469


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.2.A.5. - PEKERJAAN SANITARY

III.2.A.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan kelengkapan


material bantu (adukan, plesteran, acian, nad, sealan, grouting, bahan
bantu pengubung (doble niple) yang berhubungan dengan instalasi ME
dan lainnya berikut pemasangan dan perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik


pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

Lantai 1
Toilet Male

- Wastafel Set setara ex TOTO LW549J bh 3.00 - 3,644,970 10,934,910 -


- Closet Duduk Set setara ex. TOTO bh 3.00 - 3,385,100 10,155,300 -
- CW860NJ/SW861JP
Floor Drain setara ex. TOTO TX 1 BN bh 4.00 - 385,700 1,542,800 -
- Tissue Holder setara ex. TX 720 ACRB bh 3.00 - 267,820 803,460 -

- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -


- Faucet setara ex. TOTO TX 108LDN bh 3.00 - 1,301,490 3,904,470 -
- Urinoir setara ex. TOTO UW 930 JM bh 3.00 - 3,483,960 10,451,880 -
- Urinoir Divider setara ex. TOTO AW 115 J bh 2.00 - 3,483,960 6,967,920 -

Toilet Female

- Wastafel Set setara ex TOTO LW549J bh 3.00 - 3,644,970 10,934,910 -


- Closet Duduk Set setara ex. TOTO bh 3.00 - 3,385,100 10,155,300 -
- CW860NJ/SW861JP
Floor Drain setara ex. TOTO TX 1 BN bh 4.00 - 385,700 1,542,800 -
- Tissue Holder setara ex. TX 720 ACRB bh 3.00 - 267,820 803,460 -

- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 - 581,660 1,744,980 -


- Faucet setara ex. TOTO TX 108LDN bh 3.00 - 1,301,490 3,904,470 -

Toilet Difable

- Wastafel Set setara ex TOTO LW549J bh 1.00 - 3,644,970 3,644,970 -


- Closet Duduk Set setara ex. TOTO bh 1.00 - 3,385,100 3,385,100 -
- CW860NJ/SW861JP
Floor Drain setara ex. TOTO TX 1 BN bh 2.00 - 385,700 771,400 -
- Tissue Holder setara ex. TX 720 ACRB bh 1.00 - 267,820 267,820 -

- Jetwasher setara ex. TOTO TB 19 CSN bh 1.00 - 581,660 581,660 -


- Faucet setara ex. TOTO TX 108LDN bh 1.00 - 1,301,490 1,301,490 -
- Grab bar (provisional) bh 1.00 - 555,220 555,220 -

Lantai 2
Toilet Male

- Wastafel Set setara ex TOTO LW549J bh 3.00 (3.00) 3,644,970 10,934,910 (10,934,910)
- Closet Duduk Set setara ex. TOTO bh 3.00 (1.00) 3,385,100 10,155,300 (3,385,100)
- CW860NJ/SW861JP
Floor Drain setara ex. TOTO TX 1 BN bh 4.00 (1.00) 385,700 1,542,800 (385,700)
- Tissue Holder setara ex. TX 720 ACRB bh 3.00 (1.00) 267,820 803,460 (267,820)

- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 (1.00) 581,660 1,744,980 (581,660)
- Faucet setara ex. TOTO TX 108LDN bh 3.00 (3.00) 1,301,490 3,904,470 (3,904,470)
- Urinoir setara ex. TOTO UW 930 JM bh 3.00 (1.00) 3,483,960 10,451,880 (3,483,960)
- Urinoir Divider setara ex. TOTO AW 115 J bh 2.00 - 3,483,960 6,967,920 -

Toilet Female

- Wastafel Set setara ex TOTO LW549J bh 3.00 (2.00) 3,644,970 10,934,910 (7,289,940)
- Closet Duduk Set setara ex. TOTO bh 3.00 (2.00) 3,385,100 10,155,300 (6,770,200)
- CW860NJ/SW861JP
Floor Drain setara ex. TOTO TX 1 BN bh 4.00 (2.00) 385,700 1,542,800 (771,400)
- Tissue Holder setara ex. TX 720 ACRB bh 3.00 (2.00) 267,820 803,460 (535,640)

- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 (2.00) 581,660 1,744,980 (1,163,320)
- Faucet setara ex. TOTO TX 108LDN bh 3.00 (2.00) 1,301,490 3,904,470 (2,602,980)

Lantai 2 (Lanjutan)
Toilet Difable

- Wastafel Set setara ex TOTO LW549J bh 1.00 (1.00) 3,644,970 3,644,970 (3,644,970)
- Closet Duduk Set setara ex. TOTO bh 1.00 (1.00) 3,385,100 3,385,100 (3,385,100)
- CW860NJ/SW861JP
Floor Drain setara ex. TOTO TX 1 BN bh 2.00 (2.00) 385,700 771,400 (771,400)
- Tissue Holder setara ex. TX 720 ACRB bh 1.00 (1.00) 267,820 267,820 (267,820)

- Jetwasher setara ex. TOTO TB 19 CSN bh 1.00 (1.00) 581,660 581,660 (581,660)
- Faucet setara ex. TOTO TX 108LDN bh 1.00 (1.00) 1,301,490 1,301,490 (1,301,490)
- Grab bar (provisional) bh 1.00 - 555,220 555,220 -
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.2.A.5. - PEKERJAAN SANITARY

DAFTAR NO. III.2.A.5. - PEKERJAAN SANITARY 172,198,600 (52,029,540)


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.2.A.6. - PEKERJAAN LAIN-LAIN

III.2.A.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai


gambar dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Railing
Railing Tangga steel Pipe dia. 50 W/OP dan dia. 38 W/OP with paint
finish welded & grind smooth tinggi 1100 mm, termasuk Hand Railing dan
alat-alat bantu lainnya dengan peralatan perlengkapan terpasang Sesuai
spesifikasi dan gambar pada :
Lantai 1
- Tangga security (provisional) m' 10.35 - 723,422 7,484,460 -

2 Cermin
Kaca cermin tebal 6mm, lengkap dengan bevel bagian pinggir, berikut
lapisan belakang dari multiplek tebal 12 mm, berikut sealant, bracket, dll
termasuk alat-alat bantu lainnya dengan peralatan dan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :
Lantai 1
- Female toilet (uk. 1850x1000 mm) unit 1.00 - 2,294,894 2,294,894 -
- Male toilet (uk. 2650x1000 mm) unit 1.00 - 3,287,281 3,287,281 -
- Difable toilet (uk. 650 x1000 mm) unit 1.00 - 806,314 806,314 -
Lantai 2
- Female toilet (uk. 1850x1000 mm) unit 1.00 - 2,294,894 2,294,894 -
- Male toilet (uk. 2650x1000 mm) unit 1.00 - 3,287,281 3,287,281 -
- Difable toilet (uk. 650 x1000 mm) unit 1.00 (1.00) 806,314 806,314 (806,314)

3 Meja Lavatory
Meja Lavatory granite hitam nero absolute, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :
Lantai 1
- Female toilet (uk. 1850x1000 mm) unit 1.00 - 5,765,118 5,765,118 -
- Male toilet (uk. 2650x1000 mm) unit 1.00 - 8,258,142 8,258,142 -
Lantai 2
- Female toilet (uk. 1850x1000 mm) unit 1.00 - 5,765,118 5,765,118 -
- Male toilet (uk. 2650x1000 mm) unit 1.00 - 8,258,142 8,258,142 -

4 Parapet
Dinding parapet beton tinggi 1200 mm, finish plester aci dan cat
weathershield,
Lantai 1 termasuk alat bantu lainnya dengan perlengkapan
- Ramp m' 83.13 - 304,910 25,347,168 -
- Bangunan m' 269.90 - 304,910 82,295,209 -

5 Tanggulan
Tanggulan Urinoir tinggi 1200 mm, tebal 115 mm lapis keramik, sesuai
gambar
Lantai 1dan spesifikasi pada :
- Male toilet (uk. 2650x1000 mm) m' 3.38 0.02 304,910 1,030,596 6,098
Lantai 2
- Male toilet (uk. 2650x1000 mm) m' 3.38 0.02 304,910 1,030,596 6,098
Tanggulan Closet tinggi 1200 mm, tebal 115 mm lapis keramik, sesuai
gambar dan spesifikasi pada :
Lantai 1
- Male toilet (uk. 2650x1000 mm) m' 2.38 0.02 304,910 725,991 5,793
- Female toilet (uk. 1850x1000 mm) m' 2.38 0.02 304,910 725,991 5,793
Lantai 2
- Male toilet (uk. 2650x1000 mm) m' 2.38 0.02 304,910 725,991 5,793
- Female toilet (uk. 1850x1000 mm) m' 2.38 0.02 304,910 725,991 5,793

6 Groove (Provisional)
Cutter Grove uk. 10x10 mm termasuk gutter 50x30 mm terpasang sesuai
gambar dan spesifikasi pada :
Lantai 1
- Groove ramp 1 m2 129.95 - 26,120 3,394,294 -
- Groove ramp 2 m2 104.60 - 26,120 2,732,152 -

7 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material bantu
dan kelengkapan lainnya, sesuai spesifkasi & gambar pada: (Provisional)
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.2.A.6. - PEKERJAAN LAIN-LAIN


- Lantai Atap m2 3,176.00 - 198,663 630,953,226 -
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.2.A.6. - PEKERJAAN LAIN-LAIN


8 Grill (Provisional)
Grill ukuran 300 mm, sesuai gambar dan spesifikasi, pada :

Lantai 1
- Horse Box m' 220.80 - 333,887 73,722,283 -

9 PERLENGKAPAN
Tempat makan kuda, sesuai gambar dan spesifikasi pada :
Lantai 1
- Horse Box bh 64.00 32.00 237,872 15,223,829 7,611,915

Tempat minum kuda, sesuai gambar dan spesifikasi pada :


Lantai 1
- Horse Box bh 64.00 32.00 237,872 15,223,829 7,611,915

DAFTAR No. III.2.A.6. - PEKERJAAN LAIN-LAIN 902,165,107 14,452,885


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.2.A.7. - PEKERJAAN ATAP

III.2.A.7.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari konsultan


terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Pemasangan Atap Baru

Atap UPVC setara ex Alderon berikut alat bantu dengan peralatan


perlengkapan sesuai dengan spesifikasi dan gambar pada :

Roof top
- Atap bawah m2 2,193.00 2,349.51 300,498 658,993,069 706,024,079
- Atap monitor (Pekerjaan baja masuk struktur baja) m2 983.00 (237.40) 300,498 295,389,962 (71,338,329)

2
Bongkaran atap UPVC Existing, sesuai lapangan dan gambar pada :

- Atap bawah m2 2,193.00 2,349.51 222,591 488,143,014 522,980,800


- Atap monitor m2 246.00 79.60 222,591 54,757,493 17,718,278

DAFTAR No. III.2.A.7. - PEKERJAAN ATAP 1,497,283,538 1,175,384,829


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harga satuan Rp Rp (+/-)

DAFTAR NO. III.2.A.8 - PEKERJAAN FAÇADE

III.2.A.8.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber gasket

(sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk alat


penggantung (ironmongery sets) dan sistem kunci (keying system) dan
pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari peserta
tender, seperti merk dan jenis kunci ataupun alat-alat penggantung, dll..

A Cat eksterior setara ex.Jotun Tipe standar, termasuk peralatan dan


perlengkapan sesuai spesifikasi dan gambar pada :
Eksterior
- Lantai 1
Parapet Ramp 1 m2 246.05 41.01 29,490 7,255,956 1,209,326
Parapet Ramp 2 m2 246.35 40.71 29,490 7,264,714 1,200,567
Eksterior Bangunan Penunjang m2 536.82 (195.73) 29,490 15,830,963 (5,772,190)
Eksterior R. Pengelola m2 214.42 98.38 29,490 6,323,187 2,901,285
Kolom 350x350 m2 894.60 (2.52) 29,490 26,381,754 (74,315)
Kolom 250x350 m2 275.40 (91.80) 29,490 8,121,546 (2,707,182)
- Lantai 2
Parapet m2 1,071.45 376.47 29,490 31,597,061 11,102,100

B GRC
Rib cetak GRC finishing cat Acrylic Emultion berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar pada :
(Provisional)
- Dinding samping m2 990.40 - 686,690 680,097,776 -

DAFTAR NO. III.2.A.8 - PEKERJAAN FAÇADE 782,872,956 7,859,592


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.B - PEKERJAAN ARSITEKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp

DAFTAR NO. III.2.B.1 - PEKERJAAN DINDING

III.2.B.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah


termasuk adukan biasa atau drymix, kolom praktis, ringbalk,
angkur, sparing dan semua pekerjaan bantu yang berhubungan
dengan pekerjaan dinding tersebut.

II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton maupun
bata , kawat ayam (jika diperlukan) dan semua pekerjaan bantu
yang berhubungan dengan plesteran. Volume plesteran dan
acian sudah ditambahkan 10cm di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit,


marmer, keramik, porselin) sudah termasuk adukan, cor
beton,perekat (calbond), angkur, kawat pengikat alumunium
fixing pada dinding dengan ketinggian lebih dari 2m,
pemotongan, pinggulan, adu manis, naad, dan alat bantu
lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk


dinding kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian


cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi.

I PEK. PASANG DINDING

1 Pekerjaan Dinding Include Horse Stable

DAFTAR NO. III.2.B.1 - PEKERJAAN DINDING -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.B - PEKERJAAN ARSITEKTUR CHANGING ROO Vol Vol (+/-) Harsat Rp

DAFTAR NO. III.2.A.2 - PEKERJAAN PINTU dan JENDELA

III.2.A.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis sekeliling
pintu & jendela, dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU

1 Pekerjaan Pintu dan jendela Include Horse Stable

DAFTAR NO. III.2.A.2 - PEKERJAAN PINTU dan JENDELA -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.B - PEKERJAAN ARSITEKTUR CHANGING ROO Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. III.2.A.3 - PEKERJAAN LANTAI

III.2.A.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)

II Harga satuan sudah termasuk levelling (sloping) mortarmix


sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

HOMOGENEOUS TILE

Homogeneous Tile (polished) uk 400 x 400 mm setara


ex.Niro granite / Essenza, berikut adukan mortar, additiv,
grouting nat termasuk alat-alat bantu lainnya dengan
peralatan perlengkapan sesuai spesifikasi dan gambar pada
:
- Koridor m2 78.60 - 388,340 30,522,763 -
- Foyer m2 6.89 - 388,340 2,675,555 -

PLINT HOMOGENEOUS TILE

Homogeneous Tile uk. 100 x 400 mm setara ex Niro granite


/ Essenza berikut adukan mortar, additiv, grouting nat
termasuk alat-alat bantu lainnya dengan peralatan
perlengkapan sesuai spesifikasi dan gambar pada :

- Koridor m' 25.65 - 14,270 366,014 -

Homogeneous Tile uk. 100 x 400 mm setara ex Niro granite


/ Essenza berikut adukan mortar, additiv, grouting nat
termasuk alat-alat bantu lainnya dengan peralatan
perlengkapan sesuai spesifikasi dan gambar pada :-
Lanjutan

- Foyer m' 7.69 - 14,270 109,729 -

DAFTAR NO. III.2.A.3 - PEKERJAAN LANTAI 33,674,061 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.B - PEKERJAAN ARSITEKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.2.B.4 - PEKERJAAN PLAFOND

III.2.B.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A Plafond Gypsumboard tebal 9 mm rangka metal furing hollow setara ex.


Jayaboard, finishing cat Acrylic Emulsion paint setara ex.ICI, termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :

- Koridor m2 72.52 124,090 8,999,007 -


- Foyer m2 6.75 124,090 838,194 -

DAFTAR NO. III.2.B.4 - PEKERJAAN PLAFOND 9,837,200 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.B - PEKERJAAN ARSITEKTUR CHANGING RO Vol Vol (+/-) Harsat Rp

DAFTAR NO. III.2.B.5. - PEKERJAAN SANITARY

III.2.B.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan


kelengkapan material bantu (adukan, plesteran, acian, nad, sealan,
grouting, bahan bantu pengubung (doble niple) yang berhubungan
dengan instalasi ME dan lainnya berikut pemasangan dan
perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Sanitary by Interior

DAFTAR NO. III.2.B.5. - PEKERJAAN SANITARY -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.B - PEKERJAAN ARSITEKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.2.B.6. - PEKERJAAN LAIN-LAIN

III.2.B.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu, perlengkapan


dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai gambar


dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Cermin
Kaca cermin tebal 8mm, lengkap dengan blocking plywood, berikut lapisan
granit hitam, berikut sealant, bracket, dll termasuk alat-alat bantu lainnya
dengan peralatan dan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :

Wastafel
- Changing Room Pria (762 x1142 mm) unit 4.00 - 1,077,583 4,310,333 -
- Changing Room wanita (762 x1142 mm) unit 8.00 - 1,077,583 8,620,666 -

Kaca cermin tebal 6mm, lengkap dengan blocking plywood, berikut sealant,
bracket, dll termasuk alat-alat bantu lainnya dengan peralatan dan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

- Changing Room Pria (3244 x2000 mm) unit 2.00 - 8,038,333 16,076,666 -
- Changing Room Pria (3069 x2000 mm) unit 1.00 - 7,616,569 7,616,569 -
- Changing Room Wanita (3069 x2000 mm) unit 3.00 - 7,616,569 22,849,706 -

2 Meja Lavatory
Meja Lavatory granite hitam nero absolute tebal 200 mm, termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :
Lantai 1
- Changing Room Pria (4180 x570 mm) unit 1.00 - 7,335,245 7,335,245 -
- Changing Room wanita (4180x570 mm) unit 1.00 - 7,335,245 7,335,245 -
- Changing Room Pria (2850x570 mm) unit 1.00 - 5,001,303 5,001,303 -
- Changing Room Wanita (2850x570 mm) unit 1.00 - 5,001,303 5,001,303 -

3 Tanggulan

Tanggulan Urinoir tinggi 1000 mm, tebal 175 mm lapis keramik, sesuai
gambar
Lantai 1dan spesifikasi pada :
- Male toilet m' 2.34 - 457,365 1,070,234 -

4 Tanggulan Closet tinggi 1000 mm, tebal 175 mm lapis keramik, sesuai
gambar
Lantai 1dan spesifikasi pada :
- Male toilet m' 3.88 - 457,365 1,774,576 -
- Female toilet m' 3.88 - 457,365 1,774,576 -

5 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material bantu dan
kelengkapan lainnya, sesuai spesifkasi & gambar pada: (Provisional)
- Lantai Atap m2 434.65 - 198,663 86,348,810 -

DAFTAR No. III.2.B.6. - PEKERJAAN LAIN-LAIN 175,115,232 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.B - PEKERJAAN ARSITEKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. III.2.B.8. - PEKERJAAN ATAP

III.2.B.8.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu, perlengkapan


dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari konsultan


terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Atap

Atap UPVC setara ex Alderon berikut alat bantu dengan peralatan


perlengkapan sesuai dengan spesifikasi dan gambar pada :

Roof top Baja masuk Struktur Pekerjaan Baja


- Changing room m2 707.30 71.55 300,498 212,542,544 21,500,062

DAFTAR No. III.2.B.8. - PEKERJAAN ATAP 212,542,544 21,500,062


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.2.B - PEKERJAAN ARSITEKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.2.B.9 - PEKERJAAN FAÇADE

III.2.B.9.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber gasket

(sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk alat


penggantung (ironmongery sets) dan sistem kunci (keying system) dan
pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari peserta
tender, seperti merk dan jenis kunci ataupun alat-alat penggantung, dll..

A GRC

Rib cetak GRC finishing cat weathershild berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar pada :

Dinding samping
- Changing room m2 97.96 95.90 686,690 67,268,152 65,853,571

B Cat Weathershield (Provisional)


Finishing cat weathershiled berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :

Dinding depan dan belakang


- Eksterior m2 134.69 - 29,490 3,972,008 -

DAFTAR NO. III.2.B.9 - PEKERJAAN FAÇADE 71,240,161 65,853,571


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.4 - PEKERJAAN ARSITEKTUR CHANGING RO Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.4.1. - PEKERJAAN DINDING

III.4.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah


termasuk adukan biasa atau drymix, kolom praktis, ringbalk,
angkur, sparing dan semua pekerjaan bantu yang berhubungan
dengan pekerjaan dinding tersebut.

II Harga satuan plesteran biasa atau drymix sudah termasuk


acian, skonengan, tali air , ketrikan atau bobokan beton maupun
bata , kawat ayam (jika diperlukan) dan semua pekerjaan bantu
yang berhubungan dengan plesteran.

III Harga satuan pekerjaan pelapis dinding (seperti : granit,


marmer, keramik, porselin) sudah termasuk adukan, cor
beton,perekat (calbond), angkur, kawat pengikat alumunium
fixing pada dinding dengan ketinggian lebih dari 2m,
pemotongan, pinggulan, adu manis, naad, dan alat bantu
lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk


dinding kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian


cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi.

W1, Pasangan bata ringan, tebal 100 mm dan perekat, adukan


kering, kolom dan balok praktis, sesuai spesifikasi dan gambar
pada : (reff.gbr : INT-1107 & INT-1108)

- Changing Room Pria m2 by arsitek


- Changing Room Wanita m2 by arsitek
- Dinning Room m2 by arsitek
- Steward Office m2 by arsitek
- -
- -
Plester dan Acian termasuk perekat, adukan kering, kolom dan
balok praktis, sesuai spesifikasi dan gambar pada : (reff.gbr :
INT-1107 & INT-1108)

- Changing Room m2 542.46 - 61,540 33,383,099 -


- Dinning Room m2 130.52 - 61,540 8,032,188 -
- Steward Office m2 82.73 - 61,540 5,091,026 -

W2, Dinding Keramik HT 600x600 mm Bianco Damasco setara


ex. Indogress, termasuk perekat, adukan kering, sesuai
spesifikasi dan gambar pada : (reff.gbr : INT-1107 & INT-1108)

- Changing Room Pria m2 60.80 - 348,040 21,160,414 -


- Changing Room Wanita m2 60.80 - 348,040 21,160,414 -

W2, Dinding Keramik HT 600x600 mm White Onyx setara ex.


Indogress, termasuk perekat, adukan kering, sesuai spesifikasi
dan gambar pada : (reff.gbr : INT-1107 & INT-1108)

- Changing Room Pria m2 9.02 - 361,890 3,264,783 -


- Changing Room Wanita m2 8.00 - 361,890 2,895,308 -

Pengecatan dengan fin. cat Acrylic Emultion white setara ex


Pentalite Dulux, ICI termasuk peralatan dan perlengkapan
sesuai spesifikasi dan gambar pada : reff.gbr : INT-1102 & INT-
2101)
- Changing Room m2 542.46 - 18,360 9,959,599 -
- Dinning Room m2 130.52 - 18,360 2,396,344 -
- Steward Office m2 82.73 - 18,360 1,518,870 -

Cubical Partisi kaca tempered 12mm, uk panjang 1450mm x


tinggi 2000mm, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1107 & INT-3101)
- Toilet Pria unit 3.00 - 8,068,939 24,206,818 -
- Toilet Wanita unit 3.00 - 8,068,939 24,206,818 -

Cubical Partisi kaca tempered 12mm, uk panjang 3990mm x


tinggi 2000mm, termasuk pintu kaca danhardware, handle TX
108 setara ex TOTO alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1107 & INT-3101)
- Toilet Pria unit 1.00 - 21,702,665 21,702,665 -
- Toilet Wanita unit 1.00 - 21,702,665 21,702,665 -

Cubical kaca tempered 12mm, uk panjang 995mm x tinggi


2040mm, termasuk pintu dan hardware serta alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada : (reff.gbr : INT-1107 & INT-2101)
DAFTAR No. III.4 - PEKERJAAN ARSITEKTUR CHANGING RO Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.4.1. - PEKERJAAN DINDING


- Shower Pria unit 2.00 5,647,701 11,295,402 -
- Shower Wanita unit 2.00 - 5,647,701 11,295,402 -

Cubical kaca tempered 12mm, uk panjang 1015mm x tinggi


2040mm, termasuk pintu dan hardware setara ex KEND handle
TX 108 setara ex TOTO serta alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : INT-1107 & INT-2101)
- Shower Pria unit 2.00 8,068,939 16,137,879 -
- Shower Wanita unit 2.00 - 8,068,939 16,137,879 -

Cubical kaca tempered 12mm, uk panjang 1025mm x tinggi


2040mm, termasuk pintu dan hardware setara ex KEND handle
TX 108 setara ex TOTO serta alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : INT-1107 & INT-2101)
- Shower Pria unit 2.00 8,068,939 16,137,879 -
- Shower Wanita unit 2.00 - 8,068,939 16,137,879 -

Partisi kaca tempered 12mm, uk panjang 320mm x tinggi


2100mm, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1107 & INT-3104)
- Shower Pria unit 6.00 - 1,752,908 10,517,445 -
- Shower Wanita unit 6.00 - 1,752,908 10,517,445 -

DAFTAR NO. III.4.1. - PEKERJAAN DINDING 308,858,223 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.4 - PEKERJAAN ARSITEKTUR CHANGING ROO Vol Vol (+/-) Harsat Rp

DAFTAR NO. III.4.2 - PEKERJAAN PINTU dan JENDELA

III.4.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk


angkur, sealant, karet, kaca, pengelasan, pemasangan kolom
praktis sekeliling pintu & jendela, dan peralatan bantu yang
diperlukan dan bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

DAFTAR NO. III.4.2 - PEKERJAAN PINTU dan JENDELA -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.4 - PEKERJAAN ARSITEKTUR CHANGING RO Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.4.3. - PEKERJAAN LANTAI

III.4.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

HOMOGENEOUS TILE

FL-01,Homogenious Tile 600x600mm White Onyx Color 1,


setara ex. Indogress termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : INT-1105 & INT-1106)

- Changing Room Pria m2 85.07 - 532,430 45,293,918 -


- Changing Room Wanita m2 75.64 - 532,430 40,273,571 -
- Dining Room m2 93.56 - 532,430 49,812,690 -
- Steward Office m2 60.25 - 532,430 32,078,983 -

FL-02,Homogenious Tile 600x600mm White Onyx Color 2,


setara ex. Indogress termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : INT-1105 & INT-1106)
- Changing Room Pria m2 37.19 - 532,430 19,802,459 -
- Changing Room Wanita m2 40.15 - 532,430 21,376,105 -
- Dinning Room m2 30.66 - 532,430 16,325,341 -

PLINT HOMOGENEOUS TILE

FL-03, Plint Homogenious Tile 100x600mm White Onyx setara


ex. Indogress termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1105 & INT-1106)

- Changing Room Pria m' 65.70 - 532,430 34,978,774 -


- Changing Room Wanita m' 66.36 - 532,430 35,333,250 -
- Dinning Room m' 56.36 - 532,430 30,007,817 -
- Steward Office m' 27.60 - 532,430 14,695,071 -

WATERPROOFING

Continuous Waterproofing Coating, termasuk pada dinding


setinggi 300mm terpasang sesuai dengan spesifikasi dan
gambar pada : (Provisional)

- Changing Room Pria m2 122.26 - 44,520 5,443,139 -


- Changing Room Wanita m2 115.79 - 44,520 5,154,938 -

DAFTAR NO. III.4.3. - PEKERJAAN LANTAI 350,576,055 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.4 - PEKERJAAN ARSITEKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.4.4 - PEKERJAAN PLAFOND

III.4.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A C1, Gypsum Board, setara ex. Jaya Board , tebal 9mm dengan rangka
hollow 40x40mm tebal 6 mm dan 40x20mm tebal 6 mm termasuk cat finish
Acrylic emulsion brilliant white setara ex pentalite dulux, ICI dan alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : INT-1111 & INT-1112)

- Changing Room Pria m2 84.83 - 124,090 10,526,349 -


- Changing Room Wanita m2 78.45 - 124,090 9,735,278 -
- Dinning Room m2 105.52 - 124,090 13,094,571 -
- Steward Office m2 60.25 - 124,090 7,476,435 -

C4, Gypsum Water resistant , setara ex. Jaya Board, tinggi plafond h=
2900mm dengan rangka hollow 40x40mm tebal 6 mm dan 40x20mm tebal
6 mm termasuk cat finish Acrylic emulsion brilliant white setara ex pentalite
dulux, ICI dan alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (reff.gbr : INT-1111 & INT-1112)

- Changing Room Pria m2 32.04 - 150,250 4,813,624 -


- Changing Room Wanita m2 32.26 - 150,250 4,846,494 -
- Dinning Room (Preparation Pantry) m2 15.46 - 150,250 2,323,053 -

C2, Translucent Membrane Ceiling, tinggi h= 2900mm dengan rangka


hollow termasuk alat bantu lainnya dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada : (reff.gbr : INT-1107)
- Changing Room Pria m2 22.50 - 1,214,878 27,331,693 -
- Changing Room Wanita m2 15.97 - 1,214,878 19,403,504 -

Drop Panel Ceilling 01, Gypsumboard 9mm setara ex. Jaya Board, tinggi
h= 200 mm dengan rangka hollow galvanis termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (reff.gbr : INT-3201)
- Changing Room Pria m' 8.29 - 83,140 688,815 -
- Changing Room Wanita m' 8.28 - 83,140 687,984 -
- Dinning Room m' 42.60 - 83,140 3,541,764 -
- Steward Office m' 5.50 - 83,140 457,270 -

DAFTAR NO. III.4.4 - PEKERJAAN PLAFOND 104,926,834 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.4 - PEKERJAAN ARSITEKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.4.5. - PEKERJAAN SANITARY

III.4.5.0. Catatan Harga

I
Harga satuan Upah sanitair (sanitary equipment) dengan kelengkapan
material bantu (adukan, plesteran, acian, nad, sealan, grouting, bahan
bantu pengubung (doble niple) yang berhubungan dengan instalasi ME
dan lainnya berikut pemasangan dan perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik


pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

Male Changing Room

- Wastafel Set setara ex TOTO LW549J bh 4.00 3,644,970 14,579,880 -


- Closet Duduk Set ex. TOTO CW860NJ/SW861JP bh 4.00 3,385,100 13,540,400 -
- Floor Drain setara ex. TOTO TX 1 BN bh 10.00 385,700 3,857,000 -
- Tissue Holder setara ex. TX 720 ACRB bh 4.00 267,820 1,071,280 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 4.00 581,660 2,326,640 -
- Faucet setara ex. TOTO TX 108LDN bh 4.00 1,301,490 5,205,960 -
- Sliding Rail (638 mm) setara ex. TOTO TX721AN bh 6.00 392,850 2,357,100 -
- Shower set setara ex. TOTO TX 432 SHBR bh 6.00 2,122,450 12,734,700 -
- Urinoir setara ex. TOTO UW 930 JM bh 3.00 3,483,960 10,451,880 -
- Urinoir Divider setara ex. TOTO AW 115 J bh 2.00 3,483,960 6,967,920 -
- Robe Hook setara ex TOTO (Provisional) bh 9.00 186,400 1,677,600 -

Female Changing Room

- Wastafel Set setara ex TOTO LW549J bh 4.00 3,644,970 14,579,880 -


- Closet Duduk Set ex. TOTO CW860NJ/SW861JP bh 4.00 3,385,100 13,540,400 -
- Floor Drain setara ex. TOTO TX 1 BN bh 10.00 385,700 3,857,000 -
- Tissue Holder setara ex. TX 720 ACRB bh 4.00 267,820 1,071,280 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 4.00 581,660 2,326,640 -
- Faucet setara ex. TOTO TX 108LDN bh 4.00 1,301,490 5,205,960 -
- Sliding Rail (638 mm) setara ex. TOTO TX721AN bh 6.00 392,850 2,357,100 -
- Shower set setara ex. TOTO TX 432 SHBR bh 6.00 2,122,450 12,734,700 -
- Robe Hook setara ex TOTO (Provisional) bh 9.00 186,400 1,677,600 -

DAFTAR NO. III.4.5. - PEKERJAAN SANITARY 132,120,920 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.4 - PEKERJAAN ARSITEKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.4.6. - PEKERJAAN FIX FURNITURE

III.4.6.0. Catatan Harga

I
Harga satuan pekerjaan sudah termasuk fitting, accessories,
alat bantu, perlengkapan dan peralatan yang diperlukan

II Harga satuan Backdrop dinding panel HPL sudah termasuk


rangka, penyesuaian pola permukaan, bahan terbuang,
biaya pengeringan kayu, anti rayap, penyambungan dan
finishing

III Harga satuan pada pekerjaan Movable Partition sudah


termasuk biaya untuk rangka, perkuatan struktur
penggantung, sound berrier, siap cat harus sudah termasuk
biaya fabrikasi, handling dan pemasangan, angkur-angkur,
bracket, sealant dan back of rod pada celah-celah horisontal
dan vertikal untuk mencegah kebocoran udara, air dan
suara.

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

V Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste)

VI Harga satuan sesuai dengan gambar dan spesifikasi teknis

Signed 1 & Console, Signed Acrylic uk lebar 800mm x tinggi 1400mm dan
lebar 400mm x tinggi 1400mm, Console plywood fin HPL uk
400mmx1692mmx200mm , termasuk rangka hollow alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (reff.gbr : INT-3401)
- Changing Room Pria unit 1.00 3,739,536 3,739,536 -
- Changing Room Wanita unit 1.00 3,739,536 3,739,536 -

Signed 2 Acrylic, uk lebar 800mm x tinggi 1400mm dan lebar 400mm x


tinggi 1400mm, Acrylic ex…..., termasuk rangka hollow alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (reff.gbr : INT-3401)

- Changing Room Pria unit 1.00 3,739,536 3,739,536 -


- Changing Room Wanita unit 1.00 3,739,536 3,739,536 -

Signed 3 Acrylic, uk lebar 615mm x tinggi 1400mm dan lebar 2500mm x


tinggi 1400mm, Acrylic ex…..., termasuk rangka hollow alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (reff.gbr : INT-3401)

- Changing Room Pria unit 1.00 2,804,652 2,804,652 -


- Changing Room Wanita unit 1.00 2,804,652 2,804,652 -

Ambalan Rangka Kayu, uk 300mm x 800mm x 80mm, Plywood 12 mm fin


HPL ex…..., termasuk rangka hollow alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada : (reff.gbr :
INT-3103)

- Changing Room Pria unit 3.00 250,415 751,246 -


- Changing Room Wanita unit 3.00 250,415 751,246 -

DAFTAR NO. III.4.6. - PEKERJAAN FIX FURNITURE 22,069,941 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. III.4 - PEKERJAAN ARSITEKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. III.4.7. - PEKERJAAN LOOSE FURNITURE

III.4.7.0. Catatan Harga

I Harga satuan pekerjaan furniture sudah termasuk fitting, accessories, alat


bantu, perlengkapan dan peralatan yang diperlukan

II Harga satuan sudah termasuk lampu, kabel, fitting dan sparing-sparing


sesuai gambar dari konsultan terkait

III Harga satuan Backdrop dinding panel HPL sudah termasuk rangka,
penyesuaian pola permukaan, bahan terbuang, biaya pengeringan kayu,
anti rayap, penyambungan dan finishing

IV
Harga satuan pada pekerjaan Movable Partition sudah termasuk biaya
untuk rangka, perkuatan struktur penggantung, sound berrier, siap cat
harus sudah termasuk biaya fabrikasi, handling dan pemasangan, angkur-
angkur, bracket, sealant dan back of rod pada celah-celah horisontal dan
vertikal untuk mencegah kebocoran udara, air dan suara.

V Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik


pembuat

VI Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste)

VII Harga satuan sesuai dengan gambar dan spesifikasi teknis

F4, BENCH ( Custom Funiture),uk panjang 2725mm x lebar 400mm x


tinggi 450 mm dan panjang 840 mm x lebar 400mm x tinggi 450 mm,
Plywood finished HPL dan painted steel 40/40 foot base ex.......... ,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :

1 - Changing Room unit 2.00 9,687,179 19,374,358 -

F3,Locker & Storage, uk panjang 800mm x lebar 600mm x tinggi


2100mm, Plywood finish HPL setara ex Arborite,vynil edging bagian
dalam melaminto termasuk fitting acccessories ex Hafelle atau setara dan
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :

2 - Changing Room Pria unit 30.00 2,504,154 75,124,609 -


3 - Changing Room Wanita unit 24.00 2,504,154 60,099,687 -

F1, Desk Reception, uk panjang 800mm x lebar 700mm x tinggi


1100mm, Plywood finish HPL setara ex. Arborite, vynil edging bagian
dalam Melaminto termasuk fiiting accessories ex Hafelle atau setara alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
4 - Changing Room Pria unit 1.00 4,407,310 4,407,310 -
5 - Changing Room Wanita unit 1.00 4,407,310 4,407,310 -

F2, Credenza, uk Panjang 2650mm x 375mm x tinggi 760mm, Plywood


finish HPL setara ex. Arbatise, Vynil edging bagian dalam melaminto
termasuk fitting accessories ex Hafelle atau setara dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

6 - Changing Room unit 2.00 11,539,140 23,078,280 -

C1, Kursi Type C 200 N Black / Lime green, ex. Morelli atau setara, uk
panjang 480mm x lebar 450mm x tinggi 610mm, termasuk mesh back,
foam seat fabric unpholstery setara ex Ateja sesuai spesifikasi dan
gambar pada :
7 - Changing Room unit 2.00 1,869,768 3,739,536 -
8 - Steward Office unit 12.00 1,869,768 22,437,217 -

DT, Dinning Table, uk Panjang 1800mmx800mm x tinggi 720mm, Top


Table plywood 18mm finish HPL dan powder coated steel pipe 2",
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :
9 - Dinning Room unit 6.00 3,561,463 21,368,778 -

DT, Dinning Table, uk Panjang 1200mmx800mm x tinggi 720mm, Top


Table plywood 18mm finish HPL dan powder coated steel pipe 2",
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :
10 - Dinning Room unit 3.00 3,383,390 10,150,169 -

C3, Kursi Makan Type Short Verna, uk diameter 450mm x 450mm x


tinggi 720mm, Alumunium Look finish solid wood seats setara ex Ikons
atau setara, termasuk alat bantu lainnya dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-1104)
10 - Dinning Room unit 48.00 1,120,080 53,763,845 -

F5, Coffe Table, uk 900mmx900mm x tinggi 400mm, Plywood finish HPL


setara ex Arborite, vynil edging alumunium extrusi foot base termasuk
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :

11 - Dinning Room unit 2.00 1,342,672 2,685,343 -

F6, Coffe Table, uk 500mmx500mm x tinggi 400mm, Plywood finish HPL


setara ex Arborite, vynil edging alumunium extrusi foot base termasuk
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :
F6, Coffe
DAFTAR No. Table, uk 500mmx500mm
III.4 - PEKERJAAN x tinggi 400mm,
ARSITEKTUR Plywood
CHANGING ROOM finish HPL Vol Vol (+/-) Harsat Rp Rp (+/-)
setara ex Arborite, vynil edging alumunium extrusi foot base termasuk
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
DAFTAR NO. III.4.7. - PEKERJAAN LOOSE FURNITURE
pada :

12 - Dinning Room unit 2.00 1,342,672 2,685,343 -

SF1, Soffa 1 Seat type Maya ex. Vivere atau setara, Mahogany wood
base stain fin, foam rubber seats dan cushion fabric uphoistery sesuai
spesifikasi dan gambar pada :
12 - Dinning Room unit 2.00 4,273,756 8,547,511 -

SF2, Soffa 3 Seat type Maya ex. Vivere atau setara, Mahogany wood
base stain fin, foam rubber seats dan cushion fabric uphoistery sesuai
spesifikasi dan gambar pada :
13 - Dinning Room unit 2.00 7,835,218 15,670,437 -

F8, Buffet Table, uk diameter 4050mm x 600mm x tinggi 2400mm,


Plywood finish HPL, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

14 - Dinning Room unit 1.00 3,456,552 3,456,552 -

BT, Buffet Table, uk diameter 1950mm x 600mm x tinggi 2400mm,


Plywood finish HPL, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

15 - Dinning Room unit 1.00 1,869,768 1,869,768 -

FL, Filling Type Elite file drawer, uk diameter 465mm x 620mm x tinggi
1300mm, metal file cabinet 4 drawer metal 0.8 mm powder coating finish,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :

16 - Steward Office unit 11.00 3,179,878 34,978,658 -

F10, Work Table Credenza, uk diameter 1200mm x 600mm x tinggi


750mm dan uk. 450mm x 600mm x 750mm, Plywood finish HPL setara
ex. Arborite, vynil edging alumunium extrussi foot base, termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
17 - Steward Office unit 12.00 3,739,536 44,874,433 -

F9, Steward Table Credenza, uk diameter 750mm x 600mm x tinggi


400mm, Plywood finish HPL setara ex. Arborite, vynil edging alumunium
extrussi foot base, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

18 - Steward Office unit 3.00 1,907,926 5,723,779 -

C2, Kursi Tamu Single type Savio setara ex. Ikons, Mahogany wood
base stain fin, foam rubber seats dan cushion fabric uphoistery sesuai
spesifikasi dan gambar pada :
24 - Steward Office unit 6.00 1,157,475 6,944,853 -

DAFTAR NO. III.4.7. - PEKERJAAN LOOSE FURNITURE 425,387,777 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.1 - PEKERJAAN STRUKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. IV.1.1 - PEKERJAAN TANAH

IV.1.1.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko


longsoran, volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah


termasuk kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi


dan tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-IV.1.1 ( 142 ) TANAH


DAFTAR No. IV.1 - PEKERJAAN STRUKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. IV.1.1 - PEKERJAAN TANAH


A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan m2 347.08 11,130 3,862,852 -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 101.94 55,640 5,671,752 -
- Pile Cap m3 17.79 55,640 989,752 -
- Tie Beam m3 15.55 55,640 865,343 -
- Bio Tank Equine Clinic m3 28.64 55,640 1,593,619 -

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai basement inc Tie Beam m3 91.40 272,340 24,892,965 -
- Pondasi Batu kali m3 9.04 272,340 2,462,209 -
- Pile Cap m3 3.01 272,340 820,560 -
- Tie Beam m3 2.36 272,340 641,754 -
- Bio Tank Equine Clinic m3 0.60 272,340 162,424 -

Urugan tanah untuk mencapai level yang diinginkan, termasuk pemadatan,


dengan memaksimalkan tanah dipakai dari bekas galian serta tanah dari
luar site jika diperlukan sesuai spek dan gambar
- Pondasi Batu kali m3 31.38 55,648 1,746,232 -
- Pile Cap m3 14.78 55,648 822,225 -
- Tie Beam m3 13.20 55,648 734,334 -

D Pek. Lain - Lain


D.1 Pek. Bobok kepala tiang Pondasi Pancang

Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar

- Mini Pile diameter 25 cm ttk tdk ada - -


D.2 Pekerjaan Anti rayap
Anti rayap pada Lantai dan dinding basement , termasuk alat - alat bantu, m2 347.08 16,690 5,792,765 -
peralatan perlengkapan sesuai spesifikasi dan gambar

D.3 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan
sesuai spesifikasi dan gambar (Kontraktor diminta untuk melampirkan
breakdown harganya) Ls 1.00 Exclude - -

DAFTAR No. IV.1.1 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 51,058,787 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-IV.1.1 ( 143 ) TANAH


DAFTAR No. IV.1 - PEKERJAAN STRUKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.1.2 - PEKERJAAN STRUKTUR BETON

IV.1.2.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- III.1.2 ( 144 ) SAMEP


DAFTAR No. IV.1 - PEKERJAAN STRUKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.1.2 - PEKERJAAN STRUKTUR BETON

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai basement incl Tie beam m3 30.79 (14.82) 667,780 20,558,635 (9,893,822)
2) Pondasi batu kali m3 90.49 - 667,780 60,425,362 -
3) Pile cap m3 15.07 (13.56) 667,780 10,060,106 (9,054,095)
4) Bio Tank pada Equine Clinic m3 1.19 667,780 796,528

B Beton mutu K-300 :


1) Pile cap m3 9.04 (3.62) 759,480 6,864,940 (2,745,976)
2) Tie beam / sloof 200 x 300 m3 4.24 2.69 759,480 3,221,412 2,042,696
3) Pelat, pada:
- Lantai dasar m3 36.56 3.36 759,480 27,767,804 2,555,479
4) Balok, pada:
- Lantai dasar m3 3.82 1.54 759,480 2,901,116 1,169,696
5) Bio Tank pada Equine Clinic m3 11.16 759,480 8,479,442

C Beton mutu K-350 :


1) Kolom, pada:
- Lantai dasar m3 5.59 0.17 782,410 4,371,481 135,200

PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada:
- Lantai dasar m2 304.68 14.73 53,220 16,215,070 783,984
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pile cap kg 1,289.59 (305.06) 8,859 11,423,875 (2,702,343)
2) Tie beam / sloof 200 x 300 kg 1,052.85 (55.88) 8,859 9,326,645 (495,036)
3) Balok, pada:
- Lantai 1 kg 708.06 104.91 8,859 6,272,384 929,343
4) Kolom, pada:
- Lantai dasar kg 764.49 146.79 8,859 6,772,207 1,300,330
5) Bio Tank Equine Clinic kg 1,674.72 8,858.50 14,835,507 -

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap m2 26.28 (10.51) 84,790 2,228,281 (891,312)
2) Sisi tegak Tie Beam / sloof 200 x 300 m2 42.42 26.90 84,790 3,596,454 2,280,510

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada:
- Lantai 1 (Bawah pelat, bawah balok dan sisi tegak) m2 314.62 14.50 100,570 31,640,931 1,458,464
2) Kolom, pada:
- Lantai dasar m2 74.50 2.30 129,920 9,678,520 299,336
3) Balok (sisi tegak), pada:
- Lantai dasar m2 38.20 15.40 104,000 3,972,667 1,601,733
4) Bio Tank pada Equine Clinic m2 69.80 100,570 7,020,188 -

PEKERJAAN LAIN-LAIN (Provisional)


Water Proofing Integral termasuk sesuai dengan gambar dan
A
spesifikasi, pada :
1) Pile Cap m3 9.04 (3.62) 100,170 905,437 (362,175)

B Pondasi Batu Kali


1) Pondasi Batu Kali m3 43.43 - 611,910 26,577,532 -
2) Pasangan Aanstamping t=15cm m3 18.08 - 398,440 7,204,544 -
3) Beton tumbuk m3 90.49 - 720,190 65,167,782 -
4) Angkur D13-500 kg 17.19 - 18,920 325,260 -

DAFTAR NO. IV.1.2 - PEKERJAAN STRUKTUR BETON


Dipindahkan ke Penjumlahan Total 368,610,109 (11,587,987)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- III.1.2 ( 145 ) SAMEP


DAFTAR No. IV.1 - PEKERJAAN STRUKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.1.3 - PEKERJAAN STRUKTUR BAJA

IV.1.3.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang diperlukan,
seperti : pengelasan, pembuatan lubang-lubang baut, perapihan
dengan gerinda, penyediaan peralatan bantu untuk pemasangan
dan mendirikan atap+rangka serta sisa terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi dan


pengiriman ke lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi

I Pekerjaan Structure Atap


1) WF 300 x 150 x 6,5 x 9 Kg 4,226.52 18,364 77,614,918 -
2) WF 200 x 100 x 5,5 x 8 Kg 180.11 18,364 3,307,512 -
3) CNP 200 x 75 x 20 x 3.2 Kg 4,805.57 18,364 88,248,457 -
4) HB 200 x 200 x 12 x 12 Kg 196.73 18,364 3,612,796 -
5) L 40 x 40 x 4 Kg 549.43 18,364 10,089,655 -
6) Plate T = 6 Kg 144.22 17,807 2,568,161 -
7) Plate T = 12 Kg 226.03 17,807 4,025,066 -
8) Baut Diameter M 12 mm bh 422.00 31,163 13,150,702 -
9) Baut Diameter M 19 mm bh 196.00 31,163 6,107,909 -
10) Trekstang dia 10mm Kg 83.65 17,807 1,489,611 -
11) Angkur M 12 Kg 28.00 222,591 6,232,560 -
12) Roundbar Ø 8 bh 28.12 31,163 876,356 -
13) Cat Dasar (Zincromate) Kg 10,440.27 3,339 34,858,718 -
14) Cat Dasar (Zincromate) Kg 10,440.27 3,339 34,858,718 -

DAFTAR NO. IV.1.3 - PEKERJAAN STRUKTUR BAJA 287,041,140 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- III.1.3 ( 146 ) SAMEP


DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.2.1. - PEKERJAAN DINDING

IV.2.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah termasuk


adukan biasa atau drymix, kolom praktis, ringbalk, angkur, sparing
dan semua pekerjaan bantu yang berhubungan dengan pekerjaan
dinding tersebut.

II
Harga satuan plesteran biasa atau drymix sudah termasuk acian,
skonengan, tali air , ketrikan atau bobokan beton maupun bata ,
kawat ayam (jika diperlukan) dan semua pekerjaan bantu yang
berhubungan dengan plesteran. Volume plesteran dan acian sudah
ditambahkan 10cm di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit, marmer,


keramik, porselin) sudah termasuk adukan, cor beton,perekat
(calbond), angkur, kawat pengikat alumunium fixing pada dinding
dengan ketinggian lebih dari 2m, pemotongan, pinggulan, adu manis,
naad, dan alat bantu lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk dinding


kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian cat


dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi.

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. Primacon, termasuk
dinding penebalan,urinoir, perekat, adukan kering kolom dan balok
praktis
- Lantaisesuai
1 spesifikasi dan gambar : m2 507.14 81.45 103,480 52,478,388 8,428,284

II PEK. PELAPIS DINDING

A Plesteran dan Acian, Plesteran halus berikut acian halus, termasuk


peralatan dan perlengkapan sesuai spesifikasi dan gambar pada :

- Lantai 1 m2 509.99 (27.05) 61,540 31,384,674 (1,664,854)


- Area Exterior m2 178.81 (114.39) 61,540 11,003,697 (7,039,598)

Keramik Roman 300x300 setara ex Roman/Mulia tipe standar, sesuai


B
spesifikasi dan gambar ;

- Lantai 1
Wastafel Room m2 - by interior
Toilet As. 00-01 m2 - by interior
Toilet Vet Room m2 - by interior

C Pengecatan dengan fin. cat Acrylic Emultion white setara ex


Pentalite Dulux, ICI termasuk peralatan dan perlengkapan sesuai
spesifikasi dan gambar pada : reff.gbr : INT-1102 & INT-2101)

- Lantai 1
Vet Room m2 56.63 (56.63) by interior
Medicine Storage m2 24.31 (24.31) by interior
Coridor m2 28.62 15.22 18,360 525,423 279,480

D Pengecatan dengan fin. cat Acrylic Emultion ex setara Jotun +


Rubber, termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :

- Lantai 1
Sick Horse Box As. 00-01 m2 37.35 (0.00) 18,360 685,746 (37)
Sick Horse Box As. 01-02 m2 37.35 (0.00) 18,360 685,746 (37)
Treatment Room m2 166.43 (18.42) 18,360 3,055,625 (338,162)
Farrier Quarter/ Sick Horse Box As. 03-04 m2 50.86 1.48 18,360 933,790 27,173
Farrier Quarter/ Sick Horse Box As. 04-05 m2 50.06 1.88 18,360 919,102 34,517
Sick Horse Box As. 05-06 m2 50.86 1.48 18,360 933,790 27,173
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.2.1. - PEKERJAAN DINDING

DAFTAR NO. IV.2.1. - PEKERJAAN DINDING 102,605,980 (246,061)


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.2.2 - PEKERJAAN PINTU dan JENDELA

IV.2.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis sekeliling
pintu & jendela, dan peralatan bantu yang diperlukan dan bahan yang
terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling pintu
& jendela , dan peralatan bantu yang diperlukan dan bahan yang
terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU KAYU
Pintu Kayu P1 Terdiri dari 1 pintu dan 2 daun pintu dengan
kusen/frame alumunium ukuran 2628x2400 mm, Plywood, kaca 5
mmTHK.
- Lantai 1 lengkap terpasang termasuk, hardware, accesories dan unit 3.00 (2.00) 7,927,037 23,781,112 (15,854,075)

Hardware :
Lever handle art - 306 SS psg 1.00 - Include
Lockcase wilka art-1490.55 SS bh 1.00 - Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 - Include
Hinges Gracia BB 5"x3"x3 mm SS bh 8.00 - Include
Flush bolt Gracia 200/350 mm SS set 1.00 - Include
Door closer Dorma TS 68 RA Silver bh 1.00 - Include

Pintu Kusen P2 terdiri dari 1 daun pintu Alumunium 40 mm clear


anodized, ukuran 1000x2400 mm, alumunium, Daun pintu double
teakwodd
- Lantai 1 3 mm lengkap terpasang termasuk, hardware, accesories unit 3.00 - 3,500,250 10,500,751 -

Hardware :
Lever handle art - 306 SS psg 1.00 2.00 Include
Lockcase wilka art-1490.55 SS bh 1.00 2.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 2.00 Include
Hinges Gracia BB 4"x3"x3 mm SS bh 3.00 6.00 Include
Door closer Dorma TS 68 RA Silver bh 1.00 2.00 Include

Pintu Kusen P3 terdiri dari 1 daun pintu Alumunium 40 mm clear


anodized, ukuran 720x2400 mm, kaca clear 5 mm, daun jendela
Alumunium,
- Lantai 1 daun pintu Double Teakwood 3mm, Plywood 4mm unit 2.00 - 6,485,758 12,971,516 -

Hardware :
Lever handle art - 306 SS psg 1.00 1.00 Include
Lockcase wilka art-1490.55 SS bh 1.00 1.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 1.00 Include
Hinges Gracia BB 4"x3"x3 mm SS bh 3.00 3.00 Include
Door closer Dorma TS 68 RA Silver bh 1.00 1.00 Include

Pintu Kayu PJ1A ukuran 3450x2400 mm lengkap terpasang


termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai
- Lantaispesifikasi
1 dan gambar pada : unit 2.00 - 6,773,736 13,547,471 -

Pintu Kayu PJ1B ukuran 3950x2400 mm lengkap terpasang


termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai
- Lantaispesifikasi
1 dan gambar pada : unit 2.00 - 7,522,199 15,044,399 -

Pintu Kayu PJ1C ukuran 3350x2400 mm lengkap terpasang


termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai
- Lantaispesifikasi
1 dan gambar pada : unit 1.00 - 6,345,804 6,345,804 -

B JENDELA

Jendela J1 ukuran 1000x1080 mm Kusen Alumunium 40 mm Clear


Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya
- Lantai sesuai
1 spesifikasi dan gambar pada : unit 17.00 - 4,965,458 84,412,793 -

Hardware :
Hinges Gracia BB 4"x3"x3 mm SS bh 4.00 64.00 Include
Rambuncis artt-118 silver bh 2.00 32.00 Include
Cabin hook Gracia art-50 1/8" SS bh 2.00 32.00 Include

Jendela J2 ukuran 1500x920 Kusen Alumunium 40 mm Clear


Anodized, Besi Bulat 1.5 lengkap terpasang termasuk, hardware,
accesories
- Lantai 1 dan perlengkapan bantu lainnya sesuai spesifikasi dan unit 3.00 - 4,922,640 14,767,921 -

Hardware :
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.2.2 - PEKERJAAN PINTU dan JENDELA


Hinges Gracia BB 4"x3"x3 mm SS bh 4.00 8.00 Include
Rambuncis artt-118 silver bh 2.00 4.00 Include
Cabin hook Gracia art-50 1/8" SS bh 2.00 4.00 Include
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.2.2 - PEKERJAAN PINTU dan JENDELA

Jendela J3 ukuran 1000x1107 Kusen Alumunium 40 mm Clear


Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya
- Lantai sesuai
1 spesifikasi dan gambar pada : unit 7.00 - 3,923,844 27,466,907 -

Hardware :
Flush handle art-506 SN bh 4.00 24.00 Include
Lockcase Wilka art-1436.30 SN bh 1.00 6.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 6.00 Include
Ring kunci art-901 CK SS bh 2.00 12.00 Include
Track sliding Calfis SD 100/2mtr btg 1.00 6.00 Include
Cannel Sliding Calfis CL 500/2mtr btg 1.00 6.00 Include
Bracket BK 110 btg 6.00 36.00 Include
Roda sliding Calfis pack 120 (100kg)
Terdiri dari :
- Hanger HW111 (2pcs)
- Track buffer with retained ST 112 (1Pcs)
- Floor Guide FG 115 (1Pcs)

Jendela J4 ukuran 500x340 Kusen Alumunium 40 mm Clear


Anodized, Kaca Clear 5 mm lengkap terpasang termasuk, hardware,
accesories
- Lantai 1 dan perlengkapan bantu lainnya sesuai spesifikasi dan unit 4.00 - 283,804 1,135,216 -

Hardware :
Hinges Gracia BB 4"x3"x3 mm SS bh 3.00 9.00 Include
Rambuncis artt-118 silver bh 1.00 3.00 Include
Cabin hook Gracia art-50 1/8" SS bh 1.00 3.00 Include

DAFTAR NO. IV.2.2 - PEKERJAAN PINTU dan JENDELA 209,973,890 (15,854,075)


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.2.3. - PEKERJAAN LANTAI

IV.2.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

FLOOR HARDENER

Floor Hardener 3kg/m, termasuk alat alat bantu lainnya


dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :

- Selasar Tritisan Atap Depan m2 14.69 (2.36) 33,390 490,499.09 (78,800.39)


- Ramp m2 16.87 (0.05) 33,390 563,289.30 (1,769.67)

PAVING BLOCK

Paving Block Tebal 80 mm setara Ex. Conblock ,termasuk


alat-alat bantu lainnya dengan peralatan terpasang sesuai
spesifikasi dan gambar

- Farrier Quarter 1 m2 17.51 0.04 248,600 4,352,989.48 9,940.52


- Farrier Quarter 2 m2 17.02 0.04 248,600 4,231,176.70 9,939.30
- Sick Horse Box 1 m2 20.06 0.04 248,600 4,986,894.34 9,965.66
- Sick Horse Box 2 m2 20.04 0.06 248,600 4,981,393.78 15,466.22
- Sick Horse Box 3 m2 17.51 0.04 248,600 4,352,989.75 9,940.25
- Treatment room m2 45.88 (0.09) 248,600 11,405,768.00 (22,374.00)

FLOOR HARDENER + RUBBER MATT

floor hardener 3kg/m2 + Rubber matt, termasuk alat alat


bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :

- Koridor m2 26.97 - 272,119 7,339,057.86 -


- Dead Horse m2 68.90 1.19 272,119 18,749,020.65 325,046.52
- Selasar Tritisan Atap Belakang m2 12.31 2.38 272,119 3,351,144.56 646,288.15

CERAMIC TILE (Provisional)

Ceramic Tile uk. 300 x 300 mm setara ex Roman berikut


adukan mortar, additiv, grouting nat termasuk alat-alat bantu
lainnya dengan peralatan perlengkapan sesuai spesifikasi
dan gambar pada :

- Tangga m2 7.57 - 173,260 1,310,711.90 -

STEP NOSING (Provisional)

Keramik Tile uk. 100 x 200mm ex setara ROMAN berikut


adukan mortar, additiv, grouting nat termasuk alat-alat bantu
lainnya dengan peralatan perlengkapan sesuai spesifikasi
dan gambar pada :

Lantai 1
- Tangga m' 16.30 - 150,610 2,454,943.00 -

DAFTAR NO. IV.2.3. - PEKERJAAN LANTAI 68,569,878 923,643


Dipindahkan ke Penjumlahan Total
,, DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.2.4 - PEKERJAAN PLAFOND

IV.2.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A Plafond Kalsiboard tebal 8 mm setara ex. Jayaboard, finishing cat


Weathershiled setara ex ICI / jotun, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :

- Sick horse box 1 m2 20.06 0.04 161,380 3,237,268.74 6,469.26


- Sick horse box 2 m2 20.04 0.06 161,380 3,233,698.02 10,039.98
- Selasar Tritisan atap depan m2 14.69 27.62 161,380 2,370,672.17 4,457,315.63
- Selasar Tritisan atap belakang (Provisional) m2 49.50 - 161,380 7,988,309.98 -

B Beton exposed aci halus finish cat interior ex.Jotun tipe standar, termasuk
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
dengan spesifikasi dan gambar pada :

- Sick horse box 3 m2 17.51 0.04 51,760 906,318.38 2,069.62


- Coridor m2 26.97 0.00 51,760 1,395,837.80 129.40
- Farrier Quarter 1 m2 17.51 0.04 51,760 906,318.32 2,069.68
- Farrier Quarter 2 m2 17.02 0.04 51,760 880,956.18 2,069.42
- Treatment room m2 45.88 (0.09) 51,760 2,374,748.80 (4,658.40)
- Dead horse door m2 68.90 0.02 51,760 3,566,134.59 1,164.61

c Listplank GRC Cetak finishing cat Weathershield setara ex. ICI / Jotun,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :

- Tritisan atap m' 66.67 (14.25) 267,110 17,808,205.07 (3,806,313.52)

DAFTAR NO. IV.2.4 - PEKERJAAN PLAFOND 44,668,468 670,356


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp

DAFTAR NO. IV.2.5. - PEKERJAAN SANITARY

IV.2.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan


kelengkapan material bantu (adukan, plesteran, acian, nad, sealan,
grouting, bahan bantu pengubung (doble niple) yang berhubungan
dengan instalasi ME dan lainnya berikut pemasangan dan
perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Sanitary by Interior

-
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. IV.2.6. - PEKERJAAN LAIN-LAIN

IV.2.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai


gambar dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Cermin
Kaca cermin tebal 5mm, lengkap lapisan belakang dari multiplek tebal 12
mm, berikut sealant, bracket, dll termasuk alat-alat bantu lainnya dengan
peralatan dan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :
- Toilet dokter 1 (uk. 800x1550 mm) unit 1.00 - 1,590,601 1,590,601 -

Kaca cermin tebal 5mm, blocking hollow 40x40 mm lengkap lapisan


belakang dari multiplek tebal 12 mm, berikut sealant, bracket, dll
termasuk alat-alat bantu lainnya dengan peralatan dan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :
- Toilet 2 umum (uk. 400x1550 mm) unit 1.00 - 1,214,459 1,214,459 -

2 Meja Beton
Meja Beton tebal 180mm lapis keramik, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :(provisional)
Lantai 1
- Toilet dokter 1 (uk. 1050x500 mm) unit 1.00 - 466,520 466,520 -
- Toilet 2 umum (uk. 1000x470 mm) unit 1.00 - 466,520 466,520 -

3 Tanggulan

Tanggulan Closet tinggi 900 mm, tebal 100 mm lapis keramik, sesuai
gambar
Lantai 1dan spesifikasi pada :
- Toilet dokter 1 m' 1.05 - 457,365 480,233 -
- Toilet 2 umum m' 1.20 - 457,365 548,838 -

4 Groove (Provisional)
Cutter Grove uk. 10x10 mm termasuk gutter 50x30 mm terpasang sesuai
gambar dan spesifikasi pada :
Lantai 1
- Groove ramp m2 16.87 - 26,120 440,644 -

5 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material bantu
dan kelengkapan lainnya, sesuai spesifkasi & gambar pada:
(Provisional)
- Lantai Atap m2 344.44 - 198,663 68,427,434 -

6 PERLENGKAPAN
Tempat minum kuda, sesuai gambar dan spesifikasi pada :
Lantai 1
- Sick Horse bh 5.00 - 237,872 1,189,362 -

DAFTAR No. IV.2.6. - PEKERJAAN LAIN-LAIN 74,824,611 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. IV.2.8. - PEKERJAAN ATAP CANOPY

IV.2.8.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari


konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Atap EQUINE CLINIC

Atap UPVC ex Alderon berikut alat bantu dengan peralatan


perlengkapan sesuai dengan spesifikasi dan gambar pada :

Roof top Baja masuk Struktur Pekerjaan Baja


- Equine clinic m2 445.24 (3.72) 300,498 133,793,923 (1,117,674)

DAFTAR No. IV.2.8. - PEKERJAAN ATAP CANOPY 133,793,923 (1,117,674)


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.2.9 - PEKERJAAN FAÇADE

IV.2.9.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber gasket

(sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk alat


penggantung (ironmongery sets) dan sistem kunci (keying system) dan
pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari peserta
tender, seperti merk dan jenis kunci ataupun alat-alat penggantung, dll..

A GRC
Rib cetak GRC finishing cat Acrylic Emultion berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar pada :
(Provisional)
- Dinding samping m2 150.52 - 686,690 103,360,579 -

B CAT WEATHERSHILED
Finishing cat weathershiled berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :

- Dinding samping m2 58.70 319.32 29,490 1,731,063 9,416,700


- Eksterior m2 214.07 (143.00) 29,490 6,312,795 (4,217,088)

C WOOD PLASTIC COMPOSITE


Wood plastic Composite berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :

- Dinding Exterior m2 24.15 11.74 834,718 20,158,437 9,802,509

D CAT KAMPROT
Cat Kamprot berikut alat bantu dengan peralatan perlengkapan sesuai
dengan spesifikasi dan gambar pada :

- Dinding depan & belakang m2 56.56 27.19 61,213 3,462,187 1,664,464

DAFTAR NO. IV.2.9 - PEKERJAAN FAÇADE 135,025,060 16,666,585


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.4 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.4.1. - PEKERJAAN DINDING

IV.4.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah termasuk


adukan biasa atau drymix, kolom praktis, ringbalk, angkur, sparing
dan semua pekerjaan bantu yang berhubungan dengan pekerjaan
dinding tersebut.

II Harga satuan plesteran biasa atau drymix sudah termasuk acian,


skonengan, tali air , ketrikan atau bobokan beton maupun bata ,
kawat ayam (jika diperlukan) dan semua pekerjaan bantu yang
berhubungan dengan plesteran.

III Harga satuan pekerjaan pelapis dinding (seperti : granit, marmer,


keramik, porselin) sudah termasuk adukan, cor beton,perekat
(calbond), angkur, kawat pengikat alumunium fixing pada dinding
dengan ketinggian lebih dari 2m, pemotongan, pinggulan, adu
manis, naad, dan alat bantu lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk dinding


kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian cat


dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi.

I DINDING DAN PELAPIS DINDING


C, Pasangan bata ringan, tebal 100 mm dan perekat, adukan
kering, kolom dan balok praktis, sesuai spesifikasi dan gambar
pada : (reff.gbr : INT-1102 & INT-2102)
- Vet Room m2 by arsitek

Plester dan Acian, tebal 25 mm, termasuk perekat, adukan kering,


kolom dan balok praktis, sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1102 & INT-2101)
- Vet Room m2 54.20 (54.20) 61,540 3,335,640 (3,335,640)
- Medicine Storage m2 26.39 (26.39) 61,540 1,624,164 (1,624,164)
- Toilet 1 Dokter m2 8.24 (8.24) 61,540 507,090 (507,090)
- Toilet 2 Umum m2 6.52 (6.52) 61,540 401,044 (401,044)

HT, Dinding Keramik HT 400x400 mm type Moonstone setara ex.


Indogress, termasuk perekat, adukan kering, sesuai spesifikasi dan
gambar pada : (reff.gbr : INT-1102 & INT-2102)

- Toilet 1 Dokter m2 19.02 2.93 288,430 5,485,939 845,100


- Toilet 2 Umum m2 14.71 16.52 288,430 4,243,382 4,764,287

Pengecatan dengan fin. cat Acrylic Emultion white setara ex


Pentalite Dulux, ICI termasuk peralatan dan perlengkapan sesuai
spesifikasi dan gambar pada : reff.gbr : INT-1102 & INT-2101)

- Lantai 1
- Vet Room m2 54.20 (2.09) 18,920 1,025,517 (39,634)
- Medicine Storage m2 26.39 (3.09) 18,920 499,337 (58,501)
- Toilet 1 Dokter m2 8.24 (5.15) 18,920 155,901 (97,438)
- Toilet 2 Umum m2 6.52 (2.52) 18,920 123,298 (47,694)

GC, Glass Cubicle clear Tempered 10mm, uk panjang 2.507mm x


tinggi 2000mm, termasuk hardware setara ex. KEND, Handle TX 10
B dan alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (reff.gbr : INT-1102 & INT-
2102)
- Toilet 1 Dokter unit 1.00 - 13,911,965 13,911,965 -

DAFTAR NO. IV.4.1. - PEKERJAAN DINDING 31,313,275 (501,817)


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.4 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp

DAFTAR NO. IV.4.2 - PEKERJAAN PINTU dan JENDELA

IV.4.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk


angkur, sealant, karet, kaca, pengelasan, pemasangan kolom
praktis sekeliling pintu & jendela, dan peralatan bantu yang
diperlukan dan bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

DAFTAR NO. IV.4.2 - PEKERJAAN PINTU dan JENDELA -


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.4 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.4.3. - PEKERJAAN LANTAI

IV.4.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping)
mortarmix sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

HOMOGENEOUS TILE

FL-01,Homogenious Tile 600x600mm ,Type Moonstone


setara ex. Indogress, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : INT-1102)
- Vet Room m2 22.33 0.31 377,325 8,425,886.17 116,741.19
- Medicine Storage m2 5.34 0.15 377,325 2,015,859.70 55,651.97

FL-2,Homogenious Tile 400x400mm, Type Moonstone setara


ex. Indogress, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1102)
- Toilet 1 Dokter m2 6.18 (0.03) 388,340 2,398,167.96 (10,653.64)
- Toilet 2 Umum m2 5.54 0.00 388,340 2,150,317.02 309.90

PLINT HOMOGENEOUS TILE

Homogenious Tile 100x600mm ,Type Moonstone setara


ex. Indogress, berikut adukan mortar, additiv, grouting nat
termasuk alat-alat bantu lainnya dengan peralatan
perlengkapan sesuai spesifikasi dan gambar pada :

- Vet Room m 20.20 (1.71) 20,601 416,147.70 (35,228.35)


- Medicine Storage m 9.00 - 20,601 185,412.34 -

Homogenious Tile 100x400mm ,Type Moonstone setara


ex. Indogress, berikut adukan mortar, additiv, grouting nat
termasuk alat-alat bantu lainnya dengan peralatan
perlengkapan sesuai spesifikasi dan gambar pada :

- Toilet 2 Umum m 7.10 (0.89) 13,734 97,513.16 (12,223.48)

WATER PROOFING

Continuous Waterproofing Coating, termasuk pada dinding


setinggi 300mm terpasang sesuai dengan spesifikasi dan
gambar pada : (Provisional)

- Toilet 1 Dokter m2 6.18 - 44,520 274,930.31 -


- Toilet 2 Umum m2 5.54 - 44,520 246,516.23 -
-

DAFTAR NO. IV.4.3. - PEKERJAAN LANTAI 16,210,751 114,598


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.4 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.4.4 - PEKERJAAN PLAFOND

IV.4.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang
equipment M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah


termasuk anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire
retardant dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A G, Gypsum Board, setara ex. Jaya Board, tebal 9mm tinggi plafond h=
2700mm dengan rangka hollow 40x40mm tebal 6 mm dan 40x20mm
tebal 6 mm termasuk cat finish Acrylic emulsion brilliant white setara ex
pentalite dulux, ICI dan alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada : (reff.gbr :
INT-1101 & INT-2102)

- Vet Room m2 22.33 0.01 124,090 2,771,124 1,047


- Medicine Storage m2 5.34 (0.00) 124,090 662,725 (84)

G, Gypsum Water resistant Board tebal 9mm, setara ex. Jaya Board,
tinggi plafond h= 2700mm dengan rangka hollow 40x40mm tebal 6 mm
dan 40x20mm tebal 6 mm termasuk cat finish Acrylic emulsion brilliant
white setara ex pentalite dulux, ICI dan alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1101 & INT-2102)

- Toilet 1 Dokter m2 5.56 0.00 150,250 835,053 337


- Toilet 2 Umum m2 4.12 0.14 150,250 618,654 21,411

G, Gypsum Water resistant Board tebal 9mm , setara ex. Jaya Board,
tinggi plafond h= 2550mm dengan rangka hollow 40x40mm tebal 6 mm
dan 40x20mm tebal 6 mm termasuk cat finish Acrylic emulsion brilliant
white setara ex pentalite dulux, ICI dan alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1101 & INT-2102)

- Toilet 1 Dokter m2 0.48 0.00 150,250 72,096 24


- Toilet 2 Umum m2 1.17 - 150,250 175,793 -

Drop Panel Ceilling 01, Gypsum Water resistant Board 9mm setara ex.
Jaya Board, tinggi h= 150mm dengan rangka hollow termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (reff.gbr : INT- 1101 & INT-2102)
- Toilet 1 Dokter m' 2.25 (0.88) 116,861 262,936 (102,837)
- Toilet 2 Umum m' 1.17 1.08 116,861 136,727 126,209

DAFTAR NO. IV.4.4 - PEKERJAAN PLAFOND 5,535,108 46,106


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.4 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.4.5. - PEKERJAAN SANITARY

IV.4.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan kelengkapan


material bantu (adukan, plesteran, acian, nad, sealan, grouting, bahan
bantu pengubung (doble niple) yang berhubungan dengan instalasi
ME dan lainnya berikut pemasangan dan perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

Toilet 1 Dokter

- Wastafel Set setara ex TOTO LW 641 NJ bh 1.00 3,644,970 3,644,970 -


- Closet Duduk Set setara ex. TOTO CW 821 J/SW 821 JP bh 1.00 3,385,100 3,385,100 -
- Floor Drain setara ex. TOTO TX 1 BN bh 2.00 385,700 771,400 -

- Tissue Holder setara ex. TX 720 ACRB bh 1.00 267,820 267,820 -

- Jetwasher setara ex. TOTO TX 403 SMCRB bh 1.00 581,660 581,660 -


- Shower set setara ex. TOTO TX 721 AN + TX 432 SHBR bh 1.00 2,122,450 2,122,450 -
- Faucet setara ex. TOTO TX 108LDN bh 1.00 1,301,490 1,301,490 -
- Robe Hook setara ex. TOTO (provisional) bh 1.00 186,400 186,400 -

Toilet Umum

- Wastafel Set setara ex TOTO LW549J bh 1.00 3,644,970 3,644,970 -


- Closet Duduk Set setara ex. TOTO CW860NJ/SW861JP bh 1.00 3,385,100 3,385,100 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 385,700 385,700 -
- Tissue Holder setara ex. TX 720 ACRB bh 1.00 267,820 267,820 -

- Jetwasher setara ex. TOTO TB 19 CSN bh 1.00 581,660 581,660 -


- Faucet setara ex. TOTO TX 108LDN bh 1.00 1,301,490 1,301,490 -
- Robe Hook setara ex. TOTO (provisional) bh 1.00 186,400 186,400 -

Ruang Kerja Dokter

- Wastafel Set setara ex TOTO LW549J bh 1.00 3,644,970 3,644,970 -


- Faucet setara ex. TOTO TX 108LDN bh 1.00 1,301,490 1,301,490 -

DAFTAR NO. IV.4.5. - PEKERJAAN SANITARY 26,960,890 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.4 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.4.6. - PEKERJAAN FIX FURNITURE

IV.4.6.0. Catatan Harga

I Harga satuan pekerjaan sudah termasuk fitting, accessories, alat


bantu, perlengkapan dan peralatan yang diperlukan

II Harga satuan Backdrop dinding panel HPL sudah termasuk


rangka, penyesuaian pola permukaan, bahan terbuang, biaya
pengeringan kayu, anti rayap, penyambungan dan finishing

III Harga satuan pada pekerjaan Movable Partition sudah termasuk


biaya untuk rangka, perkuatan struktur penggantung, sound
berrier, siap cat harus sudah termasuk biaya fabrikasi, handling
dan pemasangan, angkur-angkur, bracket, sealant dan back of
rod pada celah-celah horisontal dan vertikal untuk mencegah
kebocoran udara, air dan suara.

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat

V Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste)

VI Harga satuan sesuai dengan gambar dan spesifikasi teknis

BD1, Backdrop TV, ukuran 40mm x 1800mm x 2400mm dan uk.


250mm x 2100mm x 275mm, MDF finish HPL ex. ....., termasuk
alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-3101)

1 - Vet Room unit 1.00 8,982,190 8,982,190 -

DAFTAR NO. IV.4.6. - PEKERJAAN FIX FURNITURE 8,982,190 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. IV.4 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.4.7. - PEKERJAAN LOOSE FURNITURE

IV.4.7.0. Catatan Harga

I Harga satuan pekerjaan furniture sudah termasuk fitting,


accessories, alat bantu, perlengkapan dan peralatan yang
diperlukan

II Harga satuan sudah termasuk lampu, kabel, fitting dan sparing-


sparing sesuai gambar dari konsultan terkait

III Harga satuan Backdrop dinding panel HPL sudah termasuk


rangka, penyesuaian pola permukaan, bahan terbuang, biaya
pengeringan kayu, anti rayap, penyambungan dan finishing

IV Harga satuan pada pekerjaan Movable Partition sudah termasuk


biaya untuk rangka, perkuatan struktur penggantung, sound
berrier, siap cat harus sudah termasuk biaya fabrikasi, handling
dan pemasangan, angkur-angkur, bracket, sealant dan back of
rod pada celah-celah horisontal dan vertikal untuk mencegah
kebocoran udara, air dan suara.

V Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

VI Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste)

VII Harga satuan sesuai dengan gambar dan spesifikasi teknis

WD1, Meja kerja Dokter, ukuran 400mm x 650mm x 800mm


dan 1100mm x 700mm x 750mm, Top table with Plywood lapis
HPL, Kaki meja with tubular pipe leg dia 2", Drawer pedestal
plywood fin HPL bagian dalam melaminto, termasuk cable
management, accessories ex Hafelle atau setara dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (Reff.gbr : INT 3101)

1 - R Kerja Dokter unit 1 6,602,017 6,602,017 -

CR1, Credenza Dokter, ukuran 2250mm x 600mm x 850mm,


Top table with Plywood finish HPL, Drawer pedestal credenza
plywood fin HPL, termasuk wastafel dan kran, alaaccessories
ex Hafelle atau setara dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada : (Reff.gbr : INT
3101)

2 - R Kerja Dokter unit 1 5,723,779 5,723,779 -

WD2 & WD2', Meja Kerja Asisten dan Lemari Gantung,


ukuran WD2 panjang 2100mm x lebar 400mm x tinggi 730mm
ukuran dan WD2' panjang 2100mm x lebar 400mm x tinggi
730mm, Ukuran Lemari Gantung panjang 1800mm x lebar
300mm x tinggi 770mm, MDF finish HPL , termasuk accessories
ex Hafelle atau setara dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-
3101)

3 - R Kerja Dokter unit 1 6,619,234 6,619,234 -

SH1 SH2 SH3 SH4, Lemari Simpan, ukuran SH1 panjang


1200mm x lebar 520mm x tinggi 270mm, ukuran SH2 panjang
1200mm x lebar 520mm x tinggi 270mm, ukuran SH3 panjang
1045mm x lebar 520mm x tinggi 270mm, ukuran SH3 panjang
1050mm x lebar 500mm x tinggi 270mm, MDF finish HPL ,
termasuk accessories ex Hafelle atau setara dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(Reff.gbr : INT-3102)

4 - Storage unit 1 15,145,121 15,145,121 -

C1, Kursi Kerja Type S 220 LB slim series black ex. Morelli
atau setara, uk panjang 450mm x lebar 450mm x tinggi 610mm,
Mesh back foam seat fabric upholstery ex Ateja atau setara
terpasang sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-
3102 )
5 - R Kerja unit 1 1,028,372 1,028,372 -

C2, Kursi Hadap Type C 200 NCL WA Black/Lime Green ex


Morelli atau setara, uk panjang 480mm x lebar 400mm x tinggi
500mm, Mesh back foam seat fabric upholstery ex Ateja atau
setara terpasang sesuai spesifikasi dan gambar pada :
(Reff.gbr : INT-3102 )

6 - R Kerja unit 1 754,140 754,140 -

C3, Kursi Kerja Assist / Staf Type C 200 N Black/Lime Green


ex Morelli atau setara, uk panjang 480mm x lebar 400mm x
tinggi 610mm, Mesh back foam seat fabric upholstery ex Ateja
atau setara terpasang sesuai spesifikasi dan gambar pada :
(Reff.gbr : INT-3102 )
DAFTAR No. IV.4 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.4.7. - PEKERJAAN LOOSE FURNITURE


7 - R Kerja unit 1 903,721 903,721 -
DAFTAR No. IV.4 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IV.4.7. - PEKERJAAN LOOSE FURNITURE

DAFTAR NO. IV.4.7. - PEKERJAAN LOOSE FURNITURE 36,776,384 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.1 - PEKERJAAN STRUKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. V.1.1 - PEKERJAAN PONDASI TIANG PANCANG

V.1.1.0. Catatan Harga

Catatan Harga (Pricing Notes)


I Harga satuan tiang pancang sudah termasuk :

- harga tukang, alat dan material untuk pemancangan lengkap


termasuk waste

- keperluan galian tanah insidentil termasuk buangan tanah

penggantian tiang pancang yang rusak atau tiang pancang yang


- meleset atau tiang pancang yang gagal test

- topi pondasi dan sepatu pondasi tiang pancang

perbaikan tiang pancang yang menyimpang dari as bagian


-
bawah atau atas

- biaya test sudah termasuk pengadaan balok beton pemindahan


balok beton dan hal - hal lain

- pondasi tiang diperhitungkan net tidak ada biaya untuk


tambahan panjang tiang pada pie head

Kedalaman pemancangan dihitung dari muka tanah asli (peil +/-


2
0.000 pada gambar lokasi).

Harga satuan untuk pemancangan dan galian tanah sudah harus


diperhitungkan kemungkinan resiko longsor, pembuangan sisa-sisa
3
akar tanaman, sisa konstruksi bangunan lama yang masih
tertanam, pembersihan lumpur (wash boring), dan lain-lain.

Perbedaan berat yang dikeluarkan oleh pabrik yang satu dengan


4 pabrik yang lainnya untuk diameter yang sama menjadi tanggung
jawab pemborong.

Tabel berat yang dipakai dalam menghitung berat besi dalam


5
Daftar ini, adalah :
Diameter Ø Kg/m (polos)

6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.186
32 mm 6.313

Monitoring lapangan :

harga sudah termasuk observasi lapangan, test lapangan dan


-
test laboratorium

- harga sudah termasuk penyediaan contoh, analisa tanah,


termasuk persiapan test

- harga sudah termasuk penyelesaian laporan yang diperlukan


untuk pekerjaan tersebut diatas

- pengukuran dilokasi tiang sebelum dan sesudah pemancangan

- pembersihan lapangan, jalan sementara, lantai kerja, jalan


masuk yang mungkin diperlukan untuk pelaksanan
pemancangan

VOLUME PROVISIONAL (HARGA SATUAN TETAP)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-V.1.1 ( 167 ) PONDASI


DAFTAR No. V.1 - PEKERJAAN STRUKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. V.1.1 - PEKERJAAN PONDASI TIANG PANCANG

A PENGADAAN TIANG PANCANG

Pengadaan Tiang Pancang untuk pemancangan, sesuai spesifikasi


dan gambar
Ukuran 250 x 250 mm, 4D13 U-40, stirup Ø5 -75 pada atas dan
bawah, stirup Ø5 -150 pada tengah
kedalaman pemancangan = 11 m' m' 2,123 11,130 23,628,081 -
Jumlah titik pemancangan = 193 titik

B PEMANCANGAN TIANG PANCANG

Pemancangan Tiang Pancang dengan drop hammer 1500 kg untuk


Test Pile dan Reaction Pile (used pile), sesuai spesifikasi dan
gambar

Ukuran 250 x 250 mm, 4D13 U-40, stirup Ø5 -75 pada atas dan
bawah, stirup Ø5 -150 pada tengah
kedalaman pemancangan = 11 m' m' 2,123 155,814 330,793,130 -
Jumlah titik pemancangan = 193 titik

C PEK. SAMBUNGAN T. PANCANG


Pekerjaan sambungan tiang pancang beton ukuran 250 x 250
mm lengkap dgn alat - alat bantu berikut dgn pengelasan
terpasang sesuai spesifikasi dan gambar

Sambungan tiang pancang ukuran 250 x 250 mm nos 193 Rate only
- -
Note : Kedalaman tiang pancang 11 m'

D PEK. DOLLY

Pekerjaan Dolly tiang pancang ukuran 250 x 250 mm, dengan titik 193 Rate only
kedalaman = 2 ~ 3 m' - -

E PEK. TEST PONDASI TIANG PANCANG (USE PILE)

Test beban pendahuluan reaction pile pada tiang pancang dengan


bh 2.00
beban sebesar 250% x 3,5 ton 38,953,501 77,907,002 -

Test beban pancang + PDA (Pile Driving Analysis) test ttk 2.00 7,790,700
15,581,400 -

F PEKERJAAN LAIN - LAIN

Mobilisasi dan demobilisasi blok2 beton dan peralatan loading test


lainnya (2 x 75 ton) ls 1.00 8,903,657
8,903,657 -
Loading test 2 x 75 ton titik 1.00 38,953,501
38,953,501 -

DAFTAR No. V.1.1 - PEKERJAAN PONDASI TIANG PANCANG


Dipindahkan ke Penjumlahan Total 495,766,771 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-V.1.1 ( 168 ) PONDASI


DAFTAR No. V.1 - PEKERJAAN STRUKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. V.1.2 - PEKERJAAN TANAH

V.1.2.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat
kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko


longsoran, volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah


termasuk kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar


lokasi dan tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-V.1.2 ( 169 ) TANAH


DAFTAR No. V.1 - PEKERJAAN STRUKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. V.1.2 - PEKERJAAN TANAH


A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan m2 878.34 - 11,130 9,775,573 -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu
dan kelengkapannya pada:
- Pile Cap m3 123.77 - 55,640 6,886,803 -
- Tie Beam m3 64.32 94.58 55,640 3,578,934 5,262,470
- Bio Tank Pada :
Zoning Dormitory 1 m3 51.60 55,640 2,871,024 -
Zoning Dormitory 2 m3 51.60 55,640 2,871,024 -

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai, Tie Beam m3 7.68 2.22 272,340 2,090,443 604,944
- Pile Cap m3 9.40 0.21 272,340 2,559,940 56,627
- Bio Tank Pada :
Zoning Dormitory 1 m3 1.66 272,340 452,057 -
Zoning Dormitory 2 m3 1.66 272,340 452,057 -

Urugan tanah untuk mencapai level yang diinginkan, termasuk


pemadatan, dengan memaksimalkan tanah dipakai dari bekas galian
serta tanah dari luar site jika diperlukan sesuai spek dan gambar
- Pile Cap m3 114.37 - 55,648 6,364,697 -
- Tie Beam m3 54.92 - 55,648 3,056,361 -

D Pek. Lain - Lain


D.1 Pek. Bobok kepala tiang Pondasi Pancang

Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek


sesuai spesifikasi dan gambar

- Mini Pile diameter 25 cm ttk 193 2.00 83,472 16,110,055 166,944

D.2 Pekerjaan Anti rayap


Anti rayap pada Lantai dan dinding bawah , termasuk alat - alat bantu, m2 624.07 - 16,690 10,415,745 -
peralatan perlengkapan sesuai spesifikasi dan gambar

D.3 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan
sesuai spesifikasi dan gambar (Kontraktor diminta untuk melampirkan
breakdown harganya) Ls 1.00 - exclude - -

DAFTAR No. V.1.2 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 67,484,713 6,090,985

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-V.1.2 ( 170 ) TANAH


DAFTAR No. V.1 - PEKERJAAN STRUKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. V.1.3 - PEKERJAAN STRUKTUR BETON

V.1.3.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- V.1.3 ( 171 ) BETON


DAFTAR No. V.1 - PEKERJAAN STRUKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. V.1.3 - PEKERJAAN STRUKTUR BETON

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam m3 76.76 (27.27) 667,780 51,257,841 (18,212,284)
2) Pile cap m3 94.00 (89.19) 667,780 62,769,955 (59,562,032)
8) Bio Tank Pada :
- Zoning Dormitory 1 m3 0.83 667,780 554,224 -
- Zoning Dormitory 2 m3 0.83 667,780 554,224 -

B Beton mutu K-300 :


1) Pile cap m3 80.62 (13.44) 759,480 61,230,488 (10,207,407)
2) Tie beam m3 26.51 37.29 759,480 20,133,035 28,322,097
3) Pelat, pada:
- Lantai 1 m3 120.61 27.85 759,480 91,599,195 21,150,992
4) Bio Tank Pada :
- Zoning Dormitory 1 m3 16.54 759,480 12,558,944 -
- Zoning Dormitory 2 m3 16.54 759,480 12,558,944 -

C Beton mutu K-350 :


3) Pelat, pada:
- Lantai 2 m3 114.67 (5.45) 782,410 89,722,474 (4,263,762)
- Lantai 3 m3 114.67 (5.45) 782,410 89,722,474 (4,263,762)
- Lantai 4 m3 114.67 (5.92) 782,410 89,722,474 (4,632,422)
- Lantai Atap m3 114.94 5.81 782,410 89,927,727 4,548,539

4) Balok, pada:
- Lantai 2 m3 49.69 5.49 782,410 38,876,126 4,291,689
- Lantai 3 m3 49.69 5.49 782,410 38,876,126 4,291,689
- Lantai 4 m3 49.69 5.25 782,410 38,876,126 4,105,468
- Lantai Atap m3 50.11 10.76 782,410 39,203,076 8,415,932

5) Tangga ( Pelat, Bordes, Balok, dan Trap tangga ), pada:(Provisional)


Lantai 1
- Tangga as 16-17 / C-D m3 3.81 - 782,410 2,979,175 -
- Tangga as 0-1 / C-D m3 3.81 - 782,410 2,979,175 -
Lantai 2
- Tangga as 16-17 / C-D m3 3.81 - 782,410 2,979,175 -
- Tangga as 0-1 / C-D m3 3.81 - 782,410 2,979,175 -
Lantai 3
- Tangga as 16-17 / C-D m3 3.81 - 782,410 2,979,175 -
- Tangga as 0-1 / C-D m3 3.81 - 782,410 2,979,175 -

6) Kolom, pada:
- Lantai 1 m3 20.87 (2.63) 782,410 16,331,205 (2,060,046)
- Lantai 2 m3 20.87 (3.21) 782,410 16,331,205 (2,510,715)
- Lantai 3 m3 20.87 (5.09) 782,410 16,331,205 (3,979,142)
- Lantai 4 m3 20.87 (5.09) 782,410 16,331,205 (3,979,142)

7) Core wall, pada:


- Lantai 1 m3 24.69 6.55 782,410 19,313,791 5,125,568
- Lantai 2 m3 24.69 5.56 782,410 19,313,791 4,353,799
- Lantai 3 m3 24.69 2.21 782,410 19,313,791 1,726,466
- Lantai 4 m3 24.69 3.08 782,410 19,313,791 2,412,561

PEKERJAAN PEMBESIAN
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pile cap kg 18,974.37 (6,682.08) 8,859 168,084,458 (59,193,235)
2) Tie beam kg 9,270.81 8,959.29 8,859 82,125,454 79,365,900

3) Pelat, pada:
- Lantai 1 kg 13,935.96 2,098.14 8,859 123,451,699 18,586,330
- Lantai 2 kg 8,535.21 (581.59) 8,859 75,609,163 (5,152,034)
- Lantai 3 kg 8,535.21 (581.59) 8,859 75,609,163 (5,152,034)
- Lantai 4 kg 8,535.21 (615.90) 8,859 75,609,163 (5,455,979)
- Lantai Atap kg 11,367.39 (968.69) 8,859 100,698,050 (8,581,161)

4) Balok, pada:
- Lantai 2 kg 14,136.37 4,811.95 8,859 125,227,010 42,626,698
- Lantai 3 kg 14,136.37 4,811.95 8,859 125,227,010 42,626,698
- Lantai 4 kg 14,136.37 4,730.21 8,859 125,227,010 41,902,595
- Lantai Atap kg 14,358.25 6,543.91 8,859 127,192,519 57,969,203

5) Tangga ( Pelat, Bordes, Balok, dan Trap tangga), pada:(Provisional)

Lantai 1
- Tangga as 16-17 / C-D kg 701.34 - 8,859 6,212,779 -
- Tangga as 0-1 / C-D kg 701.34 - 8,859 6,212,779 -
Lantai 2
- Tangga as 16-17 / C-D kg 701.34 - 8,859 6,212,779 -
- Tangga as 0-1 / C-D kg 701.34 - 8,859 6,212,779 -

6) Kolom, pada:
- Lantai 1 kg 5,102.80 1,857.33 8,859 45,203,140 16,453,181
- Lantai 2 kg 5,102.80 (165.47) 8,859 45,203,140 (1,465,817)
- Lantai 3 kg 5,102.80 (379.82) 8,859 45,203,140 (3,364,607)
- Lantai 4 kg 5,102.80 (979.66) 8,859 45,203,140 (8,678,304)

7) Core wall, pada:


- Lantai 1 kg 2,246.04 7,345.64 8,859 19,896,527 65,071,347
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- V.1.3 ( 172 ) BETON
DAFTAR No. V.1 - PEKERJAAN STRUKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. V.1.3 - PEKERJAAN STRUKTUR BETON

- Lantai 2 kg 1,906.10 4,613.94 8,859 16,885,173 40,872,572


- Lantai 3 kg 1,906.10 355.63 8,859 16,885,173 3,150,320
- Lantai 4 kg 1,906.10 384.11 8,859 16,885,173 3,402,605

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- V.1.3 ( 173 ) BETON


DAFTAR No. V.1 - PEKERJAAN STRUKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. V.1.3 - PEKERJAAN STRUKTUR BETON

8) Bio Tank Pada :


- Zoning Dormitory 1 kg 2,480.44 8,859 21,972,942 -
- Zoning Dormitory 2 kg 2,480.44 8,859 21,972,942 -

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap m2 233.67 (46.91) 84,790 19,812,575 (3,977,257)
2) Sisi tegak Tie Beam m2 181.38 265.48 84,790 15,378,943 22,510,151
3) Bio Tank Pada :
- Zoning Dormitory 1 m2 7.34 84,790 622,359 -
- Zoning Dormitory 2 m2 7.34 84,790 622,359 -

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada:
- Lantai 1 (Bawah pelat, bawah balok dan sisi tegak) m2 833.96 179.83 100,570 83,871,528 18,085,128
- Lantai 2 (Bawah pelat, bawah balok dan sisi tegak) m2 867.91 (8.24) 100,570 87,285,613 (828,799)
- Lantai 3 (Bawah pelat, bawah balok dan sisi tegak) m2 867.91 (8.24) 100,570 87,285,613 (828,799)
- Lantai 4 (Bawah pelat, bawah balok dan sisi tegak) m2 867.91 (11.64) 100,570 87,285,613 (1,170,729)
- Lantai Atap (Bawah pelat, bawah balok dan sisi tegak) m2 924.40 64.56 100,570 92,967,315 6,492,371

2) Kolom, pada:
- Lantai 1 m2 208.44 (13.50) 129,920 27,080,525 (1,753,920)
- Lantai 2 m2 208.44 (19.66) 129,920 27,080,525 (2,553,708)
- Lantai 3 m2 208.44 (31.80) 129,920 27,080,525 (4,131,456)
- Lantai 4 m2 208.44 (31.80) 129,920 27,080,525 (4,131,456)

3) Balok (sisi tegak), pada:


- Lantai 2 m2 346.69 37.86 104,000 36,056,022 3,937,567
- Lantai 3 m2 346.69 37.86 104,000 36,056,022 3,937,567
- Lantai 4 m2 346.69 36.20 104,000 36,056,022 3,765,039
- Lantai Atap m2 350.04 74.17 104,000 36,403,694 7,713,781

4) Core wall, pada:


- Lantai 1 m2 144.43 75.21 112,040 16,182,161 8,426,304
- Lantai 2 m2 144.43 68.27 112,040 16,182,161 7,649,195
- Lantai 3 m2 144.43 50.79 112,040 16,182,161 5,690,736
- Lantai 4 m2 144.43 57.16 112,040 16,182,161 6,403,982

5) Tangga: ( Plat, Balok, dan Trap tangga, ), pada:(Provisional)


- Lantai 1 m2 25.80 - 104,000 2,683,221 -
- Lantai 2 m2 25.80 - 104,000 2,683,221 -
- Lantai 3 m2 25.80 - 104,000 2,683,221 -
- Lantai 4 m2 25.80 - 104,000 2,683,221 -

6) Bio Tank Pada :


- Zoning Dormitory 1 m2 108.24 104,000 11,256,482 -
- Zoning Dormitory 2 m2 108.24 104,000 11,256,482 -

PEKERJAAN LAIN-LAIN (Provisional)

Waterproofing membrane termasuk screed tebal rata-rata 50 mm +


A wire mesh M6 termasuk peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar: (Provisional)

1) lantai atap
- Atap + Atap Tangga m2 950.20 - 160,780 152,773,838 -

Water Proofing Integral termasuk sesuai dengan gambar dan


B
spesifikasi, pada :
1) Pelat lantai 1 m3 120.61 27.85 100,170 12,081,281 2,789,665
2) Pile Cap m3 80.62 (13.44) 100,170 8,075,865 (1,346,284)

DAFTAR NO. V.1.3 - PEKERJAAN STRUKTUR BETON


Dipindahkan ke Penjumlahan Total 3,511,752,041 366,737,441

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- V.1.3 ( 174 ) BETON


DAFTAR No. V.1 - PEKERJAAN STRUKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. V.1.4 - PEKERJAAN STRUKTUR BAJA

V.1.4.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang diperlukan, seperti :
pengelasan, pembuatan lubang-lubang baut, perapihan dengan gerinda,
penyediaan peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi dan pengiriman


ke lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan


sesuai spesifikasi

I Tangga baja
1) WF 250 x 125 x 6 x 9 Kg 284.16 18,364 5,218,256 -
2) HB 150 x 150 x 7 x 10 Kg 78.75 18,364 1,446,149 -
3) Plate 6 mm Kg 49.13 17,807 874,890 -
4) Base Plate 12 mm Kg 12.26 17,807 218,320 -
5) Plate 9 mm Kg 46.73 17,807 832,224 -
6) Stifner 9 mm Kg 14.20 17,807 252,875 -
7) Plate 12 mm Kg 1,133.93 17,807 20,192,293 -
8) Angkur M16 L = 500mm Bh 18.00 222,591 4,006,646 -
9) Baut M16 Bh 18.00 31,163 560,930 -
10) Nonshrink Grout, T = 25 mm, Uk 190 x 190mm titik 1.00 38,954 38,954 -
10) Nonshrink Grout, T = 25 mm, Uk 600 x 200mm titik 1.00 66,777 66,777 -
11) Nonshrink Grout, T = 25 mm, Uk 310 x 200mm titik 1.00 44,518 44,518 -
12) Cat Dasar (Zincromate) Kg 192.00 3,339 641,063 -
13) Cat Finish Kg 192.00 3,339 641,063

DAFTAR NO. V.1.4 - PEKERJAAN STRUKTUR BAJA 35,034,959 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- V.1.4 ( 175 ) BAJA


DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.2.1. - PEKERJAAN DINDING

V.2.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah termasuk


adukan biasa atau drymix, kolom praktis, ringbalk, angkur, sparing
dan semua pekerjaan bantu yang berhubungan dengan pekerjaan
dinding tersebut.

II
Harga satuan plesteran biasa atau drymix sudah termasuk acian,
skonengan, tali air , ketrikan atau bobokan beton maupun bata ,
kawat ayam (jika diperlukan) dan semua pekerjaan bantu yang
berhubungan dengan plesteran. Volume plesteran dan acian
sudah ditambahkan 10cm di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit, marmer,


keramik, porselin) sudah termasuk adukan, cor beton,perekat
(calbond), angkur, kawat pengikat alumunium fixing pada dinding
dengan ketinggian lebih dari 2m, pemotongan, pinggulan, adu
manis, naad, dan alat bantu lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk dinding


kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian


cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi.

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. Primacon,


termasuk dinding penebalan,urinoir, perekat, adukan kering kolom
dan balok
- Lantai 1 praktis sesuai spesifikasi dan gambar : m2 1,565.53 42.19 103,480 162,001,043 4,365,461
- Lantai 2 m2 1,790.69 70.72 103,480 185,300,614 7,318,517
- Lantai 3 m2 1,790.69 70.72 103,480 185,300,614 7,318,517
- Lantai 4 m2 1,790.69 70.72 103,480 185,300,614 7,318,517

II PEK. PELAPIS DINDING

A Plesteran dan Acian, Plesteran halus berikut acian halus,


termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :
- Lantai 1 m2 1,708.35 (135.90) 61,540 105,131,720 (8,363,267)
- Lantai 2 m2 1,569.22 578.86 61,540 96,570,082 35,623,336
- Lantai 3 m2 1,569.22 578.86 61,540 96,570,082 35,623,336
- Lantai 4 m2 1,569.22 578.86 61,540 96,570,082 35,623,336
- Area Exterior m2 1,053.32 1,085.30 61,540 64,821,128 66,789,547
Homogeneous Tile 400x400 setara ex Indogress tipe standar,
B
sesuai spesifikasi dan gambar ;
- Lantai 1
Toilet
- Room as A-B/0-1 m2 - Included Interior
- Room as A-B/1-2 m2 - Included Interior
- Room as A-B/2-3 m2 - Included Interior
- Room as A-B/3-4 m2 - Included Interior
- Room as A-B/4-5 m2 - Included Interior
- Room as A-B/5-6 m2 - Included Interior
- Room as A-B/6-7 m2 - Included Interior
- Room as C-D/1-2 m2 - Included Interior
- Room as C-D/2-3 m2 - Included Interior
- Room as C-D/3-4 m2 - Included Interior
- Room as C-D/4-5 m2 - Included Interior
- Room as C-D/5-6 m2 - Included Interior
- Room as C-D/6-7 m2 - Included Interior
Homogeneous Tile 400x400 setara ex Indoggress tipe standar,
B
sesuai spesifikasi dan gambar ;-Lanjutan
- Lantai 1
Locker staff male m2 - Included Interior
Shower staff male m2 - Included Interior
Locker staff Female m2 - Included Interior
Shower staff Female m2 - Included Interior
Male Public Toilet as C-D/10-11 m2 - Included Interior
Female Public Toilet as C-D/10-11 m2 - Included Interior
- Lantai 2
Toilet
- Room as A-B/0-1 m2 - Included Interior
- Room as A-B/1-2 m2 - Included Interior
- Room as A-B/2-3 m2 - Included Interior
- Room as A-B/3-4 m2 - Included Interior
- Room as A-B/4-5 m2 - Included Interior
- Room as A-B/5-6 m2 - Included Interior
- Room as A-B/6-7 m2 - Included Interior
- Room as A-B/12-13 m2 - Included Interior
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.2.1. - PEKERJAAN DINDING


- Room as A-B/13-14 m2 - Included Interior
- Room as A-B/14-15 m2 - Included Interior
- Room as A-B/15-16 m2 - Included Interior
- Room as A-B/16-17 m2 - Included Interior
- Room as C-D/1-2 m2 - Included Interior
- Room as C-D/2-3 m2 - Included Interior
- Room as C-D/3-4 m2 - Included Interior
- Room as C-D/4-5 m2 - Included Interior
- Room as C-D/5-6 m2 - Included Interior
- Room as C-D/6-7 m2 - Included Interior
- Room as C-D/10-11 m2 - Included Interior
- Room as C-D/11-12 m2 - Included Interior
- Room as C-D/12-13 m2 - Included Interior
- Room as C-D/13-14 m2 - Included Interior
- Room as C-D/14-15 m2 - Included Interior
- Room as C-D/15-16 m2 - Included Interior
- Lantai 3
Toilet
- Room as A-B/0-1 m2 - Included Interior
- Room as A-B/1-2 m2 - Included Interior
- Room as A-B/2-3 m2 - Included Interior
- Room as A-B/3-4 m2 - Included Interior
- Room as A-B/4-5 m2 - Included Interior
- Room as A-B/5-6 m2 - Included Interior
- Room as A-B/6-7 m2 - Included Interior
- Room as A-B/12-13 m2 - Included Interior
- Room as A-B/13-14 m2 - Included Interior
- Room as A-B/14-15 m2 - Included Interior
- Room as A-B/15-16 m2 - Included Interior
- Room as A-B/16-17 m2 - Included Interior
- Room as C-D/1-2 m2 - Included Interior
- Room as C-D/2-3 m2 - Included Interior
- Room as C-D/3-4 m2 - Included Interior
- Room as C-D/4-5 m2 - Included Interior
- Room as C-D/5-6 m2 - Included Interior
- Room as C-D/6-7 m2 - Included Interior
- Room as C-D/10-11 m2 - Included Interior
- Room as C-D/11-12 m2 - Included Interior
- Room as C-D/12-13 m2 - Included Interior
- Room as C-D/13-14 m2 - Included Interior
- Room as C-D/14-15 m2 - Included Interior
- Room as C-D/15-16 m2 - Included Interior
- Lantai 4
Toilet
- Room as A-B/0-1 m2 - Included Interior
- Room as A-B/1-2 m2 - Included Interior
- Room as A-B/2-3 m2 - Included Interior
- Room as A-B/3-4 m2 - Included Interior
Homogeneous Tile 400x400 setara ex Indoggress tipe standar,
B
sesuai spesifikasi dan gambar ;-Lanjutan
- Lantai 4
Toilet
- Room as A-B/4-5 m2 - Included Interior
- Room as A-B/5-6 m2 - Included Interior
- Room as A-B/6-7 m2 - Included Interior
- Room as A-B/12-13 m2 - Included Interior
- Room as A-B/13-14 m2 - Included Interior
- Room as A-B/14-15 m2 - Included Interior
- Room as A-B/15-16 m2 - Included Interior
- Room as A-B/16-17 m2 - Included Interior
- Room as C-D/1-2 m2 - Included Interior
- Room as C-D/2-3 m2 - Included Interior
- Room as C-D/3-4 m2 - Included Interior
- Room as C-D/4-5 m2 - Included Interior
- Room as C-D/5-6 m2 - Included Interior
- Room as C-D/6-7 m2 - Included Interior
- Room as C-D/10-11 m2 - Included Interior
- Room as C-D/11-12 m2 - Included Interior
- Room as C-D/12-13 m2 - Included Interior
- Room as C-D/13-14 m2 - Included Interior
- Room as C-D/14-15 m2 - Included Interior
- Room as C-D/15-16 m2 - Included Interior

C Pengecatan dengan fin. cat acrylic emultion setara ex.Jotun tipe


standar, termasuk peralatan dan perlengkapan sesuai spesifikasi
dan gambar pada :

- Lantai 1
Living room + bedroom
- Room as A-B/0-1 m2 36.77 0.74 18,360 675,015 13,500
- Room as A-B/1-2 m2 35.99 0.72 18,360 660,715 13,214
- Room as A-B/2-3 m2 35.90 0.72 18,360 659,148 13,183
- Room as A-B/3-4 m2 36.05 0.72 18,360 661,957 13,239
- Room as A-B/4-5 m2 35.97 0.72 18,360 660,426 13,209
- Room as A-B/5-6 m2 36.05 0.72 18,360 661,957 13,239
- Room as A-B/6-7 m2 36.49 0.73 18,360 669,932 13,399
- Room as C-D/1-2 m2 36.05 0.72 18,360 661,875 13,238
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.2.1. - PEKERJAAN DINDING


- Room as C-D/2-3 m2 36.06 0.72 18,360 662,024 13,240
- Room as C-D/3-4 m2 36.05 0.72 18,360 661,891 13,238
- Room as C-D/4-5 m2 36.06 0.72 18,360 662,024 13,240
- Room as C-D/5-6 m2 36.05 0.72 18,360 661,875 13,237
- Room as C-D/6-7 m2 36.42 0.73 18,360 668,604 13,372
Foyer
- Room as A-B/0-1 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/1-2 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/2-3 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/4-5 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/6-7 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/1-2 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/2-3 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/4-5 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/6-7 m2 12.01 0.24 18,360 220,452 4,409
Ruang panel m2 32.86 0.66 18,360 603,339 12,067
Lobby Lift m2 14.19 (14.19) 18,360 260,510 (260,510)
Dining Area as A-B / 9-12 m2 40.08 - 18,360 735,812 -
Kitchen Area m2 57.45 (3.24) 18,360 1,054,855 (59,505)
Dry Storage m2 24.98 - 18,360 458,614 -
Cold Storage m2 21.23 - 18,360 389,810 -
Linen Storage m2 32.80 - 18,360 602,287 -
Locker staff Female m2 20.59 (20.59) 18,360 378,032 (378,032)
Shower staff Female m2 11.38 (11.38) 18,360 208,983 (208,983)
Reception m2 91.58 (91.58) 18,360 1,681,464 (1,681,464)

C Pengecatan dengan fin. cat acrylic emultion setara ex.Jotun tipe


standar, termasuk peralatan dan perlengkapan sesuai spesifikasi
dan gambar pada : -Lanjutan
- Lantai 1
Drugstore as C-D/10-11 m2 35.41 11.13 18,360 650,207 204,378
Room as C-D/11-12 m2 53.05 (19.70) 18,360 974,004 (361,606)
Office Management as C-D / 12-14 m2 74.72 (1.55) 18,360 1,371,854 (28,434)
Mushola m2 73.93 (4.35) 18,360 1,357,294 (79,934)
Time Keeper & Security Office as C-C'/14-15 m2 47.05 - 18,360 863,830 -
Foyer Public Toilet m2 12.30 2.50 18,360 225,743 45,985
Staff Dining m2 27.90 18.79 18,360 512,227 345,038
Koridor m2 207.89 (31.67) 18,360 3,816,883 (581,484)

- Lantai 2
Living room + bedroom
- Room as A-B/0-1 m2 36.55 0.73 18,360 671,025 13,421
- Room as A-B/1-2 m2 35.68 37.11 18,360 655,056 681,258
- Room as A-B/2-3 m2 35.67 37.10 18,360 654,970 681,168
- Room as A-B/3-4 m2 35.68 0.71 18,360 655,036 13,101
- Room as A-B/4-5 m2 35.68 0.71 18,360 655,036 13,101
- Room as A-B/5-6 m2 35.68 0.71 18,360 655,032 13,101
- Room as A-B/6-7 m2 36.11 0.72 18,360 662,973 13,259
- Room as A-B/12-13 m2 35.68 0.71 18,360 655,065 13,101
- Room as A-B/13-14 m2 35.68 0.71 18,360 655,022 13,100
- Room as A-B/14-15 m2 35.68 0.71 18,360 655,023 13,100
- Room as A-B/15-16 m2 35.68 0.71 18,360 655,022 13,100
- Room as A-B/16-17 m2 36.55 0.73 18,360 670,968 13,419
- Room as C-D/1-2 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/2-3 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/3-4 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/4-5 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/5-6 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/6-7 m2 36.11 0.72 18,360 663,022 13,260
- Room as C-D/10-11 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/11-12 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/12-13 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/13-14 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/14-15 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/15-16 m2 35.68 0.71 18,360 655,036 13,101
Foyer
- Room as A-B/0-1 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/1-2 m2 12.01 12.49 18,360 220,452 229,270
- Room as A-B/2-3 m2 12.01 12.49 18,360 220,452 229,270
- Room as A-B/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/4-5 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/6-7 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/12-13 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/13-14 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/14-15 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/15-16 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/16-17 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/1-2 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/2-3 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/4-5 m2 12.01 0.24 18,360 220,452 4,409
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.2.1. - PEKERJAAN DINDING


- Room as C-D/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/6-7 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/10-11 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/11-12 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/12-13 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/13-14 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/14-15 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/15-16 m2 12.01 0.24 18,360 220,452 4,409
Ruang panel m2 32.86 0.66 18,360 603,339 12,067
Lobby Lift m2 13.46 (13.46) 18,360 247,194 (247,194)
Lounge m2 27.33 (27.33) 18,360 501,724 (501,724)
Koridor m2 214.36 (13.66) 18,360 3,935,599 (250,747)
Void m2 38.49 (13.56) 18,360 706,633 (248,955)
C Pengecatan dengan fin. cat acrylic emultion setara ex.Jotun tipe
standar, termasuk peralatan dan perlengkapan sesuai spesifikasi
dan gambar pada : -Lanjutan

- Lantai 3
Living room + bedroom
- Room as A-B/0-1 m2 36.55 0.73 18,360 671,025 13,421
- Room as A-B/1-2 m2 35.68 37.11 18,360 655,056 681,258
- Room as A-B/2-3 m2 35.67 37.10 18,360 654,970 681,168
- Room as A-B/3-4 m2 35.68 0.71 18,360 655,036 13,101
- Room as A-B/4-5 m2 35.68 0.71 18,360 655,036 13,101
- Room as A-B/5-6 m2 35.68 0.71 18,360 655,032 13,101
- Room as A-B/6-7 m2 36.11 0.72 18,360 662,973 13,259
- Room as A-B/12-13 m2 35.68 0.71 18,360 655,065 13,101
- Room as A-B/13-14 m2 35.68 0.71 18,360 655,022 13,100
- Room as A-B/14-15 m2 35.68 0.71 18,360 655,023 13,100
- Room as A-B/15-16 m2 35.68 0.71 18,360 655,022 13,100
- Room as A-B/16-17 m2 36.55 0.73 18,360 670,968 13,419
- Room as C-D/1-2 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/2-3 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/3-4 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/4-5 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/5-6 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/6-7 m2 36.11 0.72 18,360 663,022 13,260
- Room as C-D/10-11 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/11-12 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/12-13 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/13-14 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/14-15 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/15-16 m2 35.68 0.71 18,360 655,036 13,101
Foyer
- Room as A-B/0-1 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/1-2 m2 12.01 12.49 18,360 220,452 229,270
- Room as A-B/2-3 m2 12.01 12.49 18,360 220,452 229,270
- Room as A-B/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/4-5 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/6-7 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/12-13 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/13-14 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/14-15 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/15-16 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/16-17 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/1-2 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/2-3 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/4-5 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/6-7 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/10-11 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/11-12 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/12-13 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/13-14 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/14-15 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/15-16 m2 12.01 0.24 18,360 220,452 4,409
Ruang panel m2 32.86 0.66 18,360 603,339 12,067
Lobby Lift m2 13.46 (13.46) 18,360 247,194 (247,194)
Lounge m2 27.33 (27.33) 18,360 501,724 (501,724)
Koridor m2 214.36 (13.66) 18,360 3,935,599 (250,747)
Void m2 38.49 11.37 18,360 706,633 208,723

- Lantai 4
Living room + bedroom
- Room as A-B/0-1 m2 36.55 0.73 18,360 671,025 13,421
- Room as A-B/1-2 m2 35.68 37.11 18,360 655,056 681,258
- Room as A-B/2-3 m2 35.67 37.10 18,360 654,970 681,168
- Room as A-B/3-4 m2 35.68 0.71 18,360 655,036 13,101
- Room as A-B/4-5 m2 35.68 0.71 18,360 655,036 13,101

C Pengecatan dengan fin. cat acrylic emultion setara ex.Jotun tipe


standar, termasuk peralatan dan perlengkapan sesuai spesifikasi
dan gambar pada : -Lanjutan
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.2.1. - PEKERJAAN DINDING


- Lantai 4
Living room + bedroom
- Room as A-B/5-6 m2 35.68 0.71 18,360 655,032 13,101
- Room as A-B/6-7 m2 36.11 0.72 18,360 662,973 13,259
- Room as A-B/12-13 m2 35.68 0.71 18,360 655,065 13,101
- Room as A-B/13-14 m2 35.68 0.71 18,360 655,022 13,100
- Room as A-B/14-15 m2 35.68 0.71 18,360 655,023 13,100
- Room as A-B/15-16 m2 35.68 0.71 18,360 655,022 13,100
- Room as A-B/16-17 m2 36.55 0.73 18,360 670,968 13,419
- Room as C-D/1-2 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/2-3 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/3-4 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/4-5 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/5-6 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/6-7 m2 36.11 0.72 18,360 663,022 13,260
- Room as C-D/10-11 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/11-12 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/12-13 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/13-14 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/14-15 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/15-16 m2 35.68 0.71 18,360 655,036 13,101
Foyer
- Room as A-B/0-1 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/1-2 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/2-3 m2 12.01 12.49 18,360 220,452 229,270
- Room as A-B/3-4 m2 12.01 12.49 18,360 220,452 229,270
- Room as A-B/4-5 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/6-7 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/12-13 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/13-14 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/14-15 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/15-16 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/16-17 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/1-2 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/2-3 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/4-5 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/6-7 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/10-11 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/11-12 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/12-13 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/13-14 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/14-15 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/15-16 m2 12.01 0.24 18,360 220,452 4,409
Ruang panel m2 32.86 0.66 18,360 603,339 12,067
Lobby Lift m2 13.46 (13.46) 18,360 247,194 (247,194)
Lounge m2 27.33 (27.33) 18,360 501,724 (501,724)
Koridor m2 214.36 (13.66) 18,360 3,935,599 (250,747)
Void m2 38.49 11.37 18,360 706,633 208,723

D Cat minyak ex. ... Tipe standar, termasuk peralatan dan


perlengkapan sesuai spesifikasi dan gambar pada :

- Lantai 1
Fire Stairs As. 00-01 m2 72.73 (12.00) 33,390 2,428,538 (400,767)
Fire Stairs As. 16-17 m2 76.41 (17.31) 33,390 2,551,213 (577,984)
- Lantai 2
Fire Stairs As. 00-01 m2 72.73 (12.00) 33,390 2,428,538 (400,767)
Fire Stairs As. 16-17 m2 76.41 (17.31) 33,390 2,551,213 (577,984)
- Lantai 3
Fire Stairs As. 00-01 m2 72.73 (12.00) 33,390 2,428,538 (400,767)
Fire Stairs As. 16-17 m2 76.41 (17.31) 33,390 2,551,213 (577,984)

D Cat minyak ex. ... Tipe standar, termasuk peralatan dan


perlengkapan sesuai spesifikasi dan gambar pada :- Lanjutan

- Lantai 4
Fire Stairs As. 00-01 m2 72.73 (12.00) 33,390 2,428,538 (400,767)
Fire Stairs As. 16-17 m2 76.41 (17.31) 33,390 2,551,213 (577,984)

E Skim coat pada permukaan kolom beton, termasuk peralatan dan


perlengkapan sesuai spesifikasi dan gambar pada :
- Lantai 1 m2 102.94 9.84 33,950 3,494,778 334,039
- Lantai 2 m2 115.32 11.53 33,950 3,915,216 391,522
- Lantai 3 m2 115.32 11.53 33,950 3,915,216 391,522
- Lantai 4 m2 115.32 11.53 33,950 3,915,216 391,522
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.2.1. - PEKERJAAN DINDING

DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY 1,321,526,231 190,235,389


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.2.2 - PEKERJAAN PINTU dan JENDELA

V.2.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk


angkur, sealant, karet, kaca, pengelasan, pemasangan kolom
praktis sekeliling pintu & jendela, dan peralatan bantu yang
diperlukan dan bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU BAJA
Pintu Baja P10 terdiri dari 1 daun pintu ukuran 2200x4300mm
kusen besi finish powder coating + kaca tebal kaca 6 mm, fire
rated 2 hours, lengkap terpasang termasuk, hardware,
Fire stair
- Lantai 1 unit 2.00 - 10,127,910 20,255,820 -

Hardware :
Lockset Wilka Art - 8379/855 HF BKSS set 1.00 1.00 Include
Hinges gracia BB 4,5"x4"x3 mm SS bh 3.00 3.00 Include
Door closer dorma TS 300 EN 4 RA silver bh 1.00 1.00 Include

Pintu Baja PS1 terdiri dari 1 daun pintu ukuran 500x1200 mm,
kusen besi finish powder coating, lengkap terpasang termasuk,
hardware,
Shaft accesories dan perlengkapan bantu lainnya sesuai
- Lantai 1 unit 15.00 (15.00) 4,173,589 62,603,841 (62,603,841)
- Lantai 2 unit 15.00 (15.00) 4,173,589 62,603,841 (62,603,841)
- Lantai 3 unit 15.00 (15.00) 4,173,589 62,603,841 (62,603,841)
- Lantai 4 unit 15.00 (15.00) 4,173,589 62,603,841 (62,603,841)

Hardware :
Ring handle art-8-3 SS bh 1.00 (1.00) Include
Shaft door art -542 Nickel bh 1.00 (1.00) Include
Anak kunci shaft door art-543 Nickel bh 1.00 (1.00) Include
Hinges Gracia BB 4"x3"x3 mm SS bh 2.00 (2.00) Include

B PINTU KACA
Pintu Kaca P1 terdiri dari 1 pintu dan 2 daun pintu Stainless
Panel Patch, ukuran 7200x6060, Kaca Tempered 12mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan
Main Entrance
- Lantai 1 unit 1.00 - 34,888,883 34,888,883 -

Hardware :
Pull handle art-243/600 mm SS psg 2.00 - Include
Patch fitting Dorma PT10,PT20 US 10 + Cylinder set 2.00 - Include
Patch fitting Dorma PT40 bh 2.00 - Include
Floor hinges Dorma BTS 84 T/ Complete SS set 2.00 - Include

Pintu Kaca P2 terdiri dari 1 pintu dan 2 daun pintu Melamic


Kusen Alumunium 3" powder coating ukuran 3580x4800, solid
wood + kaca 6mm lengkap terpasang termasuk, hardware,

Main Entrance
- Lantai 1 unit 2.00 - 8,837,002 17,674,005 -
- Lantai 2 unit 2.00 - 8,837,002 17,674,005 -
- Lantai 3 unit 2.00 - 8,837,002 17,674,005 -
- Lantai 4 unit 2.00 - 8,837,002 17,674,005 -

Hardware :
Lever handle art-352 SS psg 1.00 7.00 Include
Lockcase Wilka art-1438.30 SN + striking plate bh 1.00 7.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 7.00 Include
Hinges Gracia BB 4"x3"x2" mm silver bh 6.00 42.00 Include
Flush bolt Rioby 456/250 mm silver set 1.00 7.00 Include
Door closer Dorma TS 68 RA silver bh 1.00 7.00 Include

Pintu Kaca P9 terdiri dari 1 daun pintu ukuran 1693x4800, kaca


tempered + engsel pivot, sanblast, tebal kaca 12 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan
guest bathroom
- Lantai 1 unit 13.00 - 10,494,955 136,434,410 -
- Lantai 2 unit 26.00 - 10,494,955 272,868,820 -
- Lantai 3 unit 26.00 - 10,494,955 272,868,820 -
- Lantai 4 unit 26.00 - 10,494,955 272,868,820 -
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.2.2 - PEKERJAAN PINTU dan JENDELA

C PINTU KAYU
Pintu kayu P3 terdiri dari 1 daun pintu Kusen Alumunium 3" finish
powder coating ukuran 1880x4800, plywood + rangka kayu finish
HPL lengkap terpasang termasuk, hardware, accesories dan
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.2.2 - PEKERJAAN PINTU dan JENDELA


panel & office
- Lantai 1 unit 6.00 (1.00) 3,484,947 20,909,683 (3,484,947)
- Lantai 2 unit 1.00 - 3,484,947 3,484,947 -
- Lantai 3 unit 1.00 - 3,484,947 3,484,947 -
- Lantai 4 unit 1.00 - 3,484,947 3,484,947 -

Hardware :
Lever handle art-306 SS psg 1.00 7.00 Include
Lockcase Wilka art-1490.55 SN bh 1.00 7.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 7.00 Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 21.00 Include
Door closer Dorma TS 68 RA silver bh 1.00 7.00 Include

Pintu Kayu P4 terdiri dari 1 daun pintu Kusen Alumunium 3"


finish powder coating ukuran 1780x4800, plywood + rangka kayu
finish
powder HPL lengkap
& loker staf terpasang termasuk, hardware, accesories
- Lantai 1 unit 4.00 - 3,937,086 15,748,344 -

Hardware :
Lever handle art-306 SS psg 1.00 3.00 Include
Lockcase Wilka art-1490.55 SN bh 1.00 3.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 3.00 Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 9.00 Include
Door closer Dorma TS 68 RA silver bh 1.00 3.00 Include

Pintu Kayu P5 terdiri dari 1 daun pintu kusen Alumunium 3" finish
powder coating ukuran 1780x4800, plywood + rangka kayu +
lubang
kitchen kaca finish Hpl, tebal kaca 6 mm lengkap terpasang
- Lantai 1 unit 1.00 - 3,839,702 3,839,702 -

Hardware :
Lever handle art-306 SS psg 1.00 - Include
Lockcase Wilka art-1490.55 SN bh 1.00 - Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 - Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 - Include
Door closer Dorma TS 68 RA silver bh 1.00 - Include

Pintu Kayu P6 terdiri dari 1 pintu dan 2 daun pintu kusen


Alumunium 3" powder coating ukuran 3580x4800, plywood +
rangka
kitchen kayu + lubang kaca finish Hpl, tebal kaca 6 mm lengkap
- Lantai 1 unit 1.00 - 6,594,271 6,594,271 -

Hardware :
Lever handle art-306 SS psg 1.00 - Include
Lockcase Wilka art-1490.55 SN bh 1.00 - Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 - Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 - Include
Flush bolt gracia 200/350 mm SS bh 1.00 - Include
Door closer Dorma TS 68 RA silver bh 1.00 - Include

Pintu Kayu P7 terdiri dari 1 daun pintu kusen Alumunium 3" finish
powder coating ukuran 1780x4800, plywood + rangka kayu finish
Hpl lengkap
kitchen, dry &terpasang termasuk, hardware, accesories dan
cold stroge
- Lantai 1 unit 2.00 - 3,477,991 6,955,982 -
Hardware :
Lever handle art-306 SS psg 1.00 1.00 Include
Lockcase Wilka art-1490.55 SN bh 1.00 1.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 1.00 Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 3.00 Include
Door closer Dorma TS 68 RA silver bh 1.00 1.00 Include

Pintu Kayu P8 terdiri dari 1 daun pintu kusen Alumunium 3"


powder coating ukuran 1880x4800, plywood + rangka kayu finish
Hpl lengkap terpasang termasuk, hardware, accesories dan
Guestroom
- Lantai 1 unit 13.00 - 3,484,947 45,304,313 -
- Lantai 2 unit 26.00 - 3,484,947 90,608,626 -
- Lantai 3 unit 26.00 - 3,484,947 90,608,626 -
- Lantai 4 unit 26.00 - 3,484,947 90,608,626 -

Hardware :
Lever handle art-345 SS psg 1.00 90.00 Include
Lockcase Wilka art-1490.55 SN bh 1.00 90.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 90.00 Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 270.00 Include
Door stopper Dorma art-601 SN bh 1.00 90.00 Include

B JENDELA

Jendela J1 Alumunium powder coating ukuran 3000x4600 ,


tebal kaca 6 mm lengkap terpasang termasuk, hardware,
accesories dan perlengkapan bantu lainnya sesuai spesifikasi
dan gambar
Guestroom
- Lantai 1 unit 28.00 (2.00) 14,340,453 401,532,687 (28,680,906)
- Lantai 2 unit 28.00 (2.00) 14,340,453 401,532,687 (28,680,906)
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.2.2 - PEKERJAAN PINTU dan JENDELA


- Lantai 3 unit 28.00 (2.00) 14,340,453 401,532,687 (28,680,906)
- Lantai 4 unit 28.00 (2.00) 14,340,453 401,532,687 (28,680,906)

Jendela J2 Alumunium powder coating ukuran 3000x4600 ,


tebal kaca 6 mm lengkap terpasang termasuk, hardware,
accesories dan perlengkapan bantu lainnya sesuai spesifikasi
ujung koridor
- Lantai 2 unit 2.00 - 14,340,453 28,680,906 -
- Lantai 3 unit 2.00 - 14,340,453 28,680,906 -
- Lantai 4 unit 2.00 - 14,340,453 28,680,906 -

DAFTAR NO. V.2.2 - PEKERJAAN PINTU dan JENDELA 3,405,103,437 (368,623,935)


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp

DAFTAR NO. V.2.3 - PEKERJAAN LANTAI

V.2.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

1 Pekerjaan lantai by Interior

DAFTAR NO. V.2.3 - PEKERJAAN LANTAI -


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp

DAFTAR NO. V.2.4 - PEKERJAAN PLAFOND

V.2.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

1 Pekerjaan Plafond by Interior

DAFTAR NO. V.2.4 - PEKERJAAN PLAFOND -


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp

DAFTAR NO. V.2.5. - PEKERJAAN SANITARY

V.2.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan


kelengkapan material bantu (adukan, plesteran, acian, nad, sealan,
grouting, bahan bantu pengubung (doble niple) yang berhubungan
dengan instalasi ME dan lainnya berikut pemasangan dan
perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Pekerjaan Sanitary by Interior

-
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. V.2.6. - PEKERJAAN LAIN-LAIN

V.2.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai


gambar dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Hand Railing Pipa besi h=1100mmØ2,5" besi Ø2", termasuk hand railing
dan alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (reff.gbr : GD-AR 2201)

Lantai 1
- Tangga darurat 01 m' 12.73 28.37 278,239 3,541,986 7,893,649
- Tangga darurat 02 m' 12.73 28.37 278,239 3,541,986 7,893,649
- Tangga as 7-8/C-D (Provisional) m' 5.95 - 278,239 1,655,524 -

2 Railing besi pipa Ø12 finish cat hitam, termasuk angkur baut dan alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (reff.gbr : GD-AR 2202)
Lantai 1
- Tangga as 7-8/C-D m' 59.71 (59.71) 311,629 18,607,385 (18,607,385)

3 Railling Kaca
Railling Kaca Tempered 12mm dan Railing stainless steel 20mm x 60mm
(custom) + Hand Railling Stainless Steel 40mm x 80mm with paint finish
welded & grind smooth tinggi 1000 mm , termasuk angkur baut, sealant
dan kelengkapan lainnya sesuai gambar dan spesifikasi pada :
Lantai 2
- Void m' 8.58 - 3,199,752 27,453,871 -
Lantai 3
- Void m' 10.70 - 3,199,752 34,237,345 -
Lantai 4
- Void m' 10.70 - 3,199,752 34,237,345 -

4 Meja Beton
Meja Beton tebal 100mm lapis black granit, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :(provisional)
Lantai 1
- Guest room (uk. 1100x500 mm) unit 13.00 - 466,520 6,064,760 -
Lantai 2
- Guest room (uk. 1100x500 mm) unit 26.00 - 466,520 12,129,520 -
Lantai 3
- Guest room (uk. 1100x500 mm) unit 26.00 - 466,520 12,129,520 -
Lantai 4
- Guest room (uk. 1100x500 mm) unit 26.00 - 466,520 12,129,520 -

5 Meja Lavatory
Meja Lavatory rangka lapis black granit, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :(provisional)
Lantai 1
- Powder room male (uk. 800x665 mm) unit 1.00 - 1,117,760 1,117,760 -
- Powder room female (uk. 1000x665 mm) unit 1.00 - 1,303,820 1,303,820 -
- Locker male (uk. 2250x890 mm) unit 1.00 - 3,127,830 3,127,830 -
- Locker female (uk. 2250x890 mm) unit 1.00 - 3,127,830 3,127,830 -

6 Tanggulan
Tanggulan Janitor tinggi 300 mm, tebal 145 mm lapis keramik, sesuai
gambar
Lantai 1dan spesifikasi pada :
- Locker male m' 1.70 - 304,910 518,347 -
- Locker female m' 1.78 - 304,910 541,215 -
Tanggulan Urinoir tinggi 1070 mm, tebal 150 mm lapis black granit,
sesuai
Lantaigambar
1 dan spesifikasi pada :
- Locker male m' 1.76 - 457,365 804,962 -

7 Groove (Provisional)
Cutter Grove uk. 10x10 mm termasuk gutter 50x30 mm terpasang sesuai
gambar dan spesifikasi pada :
Lantai 1
- Groove ramp m2 8.89 - 26,120 232,207 -
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. V.2.6. - PEKERJAAN LAIN-LAIN


8 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material bantu
dan kelengkapan lainnya, sesuai spesifkasi & gambar pada: (Provisional)
- Lantai Atap m2 812.40 - 198,663 161,393,703 -

9 Fire
FireStop
Stop(Provisional)
termasuk plat untuk dudukan dan glasswool, insulasi, rangka,
angkur, sealant, material bantu dan perlengkapan lainnya sesuai gambar
dan spesifikasi
Area shaft pada:
- Lantai 1 m2 3.75 - 556,479 2,086,795 -
- Lantai 2 m2 4.08 - 556,479 2,270,433 -
- Lantai 3 m2 4.08 - 556,479 2,270,433 -
- Lantai 4 m2 4.08 - 556,479 2,270,433 -

10 Jamb Lift (Provisional)


Wide jamb Wood panel sesuai spesifikasi dan gambar pada :
Lantai 1
- Public area lift m' 13.00 - 389,535 5,063,955 -
Lantai 2
- Public area lift m' 13.00 - 389,535 5,063,955 -
Lantai 3
- Public area lift m' 13.00 - 389,535 5,063,955 -
Lantai 4
- Public area lift m' 13.00 - 389,535 5,063,955 -

11 Pasangan Dinding
Pasangan bata ringan, tebal 100 mm dan perekat, adukan kering, kolom
dan balok praktis, sesuai spesifikasi dan gambar pada :
- Trap tangga (Provisional) m2 11.60 - 103,480 1,200,368 -
- Tangga darurat 01 m2 8.63 10.32 103,480 893,032 1,068,328
- Tangga darurat 02 m2 8.63 10.32 103,480 893,032 1,068,328
- Parapet Ramp kiri dan kanan m2 16.39 - 103,480 1,696,037 -

12 Finishing Cat
Cat Interior ex.Jotun Tipe standar, termasuk peralatan dan perlengkapan
sesuai spesifikasi dan gambar pada :
- Trap tangga (Provisional) m2 11.60 - 18,360 212,976 -

Cat Exterior ex.Jotun Tipe standar, termasuk peralatan dan


perlengkapan sesuai spesifikasi dan gambar pada :
- Parapet Ramp kiri dan kanan m2 32.78 - 29,490 966,682 -

13 Cove lampu cermin


Lapisan belakang dari multiplek tebal 12 mm lebar 140mm termasuk alat-
alat bantu lainnya dengan peralatan dan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :

Lantai 1
Powder room
- Female toilet m' 0.60 - 343,107 205,864 -
- Male toilet m' 0.60 - 343,107 205,864 -
Locker room
- Female toilet m' 2.25 - 343,107 771,991 -
- Male toilet m' 2.25 - 343,107 771,991 -

14 Cove lampu
Cove lampu lebar 200mm termasuk alat-alat bantu lainnya dengan
peralatan dan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :

Lantai 1
- Guest room m' 43.05 5.70 343,107 14,770,764 1,955,711
Lantai 2
- Guest room m' 86.10 11.40 343,107 29,541,528 3,911,422
Lantai 3
- Guest room m' 86.10 11.40 343,107 29,541,528 3,911,422
Lantai 4
- Guest room m' 86.10 11.40 343,107 29,541,528 3,911,422

15 Jamb Lift
Wide jamb stainless steel hairline (ex local) sesuai spesifikasi dan gambar
pada :
Lantai 1
- lift ( 2 unit) m' 11.17 0.03 389,535 4,351,106 11,686
Lantai 2
- lift ( 2 unit) m' 11.17 0.03 389,535 4,351,106 11,686
Lantai 3
- lift ( 2 unit) m' 11.17 0.03 389,535 4,351,106 11,686
Lantai 4
- lift ( 2 unit) m' 11.17 0.03 389,535 4,351,106 11,686
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. V.2.6. - PEKERJAAN LAIN-LAIN

DAFTAR No. V.2.6. - PEKERJAAN LAIN-LAIN 495,667,960 13,053,288


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. IV.2.7. - PEKERJAAN ATAP CANOPY

IV.2.7.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari


konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Atap
Roof covering metal roof pada atap, sesuai gambar dan spesifikasi
pada :
- Roof m2 9.86 13.34 681,690 6,721,463 9,093,745

DAFTAR No. IV.2.7. - PEKERJAAN ATAP CANOPY 6,721,463 9,093,745


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VIII.2.8 - PEKERJAAN FAÇADE

VIII.2.8.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber gasket

(sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya.,
rubber gasket (sealant), neoprene, penyetelan dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di


dalam daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk alat


penggantung (ironmongery sets) dan sistem kunci (keying system)
dan pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan


sketch detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari
peserta tender, seperti merk dan jenis kunci ataupun alat-alat
penggantung, dll..

A ALUMUNIUM COMPOSITE PANEL


Alumunium Composite panel Setara Alucobond terpasang, berikut
alat bantu dengan peralatan perlengkapan sesuai dengan spesifikasi
dan gambar pada :
- Depan m2 100.54 40.50 855,200 85,981,808 34,635,600
- Belakang m2 53.96 (2.28) 855,200 46,146,592 (1,949,856)

B CAT WEATHERSHILED
Cat eksterior ex.Jotun Tipe standar, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :

Exterior
- Lantai 1 m2 490.30 20.91 29,490 14,459,065 616,636
- Lantai 2 m2 455.89 51.91 29,490 13,444,285 1,530,855
- Lantai 3 m2 455.89 51.91 29,490 13,444,285 1,530,855
- Lantai 4 m2 455.89 51.91 29,490 13,444,285 1,530,855

C ALUMUNIUM GRILL
Alumunium Grill berikut alat bantu dengan peralatan perlengkapan
sesuai dengan spesifikasi dan gambar pada :

- Dinding belakang m2 66.04 37.32 1,001,661 66,149,722 37,382,005

D TERALIS
Teralis Ac out door berikut alat bantu dengan peralatan perlengkapan
sesuai dengan spesifikasi dan gambar pada :

- Dinding Exterior m 190.40 33.92 250,415 47,679,085 8,494,089

DAFTAR NO. VIII.2.8 - PEKERJAAN FAÇADE 300,749,126 83,771,041


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.4.1. - PEKERJAAN DINDING

V.3.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah termasuk


adukan biasa atau drymix, kolom praktis, ringbalk, angkur, sparing
dan semua pekerjaan bantu yang berhubungan dengan pekerjaan
dinding tersebut.

II Harga satuan plesteran biasa atau drymix sudah termasuk acian,


skonengan, tali air , ketrikan atau bobokan beton maupun bata ,
kawat ayam (jika diperlukan) dan semua pekerjaan bantu yang
berhubungan dengan plesteran.

III Harga satuan pekerjaan pelapis dinding (seperti : granit, marmer,


keramik, porselin) sudah termasuk adukan, cor beton,perekat
(calbond), angkur, kawat pengikat alumunium fixing pada dinding
dengan ketinggian lebih dari 2m, pemotongan, pinggulan, adu
manis, naad, dan alat bantu lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk dinding


kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian cat


dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi.
I PEK. PASANG DINDING

Pasangan bata ringan, tebal 100 mm dan perekat, adukan kering,


kolom dan balok praktis, sesuai spesifikasi dan gambar pada :
- Lantai 1 m2 1,732.23 by Arsitek
- Lantai 2 m2 1,732.23 by Arsitek
- Lantai 3 m2 1,732.23 by Arsitek
- Lantai 4 m2 1,732.23 by Arsitek
1,732.23
1,732.23
Plester dan Acian, tebal 25 mm, termasuk finish cat elmusi Acrylic
setara ex. Dulux / ICI dan perekat, adukan kering, kolom dan balok
praktis, sesuai spesifikasi dan gambar pada :

II - Lantai 1 m2 1,072.45 by Arsitek


- Lantai 2 m2 1,119.21 by Arsitek
- Lantai 3 m2 1,119.21 by Arsitek
- Lantai 4 m2 1,119.21 by Arsitek

W2, Dinding Keramik HT 400x400 mm White Onyx setara ex.


Indogress, termasuk perekat, adukan kering, sesuai spesifikasi dan
gambar pada : (reff.gbr : GD INT 3102)
Lantai 1
- Guest Room m2 210.54 9.16 361,890 76,191,452 3,315,781
Lantai 2
- Guest Room m2 421.08 18.32 361,890 152,382,904 6,631,562
Lantai 3
- Guest Room m2 421.08 18.32 361,890 152,382,904 6,631,562
Lantai 4
- Guest Room m2 421.08 18.32 361,890 152,382,904 6,631,562

W2, Dinding Keramik HT 400x400 mm Zirconium setara ex.


Indogress, termasuk perekat, adukan kering, sesuai spesifikasi dan
gambar pada : (reff.gbr : GD INT 3102)
Lantai 1
- Powder Room Pria m2 14.48 2.03 310,480 4,495,750 629,343
- Powder Room Wanita m2 13.44 1.82 310,480 4,172,851 565,074
- Ruang Ganti & Locker Pria m2 68.05 1.76 310,480 21,128,164 546,445
- Ruang Ganti & Locker Wanita m2 68.84 2.74 310,480 21,373,971 849,877

Shower Cubical Partisi kaca tampered 12mm, uk panjang


1450mm x tinggi 2000mm, termasuk Hardware handle ex TOTO TX
10 B dan engsel ex. KEND atau setara dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Guest Room unit 13.00 - 6,121,264 79,576,438 -
Lantai 2
- Guest Room unit 26.00 - 6,121,264 159,152,875 -
Lantai 3
- Guest Room unit 26.00 - 6,121,264 159,152,875 -
Lantai 4
- Guest Room unit 26.00 - 6,121,264 159,152,875 -

Cubical Partisi kaca tampered 12mm, uk panjang 3000mm x


tinggi 2000mm, termasuk pintu kaca dan uk 2 x 1546mm x 2000mm
untuk sekat serta hardware alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Ruang Ganti & Locker Pria unit 1.00 - 16,694,358 16,694,358 -
- Ruang Ganti & Locker Wanita unit 1.00 - 16,694,358 16,694,358 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.4.1. - PEKERJAAN DINDING


DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.4.1. - PEKERJAAN DINDING

DAFTAR NO. V.4.1. - PEKERJAAN DINDING 1,174,934,679 25,801,205


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITO Vol Vol (+/-) Harsat Rp

DAFTAR NO. V.3.2 - PEKERJAAN PINTU dan JENDELA

V.3.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk


angkur, sealant, karet, kaca, pengelasan, pemasangan kolom
praktis sekeliling pintu & jendela, dan peralatan bantu yang
diperlukan dan bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Pekerjaan Pintu dan Jendela by Arsitek

DAFTAR NO. V.3.2 - PEKERJAAN PINTU dan JENDELA -


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.3. - PEKERJAAN LANTAI

V.3.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

HOMOGENEOUS TILE

FL-01,Homogenious Tile 800x800mm White Onyx Color 1,


setara ex. Indogress termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :

Lantai 1
- Guest Room m2 216.15 2.90 1,073,930 232,132,207 3,112,160
- Kamar Mandi Guest Room m2 43.03 0.13 1,073,930 46,211,208 139,611
- Koridor m2 111.21 (111.21) 1,073,930 119,428,573 (119,428,573)
- Drugstore m2 10.34 10.27 1,073,930 11,104,436 11,029,261
- Room m2 20.41 2.46 1,073,930 21,918,911 2,641,868
- Time Keeper & Security Office m2 12.82 (0.02) 1,073,930 13,767,783 (21,479)
- Panel Room m2 4.09 0.12 1,073,930 4,392,374 128,872
- Tangga Kebakaran Kiri m2 20.82 (2.37) 1,073,930 22,359,223 (2,545,214)
- Tangga Tengah m2 9.77 (9.77) 1,073,930 10,496,059 (10,496,059)
- Tangga Kebakaran Kanan m2 20.66 (2.21) 1,073,930 22,187,394 (2,373,385)
- Trap tangga (Provisional) m2 11.60 - 1,073,930 12,457,588 -
- Teras entrance & Ramp (Provisional) m2 29.15 - 1,073,930 31,305,060 -

Lantai 2
- Guest Room m2 434.27 3.83 1,073,930 466,380,526 4,108,207
- Kamar Mandi Guest Room m2 86.06 0.26 1,073,930 92,422,416 279,222
- Koridor m2 83.14 (83.14) 1,073,930 89,286,876 (89,286,876)
- Reception area, Dinning Room m2 68.69 (68.69) 1,073,930 73,766,311 (73,766,311)
- Panel Room m2 4.23 (0.02) 1,073,930 4,542,724 (21,479)
- Tangga Kebakaran Kanan m2 20.49 (2.04) 1,073,930 22,004,826 (2,190,817)
- Tangga Tengah m2 13.80 (13.80) 1,073,930 14,820,234 (14,820,234)
- Tangga Kebakaran Kiri m2 20.56 (2.11) 1,073,930 22,080,001 (2,265,992)

Lantai 3
- Guest Room m2 434.27 3.83 1,073,930 466,380,526 4,108,207
- Kamar Mandi Guest Room m2 86.06 0.26 1,073,930 92,422,416 279,222
- Koridor m2 83.14 (83.14) 1,073,930 89,286,876 (89,286,876)
- Reception area, Dinning Room m2 68.69 (68.69) 1,073,930 73,766,311 (73,766,311)
- Panel Room m2 4.23 (0.02) 1,073,930 4,542,724 (21,479)
- Tangga Kebakaran Kanan m2 20.49 (2.04) 1,073,930 22,004,826 (2,190,817)
- Tangga Tengah m2 13.80 (13.80) 1,073,930 14,820,234 (14,820,234)
- Tangga Kebakaran Kiri m2 20.56 (2.11) 1,073,930 22,080,001 (2,265,992)

Lantai 4
- Guest Room m2 434.27 3.83 1,073,930 466,380,526 4,108,207
- Kamar Mandi Guest Room m2 86.06 0.26 1,073,930 92,422,416 279,222
- Koridor m2 46.08 (46.08) 1,073,930 49,488,372 (49,488,372)
- Reception area, Dinning Room m2 68.69 (68.69) 1,073,930 73,766,311 (73,766,311)
- Panel Room m2 4.23 (0.02) 1,073,930 4,542,724 (21,479)
- Tangga Kebakaran Kanan m2 20.49 (2.04) 1,073,930 22,004,826 (2,190,817)
- Tangga Tengah m2 13.80 (13.80) 1,073,930 14,820,234 (14,820,234)
- Tangga Kebakaran Kiri m2 20.56 (2.11) 1,073,930 22,080,001 (2,265,992)

HOMOGENEOUS TILE -Lanjutan

FL-02,Homogenious Tile 1200x600mm, setara ex. Indogress


termasuk alat bantu lainnya dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Koridor m2 2.51 2.13 707,870 1,777,196 1,509,261

Lantai 2
- Koridor m2 4.63 (4.63) 707,870 3,278,323 (3,278,323)

Lantai 3
- Koridor m2 4.63 (4.63) 707,870 3,278,323 (3,278,323)

Lantai 4
- Koridor m2 4.63 (4.63) 707,870 3,278,323 (3,278,323)

FL-01,Homogenious Tile 1200x600mm Bianco


Travertino,setara ex. Indogress termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :

Lantai 1
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.3. - PEKERJAAN LANTAI


- Reception area & Elevator Lobby m2 59.60 50.61 707,870 42,188,167 35,827,766
- Dinning Room & Lounge m2 85.97 73.01 707,870 60,857,916 51,682,814
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.3. - PEKERJAAN LANTAI

FL-01,Homogenious Tile 800x800mm Zircorium, setara ex.


Indogress termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Office Management m2 41.69 (0.01) 507,040 21,138,498 (5,070)
- Kitchen m2 31.33 0.36 507,040 15,885,563 182,534
- Dry Storage m2 4.61 0.10 507,040 2,337,454 50,704
- Cold Storage m2 4.45 0.11 507,040 2,256,328 55,774
- Staf Dinning m2 10.26 (10.26) 507,040 5,202,230 (5,202,230)
- Linen Storage m2 10.11 0.13 507,040 5,126,174 65,915

FL-01,Homogenious Tile 400x400mm White Onyx Color 1,


setara ex. Indogress termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :

Lantai 1
- Powder Room Pria m2 2.67 0.01 376,210 1,004,481 3,762
- Powder Room Wanita m2 2.16 - 376,210 812,614 -

FL-01,Homogenious Tile 600x600mm Zircorium, setara ex.


Indogress termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1105 & INT-1106)

Lantai 1
- Men's Locker & Toilet m2 19.71 (0.45) 470,030 9,264,291 (211,514)
- Women's Locker & Toilet m2 19.57 (0.37) 470,030 9,198,487 (173,911)

Solid wood Finish melamic termasuk alat bantu lainnya dengan


peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : GD-INT 3101)
Lantai 1
- - Tangga as 7-8/C-D m2 11.34 556,479 6,310,467 -

Carpet, Carpet Roll Odysey W4000,ex. Classic atau setara


termasuk alat bantu lainnya dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Praying Room/Mushola m2 27.84 (27.84) 228,156 6,351,869 (6,351,869)

FL-03, Plint Homogenious Tile 100x800mm White Onyx setara


ex. Indogress termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Guest Room m' 98.67 136.11 40,069 3,953,568 5,453,736
- Koridor m' 113.27 (15.81) 40,069 4,538,570 (633,467)
- Drugstore m' 14.07 3.18 40,069 563,765 127,418
- Room m' 19.82 (1.32) 40,069 794,160 (52,891)
- Time Keeper & Security Office m' 16.69 (0.93) 40,069 668,745 (37,264)
- Panel Room m' 8.58 0.17 40,069 343,789 6,812
- Tangga Kebakaran Kanan (Provisional) m' 20.12 - 40,069 806,180 -
- Tangga Kebakaran Kiri (Provisional) m' 20.42 - 40,069 818,201 -

Lantai 2
- Guest Room m' 475.28 (5.72) 40,069 19,043,977 (229,367)
- Koridor m' 70.41 13.66 40,069 2,821,150 547,417
- Tangga Kebakaran Kanan (Provisional) m' 20.43 - 40,069 818,688 -
- Tangga Kebakaran Kiri (Provisional) m' 20.13 - 40,069 806,668 -

Lantai 3
- Guest Room m' 475.28 (5.72) 40,069 19,043,977 (229,367)
- Koridor m' 70.41 13.66 40,069 2,821,150 547,417
- Tangga Kebakaran Kanan (Provisional) m' 20.43 - 40,069 818,688 -
- Tangga Kebakaran Kiri (Provisional) m' 20.13 - 40,069 806,668 -

Lantai 4
- Guest Room m' 475.28 (5.72) 40,069 19,043,977 (229,367)
- Koridor m' 70.41 13.66 40,069 2,821,150 547,417
- Tangga Kebakaran Kanan (Provisional) m' 20.43 - 40,069 818,688 -
- Tangga Kebakaran Kiri (Provisional) m' 20.13 - 40,069 806,668 -

FL-03, Plint Homogenious Tile 100x600mm Bianco Cemento


setara ex. Indogress termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :

Lantai 1
- Reception area & Elevator Lobby m' 13.56 (1.89) 27,355 371,025 (51,786)
- Dinning Room & Lounge m' 17.53 (2.45) 27,355 479,413 (66,914)

FL-01, Plint Homogenious Tile 100x800mm Zircorium,ex.


Indogress atau setara termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.3. - PEKERJAAN LANTAI


Lantai 1
- Office Management m' 28.36 (1.03) 95,131 2,697,904 (97,985)
- Kitchen m' 24.68 (2.66) 95,131 2,347,823 (253,047)
- Dry Storage m' 9.35 (0.95) 95,131 889,471 (90,374)
- Cold Storage m' 9.14 (0.94) 95,131 869,494 (89,423)
- Staf Dinning m' 10.39 (1.45) 95,131 988,407 (137,956)
- Linen Storage m' 13.18 (0.94) 95,131 1,253,821 (89,423)

STEP NOSING (Provisional)

Step Nosing Homogeneous Tile 600 x 600mm, berikut


adukan mortar, additiv, grouting nat termasuk alat-alat bantu
lainnya dengan peralatan perlengkapan sesuai spesifikasi
dan gambar pada :
Lantai 1
- Tangga Kebakaran Kanan m' 34.65 - 115,330 3,996,185 -
- Tangga Kebakaran Kiri m' 34.65 - 115,330 3,996,185 -

WATER PROOFING

Continuous Waterproofing Coating, termasuk pada dinding


setinggi 300mm terpasang sesuai dengan spesifikasi dan
gambar pada : (Provisional)

Lantai 1
- Kamar Mandi Guest Room m2 44.32 - 44,520 1,973,166 -
- Powder Room Pria m2 2.75 - 44,520 122,434 -
- Powder Room Wanita m2 2.22 - 44,520 99,048 -
- Men's Locker & Toilet m2 20.30 - 44,520 903,814 -
- Women's Locker & Toilet m2 20.16 - 44,520 897,394 -

Lantai 2
- Kamar Mandi Guest Room m2 88.64 - 44,520 3,946,333 -

Lantai 3
- Kamar Mandi Guest Room m2 88.64 - 44,520 3,946,333 -

Lantai 4
- Kamar Mandi Guest Room m2 88.64 - 44,520 3,946,333 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.3. - PEKERJAAN LANTAI


DAFTAR NO. V.3.3. - PEKERJAAN LANTAI 3,180,103,761 (539,366,720)
Dipindahkan ke Penjumlahan Total
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.4 - PEKERJAAN PLAFOND

V.3.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka pada
pertemuannya dengan kolom, balok, dinding dan lubang equipment M/E
(lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant dan
telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII
Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

C1, Gypsum Board, setara ex. Jaya Board, tebal 9mm dengan rangka
hollow 40x40mm tebal 6 mm dan 40x20mm tebal 6 mm termasuk cat finish
Acrylic emulsion brilliant white setara ex pentalite dulux, ICI dan alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr :AR06)
Lantai 1
- Guest Room m2 215.39 1.45 124,090 26,728,100 179,576
- Koridor m2 111.21 (33.00) 124,090 13,799,681 (4,095,248)
- Drugstore m2 10.34 10.27 124,090 1,283,091 1,274,404
- Room m2 20.41 (5.59) 124,090 2,532,677 (693,663)
- Time Keeper & Security Office m2 12.82 (0.02) 124,090 1,590,834 (2,482)
- Panel Room m2 4.09 (0.01) 124,090 507,528 (1,241)
- Reception area & Elevator Lobby m2 59.60 (11.94) 124,090 7,395,609 (1,482,050)
- Dinning Room & Lounge m2 85.97 (17.23) 124,090 10,668,426 (2,137,909)
- Office Management m2 41.69 (0.15) 124,090 5,173,312 (18,613)
- Kitchen m2 31.33 (0.03) 124,090 3,887,740 (3,723)
- Dry Storage m2 4.61 (0.03) 124,090 572,055 (3,723)
- Cold Storage m2 4.45 (0.02) 124,090 552,201 (2,482)
- Staf Dinning m2 10.26 (3.04) 124,090 1,273,163 (377,829)
- Linen Storage m2 10.11 (0.01) 124,090 1,254,550 (1,241)
- Praying Room/Mushola m2 27.84 (0.24) 124,090 3,454,666 (29,782)
Lantai 2
- Guest Room m2 430.79 2.89 124,090 53,456,200 359,152
- Koridor m2 87.77 0.15 124,090 10,891,573 18,420
- Reception area, Dinning Room m2 116.16 (116.16) 124,090 14,414,288 (14,414,288)
- Panel Room m2 4.23 (0.15) 124,090 524,901 (18,614)
- Tangga Kanan m2 20.49 (20.49) 124,090 2,542,604 (2,542,604)
- Tangga Tengah m2 13.80 (13.80) 124,090 1,712,442 (1,712,442)
- Tangga Kiri m2 20.56 (20.56) 124,090 2,551,290 (2,551,290)
Lantai 3
- Guest Room m2 430.79 2.89 124,090 53,456,200 359,152
- Koridor m2 87.77 0.15 124,090 10,891,573 18,420
- Reception area, Dinning Room m2 116.16 (116.16) 124,090 14,414,288 (14,414,288)
- Panel Room m2 4.23 (0.15) 124,090 524,901 (18,614)
- Tangga Kanan m2 20.49 (20.49) 124,090 2,542,604 (2,542,604)
- Tangga Tengah m2 13.80 (13.80) 124,090 1,712,442 (1,712,442)
- Tangga Kiri m2 20.56 (20.56) 124,090 2,551,290 (2,551,290)
Lantai 4
- Guest Room m2 430.79 2.89 124,090 53,456,200 359,152
- Koridor m2 87.77 0.15 124,090 10,891,573 18,420

C1, Gypsum Board, setara ex. Jaya Board, tebal 9mm dengan rangka
hollow 40x40mm tebal 6 mm dan 40x20mm tebal 6 mm termasuk cat finish
Acrylic emulsion brilliant white setara ex pentalite dulux, ICI dan alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr :AR06)-Lanjutan
Lantai 4
- Reception area, Dinning Room m2 116.16 (116.16) 124,090 14,414,288 (14,414,288)
- Panel Room m2 4.23 (0.15) 124,090 524,901 (18,614)
- Tangga Kanan m2 20.49 (20.49) 124,090 2,542,604 (2,542,604)
- Tangga Tengah m2 13.80 (13.80) 124,090 1,712,442 (1,712,442)
- Tangga Kiri m2 20.56 (20.56) 124,090 2,551,290 (2,551,290)

C4, Gypsum Water resistant , setara ex. Jaya Board, tebal 9mm dengan
rangka hollow 40x40mm tebal 6 mm dan 40x20mm tebal 6 mm termasuk cat
finish Acrylic emulsion brilliant white setara ex pentalite dulux, ICI dan alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada : (reff.gbr : AR06 )
Lantai 1
- Kamar Mandi Guest Room m2 41.37 1.79 150,250 6,216,218 268,572
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.4 - PEKERJAAN PLAFOND


- Powder Room Pria m2 2.67 (0.13) 150,250 401,168 (19,533)
- Powder Room Wanita m2 2.16 (0.14) 150,250 324,540 (21,035)
- Men's Locker & Toilet m2 19.71 (0.59) 150,250 2,961,428 (88,648)
- Women's Locker & Toilet m2 19.57 (0.51) 150,250 2,940,393 (76,628)

Lantai 2
- Kamar Mandi Guest Room m2 82.75 3.57 150,250 12,432,436 537,144

Lantai 3
- Kamar Mandi Guest Room m2 82.75 3.57 150,250 12,432,436 537,144

Lantai 4
- Kamar Mandi Guest Room m2 82.75 3.57 150,250 12,432,436 537,144

Drop Panel Ceilling 01, Gypsumboard 9mm setara ex. Jaya Board, tinggi
h= 100mm dengan rangka hollow galvanis termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (reff.gbr : AR06)
Lantai 1
- Koridor m' 45.37 0.24 100,166 4,544,738 23,840
- Powder Room m' 1.75 4.65 100,166 175,291 465,773
- Powder Room 1 m' 1.10 5.30 100,166 110,183 530,881
Lantai 2
- Koridor m' 74.03 (19.94) 100,166 7,415,099 (1,997,113)

Lantai 3
- Koridor m' 74.03 (19.94) 100,166 7,415,099 (1,997,113)

Lantai 4
- Koridor m' 74.03 (19.94) 100,166 7,415,099 (1,997,113)

Drop Panel Ceilling 01, Gypsum Water Resistant 9mm setara ex. Jaya
Board, tinggi h= 100mm dengan rangka hollow galvanis termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : AR06)
Lantai 1
- Kamar Mandi Guest Room m' 55.25 47.58 105,731 5,841,634 5,030,678
- Reception area, Dinning Room m' 49.25 (49.25) 105,731 5,207,248 (5,207,248)
Lantai 2
- Kamar Mandi Guest Room m' 110.50 95.16 105,731 11,683,268 10,061,355
- Reception area, Dinning Room m' 35.75 (35.75) 105,731 3,779,352 (3,779,352)
Lantai 3
- Kamar Mandi Guest Room m' 110.50 95.16 105,731 11,683,268 10,061,355
- Reception area, Dinning Room m' 35.75 (35.75) 105,731 3,779,352 (3,779,352)
Lantai 4
- Kamar Mandi Guest Room m' 110.50 95.16 105,731 11,683,268 10,061,355
- Reception area, Dinning Room m' 35.75 (35.75) 105,731 3,779,352 (3,779,352)

Drop Panel Ceilling 01, Gypsumboard 9mm setara ex. Jaya Board, tinggi
h= 200mm dengan rangka hollow galvanis termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (reff.gbr : AR06)
Lantai 1
- Guest Room m' 43.05 5.70 100,166 4,312,273 570,827
Lantai 2
- Guest Room m' 86.10 11.40 100,166 8,624,545 1,141,654
Lantai 3
- Guest Room m' 86.10 11.40 100,166 8,624,545 1,141,654
Lantai 4
- Guest Room m' 86.10 11.40 100,166 8,624,545 1,141,654

Drop Panel Ceilling 01, Gypsumboard 9mm setara ex. Jaya Board, tinggi
h= 100mm + 100mm dengan rangka hollow galvanis termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : GD-INT 3102)
Lantai 1
- Guest Room m' 30.55 - 100,166 3,060,076 -
Lantai 2
- Guest Room m' 61.10 - 100,166 6,120,151 -
Lantai 3
- Guest Room m' 61.10 - 100,166 6,120,151 -
Lantai 4
- Guest Room m' 61.10 - 100,166 6,120,151 -

Shadow line, Gypsumboard ex. Jaya Board atau setara, lebar 20mm
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (reff.gbr : GD-INT 3102)-Provisional

Lantai 1
- Guest Room m' 257.79 - 19,480 5,021,749 -
Lantai 2
- Guest Room m' 515.58 - 19,480 10,043,498 -
Lantai 3
- Guest Room m' 515.58 - 19,480 10,043,498 -
Lantai 4
- Guest Room m' 515.58 - 19,480 10,043,498 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.4 - PEKERJAAN PLAFOND

DAFTAR NO. V.3.4 - PEKERJAAN PLAFOND 560,365,516 (50,612,463)


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.5. - PEKERJAAN SANITARY

V.3.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan kelengkapan


material bantu (adukan, plesteran, acian, nad, sealan, grouting, bahan
bantu pengubung (doble niple) yang berhubungan dengan instalasi ME
dan lainnya berikut pemasangan dan perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik


pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

Lantai 1

Guest Room

- Wastafel Set setara ex TOTO LW 642 CJ bh 13.00 - 3,644,970 47,384,610 -


- Closet Duduk Set setara ex. TOTO CW 860 NJ / SW 861 JP bh 13.00 - 3,385,100 44,006,300 -
- Floor Drain setara ex. TOTO TX 1 BN bh 26.00 - 385,700 10,028,200 -

- Tissue Holder setara ex. TX 720 ACRB bh 13.00 - 267,820 3,481,660 -

- Faucet setara ex TOTO type TX 108 LDN bh 13.00 - 1,301,490 16,919,370 -

- Jetwasher setara ex. TOTO TX 403 SMCRB bh 13.00 - 581,660 7,561,580 -


- Shower set setara ex. TOTO TX 471 SU bh 13.00 - 2,122,450 27,591,850 -
- Towel Bar setara ex. TOTO (provisional) bh 13.00 - 990,290 12,873,770 -

Powder Room Pria

- Wastafel Set setara ex TOTO LW 642 CJ bh 1.00 - 3,644,970 3,644,970 -


- Closet Duduk Set setara ex. TOTO CW 821 J/SW 821 JP bh 1.00 - 3,385,100 3,385,100 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -

- Tissue Holder setara ex. TX 720 ACRB bh 1.00 - 267,820 267,820 -

- Faucet setara ex TOTO type TX 108 LDN bh 1.00 - 1,301,490 1,301,490 -

- Jetwasher setara ex. TOTO TX 403 SMCRB bh 1.00 - 581,660 581,660 -


- Urinoir setara ex. TOTO UW 930 JM bh 1.00 - 3,483,960 3,483,960 -

- Robe Hook setara ex. TOTO (provisional) bh 1.00 - 186,400 186,400 -

Powder Room Wanita

- Wastafel Set setara ex TOTO LW 642 CJ bh 1.00 - 3,644,970 3,644,970 -


- Closet Duduk Set setara ex. TOTO CW 821 J/SW 821 JP bh 1.00 - 3,385,100 3,385,100 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -

- Tissue Holder setara ex. TX 720 ACRB bh 1.00 - 267,820 267,820 -

- Faucet setara ex TOTO type TX 108 LDN bh 1.00 - 1,301,490 1,301,490 -

- Jetwasher setara ex. TOTO TX 403 SMCRB bh 1.00 - 581,660 581,660 -


- Robe Hook setara ex. TOTO (provisional) bh 1.00 - 186,400 186,400 -

Ruang Ganti & Kamar Mandi Pria

- Wastafel Set ex TOTO LW 549 J bh 2.00 - 3,644,970 7,289,940 -


- Closet Duduk Set ex. TOTO CW 860 NJ / SW 861 JP bh 2.00 - 3,385,100 6,770,200 -
- Floor Drain ex. TOTO TX 1 BN bh 4.00 - 385,700 1,542,800 -
- Tissue Holder ex. TX 720 ACRB bh 2.00 - 267,820 535,640 -
- Faucet ex TOTO type TX 108 LDN bh 2.00 - 1,301,490 2,602,980 -
- Jetwasher ex. TOTO TX 403 SMCRB bh 2.00 - 581,660 1,163,320 -
- Shower set ex. TOTO TX 721 AN + TX 432 bh 1.00 - 2,122,450 2,122,450 -
SHBR

- Urinoir ex. TOTO UW 930 JM bh 2.00 - 3,483,960 6,967,920 -

- Devider Urinoir ex. TOTO AW 115 J bh 1.00 - 3,483,960 3,483,960 -

- Robe Hook ex. TOTO (provisional) bh 3.00 - 186,400 559,200 -


- Soap Holder ex. TOTO (provisional) bh 1.00 - 102,210 102,210 -

- Kran wudhu ex. TOTO (provisional) bh 2.00 - 492,080 984,160 -


DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.5. - PEKERJAAN SANITARY


Lantai 1

Ruang Ganti & Kamar Mandi Wanita

- Wastafel Set ex TOTO LW 549 J bh 2.00 - 3,644,970 7,289,940 -


- Closet Duduk Set ex. TOTO CW 860 NJ / SW 861 JP bh 2.00 - 3,385,100 6,770,200 -
- Floor Drain ex. TOTO TX 1 BN bh 4.00 - 385,700 1,542,800 -
- Tissue Holder ex. TX 720 ACRB bh 2.00 - 267,820 535,640 -
- Faucet ex TOTO type TX 108 LDN bh 2.00 - 1,301,490 2,602,980 -
- Jetwasher ex. TOTO TX 403 SMCRB bh 2.00 - 581,660 1,163,320 -
- Shower set ex. TOTO TX 721 AN + TX 432 bh 1.00 - 2,122,450 2,122,450 -
SHBR

- Robe Hook ex. TOTO (provisional) bh 3.00 (1.00) 186,400 559,200 (186,400)
- Soap Holder ex. TOTO (provisional) bh 1.00 - 102,210 102,210 -

- Kran wudhu ex. TOTO (provisional) bh 2.00 1.00 492,080 984,160 492,080

Lantai 2

Guest Room

- Wastafel Set ex TOTO LW 642 CJ bh 26.00 - 3,644,970 94,769,220 -


- Closet Duduk Set ex. TOTO CW 860 NJ / SW 861 JP bh 26.00 - 3,385,100 88,012,600 -
- Floor Drain ex. TOTO TX 1 BN bh 52.00 - 385,700 20,056,400 -

- Tissue Holder ex. TX 720 ACRB bh 26.00 - 267,820 6,963,320 -

- Faucet ex TOTO type TX 108 LDN bh 26.00 - 1,301,490 33,838,740 -


- Jetwasher ex. TOTO TX 403 SMCRB bh 26.00 - 581,660 15,123,160 -

- Shower set ex. TOTO TX 471 SU bh 26.00 - 2,122,450 55,183,700 -


- Towel Bar ex. TOTO (provisional) bh 26.00 - 990,290 25,747,540 -

Lantai 3

Guest Room

- Wastafel Set ex TOTO LW 642 CJ bh 26.00 - 3,644,970 94,769,220 -


- Closet Duduk Set ex. TOTO CW 860 NJ / SW 861 JP bh 26.00 - 3,385,100 88,012,600 -
- Floor Drain ex. TOTO TX 1 BN bh 52.00 - 385,700 20,056,400 -

- Tissue Holder ex. TX 720 ACRB bh 26.00 - 267,820 6,963,320 -

- Faucet ex TOTO type TX 108 LDN bh 26.00 - 1,301,490 33,838,740 -


- Jetwasher ex. TOTO TX 403 SMCRB bh 26.00 - 581,660 15,123,160 -

- Shower set ex. TOTO TX 471 SU bh 26.00 - 2,122,450 55,183,700 -


- Towel Bar ex. TOTO (provisional) bh 26.00 - 990,290 25,747,540 -

Lantai 4

Guest Room

- Wastafel Set ex TOTO LW 642 CJ bh 26.00 - 3,644,970 94,769,220 -


- Closet Duduk Set ex. TOTO CW 860 NJ / SW 861 JP bh 26.00 - 3,385,100 88,012,600 -
- Floor Drain ex. TOTO TX 1 BN bh 52.00 - 385,700 20,056,400 -

- Tissue Holder ex. TX 720 ACRB bh 26.00 - 267,820 6,963,320 -

- Faucet ex TOTO type TX 108 LDN bh 26.00 - 1,301,490 33,838,740 -


- Jetwasher ex. TOTO TX 403 SMCRB bh 26.00 - 581,660 15,123,160 -

- Shower set ex. TOTO TX 471 SU bh 26.00 - 2,122,450 55,183,700 -


- Towel Bar ex. TOTO (provisional) bh 26.00 - 990,290 25,747,540 -

DAFTAR NO. V.3.5. - PEKERJAAN SANITARY 1,269,719,300 305,680


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.6. - PEKERJAAN FIX FURNITURE

V.3.6.0. Catatan Harga

I Harga satuan pekerjaan sudah termasuk fitting, accessories, alat


bantu, perlengkapan dan peralatan yang diperlukan

II Harga satuan Backdrop dinding panel HPL sudah termasuk


rangka, penyesuaian pola permukaan, bahan terbuang, biaya
pengeringan kayu, anti rayap, penyambungan dan finishing

III Harga satuan pada pekerjaan Movable Partition sudah termasuk


biaya untuk rangka, perkuatan struktur penggantung, sound
berrier, siap cat harus sudah termasuk biaya fabrikasi, handling
dan pemasangan, angkur-angkur, bracket, sealant dan back of
rod pada celah-celah horisontal dan vertikal untuk mencegah
kebocoran udara, air dan suara.

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat

V Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste)

VI Harga satuan sesuai dengan gambar dan spesifikasi teknis

Signed Guest Room, Room number Stainless Steel, termasuk


alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (reff.gbr : AR02) Provisional

- Lantai 1 unit 13.00 556,479 7,234,222 -


- Lantai 2 unit 26.00 556,479 14,468,443 -
- Lantai 3 unit 26.00 556,479 14,468,443 -
- Lantai 4 unit 26.00 556,479 14,468,443 -

Cermin kaca tampered 12mm, uk panjang 600mm x tinggi


1400mm, termasuk plywood alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : AR12)
- Powder Room Pria unit 1.00 1,042,006 1,042,006 -
- Powder Room Wanita unit 1.00 1,042,006 1,042,006 -

Cermin kaca tampered 12mm, uk panjang 950mm x tinggi


1400mm, termasuk plywood alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : AR12)
- Guest Room Pria unit 13.00 1,649,843 21,447,960 -
- Guest Room Wanita unit 26.00 1,649,843 42,895,920 -

Cermin kaca tampered 12mm, uk panjang 2250mm x tinggi


1850mm, termasuk plywood alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : AR12)
- Ruang Ganti & Locker Pria unit 1.00 5,163,513 5,163,513 -
- Ruang Ganti & Locker Wanita unit 1.00 5,163,513 5,163,513 -

WALL DECORATIVE

WP2, Wood panel, Plywood finish HPL termasuk alat bantu


lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
Lantai 1
- Reception Area m2 5.82 445,183 2,590,964 -
Lantai 3
- Reception Area m2 5.82 445,183 2,590,964 -

WP1, Wood panel, Plywood finish HPL termasuk alat bantu


lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
Lantai 1
- Lift Area m2 10.48 445,183 4,665,516 -
Lantai 3
- Lift Area m2 10.48 445,183 4,665,516 -

WP4, Wood panel, Plywood finish HPL termasuk alat bantu


lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
Lantai 2
- Reception Area m2 5.82 445,183 2,590,964 -
Lantai 4
- Reception Area m2 5.82 445,183 2,590,964 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. V.3.6. - PEKERJAAN FIX FURNITURE


WP3, Wood panel, Plywood finish HPL termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
Lantai 2
- Lift Area m2 10.48 445,183 4,665,516 -
Lantai 4
- Lift Area m2 10.48 445,183 4,665,516 -

DV1, Devider,uk. 3000mm x 2700mm, Rangka Hollow Finish cat


hitam dengan Kawat ayam 40x40mm termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : AR05 & F06)
Lantai 1
- Lift Area unit 1.00 14,524,091 14,524,091 -

DV2, Devider,uk. 3000mm x 2700mm, Rangka Hollow Finish cat


hitam dengan Kawat ayam 40x40mm termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : AR05 & F06)
Lantai 1
- Lift Area unit 1.00 14,524,091 14,524,091 -

Bed Head, Plywood lapis HPL tebal 18mm + 3 mm, Plywood


finished HPL Wood Grain ex. Arbirite atau setara , termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (Reff.Gbr : AR03)
Lantai 1
- Guest Room unit 13.00 2,504,154 32,553,997 -
Lantai 2
- Guest Room unit 26.00 2,504,154 65,107,994 -
Lantai 3
- Guest Room unit 26.00 2,504,154 65,107,994 -
Lantai 4
- Guest Room unit 26.00 2,504,154 65,107,994 -

Share Console & Private Console, Plywood lapis HPL tebal


18mm, Plywood finished HPL Wood Grain metal plate support
insside funiture, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(Reff.Gbr : AR03)
Lantai 1
- Guest Room unit 13.00 3,739,536 48,613,969 -
Lantai 2
- Guest Room unit 26.00 3,739,536 97,227,938 -
Lantai 3
- Guest Room unit 26.00 3,739,536 97,227,938 -
Lantai 4
- Guest Room unit 26.00 3,739,536 97,227,938 -

Backdrop TV, Plywood lapis HPL tebal 18mm + 3 mm,


Plywood finished HPL Wood Grain ex. Arborite atau setara,
termasuk alat bantu lainnya dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada : (Reff.Gbr : AR03)

Lantai 1
- Guest Room unit 13.00 9,603,429 124,844,579 -
Lantai 2
- Guest Room unit 26.00 9,603,429 249,689,158 -
Lantai 3
- Guest Room unit 26.00 9,603,429 249,689,158 -
Lantai 4
- Guest Room unit 26.00 9,603,429 249,689,158 -

CT2, Shelf, Plywood lapis HPL tebal 18mm, Plywood finished


HPL, termasuk alat bantu lainnya dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada : (Reff.Gbr : AR03
& F02)
Lantai 1 (Provisional) unit 1.00 2,782,392.92 2,782,393 -

Artwork, metal finished cat, termasuk alat bantu lainnya dengan


peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (Reff.Gbr : GD-INT 3102)(Provisional)
Lantai 1
- Powder room unit 2.00 6,121,264.43 12,242,529 -

DAFTAR NO. V.3.6. - PEKERJAAN FIX FURNITURE 1,642,581,314 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY sat. volume vol +/- H. Satuan Jumlah Harga Jumlah Harga
Rp. Rp. (+/-)
DAFTAR NO. V.3.7. - PEKERJAAN LOOSE FURNITURE

V.3.7.0. Catatan Harga

I Harga satuan pekerjaan furniture sudah termasuk fitting, accessories,


alat bantu, perlengkapan dan peralatan yang diperlukan

II Harga satuan sudah termasuk lampu, kabel, fitting dan sparing-sparing


sesuai gambar dari konsultan terkait

III Harga satuan Backdrop dinding panel HPL sudah termasuk rangka,
penyesuaian pola permukaan, bahan terbuang, biaya pengeringan
kayu, anti rayap, penyambungan dan finishing

IV Harga satuan pada pekerjaan Movable Partition sudah termasuk biaya


untuk rangka, perkuatan struktur penggantung, sound berrier, siap cat
harus sudah termasuk biaya fabrikasi, handling dan pemasangan,
angkur-angkur, bracket, sealant dan back of rod pada celah-celah
horisontal dan vertikal untuk mencegah kebocoran udara, air dan
suara.

V Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat

VI Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste)

VII Harga satuan sesuai dengan gambar dan spesifikasi teknis

BED, Kasur ex. Chantique atau setara , termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (Reff.Gbr : AR03)

Lantai 1
- Guest Room unit 26.00 - 2,671,097 69,448,527 -
Lantai 2
- Guest Room unit 52.00 - 2,671,097 138,897,055 -
Lantai 3
- Guest Room unit 52.00 - 2,671,097 138,897,055 -
Lantai 4
- Guest Room unit 52.00 - 2,671,097 138,897,055 -

Lemari, Plywood Lpais HPL tebal 18mm + 3mm wood grain ex


Arborite atau setara,vynil edging termasuk Decorative steel hollow 1.5"
warna hitam fin powder coating terpasang sesuai spesifikasi dan
gambar pada : (Reff.gbr : AR03)
Lantai 1
- Guest Room unit 13.00 - 5,342,194 69,448,527 -
Lantai 2
- Guest Room unit 26.00 - 5,342,194 138,897,055 -
Lantai 3
- Guest Room unit 26.00 - 5,342,194 138,897,055 -
Lantai 4
- Guest Room unit 26.00 - 5,342,194 138,897,055 -

Refrigenerator Cabinet & Meja, Plywood Lpais HPL tebal 18mm +


3mm wood grain ex Arborite atau setara, vynil edging 1.5" warna fitting
Chrome ex Hafelle atau setara terpasang sesuai spesifikasi dan
gambar pada : (Reff.gbr : AR03)
Lantai 1
- Guest Room unit 13.00 - 6,677,743 86,810,659 -
Lantai 2
- Guest Room unit 26.00 - 6,677,743 173,621,318 -
Lantai 3
- Guest Room unit 26.00 - 6,677,743 173,621,318 -
Lantai 4
- Guest Room unit 26.00 - 6,677,743 173,621,318 -

C9, Kursi Single hitam/Lime greenType Slim Aime ex. Ikons atau
setara, dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada : (Reff.gbr : AR03)

Lantai 1
- Guest Room unit 13.00 - 1,402,326 18,230,238 -
Lantai 2
- Guest Room unit 26.00 - 1,402,326 36,460,477 -
Lantai 3
- Guest Room unit 26.00 - 1,402,326 36,460,477 -
Lantai 4
- Guest Room unit 26.00 - 1,402,326 36,460,477 -

T1, Reception Desk, Plywood finish HPL tebal 18mm+3mm wood


grain ex. Arborite atau setara, vynil edging, Black Glassstone ex.
Himalaya atau setara termasuk fiiting accessories ex Hafelle atau
setara alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR03 & F01)
T1, Reception Desk, Plywood finish HPL tebal 18mm+3mm wood
DAFTAR No.Arborite
grain ex. V.4 - PEKERJAAN ARSITEKTUR
atau setara, vynil GROOM
edging, Black DORMITORY
Glassstone ex. sat. volume vol +/- H. Satuan Jumlah Harga Jumlah Harga
Himalaya atau setara termasuk fiiting accessories ex Hafelle atau Rp. Rp. (+/-)
setara alat bantu lainnya dengan peralatan
DAFTAR NO. V.3.7. - PEKERJAAN LOOSE FURNITURE perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR03 & F01)

Lantai 1
- Meja Reception unit 1.00 - 3,305,483 3,305,483 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY sat. volume vol +/- H. Satuan Jumlah Harga Jumlah Harga
Rp. Rp. (+/-)
DAFTAR NO. V.3.7. - PEKERJAAN LOOSE FURNITURE

C1, Kursi Kerja Penerima Type Winona Black / Lime green, ex.
Ikons atau setara, uk panjang 410mm x lebar 510mm x tinggi 690mm,
termasuk Mahogany wood chair stain finish fabric cushions include
sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-1103 )

Lantai 1
- R Penerima Lobby unit 1.00 1.00 734,552 734,552 734,552

T2, Dinning Table, uk. 1200mm x 800mm, Top Table plywood 40mm
finish HPL dan powder coated steel pipe Ø2,5", dan besi Ø3/4"
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR03 & F01)

Lantai 1
- Dinning Table unit 3.00 (1.00) 1,936,545 5,809,636 (1,936,545)

T2A, Dinning Table, uk. 1800mm x 800mm, Top Table plywood


40mm finish HPL dan powder coated steel pipe Ø2,5", dan besi Ø3/4"
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR03 & F01)

Lantai 1
- Dinning Table unit 8.00 - 1,936,545 15,492,364 -

C2, Kursi Single, uk diameter 510mm x 410mm x tinggi 690mm, type


Wninona black/lim green Ex Ikons atau setara, Mahogany wood chair
stain finish fabric cushions included termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (Reff.gbr : AR03)

Lantai 1
- Dinning Room unit 60.00 - 1,402,326 84,139,562 -
Lantai 2
- Lounge unit 6.00 - 1,402,326 8,413,956 -

C3, Kursi hadap , uk diameter 500mm x 490mm x tinggi 450mm, type


Mesh back, foam seat fabric upholstery ateja atau setara termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (Reff.gbr : AR03)

Lantai 1
- Office Management unit 4.00 - 591,314 2,365,257 -

WD1, Meja Bulat, uk diameter 900mm x tinggi 750mm, Top Table


plywood 18mm finish HPL dan powder coated steel pipe 2", termasuk
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (Reff.gbr : AR03 & F01)

Lantai 1
- Office Management unit 1.00 - 2,126,861 2,126,861 -

WD2, Meja kerja bentuk L, uk 700mmx1100mm x tinggi 750mm dan


400mmx1200x650mm, Top Table plywood 18mm finish HPL dan kaki
meja besi finish cat, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(Reff.gbr : AR03 & F03)
Lantai 1
- Office Management unit 1.00 - 4,357,895 4,357,895 -

WD3, Workstation, uk 2800mmx1200mm x tinggi 750mm, Top Table


plywood 18mm finish HPL dan Kaki meja besi finish cat, termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (Reff.gbr : AR03 & F03)

Lantai 1
- Office Management unit 6.00 - 9,025,637 54,153,825 -
- time keeper unit 2.00 - 9,025,637 18,051,275 -

CR2, Credenza, uk 4000mmx575mm x tinggi 2900mm, Portal Plywood


finish HPL dan Jalusi devider Alumunium finish natural, termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (Reff.gbr : AR03 & F04)

Lantai 1
- Office Management unit 1.00 - 23,238,546 23,238,546 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY sat. volume vol +/- H. Satuan Jumlah Harga Jumlah Harga
Rp. Rp. (+/-)
DAFTAR NO. V.3.7. - PEKERJAAN LOOSE FURNITURE
PR1, Devider, uk 1500mmx200mm x tinggi 2900mm, Portal Devider
Plywood finish HPL dan Jalusi devider Alumunium finish natural,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR03 & F04)

Lantai 1
- Office Management unit 1.00 - 8,714,455 8,714,455 -

C4, Kursi Kerja Reserver Type S 220 LB Black, uk diameter 450mm


x 460mm x tinggi 610mm, Ex Morelli atau setara, Meshback, Foam
seat Fabric uppholdtery ex. Ateja atau setara dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(Reff.gbr : AR02 & F02)

Lantai 1
- Office Management unit 1.00 - 771,279 771,279 -

C7, Kursi FO Manager Type S 320 MB Black, uk diameter 620mm x


620mm x 540mm, Ex Morelli atau setara, Meshback, Foam seat Fabric
uppholdtery ex. Ateja atau setara dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada : (Reff.gbr : AR02 &
F02)

Lantai 1
- Office Management unit 2.00 - 1,355,582 2,711,164 -

C5, Kursi Hadap FO Manager Type S 224 LB CL WA Black, uk


diameter 500mm x 490mm x 450mm, Ex Morelli atau setara,
Meshback, Foam seat Fabric uppholdtery ex. Ateja atau setara
Cantilever nase dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (Reff.gbr : AR02 & F02)

Lantai 1
- Office Management unit 1.00 - 590,980 590,980 -

C6, Kursi Kerja Staff Type C 20 N Black, uk diameter 500mm x


490mm x 450mm, Ex Morelli atau setara, Meshback, Foam seat Fabric
uppholdtery ex. Ateja atau setara dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada : (Reff.gbr : AR02 &
F02)

Lantai 1
- Office Management unit 6.00 - 677,791 4,066,745 -
- Security Office & Time keeper unit 3.00 - 677,791 2,033,373 -
CT1
C2, Kursi Single Type Winona, uk diameter 510mm x 410mm x
690mm, Ex Ikons atau setara, Mahogany wood chair stain finish,
Fabric cushins include dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR02 & F02)

Lantai 1
- Dinning Staff unit 6.00 - 1,402,326 8,413,956 -
Lantai 2
- Lounge unit 6.00 - 1,402,326 8,413,956 -

C11, Kursi Bar Stool Type Stefanie, Ex Ikons atau setara,


Alumunium Look finish, dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR02 & F02)

Lantai 2
- Lounge unit 1.00 - 2,136,878 2,136,878 -

T3, Meja Lounge, uk 2600mmx600mm x tinggi 730mm, Top Table


plywood 18mm finish HPL dan Kaki meja Besi kotak finish cat hitam,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR03 & F01)

Lantai 2
- Lounge unit 1.00 - 3,472,426 3,472,426 -

T4, Meja Lounge Betuk L, uk 3770mmx600mm x tinggi 730mm dan


1650mm x 600mm x 730mm, Top Table plywood 18mm finish HPL dan
Kaki meja Besi kotak finish cat hitam, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (Reff.gbr : AR03 & F01)

Lantai 2
- Lounge unit 1.00 - 4,006,646 4,006,646 -

B1, Bench, uk diameter 1600mm x 410mm x tinggi 450mm, Dudukan


kayu solid finish melamic water base dan kaki bench besi finish cat
hitam, termasuk peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada : (Reff.gbr : AR03 & F03)
B1, Bench, uk diameter 1600mm x 410mm x tinggi 450mm, Dudukan
kayu solid
DAFTAR finish
No. V.4 melamic waterARSITEKTUR
- PEKERJAAN base dan kakiGROOM
bench besi finish cat
DORMITORY sat. volume vol +/- H. Satuan Jumlah Harga Jumlah Harga
hitam, termasuk peralatan perlengkapan terpasang sesuai spesifikasi Rp. Rp. (+/-)
dan gambar
DAFTAR pada-:PEKERJAAN
NO. V.3.7. (Reff.gbr : AR03 & F03)
LOOSE FURNITURE

Lantai 1
- Ruang Ganti & Locker wanita unit 1.00 - 4,140,201 4,140,201 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY sat. volume vol +/- H. Satuan Jumlah Harga Jumlah Harga
Rp. Rp. (+/-)
DAFTAR NO. V.3.7. - PEKERJAAN LOOSE FURNITURE

LK1, Loker Bentuk L, uk 3100mm x 500mm x tinggi 2150mm dan uk


1500mmx500mmx2150mm, Plywood finish HPL ex. Arborite atau
setara bagian dalam loker finish Tacosheet warna putih, termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (Reff.gbr : AR03 & F05)

Lantai 1
- Ruang Ganti & Locker pria unit 1.00 - 4,340,533 4,340,533 -
- Ruang Ganti & Locker wanita unit 1.00 - 4,340,533 4,340,533 -

DAFTAR NO. V.3.7. - PEKERJAAN LOOSE FURNITURE 1,987,908,002 (1,201,994)


Dipindahkan ke Penjumlahan Total
DAFTAR No. VI.1 - PEKERJAAN STRUKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VI.1.1 - PEKERJAAN PONDASI TIANG PANCANG

VI.1.1.0. Catatan Harga

Catatan Harga (Pricing Notes)


I Harga satuan tiang pancang sudah termasuk :

- harga tukang, alat dan material untuk pemancangan lengkap


termasuk waste

- keperluan galian tanah insidentil termasuk buangan tanah

penggantian tiang pancang yang rusak atau tiang pancang


- yang meleset atau tiang pancang yang gagal test

- topi pondasi dan sepatu pondasi tiang pancang

perbaikan tiang pancang yang menyimpang dari as bagian


-
bawah atau atas

- biaya test sudah termasuk pengadaan balok beton


pemindahan balok beton dan hal - hal lain

- pondasi tiang diperhitungkan net tidak ada biaya untuk


tambahan panjang tiang pada pie head

Kedalaman pemancangan dihitung dari muka tanah asli (peil


2
+/- 0.000 pada gambar lokasi).

Harga satuan untuk pemancangan dan galian tanah sudah harus


diperhitungkan kemungkinan resiko longsor, pembuangan sisa-
3
sisa akar tanaman, sisa konstruksi bangunan lama yang masih
tertanam, pembersihan lumpur (wash boring), dan lain-lain.

Perbedaan berat yang dikeluarkan oleh pabrik yang satu dengan


4 pabrik yang lainnya untuk diameter yang sama menjadi tanggung
jawab pemborong.

Tabel berat yang dipakai dalam menghitung berat besi dalam


5
Daftar ini, adalah :
Diameter Ø Kg/m (polos)

6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.186
32 mm 6.313

Monitoring lapangan :

harga sudah termasuk observasi lapangan, test lapangan dan


-
test laboratorium

- harga sudah termasuk penyediaan contoh, analisa tanah,


termasuk persiapan test

- harga sudah termasuk penyelesaian laporan yang diperlukan


untuk pekerjaan tersebut diatas

- pengukuran dilokasi tiang sebelum dan sesudah pemancangan

- pembersihan lapangan, jalan sementara, lantai kerja, jalan


masuk yang mungkin diperlukan untuk pelaksanan
pemancangan

VOLUME PROVISIONAL (HARGA SATUAN TETAP)

A PENGADAAN TIANG PANCANG

Pengadaan Tiang Pancang untuk pemancangan, sesuai


spesifikasi dan gambar
Ukuran 250 x 250 mm, 4D13 U-40, stirup Ø5 -75 pada atas
dan bawah, stirup Ø5 -150 pada tengah
kedalaman pemancangan = 11 m' m' 594 11,130 6,610,966 -
Jumlah titik pemancangan = 54 titik

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VI.1.1 ( 216 ) PONDASI


DAFTAR No. VI.1 - PEKERJAAN STRUKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VI.1.1 - PEKERJAAN PONDASI TIANG PANCANG

B PEMANCANGAN TIANG PANCANG

Pemancangan Tiang Pancang dengan drop hammer 1500 kg


untuk Test Pile dan Reaction Pile (used pile), sesuai spesifikasi
dan gambar
Ukuran 250 x 250 mm, 4D13 U-40, stirup Ø5 -75 pada atas
dan bawah, stirup Ø5 -150 pada tengah
kedalaman pemancangan = 11 m' m' 594 155,814 92,553,518 -
Jumlah titik pemancangan = 54 titik

C PEK. SAMBUNGAN T. PANCANG


Pekerjaan sambungan tiang pancang beton ukuran 250 x 250
mm lengkap dgn alat - alat bantu berikut dgn pengelasan
terpasang sesuai spesifikasi dan gambar

Sambungan tiang pancang ukuran 250 x 250 mm nos 54 Rate only


- -
Note : Kedalaman tiang pancang 11 m'

D PEK. DOLLY

Pekerjaan Dolly tiang pancang ukuran 250 x 250 mm, dengan titik 54 Rate only
kedalaman = 2 ~ 3 m' - -

E PEK. TEST PONDASI TIANG PANCANG (USE PILE)

Test beban pendahuluan reaction pile pada tiang pancang


bh 1.00
dengan beban sebesar 250% x 3,5 ton 38,953,501 38,953,501 -

Test beban pancang + PDA (Pile Driving Analysis) test ttk 1.00 7,790,700
7,790,700 -

F PEKERJAAN LAIN - LAIN

Mobilisasi dan demobilisasi blok2 beton dan peralatan loading test


lainnya (2 x 75 ton) ls 1.00 8,903,657
8,903,657 -
Loading test 2 x 75 ton titik 1.00 38,953,501
38,953,501 -

DAFTAR No. VI.1.1 - PEKERJAAN PONDASI TIANG PANCANG


Dipindahkan ke Penjumlahan Total 193,765,843 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VI.1.1 ( 217 ) PONDASI


DAFTAR No. VI.1 - PEKERJAAN STRUKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VI.1.2 - PEKERJAAN TANAH

VI.1.2.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko


longsoran, volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah


termasuk kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi


dan tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VI.1.2 ( 218 ) TANAH


DAFTAR No. VI.1 - PEKERJAAN STRUKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VI.1.2 - PEKERJAAN TANAH


A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan m2 806.44 - 11,130 8,975,304 -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pile Cap m3 25.24 (9.17) 55,640 1,404,628 (510,224)
- Tie Beam m3 74.45 (3.65) 55,640 4,142,612 (203,097)

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar

- Dibawah plat lantai inc Tie Beam m3 8.66 (8.66) 272,340 2,357,239 (2,357,239)
- Pile Cap m3 2.09 (0.37) 272,340 569,191 (101,038)

Urugan tanah untuk mencapai level yang diinginkan, termasuk pemadatan,


dengan memaksimalkan tanah dipakai dari bekas galian serta tanah dari
luar site jika diperlukan sesuai spek dan gambar
- Pile Cap m3 23.15 - 55,648 1,288,523 -
- Tie Beam m3 65.80 - 55,648 3,661,537 -

D Pek. Lain - Lain


D.1 Pek. Bobok kepala tiang Pondasi Pancang

Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar

- Mini Pile diameter 25 cm ttk 54.00 (1.00) 83,472 4,507,477 (83,472)


D.2 Pekerjaan Anti rayap
Anti rayap pada Lantai dan dinding basement , termasuk alat - alat bantu, m2 806.44 - 16,690 13,459,442 -
peralatan perlengkapan sesuai spesifikasi dan gambar

D.3 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan
sesuai spesifikasi dan gambar (Kontraktor diminta untuk melampirkan
breakdown harganya) Ls 1.00 - exclude - -

DAFTAR No. VI.1.2 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 40,365,953 (3,255,069)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VI.1.2 ( 219 ) TANAH


DAFTAR No. VI.1 - PEKERJAAN STRUKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VI.1.3 - PEKERJAAN STRUKTUR BETON

VI.1.3.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VI.1.3 ( 220 ) BETON


DAFTAR No. VI.1 - PEKERJAAN STRUKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VI.1.3 - PEKERJAAN STRUKTUR BETON

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam, termasuk GWT m3 86.56 (49.22) 667,780 57,799,698 (32,865,001)
2) Pile cap m3 1.04 (0.18) 667,780 694,491 (120,534)

B Beton mutu K-300 :


1) Pile cap m3 14.06 (2.12) 759,480 10,678,289 (1,610,667)
2) Tie beam m3 49.56 (6.66) 759,480 37,636,745 (5,058,981)
3) Pelat, pada:
- Lantai 1 m3 207.75 (82.23) 759,480 157,781,211 (62,454,681)

C Beton mutu K-350 :


3) Pelat, pada:
- Lantai 2 m3 43.32 10.28 782,410 33,895,762 8,040,436

4) Balok, pada:
- Lantai 2 m3 22.79 (1.18) 782,410 17,831,124 (919,527)

5) Core wall, pada:


- Lantai 1 m3 65.55 6.64 782,410 51,284,041 5,196,180

6) Kolom, pada:
- Lantai 1 m3 12.78 (0.71) 782,410 9,996,383 (553,477)

PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada:
- Lantai 1 m2 788.40 (41.61) 53,220 41,958,648 (2,214,285)

A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:


1) Pile cap kg 4,815.51 (3,004.12) 8,859 42,658,195 (26,611,986)
2) Tie beam kg 11,888.96 (1,011.58) 8,859 105,318,393 (8,961,082)

3) Pelat, pada:
- Lantai 1 kg 4,383.39 560.30 8,859 38,830,249 4,963,406
- Lantai atap kg 3,227.53 783.85 8,859 28,591,107 6,943,773

4) Balok, pada:
- Lantai 2 kg 5,485.09 124.62 8,859 48,589,670 1,103,977

5) Core wall, pada:


- Lantai 1 kg 9,906.49 2,589.42 8,859 87,756,665 22,938,388

6) Kolom, pada:
- Lantai 1 kg 1,954.75 133.61 8,859 17,316,168 1,183,562

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap m2 13.29 24.19 84,790 1,126,859 2,050,731
2) Sisi tegak Tie Beam m2 271.71 7.37 84,790 23,038,664 625,232

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada:
- Lantai 1 (Bawah pelat, bawah balok dan sisi tegak) m2 41.15 (21.95) 129,920 5,345,688 (2,851,224)
- Lantai atap (Bawah pelat, bawah balok dan sisi tegak) m2 312.83 63.70 129,920 40,642,874 8,275,254

2) Kolom, pada:
- Lantai 1 m2 170.35 (9.43) 129,920 22,132,132 (1,225,405)

3) Balok (sisi tegak), pada:


- Lantai 2 m2 144.47 1.95 104,000 15,024,880 202,696

4) Core wall, pada:


- Lantai 1 m2 364.21 213.29 112,040 40,806,088 23,897,012

PEKERJAAN LAIN-LAIN (Provisional)

Waterproofing membrane termasuk screed tebal rata-rata 50


A mm + wire mesh M6 termasuk peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar: (Provisional)

1) lantai atap
- Atap m2 312.83 - 127,690 39,945,263 -

Water Proofing Integral termasuk sesuai dengan gambar dan


B
spesifikasi, pada :
1) Pelat lantai 1 m3 207.75 - 100,170 20,810,217 -
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VI.1.3 ( 221 ) BETON
DAFTAR No. VI.1 - PEKERJAAN STRUKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VI.1.3 - PEKERJAAN STRUKTUR BETON

2) Pile Cap m3 14.06 - 100,170 1,408,390 -

Waterstop, pada sambungan plat lantai dengan dinding


C
beton, pada:
1) GWT m 49.20 - 94,600 4,654,320 -

D Talang beton pada atap selasar, pada: -(Provisional)


1) Beton m3 20.88 - 667,780 13,943,246 -
2) Bekesting m2 154.47 - 104,000 16,064,880 -

DAFTAR NO. VI.1.3 - PEKERJAAN STRUKTUR BETON


Dipindahkan ke Penjumlahan Total 1,033,560,341 (60,026,205)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VI.1.3 ( 222 ) BETON


DAFTAR No. VI.1 - PEKERJAAN STRUKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. VI.1.4 - PEKERJAAN STRUKTUR BAJA

VI.1.4.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-
lubang baut, perapihan dengan gerinda, penyediaan
peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi


dan pengiriman ke lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi

I Canopy Atap
1) WF 250 x 125 x 6 x 9 Kg 87.35 18,364 1,604,070 -
2) WF 200 x 100 x 5,5 x 8 Kg 5,040.90 18,364 92,569,972 -
3) CNP 150 x 50 x 20 x 2,3 Kg 4,291.20 18,364 78,802,710 -
4) L 50 x 50 x 5 Kg 1,503.45 18,364 27,609,045 -
5) HB 200 x 200 x 8 x 12 Kg 1,528.30 18,364 28,065,400 -
6) Plate T = 6 mm Kg 169.73 17,807 3,022,428 -
7) Plate T = 8 mm Kg 80.25 17,807 1,428,963 -
8) Plate T = 10 mm Kg 82.86 17,807 1,475,596 -
9) Plate T = 12 mm Kg 982.77 17,807 17,500,423 -
10) Baut Diameter M 12 mm bh 390.00 31,163 12,153,492 -
11) Baut Diameter M 16 mm bh 542.00 31,163 16,890,238 -
12) Trekstang dia 10mm Kg 142.86 17,807 2,543,871 -
13) Angkur M 16, L=500 mm bh 104.00 222,591 23,149,509 -
14) Roundbar Ø 10 Kg 149.09 18,364 2,737,802 -
15) Cat Dasar (Zincromate) Kg 14,162.74 3,339 47,287,585 -
15) Cat Finish Kg 28,485.28 3,339 95,108,705 -
16) Nonshrink grout t=25 m3 0.59 13,355,486 7,812,959 -

DAFTAR NO. VI.1.4 - PEKERJAAN STRUKTUR BAJA 459,762,768 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VI.1.4 ( 223 ) SAMEP


DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VI.2.1. - PEKERJAAN DINDING

VI.2.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah


termasuk adukan biasa atau drymix, kolom praktis, ringbalk,
angkur, sparing dan semua pekerjaan bantu yang
berhubungan dengan pekerjaan dinding tersebut.

II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton
maupun bata , kawat ayam (jika diperlukan) dan semua
pekerjaan bantu yang berhubungan dengan plesteran. Volume
plesteran dan acian sudah ditambahkan 10cm di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit,


marmer, keramik, porselin) sudah termasuk adukan, cor
beton,perekat (calbond), angkur, kawat pengikat alumunium
fixing pada dinding dengan ketinggian lebih dari 2m,
pemotongan, pinggulan, adu manis, naad, dan alat bantu
lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk


dinding kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk


pengertian cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi.

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. Primacon,


termasuk dinding penebalan,urinoir, perekat, adukan kering
kolom
- Lantaidan
1 balok praktis sesuai spesifikasi dan gambar : m2 794.06 32.29 103,480 82,169,453 3,341,773

II PEK. PELAPIS DINDING

A Plesteran dan Acian, Plesteran halus berikut acian halus,


termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :
- Lantai 1 m2 1,640.15 37.55 61,540 100,934,702 2,310,992
- Area Exterior m2 485.61 (76.52) 61,540 29,884,230 (4,708,832)

B Pengecatan dengan fin. cat acrylic emultion setara ex.Jotun


tipe standar, termasuk peralatan dan perlengkapan sesuai
spesifikasi dan gambar pada :

- Lantai 1
Horse Food Storage m2 61.92 3.10 18,360 1,136,759 56,838
Bedding Storage 1 m2 216.83 (10.96) 18,360 3,980,966 (201,266)
Bedding Storage 2 m2 219.06 (11.70) 18,360 4,021,909 (214,779)
Equipment Storage m2 323.25 16.16 18,360 5,934,797 296,740
Ruang trafo & Ruang PDTM m2 128.90 6.44 18,360 2,366,531 118,327
Kapasitor bank m2 53.21 2.66 18,360 977,009 48,850
Ruang PDTR m2 77.70 3.88 18,360 1,426,508 71,325
Ruang Genset m2 213.77 10.69 18,360 3,924,821 196,241
Ruang Pompa m2 69.71 3.49 18,360 1,279,894 63,995
Selasar as 2-2'/a-d m2 168.41 8.42 18,360 3,091,984 154,599
Ramp as 2-2'/c'-e m2 107.40 5.37 18,360 1,971,939 98,597

DAFTAR NO. VI.2.1. - PEKERJAAN DINDING 243,101,500 1,633,400


Dipindahkan ke Penjumlahan Total
DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VI.2.2 - PEKERJAAN PINTU dan JENDELA

VI.2.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis sekeliling
pintu & jendela, dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU BAJA
Pintu Baja P1 Steel plat tebal 1,5 mm 2 daun pintu ukuran 2230 x
2550 mm lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
Main Entrance unit 10.00 (10.00) 13,745,021 137,450,210 (137,450,210)
- Lantai 1

Hardware :
Lever handle art-306 SS psg 1.00 (1.00) Include
Lockcase Wilka art-1490.55 SS bh 1.00 (1.00) Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 (1.00) Include
Hinges Gracia BB 5" x 3" x 3 mm bh 8.00 (8.00) Include
Flush bolt gracia 200/350 mm SS set 1.00 (1.00) Include
Door closer Dorma TS 68 RA Silver bh 1.00 (1.00) Include

Pintu Baja P2 ukuran 2628 x 2400 mm Kusen alumunium 40mm,


Daun Pintu Double Teakwood + kaca tebel 5mm, lengkap terpasang
termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 1.00 (1.00) 14,049,971 14,049,971 (14,049,971)

Hardware :
Lever handle art-306 SS psg 1.00 (1.00) Include
Lockcase Wilka art-1490.55 SS bh 1.00 (1.00) Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 (1.00) Include
Floor hinges dorma BTS 80 complete SS bh 2.00 (2.00) Include
Flush bolt gracia 200/350 mm SS set 1.00 (1.00) Include

Pintu Baja P3 Steel plat tebal 1,5 mm 2 daun pintu ukuran 2120 x
2150 mm lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
Main Entrance unit 2.00 (2.00) 10,145,718 20,291,435 (20,291,435)
- Lantai 1

Hardware :
Lever handle art-306 SS psg 1.00 (1.00) Include
Lockcase Wilka art-1490.55 SS bh 1.00 (1.00) Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 (1.00) Include
Hinges Gracia BB 5" x 3" x 3 mm bh 8.00 (8.00) Include
Flush bolt gracia 200/350 mm SS set 1.00 (1.00) Include
Door closer Dorma TS 68 RA Silver bh 1.00 (1.00) Include

Pintu Baja P4 Steel plat tebal 1,5 mm 1 daun pintu ukuran 1120 x
2150 mm lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
Main Entrance unit 2.00 (2.00) 5,360,002 10,720,003 (10,720,003)
- Lantai 1

Hardware :
Lever handle art-306 SS psg 1.00 (1.00) Include
Lockcase Wilka art-1490.55 SS bh 1.00 (1.00) Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 (1.00) Include
Hinges Gracia BB 5" x 3" x 3 mm bh 8.00 (8.00) Include
Flush bolt gracia 200/350 mm SS set 1.00 (1.00) Include
Door closer Dorma TS 68 RA Silver bh 1.00 (1.00) Include

B JENDELA

Jendela J1 Louvre Alumunium, Kusen Alumunium 30x70mm Clear


Anodized ukuran 1235x4251030 x 2220mm lengkap terpasang
termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada : 443,400
- Lantai 1 unit 30.00 (30.00) 5,299,733 158,991,980 (158,991,980)

Jendela kaca tebal 5mm, Kusen Alumunium 30x70mm Clear


Anodized ukuran 1030 x 2220mm lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)
Jendela kaca tebal 5mm, Kusen Alumunium 30x70mm Clear
DAFTAR
Anodized NO. VI.2.21030
ukuran - PEKERJAAN PINTU dan
x 2220mm lengkap JENDELA
terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
- Lantai 1 unit 1.00 (1.00) 2,286,159 2,286,159 (2,286,159)
DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VI.2.2 - PEKERJAAN PINTU dan JENDELA

DAFTAR NO. VI.2.2 - PEKERJAAN PINTU dan JENDELA 343,789,760 (343,789,760)


Dipindahkan ke Penjumlahan Total
DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VI.2.3 - PEKERJAAN LANTAI

VI.2.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

CONCRETE SLAB

Floor Hardener 3kg/m2 setara ex Fosroc, Sika, MU, termasuk


alat alat bantu lainnya dengan peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :

- Horse Food Storage m2 23.19 0.34 33,390 774,314 11,486


- Bedding Storage 1 m2 62.31 0.38 33,390 2,080,531 12,822
- Bedding Storage 2 m2 62.33 0.70 33,390 2,081,199 23,306
- Equipment Storage m2 127.32 0.41 33,390 4,251,215 13,823
- Ruang trafo & Ruang PDTM m2 53.02 0.02 33,390 1,770,338 668
- Kapasitor bank m2 14.05 0.09 33,390 469,130 2,938
- Ruang PDTR m2 29.54 0.07 33,390 986,341 2,204
- Ruang Genset m2 66.77 2.39 33,390 2,229,450 79,802
- Ruang Pompa m2 124.64 0.63 33,390 4,161,730 20,969
- Selasar as 2-2'/a-d m2 35.51 0.09 33,390 1,185,679 3,005
- Ramp as 2-2'/c'-e m2 20.90 2.20 33,390 697,851 73,592
- GWT m2 113.85 1.23 33,390 3,801,452 41,070

Continuous Waterproofing Coating, termasuk pada dinding


setinggi 300mm terpasang sesuai dengan spesifikasi dan
gambar pada : (Provisional)

- GWT m2 113.85 - 44,520 5,068,602 -

DAFTAR NO. VI.2.3 - PEKERJAAN LANTAI 29,557,830 285,685


Dipindahkan ke Penjumlahan Total
DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VI.2.4 - PEKERJAAN PLAFOND

VI.2.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A Beton exposed aci halus finish cat interior ex.Jotun tipe standar, termasuk
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
dengan spesifikasi dan gambar pada :

- Horse Food Storage m2 23.19 0.01 52,310 1,213,069 523


- Bedding Storage 1 m2 62.31 0.05 52,310 3,259,436 2,615
- Bedding Storage 2 m2 62.33 0.03 52,310 3,260,482 1,569
- Equipment Storage m2 127.32 0.08 52,310 6,660,109 4,185
- Ruang trafo & Ruang PDTM m2 53.02 - 52,310 2,773,476 -
- Kapasitor bank m2 14.05 - 52,310 734,956 -
- Ruang PDTR m2 29.54 - 52,310 1,545,237 -
- Ruang Genset m2 66.77 2.39 52,310 3,492,739 125,021
- Ruang Pompa m2 124.64 - 52,310 6,519,918 -
- Selasar as 2-2'/a-d m2 35.51 - 52,310 1,857,528 -
- Ramp as 2-2'/c'-e m2 20.90 1.80 52,310 1,093,279 94,367
- GWT m2 113.85 1.23 52,310 5,955,494 64,341

DAFTAR NO. VI.2.4 - PEKERJAAN PLAFOND 38,365,723 292,622


Dipindahkan ke Penjumlahan Total
DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp

DAFTAR NO. VI.2.5. - PEKERJAAN SANITARY

VI.2.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan


kelengkapan material bantu (adukan, plesteran, acian, nad, sealan,
grouting, bahan bantu pengubung (doble niple) yang berhubungan
dengan instalasi ME dan lainnya berikut pemasangan dan
perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

-
DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VI.2.6. - PEKERJAAN LAIN-LAIN

VI.2.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai


gambar dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Trap tangga
Pasangan bata ringan, tebal 100 mm dan perekat, adukan kering, kolom
dan balok praktis, sesuai spesifikasi dan gambar pada :
- Trap tangga (Provisional) m2 25.22 103,480 2,609,766 -

DAFTAR No. VI.2.6. - PEKERJAAN LAIN-LAIN 2,609,766 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VI.2.7. - PEKERJAAN ATAP CANOPY

VI.2.7.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari


konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Atap

Atap UPVC ex Alderon berikut alat bantu dengan peralatan


perlengkapan sesuai dengan spesifikasi dan gambar pada :

Roof top
- Storage m2 928.66 4.50 300,498 279,060,877 1,350,740

DAFTAR No. VI.2.7. - PEKERJAAN ATAP CANOPY 279,060,877 1,350,740


Dipindahkan ke Penjumlahan Total
DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. VIII.2.9 - PEKERJAAN FAÇADE

VIII.2.9.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber gasket

(sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk alat


penggantung (ironmongery sets) dan sistem kunci (keying system) dan
pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari peserta
tender, seperti merk dan jenis kunci ataupun alat-alat penggantung, dll..

A Cat Weathershield (Provisional)


Finishing cat weathershiled berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :

- Eksterior m2 485.61 29,490 14,320,539 -

DAFTAR NO. VIII.2.9 - PEKERJAAN FAÇADE 14,320,539 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. VII.1 - PEKERJAAN STRUKTUR ADMINISTRATION OFFICE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VII.1.1 - PEKERJAAN TANAH

VII.1.1.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko longsoran,
volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah termasuk
kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi dan tidak
mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan sesuai
gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VII.1.1 ( 234 ) TANAH


DAFTAR No. VII.1 - PEKERJAAN STRUKTUR ADMINISTRATION OFFICE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VII.1.1 - PEKERJAAN TANAH


A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan m2 581.16 - 11,130 6,468,062 -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan) untuk
urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 166.58 - 55,640 9,268,336 -
- Pile Cap m3 15.03 - 55,640 836,380 -
- Tie Beam m3 16.19 - 55,640 900,800 -

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu berikut
peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai inc Tie Beam m3 2.45 - 272,340 668,050 -
- Pondasi Batu kali m3 14.77 - 272,340 4,023,551 -
- Pile Cap m3 2.74 (2.23) 272,340 746,756 (607,318)

Urugan tanah untuk mencapai level yang diinginkan, termasuk pemadatan,


dengan memaksimalkan tanah dipakai dari bekas galian serta tanah dari luar site
jika diperlukan sesuai spek dan gambar
- Pondasi Batu kali m3 55.77 - 55,648 3,103,584 -
- Pile Cap m3 12.29 - 55,648 683,912 -
- Tie Beam m3 13.74 - 55,648 764,424 -

D Pek. Lain - Lain


D.1 Pek. Bobok kepala tiang Pondasi Pancang

Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar

- Borpile diameter 600 mm ttk tidak ada - - -


D.2 Pekerjaan Anti rayap
Anti rayap pada Lantai dan dinding basement , termasuk alat - alat bantu, m2 581.16 - 16,690 9,699,560 -
peralatan perlengkapan sesuai spesifikasi dan gambar

D.3 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan sesuai
spesifikasi dan gambar (Kontraktor diminta untuk melampirkan breakdown
harganya) Ls 1.00 - exclude - -

DAFTAR No. VII.1.1 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 37,163,416 (607,318)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VII.1.1 ( 235 ) TANAH


DAFTAR No. VII.1 - PEKERJAAN STRUKTUR ADMINISTRATION OFFICE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VII.1.2 - PEKERJAAN STRUKTUR BETON

VII.1.2.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VII.1.2 ( 236 ) BETON


DAFTAR No. VII.1 - PEKERJAAN STRUKTUR ADMINISTRATION OFFICE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VII.1.2 - PEKERJAAN STRUKTUR BETON

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam m3 24.53 - 667,780 16,380,643 -
2) Pile cap m3 27.42 (27.16) 667,780 18,310,528 (18,139,576)

B Beton mutu K-300 :


1) Pile cap m3 6.86 (5.58) 759,480 5,206,235 (4,234,101)
2) Tie beam m3 6.13 (3.66) 759,480 4,656,220 (2,782,431)
3) Pelat, pada:
- Lantai 1 m3 72.46 - 759,480 55,032,073 -

C Beton mutu K-350 :


4) Balok, pada:
- Lantai 2 m3 16.81 (13.85) 782,410 13,150,747 (10,834,814)
5) Kolom, pada:
- Lantai 1 m3 6.93 (4.41) 782,410 5,422,101 (3,450,428)

PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada:
- Lantai 1 m2 546.71 - 53,220 29,095,906 -

A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:


1) Pile cap kg 824.88 (636.28) 8,859 7,307,173 (5,636,463)
2) Tie beam kg 1,559.65 (1,214.92) 8,859 13,816,123 (10,762,336)
3) Pelat, pada:
- Lantai 1 kg 158.55 - 8,859 1,404,528 -
4) Balok, pada:
- Lantai 2 kg 2,296.69 (1,820.78) 8,859 20,345,196 (16,129,361)
5) Kolom, pada:
- Lantai 1 kg 1,088.77 (675.91) 8,859 9,644,892 (5,987,574)

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap m2 23.40 (17.00) 84,790 1,984,086 (1,441,430)
2) Sisi tegak Tie Beam m2 61.31 (36.64) 84,790 5,198,305 (3,106,366)

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada:
- Lantai 1 (Bawah pelat, bawah balok dan sisi tegak) m2 591.66 - 100,570 59,503,045 -
2) Kolom, pada:
- Lantai 1 m2 92.40 (58.80) 129,920 12,004,608 (7,639,296)
3) Balok (sisi tegak), pada:
- Lantai 2 m2 127.12 (96.04) 104,000 13,220,480 (9,988,160)

PEKERJAAN LAIN-LAIN (Provisional)


Water Proofing Integral termasuk sesuai dengan gambar dan spesifikasi,
A
pada :
1) Pelat lantai 1 m3 65.61 - 100,170 6,571,673 -
2) Pile Cap m3 6.86 - 100,170 686,665 -

B Pondasi Batu Kali


1) Pondasi Batu Kali m3 66.48 - 611,910 40,681,613 -
2) Pasangan Aanstamping t=15cm m3 29.55 - 398,440 11,773,105 -
3) Beton tumbuk m3 73.87 - 720,190 53,200,435 -
4) Angkur D13-500 kg 21.49 - 18,920 406,575 -

DAFTAR NO. VII.1.2 - PEKERJAAN STRUKTUR BETON


Dipindahkan ke Penjumlahan Total 405,002,956 (100,132,336)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VII.1.2 ( 237 ) BETON


DAFTAR No. VII.1 - PEKERJAAN STRUKTUR ADMINISTRAT Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VII.1.3 - PEKERJAAN STRUKTUR BAJA

VII.1.3.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-
lubang baut, perapihan dengan gerinda, penyediaan
peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi


dan pengiriman ke lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi

I Struktur Atap storage


1) WF 250 x 125 x 6 x 9 Kg 4,519.74 18,364 82,999,615 -
2) WF 200 x 100 x 5.5 x 8 Kg 1,493.10 18,364 27,418,980 -
3) CNP 150 x 50 x 20 x 3.2 Kg 5,321.22 18,364 97,717,784 -
4) L 40 x 40 x 4 Kg 136.75 18,364 2,511,237 -
5) HB 200 x 200 x 8 x 12 Kg 1,687.50 18,364 30,988,822 -
6) Plate T=6mm Kg 36.06 17,807 642,127 -
7) Plate T=9mm Kg 29.26 17,807 520,999 -
8) Plate T=12mm Kg 697.32 17,807 12,417,317 -
9) Stifner 8 Kg 62.53 17,807 1,113,457 -
10) Stifner 12 Kg 182.49 17,807 3,249,578 -
11) Baut M12 mm Bh 360.00 31,163 11,218,608 -
12) Baut M16 mm Bh 192.00 31,163 5,983,258 -
13) Baut M20 mm Bh 288.00 31,163 8,974,887 -
14) Trekstang dia 10mm Kg 83.65 17,807 1,489,611 -
15) Angkur 2M12 Kg 72.00 222,591 16,026,583 -
16) Nonshrink grout t=25 m3 0.81 13,355,486 10,817,944 -
17) Cat Dasar (Zincromate) Kg 14,321.61 3,339 47,818,001 -
17) Cat Finish Kg 10,079.02 3,339 33,652,558 -

DAFTAR NO. VII.1.3 - PEKERJAAN STRUKTUR BAJA 395,561,365 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VII.1.3 ( 238 ) BAJA


DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR ADMINISTRASI Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VII.2.1. - PEKERJAAN DINDING

VII.2.1.0. Catatan Harga

I
Harga satuan dinding batako, bata, hebel, celcon sudah termasuk adukan biasa
atau drymix, kolom praktis, ringbalk, angkur, sparing dan semua pekerjaan bantu
yang berhubungan dengan pekerjaan dinding tersebut.

II
Harga satuan plesteran biasa atau drymix sudah termasuk acian, skonengan, tali
air , ketrikan atau bobokan beton maupun bata , kawat ayam (jika diperlukan)
dan semua pekerjaan bantu yang berhubungan dengan plesteran. Volume
plesteran dan acian sudah ditambahkan 10cm di atas plafond

III
Harga satuan pekerjaan pelapis dinding (seperti : granit, marmer, keramik,
porselin) sudah termasuk adukan, cor beton,perekat (calbond), angkur, kawat
pengikat alumunium fixing pada dinding dengan ketinggian lebih dari 2m,
pemotongan, pinggulan, adu manis, naad, dan alat bantu lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk dinding kedap air
sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian cat dasar (meni,
plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan sesuai
spesifikasi.

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. primacon, termasuk dinding
penebalan,urinoir, perekat, adukan kering kolom dan balok praktis sesuai
spesifikasi
- Lantai 1 dan gambar :
Kantor Administrasi m2 158.63 0.64 103,480 16,415,032 66,363

II PEK. PELAPIS DINDING

A Plesteran dan Acian, Plesteran halus berikut acian halus, termasuk peralatan
dan perlengkapan sesuai spesifikasi dan gambar pada :

- Lantai 1
Kantor Administrasi m2 81.77 0.10 61,540 5,031,830 6,388
- Area Exterior
Kantor Administrasi m2 120.04 0.09 61,540 7,387,262 5,600

B Pengecatan dengan fin. cat Acrylic emulsion paint ex.setara ICI / Jotun tipe
ambience majestic, termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :

- Kantor Administrasi
Administration Office m2 74.55 (4.09) 18,360 1,368,650 (75,004)
Toilet Room m2 23.42 (23.42) 18,360 429,903 (429,903)

DAFTAR NO. VII.2.1. - PEKERJAAN DINDING 30,632,676 (426,557)


Dipindahkan ke Penjumlahan Total
DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR ADMINISTRASI Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VII.2.2 - PEKERJAAN PINTU dan JENDELA

VII.2.2.0. Catatan Harga

I
Harga satuan pintu dan jendela kayu sudah termasuk angkur, perlengkapan
kaca, pemasangan kolom & ringbalk praktis sekeliling pintu & jendela, dan
peralatan bantu yang diperlukan dan bahan yang terbuang (waste).

II
Harga satuan pintu dan jendela besi sudah termasuk angkur, pengelasan, kaca,
pemasangan kolom & balok praktis sekeliling pintu & jendela , dan peralatan
bantu yang diperlukan dan bahan yang terbuang (waste).

III
Harga satuan pintu dan jendela aluminium sudah termasuk angkur, sealant,
karet, kaca, pengelasan, pemasangan kolom praktis sekeliling pintu & jendela,
dan peralatan bantu yang diperlukan dan bahan yang terbuang (waste).

IV
Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU KAYU
Pintu Kayu P1 Terdiri dari 1 pintu dan 2 daun pintu dengan kusen/frame
alumunium ukuran 1790x2400 mm, Plywood, kaca 5 mm THK. lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai
- Lantaispesifikasi
1 dan gambar pada :-Provisional unit 1.00 2,281,562 2,281,562 -

Hardware :
Lever handle art-LH UL306/22 mm SS psg 1.00 Include
Lockcase Calfis art 17180.55 SS bh 1.00 Include
Cylinder Calfis art-17140.62 S. Nickel bh 1.00 Include
Hinges Gracia BB 5"x3"3" mm SS bh 3.00 Include
Door closer Calfis CFS 2002 RA Silver bh 1.00 Include
Friction Stay Top hung Art-12" psg 1.00 Include
Rambuncis art-118 Silver bh 1.00 Include

Pintu Kusen P2 terdiri dari 1 daun pintu Alumunium 40 mm clear anodized,


ukuran 857x2400 mm, alumunium, Daun pintu double teakwodd 3 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai
- Lantaispesifikasi
1 dan gambar pada :-(Provisional) unit 1.00 2,225,914 2,225,914 -

Hardware :
Lever handle art-LH UL306/22 mm SS psg 1.00 Include
Lockcase Calfis art 17180.55 SS bh 1.00 Include
Cylinder Calfis art-17140.62 S. Nickel bh 1.00 Include
Hinges Gracia BB 5"x3"3" mm SS bh 3.00 Include
Door closer Calfis CFS 2002 RA Silver bh 1.00 Include
Friction Stay Top hung Art-12" psg 1.00 Include
Rambuncis art-118 Silver bh 1.00 Include

Jendela J1 ukuran 1500x2300 mm Kusen Alumunium 40 mm Clear Anodized,


Daun Jendela Alumunium, Kaca Clear 5 mm lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai spesifikasi dan
gambar pada :-(Provisional)
- Lantai 1 unit 12.00 3,585,113 43,021,359 -

Hardware :
Flush handle art- 506 SN bh 4.00 Include
Lockcase Calfis art-17136.30 SS bh 1.00 Include
Ring kunci art-901 CK SS bh 1.00 Include
Track Sliding Calfis SD 100/2 mtr bh 2.00 Include
Cannel Sliding Calfis CL 500/2mtr bh 1.00 Include
Bracket BK110 btg 1.00 Include
Roda sliding Calfis pack 120 (100kg) btg 6.00 Include
Terdiri dari :
- Hanger HW 111 (2pcs)
- Track Buffer with retained ST 112 (1 Pcs)
- Floor Guide FG 115 (1 Pcs)
DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR ADMINISTRASI Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VII.2.2 - PEKERJAAN PINTU dan JENDELA

DAFTAR NO. VII.2.2 - PEKERJAAN PINTU dan JENDELA 47,528,836 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR ADMINIST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VII.2.3 - PEKERJAAN LANTAI

VI.2.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

HOMOGENOUS TILE

Homogenous Tile uk. 600 x 600 mm White onyx setara ex


Indogress berikut adukan mortar, additiv, grouting nat termasuk
alat-alat bantu lainnya dengan peralatan perlengkapan sesuai
spesifikasi dan gambar pada :

- Administrasi office m2 49.77 0.82 528,200 26,289,835 431,803


- Teras m2 7.96 (0.16) 528,200 4,205,793 (85,833)

Homogenous Tile uk. 400 x 400 mm White Onyx setara ex


Indogress berikut adukan mortar, additiv, grouting nat termasuk
alat-alat bantu lainnya dengan peralatan perlengkapan sesuai
spesifikasi dan gambar pada :

- Toilet m2 3.41 - 388,340 1,323,269 -

PLINT HOMOGENOUS TILE

Plint Homogenious Tile 100x600mm White Onyx setara ex.


Indogress termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :

- Administrasi office m 29.40 0.60 31,592 928,817 18,955


- Teras m 9.86 0.14 31,592 311,501 4,423

DAFTAR NO. VII.2.3 - PEKERJAAN LANTAI 33,059,213 369,349


Dipindahkan ke Penjumlahan Total
DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR ADMINISTRASI Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VII.2.4 - PEKERJAAN PLAFOND

VII.2.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A Plafond Gypsum board tebal 9 mm setara ex. Jayaboard, finishing cat


Weathershiled setara ex. ICI, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :

- Administrasi office m2 49.77 0.43 124,090 6,176,270 53,048


- Teras m2 7.96 (0.16) 124,090 988,067 (20,165)

B Plafond Kalsiboard tebal 8 mm setara ex. Jayaboard, finishing cat


Weathershiled setara ex ICI / jotun, termasuk alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :

- Toilet m2 3.41 (0.01) 161,380 549,902 (1,210)

C Listplank GRC Cetak finishing cat Weathershield setara ex. ICI / Jotun,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :

- Depan teras m' 7.65 8.35 267,110 2,043,389 2,230,366

DAFTAR NO. VII.2.4 - PEKERJAAN PLAFOND 9,757,628 2,262,040


Dipindahkan ke Penjumlahan Total
DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR ADMINISTRASI Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VII.2.5. - PEKERJAAN SANITARY

VII.2.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan kelengkapan material


bantu (adukan, plesteran, acian, nad, sealan, grouting, bahan bantu pengubung
(doble niple) yang berhubungan dengan instalasi ME dan lainnya berikut
pemasangan dan perapihannya.

II
Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

I Lantai 1

- Wastafel Set setara ex TOTO LW549J bh 1.00 3,644,970 3,644,970 -


- Closet Duduk Set setara ex. TOTO CW860NJ/SW861JP bh 1.00 3,385,100 3,385,100 -
- Floor Drain setara ex. TOTO TX 1 BN bh 2.00 385,700 771,400 -
- Tissue Holder setara ex. TX 720 ACRB bh 1.00 267,820 267,820 -

- Jetwasher setara ex. TOTO TB 19 CSN bh 1.00 581,660 581,660 -


- Faucet setara ex. TOTO TX 108LDN bh 1.00 1,301,490 1,301,490 -
- Shower set setara ex. TOTO TX 721 AN + TX 432 SHBR bh 1.00 2,122,450 2,122,450 -

12,074,890 -
DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR ADMINISTR Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VIII.2.6. - PEKERJAAN LAIN-LAIN

VIII.2.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai


gambar dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Cermin
Kaca cermin tebal 6mm, lengkap dengan bevel bagian pinggir, berikut
lapisan belakang dari multiplek tebal 12 mm, berikut sealant, bracket, dll
termasuk alat-alat bantu lainnya dengan peralatan dan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :

Lantai 1
- Toilet (uk. 1000x1000 mm) unit 1.00 800,216.20 800,216 -

2 Meja Lavatory
Meja Lavatory lapis keramik tebal 180 mm, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
Lantai 1
- Toilet (uk. 1000x478 mm) unit 1.00 408,110 408,110 -

DAFTAR No. VIII.2.6. - PEKERJAAN LAIN-LAIN 1,208,326 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR Vol Vol (+/-) Harsat Rp Rp (+/-)
ADMINISTRASI

DAFTAR No. VII.2.7. - PEKERJAAN ATAP CANOPY

VII.2.7.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari


konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Atap

Atap UPVC ex Alderon berikut alat bantu dengan peralatan


perlengkapan sesuai dengan spesifikasi dan gambar pada :

Roof top
- Kantor Administrasi m2 88.77 (0.77) 300,498 26,675,246 (231,384)

DAFTAR No. VII.2.7. - PEKERJAAN ATAP CANOPY 26,675,246 (231,384)


Dipindahkan ke Penjumlahan Total
DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR ADMINISTRAS Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VII.2.8 - PEKERJAAN FAÇADE

VII.2.8.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber

gasket (sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci
& alat-alat penggantung, perlengkapan yang dibutuhkan seperti
mur, baut, handle, engsel, kait angin, sealant, dan
kelengkapannya., rubber gasket (sealant), neoprene, penyetelan
dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di


dalam daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk alat


penggantung (ironmongery sets) dan sistem kunci (keying system)
dan pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan


sketch detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari
peserta tender, seperti merk dan jenis kunci ataupun alat-alat
penggantung, dll..

A GRC
Rib cetak GRC finishing cat acrylic emultion berikut alat bantu
dengan peralatan perlengkapan sesuai dengan spesifikasi dan
gambar pada :
Dinding samping
- Kantor administrasi m2 70.10 1.21 686,690 48,136,969 830,895

B Cat Weathershield
Finishing cat weathershiled berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :
Dinding depan dan belakang
- Eksterior m2 37.11 13.30 29,490 1,094,374 392,099

DAFTAR NO. VII.2.8 - PEKERJAAN FAÇADE 49,231,343 1,222,994


Dipindahkan ke Penjumlahan Total
DAFTAR No. VIII.1 - PEKERJAAN STRUKTUR QUARANTINE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VIII.1.1 - PEKERJAAN TANAH

VIII.1.1.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko


longsoran, volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah


termasuk kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi


dan tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VIII.1.1 ( 248 ) TANAH


DAFTAR No. VIII.1 - PEKERJAAN STRUKTUR QUARANTINE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VIII.1.1 - PEKERJAAN TANAH


A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan m2 162.06 - 11,130 1,803,658 -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 59.84 - 55,640 3,329,498 -
- Pile Cap m3 28.51 - 55,640 1,586,408 -
- Tie Beam m3 5.87 5.31 55,640 326,829 295,448

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai inc Tie Beam m3 1.78 - 272,340 484,765 -
- Pondasi Batu kali m3 5.44 - 272,340 1,481,530 -
- Pile Cap m3 1.20 - 272,340 326,808 -

Urugan tanah untuk mencapai level yang diinginkan, termasuk pemadatan,


dengan memaksimalkan tanah dipakai dari bekas galian serta tanah dari
luar site jika diperlukan sesuai spek dan gambar
- Pondasi Batu kali m3 6.62 - 55,648 368,111 -
- Pile Cap m3 24.29 - 55,648 1,351,776 -
- Tie Beam m3 - 55,648 - -

D Pek. Lain - Lain


D.1 Pek. Bobok kepala tiang Pondasi Pancang

Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar

- Mini Pile diameter 25 cm ttk - exclude - -


D.2 Pekerjaan Anti rayap
Anti rayap pada Lantai dan dinding basement , termasuk alat - alat bantu, m2 162.06 - 16,690 2,704,781 -
peralatan perlengkapan sesuai spesifikasi dan gambar

D.3 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan
sesuai spesifikasi dan gambar (Kontraktor diminta untuk melampirkan
breakdown harganya) Ls 1.00 - exclude - -

DAFTAR No. VIII.1.1 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 13,764,163 295,448

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VIII.1.1 ( 249 ) TANAH


DAFTAR No. VIII.1 - PEKERJAAN STRUKTUR QUARANTINE ST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VIII.1.2 - PEKERJAAN STRUKTUR BETON

VIII.1.2.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VIII.1.2 ( 250 ) BETON


DAFTAR No. VIII.1 - PEKERJAAN STRUKTUR QUARANTINE ST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VIII.1.2 - PEKERJAAN STRUKTUR BETON

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam m3 0.89 - 667,780 594,324 -
2) Pile cap m3 0.60 - 667,780 400,668 -

B Beton mutu K-300 :


1) Pile cap m3 4.22 (1.22) 759,480 3,205,309 (926,869)
2) Tie beam m3 2.99 2.60 759,480 2,269,326 1,977,686
3) Pelat, pada:
- Lantai dasar m3 17.64 - 759,480 13,397,227 -

C Beton mutu K-350 :


3) Balok, pada:
- Lantai 2 m3 3.63 0.91 782,410 2,841,713 710,428

4) Kolom, pada:
- Lantai 1 m3 3.02 1.30 782,410 2,366,008 1,014,003

PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada:
- Lantai 1 m2 147.00 - 53,220 7,823,340 -

A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:


1) Pile cap kg 648.07 (235.26) 8,859 5,740,912 (2,084,049)
2) Tie beam kg 706.91 79.12 8,859 6,262,127 700,873

3) Balok, pada:
- Lantai 2 kg 549.14 110.14 8,859 4,864,563 975,679

4) Kolom, pada:
- Lantai dasar kg 505.10 189.72 8,859 4,474,449 1,680,642

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap m2 28.27 (16.27) 84,790 2,397,183 (1,379,703)
2) Sisi tegak Tie Beam m2 29.88 26.04 84,790 2,533,525 2,207,932

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada:
- Lantai dasar (Bawah pelat, bawah balok dan sisi tegak) m2 5.88 - 100,570 591,352 -

2) Kolom, pada:
- Lantai dasar m2 40.32 17.28 129,920 5,238,374 2,245,018

3) Balok (sisi tegak), pada:


- Lantai 2 m2 36.32 (0.00) 104,000 3,777,280 (0)

PEKERJAAN LAIN-LAIN (Provisional)


Water Proofing Integral termasuk sesuai dengan gambar dan
A
spesifikasi, pada :
1) Pelat lantai dasar m3 17.64 - 100,170 1,766,999 -
2) Pile Cap m3 4.22 - 100,170 422,757 -

B Pondasi Batu Kali


1) Pondasi Batu Kali m3 24.48 - 611,910 14,979,557 -
2) Pasangan Aanstamping t=15cm m3 10.88 - 398,440 4,335,027 -
3) Beton tumbuk m3 4.90 - 720,190 3,526,050 -
4) Angkur D13-500 kg 57.10 - 18,920 1,080,259 -

DAFTAR NO. VIII.1.2 - PEKERJAAN STRUKTUR BETON


Dipindahkan ke Penjumlahan Total 94,888,330 7,121,639

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VIII.1.2 ( 251 ) BETON


DAFTAR No. VIII.1 - PEKERJAAN STRUKTUR QUARANTIN Vol Vol (+/-) Harsat Rp Rp

DAFTAR NO. VIII.1.3 - PEKERJAAN STRUKTUR BAJA

VIII.1.3.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-
lubang baut, perapihan dengan gerinda, penyediaan
peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi


dan pengiriman ke lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi

I Canopy Atap
1) WF 250 x 125 x 6 x 9 Kg 2,237.76 18,364 41,093,762 -
2) WF 200 x 100 x 5,5 x 8 Kg 2,989.60 18,364 54,900,396 -
3) HB 200 x 200 x 8 x 12 Kg 239.52 18,364 4,398,496 -
4) Gording CNP 150 x 50 x 20 x 2,3 Kg 1,050.00 18,364 19,281,983 -
5) Plate 6 mm Kg 130.56 17,807 2,324,944 -
6) Plate 8 mm Kg 50.24 17,807 894,639 -
7) Plate 10 mm Kg 28.26 17,807 503,235 -
8) Plate 12 mm Kg 386.26 17,807 6,878,212 -
9) Stifner 8 mm Kg 77.24 17,807 1,375,508 -
10) Stifner 12 mm Kg 51.58 17,807 918,571 -
11) Trekstang dia 10mm Kg 75.46 17,807 1,343,733 -
12) Bracing dia 16mm Kg 119.95 18,920 2,269,415 -
13) Spanskrup Bh 28.00 18,920 529,768 -
14) Angkur M20 L = 660mm Bh 32.00 222,591 7,122,926 -
15) Baut M12 Bh 432.00 31,163 13,462,330 -
16) Baut M 16 Bh 352.00 31,163 10,969,306 -
17) Nonshrink Grout, T = 25 mm, Uk 300 x 300mm titik 8.00 50,083 400,665 -
18) Cat Dasar (Zincromate) Kg 7,436.43 3,339 24,829,293 -
18) Cat Dasar (Zincromate) Kg 7,436.43 3,339 24,829,293 -

DAFTAR NO. VIII.1.3 - PEKERJAAN STRUKTUR BAJA 218,326,475 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VIII.1.3 ( 252 ) BAJA


DAFTAR No. VIII.2 - PEKERJAAN ARSITEKTUR Vol Vol (+/-) Harsat Rp Rp (+/-)
QUARANTINE STABLE

DAFTAR NO. VIII.2.1. - PEKERJAAN DINDING

VIII.2.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah termasuk


adukan biasa atau drymix, kolom praktis, ringbalk, angkur,
sparing dan semua pekerjaan bantu yang berhubungan dengan
pekerjaan dinding tersebut.

II Harga satuan plesteran biasa atau drymix sudah termasuk acian,


skonengan, tali air , ketrikan atau bobokan beton maupun bata ,
kawat ayam (jika diperlukan) dan semua pekerjaan bantu yang
berhubungan dengan plesteran. Volume plesteran dan acian
sudah ditambahkan 10cm di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit, marmer,


keramik, porselin) sudah termasuk adukan, cor beton,perekat
(calbond), angkur, kawat pengikat alumunium fixing pada dinding
dengan ketinggian lebih dari 2m, pemotongan, pinggulan, adu
manis, naad, dan alat bantu lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk dinding


kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian


cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi.

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. primacon,


termasuk dinding penebalan,urinoir, perekat, adukan kering
kolom
- Lantaidan
1 balok praktis sesuai spesifikasi dan gambar : m2 205.03 22.67 103,480 21,216,800 2,345,876

II PEK. PELAPIS DINDING

A Plesteran dan Acian, Plesteran halus berikut acian halus,


termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :

- Dinding dalam m2 60.58 77.79 61,540 3,727,822 4,787,344


- Area Exterior m2 134.69 0.05 61,540 8,288,823 3,077

A Rubber math 1,2 m berikut acian halus, termasuk peralatan dan


perlengkapan sesuai spesifikasi dan gambar pada :

- Dinding dalam m2 91.48 5.89 389,535 35,634,663 2,293,582

B Pengecatan dengan fin. cat Acrylic emulsion paint ex.setara ICI /


Jotun tipe ambience majestic, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :

- Lantai 1
Horse Box 1 m2 30.65 0.15 18,360 562,734 2,818
Horse Box 2 m2 28.75 0.15 18,360 527,850 2,681
Horse Box 3 m2 30.65 0.15 18,360 562,734 2,818
Horse Box 4 m2 30.65 0.15 18,360 562,734 2,818
Horse Box 5 m2 28.75 0.15 18,360 527,850 2,681
Horse Box 6 m2 30.65 0.15 18,360 562,734 2,818
Coridor m2 15.29 44.84 18,360 280,644 823,306

DAFTAR NO. VIII.2.1. - PEKERJAAN DINDING 72,455,387 10,269,820


Dipindahkan ke Penjumlahan Total
DAFTAR No. VIII.2 - PEKERJAAN ARSITEKTUR Vol Vol (+/-) Harsat Rp Rp (+/-)
QUARANTINE STABLE

DAFTAR No. VIII.2 - PEKERJAAN ARSITEKTUR QUARANTINE STABLE

VIII.2.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis sekeliling
pintu & jendela, dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU KAYU
Pintu Kayu P1 Terdiri dari 1 pintu dan 2 daun pintu, ukuran
2628x2400 wood clear glass lengkap terpasang termasuk,
hardware,
- Lantai 1 accesories dan perlengkapan bantu lainnya sesuai unit 2.00 - 7,456,813 14,913,626 -

Hardware :
Lever handle art-LH UL306/22 mm SS psg 1.00 1.00 Include
Lockcase Calfis art 17180.55 SS bh 1.00 1.00 Include
Cylinder Calfis art-17140.62 S. Nickel bh 1.00 1.00 Include
Hinges Gracia BB 5"x3"3" mm SS bh 8.00 8.00 Include
Flush bolt Calfis 150/350 mm SN set 1.00 1.00 Include
Door closer Calfis CFS 2002 RA Silver bh 1.00 1.00 Include

B JENDELA

Jendela J1 ukuran 1500x1000 Kusen Alumunium 40mm Clear


Anodized, Daun Jendela Alumunium, besi bulat 1,5" lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya
- Lantai sesuai
1 spesifikasi dan gambar pada : unit 4.00 - 1,558,745 6,234,980 -

Jendela J2 ukuran 4150x2462 Kusen Alumunium 40mm Clear


Anodized, lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 2.00 - 10,608,818 21,217,636 -

C PINTU JENDELA

Jendela PJ1 ukuran 3350x2400, besi hollow Ø20, pipa besi Ø50
lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 6.00 - 8,354,873 50,129,236 -

DAFTAR No. VIII.2 - PEKERJAAN ARSITEKTUR QUARANTINE STABLE 92,495,477 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. VIII.2 - PEKERJAAN ARSITEKTUR QUARANTINE STA Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VIII.2.3 - PEKERJAAN LANTAI

VIII.2.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

A PAVING BLOCK

Paving Block uk 210 x 210 x 80mm Setara ex Cisangkan,


termasuk alat-alat bantu lainnya dengan peralatan terpasang
sesuai spesifikasi dan gambar pada :

- Horse Box m2 94.07 1.33 248,600 23,385,557 330,883


- Koridor m2 45.02 0.66 248,600 11,192,594 163,454
- Teras (Provisional) m2 17.40 - 248,600 4,325,640 -

DAFTAR NO. VIII.2.3 - PEKERJAAN LANTAI 38,903,790 494,337


Dipindahkan ke Penjumlahan Total
DAFTAR No. VIII.2 - PEKERJAAN ARSITEKTUR QUARANTINE Vol Vol (+/-) Harsat Rp Rp (+/-)
STABLE

DAFTAR NO. VIII.2.4 - PEKERJAAN PLAFOND

VIII.2.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A Beton exposed aci halus, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai dengan spesifikasi dan gambar pada :

- Horse Box m2 94.07 1.33 33,950 3,193,643 4,250,691


- Koridor m2 45.02 (0.12) 33,950 1,528,514 (187,243)

DAFTAR NO. VIII.2.4 - PEKERJAAN PLAFOND 4,722,157 4,063,448


Dipindahkan ke Penjumlahan Total
DAFTAR No. VIII.2 - PEKERJAAN ARSITEKTUR QUARANTINE S Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VIII.2.5. - PEKERJAAN SANITARY

VIII.2.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan


kelengkapan material bantu (adukan, plesteran, acian, nad, sealan,
grouting, bahan bantu pengubung (doble niple) yang berhubungan
dengan instalasi ME dan lainnya berikut pemasangan dan
perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Sanitary -

DAFTAR NO. VIII.2.5. - PEKERJAAN SANITARY - -


Dipindahkan ke Penjumlahan Total
DAFTAR No. VIII.2 - PEKERJAAN ARSITEKTUR QUARANTINE STA Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. VIII.2.6. - PEKERJAAN LAIN-LAIN

VIII.2.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai


gambar dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material
bantu dan kelengkapan lainnya, sesuai spesifkasi & gambar pada:
(Provisional)
- Lantai Atap m2 200.70 946,014 189,864,928 -

2 Grill (Provisional)
Grill ukuran 300 mm, sesuai gambar dan spesifikasi, pada :
Lantai 1
- Horse Box m' 20.10 333,887 6,711,132 -

3 PERLENGKAPAN
Tempat minum kuda, sesuai gambar dan spesifikasi pada :
Lantai 1
- Horse Box bh 6.00 237,872 1,427,234 -

DAFTAR No. VIII.2.6. - PEKERJAAN LAIN-LAIN 198,003,294 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. VIII.2 - PEKERJAAN ARSITEKTUR Vol Vol (+/-) Harsat Rp Rp (+/-)
QUARANTINE STABLE

DAFTAR No. VIII.2.8. - PEKERJAAN ATAP CANOPY

VIII.2.8.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari


konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Atap

Atap UPVC ex Alderon berikut alat bantu dengan peralatan


perlengkapan sesuai dengan spesifikasi dan gambar pada :

Roof top
- Quarantine stable m2 188.02 44.50 300,498 56,499,716 13,372,180

DAFTAR No. VIII.2.8. - PEKERJAAN ATAP CANOPY 56,499,716 13,372,180


Dipindahkan ke Penjumlahan Total
DAFTAR No. VIII.2 - PEKERJAAN ARSITEKTUR QUARANTINE STABL Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. VIII.2.9 - PEKERJAAN FAÇADE

VIII.2.9.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber

gasket (sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya.,
rubber gasket (sealant), neoprene, penyetelan dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di


dalam daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk alat


penggantung (ironmongery sets) dan sistem kunci (keying system)
dan pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan


sketch detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari
peserta tender, seperti merk dan jenis kunci ataupun alat-alat
penggantung, dll..

A GRC
Rib cetak GRC finishing cat weathershild berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar
pada :
Dinding depan
- Quarantine stable m2 103.08 4.46 686,690 70,784,005 3,062,637

B Cat Weathershield (Provisional)


Finishing cat weathershiled berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :

Dinding depan dan belakang


- Quarantine stable m2 65.09 - 29,490 1,919,504 -
- Eksterior m2 134.69 - 29,490 3,972,008 -

C WOOD PLASTIC COMPOSITE


Wood plastic Composite berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :

- Dinding Exterior m2 11.29 0.71 834,718 9,423,965 592,650

D CAT KAMPROT
Cat Kamprot berikut alat bantu dengan peralatan perlengkapan
sesuai dengan spesifikasi dan gambar pada :

- Dinding Exterior m2 11.29 0.71 61,213 691,091 43,461

E KAWAT NYAMUK STAINLESS STEEL


Kawat Nyamuk berikut alat bantu dengan peralatan perlengkapan
sesuai dengan spesifikasi dan gambar pada :

- Dinding Exterior m2 10.68 30.10 306,063 3,268,755 9,212,503

DAFTAR NO. VIII.2.9 - PEKERJAAN FAÇADE 90,059,328 12,911,251


Dipindahkan ke Penjumlahan Total
DAFTAR No. IX.1 - PEKERJAAN STRUKTUR COVERED TRAINING AREA Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. IX.1.1 - PEKERJAAN TANAH

IX.1.1.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko longsoran,
volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah termasuk
kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi dan
tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan sesuai
gambar spesifikasi

A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan m2 201.66 - 11,130 2,244,389 -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan) untuk
urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi telapak m3 59.54 (35.73) 55,640 3,312,527 (1,988,017)
- Balok m3 42.48 - 55,640 2,363,587 -

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu berikut
peralatan perlengkapan sesuai spesifikasi dan gambar
- Tangga tribun m3 8.34 - 272,340 2,271,316 -
- Ramp m3 1.78 - 272,340 484,765 -
- Pondasi telapak m3 3.97 3.97 272,340 1,080,917 1,080,917
- Balok m3 5.66 (0.41) 272,340 1,542,534 (111,115)

Urugan tanah untuk mencapai level yang diinginkan, termasuk pemadatan,


dengan memaksimalkan tanah dipakai dari bekas galian serta tanah dari luar
site jika diperlukan sesuai spek dan gambar
- Tangga tribun m3 81.67 - 55,648 4,544,761 -
- Ramp m3 0.08 - 55,648 4,396 -
- Pondasi telapak m3 49.61 - 55,648 2,760,829 -

DAFTAR No. IX.1.1 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 20,610,022 (1,018,214)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-IX.1.1 ( 261 ) TANAH


DAFTAR No. IX.1 - PEKERJAAN STRUKTUR COVERED TRAINING Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IX.1.2 - PEKERJAAN STRUKTUR BETON

IX.1.2.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- IX.1.2 ( 262 ) BETON


DAFTAR No. IX.1 - PEKERJAAN STRUKTUR COVERED TRAINING Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. IX.1.2 - PEKERJAAN STRUKTUR BETON

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pondasi telapak m3 1.98 1.98 667,780 1,325,209 1,325,209
2) Di bawah balok m3 2.83 (0.20) 667,780 1,891,153 (136,227)

B Beton mutu K-300 :


1) Pondasi telapak m3 9.92 9.92 759,480 7,535,940 7,535,940
2) Kolom pedestal m3 9.36 10.80 759,480 7,108,733 8,202,384
3) Balok m3 31.10 0.43 759,480 23,622,866 328,095

PEKERJAAN PEMBESIAN
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pondasi telapak kg 1,164.52 1,173.62 8,859 10,315,893 10,396,501
2) Kolom pedestal kg 2,249.69 (152.12) 8,859 19,928,842 (1,347,573)
3) Balok kg 4,908.69 56.94 8,859 43,483,660 504,443

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Pondasi Telapak m2 18.90 18.90 84,790 1,602,531 1,602,531

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Kolom pedestal m2 93.60 108.00 129,920 12,160,512 14,031,360
2) Sisi tegak Balok m2 201.60 - 104,000 20,966,400 -

DAFTAR NO. IX.1.2 - PEKERJAAN STRUKTUR BETON


Dipindahkan ke Penjumlahan Total 149,941,740 42,442,664

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- IX.1.2 ( 263 ) BETON


DAFTAR No. IX.1 - PEKERJAAN STRUKTUR COVERED Vol Vol (+/-) Harsat Rp Rp (+/-)
TRAINING AREA

DAFTAR NO. IX.1.3 - PEKERJAAN STRUKTUR BAJA

IX.1.3.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang diperlukan,
seperti : pengelasan, pembuatan lubang-lubang baut, perapihan
dengan gerinda, penyediaan peralatan bantu untuk pemasangan
dan mendirikan atap+rangka serta sisa terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi dan


pengiriman ke lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi

I PEKERJAAN STRUKTUR BAJA (Provisional Quantity)


1) CNP 150 x 50 x 20 x 2,3 Kg 34,320.00 18,364 630,245,386 -
2) Ikatan angin besi dia 16mm Kg 692.83 18,364 12,722,987 -
3) Spanskrup dia 16mm Bh 40.00 18,920 756,811 -
4) WF 200X100X5,5X8 Kg 33,217.56 18,364 610,000,460 -
5) WF 200X200X8X12 Kg 11,761.93 18,364 215,993,633 -
6) Siku. 60X60X5 Kg 10,019.65 18,364 183,998,708 -
7) Siku. 50X50X5 Kg 8,354.32 18,364 153,417,006 -
8) baut 2 m12 bh 6,548.00 31,163 204,054,019 -
9) plat t=8mm kg 5,388.13 17,807 95,948,180 -
10) plat t=12mm kg 3,028.34 17,807 53,926,632 -
11) L 40x40x4 @400mm kg 742.70 18,364 13,638,753 -
12) angkur baut 6 m20 p=60cm bh 216.00 222,591 48,079,750 -
13) plat t=12mm kg 211.95 17,807 3,774,260 -
14) Non Shrink Groute uk 30cm x 30cm , tebal 25mm titik 36.00 50,083 1,802,991 -
15) Cat Dasar (Zincromate) Kg 107,737.41 3,339 359,721,370 -
15) Cat Dasar Finsh Kg 107,737.41 3,339 359,721,370 -

CATATAN
Pekerjaan STRUKTUR COVERED TRAINING ARENA adalah
Pekerjaan STRUKTUR COVERED TRAINING ARENA yang sudah
ada dng ukuran 38 m x 58 m, dipindahkan ketempat lain dan
dimodifikasi menjadi ukuran 48 m x 80 m dengan memanfaatkan
Struktur yang masih dapat dipakai

DAFTAR NO. IX.1.3 - PEKERJAAN STRUKTUR BAJA 2,947,802,315 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- IX.1.3 ( 264 ) BAJA


DAFTAR No. IX.2 - PEKERJAAN ARSITEKTUR COVERED Vol Vol (+/-) Harsat Rp Rp (+/-)
TRAINING ARENA

DAFTAR NO. IX.2.1. - PEKERJAAN DINDING

IX.2.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah termasuk


adukan biasa atau drymix, kolom praktis, ringbalk, angkur,
sparing dan semua pekerjaan bantu yang berhubungan dengan
pekerjaan dinding tersebut.

II Harga satuan plesteran biasa atau drymix sudah termasuk acian,


skonengan, tali air , ketrikan atau bobokan beton maupun bata ,
kawat ayam (jika diperlukan) dan semua pekerjaan bantu yang
berhubungan dengan plesteran. Volume plesteran dan acian
sudah ditambahkan 10cm di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit, marmer,


keramik, porselin) sudah termasuk adukan, cor beton,perekat
(calbond), angkur, kawat pengikat alumunium fixing pada dinding
dengan ketinggian lebih dari 2m, pemotongan, pinggulan, adu
manis, naad, dan alat bantu lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk dinding


kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian


cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi.

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. Primacon,


termasuk dinding penebalan,urinoir, perekat, adukan kering
kolom dantribun
- Tangga balok praktis sesuai spesifikasi dan gambar : m2 205.03 (30.31) 103,480 21,216,800 (3,136,774)

II PEK. PELAPIS DINDING

Ceramic Tile 400x400 setara ex Roman unpolished, sesuai


B
spesifikasi dan gambar ;
- Dinding dalam dan luar m2 126.56 0.26 139,520 17,657,651 36,275

DAFTAR NO. IX.2.1. - PEKERJAAN DINDING 38,874,451 (3,100,499)


Dipindahkan ke Penjumlahan Total
DAFTAR No. IX.2 - PEKERJAAN ARSITEKTUR COVERED Vol Vol (+/-) Harsat Rp Rp (+/-)
TRAINING ARENA

DAFTAR NO.IX.2.2 - PEKERJAAN LANTAI

IX.2.2.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

A CERAMIC TILE

Homogenous Tile 400x400 ex setara Indogress unpolished,


sesuai spesifikasi dan gambar, termasuk alat-alat bantu lainnya
dengan peralatan terpasang sesuai spesifikasi dan gambar
pada :

- Lantai Tribun m2 64.57 2.89 401,270 25,910,004 1,159,670


- Tangga tribun m2 117.79 2.22 401,270 47,265,593 889,214
- Ramp m2 43.19 0.15 401,270 17,330,851 61,796

B SPECIAL FOOTING

LAPISAN BAWAH
1 Porous asphalt tebal 50 mm m2 3,518.32 86.68 166,832 586,969,346 14,461,022
2 Geotextile non woven pori maks 180 gr/m2 m2 3,518.32 86.68 22,259 78,314,789 1,929,423
3 Gravel 2/3 tebal 125 mm m2 3,518.32 86.68 52,300 184,008,918 4,533,383
4 Geotextile non woven pori maks 180 gr/m2 m2 3,518.32 86.68 22,259 78,314,789 1,929,423
5 Sub base dia 15-30 cm Tebal 445 mm m2 3,518.32 86.68 168,831 594,002,797 14,634,304

B SPECIAL FOOTING :
1 Pasir dengan campuran serat fibre geotextile dan anti debu m2 3,518.32 BY OTHER
( Material Ex Import )

C PAGAR

1 Concrete tebal 30x65cm (Provisional) m3 48.28 - 782,410 37,776,320 -


2 Railing tinggi 1600mm dengan pipa pembagi co extrude m' 247.60 2.56 401,475 99,405,164 1,027,776
3 PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght max
Bekisting kayu m2 408.54 100,570.00 41,086,868 -

4 Railing tinggi 1600mm dengan pipa pembagi co extrude m' 247.60 973,840.00 241,122,784 -
PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght max
4m co extrude PVC/ASA dan kelengkapan lainnya sesuai
gambar dan spesifikasi

DAFTAR NO.IX.2.2 - PEKERJAAN LANTAI 2,031,508,224 40,626,010


Dipindahkan ke Penjumlahan Total
DAFTAR No. IX.2 - PEKERJAAN ARSITEKTUR COVERED Vol Vol (+/-) Harsat Rp Rp (+/-)
TRAINING ARENA

DAFTAR No. IX.2.3. - PEKERJAAN ATAP CANOPY

IX.2.3.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari


konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Penutup Atap Baru

Atap UPVC ex Alderon berikut alat bantu dengan peralatan


perlengkapan sesuai dengan spesifikasi dan gambar pada :

Roof top
- Covered Training Arena m2 3,963.25 844 300,498 1,190,950,425 253,605,655

DAFTAR No. IX.2.3. - PEKERJAAN ATAP CANOPY 1,190,950,425 253,605,655


Dipindahkan ke Penjumlahan Total
DAFTAR No. X.1 - PEKERJAAN STRUKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. X.1.1 - PEKERJAAN TANAH

X.1.1.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko


longsoran, volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah


termasuk kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi


dan tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-X.1.1 ( 268 ) TANAH


DAFTAR No. X.1 - PEKERJAAN STRUKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. X.1.1 - PEKERJAAN TANAH


A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan (Tipe 1A, 1B, dan 1C) m2 58.12 - 11,130 646,806 -
- Lokasi area lahan (Tipe 2) m2 9.92 - 11,130 110,428 -
- Lokasi area lahan (Tipe 3) m2 21.75 - 11,130 242,068 -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu
dan kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m (Tipe 1A, 1B dan 1C) m3 67.32 - 55,640 3,745,685 -
- Pondasi Batu kali sedalam 1,1 m Tipe 2 (provisional) m3 13.38 - 55,640 744,241 -
- Pondasi Batu kali sedalam 1,1 m Tipe 3 (provisional) m3 16.63 - 55,640 925,404 -
- Pile Cap (Tipe 1A, 1B dan 1C) m3 9.50 - 55,640 528,803 -
- Pile Cap Tipe 2 (provisional) m3 2.11 - 55,640 117,512 -
- Pile Cap Tipe 3 (provisional) m3 2.11 - 55,640 117,512 -
- Tie Beam (Tipe 1A, 1B dan 1C) m3 5.05 (2.28) 55,640 280,926 (126,692)
- Tie Beam Tipe 2 (provisional) m3 1.00 - 55,640 55,818 -
- Tie Beam Tipe 3 (provisional) m3 1.25 - 55,640 69,405 -

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar

- Dibawah plat lantai inc Tie Beam (Tipe 1A, 1B dan 1C) m3 17.73 - 272,340 4,828,588 -
- Dibawah plat lantai inc Tie Beam Tipe 2 (provisional) m3 0.30 - 272,340 82,791 -
- Dibawah plat lantai inc Tie Beam Tipe 3 (provisional) m3 0.38 - 272,340 102,945 -
- Pondasi Batu kali (Tipe 1A, 1B dan 1C) m3 6.12 - 272,340 1,666,721 -
- Pondasi Batu kali Tipe 2 (provisional) m3 1.22 - 272,340 331,165 -
- Pondasi Batu kali Tipe 3 (provisional) m3 1.51 - 272,340 411,778 -
- Pile Cap (Tipe 1A, 1B dan 1C) m3 0.32 - 272,340 88,238 -
- Pile Cap Tipe 2 (provisional) m3 0.07 - 272,340 19,608 -
- Pile Cap Tipe 3 (provisional) m3 0.07 - 272,340 19,608 -

Urugan tanah untuk mencapai level yang diinginkan, termasuk


pemadatan, dengan memaksimalkan tanah dipakai dari bekas galian
serta tanah dari luar site jika diperlukan sesuai spek dan gambar
- Pile Cap (Tipe 1A, 1B dan 1C) m3 7.99 - 55,648 444,675 -
- Pile Cap Tipe 2 (provisional) m3 1.78 - 55,648 98,817 -
- Pile Cap Tipe 3 (provisional) m3 1.78 - 55,648 98,817 -

D Pek. Lain - Lain


D.1 Pek. Bobok kepala tiang Pondasi Pancang

Bobok kepala Borpile, termasuk buang keluar lokasi proyek sesuai


spesifikasi dan gambar

- Borpile diameter 600 mm ttk - exclude - -


D.2 Pekerjaan Anti rayap
Anti rayap pada Lantai dan dinding basement , termasuk alat - alat m2 89.79 - 16,690 1,498,562 -
bantu, peralatan perlengkapan sesuai spesifikasi dan gambar

D.3 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan
sesuai spesifikasi dan gambar (Kontraktor diminta untuk melampirkan
breakdown harganya) Ls 1.00 - exclude - -

DAFTAR No. X.1.1 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 17,276,921 (126,692)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-X.1.1 ( 269 ) TANAH


DAFTAR No. X.1 - PEKERJAAN STRUKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.1.2 - PEKERJAAN STRUKTUR BETON

X.1.2.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- X.1.2 ( 270 ) BETON


DAFTAR No. X.1 - PEKERJAAN STRUKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.1.2 - PEKERJAAN STRUKTUR BETON

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam (Tipe 1A, 1B dan 1C) m3 3.47 - 667,780 2,313,858 -
2) Di bawah pelat lantai, Tie beam Tipe 2 (provisional) m3 0.99 - 667,780 658,698 -
3) Di bawah pelat lantai, Tie beam Tipe 3 (provisional) m3 1.24 - 667,780 827,780 -
4) Pile cap + kolom pedestal (Tipe 1A, 1B dan 1C) m3 0.16 (0.11) 667,780 108,180 (72,120)
5) Pile cap + kolom pedestal Tipe 2 (provisional) m3 0.04 - 667,780 24,040 -
6) Pile cap + kolom pedestal Tipe 3 (provisional) m3 0.04 - 667,780 24,040 -

B Beton mutu K-300 :


1) Pile cap + kolom pedestal (Tipe 1A, 1B dan 1C) m3 1.51 (1.24) 759,480 1,149,188 (944,129)
2) Pile cap + kolom pedestal Tipe 2 (provisional) m3 0.34 - 759,480 255,375 -
3) Pile cap + kolom pedestal Tipe 3 (provisional) m3 0.34 - 759,480 255,375 -
4) Tie beam (Tipe 1A, 1B dan 1C) m3 2.72 (1.34) 759,480 2,067,001 (1,014,361)
5) Tie beam Tipe 2 (provisional) m3 0.54 - 759,480 407,385 -
6) Tie beam Tipe 3 (provisional) m3 0.67 - 759,480 508,548 -
7) Pelat, pada: (Tipe 1A, 1B dan 1C) -
- Lantai 1 m3 6.48 - 759,480 4,921,430 -
8) Pelat, pada: Tipe 2 (provisional) -
- Lantai 1 m3 1.08 - 759,480 820,238 -
9) Pelat, pada: Tipe 3 (provisional) -
- Lantai 1 m3 1.37 - 759,480 1,038,969 -

PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada: (Tipe 1A, 1B dan 1C)
- Lantai 1 m2 54.00 - 53,220 2,873,880 -
2) Pelat, pada: Tipe 2 (provisional)
- Lantai 1 m2 9.00 - 53,220 478,980 -
3) Pelat, pada: Tipe 3 (provisional)
- Lantai 1 m2 11.40 - 53,220 606,708 -

A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:


1) Pile cap + kolom pedestal (Tipe 1A, 1B dan 1C) kg 294.07 (264.63) 8,859 2,605,046 (2,344,216)
2) Pile cap + kolom pedestal Tipe 2 (provisional) kg 65.35 - 8,859 578,899 -
3) Pile cap + kolom pedestal Tipe 3 (provisional) kg 65.35 - 8,859 578,899 -
4) Tie beam (Tipe 1A, 1B dan 1C) kg 632.27 (426.36) 8,859 5,600,991 (3,776,867)
5) Tie beam Tipe 2 (provisional) kg 129.86 - 8,859 1,150,326 -
7) Tie beam Tipe 3 (provisional) kg 157.75 - 8,859 1,397,459 -

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap + kolom pedestal (Tipe 1A, 1B dan 1C) m2 16.65 (14.85) 84,790 1,411,754 (1,259,132)
2) Sisi tegak pile cap + kolom pedestal Tipe 2 (provisional) m2 3.70 - 84,790 313,723 -
3) Sisi tegak pile cap + kolom pedestal Tipe 3 (provisional) m2 3.70 - 84,790 313,723 -
4) Sisi tegak Tie Beam (Tipe 1A, 1B dan 1C) m2 27.22 (13.36) 84,790 2,307,645 (1,132,455)
5) Sisi tegak Tie Beam Tipe 2 (provisional) m2 5.36 - 84,790 454,814 -
6) Sisi tegak Tie Beam Tipe 3 (provisional) m2 6.70 - 84,790 567,754 -

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada: (Tipe 1A, 1B dan 1C)
- Lantai 1 (Bawah pelat, bawah balok dan sisi tegak) m2 6.48 - 100,570 651,694 -
2) Pelat, pada: Tipe 2 (provisional) -
- Lantai 1 (Bawah pelat, bawah balok dan sisi tegak) m2 1.44 - 100,570 144,821 -
3) Pelat, pada: Tipe 3 (provisional) -
- Lantai 1 (Bawah pelat, bawah balok dan sisi tegak) m2 1.63 - 100,570 164,130 -

PEKERJAAN LAIN-LAIN (Provisional)


Water Proofing Integral termasuk sesuai dengan gambar dan
A
spesifikasi, pada :
1) Pelat lantai 1 m3 8.93 - 100,170 894,318 -
2) Pile Cap m3 2.19 - 100,170 218,934 -

PEKERJAAN LAIN-LAIN -Lanjutan

B Pondasi Batu Kali (Tipe 1A, 1B dan 1C)


1) Pondasi Batu Kali m3 27.54 - 611,910 16,852,001 -
2) Pasangan Aanstamping t=15cm m3 12.24 - 398,440 4,876,906 -
3) Beton tumbuk m3 5.51 - 720,190 3,966,807 -
4) Angkur D13-500 kg 65.01 - 18,920 1,230,075 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- X.1.2 ( 271 ) BETON


DAFTAR No. X.1 - PEKERJAAN STRUKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.1.2 - PEKERJAAN STRUKTUR BETON

C Pondasi Batu Kali Tipe 2 (provisional)


1) Pondasi Batu Kali m3 5.47 - 611,910 3,348,372 -
2) Pasangan Aanstamping t=15cm m3 2.43 - 398,440 969,006 -
3) Beton tumbuk m3 1.09 - 720,190 788,176 -
4) Angkur D13-500 kg 13.09 - 18,920 247,592 -

D Pondasi Batu Kali Tipe 3 (provisional)


1) Pondasi Batu Kali m3 6.80 - 611,910 4,163,436 -
2) Pasangan Aanstamping t=15cm m3 3.02 - 398,440 1,204,883 -
3) Beton tumbuk m3 1.36 - 720,190 980,035 -
4) Angkur D13-500 kg 16.17 - 18,920 305,942 -

DAFTAR NO. X.1.2 - PEKERJAAN STRUKTUR BETON


Dipindahkan ke Penjumlahan Total 77,627,831 (10,543,280)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- X.1.2 ( 272 ) BETON


DAFTAR No. X.1 - PEKERJAAN STRUKTUR GUARD
Vol Vol (+/-) Harsat Rp Rp (+/-)
POST
DAFTAR NO. VII.1.3 - PEKERJAAN STRUKTUR BAJA

VII.1.3.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-
lubang baut, perapihan dengan gerinda, penyediaan
peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi dan


pengiriman ke lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi

I Canopy Atap (Tipe 1A, 1B dan 1C)


1) WF 200 x 100 x 5,5 x 8 Kg 632.61 18,364 11,617,119 -
2) WF 150 x 150 x 7 x 10 Kg 992.25 18,364 18,221,474 -
3) Gording CNP 150 x 50 x 20 x 2,3 Kg 360.00 18,364 6,610,966 -
4) Plate 6 mm Kg 58.75 17,807 1,046,225 -
5) Plate 10 mm Kg 20.42 17,807 363,587 -
6) Plate 8 mm Kg 36.17 17,807 644,140 -
7) Stifner 8 mm Kg 113.32 17,807 2,017,971 -
8) Trekstang dia 10mm Kg 26.63 17,807 474,259 -
9) Bracing dia 16mm Kg 132.57 18,920 2,508,301 -
10) Spanskrup Bh 24.00 18,920 454,087 -
11) Angkur M16 L = 500mm Bh 36.00 222,591 8,013,292 -
12) Baut M12 Bh 252.00 31,163 7,853,026 -
13) Nonshrink Grout, T = 25 mm, Uk 300 x 300mm titik 9.00 50,083 450,748 -
14) Cat Dasar (Zincromate) Kg 2,372.73 3,339 7,922,243 -
15) Cat Dasar (Zincromate) Kg 2,372.73 3,339 7,922,243 -

II Canopy Atap Tipe 2 dan 3(Provisional)


1) WF 200 x 100 x 5,5 x 8 Kg 281.16 18,364 5,163,164 -
2) WF 150 x 150 x 7 x 10 Kg 441.00 18,364 8,098,433 -
3) Gording CNP 150 x 50 x 20 x 2,3 Kg 120.00 18,364 2,203,655 -
4) Plate 6 mm Kg 26.11 17,807 464,989 -
5) Plate 10 mm Kg 9.07 17,807 161,594 -
6) Plate 8 mm Kg 16.08 17,807 286,285 -
7) Stifner 8 mm Kg 50.37 17,807 896,876 -
8) Trekstang dia 10mm Kg 11.84 17,807 210,782 -
9) Bracing dia 16mm Kg 88.38 18,920 1,672,201 -
10) Spanskrup Bh 16.00 18,920 302,724 -
11) Angkur M16 L = 500mm Bh 16.00 222,591 3,561,463 -
12) Baut M12 Bh 112.00 31,163 3,490,234 -
13) Nonshrink Grout, T = 25 mm, Uk 300 x 300mm titik 4.00 50,083 200,332 -
14) Cat Dasar (Zincromate) Kg 1,044.01 3,339 3,485,807 -
14) Cat Finish Kg 1,044.01 3,339 3,485,807 -

DAFTAR NO. VII.1.3 - PEKERJAAN STRUKTUR BAJA 109,804,026 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- VII.1.3 ( 273 ) BAJA


DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.1. - PEKERJAAN DINDING

X.2.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah


termasuk adukan biasa atau drymix, kolom praktis, ringbalk,
angkur, sparing dan semua pekerjaan bantu yang berhubungan
dengan pekerjaan dinding tersebut.

II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton maupun
bata , kawat ayam (jika diperlukan) dan semua pekerjaan bantu
yang berhubungan dengan plesteran. Volume plesteran dan
acian sudah ditambahkan 10cm di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit,


marmer, keramik, porselin) sudah termasuk adukan, cor
beton,perekat (calbond), angkur, kawat pengikat alumunium
fixing pada dinding dengan ketinggian lebih dari 2m,
pemotongan, pinggulan, adu manis, naad, dan alat bantu
lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk


dinding kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk pengertian


cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi.

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. primacon,


termasuk dinding penebalan,urinoir, perekat, adukan kering
kolom dan balok praktis sesuai spesifikasi dan gambar :
- Lantai 1
Pos Jaga Type 1A m2 225.83 0.97 103,480 23,369,104 100,160
Pos Jaga Type 1B m2 150.48 0.86 103,480 15,571,753 88,589
Pos Jaga Type 1C m2 70.87 (0.12) 103,480 7,333,141 (12,345)
Pos Jaga Type 2 m2 52.14 0.53 103,480 5,395,541 54,544
Pos Jaga Type 3 m2 71.39 0.05 103,480 7,387,358 5,461

II PEK. PELAPIS DINDING

A Plesteran dan Acian, Plesteran halus berikut acian halus,


termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :
- Lantai 1
Pos Jaga Type 1A m2 186.21 0.50 61,540 11,459,640 30,647
Pos Jaga Type 1B m2 124.14 0.81 61,540 7,639,760 49,632
Pos Jaga Type 1C m2 57.80 0.78 61,540 3,556,797 47,909
Pos Jaga Type 2 m2 30.11 3.26 61,540 1,852,692 200,897
Pos Jaga Type 3 m2 49.46 0.09 61,540 3,043,799 5,612
- Area Exterior
Pos Jaga Type 1A m2 156.71 1.02 61,540 9,643,718 62,525
Pos Jaga Type 1B m2 104.47 1.73 61,540 6,429,145 106,403
Pos Jaga Type 1C m2 47.96 0.80 61,540 2,951,489 49,386
Pos Jaga Type 2 m2 32.14 0.38 61,540 1,977,619 23,416
Pos Jaga Type 3 m2 42.79 (0.50) 61,540 2,633,327 (30,493)

Keramik Roman 300x300 setara ex Roman/Mulia tipe standar,


B
sesuai spesifikasi dan gambar ;Provisional

- Lantai 1 (Toilet)
Pos Jaga Type 1A m2 32.97 - 161,560 5,326,633 -
Pos Jaga Type 1B m2 21.98 - 161,560 3,551,089 -
Pos Jaga Type 1C m2 10.99 - 161,560 1,775,544 -
Pos Jaga Type 2 m2 11.95 - 161,560 1,930,642 -
Pos Jaga Type 3 m2 11.47 - 161,560 1,853,093 -

C Pengecatan dengan fin. cat Acrylic emulsion paint ex.setara ICI /


Jotun tipe ambience majestic, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :

- Pos Jaga Type 1A


Security Office m2 92.52 0.77 18,360 1,698,585 14,174
Bedroom m2 78.31 0.23 18,360 1,437,753 4,241
Toilet Room m2 15.39 (0.27) 18,360 282,560 (4,957)
- Pos Jaga Type 1B
Security Office m2 61.68 1.05 18,360 1,132,390 19,306
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.1. - PEKERJAAN DINDING


Bedroom m2 52.21 0.83 18,360 958,502 15,312
Toilet Room m2 10.26 (0.43) 18,360 188,374 (7,932)
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.1. - PEKERJAAN DINDING


- Pos Jaga Type 1C
Security Office m2 26.56 0.06 18,360 487,706 1,129
Bedroom m2 26.10 0.42 18,360 479,251 7,656
Toilet Room m2 5.13 0.54 18,360 94,187 9,914
- Pos Jaga Type 2
Security Office m2 24.60 0.95 18,360 451,573 17,433
Toilet Room m2 5.51 0.58 18,360 101,164 10,649
- Pos Jaga Type 3
Security Office m2 20.48 0.47 18,360 376,022 8,712
Bedroom m2 23.66 1.27 18,360 434,398 23,317
Toilet Room m2 5.32 0.56 18,360 97,675 10,282

DAFTAR NO. X.2.1. - PEKERJAAN DINDING 132,902,025 911,578


Dipindahkan ke Penjumlahan Total
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.2 - PEKERJAAN PINTU dan JENDELA

X.2.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU KAYU
Pintu Kayu P1 Terdiri dari 1 pintu dengan kusen/frame alumunium
ukuran 1000x2400 mm, Plywood lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :

Hardware :
Lever handle art-LH UL 306/22 mm SS psg - -
Lockcase Calfis art-17180.55 SS bh - -
Cylinder Calfis art-17140.62 S Nickel bh - -
Hinges gracia BB 5"x3"x3mm SS bh - -
Door closer Calfis CFS 2002 RA silver bh - -
Friction stay Top hung art-12" psg - -
Rambuncis art-118 silver bh - -

Tipe 1A
- Pintu utama unit 1.00 2.00 2,281,562 2,281,562 4,563,124
- Bedroom unit 1.00 2.00 2,281,562 2,281,562 4,563,124
Tipe 1B
- Pintu utama unit 1.00 1.00 2,281,562 2,281,562 2,281,562
- Bedroom unit 1.00 1.00 2,281,562 2,281,562 2,281,562
Tipe 1C
- Pintu utama unit 1.00 - 2,281,562 2,281,562 -
- Bedroom unit 1.00 - 2,281,562 2,281,562 -
Tipe 2
- Pintu utama unit 1.00 - 2,281,562 2,281,562 -
Tipe 3
- Pintu utama unit 2.00 - 2,281,562 4,563,124 -

Pintu Kusen P2 terdiri dari 1 daun pintu Alumunium 40 mm clear


anodized, ukuran 720x2400 mm, alumunium, lengkap terpasang
termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :

Hardware :
Lever handle art-LH UL 306/22 mm SS psg - - -
Lockcase Calfis art-17180.55 SS bh - - -
Cylinder Calfis art-17140.62 S Nickel bh - - -
Hinges gracia BB 5"x3"x3mm SS bh - - -
Door closer Calfis CFS 2002 RA silver bh - - -
Friction stay Top hung art-12" psg - - -
Rambuncis art-118 silver bh - - -

Tipe 1A
- Toilet unit 1.00 2.00 2,225,914 2,225,914 4,451,829
Tipe 1B
- Toilet unit 1.00 1.00 2,225,914 2,225,914 2,225,914
Tipe 1C
- Toilet unit 1.00 - 2,225,914 2,225,914 -
Tipe 2
- Toilet unit 1.00 - 2,225,914 2,225,914 -
Tipe 3
- Toilet unit 1.00 - 2,225,914 2,225,914 -

B JENDELA
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.2 - PEKERJAAN PINTU dan JENDELA


Jendela J1 ukuran 1000x1500 mm Kusen Alumunium 40 mm Clear
Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR
Jendela NO.
J1 ukuran
X.2.2 -1000x1500
PEKERJAAN mmPINTU
Kusendan
Alumunium
JENDELA
40 mm Clear
Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :

Hardware :
Flush handle art-506 SN bh - - -
Lockcase Calfis art-17136.30 SS bh - - -
Cylinder Calfis art-17140.62 S Nickel bh - - -
Ring kunci art-901 CK SS bh - - -
Track sliding Calfis CL 500/2mtr btg - - -
Bracket BK 110 btg - - -
Roda sliding Calfis Pack 120 (100kg) btg - - -
- Hanger HW 111 (2 pcs)
- Track Buffer with Retained ST 112
- Floor guide FG 115
Tipe 1A
- Lantai 1 unit 2.00 4.00 1,558,700 3,117,400 6,234,800
Tipe 1B
- Lantai 1 unit 2.00 2.00 1,558,700 3,117,400 3,117,400

B JENDELA-Lanjutan

Jendela J1 ukuran 1000x1500 mm Kusen Alumunium 40 mm Clear


Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :

Tipe 1C
- Lantai 1 unit 2.00 - 1,558,700 3,117,400 -
Tipe 2
- Lantai 1 unit 1.00 - 1,558,700 1,558,700 -
Tipe 3
- Lantai 1 unit 1.00 - 1,558,700 1,558,700 -

Jendela J2 ukuran 4850x1500 mm Kusen Alumunium 40 mm Clear


Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :

Tipe 1A
- Lantai 1 unit 1.00 2.00 7,559,913 7,559,913 15,119,826
Tipe 1B
- Lantai 1 unit 1.00 1.00 7,559,913 7,559,913 7,559,913

Jendela J2 ukuran 6000x1500 mm Kusen Alumunium 40 mm Clear


Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :

Tipe 1C
- Lantai 1 unit 1.00 - 9,352,469 9,352,469 -

Jendela J2 ukuran 3645x1500 mm Kusen Alumunium 40 mm Clear


Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :

Tipe 2
- Lantai 1 unit 1.00 - 5,689,419 5,689,419 -

Jendela J2 ukuran 2890 x1500 mm Kusen Alumunium 40 mm


Clear Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm
lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :

Tipe 3
- Lantai 1 unit 1.00 - 4,504,773 4,504,773 -

Jendela J3ukuran 2850x1500 mm Kusen Alumunium 40 mm Clear


Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :

Tipe 1B
- Lantai 1 unit 1.00 1.00 4,442,423 4,442,423 4,442,423
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.2 - PEKERJAAN PINTU dan JENDELA


Jendela J3ukuran 1650x1500 mm Kusen Alumunium 40 mm Clear
Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :

Tipe 1C
- Lantai 1 unit 1.00 - 2,571,929 2,571,929 -
Tipe 2
- Lantai 1 unit 1.00 - 2,571,929 2,571,929 -

Jendela Bovenlight B1 ukuran 500x340 mm lengkap terpasang


termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
Tipe 1A
- Toilet unit 1.00 2.00 176,658 176,658 353,316
Tipe 1B
- Toilet unit 1.00 1.00 176,658 176,658 176,658
Tipe 1C
- Toilet unit 1.00 - 176,658 176,658 -
Tipe 2
- Toilet unit 1.00 - 176,658 176,658 -
Tipe 3
- Toilet unit 1.00 - 176,658 176,658 -

DAFTAR NO. X.2.2 - PEKERJAAN PINTU dan JENDELA 89,269,288 57,371,451


Dipindahkan ke Penjumlahan Total
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.3 - PEKERJAAN LANTAI

X.2.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

CERAMIC TILE

Ceramic Tile uk. 200 x 200 mm setara ex Roman berikut


adukan mortar, additiv, grouting nat termasuk alat-alat bantu
lainnya dengan peralatan perlengkapan sesuai spesifikasi dan
gambar pada :

- Pos Jaga Type 1A


Security Office m2 9.35 (9.35) 150,610 1,408,524 (1,408,524)
Bedroom m2 4.70 (4.70) 150,610 708,242 (708,242)
Toilet Room m2 1.73 3.37 150,610 260,932 507,179
- Pos Jaga Type 1B
Security Office m2 9.35 (9.35) 150,610 1,408,524 (1,408,524)
Bedroom m2 4.70 (4.70) 150,610 708,242 (708,242)
Toilet Room m2 1.73 1.67 150,610 260,932 251,142
- Pos Jaga Type 1C
Security Office m2 9.38 (9.38) 150,610 1,413,098 (1,413,098)
Bedroom m2 4.70 (4.70) 150,610 708,244 (708,244)
Toilet Room m2 1.73 (0.03) 150,610 260,932 (4,895)
- Pos Jaga Type 2
Security Office m2 5.72 (5.72) 150,610 861,866 (861,866)
Toilet Room m2 1.94 (0.04) 150,610 292,560 (6,401)
- Pos Jaga Type 3
Security Office m2 4.27 (4.27) 150,610 642,728 (642,728)
Bedroom m2 3.55 (3.55) 150,610 534,289 (534,289)
Toilet Room m2 1.84 (0.04) 150,610 276,746 (5,648)

PLINT CERAMIC TILE

Plint Ceramic Tile 100x200mm setara ex. Roman termasuk alat


bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :

- Pos Jaga Type 1A


Security Office m 13.79 (13.79) 1,720 23,710 (23,710)
Bedroom m 9.00 (9.00) 1,720 15,480 (15,480)
- Pos Jaga Type 1B
Security Office m 13.79 (13.79) 1,720 23,710 (23,710)
Bedroom m 9.00 (9.00) 1,720 15,480 (15,480)
- Pos Jaga Type 1C
Security Office m 13.80 (13.80) 1,720 23,736 (23,736)
Bedroom m 9.00 (9.00) 1,720 15,480 (15,480)
- Pos Jaga Type 2
Security Office m 11.40 (11.40) 1,720 19,608 (19,608)
- Pos Jaga Type 3
Security Office m 9.20 (9.20) 1,720 15,824 (15,824)
Bedroom m 7.60 (7.60) 1,720 13,072 (13,072)

DAFTAR NO. X.2.3 - PEKERJAAN LANTAI 9,911,957 (7,818,478)


Dipindahkan ke Penjumlahan Total
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.4 - PEKERJAAN PLAFOND

X.2.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi


DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.4 - PEKERJAAN PLAFOND


A Beton exposed aci halus, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai dengan spesifikasi dan gambar pada :

- Pos Jaga Type 1A


Security Office m2 9.35 33,950 317,505 -
Bedroom m2 4.70 33,950 159,649 -
- Pos Jaga Type 1B
Security Office m2 9.35 33,950 317,505 -
Bedroom m2 4.70 33,950 159,649 -
- Pos Jaga Type 1C
Security Office m2 9.38 33,950 318,536 -
Bedroom m2 4.70 33,950 159,650 -
- Pos Jaga Type 2
Security Office m2 5.72 33,950 194,279 -
- Pos Jaga Type 3
Security Office m2 4.27 33,950 144,882 -
Bedroom m2 3.55 33,950 120,438 -

B Plafond Kalsium silikat tebal 8 mm ex. Jayaboard, finishing cat


Weathershiled Ex............, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :-
provisional

- Pos Jaga Type 1A


Toilet Room m2 1.73 3.37 155,810 269,941 524,690
- Pos Jaga Type 1B
Toilet Room m2 1.73 1.67 155,810 269,941 259,813
- Pos Jaga Type 1C
Toilet Room m2 1.73 (0.03) 155,810 269,941 (5,064)
- Pos Jaga Type 2
Toilet Room m2 1.94 (0.04) 155,810 302,661 (6,622)
- Pos Jaga Type 3
Toilet Room m2 1.84 (0.04) 155,810 286,301 (5,843)

C Plafond Gypsumboard tebal 9 mm rangka metal furing hollow setara ex.


Jayaboard, finishing cat Acrylic Emulsion paint setara ex.ICI, termasuk
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :(Provisional)

- Pos Jaga Type 1A


Selasar m2 36.73 (36.73) 124,090 4,557,826 (4,557,826)
- Pos Jaga Type 1B
Selasar m2 36.73 (36.73) 124,090 4,557,826 (4,557,826)

C Plafond Gypsumboard tebal 9 mm rangka metal furing hollow setara ex.


Jayaboard, finishing cat Acrylic Emulsion paint setara ex.ICI, termasuk
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :(Provisional)

- Pos Jaga Type 1C


Selasar m2 36.73 (36.73) 124,090 4,557,826 (4,557,826)
- Pos Jaga Type 2
Selasar m2 28.45 (28.45) 124,090 3,530,361 (3,530,361)
- Pos Jaga Type 3
Selasar m2 30.66 (30.66) 124,090 3,804,599 (3,804,599)
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.4 - PEKERJAAN PLAFOND


DAFTAR NO. X.2.4 - PEKERJAAN PLAFOND 24,299,314 (20,241,463)
Dipindahkan ke Penjumlahan Total
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.5. - PEKERJAAN SANITARY

X.2.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan


kelengkapan material bantu (adukan, plesteran, acian, nad, sealan,
grouting, bahan bantu pengubung (doble niple) yang berhubungan
dengan instalasi ME dan lainnya berikut pemasangan dan
perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Pos Jaga type 1A

- Closet Set ex. TOTO CW821PJ bh 1.00 3,385,100 3,385,100 -


- Floor Drain ex. TOTO TX133L bh 1.00 385,700 385,700 -
- Tissue Holder ex. TX270AXRB bh 1.00 267,820 267,820 -
- Jetwasher setara ex. TOTO TX 403 SMCRB bh 1.00 581,660 581,660 -
- Faucet ex. TOTO TX115LESBR bh 1.00 1,301,490 1,301,490 -

2 Pos Jaga type 1B

- Closet Set ex. TOTO CW821PJ bh 1.00 3,385,100 3,385,100 -


- Floor Drain ex. TOTO TX133L bh 1.00 385,700 385,700 -
- Tissue Holder ex. TX270AXRB bh 1.00 267,820 267,820 -
- Jetwasher setara ex. TOTO TX 403 SMCRB bh 1.00 581,660 581,660 -
- Faucet ex. TOTO TX115LESBR bh 1.00 1,301,490 1,301,490 -

3 Pos Jaga type 1C

- Closet Set ex. TOTO CW821PJ bh 1.00 3,385,100 3,385,100 -


- Floor Drain ex. TOTO TX133L bh 1.00 385,700 385,700 -
- Tissue Holder ex. TX270AXRB bh 1.00 267,820 267,820 -
- Jetwasher setara ex. TOTO TX 403 SMCRB bh 1.00 581,660 581,660 -
- Faucet ex. TOTO TX115LESBR bh 1.00 1,301,490 1,301,490 -

4 Pos Jaga type 2

- Closet Set ex. TOTO CW821PJ bh 1.00 3,385,100 3,385,100 -


- Floor Drain ex. TOTO TX133L bh 1.00 385,700 385,700 -
- Tissue Holder ex. TX270AXRB bh 1.00 267,820 267,820 -
- Jetwasher setara ex. TOTO TX 403 SMCRB bh 1.00 581,660 581,660 -
- Faucet ex. TOTO TX115LESBR bh 1.00 1,301,490 1,301,490 -

5 Pos Jaga type 3

- Closet Set ex. TOTO CW821PJ bh 1.00 3,385,100 3,385,100 -


- Floor Drain ex. TOTO TX133L bh 1.00 385,700 385,700 -
- Tissue Holder ex. TX270AXRB bh 1.00 267,820 267,820 -
- Jetwasher setara ex. TOTO TX 403 SMCRB bh 1.00 581,660 581,660 -
- Faucet ex. TOTO TX115LESBR bh 1.00 1,301,490 1,301,490 -

DAFTAR NO. X.2.5. - PEKERJAAN SANITARY 29,608,850 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. X.2.6. - PEKERJAAN LAIN-LAIN

X.2.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai


gambar dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

### Tanggulan
Tanggulan Closet tinggi 930 mm, tebal 95 mm lapis keramik, sesuai
gambar dan spesifikasi pada :
Pos Jaga 1A
- toilet m' 1.05 457,365 480,233 -
Pos Jaga 1B
- toilet m' 1.05 457,365 480,233 -
Pos Jaga 1C
- toilet m' 1.05 457,365 480,233 -
Pos Jaga 2
- toilet m' 1.05 457,365 480,233 -
Pos Jaga 3
- toilet m' 1.05 457,365 480,233 -

DAFTAR No. X.2.6. - PEKERJAAN LAIN-LAIN 2,401,166 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR No. X.2.7. - PEKERJAAN ATAP CANOPY

X.2.7.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari


konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A Atap

Atap UPVC ex Alderon berikut alat bantu dengan peralatan


perlengkapan sesuai dengan spesifikasi dan gambar pada :

- Roof top
Pos Jaga 1A m2 43.54 92.22 300,498 13,083,702 27,710,764
Pos Jaga 1B m2 43.54 46.96 300,498 13,083,702 14,112,609
Pos Jaga 1C m2 43.54 1.71 300,498 13,083,702 514,453
Pos Jaga 2 m2 28.09 0.53 300,498 8,441,001 159,264
Pos Jaga 3 m2 32.46 0.59 300,498 9,754,179 176,693

DAFTAR No. X.2.7. - PEKERJAAN ATAP CANOPY 57,446,286 42,673,783


Dipindahkan ke Penjumlahan Total
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. X.2.8 - PEKERJAAN FAÇADE

X.2.8.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber gasket

(sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk alat


penggantung (ironmongery sets) dan sistem kunci (keying system) dan
pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari peserta
tender, seperti merk dan jenis kunci ataupun alat-alat penggantung, dll..

A Cat Weathershield
Cat weathershiled setara ex.Jotun Tipe standar, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :
Eksterior
- Lantai 1
Pos Jaga Type 1A m2 156.71 1.02 29,490 4,621,275 29,962
Pos Jaga Type 1B m2 104.47 1.73 29,490 3,080,850 50,988
Pos Jaga Type 1C m2 47.96 0.80 29,490 1,414,355 23,666
Pos Jaga Type 2 m2 32.14 0.38 29,490 947,676 11,221
Pos Jaga Type 3 m2 42.79 (0.50) 29,490 1,261,892 (14,612)

DAFTAR NO. X.2.8 - PEKERJAAN FAÇADE 11,326,047 101,224


Dipindahkan ke Penjumlahan Total
DAFTAR No. XI.1 - PEKERJAAN STRUKTUR FOOD & BEVERAGE Vol Vol (+/-) Harsat Rp Rp (+/-)
+ MUSHOLLA

DAFTAR No. XI.1.1 - PEKERJAAN TANAH

XI.1.1.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko


longsoran, volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah


termasuk kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi


dan tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-XI.1.1 ( 289 ) TANAH


DAFTAR No. XI.1 - PEKERJAAN STRUKTUR FOOD & BEVERAGE Vol Vol (+/-) Harsat Rp Rp (+/-)
+ MUSHOLLA

DAFTAR No. XI.1.1 - PEKERJAAN TANAH


A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan m2 444.51 - 11,130 4,947,249 -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 30.95 - 55,640 1,722,058 -
- Pile Cap m3 8.27 (2.83) 55,640 460,143 (157,461)

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar

- Dibawah plat lantai inc Tie Beam m3 135.43 (135.43) 272,340 36,883,006 (36,883,006)
- Pondasi Batu kali m3 2.81 - 272,340 765,275 -
- Pile Cap m3 1.22 0.00 272,340 332,255 1,089

Urugan tanah untuk mencapai level yang diinginkan, termasuk pemadatan,


dengan memaksimalkan tanah dipakai dari bekas galian serta tanah dari
luar site jika diperlukan sesuai spek dan gambar
- Pile Cap m3 3.62 - 55,648 201,445 -

D Pek. Lain - Lain


D.1 Pek. Bobok kepala tiang Pondasi Pancang

Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar

- Mini Pile diameter 25 cm ttk - - 83,472 - -


D.2 Pekerjaan Anti rayap
Anti rayap pada Lantai dan dinding basement , termasuk alat - alat bantu, m2 444.51 - 16,690 7,418,937 -
peralatan perlengkapan sesuai spesifikasi dan gambar

D.3 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan
sesuai spesifikasi dan gambar (Kontraktor diminta untuk melampirkan
breakdown harganya) Ls 1.00 - exclude - -

DAFTAR No. XI.1.1 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 52,730,369 (37,039,378)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-XI.1.1 ( 290 ) TANAH


DAFTAR No. XI.1 - PEKERJAAN STRUKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLLA

DAFTAR NO. XI.1.2 - PEKERJAAN STRUKTUR BETON

XI.1.2.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- XI.1.2 ( 291 ) BETON


DAFTAR No. XI.1 - PEKERJAAN STRUKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLLA

DAFTAR NO. XI.1.2 - PEKERJAAN STRUKTUR BETON

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai m3 22.57 - 667,780 15,071,795 -
2) Pile cap m3 0.61 0.00 667,780 407,346 1,336

B Beton mutu K-300 :


1) Pile cap m3 4.65 (1.59) 759,480 3,531,582 (1,207,573)
2) Pelat, pada:
- Lantai 1 m3 54.17 - 759,480 41,141,032 -
C Beton mutu K-350 :
3) Balok, pada:
- Lantai 1 m3 5.91 (1.37) 782,410 4,624,043 (1,071,902)

PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada:
- Lantai dasar m2 451.45 - 53,220 24,026,169 -
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pile cap kg 1,200.17 (279.00) 8,859 10,631,706 (2,471,539)

2) Balok, pada:
- Lantai 1 kg 1,208.88 (549.60) 8,859 10,708,863 (4,868,622)

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap m2 31.01 (10.61) 84,790 2,629,338 (899,622)

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada:
- Lantai 1 (Bawah pelat, bawah balok dan sisi tegak) m2 16.39 - 100,570 1,648,342 -

2) Balok, pada:
- Lantai 1 m2 59.10 (22.78) 104,000 6,146,400 (2,369,120)

PEKERJAAN LAIN-LAIN (Provisional)

A Pondasi Batu Kali


1) Pondasi Batu Kali m3 12.66 - 611,910 7,746,781 -
2) Pasangan Aanstamping t=15cm m2 5.63 - 398,440 2,243,217 -
3) Beton tumbuk m3 2.53 - 720,190 1,822,081 -
4) Angkur D13-500 kg 30.42 - 18,920 575,555 -

B Peninggian Elevasi beton 6,5 cm


1) Beton m3 1.54 - 667,780 1,028,381 -
2) Bekesting m2 3.86 - 104,000 401,440 -

C Peninggian Elevasi bata ringan


1) Pasangan bata tinggi 22,5 cm m2 28.49 - 87,470 2,492,020 -

DAFTAR NO. XI.1.2 - PEKERJAAN STRUKTUR BETON 136,876,090 (12,887,042)


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- XI.1.2 ( 292 ) BETON


DAFTAR No. XI.1 - PEKERJAAN STRUKTUR FOOD & BEVERAGE + MUSHOLLA Rp Rp (+/-)

DAFTAR NO. XI.1.3 - PEKERJAAN STRUKTUR BAJA

XI.1.3.0. Catatan Harga

I
Harga satuan atap sudah termasuk semua hal yang diperlukan,
seperti : pengelasan, pembuatan lubang-lubang baut, perapihan
dengan gerinda, penyediaan peralatan bantu untuk pemasangan dan
mendirikan atap+rangka serta sisa terbuang (waste)

II Harga satuan konstruksi baja sudah termasuk fabrikasi dan


pengiriman ke lokasi

III Volume pengecatan finishing baja dihitung berdasarkan


berat baja.

IV Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi

I Canopy Atap
1) Pipa Baja Hitam 6", tebal 6mm Kg 9,475.40 23,372 221,460,002
2) Pipa Baja Hitam 4", tebal 4,5mm Kg 3,733.20 23,372 87,252,726
3) Pipa Baja Hitam 3", tebal 4mm Kg 1,501.62 23,372 35,096,014
4) Shear Stud dia 13mm, p = 10 cm bh 204.00 66,777 13,622,596
5) Nonshrink Grout, T = 50 mm, Uk 280 x 280mm titik 204.00 44,518 9,081,730
6) Cat Zinchromate Kg 14,710.22 3,339 49,115,534
7) Cat Finish Kg 14,710.22 3,339 49,115,534

DAFTAR NO. XI.1.3 - PEKERJAAN STRUKTUR BAJA 464,744,136 -


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- XI.1.3 ( 293 ) BAJA


DAFTAR No. XI.2 - PEKERJAAN ARSITEKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLA

DAFTAR NO. IX.2.1. - PEKERJAAN DINDING

XI.2.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah


termasuk adukan biasa atau drymix, kolom praktis, ringbalk,
angkur, sparing dan semua pekerjaan bantu yang
berhubungan dengan pekerjaan dinding tersebut.

II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton
maupun bata , kawat ayam (jika diperlukan) dan semua
pekerjaan bantu yang berhubungan dengan plesteran. Volume
plesteran dan acian sudah ditambahkan 10cm di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit,


marmer, keramik, porselin) sudah termasuk adukan, cor
beton,perekat (calbond), angkur, kawat pengikat alumunium
fixing pada dinding dengan ketinggian lebih dari 2m,
pemotongan, pinggulan, adu manis, naad, dan alat bantu
lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk


dinding kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk


pengertian cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi.
DAFTAR No. XI.2 - PEKERJAAN ARSITEKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLA

DAFTAR NO. IX.2.1. - PEKERJAAN DINDING

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. primacon,


termasuk dinding penebalan,urinoir, perekat, adukan kering
kolom dan balok praktis sesuai spesifikasi dan gambar :
- Lantai 1
Mushola m2 73.29 (10.11) 103,480 7,583,842 (1,045,976)

II PEK. PELAPIS DINDING

A Plesteran dan Acian, Plesteran halus berikut acian halus,


termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :
- Lantai 1
Mushola m2 146.58 (22.12) 61,540 9,020,287 (1,361,302)

B Pengecatan dengan fin. cat Interior ex.Jotun tipe standar,


termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :

- Lantai 1
Mushola m2 54.30 (22.24) 18,360 996,948 (408,337)
Toilet 1 m2 6.29 (6.29) 18,360 115,484 (115,484)
Toilet 2 m2 6.29 (6.29) 18,360 115,484 (115,484)

C Cat weathershiled setara ex.Jotun Tipe standar, termasuk


peralatan dan perlengkapan sesuai spesifikasi dan gambar
pada :
Eksterior
- Lantai 1
Mushola m2 56.54 (14.62) 29,490 1,667,365 (431,055)

D CERAMIC TILE

Ceramic Tile uk. 200 x 200 mm ex Roman berikut adukan


mortar, additiv, grouting nat termasuk alat-alat bantu lainnya
dengan peralatan perlengkapan sesuai spesifikasi dan gambar
pada :
- Tempat wudhu m2 26.28 0.50 139,750 3,672,316 70,189
- Toilet 1 m2 11.88 (0.03) 139,750 1,659,951 (4,402)
- Toilet 2 m2 11.88 (0.03) 139,750 1,659,951 (4,402)

DAFTAR NO. IX.2.1. - PEKERJAAN DINDING 26,491,627 (3,416,254)


DAFTAR No. XI.2 - PEKERJAAN ARSITEKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLA

DAFTAR NO. IX.2.1. - PEKERJAAN DINDING


Dipindahkan ke Penjumlahan Total
DAFTAR No. XI.2 - PEKERJAAN ARSITEKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLA

DAFTAR NO. XI.2.2 - PEKERJAAN PINTU dan JENDELA

XI.2.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU PVC
Pintu PVC P1 Terdiri dari 1 daun pintu dengan kusen/frame
alumunium ukuran 720x2100 mm, lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
- Pintu toilet unit 2.00 4,206,978 8,413,956 -

DAFTAR NO. XI.2.2 - PEKERJAAN PINTU dan JENDELA 8,413,956 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XI.2 - PEKERJAAN ARSITEKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLA

DAFTAR NO. XI.2.3 - PEKERJAAN LANTAI

XI.2.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

A CERAMIC TILE

Ceramic Tile uk. 300 x 300 mm setara ex Roman berikut adukan


mortar, additiv, grouting nat termasuk alat-alat bantu lainnya
dengan peralatan perlengkapan sesuai spesifikasi dan gambar
pada :

- F&B (Provisional) m2 408.75 173,260 70,820,268 -


- Mushola m2 24.63 173,260 4,267,827 -
- Ruang wudhu m2 5.96 173,260 1,031,763 -
- Toilet 1 m2 1.69 173,260 292,376 -
- Toilet 2 m2 1.69 173,260 292,376 -
- Selasar m2 1.80 173,260 311,868 -

DAFTAR NO. XI.2.3 - PEKERJAAN LANTAI 77,016,478 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XI.2 - PEKERJAAN ARSITEKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLA

DAFTAR NO. XI.2.4 - PEKERJAAN PLAFOND

XI.2.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah


termasuk anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire
retardant dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A Beton exposed aci halus, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai dengan spesifikasi dan gambar pada :

- Ruang wudhu m2 10.77 33,950 365,654 -


- Toilet 1 m2 2.74 33,950 92,938 -
- Toilet 2 m2 2.74 33,950 92,938 -

B Plafond Gypsumboard tebal 9 mm rangka metal furing hollow setara ex.


Jayaboard, finishing cat Acrylic Emulsion paint setara ex.ICI, termasuk
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :

- Mushola m2 24.63 124,090 3,056,647 -


- Selasar m2 1.80 124,090 223,362 -

DAFTAR NO. XI.2.4 - PEKERJAAN PLAFOND 3,831,539 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XI.2 - PEKERJAAN ARSITEKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLA

DAFTAR NO. XI.2.5. - PEKERJAAN SANITARY

XI.2.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan


kelengkapan material bantu (adukan, plesteran, acian, nad, sealan,
grouting, bahan bantu pengubung (doble niple) yang berhubungan
dengan instalasi ME dan lainnya berikut pemasangan dan
perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

I Lantai 1

Toilet
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 2.00 3,385,100 6,770,200 -
- Floor Drain ex. TOTO TX133L bh 2.00 385,700 771,400 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 2.00 581,660 1,163,320 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 2.00 267,820 535,640 -

Tempat Wudhu
- Floor Drain ex. TOTO TX133L bh 2.00 385,700 771,400 -
- Kran air bh 4.00 492,080 1,968,320 -

Area Makan
- Wastafel Set setara ex TOTO LW549J bh 8.00 3,644,970 29,159,760 -
- Kran air bh 8.00 492,080 3,936,640 -

DAFTAR NO. XI.2.5. - PEKERJAAN SANITARY 45,076,680 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XI.2 - PEKERJAAN ARSITEKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLA

DAFTAR No. XI.2.6 - PEKERJAAN LAIN-LAIN

XI.2.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai


gambar dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Penebalan
Penebalan closet tinggi 200 mm, tebal 100 mm lapis keramik, sesuai
gambar dan spesifikasi pada :
Lantai 1
- Toilet 1 m2 0.80 152,455 121,964 -
- Toilet 2 m2 0.80 152,455 121,964 -

2 Tanggulan
Tanggulan wudhu tinggi 340 mm, tebal 100 mm lapis keramik, sesuai
gambar dan spesifikasi pada :
Lantai 1
- Toilet 1 m' 3.85 167,701 645,647 -
- Toilet 2 m' 3.85 167,701 645,647 -

DAFTAR No. XI.2.6 - PEKERJAAN LAIN-LAIN 1,535,222 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XI.2 - PEKERJAAN ARSITEKTUR FOOD & Vol Vol (+/-) Harsat Rp Rp (+/-)
BEVERAGE + MUSHOLA

DAFTAR No. XI.2.7. - PEKERJAAN ATAP CANOPY

XI.2.7.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari


konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Atap
Atap Membran ex Ferari berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :
- F&B m2 512.02 144,680 74,078,335 -

DAFTAR No. XI.2.7. - PEKERJAAN ATAP CANOPY 74,078,335 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XI.2 - PEKERJAAN ARSITEKTUR FOOD & Vol Vol (+/-) Harsat Rp
BEVERAGE + MUSHOLA

DAFTAR NO. XI.2.8 - PEKERJAAN FAÇADE

XI.2.8.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber gasket

(sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk alat


penggantung (ironmongery sets) dan sistem kunci (keying system) dan
pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari peserta
tender, seperti merk dan jenis kunci ataupun alat-alat penggantung, dll..

DAFTAR NO. XI.2.8 - PEKERJAAN FAÇADE -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.1. - PEKERJAAN SOFTSCAPE

XII.1.1.0. Catatan Harga

I Semua tanaman harus bebas dari hama, korasil, tegak, segar / tidak
layu berakar baik dengan diameter ketinggian tanaman sesuai yang
dikehendaki

II
Tanaman sudah termasuk pemupukan, penyiraman steiger/
penyangga, pembuangan tanaman / umbi-umbian yang tidak
diperlukan termasuk akarnya, batu-batuan dan perawatan baik
pemupukan, pemangkasan, dan penyemprotan pestisida.

III Harga satuan sudah termasuk :

Penyiapan tanaman untuk proyek dilokasi nursery /pengumpulan


sementara.yang akan ditinjau oleh Arsitek Landscape, paling lambat
1 (satu) bulan sebelum jadwal penanaman Tanaman harus dalam
keadaan sehat, subur, dan segar.

Jenis dan jumlah tanaman,ukuran batang dan tajuk, harus sesuai


dengan gambar perencanaan dan dan spesifikasi teknis untuk
mendapat persetujuan dari Arsitek Landscape.

IV Pada saat akan ditanam, kontraktor harus mengirimkan


pemberitahuan tertulis kepada Arsitek Landscape.

V Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.

VI
Perawatan tanaman selama masa peleksanaan dan pemeliharaan.

VII Volume tanah pengisi / soil-mixed adalah dihitung volume terpasang


/ padat, termasuk pemadatan, penyusutan, bahan terbuang. Untuk
timbunan pada tanah existing, elevasi awal dan akhir harus diukur
bersama konsultan pengawas.

VIII Harga satuan tanah pengisi / soil-mixed harus sudah termasuk


pemakaian anti rayap danpengadukannya harus didalam lokasi
Proyek.

IX Untuk harga satuan pekerjaan harus sudah termasuk overhead dan


jasa Pemborong.

X Harga satuan pekerjaan harus sesuai gambar dan spesifikasi

I PEKERJAAN TANAH

A Pemberian tanah subur 10 cm diatas tanah urug m3 1,527.53 150,249 229,510,113 -

B Pemberian Pupuk Kandang untuk


a. Pohon m3 153.90 111,296 17,128,411 -
b. Semak Perdu, Penutup tanah m3 3.10 111,296 345,017 -
c. Rumput m3 661.64 111,296 73,637,698 -

C Pemberian Pasir m3 245.29 278,239 68,249,706 -

D Pembuatan Lubang tanam titik 513.00 22,259 11,418,941 -

E Fine Grading yaitu Pembentukan muka tanah untuk menjadi lebih m2 9,934.70 8,904 88,455,165 -
rata permukaannya ( Level tertinggi yang menjadi patokan
permukaannya adalah area ex Green atau Hole Golf

II PEKERJAAN PENANAMAN

1.POHON BARU

A TREMBESI (Samane Saman), Tinggi Overal 4 m daun, Diameter phn 14.00 3,561,463 49,860,481 -
batang 30 - 35 cm, Warna daun hijau, bunga warna Pink, Tertanam
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan (04122015))

B ANGGUR LAUT (Cocoloba spa), Tinggi Overal 3 - 4 m daun, phn 18.00 667,774 12,019,937 -
Diameter batang 8 - 10 cm, Warna daun hijau, bunga warna kuning,
Terpasang Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan

C KETAPANG KENCANA (Bucida Molinety), Tinggi Overal 3 m phn 52.00 712,293 37,039,215 -
daun, Diameter batang 8 - 10 cm, Warna daun hijau, bunga warna
………., Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr
For Tender Softscape Master Plan
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.1. - PEKERJAAN SOFTSCAPE


KETAPANG KENCANA (Bucida Molinety), Tinggi Overal 3 m
daun, Diameter batang 8 - 10 cm, Warna daun hijau, bunga warna
………., Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr
For Tender Softscape Master Plan

D phn 16.00 356,146 5,698,341 -


KAYU PUTIH BATANG WARNA (Eucaliptus Deglupta), Tinggi
Overal 2 - 2,5 m daun, Diameter batang 2 - 3 cm, Warna daun hijau,
warna bunga …………..., Tertanam Sesuai Spesifikasi dan Gambar
pada: (Reff. Gbr For Tender Softscape Master Plan.

E TABEBUYA BUNGA KUNING (Tabebuia Argentea), Tinggi Overal phn 51.00 667,774 34,056,489 -
3 - 4 m daun, Diameter batang 8 - 10 cm, Warna daun hijau, warna
bunga kuning, Tertanam Sesuai Spesifikasi dan Gambar pada:
(Reff. Gbr For Tender Softscape Master Plan.

F phn deleted 267,110 - -


PUCUK MERAH DIPANGKAS 2 M (Syzygium sp), Tinggi Overal
2 m daun, Diameter batang 4 cm, Warna daun hijau merah,
warna bunga …………..., Tertanam Sesuai Spesifikasi dan Gambar
pada: (Reff. Gbr For Tender Softscape Master Plan.

G KAMBOJA BALI (Plumeria sp), Tinggi Overal 3 m daun, Diameter phn deleted 756,811 - -
batang 8 - 10 cm, Warna daun hijau bunga kuning putih, Tertanam
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan.

H phn deleted 534,219 - -


PUCUK MERAH DIPANGKAS 4 M (Syzygium sp), Tinggi Overal
4 m daun, Diameter batang 5 - 6 cm, Warna daun hijau merah
bunga …………..., Tertanam Sesuai Spesifikasi dan Gambar pada:
(Reff. Gbr For Tender Softscape Master Plan.

I TABEBUYA PINK (Tabebuia Rosea), Tinggi Overal 3 m daun, phn 58.00 712,293 41,312,970 -
Diameter batang 5 - 6 cm, Warna daun hijau, warna bunga Pink,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.

J Bunga Kupu Kupu (Bauhinia Purpurea), Tinggi Overal 3 m daun, phn 114.00 267,110 30,450,508 -
Diameter batang 7 - 8 cm, Warna daun hijau, warna bunga putih,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.

K Pulai (Alstonia Scholaris), Tinggi Overal 6 - 7 m daun, Diameter phn 2.00 890,366 1,780,731 -
batang 30 - 40 cm, Warna daun hijau, warna bunga …………...,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.

2. SEMAK PERDU

A AGAVE HIJAU (Furcraea foetida), Tinggi Overal 50 - 60 cm \ m2 151.00 106,844 16,133,427 -


Jumlah batang Tajuk 50 - 60, Tertanam Sesuai Spesifikasi dan
Gambar pada: (Reff. Gbr For Tender Softscape Master Plan.
B DENDRON MARBEL (Phylodendron marble), Tinggi Overal 30 - m2 176.00 89,037 15,670,437 -
40 cm daun, Jumlah batang Tajuk 40 - 50, Tertanam Sesuai
Spesifikasi dan Gambar pada:
C DENDRON JARI (Phylodendron bipinatifidium), Tinggi Overal 30 m2 696.00 71,229 49,575,564 -
- 40 cm daun, Jumlah batang Tajuk 40 - 50, Tertanam Sesuai
Spesifikasi dan Gambar pada:
D SPATIPILUM LOKAL(Spatiphylum Cannifolium), Tinggi Overal m2 310.00 133,555 41,402,007 -
20 - 30 cm daun, Jumlah batang Tajuk 20 - 25, Tertanam Sesuai
Spesifikasi dan Gambar pada: (Reff. Gbr For Tender Softscape
Master Plan.

D KACANG-KACANGAN BUNGA KUNING(Arachnis pintoi), Tinggi m2 19,890.00 18,920 376,324,208 -


Overal 5 cm daun, Jumlah batang Tajuk 15, Tertanam Sesuai
Spesifikasi dan Gambar pada: (Reff. Gbr For Tender Softscape
Master Plan.

3.RUMPUT

A Rumput Gajah Mini (Axonopus compressus Dwarft) Tertanam m2 8,903.15 27,824 247,720,615 -
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan.

III PEKERJAAN LAIN-LAIN


A Steger bambu diameter 7 - 10 cm dicat warna hijau Set 513.00 16,694 8,564,205 -

IV PEKERJAAN TANAMAN EXISTING

A Pohon yang dibongkar Set 75.00 200,332 15,024,922 -


B Pohon yang dipertahankan Set 52.00 100,166 5,208,640 -

V PEKERJAAN PEMELIHARAAN & PERAWATAN


DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.1. - PEKERJAAN SOFTSCAPE

A ( Selama 6 bln termasuk ) untuk pekerjaan : bln 6.00 25,598,015 153,588,089 -


1. Penyiraman
2. Pendangiran
3. Pemberantasan hama & penyakit
4. Pemupukan
5. Perbaikan steger
6. Penggantian tanaman mati

DAFTAR NO. XII.1.1. - PEKERJAAN SOFTSCAPE


Dipindahkan ke Penjumlahan Total 1,630,175,836 -
DAFTAR No. XII.2 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
BANGUNAN PENUNJANG

DAFTAR NO. XII.2.1. - PEKERJAAN SOFTSCAPE

XII.2.1.0. Catatan Harga

I Semua tanaman harus bebas dari hama, korasil, tegak, segar /


tidak layu berakar baik dengan diameter ketinggian tanaman
sesuai yang dikehendaki

II
Tanaman sudah termasuk pemupukan, penyiraman steiger/
penyangga, pembuangan tanaman / umbi-umbian yang tidak
diperlukan termasuk akarnya, batu-batuan dan perawatan baik
pemupukan, pemangkasan, dan penyemprotan pestisida.

III Harga satuan sudah termasuk :

Penyiapan tanaman untuk proyek dilokasi nursery


/pengumpulan sementara.yang akan ditinjau oleh Arsitek
Landscape, paling lambat 1 (satu) bulan sebelum jadwal
penanaman Tanaman harus dalam keadaan sehat, subur, dan
segar.

Jenis dan jumlah tanaman,ukuran batang dan tajuk, harus


sesuai dengan gambar perencanaan dan dan spesifikasi teknis
untuk mendapat persetujuan dari Arsitek Landscape.

IV Pada saat akan ditanam, kontraktor harus mengirimkan


pemberitahuan tertulis kepada Arsitek Landscape.

V Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.

VI Perawatan tanaman selama masa peleksanaan dan


pemeliharaan.

VII Volume tanah pengisi / soil-mixed adalah dihitung volume


terpasang / padat, termasuk pemadatan, penyusutan, bahan
terbuang. Untuk timbunan pada tanah existing, elevasi awal dan
akhir harus diukur bersama konsultan pengawas.

VIII Harga satuan tanah pengisi / soil-mixed harus sudah termasuk


pemakaian anti rayap danpengadukannya harus didalam lokasi
Proyek.

IX Untuk harga satuan pekerjaan harus sudah termasuk overhead


dan jasa Pemborong.

X Harga satuan pekerjaan harus sesuai gambar dan spesifikasi

I PEKERJAAN TANAH

A Pemberian tanah subur 10 cm diatas tanah urug m3 1,686.20 150,249 253,350,682 -

B Pemberian Pupuk Kandang untuk


a. Pohon m3 112.50 111,296 12,520,768 -
b. Semak Perdu, Penutup tanah m3 - - - -
c. Rumput m3 1,940.53 111,296 215,972,911 -

C Pemberian Pasir m3 325.95 278,239 90,690,762 -

D Fine Grading yaitu Pembentukan muka tanah untuk menjadi m2 16,862.03 8,904 150,133,737 -
lebih rata permukaannya ( Level tertinggi yang menjadi patokan
permukaannya adalah area ex Green atau Hole Golf

II PEKERJAAN PENANAMAN

1.POHON BARU
A Pulai (Alstonia Scholaris), Tinggi Overal 4 m daun, Diameter phn 23.00 1,112,957 25,598,015 -
batang 10 - 12 cm, Warna daun hijau, warna bunga …………...,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.

B TABEBUYA BUNGA KUNING (Tabebuia Argentea), Tinggi phn 60.00 667,774 40,066,458 -
Overal 3 - 4 m daun, Diameter batang 8 - 10 cm, Warna daun
hijau bunga kuning, Tertanam Sesuai Spesifikasi dan Gambar
pada: (Reff. Gbr For Tender Softscape Master Plan.

C phn 12.00 712,293 8,547,511 -


TABEBUYA BUNGA PINK (Tabebuia Rosea), Tinggi Overal 3
- 4 m daun, Diameter batang 5 - 6 cm, Warna daun hijau bunga
kuning, Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff.
Gbr For Tender Softscape Master Plan.

D MINDI (Melia Azedarach), Tinggi Overal 3 - 4 m daun, phn 30.00 712,293 21,368,778 -
Diameter batang 6-8 cm, Warna daun hijau, Tertanam Sesuai
Spesifikasi dan Gambar pada: (Reff. Gbr For Tender Softscape
Master Plan.
DAFTAR No. XII.2 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
BANGUNAN PENUNJANG

DAFTAR NO. XII.2.1.


MINDI (Melia - PEKERJAAN
Azedarach), SOFTSCAPE
Tinggi Overal 3 - 4 m daun,
Diameter batang 6-8 cm, Warna daun hijau, Tertanam Sesuai
Spesifikasi dan Gambar pada: (Reff. Gbr For Tender Softscape
Master Plan.

E KAMBOJA BALI (Plumeria sp), Tinggi Overal 3 m daun, phn 36.00 756,811 27,245,191 -
Diameter batang 10 - 12 cm, Warna daun hijau bunga kuning
putih, Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr
For Tender Softscape Master Plan.

F Bunga Kupu Kupu (Bauhinia Purpurea), Tinggi Overal 3 m phn 29.00 267,110 7,746,182 -
daun, Diameter batang 7 - 8 cm, Warna daun hijau, warna
bunga putih, Tertanam Sesuai Spesifikasi dan Gambar pada:
(Reff. Gbr For Tender Softscape Master Plan.

G PUCUK MERAH DIPANGKAS 1,5 M (Syzygium sp), Tinggi phn 16.00 445,183 7,122,926 -
Overal 3-4 m daun, Diameter batang 5 - 6 cm, Warna daun
hijau merah bunga …………..., Tertanam Sesuai Spesifikasi dan
Gambar pada: (Reff. Gbr For Tender Softscape Master Plan.
(Provisional)

H TREMBESI (Samane Saman), Tinggi Overal 3-4 m daun, phn 14.00 1,335,549 18,697,680 -
Diameter batang 4-5 cm, Warna daun hijau,warna bunga Pink,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan (04122015))

I DIOSPYROS (Diospyros buxifolia), Tinggi Overal 3 m daun, phn 70.00 890,366 62,325,601 -
Diameter batang 5-6 cm, Warna daun hijau,warna bunga Pink,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan

2. SEMAK PERDU

A KACANG-KACANGAN BUNGA KUNING(Arachnis pintoi), m2 13,842.00 18,920 261,894,403 -


Tinggi Overal 5 cm daun, Jumlah batang Tajuk 15, Tertanam
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan.
B BAKUNG JAWA (Hymenocalis speciosa), Tinggi Overal 30-40 m2 3,668.00 85,475 313,522,706 -
cm , Jumlah batang Tajuk 20-30, Tertanam Sesuai Spesifikasi
dan Gambar pada: (Reff. Gbr For Tender Softscape Master
Plan.
C LILI BRAZIL (Dianella gold), Tinggi Overal 20 - 25 cm \ Jumlah m2 1,142.00 85,475 97,612,576 -
batang Tajuk 15 - 20, Tertanam Sesuai Spesifikasi dan Gambar
pada: (Reff. Gbr For Tender Softscape Master Plan.
D BAKUNG BELUT(Hymenocalis sp), Tinggi Overal 20 - 30 cm m2 512.00 85,475 43,763,257 -
daun, Jumlah batang Tajuk 20 - 25, Tertanam Sesuai
Spesifikasi dan Gambar pada: (Reff. Gbr For Tender Softscape
Master Plan.
E SPATIPILUM LOKAL(Spatiphylum Cannifolium), Tinggi m2 1,044.00 133,555 139,431,274 -
Overal 20 - 30 cm daun, Jumlah batang Tajuk 20 - 25,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.
F PAKIS KELABANG (Nephrolepis exaltata), Tinggi Overal 20 - m2 779.00 166,944 130,049,045 -
30 cm daun, Jumlah batang Tajuk 20 - 30, Tertanam Sesuai
Spesifikasi dan Gambar pada:
G DENDRON JARI (Phylodendron bipinatifidium), Tinggi Overal
30 - 40 cm daun, Jumlah batang Tajuk 40 - 50, Tertanam m2 201.00 71,229 14,317,081 -
Sesuai Spesifikasi dan Gambar pada:
3. TANAMAN RAMBAT

A LEE KWAN YU (Vernonia eliptica) tinggi 30-50 cm Tertanam m2 735.00 64,106 47,118,155 -
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan.

4. RUMPUT

A Rumput Gajah Mini (Axonopus compressus Dwarft) m2 16,297.26 22,259 362,763,047 -


Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.

III PEKERJAAN LAIN-LAIN


A Steger bambu diameter 7 - 10 cm dicat warna hijau Set 375.00 13,355 5,008,307 -

IV PEKERJAAN TANAMAN EXISTING

A Pohon yang dibongkar Set 66.00 178,073 11,752,828 -


B Pohon yang dipertahankan Set 138.00 89,037 12,287,047 -

V PEKERJAAN PEMELIHARAAN & PERAWATAN

A ( Selama 6 bln termasuk ) untuk pekerjaan : bln 6.00 13,911,965 83,471,788 -


1. Penyiraman
2. Pendangiran
DAFTAR No. XII.2 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
BANGUNAN PENUNJANG

DAFTAR NO. XII.2.1. - PEKERJAAN SOFTSCAPE


3. Pemberantasan hama & penyakit
4. Pemupukan
5. Perbaikan steger
6. Penggantian tanaman mati

DAFTAR NO. XII.2.1. - PEKERJAAN SOFTSCAPE


Dipindahkan ke Penjumlahan Total 2,464,378,717 -
DAFTAR No. XII.3 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
CROSS COUNTRY

DAFTAR NO. XII.3.1. - PEKERJAAN SOFTSCAPE

XII.3.1.0. Catatan Harga

I Semua tanaman harus bebas dari hama, korasil, tegak, segar /


tidak layu berakar baik dengan diameter ketinggian tanaman
sesuai yang dikehendaki

II
Tanaman sudah termasuk pemupukan, penyiraman steiger/
penyangga, pembuangan tanaman / umbi-umbian yang tidak
diperlukan termasuk akarnya, batu-batuan dan perawatan baik
pemupukan, pemangkasan, dan penyemprotan pestisida.

III Harga satuan sudah termasuk :

Penyiapan tanaman untuk proyek dilokasi nursery /pengumpulan


sementara.yang akan ditinjau oleh Arsitek Landscape, paling
lambat 1 (satu) bulan sebelum jadwal penanaman Tanaman harus
dalam keadaan sehat, subur, dan segar.

Jenis dan jumlah tanaman,ukuran batang dan tajuk, harus sesuai


dengan gambar perencanaan dan dan spesifikasi teknis untuk
mendapat persetujuan dari Arsitek Landscape.

IV Pada saat akan ditanam, kontraktor harus mengirimkan


pemberitahuan tertulis kepada Arsitek Landscape.

V Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.

VI Perawatan tanaman selama masa peleksanaan dan


pemeliharaan.

VII Volume tanah pengisi / soil-mixed adalah dihitung volume


terpasang / padat, termasuk pemadatan, penyusutan, bahan
terbuang. Untuk timbunan pada tanah existing, elevasi awal dan
akhir harus diukur bersama konsultan pengawas.

VIII Harga satuan tanah pengisi / soil-mixed harus sudah termasuk


pemakaian anti rayap danpengadukannya harus didalam lokasi
Proyek.

IX Untuk harga satuan pekerjaan harus sudah termasuk overhead


dan jasa Pemborong.

X Harga satuan pekerjaan harus sesuai gambar dan spesifikasi

I PEKERJAAN TANAH

A Pemberian tanah subur 10 cm diatas tanah urug m3 12,345.91 150,249 1,854,963,922 -

B Pemberian Pupuk Kandang untuk


a. Pohon m3 211.20 111,296 23,505,655 -
b. Semak Perdu, Penutup tanah m3 - 111,296 - -
c. Rumput m3 6,172.96 278,239 1,717,559,187 -

C Pemberian Pasir m3 2,469.18 278,239 687,023,675 -

D Pembentukan dan penyesuaian tepi Danau meliputi pengurugan m3 2,593.70 166,944 433,001,551 -
dan penghalusan tepi Danau

E Fine Grading yaitu Pembentukan muka tanah untuk menjadi lebih m2 Exclude 8,904 - -
rata permukaannya ( Level tertinggi yang menjadi patokan
permukaannya adalah area ex Green atau Hole Golf

II PEKERJAAN PENANAMAN

1.POHON BARU
A TREMBESI (Samane Saman), Tinggi Overal 4 m daun, Diameter phn 76.00 3,561,463 270,671,183 -
batang 30 - 35 cm, Warna daun hijau,warna bunga Pink, Tertanam
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan (04122015))

B MAHONI (Switenia Mahagony), Tinggi Overal 3 m daun, phn 105.00 667,774 70,116,302 -
Diameter batang 8 - 10 cm, Warna daun hijau, warna bunga Putih,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan (04122015))

C KETAPANG (Terminalia Cattappa), Tinggi Overal 4 - 5 m daun, phn 46.00 534,219 24,574,094 -
Diameter batang 8 - 10 cm, Warna daun hijau, warna bunga
…………..., Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff.
Gbr For Tender Softscape Master Plan
DAFTAR No. XII.3 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
CROSS COUNTRY

DAFTAR NO. XII.3.1. - PEKERJAAN SOFTSCAPE


D ANGGUR LAUT (Cocoloba spa), Tinggi Overal 3 - 4 m daun, phn 13.00 667,774 8,681,066 -
Diameter batang 8 - 10 cm, Warna daun hijau, warna bunga
kuning, Terpasang Sesuai Spesifikasi dan Gambar pada: (Reff.
Gbr For Tender Softscape Master Plan

E KETAPANG KENCANA (Bucida Molinety), Tinggi Overal 3 m phn 42.00 712,293 29,916,289 -
daun, Diameter batang 8 - 10 cm, Warna daun hijau, warna bunga
………….., Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff.
Gbr For Tender Softscape Master Plan

F Pulai (Alstonia Scholaris), Tinggi Overal 6 - 7 m daun, Diameter phn 179.00 1,335,549 239,063,200 -
batang 30 - 40 cm, Warna daun hijau, warna bunga …………...,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.

G KAYU PUTIH BATANG WARNA (Eucaliptus Deglupta), Tinggi phn 15.00 356,146 5,342,194 -
Overal 2 - 2,5 m daun, Diameter batang 2 - 3 cm, Warna daun
hijau, warna bunga …………..., Tertanam Sesuai Spesifikasi dan
Gambar pada: (Reff. Gbr For Tender Softscape Master Plan.

H POHON YANG LIU (Salix Babylonica), Tinggi Overal 3 - 4 m phn 139.00 756,811 105,196,712 -
daun, Diameter batang 6 - 8 cm, Warna daun hijau, warna bunga
…………..., Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff.
Gbr For Tender Softscape Master Plan.

I TABEBUYA BUNGA KUNING (Tabebuia Argentea), Tinggi phn 100.00 667,774 66,777,430 -
Overal 3 - 4 m daun, Diameter batang 8 - 10 cm, Warna daun
hijau bunga kuning, Tertanam Sesuai Spesifikasi dan Gambar
pada: (Reff. Gbr For Tender Softscape Master Plan.

2.RUMPUT
A Rumput Gajah Mini (Axonopus compressus Dwarft) Tertanam m2 Exclude 22,259 -
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan.

III PEKERJAAN LAIN-LAIN


A Steger bambu diameter 7 - 10 cm dicat warna hijau Set 704.00 16,694 11,752,828 -

IV PEKERJAAN TANAMAN EXISTING

A Pohon yang dibongkar Set 44.00 200,332 8,814,621 -


B Pohon yang dipertahankan Set 108.00 100,166 10,817,944 -

V PEKERJAAN PEMELIHARAAN & PERAWATAN

A ( Selama 6 bln termasuk ) untuk pekerjaan : bln 6.00 40,956,824 245,740,943 -


1. Penyiraman
2. Pendangiran
3. Pemberantasan hama & penyakit
4. Pemupukan
5. Perbaikan steger
6. Penggantian tanaman mati

DAFTAR NO. XII.3.1. - PEKERJAAN SOFTSCAPE


Dipindahkan ke Penjumlahan Total 5,813,518,795 -
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.2. - PEKERJAAN HARDSCAPE

XII.1.2.0. Catatan Harga

I Sebelum memulai pekerjaan kontraktor harus terlebih dahulu


mengajukan contoh dan daftar material Hardscape dan harus
mendapatkan persetujuan dari manajer Proyek

II Pekerjaan beton Hardscape di tempat adalah termasuk :


1 - Pemadatan tanah
2 - Pemasangan lapisan pasir urug

III Pekerjaan beton cor di tempat adalah termasuk penulangan,


bekisting, finishing dan pekerjaan – pekerjaan yang berhubungan
dengan pekerjaan tersebut.

IV Harga satuan Hardscape sudah termasuk pemadatan tanah galian,


urugan, pembuangan tanah, humus / kompos pengisi (khusus
pohon) sesuai gambar dan spesifikasi.

V Harga satuan sudah termasuk :


1 - Penyiapan tanaman untuk proyek dilokasi nursery /pengumpulan
sementara.yang akan ditinjau oleh Arsitek Landscape, paling lambat
1 (satu) bulan sebelum jadwal penanaman Tanaman harus dalam
keadaan sehat, subur, dan segar.
2 - Jenis dan jumlah tanaman,ukuran batang dan tajuk, harus sesuai
dengan gambar perencanaan dan dan spesifikasi teknis untuk
mendapat persetujuan dari Arsitek Landscape.

VI Pada saat akan ditanam, kontraktor harus mengirimkan


pemberitahuan tertulis kepada Arsitek Landscape.

VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.

VII Perawatan tanaman selama masa peleksanaan dan pemeliharaan.

VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead dan
jasa Pemborong.

IX Harga satuan pekerjaan harus sesuai gambar dan spesifikasi


DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.2. - PEKERJAAN HARDSCAPE

I PEKERJAAN PERKERASAN

PERKERASAN 1 (PLAZA UTAMA - PLAZA BENDERA)


A Batu Andesit Flamed dan Granit Bush Hammer 30 x 60 cm, m2 4,189.85 828,770 3,472,421,985 -
20 X 40 cm dan 10 x 20 cm warna abu abu, Abu tuan & Hitam

PERKERASAN 2 (ENTRANCE SPECTATOR & LOBBY OUT DOOR VIP)


B Entrance Spectator & Lobby out door VIP, Batu Andesit Flamed m2 874.03 828,770 724,369,843 -
dan Granit Bush Hammer 30 x 60 cm, 20 x 40 cm dan 10 x 20 cm
warna abu abu, WARNA Abu tua & warna Hitam

PERKERASAN 3 (AKSES KE GARDU PLN)


C Batu Andesit Flamed dan Granit Bush Hammer 30 x 60 cm, m2 192.70 828,770 159,703,979 -
20 X 60 cm dan 15 x 30 cm warna abu abu, warna Abu tua &
Warna Hitam

PERKERASAN 4 (AKSES PEDESTRIAN)


D Paving Block Type Convave ukuran 21 X 21 cm m2 452.69 248,600 112,538,734 -
warna abu abu & warna Hitam

PERKERASAN 5 (PEDESTRIAN UTAMA & AKSES SPECTATOR F & B)


E Paving Block Type Convave ukuran 21 X 21 cm m2 969.60 248,600 241,042,560 -
warna abu abu & warna Hitam

PERKERASAN 6 (AREA DUDUK SPECTATOR F & B)


F Paving Block Type Constone ukuran 50 X 50 cm m2 555.46 248,600 138,087,356 -
warna abu abu & warna Hitam

PERKERASAN 7
G Batu koral Tebar / Lepas dia 3 - 5 cm m2 30.10 139,120 4,187,501 -
warna abu abu & warna Hitam

PERKERASAN 8 (AKSES JALUR VIP KE PLAZA UTAMA)


H Batu Andesit Flamed dan Granit Bush Hammer 30 x 60 cm, m2 73.11 828,770 60,591,375 -
15 X 60 cm, warna abu abu, warna Hitam

DAFTAR NO. XII.1.2. - PEKERJAAN HARDSCAPE


DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.2. - PEKERJAAN HARDSCAPE


Dipindahkan ke Penjumlahan Total 4,912,943,333 -
DAFTAR No. XII.2 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
BANGUNAN PENUNJANG

DAFTAR NO. XII.2.2. - PEKERJAAN HARDSCAPE

XII.2.2.0. Catatan Harga

I Sebelum memulai pekerjaan kontraktor harus terlebih dahulu


mengajukan contoh dan daftar material Hardscape dan harus
mendapatkan persetujuan dari manajer Proyek

II Pekerjaan beton Hardscape di tempat adalah termasuk :


1 - Pemadatan tanah
2 - Pemasangan lapisan pasir urug

III Pekerjaan beton cor di tempat adalah termasuk penulangan,


bekisting, finishing dan pekerjaan – pekerjaan yang berhubungan
dengan pekerjaan tersebut.

IV Harga satuan Hardscape sudah termasuk pemadatan tanah galian,


urugan, pembuangan tanah, humus / kompos pengisi (khusus pohon)
sesuai gambar dan spesifikasi.

V Harga satuan sudah termasuk :


1 - Penyiapan tanaman untuk proyek dilokasi nursery /pengumpulan
sementara.yang akan ditinjau oleh Arsitek Landscape, paling lambat
1 (satu) bulan sebelum jadwal penanaman Tanaman harus dalam
keadaan sehat, subur, dan segar.
2 - Jenis dan jumlah tanaman,ukuran batang dan tajuk, harus sesuai
dengan gambar perencanaan dan dan spesifikasi teknis untuk
mendapat persetujuan dari Arsitek Landscape.

VI Pada saat akan ditanam, kontraktor harus mengirimkan


pemberitahuan tertulis kepada Arsitek Landscape.

VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.

VII Perawatan tanaman selama masa peleksanaan dan pemeliharaan.

VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead dan
jasa Pemborong.

IX Harga satuan pekerjaan harus sesuai gambar dan spesifikasi


DAFTAR No. XII.2 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
BANGUNAN PENUNJANG

DAFTAR NO. XII.2.2. - PEKERJAAN HARDSCAPE

I PEKERJAAN PERKERASAN

PERKERASAN 1 (PEDESTRIAN UTAMA & AKSES SPECTATOR F & B)


Batu Andesit Flamed & Granit Bush Hammer 300x600, 200x600, m2 254.11 828,770 210,595,430 -
200x400, 100x200 mm. Warna abu abu, abu tua & warna Hitam

PERKERASAN 5 (PEDESTRIAN UTAMA & AKSES SPECTATOR F & B)


Paving Block Type Convave ukuran 21 X 21 cm warna abu abu & m2 897.18 248,600 223,038,948 -
warna Hitam

PERKERASAN 9 (JALAN LINGKUNGAN & AREA PARKIR)


Asphalt Hotmix termasuk agregat kasar & halus, split h:20cm serta m2 6,153.01 390,110 2,400,350,731 -
accesoris, alat bantu dan perapihan
Asphalt Hotmix termasuk agregat kasar & halus, split h:30cm serta m2 3,928.51 390,110 1,532,551,036 -
accesoris, alat bantu dan perapihan

PERKERASAN 10 (GALLOP TRACK)


Perkerasan Gallop Track dari Finishing Paving block ukuran 10,5 x m2 15,059.37 254,160 3,827,489,479 -
21 cm, tebal = 8 cm, warna abu abu & Hitam pola pasang
Herringbone 45 termasuk sand bedding, 125 CTB K-120 & base
course

Kansteen
Kansteen type-1 sleepform ukuran 600x450x210mm
natural colour ex..
- Zona Gallop Track m' 3,415.22 143,310 489,435,178 -
- Zona Asphalt m' 1,971.28 143,310 282,504,137 -

Car Stopper
Car Stopper ukuran 600x150x...mm natural colour ex…
- Area Parkir bh 63.00 57,160 3,601,080 -

Traffic Arrow
Traffic Arrow type-1 Thermoplastic paint finish white colour
- Jalan Area Penunjang bh 22.00 139,120 3,060,640 -

Parking Line
Zebra Cross Thermoplastic paint finish white colour
- Mobil uk. 5000mm bh 47.00 139,120 6,538,640 -
- Bus uk. 12000mm bh 17.00 139,120 2,365,040 -
DAFTAR No. XII.2 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
BANGUNAN PENUNJANG

DAFTAR NO. XII.2.2. - PEKERJAAN HARDSCAPE


DAFTAR NO. XII.2.2. - PEKERJAAN HARDSCAPE
Dipindahkan ke Penjumlahan Total 8,981,530,339 -
DAFTAR No. XII.3 - PEKERJAAN LANDSCAPE ZONA CROSS C Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.3.2. - PEKERJAAN HARDSCAPE

XII.3.2.0. Catatan Harga

I Sebelum memulai pekerjaan kontraktor harus terlebih dahulu


mengajukan contoh dan daftar material Hardscape dan harus
mendapatkan persetujuan dari manajer Proyek

II Pekerjaan beton Hardscape di tempat adalah termasuk :


1 - Pemadatan tanah
2 - Pemasangan lapisan pasir urug

III Pekerjaan beton cor di tempat adalah termasuk penulangan,


bekisting, finishing dan pekerjaan – pekerjaan yang berhubungan
dengan pekerjaan tersebut.

IV Harga satuan Hardscape sudah termasuk pemadatan tanah galian,


urugan, pembuangan tanah, humus / kompos pengisi (khusus
pohon) sesuai gambar dan spesifikasi.

V Harga satuan sudah termasuk :


1 - Penyiapan tanaman untuk proyek dilokasi nursery
/pengumpulan sementara.yang akan ditinjau oleh Arsitek
Landscape, paling lambat 1 (satu) bulan sebelum jadwal
penanaman Tanaman harus dalam keadaan sehat, subur, dan
segar.
2 - Jenis dan jumlah tanaman,ukuran batang dan tajuk, harus
sesuai dengan gambar perencanaan dan dan spesifikasi teknis
untuk mendapat persetujuan dari Arsitek Landscape.

VI Pada saat akan ditanam, kontraktor harus mengirimkan


pemberitahuan tertulis kepada Arsitek Landscape.

VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.

VII Perawatan tanaman selama masa peleksanaan dan pemeliharaan.

VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead


dan jasa Pemborong.

IX Harga satuan pekerjaan harus sesuai gambar dan spesifikasi

I PEKERJAAN PERKERASAN

PERKERASAN GALLOP TRACK


A Perkerasan Gallop Track dari Finishing Paving block ukuran 10,5 x
m2 9,375.40 By OTHER - -
21 cm, tebal = 8 cm, warna abu abu & Hitam pola pasang
Herringbone 45 termasuk sand bedding, 125 CTB K-120 & base
course

B Fine Grading Jalur Cross Country dengan tambahan taburan pasir m2 22,489.36 10,573 237,782,097 -
+ screening 3cm (provisional)

Kansteen
C Kansteen type-1 sleepform ukuran 600x450x210mm m' 2,776.30 143,310 397,871,553 -
natural colour ex..

DAFTAR NO. XII.3.2. - PEKERJAAN HARDSCAPE


Dipindahkan ke Penjumlahan Total 635,653,650 -
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.4. - PEKERJAAN PARKIR

XII.1.4.0. Catatan Harga

I Sebelum memulai pekerjaan kontraktor harus terlebih dahulu


mengajukan contoh dan daftar material Hardscape dan harus
mendapatkan persetujuan dari manajer Proyek

II Pekerjaan beton Hardscape di tempat adalah termasuk :


1 - Pemadatan tanah
2 - Pemasangan lapisan pasir urug

III Pekerjaan beton cor di tempat adalah termasuk penulangan,


bekisting, finishing dan pekerjaan – pekerjaan yang berhubungan
dengan pekerjaan tersebut.

IV Harga satuan Hardscape sudah termasuk pemadatan tanah


galian, urugan, pembuangan tanah, humus / kompos pengisi
(khusus pohon) sesuai gambar dan spesifikasi.

V Harga satuan sudah termasuk :


1 - Penyiapan tanaman untuk proyek dilokasi nursery
/pengumpulan sementara.yang akan ditinjau oleh Arsitek
Landscape, paling lambat 1 (satu) bulan sebelum jadwal
penanaman Tanaman harus dalam keadaan sehat, subur, dan
segar.
2 - Jenis dan jumlah tanaman,ukuran batang dan tajuk, harus
sesuai dengan gambar perencanaan dan dan spesifikasi teknis
untuk mendapat persetujuan dari Arsitek Landscape.

VI Pada saat akan ditanam, kontraktor harus mengirimkan


pemberitahuan tertulis kepada Arsitek Landscape.

VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.

VII Perawatan tanaman selama masa peleksanaan dan pemeliharaan.

VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead


dan jasa Pemborong.

IX Harga satuan pekerjaan harus sesuai gambar dan spesifikasi

PERKERASAN 9 (JALAN LINGKUNGAN & AREA PARKIR)


Asphalt Hotmix termasuk agregat kasar & halus, serta accesoris,
alat bantu dan perapihan
- Zona depan m2 16,548.74 390,110 6,455,828,961 -

Kansteen
Kansteen type-1 sleepform ukuran 600x450x210mm natural
colour ex..
- Jalan & Pedestrian m' 1,299.83 143,310 186,278,637 -

Kansteen type-2 ukuran 400x150x300mm natural colour ex..


- Jalan & Rumput m' 2,161.13 140,444 303,517,309 -

Kansteen type-3 ukuran 400x100x200mm natural colour ex..


- Pedestrian & Rumput m' 788.71 141,160 111,334,580 -

Car Stopper
Car Stopper ukuran 600x150x...mm natural colour ex…
- Area Parkir bh 792.00 100,740 79,786,080 -

Traffic Arrow
Traffic Arrow type-1 Thermoplastic paint finish white colour
- Jalan & Pedestrian bh 70.00 139,120 9,738,400 -

Traffic Arrow type-1.a (motor sign) Thermoplastic paint finish


white colour
- Jalan & Pedestrian bh 2.00 139,120 278,240 -

Traffic Arrow type-2 Thermoplastic paint finish white colour


- Jalan & Rumput bh 29.00 139,120 4,034,480 -

Traffic Arrow type-3 (Bus Sign) Thermoplastic paint finish white colour
- Pedestrian & Rumput bh 8.00 139,120 1,112,960 -

Zebra Cross
Zebra Cross Thermoplastic paint finish white colour
- uk. 10700x4330mm bh 1.00 139,120 139,120 -
- uk. 9900x4330mm bh 1.00 139,120 139,120 -

Parking Line
Zebra Cross Thermoplastic paint finish white colour
- Mobil uk. 5000mm bh 300.00 139,120 41,736,000 -
- Motor uk. 2000mm bh 55.00 139,120 7,651,600 -
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.4. - PEKERJAAN PARKIR


- Bus uk. 12000mm bh 5.00 139,120 695,600 -
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.4. - PEKERJAAN PARKIR


Sign Board
SG-1 Signboard Peta Orientasi wilayah
- Zona Depan bh 1.00 2,225,914 2,225,914 -

SG-2 Signboard Tanda masuk kendaraan


- Zona Depan bh 2.00 2,225,914 4,451,829 -

SG-3 Signboard Tanda keluar kendaraan white colour


- Zona Depan bh 2.00 2,225,914 4,451,829 -

SG-6 Signboard Penunjuk arah white colour


- Zona Depan bh 5.00 2,225,914 11,129,572 -

DAFTAR NO. XII.1.4. - PEKERJAAN PARKIR


Dipindahkan ke Penjumlahan Total 7,224,530,231 -
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.5. - PEKERJAAN LAIN-LAIN

XII.1.5.0. Catatan Harga

I Sebelum memulai pekerjaan kontraktor harus terlebih dahulu


mengajukan contoh dan daftar material Hardscape dan harus
mendapatkan persetujuan dari manajer Proyek

II Pekerjaan beton Hardscape di tempat adalah termasuk :


1 - Pemadatan tanah
2 - Pemasangan lapisan pasir urug

III Pekerjaan beton cor di tempat adalah termasuk penulangan, bekisting,


finishing dan pekerjaan – pekerjaan yang berhubungan dengan
pekerjaan tersebut.

IV Harga satuan Hardscape sudah termasuk pemadatan tanah galian,


urugan, pembuangan tanah, humus / kompos pengisi (khusus pohon)
sesuai gambar dan spesifikasi.

V Harga satuan sudah termasuk :


1 - Penyiapan tanaman untuk proyek dilokasi nursery /pengumpulan
sementara.yang akan ditinjau oleh Arsitek Landscape, paling lambat 1
(satu) bulan sebelum jadwal penanaman Tanaman harus dalam
keadaan sehat, subur, dan segar.
2 - Jenis dan jumlah tanaman,ukuran batang dan tajuk, harus sesuai
dengan gambar perencanaan dan dan spesifikasi teknis untuk
mendapat persetujuan dari Arsitek Landscape.

VI Pada saat akan ditanam, kontraktor harus mengirimkan pemberitahuan


tertulis kepada Arsitek Landscape.

VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus dilapisi
core darin.

VII Perawatan tanaman selama masa peleksanaan dan pemeliharaan.

VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead dan jasa
Pemborong.

IX Harga satuan pekerjaan harus sesuai gambar dan spesifikasi

Water Feature
Struktur Kolam beton bertulang, termasuk beton besi & bekisting,
perapihan dan alat bantu
- Drop Off m3 26.61 3,338,870 88,839,518 -

Pasangan bata penyangga kolam finish plester termasuk perekat,


perapihan accesoris & alat bantu
- Drop Off m2 15.68 165,020 2,587,514 -

Batu Andesit Diva Black Polished 20 x 20 cm termasuk perekat,


perapihan accesoris & alat bantu
- Zona Depan m2 202.76 828,770 168,038,090 -

Pagar
Pagar Besi (type-1) h:2400mm terdiri dari kombinasi Besi Hollow
Galvanis & plat galvanis uk.150x150mm, 80x80mm, kolom pagar beton
bertulang dan pasangan bata finish expose, sloof beton bertulang dan
pondasi batu kali termasuk perapihan perkuatan sesuai gambar dan
spesifikasi
- Zona Depan m' 31.40 612,126 19,220,770 -

Pagar Besi (type-2) h:2400mm terdiri dari Besi Hollow Galvanis


uk.150x150mm, 80x80mm, dan plat galvanis 10x80mm , sloof beton
bertulang dan pondasi batu kali termasuk perapihan perkuatan sesuai
gambar dan spesifikasi
- Zona Depan m' 366.30 612,126 224,221,916 -

Pagar BRC h:1800mm terdiri dari pagar BRC 1800x2400mm & pipa besi
Ø5cm, pondasi kolom beton 250x250mm dan pasangan bata, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi (Provisional)
Zona Depan m' 169.60 389,535 66,065,138 -

Railling
Railling Pengaman h:1000mm terdiri dari railling pipa besi galvanize
Ø3", pedestal dan kolom beton bertulang finish aci + cat, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi
- Jembatan Pintu Keluar VIP m' 47.94 1,112,957 53,350,715 -

Bangku Taman
Bangku Taman h:450mm terdiri dari beton cor bertulang, plat baja
t:7mm, pasangan bata finish plester aci, buis beton dan capping batu
andesit Diva black polish termasuk perapihan perkuatan sesuai gambar
dan spesifikasi
- Zona Depan m2 42.55 37,562 1,598,276 -
Tempat Sampah
Tempat Sampah Ø350mm h:700mm terdiri dari rangka luar besi plat
perporated, rangka dalam fiber, tutup alumunium, pondasi dudukan,
termasuk perapihan perkuatan sesuai gambar dan spesifikasi
(Provisional)
- Zona Depan bh 36.00 14,050 505,800 -

Treegrids
Treegrids uk. 1200x1200mm terdiri dari besi cor finish zincromate, pasir
urug, rabat beton finish aci, dudukan treegrids besi siku, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi
- Zona Depan bh 8.00 556,480 4,451,840 -

Gate
Ticket Booth uk. 1700x928x2150mm termasuk sloof beton bertulang
dan pondasi batu kali, perapihan perkuatan sesuai gambar dan
spesifikasi
- Main VIP Entrance bh 3.00 4,451,830 13,355,490 -
- Area Spectator Entrance bh 3.00 4,451,830 13,355,490 -
- Area Spectator Exit bh 2.00 4,451,830 8,903,660 -
- Area Parkir VIP Exit bh 3.00 4,451,830 13,355,490 -

Box Ticket Entrance uk. 400x400x1219mm termasuk pemasangan,


perapihan perkuatan sesuai gambar dan spesifikasi
- Main VIP Entrance bh 3.00 556,480 1,669,440 -
- Area Spectator Entrance bh 3.00 556,480 1,669,440 -

Boom Gate termasuk pemasangan, perapihan perkuatan sesuai gambar


dan spesifikasi
- Main VIP Entrance bh 3.00 - - -
- Area Spectator Entrance bh 3.00 - - -
- Area Spectator Exit bh 2.00 - - -
- Area Parkir VIP Exit bh 3.00 - - -

Canopy Entrance h:7100mm terdiri dari struktur Baja H Beam


200x200mm 600x200mm finish cat besi anti karat, lapisan atap
polycarbonate, besi plat t: 3mm, pondasi kolom beton, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi
- Main VIP Entrance (Uk. 3800x15062mm) bh 1.00 3,004,980 3,004,980 -
- Area Spectator Entrance (Uk. 6433x18854mm) bh 1.00 3,004,980 3,004,980 -
- Area Spectator Exit (Uk. 3000x13000mm) bh 1.00 3,004,980 3,004,980 -
- Area Parkir VIP Exit (Uk. 3300x15315mm) bh 1.00 3,004,980 3,004,980 -

Pintu Gerbang Lipat h:2316mm terdiri dari kombinasi besi hollow


galvanis uk 80x80mm & uk 40x40mm, anti karat paint finish, rail track,
termasuk perapihan perkuatan sesuai gambar dan spesifikasi
(Provisional)
- Main VIP Entrance m' 10.95 2,521,400 27,609,330 -

Bollard Ø200mm h:900mm terdiri dari beton cor bertulang finish aci
halus termasuk pemasangan, perapihan perkuatan sesuai gambar dan
spesifikasi
- Main Entrance bh 12.00 117,950 1,415,400 -
- Area Spectator Entrance bh deleted - -
- Area Spectator Exit bh deleted - -
- Area Parkir VIP Exit bh deleted - -

Logo
Logo Pulomas Jaya, termasuk perapihan perkuatan sesuai gambar dan
spesifikasi
- Kolom Pagar Type-1 bh 7.00 556,480 3,895,360 -

Logo "Jakarta International Equestrian Park" h:500mm, stainless steel


hairline, termasuk perapihan perkuatan sesuai gambar dan spesifikasi
Kolom Pagar Type-1 bh 1.00 5,676,080 5,676,080 -

Ornamen Patung
Ornamen Patung h:7075mm termasuk pedestal beton bertulang dan
pondasi, pasangan bata finish beton exposed, perapihan perkuatan
sesuai gambar dan spesifikasi
- Zona Depan bh 1.00 38,953,500 38,953,500 -

Dinding Area Patung Kuda


Dinding Area Patung Kuda tebal 300mm termasuk struktur beton
bertulang dan pondasi, pasangan bata finish beton exposed, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Depan m2 123.31 1,224,250 150,959,207 -

Ticket Box
Ticket Box Counter uk. 7000x3000x….mm termasuk sloof beton
bertulang dan pondasi batu kali, perapihan perkuatan sesuai gambar
dan spesifikasi
- Zona Depan bh deleted - - -

Tiang Bendera
Tiang Bendera h: 7000mm terdiri dari pipa stainless steel Ø4" & Ø3"
pondasi beton bertulang uk. Diameter 600 tinggi 1500mm dan besi
angkur Ø12mm, termasuk perapihan perkuatan sesuai gambar dan
spesifikasi
- Zona Depan bh 23.00 3,756,230 86,393,290 -

Drainase
Drainase tertutup lebar 500mm, terdiri U-ditch beton precast ex.
Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Depan m' 1,629.99 946,010 1,541,986,840 -

Saluran Overflow dari buist beton Ø800mm, terdiri dari Reinforced


Concrete Pipes ex. Dusaspun, pintu air mekanik, termasuk galian,
pemasangan, perapihan perkuatan sesuai gambar dan spesifikasi
- Zona Depan m' 376.03 445,180 167,401,035 -

Pergola
Pergola h:2700mm terdiri dari struktur Baja H Beam finish cat besi anti
karat, lapisan atap polycarbonate, pondasi kolom beton, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi
- Plaza Utama m2 479.51 278,240 133,418,028 -

Bak Kontrol
Bak Kontrol ukuran 600x600x450mm terdiri dari struktur beton
bertulang, waterproofing integral, n, termasuk perapihan perkuatan
sesuai gambar dan spesifikasi
- Area Drop Off Tribune bh 6.00 333,890 2,003,340 -

DAFTAR NO. XII.1.5. - PEKERJAAN LAIN-LAIN


Dipindahkan ke Penjumlahan Total 2,852,919,916 -

2,006.02
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.6 - PEKERJAAN STRUKTUR JEMBATAN

XII.1.6.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.6 - PEKERJAAN STRUKTUR JEMBATAN


PEKERJAAN BORPILE

A Pengeboran Pondasi Bored piles , Ø = 600 mm m2 175.00 - 556,479 97,383,752 -

B Beton Fc' 30 m3 87.92 - 835,830 73,486,174 -

C Besi kg 6,473.71 - 8,859 57,347,360 -

PEKERJAAN BETON

A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:


1) Dibawah pelat jembatan m3 1.13 - 667,780 754,591 -

B Beton mutu K-300 :


1) Caping beam m3 35.16 - 759,480 26,703,317 -
2) Pelat Injak m3 12.93 - 759,480 9,820,076 -
3) Pelat jembatan m3 166.97 - 759,480 126,810,376 -

PEKERJAAN PEMBESIAN
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pelat jembatan kg 22,157.69 - 8,859 196,283,897 -
2) Pelat Injak kg 1,468.64 - 8,859 13,009,947 -
3) Capping beam kg 5,864.30 - 8,859 51,948,902 -

PEKERJAAN ACUAN/ BEKISTING

A Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pelat, pada:
- Jembatan (bawah pelat dan sisi tegak) m2 374.04 - 100,570 37,617,203 -
- Pelat Injak (bawah pelat dan sisi tegak) m2 43.96 - 100,570 4,421,057 -
- Capping beam m2 245.64 - 100,570 24,704,015 -

PEKERJAAN LAIN-LAIN

A Pasir Padat dibawah jembatan m3 2.26 - 272,340 615,488 -

B Expansion joint
1) Pelat jembatan m' 28.30 (5) 61,213 1,732,318 (287,699)
2) Pelat jembatan m' 28.30 (5) 61,213 1,732,318 (287,699)

C Dowel dia 16 - 500


1) Pelat jembatan kg 43.65 - 8,859 386,674 -

D Grouting
1) Pelat jembatan m' 28.30 1,391,196.46 39,370,860 -
2) Pelat jembatan m' 28.30 1,391,196.46 39,370,860 -

DAFTAR NO. XII.1.6 - PEKERJAAN STRUKTUR JEMBATAN


Dipindahkan ke Penjumlahan Total 803,499,184 (575,399)
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.7 - PEKERJAAN STRUKTUR REFEREE TOWER

XII.1.7.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.7 - PEKERJAAN STRUKTUR REFEREE TOWER

PEKERJAAN TANAH

Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang


keluar lokasi proyek

- Lokasi area lahan m2 exclude

Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan
ditentukan) untuk urugan dan sisanya di buang ke luar site, berikut
alat-alat bantuTapak
- Pondasi dan kelengkapannya pada: m3 4.49 (4.49) 61,213 274,975 (274,975)

Pekerjaan Urugan

Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat


bantu berikut peralatan perlengkapan sesuai spesifikasi dan
gambar
- Pondasi Tapak m3 1.12 3.37 272,340 306,212 917,173

Urugan tanah untuk mencapai level yang diinginkan, termasuk


pemadatan, dengan memaksimalkan tanah dipakai dari bekas
galian serta tanah dari luar site jika diperlukan sesuai spek dan
gambar
- Pondasi Tapak m3 1.12 - 55,648 62,569 -

PEKERJAAN BETON

A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:


1) Dibawah pelat jembatan m3 1.13 (1.13) 667,780 754,591 (754,591)

B Beton mutu K-250 :


1) Pondasi tapak m3 0.64 - 759,480 486,067 -
2) Kolom pedestal m3 2.34 - 759,480 1,777,183 -
3) Tie beam m3 1.95 - 759,480 1,480,986 -
4) Pelat m3 15.99 - 759,480 12,146,577 -

PEKERJAAN PEMBESIAN
A Wiremesh M8-150
1) Pelat, pada:
- Lantai 1 m2 28.69 - 53,220 1,526,749 -

A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:


1) Pondasi tapak kg 55.25 - 8,859 489,432 -
2) Kolom pedestal kg 170.09 - 8,859 1,506,742 -
3) Tie beam kg 231.75 - 8,859 2,052,999 -

PEKERJAAN ACUAN/ BEKISTING

A Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Pondasi tapak m2 18.20 - 100,570 1,830,374 -
2) Kolom pedestal m2 15.00 - 100,570 1,508,550 -
3) Tie beam m2 15.60 - 100,570 1,568,892 -

B Bekisting bondex
1) Pelat, pada: m2 28.69 - 100,570 2,885,102 -

PEKERJAAN LAIN-LAIN

A Pondasi Tapak
1) Beton tumbuk m3 0.38 - 100,570 38,619 -

PEKERJAAN BAJA

1) HB 150 x 150 x 7 x 11 Kg 1,121.40 - 18,364 20,593,158 -


2) WF 150 x 75 x 5 x 7 Kg 566.72 - 18,364 10,407,129 -
3) CNP 150 x 50 x 20 x 2.3 Kg 670.80 - 18,364 12,318,433 -
4) Plate T=12mm Kg 3.01 - 17,807 53,678 -
5) Plate T=6mm Kg 98.91 - 17,807 1,761,321 -
6) Plate stiffner Kg 0.03 - 17,807 534 -
7) Angkur M 12 bh 80.00 - 222,591 17,807,315 -
8) Angkur M 16 bh 32.00 - 222,591 7,122,926 -
9) Nonshrink grout t=25 m3 1.00 - 13,355,486 13,355,486 -
10) Baut Diameter M 12 mm bh 69.00 - 31,163 2,150,233 -
11) Cat Dasar (Zincromate) Kg 2,460.87 - 3,339 8,216,543 -
12) Cat Finishing baja Kg 2,460.87 - 3,339 8,216,543 -
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.1.7 - PEKERJAAN STRUKTUR REFEREE TOWER

DAFTAR NO. XII.1.7 - PEKERJAAN STRUKTUR REFEREE TOWER


Dipindahkan ke Penjumlahan Total 132,699,920 (112,393)
DAFTAR No. XII.2 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
BANGUNAN PENUNJANG
DAFTAR NO. XII.2.4. - PEKERJAAN LAIN-LAIN

XII.2.4.0. Catatan Harga

I Sebelum memulai pekerjaan kontraktor harus terlebih dahulu


mengajukan contoh dan daftar material Hardscape dan harus
mendapatkan persetujuan dari manajer Proyek

II Pekerjaan beton Hardscape di tempat adalah termasuk :


1 - Pemadatan tanah
2 - Pemasangan lapisan pasir urug

III Pekerjaan beton cor di tempat adalah termasuk penulangan,


bekisting, finishing dan pekerjaan – pekerjaan yang berhubungan
dengan pekerjaan tersebut.

IV Harga satuan Hardscape sudah termasuk pemadatan tanah galian,


urugan, pembuangan tanah, humus / kompos pengisi (khusus pohon)
sesuai gambar dan spesifikasi.

V Harga satuan sudah termasuk :


1 - Penyiapan tanaman untuk proyek dilokasi nursery /pengumpulan
sementara.yang akan ditinjau oleh Arsitek Landscape, paling lambat 1
(satu) bulan sebelum jadwal penanaman Tanaman harus dalam
keadaan sehat, subur, dan segar.
2 - Jenis dan jumlah tanaman,ukuran batang dan tajuk, harus sesuai
dengan gambar perencanaan dan dan spesifikasi teknis untuk
mendapat persetujuan dari Arsitek Landscape.

VI Pada saat akan ditanam, kontraktor harus mengirimkan


pemberitahuan tertulis kepada Arsitek Landscape.

VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.

VII Perawatan tanaman selama masa peleksanaan dan pemeliharaan.

VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead dan
jasa Pemborong.

IX Harga satuan pekerjaan harus sesuai gambar dan spesifikasi

Pagar
Pagar Besi (type-2) h:2400mm terdiri dari Besi Hollow Galvanis
uk.150x150mm, 80x80mm, dan plat galvanis 10x80mm , sloof beton
bertulang dan pondasi batu kali termasuk perapihan perkuatan sesuai
gambar dan spesifikasi
- Zona Penunjang m' 803.61 612,126 491,910,441 -

Railling
Railling Pengaman h:1700mm terdiri dari railling pipa besi galvanize
Ø60mm & Ø50mm, pedestal beton bertulang finish aci, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi
- Zona Penunjang m' 142.33 1,112,957 158,406,081 -

Bangku Taman
Bangku Taman h:450mm terdiri dari beton cor bertulang, plat baja
t:7mm, pasangan bata finish plester aci, buis beton dan capping batu
andesit Diva black polish termasuk perapihan perkuatan sesuai
gambar dan spesifikasi
- Zona Penunjang m2 21.64 37,562 812,886 -

Treegrids
Treegrids uk. 1200x1200mm terdiri dari besi cor finish zincromate,
pasir urug, rabat beton finish aci, dudukan treegrids besi siku,
termasuk perapihan perkuatan sesuai gambar dan spesifikasi
- Parkir Mobil Zona Penunjang bh 10.00 556,480 5,564,800 -
- Smoking Area Zona Penunjang bh 4.00 556,480 2,225,920 -

Drainase
Drainase tertutup lebar 500mm, terdiri U-ditch beton precast ex.
Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Penunjang m' 937.71 946,010 887,083,037 -

Drainase tertutup lebar 600mm, terdiri U-ditch beton precast ex.


Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Penunjang m' 64.29 946,010 60,818,983 -

Drainase tertutup lebar 700mm, terdiri U-ditch beton precast ex.


Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Penunjang m' 786.74 946,010 744,263,907 -

Drainase tertutup lebar 800mm, terdiri U-ditch beton precast ex.


Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
DAFTAR No. XII.2 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
BANGUNAN PENUNJANG
DAFTAR
DrainaseNO. XII.2.4.
tertutup - PEKERJAAN
lebar LAIN-LAIN
800mm, terdiri U-ditch beton precast ex.
Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Penunjang m' 11.91 946,010 11,266,979 -

Drainase tertutup lebar 1000mm, terdiri U-ditch beton precast ex.


Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Penunjang m' 207.49 1,001,660 207,834,433 -

Saluran Overflow dari buist beton Ø800mm, terdiri dari Reinforced


Concrete Pipes ex. Dusaspun, pintu air mekanik, termasuk galian,
pemasangan, perapihan perkuatan sesuai gambar dan spesifikasi
- Zona Penunjang m' 443.63 445,180 197,495,203 -

Saluran Overflow dari buist beton Ø2500mm, terdiri dari Reinforced


Concrete Pipes ex. Dusaspun, pintu air mekanik, termasuk galian,
pemasangan, perapihan perkuatan sesuai gambar dan spesifikasi
- Zona Penunjang m' 106.10 1,168,610 123,989,521 -

DAFTAR NO. XII.2.4. - PEKERJAAN LAIN-LAIN


Dipindahkan ke Penjumlahan Total 2,891,672,192 -
DAFTAR No. XII.3 - PEKERJAAN LANDSCAPE ZONA CROSS COUNT Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XII.3.4. - PEKERJAAN LAIN-LAIN

XII.3.4.0. Catatan Harga

I Sebelum memulai pekerjaan kontraktor harus terlebih dahulu


mengajukan contoh dan daftar material Hardscape dan harus
mendapatkan persetujuan dari manajer Proyek

II Pekerjaan beton Hardscape di tempat adalah termasuk :


1 - Pemadatan tanah
2 - Pemasangan lapisan pasir urug

III Pekerjaan beton cor di tempat adalah termasuk penulangan, bekisting,


finishing dan pekerjaan – pekerjaan yang berhubungan dengan
pekerjaan tersebut.

IV Harga satuan Hardscape sudah termasuk pemadatan tanah galian,


urugan, pembuangan tanah, humus / kompos pengisi (khusus pohon)
sesuai gambar dan spesifikasi.

V Harga satuan sudah termasuk :


1 - Penyiapan tanaman untuk proyek dilokasi nursery /pengumpulan
sementara.yang akan ditinjau oleh Arsitek Landscape, paling lambat 1
(satu) bulan sebelum jadwal penanaman Tanaman harus dalam
keadaan sehat, subur, dan segar.
2 - Jenis dan jumlah tanaman,ukuran batang dan tajuk, harus sesuai
dengan gambar perencanaan dan dan spesifikasi teknis untuk
mendapat persetujuan dari Arsitek Landscape.

VI Pada saat akan ditanam, kontraktor harus mengirimkan pemberitahuan


tertulis kepada Arsitek Landscape.

VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus dilapisi
core darin.

VII Perawatan tanaman selama masa peleksanaan dan pemeliharaan.

VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead dan jasa
Pemborong.

IX Harga satuan pekerjaan harus sesuai gambar dan spesifikasi

I PEKERJAAN PAGAR

Pagar
Pagar Besi (type-2) h:2400mm terdiri dari Besi Hollow Galvanis
uk.150x150mm, 80x80mm, dan plat galvanis 10x80mm , sloof beton
bertulang dan pondasi batu kali termasuk perapihan perkuatan sesuai
gambar dan spesifikasi

- Zona Cross Country m' 80.00 612,126 48,970,115 -

Pagar Beton (type-3) h:3000mm terdiri dari precast panel uk. 2400x400
kolom precast panel dan pondasi beton termasuk perapihan perkuatan
sesuai gambar dan spesifikasi
- Zona Cross Country m' 1,865.30 890,370 1,660,807,161 -

Gabion
Gabion h:450mm terdiri dari pasangan batu kali h:700mm, finish caping
…... , kawat ayam, termasuk perapihan perkuatan sesuai gambar dan
spesifikasi
- Zona Cross Country m2 382.30 500,830 191,467,309 -

Signage Board
Gabion Signage board uk. 3500x800mm terdiri strukutr besi hollow anti
karat paint finish, dan acrylic, termasuk perapihan perkuatan sesuai
gambar dan spesifikasi
- Zona Cross Country bh 1.00 5,564,790 5,564,790 -

Drainase
Drainase tertutup lebar 600mm, terdiri U-ditch beton precast ex.
Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Cross Country m' 89.41 946,010 84,582,754 -

Drainase
Drainase tertutup lebar 700mm, terdiri U-ditch beton precast ex.
Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Cross Country m' 665.13 946,010 629,219,631 -

Saluran Overflow dari buist beton Ø800mm, terdiri dari Reinforced


Concrete Pipes ex. Dusaspun, pintu air mekanik, termasuk galian,
pemasangan, perapihan perkuatan sesuai gambar dan spesifikasi
- Zona Cross Country m' 2,570.75 445,180 1,144,446,485 -

Bak Kontrol
Bak Kontrol ukuran 700x700x450mm terdiri dari struktur beton
bertulang, waterproofing integral, n, termasuk perapihan perkuatan
sesuai gambar dan spesifikasi
DAFTAR No. XII.3 - PEKERJAAN LANDSCAPE ZONA CROSS COUNT Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. ukuran


Bak Kontrol XII.3.4. 700x700x450mm
- PEKERJAAN LAIN-LAIN
terdiri dari struktur beton
bertulang, waterproofing integral, n, termasuk perapihan perkuatan
sesuai gambar dan spesifikasi
- Zona Cross Country bh 204.00 333,890 68,113,560 -

DAFTAR NO. XII.3.4. - PEKERJAAN LAIN-LAIN


Dipindahkan ke Penjumlahan Total 3,833,171,806 -
DAFTAR No. XIII - OUTDOOR ARENA Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XIII.1 - PEKERJAAN LANTAI ARENA FIELD OF PLAY

XIII.1.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

SPECIAL FOOTING

A LAPISAN BAWAH
1 Geotextile non woven pori maks 180 gr /m2 m2 8,000.00 15.69 22,259 178,073,147 349,246
2 Porous asphalt tebal 6 cm m2 8,000.00 15.69 166,832 1,334,658,237 2,617,598
3 Gravel 2/3, tebal 125 mm m2 8,000.00 15.69 52,300 418,401,779 820,590
4 Geotextile non woven pori maks 75 micron m2 8,000.00 15.69 22,259 178,073,147 349,246
5 Sub base dia 15-30 cm, Tebal 44,5 cm m2 8,000.00 15.69 168,831 1,350,650,986 2,648,964

B SPECIAL FOOTING :
1 Pasir dengan campuran serat fibre geotextile dan anti debu m2 8,000.00 BY OTHER
(Material Ex, Import)

PAGAR
1 Balok beton Ukuran 30x65cm (Provisional) m3 70.21 - 835,830 58,680,482 -
2 Besi Tulangan Rasio 90 kg/m3 kg 6,318.90 8,859 55,975,976
3 Bekisting kayu m2 594.05 100,570 59,743,558
4 Railing tinggi 1600mm dengan pipa pembagi co extrude m' 360.03 0.32 973,840 350,613,563 309,681
PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght
max 4m co extrude PVC/ASA dan kelengkapan lainnya sesuai
gambar dan spesifikasi

DAFTAR NO. XIII.1 - PEKERJAAN LANTAI ARENA FIELD OF PLAY 3,984,870,875 7,095,326
Dipindahkan ke Penjumlahan Total
DAFTAR No. XIII - OUTDOOR ARENA Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XIII.2 - PEKERJAAN LANTAI ARENA WARMING UP

XIII.2.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

SPECIAL FOOTING

A LAPISAN BAWAH
1 Geotextile non woven pori maks 180 gr /m2 m2 6,000.00 410.66 22,259 133,554,860 9,140,940
2 Porous asphalt tebal 6 cm m2 6,000.00 410.66 166,832 1,000,993,678 68,511,344
3 Gravel 2/3, tebal 125 mm m2 6,000.00 410.66 52,300 313,801,334 21,477,609
4 Geotextile non woven pori maks 75 micron m2 6,000.00 410.66 22,259 133,554,860 9,140,940
5 Sub base dia 15-30 cm, Tebal 44,5 cm m2 6,000.00 410.66 168,831 1,012,988,240 69,332,292

B SPECIAL FOOTING :
1 Pasir dengan campuran serat fibre geotextile dan anti debu m2 6,000.00 BY OTHER
(Material Ex, Import)

C PAGAR
1 Concrete tebal 30x65cm m3 72.00 - 835,830 60,179,760 -
2 Besi Tulangan Rasio 90 kg/m3 kg 6,480.00 8,859 57,403,080 -
3 Bekisting kayu m2 511.50 100,570 51,441,555 -
4 Railing tinggi 1600mm dengan pipa pembagi co extrude
PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght max
4m co extrude PVC/ASA dan kelengkapan lainnya sesuai m' 310.00 10.27 973,840 301,890,400 10,001,337
gambar dan spesifikasi

DAFTAR NO. XIII.2 - PEKERJAAN LANTAI ARENA WARMING UP 3,065,807,767 187,604,461


Dipindahkan ke Penjumlahan Total
DAFTAR No. XIII - OUTDOOR ARENA Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XIII.3 - PEKERJAAN LANTAI COLLECTING ARENA

XIII.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

SPECIAL FOOTING

A LAPISAN BAWAH
1 Geotextile non woven pori maks 180 gr /m2 m2 1,500.00 22,259 33,388,715 -
2 Porous asphalt m2 1,500.00 166,832 250,248,419 -
3 Gravel 2/3 tebal 125 mm m2 1,500.00 52,300 78,450,334 -
4 Geotextile non woven pori maks 75 micron m2 1,500.00 22,259 33,388,715 -
5 Sub base dia 15-30 cm m2 1,500.00 168,831 253,247,060 -

B SPECIAL FOOTING :
1 Pasir dengan campuran serat fibre geotextile dan anti debu m2 1,500.00 BY OTHER
(Material Ex, Import)

C PAGAR
1 Balok beton Ukuran 30x65cm (Provisional) m3 33.15 835,830 27,707,765 -
2 Besi Tulangan Rasio 90 kg/m3 kg 2,983.50 8,859 26,429,335 -
3 Bekisting kayu m2 280.50 100,570 28,209,885 -
4 Railing tinggi 1600mm dengan pipa pembagi co extrude m' 170.00
PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght max
4m co extrude PVC/ASA dan kelengkapan lainnya sesuai 973,840 165,552,800 -
gambar dan spesifikasi

DAFTAR NO. XIII.3 - PEKERJAAN LANTAI COLLECTING ARENA 896,623,027 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XIII.1 - BANGUNAN ARENA Vol Vol (+/-) Harsat Rp Rp (+/-)

DAFTAR NO. XIII.4 - PEKERJAAN LANTAI TRAINING ARENA I

XIII.4.1.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

SPECIAL FOOTING

A LAPISAN BAWAH :
1 Geotextile non woven pori maks 180 gr /m2 m2 4,960.00 440.03 22,259 110,405,351 9,794,691
2 Porous asphalt tebal 6 cm m2 4,960.00 440.03 166,832 827,488,107 73,411,208
3 Gravel 2/3, tebal 125 mm m2 4,960.00 440.03 52,300 259,409,103 23,013,667
4 Geotextile non woven pori maks 75 micron m2 4,960.00 440.03 22,259 110,405,351 9,794,691
5 Sub base dia 15-30 cm, Tebal 44,5 cm m2 4,960.00 440.03 168,831 837,403,612 74,290,869

B SPECIAL FOOTING :
1 Pasir dengan campuran serat fibre geotextile dan anti debu m2 4,960.00 BY OTHER
(Material Ex, Import)

C PAGAR :
1 Balok beton Ukuran 30x65cm (Provisional) m3 55.38 - 835,830 46,288,265 -
2 Besi Tulangan Rasio 90 kg/m3 kg 4,984.20 8,859 44,152,536 -
3 Bekisting kayu m2 468.60 100,570 47,127,102 -
4 Railing tinggi 1600mm dengan pipa pembagi co extrude
PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght max
4m co extrude PVC/ASA dan kelengkapan lainnya sesuai m' 284.00 16.00 973,840 276,570,560 15,581,440
gambar dan spesifikasi

DAFTAR NO. XIII.4 - PEKERJAAN LANTAI TRAINING ARENA I 2,559,249,987 205,886,566


Dipindahkan ke Penjumlahan Total
DAFTAR No. XIII - OUTDOOR ARENA Vol Vol (+/-) Harsat Rp

DAFTAR NO. XIII.5 - PEKERJAAN FASILITAS & PERALATAN

XIII.4.1.0. Catatan Harga

I Untuk harga satuan pekerjaan harus sudah termasuk overhead


dan jasa Pemborong.
II Sebelum memasukan Equipmen/peralatan Equestrian
kontraktor harus terlebih dahulu mengajukan contoh brosur
Equipment dan harus mendapatkan persetujuan dari manajer
Proyek dan owner
III Harga satuan pekerjaan harus sesuai gambar dan spesifikasi

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

UNTUK PELAKSANAAN ARENA FOOTING


1 Small dozer/Grader ( Bobcat / John Deere) dengan laser sensore Unit 1 634,385,590 634,385,590
leveling unit untuk mengukur kerataan arena
2 Equestrian Tractor 40 - 50 HP Unit 2 445,182,870 890,365,740
3 Surface Maintenance ( Rower & Rub ) Unit 1 333,887,150 333,887,150
4 Surface Maintenance Rake 2.70 M ( Rower & Rub ) Unit 1 389,535,010 389,535,010
5 Mobil Tangki air 8000 L dng pompa sedot dan dorong yang kuat Unit 2 422,923,720 845,847,440
(Peralatan diatas dapat dilihat di www.roewer-rueb.de)

- UNTUK FASILITAS EQUESTRIAN


1 Horse Walker with Teomatic Track Roof for 6 Horse Unit 1 139,119,650 139,119,650
2 Horse Truck /Mobil Transport kuda untuk 2 ekor Unit 1 411,794,150 411,794,150
3 Horse Trailer master WCF wt extra frame for rought road Unit 1 823,588,300 823,588,300
4 Grass Cutter / Pemotong rumput untuk dipasang pada Tractor Unit 1 166,943,580 166,943,580
5 Double Cabin 3000 cc untuk menarik Trailer Unit 2 556,478,580 1,112,957,160
(Peralatan diatas dapat dilihat di www.boeckmann.com)

- UNTUK EQUIPMENT PERALATAN EQUESTRIAN


1 Rintangan untuk show Jumping 16 Jump dng 3 set ABC ( Total Set 1 89,036,570 89,036,570
25 Jumps)
2 Open Water Jump Set 1 55,647,860 55,647,860
3 Liperpool Rectangular uk.1,5 x 3,0 m Unit 1 22,259,140 22,259,140
4 Liperpool Round uk.1,5 x 3,0 m Unit 2 33,388,720 66,777,440
5 Start Finish set 3 22,259,140 66,777,420
6 FenceNo Cones set 1 89,036,570 89,036,570
7 Safety Cups Cup 30 1,112,960 33,388,800
8 Training Jump Untuk Warming Up set 1 89,036,570 89,036,570
9 40 Extra Poles 3,5 m with pole and caps, painted set 1 33,388,720 33,388,720
10 Poles trainer for up to 80 poles, ball bearing, Revolving crane set 1 33,388,720 33,388,720
11 Set Dressage arena terdiri dari Set 5 22,259,140 111,295,700
- 1 Dressage Ring 20 x 60 m
- 35 plank 4,0 m
- 2 plank 1,5 m
- 1 plank 1,0 m
11 Dressage Letters Set 5 11,129,570 55,647,850
Peralatan diatas dapat dilihat di Olaf Petersen
(www.olaf-petersen.com)

- PERALATAN UNTUK EQUINE CLINIC


1 X Ray Machine Unit 1 166,943,580 166,943,580
2 Peralatan Test darah Unit 1 55,647,860 55,647,860
(Peralatan diatas dapat dilihat di www.heska.com)

- PERALATAN TAMBAHAN SEKIRANYA PERLU ( BISA DISEWA )


1 Electric Car untuk 6 pasangan V VIP Unit 2 333,887,150 667,774,300

DAFTAR NO. XIII.5 - PEKERJAAN FASILITAS & PERALATAN 7,384,470,870


Dipindahkan ke Penjumlahan Total
DAFTAR No. XIV.1 - PEKERJAAN STRUKTUR GENSET &
Vol Vol (+/-) Harsat Rp Rp
STP
DAFTAR No. IV.1.1 - PEKERJAAN PONDASI TIANG PANCANG

IV.1.1.0. Catatan Harga

Catatan Harga (Pricing Notes)


I Harga satuan tiang pancang sudah termasuk :

- harga tukang, alat dan material untuk pemancangan lengkap


termasuk waste

- keperluan galian tanah insidentil termasuk buangan tanah

penggantian tiang pancang yang rusak atau tiang pancang yang


- meleset atau tiang pancang yang gagal test

- topi pondasi dan sepatu pondasi tiang pancang

perbaikan tiang pancang yang menyimpang dari as bagian


- bawah atau atas

- biaya test sudah termasuk pengadaan balok beton pemindahan


balok beton dan hal - hal lain

- pondasi tiang diperhitungkan net tidak ada biaya untuk


tambahan panjang tiang pada pie head

Kedalaman pemancangan dihitung dari muka tanah asli (peil +/-


2
0.000 pada gambar lokasi).

Harga satuan untuk pemancangan dan galian tanah sudah harus


diperhitungkan kemungkinan resiko longsor, pembuangan sisa-sisa
3
akar tanaman, sisa konstruksi bangunan lama yang masih
tertanam, pembersihan lumpur (wash boring), dan lain-lain.

Perbedaan berat yang dikeluarkan oleh pabrik yang satu dengan


4 pabrik yang lainnya untuk diameter yang sama menjadi tanggung
jawab pemborong.

Tabel berat yang dipakai dalam menghitung berat besi dalam


5
Daftar ini, adalah :
Diameter Ø Kg/m (polos)

6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.186
32 mm 6.313

Monitoring lapangan :

harga sudah termasuk observasi lapangan, test lapangan dan


-
test laboratorium

- harga sudah termasuk penyediaan contoh, analisa tanah,


termasuk persiapan test

- harga sudah termasuk penyelesaian laporan yang diperlukan


untuk pekerjaan tersebut diatas

- pengukuran dilokasi tiang sebelum dan sesudah pemancangan

- pembersihan lapangan, jalan sementara, lantai kerja, jalan


masuk yang mungkin diperlukan untuk pelaksanan
pemancangan

VOLUME PROVISIONAL (HARGA SATUAN TETAP)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-XIV.1.1 ( 339 ) PONDASI


DAFTAR No. XIV.1 - PEKERJAAN STRUKTUR GENSET &
Vol Vol (+/-) Harsat Rp Rp
STP
DAFTAR No. IV.1.1 - PEKERJAAN PONDASI TIANG PANCANG

A PENGADAAN TIANG PANCANG

Pengadaan Tiang Pancang untuk pemancangan, sesuai spesifikasi


dan gambar
Ukuran 250 x 250 mm, 4D13 U-40, stirup Ø5 -75 pada atas dan
bawah, stirup Ø5 -150 pada tengah
kedalaman pemancangan = 11 m' m' 165 11,130 1,836,379 -
Jumlah titik pemancangan = 15 Titik

B PEMANCANGAN TIANG PANCANG

Pemancangan Tiang Pancang dengan drop hammer 1500 kg untuk


Test Pile dan Reaction Pile (used pile), sesuai spesifikasi dan
gambar
Ukuran 250 x 250 mm, 4D13 U-40, stirup Ø5 -75 pada atas dan
bawah, stirup Ø5 -150 pada tengah
kedalaman pemancangan = 11 m' m' 165 155,814 25,709,311 -
Jumlah titik pemancangan = 372 titik

C PEK. SAMBUNGAN T. PANCANG


Pekerjaan sambungan tiang pancang beton ukuran 250 x 250
mm lengkap dgn alat - alat bantu berikut dgn pengelasan
terpasang sesuai spesifikasi dan gambar

Sambungan tiang pancang ukuran 250 x 250 mm nos 15 Rate only


- -
Note : Kedalaman tiang pancang 11 m'

D PEK. DOLLY

Pekerjaan Dolly tiang pancang ukuran 250 x 250 mm, dengan titik 15 Rate only
kedalaman = 2 ~ 3 m' - -

E PEK. TEST PONDASI TIANG PANCANG (USE PILE)

Test beban pendahuluan reaction pile pada tiang pancang dengan


bh 1.00
beban sebesar 44 ton 38,953,501 38,953,501 -

Test beban pancang + PDA (Pile Driving Analysis) test ttk 1.00 7,790,700
7,790,700 -

F PEKERJAAN LAIN - LAIN

Mobilisasi dan demobilisasi blok2 beton dan peralatan loading test


lainnya (2 x 75 ton) ls 1.00 8,903,657
8,903,657 -
Loading test 2 x 75 ton titik 1.00 38,953,501
38,953,501 -

DAFTAR No. IV.1.1 - PEKERJAAN PONDASI TIANG PANCANG


Dipindahkan ke Penjumlahan Total 122,147,049 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-XIV.1.1 ( 340 ) PONDASI


DAFTAR No. XIV.1 - PEKERJAAN STRUKTUR GENSET & STP Vol Vol (+/-) Harsat Rp Rp

DAFTAR No. XIV.1.2 - PEKERJAAN TANAH

XIV.1.2.0. Catatan Harga

I Permukaan peil tanah asli dihitung rata-rata dari peil + 0,00

II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat
kerja

III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko


longsoran, volume untuk tempat kerja

IV Harga satuan pek.urugan sudah termasuk pemadatan lapis demi lapis

V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah


termasuk kebersihan jalan maupun apabila perlu dibuat cleaning pit

VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi


dan tidak mengganggu debit air di lingkungan

VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-XIV.1.2 ( 341 ) TANAH


DAFTAR No. XIV.1 - PEKERJAAN STRUKTUR GENSET & STP Vol Vol (+/-) Harsat Rp Rp

DAFTAR No. XIV.1.2 - PEKERJAAN TANAH


A Pembersihan lokasi

Pembersihan lokasi dari puing-puing, rumput-rumput dll dibuang keluar


lokasi proyek

- Lokasi area lahan Genset m2 240.00 - 11,130 2,671,097 -


- Lokasi area lahan STP m2 - exclude - -

B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu
dan kelengkapannya pada:
- Pondasi batu kali m3 165.23 - 55,640 9,193,397 -
- Pile Cap Genset m3 5.76 (0.00) 55,640 320,486 (0)
- Plat STP m3 92.84 - 55,640 5,165,590 -
- Tie Beam Genset m3 9.72 2.96 55,640 540,821 164,583

C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai inc Tie Beam Genset m3 106.11 - 272,340 28,897,997 -
- Pondasi batu kali m3 11.55 - 272,340 3,145,527 -
- Dibawah plat lantai inc Tie Beam STP m3 2.69 - 272,340 732,867 -
- Pile Cap Genset m3 0.54 (0.00) 272,340 147,064 (0)

Urugan tanah untuk mencapai level yang diinginkan, termasuk


pemadatan, dengan memaksimalkan tanah dipakai dari bekas galian
serta tanah dari luar site jika diperlukan sesuai spek dan gambar
- Pile Cap Genset m3 2.52 - 55,648 140,233 -

D Pek. Lain - Lain


D.1 Pek. Bobok kepala tiang Pondasi Pancang

Bobok kepala Borpile, termasuk buang keluar lokasi proyek sesuai


spesifikasi dan gambar

- Borpile diameter 600 mm ttk - exclude - -


D.2 Pekerjaan Anti rayap
Anti rayap pada Lantai dan dinding basement , termasuk alat - alat m2 240.00 - 16,690 4,005,600 -
bantu, peralatan perlengkapan sesuai spesifikasi dan gambar

D.3 Pekerjaan Dewatering


System Dewatering, termasuk alat - alat bantu, peralatan perlengkapan
sesuai spesifikasi dan gambar (Kontraktor diminta untuk melampirkan
breakdown harganya) Ls 1.00 - exclude - -

DAFTAR No. XIV.1.2 - PEKERJAAN TANAH


Dipindahkan ke Penjumlahan Total 54,960,679 164,583

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-XIV.1.2 ( 342 ) TANAH


DAFTAR No. XIV.1 - PEKERJAAN STRUKTUR GENSET &
Vol Vol (+/-) Harsat Rp Rp
STP

DAFTAR NO. XIV.1.3 - PEKERJAAN STRUKTUR BETON

XIV.1.3.0. Catatan Harga

I Harga satuan beton sudah termasuk semua hal yang diperlukan,


seperti : uji kubus beton, penyiraman, sambungan-sambungan
penghentian beton - ( water stop akibat penghentian pengecoran
masuk harga satuan, sedangkan water stop pada sambungan
antara plat basement dengan retaining wall seperti pada gambar
detail, dihitung tersendiri ). pembuatan parit-parit, kemiringan
level, dsb.

II Harga satuan beton sudah termasuk aditive .

III Harga satuan beton sudah termasuk penyediaan lubang-lubang


sparing M /E

IV Harga satuan pembesian sudah termasuk semua yang diperlukan,


seperti : fabrikasi, besi kaki ayam, penyokong, sisa terbuang
(waste), kawat pengikat/ bendrad, dsb.

V Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk


diameter yang sama menjadi tanggung jawab kontraktor Tabel
berat yang dipakai dalam menghitung berat besi dalam Daftar ini,
adalah :

VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315

VII Harga satuan bekisting sudah termasuk semua hal, seperti :


sparing, pembentukan sudut-sudut miring pada balok, ramp, skoor
(balok penguat, dsb )

VIII Harga satuan campuran additive water tight intergal waterproofing


camplast (dihitung berdasarkan volume beton)

IX Volume lantai kerja dihitung netto ( tidak dikurangi dengan luas


pondasi tiang pondasi )

X Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan


dan sesuai spesifikasi dan gambar.

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- XIV.1.3 ( 343 ) BETON


DAFTAR No. XIV.1 - PEKERJAAN STRUKTUR GENSET &
Vol Vol (+/-) Harsat Rp Rp
STP

DAFTAR NO. XIV.1.3 - PEKERJAAN STRUKTUR BETON

PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam Genset m3 18.41 - 667,780 12,293,830 -
2) Di bawah pelat lantai, Tie beam STP m3 1.35 - 667,780 898,498 -
3) Pile cap Genset m3 0.27 (0.00) 667,780 180,301 (0)

B Beton mutu K-300 :


1) Pile cap, pada Genset
- Genset m3 3.24 (0.00) 759,480 2,460,715 (0)
2) Tie beam Genset m3 5.69 0.65 759,480 4,321,441 492,903
C Beton mutu K-350 :
1) Balok Genset m3 18.84 0.88 782,410 14,740,604 686,770
2) Balok pondasi STP m3 0.52 - 782,410 408,418 -
3) Kolom Genset m3 6.44 0.17 782,410 5,038,720 136,922
4) Dinding STP m3 14.21 - 782,410 11,118,046 -
5) Pelat lantai dasar, pada:
- Genset m3 69.30 (45.93) 782,410 54,221,013 (35,935,504)
- STP m3 9.99 - 782,410 7,817,450 -
- Ramp m3 32.92 - 782,410 25,756,937 -
6) Pelat lantai 1, pada:
- Genset m3 47.50 (5.14) 782,410 37,164,475 (4,023,612)

PEKERJAAN PEMBESIAN
A Wiremesh 2 lapis M8-150
1) Pelat lantai dasar, pada:
- Genset m2 346.50 (166.73) 124,830 43,253,595 (20,812,282)
- Ramp m2 346.50 - 124,830 43,253,595 -

A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:


1) Pile cap Genset kg 579.81 (42.13) 8,859 5,136,247 (373,251)
2) Tie beam Genset kg 773.47 94.93 8,859 6,851,784 840,930
3) Balok Genset kg 4,408.17 805.25 8,859 39,049,774 7,133,298
4) Balok pondasi STP kg 190.80 - 8,859 1,690,185 -
5) Kolom Genset kg 976.79 26.75 8,859 8,652,894 236,986
6) Dinding STP kg 925.45 - 8,859 8,198,124 -
7) Pelat Lantai 1, pada :
- Genset kg 5,707.38 (632.68) 8,859 50,558,826 (5,604,578)
- STP kg 785.35 - 8,859 6,956,997 -

PEKERJAAN ACUAN/ BEKISTING


A Bekisting pas.bata ( batako ) adukan ( 1 pc : 4 ps ),
1) Sisi tegak pile cap Genset m2 21.60 (0.00) 84,790 1,831,464 (0)
2) Sisi tegak Tie Beam Genset m2 56.85 6.54 84,790 4,820,312 554,527

B Bekisting / acuan Fair faced Multiplek/ plat baja (exposed)


permukaan halus dan rata serta siap cat, pada:
1) Balok
- Genset m2 125.58 49.69 104,000 13,060,320 5,167,266
- STP m2 5.22 - 104,000 542,880 -
2) Kolom
- Genset m2 85.86 2.34 129,920 11,154,931 304,013
3) Pelat
- Genset m2 390.04 (203.23) 129,920 50,673,997 (26,403,901)
- STP m2 29.59 - 129,920 3,844,333 -
- Ramp m2 9.20 - 129,920 1,195,264 -
4) Dinding
- STP m2 113.68 - 112,040 12,736,707 -

PEKERJAAN LAIN-LAIN

A Pondasi Genset uk. 650x300 mm


1) Beton m3 9.75 - 782,410 7,628,498 -
2) Besi kg 630.34 58.13 8,859 5,583,827 514,904
3) Bekisting m2 9.50 - 129,920 1,234,240 -
4) Sirtu 30 cm m3 5.85 - 55,640 325,494 -
5) Lantai kerja 5 cm m3 0.98 - 667,780 651,086 -
6) Kabel Trench ukuran 80x100 cm (Provisional) m3 16.00 - 782,410 12,518,560 -

B Pondasi Genset uk. 420x300 mm


1) Beton m3 0.59 0.01 782,410 460,057 8,287
2) Besi Wiremesh M8-150 m2 8.28 (2.29) 124,830 1,033,592 (286,371)
3) Bekisting m2 1.12 0.01 129,920 145,510 655

C Pondasi Genset uk. 220x180 mm


1) Beton m3 0.40 (0.01) 782,410 309,834 (5,075)
2) Besi Wiremesh M8-150 m2 5.72 (1.82) 124,830 714,028 (227,797)
3) Bekisting m2 0.80 (0.01) 129,920 103,936 (833)

D Pondasi Genset uk. 210x215 mm


1) Beton m3 0.45 0.03 782,410 353,258 20,765
2) Besi Wiremesh M8-150 m2 6.38 (1.59) 124,830 795,791 (199,054)
3) Bekisting m2 0.85 0.02 129,920 110,432 3,192
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- XIV.1.3 ( 344 ) BETON
DAFTAR No. XIV.1 - PEKERJAAN STRUKTUR GENSET &
Vol Vol (+/-) Harsat Rp Rp
STP

DAFTAR NO. XIV.1.3 - PEKERJAAN STRUKTUR BETON

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- XIV.1.3 ( 345 ) BETON


DAFTAR No. XIV.1 - PEKERJAAN STRUKTUR GENSET &
Vol Vol (+/-) Harsat Rp Rp
STP

DAFTAR NO. XIV.1.3 - PEKERJAAN STRUKTUR BETON

E Pondasi Batu Kali Genset


1) Pondasi Batu Kali m3 38.75 - 611,910 23,711,513 -
2) Pasangan Aanstamping t=15cm m3 17.22 - 398,440 6,861,137 -
3) Beton tumbuk m3 7.75 - 720,190 5,581,473 -
4) Angkur D13-500 kg 90.14 - 18,920 1,705,473 -

F Pondasi Batu Kali Ramp


1) Pondasi Batu Kali m3 35.78 - 611,910 21,894,140 -
2) Pasangan Aanstamping t=15cm m3 5.88 - 398,440 2,342,827 -
3) Beton tumbuk m3 1.69 - 720,190 1,217,121 -
4) Angkur D13-500 kg 20.00 - 18,920 378,405 -
5) Pasangan Gravel m3 8.75 - - -

G Ruang Pompa Cross Country


1) Beton m3 12.42 - 782,410 9,716,750 -
2) Besi kg 963.48 - 8,859 8,535,024 -
3) Bekisting m2 74.75 - 129,920 9,711,520 -
4) Galian Tanah m3 31.70 - 55,640 1,763,871 -
5) Urugan Pasir 10 cm m3 1.35 - 667,780 900,835 -
6) Lantai kerja 5 cm m3 0.67 - 782,410 527,736 -
7) Waterstop m' 15.22 - 94,600 1,439,812 -
8) Integral m3 12.42 - 100,170 1,244,011 -
9) Manhole uk 100 x 60 cm unit 1.00 - 222,591 222,591 -

H Bak kontrol
1) Beton m3 0.16 - 782,410 124,873 -
2) Besi kg 29.89 - 8,859 264,762 -
3) Bekisting m2 2.02 - 129,920 261,919 -
4) Galian Tanah m3 0.28 - 55,640 15,540 -
5) Urugan Pasir 10 cm m3 0.05 - 667,780 32,721 -
6) Lantai kerja 5 cm m3 0.02 - 782,410 19,169 -
7) Waterstop m' 2.80 - 94,600 264,880 -
8) Integral m3 0.16 - 100,170 15,987 -
9) Manhole uk 100 x 60 cm unit 1.00 - 222,591 222,591 -

I Ruang Pompa Water Supply


1) Beton m3 9.60 - 782,410 7,509,180 -
2) Besi kg 1,142.07 - 8,859 10,117,058 -
3) Bekisting m2 62.78 - 129,920 8,156,378 -
4) Galian Tanah m3 21.88 - 55,640 1,217,125 -
5) Urugan Pasir 10 cm m3 0.88 - 667,780 584,308 -
6) Lantai kerja 5 cm m3 0.44 - 782,410 342,304 -
7) Waterstop m' 12.52 - 94,600 1,184,392 -
8) Integral m3 9.60 - 100,170 961,382 -
9) Manhole uk 100 x 60 cm unit 1.00 - 222,591 222,591 -

Waterproofing membrane termasuk screed tebal rata-rata 50


J mm + wire mesh M6 termasuk peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar: (Provisional)

1) lantai atap
- Atap dak m2 201.47 124.36 127,690 25,725,066 15,879,688
DAFTAR NO. XIV.1.3 - PEKERJAAN STRUKTUR BETON
Dipindahkan ke Penjumlahan Total 676,847,284 (61,891,153)

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- XIV.1.3 ( 346 ) BETON


DAFTAR No. XIV.2 - PEKERJAAN ARSITEKTUR Vol Vol (+/-) Harsat Rp Rp (+/-)
GENSET & STP

DAFTAR NO. XIV.2.1. - PEKERJAAN DINDING

XIV.2.1.0. Catatan Harga

I Harga satuan dinding batako, bata, hebel, celcon sudah


termasuk adukan biasa atau drymix, kolom praktis, ringbalk,
angkur, sparing dan semua pekerjaan bantu yang
berhubungan dengan pekerjaan dinding tersebut.

II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton
maupun bata , kawat ayam (jika diperlukan) dan semua
pekerjaan bantu yang berhubungan dengan plesteran. Volume
plesteran dan acian sudah ditambahkan 10cm di atas plafond

III Harga satuan pekerjaan pelapis dinding (seperti : granit,


marmer, keramik, porselin) sudah termasuk adukan, cor
beton,perekat (calbond), angkur, kawat pengikat alumunium
fixing pada dinding dengan ketinggian lebih dari 2m,
pemotongan, pinggulan, adu manis, naad, dan alat bantu
lainnya

IV Harga satuan pekerjaan plesteran sudah termasuk untuk


dinding kedap air sesuai gambar dan spesifikasi

V Harga satuan pekerjaan cat dinding sudah termasuk


pengertian cat dasar (meni, plamur, stained, sealer).

VI Harga satuan pekerjaan sudah termasuk alat-alat yang


diperlukan dan sesuai spesifikasi.

I PEK. PASANG DINDING

A Pasangan Bata ringan tebal 100 mm, setara ex. primacon,


termasuk dinding penebalan,urinoir, perekat, adukan kering
kolom
- Lantaidan
1 balok praktis sesuai spesifikasi dan gambar :
Genset m2 347.64 103,480 35,973,994 -

II PEK. PELAPIS DINDING

A Plesteran dan Acian, Plesteran halus berikut acian halus,


termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :
- Lantai 1
Baseplate pdtm m2 63.93 61,540 3,934,191 -
Gardu PLN m2 90.64 61,540 5,578,035 -
Genset m2 164.20 61,540 10,105,053 -
Kapasitor bank m2 58.02 61,540 3,570,723 -
Ruang Trafo m2 60.62 61,540 3,730,382 -
Ruang PDTR m2 77.59 61,540 4,774,889 -
Dinding external m2 221.92 61,540 13,656,932 -

B Pengecatan dengan fin. cat Interior ex.Jotun tipe standar,


termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :

- Lantai 1
Baseplate pdtm m2 63.93 18,360 1,173,736 -
Gardu PLN m2 90.64 18,360 1,664,165 -
Genset m2 164.20 18,360 3,014,767 -
Kapasitor bank m2 58.02 18,360 1,065,299 -
Ruang Trafo m2 60.62 18,360 1,112,932 -
Ruang PDTR m2 77.59 18,360 1,424,552 -

C Cat weathershiled setara ex.Jotun Tipe standar, termasuk


peralatan dan perlengkapan sesuai spesifikasi dan gambar
pada :
Eksterior
- Lantai 1
Dinding external m2 221.92 29,490 6,544,409 -
DAFTAR No. XIV.2 - PEKERJAAN ARSITEKTUR Vol Vol (+/-) Harsat Rp Rp (+/-)
GENSET & STP

DAFTAR NO. XIV.2.1. - PEKERJAAN DINDING

DAFTAR NO. XIV.2.1. - PEKERJAAN DINDING 97,324,059 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XIV.2 - PEKERJAAN ARSITEKTUR GENSET & Vol Vol (+/-) Harsat Rp Rp (+/-)
STP

DAFTAR NO. XIV.2.2 - PEKERJAAN PINTU dan JENDELA

XIV.2.2.0. Catatan Harga

I Harga satuan pintu dan jendela kayu sudah termasuk angkur,


perlengkapan kaca, pemasangan kolom & ringbalk praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).

II Harga satuan pintu dan jendela besi sudah termasuk angkur,


pengelasan, kaca, pemasangan kolom & balok praktis sekeliling
pintu & jendela , dan peralatan bantu yang diperlukan dan bahan
yang terbuang (waste).

III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).

IV Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

A PINTU BAJA
Pintu Baja P1 terdiri dari 2 daun pintu ukuran 2120x2150mm
kusen besi finish powder coating, lengkap terpasang termasuk,
hardware, accesories
Ruang Kapasitor, danPDTR,
Ruang perlengkapan bantuRuang
Ruang Trafo, lainnyagardu
sesuai
PLN
- Lantai 1 unit 5.00 (2.00) 2,281,562 11,407,811 (4,563,124)

Hardware :
Ring handle art-8-3 SS bh 1.00 2.00 - -
Shaft door art -542 Nickel bh 1.00 2.00 - -
Anak kunci shaft door art-543 Nickel bh 1.00 2.00 - -
Hinges Gracia BB 4"x3"x3 mm SS bh 2.00 4.00 - -

Pintu Baja P2 terdiri dari 1 daun pintu ukuran 2120x2150mm


kusen besi finish powder coating, lengkap terpasang termasuk,
hardware,
Baseplate accesories
PDTM, Ruang danGardu
perlengkapan
PLN bantu lainnya sesuai
- Lantai 1 unit 2.00 (1.00) 2,225,914 4,451,829 (2,225,914)

Hardware :
Ring handle art-8-3 SS bh 1.00 (1.00) - -
Shaft door art -542 Nickel bh 1.00 (1.00) - -
Anak kunci shaft door art-543 Nickel bh 1.00 (1.00) - -
Hinges Gracia BB 4"x3"x3 mm SS bh 2.00 (2.00) - -

B JENDELA

Jendela J1 Alumunium powder coating ukuran 1030x1350 , tebal


kaca 5 mm lengkap terpasang termasuk, hardware, accesories
dan perlengkapan bantu lainnya sesuai spesifikasi dan gambar
Ruang Kapasitor, Ruang PDTR, Ruang Trafo
- Lantai 1 unit 3.00 - 1,558,700 4,676,100 -

DAFTAR NO. XIV.2.2 - PEKERJAAN PINTU dan JENDELA 20,535,740 (6,789,039)


Dipindahkan ke Penjumlahan Total
DAFTAR No. XIV.2 - PEKERJAAN ARSITEKTUR GENSET Vol Vol (+/-) Harsat Rp Rp (+/-)
& STP

DAFTAR NO. XIV.2.3 - PEKERJAAN LANTAI

XIV.2.3.0. Catatan Harga

I Harga satuan sudah termasuk pemasangan border,


pemotongan, pembersihan, perapihan dan bahan yang
terbuang (waste)
II Harga satuan sudah termasuk levelling (sloping) mortarmix
sesuai yang disyaratkan

III Luas pelapis lantai dihitung netto (luas bersih)

IV Setiap pekerjaan harus sesuai dengan petunjuk yang


disyaratkan pabrik pembuat

FLOOR HARDENER

Floor Hardener 3kg/m2, termasuk alat alat bantu lainnya


dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :

Baseplate pdtm m2 16.23 33,390 541,920 -


Gardu PLN m2 28.13 33,390 939,261 -
Genset m2 87.62 33,390 2,925,632 -
Kapasitor bank m2 14.10 33,390 470,799 -
Ruang Trafo m2 15.59 33,390 520,550 -
Ruang PDTR m2 23.60 33,390 788,004 -
Selasar m2 114.34 33,390 3,817,813 -
Ramp m2 74.00 33,390 2,470,860 -

DAFTAR NO. XIV.2.3 - PEKERJAAN LANTAI 12,474,838 -


Dipindahkan ke Penjumlahan Total
Vol Vol (+/-) Harsat Rp Rp (+/-)
DAFTAR No. XIV.2 - PEKERJAAN ARSITEKTUR GENSET & STP

DAFTAR NO. XIV.2.4 - PEKERJAAN PLAFOND

XIV.2.4.0. Catatan Harga

I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka


pada pertemuannya dengan kolom, balok, dinding dan lubang equipment
M/E (lampu, grill AC, dll.)

II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.

III Harga satuan plafond papan kayu, pergola, lambresiring sudah


termasuk anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire
retardant dan telah dikeringkan (dryclean)

IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C

V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)

VI Harga satuan list-list plafond sudah termasuk rangka pendukung dan


finishing (pengecatan)

VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line

VIII Harga satuan pekerjaan sesuai dengan Gambar dan spesifikasi

A Beton exposed aci halus, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai dengan spesifikasi dan gambar pada :

Baseplate pdtm m2 16.23 33,950 551,009 -


Gardu PLN m2 28.13 33,950 955,014 -
Genset m2 87.62 33,950 2,974,699 -
Kapasitor bank m2 14.10 33,950 478,695 -
Ruang Trafo m2 15.59 33,950 529,281 -
Ruang PDTR m2 23.60 33,950 801,220 -
Selasar m2 114.34 33,950 3,881,843 -

DAFTAR NO. XIV.2.4 - PEKERJAAN PLAFOND 10,171,760 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XIV.2 - PEKERJAAN ARSITEKTUR GENSET & Vol Vol (+/-) Harsat Rp
STP

DAFTAR NO. XIV.2.5. - PEKERJAAN SANITARY

XIV.2.5.0. Catatan Harga

I Harga satuan Upah sanitair (sanitary equipment) dengan


kelengkapan material bantu (adukan, plesteran, acian, nad, sealan,
grouting, bahan bantu pengubung (doble niple) yang berhubungan
dengan instalasi ME dan lainnya berikut pemasangan dan
perapihannya.

II Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

III Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

DAFTAR NO. XIV.2.5. - PEKERJAAN SANITARY -


Dipindahkan ke Penjumlahan Total
Vol Vol (+/-) Harsat Rp Rp (+/-)
DAFTAR No. XIV.2 - PEKERJAAN ARSITEKTUR GENSET & STP

DAFTAR No. XIV.2.6 - PEKERJAAN LAIN-LAIN

XIV.2.6.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk pemasangan sparing-sparing sesuai


gambar dari konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan, perapihan,


pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

1 Tangga besi moveable (Provisional)


Tangga besi moveable terpasang, sesuai gambar dan spesifikasi pada :
Lantai 1 unit 1.00 2,782,393 2,782,393 -

DAFTAR No. XIV.2.6 - PEKERJAAN LAIN-LAIN 2,782,393 -


Dipindahkan ke Penjumlahan Total
DAFTAR No. XIV.2 - PEKERJAAN ARSITEKTUR GENSET & Vol Vol (+/-) Harsat Rp
STP

DAFTAR No. XIV.2.7. - PEKERJAAN ATAP CANOPY

XIV.2.7.0. Catatan Harga

I Harga satuan sudah termasuk fitting, accessories, alat bantu,


perlengkapan dan peralatan yang diperlukan.

II Harga satuan sudah termasuk perkuatann sesuai gambar dari


konsultan terkait.

III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan


pabrik pembuat.

IV Harga satuan sudah termasuk pemotongan, pembersihan,


perapihan, pinggulan dan bahan yang terbuang (waste).

V Harga satuan pekerjaan sesuai dengan gambar dan spesifikasi.

DAFTAR No. XIV.2.7. - PEKERJAAN ATAP CANOPY -


Dipindahkan ke Penjumlahan Total
Vol Vol (+/-) Harsat Rp Rp (+/-)
DAFTAR No. XIV.2 - PEKERJAAN ARSITEKTUR GENSET & STP

DAFTAR NO. XIV.2.8 - PEKERJAAN FAÇADE

XIV.2.8.0. Catatan Harga ( Pricing Notes )

I Harga satuan rangka aluminium pada curtain wall system sudah

termasuk perlengkapan untuk sambungan-sambungan, rubber gasket

(sealant), neoprene, penyetelan dan pemasangan.

II Harga satuan kaca pada curtain wall system sudah termasuk


perlengkapan untuk sambungan-sambungan, list-list dari sealant
silikon, rubber gasket (sealant), neoprene, penyetelan dan
pemasangan serta perkuatan struktur jika diperlukan.

III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.

IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.

V Harga satuan pintu otomatis (main entrances) sudah termasuk alat


penggantung (ironmongery sets) dan sistem kunci (keying system) dan
pemasangannya.

VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail

VII Harga satuan harus disesuaikan dengan jawaban dari konsultan


maupun pemberi tugas atas pertanyaan-pertanyaan tertulis dari peserta
tender, seperti merk dan jenis kunci ataupun alat-alat penggantung, dll..

A KISI-KISI
Kisi-kisi bata finished cat uk. 500 x 200 mm berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar pada :
(Provisional)
- Eksterior
Genset m2 245.80 136,870 33,643,303 -

DAFTAR NO. XIV.2.8 - PEKERJAAN FAÇADE 33,643,303 -


Dipindahkan ke Penjumlahan Total
DAFTAR NO. XIV - PROVISIONAL SUM, Provisional Sum for Contingencies Rp
and Dayworks Allowances

XIV.1.0. Catatan Harga

I
Jumlah satuan pekerjaan maupun jumlah biaya cadangan (contingency) dan
Dana Bersyarat (Provisional Sum) yang tercantum dalam daftar ini adalah masih
diperkirakan (belum pasti), tetapi harga satuannya sudah tetap (mengikat),
sedangkan volume maupun biaya yang pasti akan dihitung kemudian.

II Biaya perkiraan dan contingency ini digunakan jika terdapat pekerjaan tambah
atas instruksi tertulis yang diterbitkan oleh Manajemen Konstruksi atau Pemberi
Tugas.

III
Harga satuan yang dicantumkan oleh Pemborong sudah mencakup keuntungan,
biaya tidak terduga seperti : waktu yang tidak produktif, lembur, bahan yang
terbuang, bahan bakar, asuransi, peralatan, biaya kerusakan, transportasi,
administrasi, supervisi, alat

IV 1 ( satu ) hari sama dengan 7 ( tujuh ) jam kerja atau 8 ( delapan ) jam termasuk
1 ( satu ) jam untuk istirahat.

V
Pemborong harus mengisi harga pada semua butir-butir yang terlampir.

XIV.1 - Dana bersyarat untuk Pekerjaan Struktur


( Provisional Sum )

Dana bersyarat untuk pekerjaan atau biaya yang belum terdefenisi jelas
pada gambar dan spesifikasi / belum jelas

A. Engineering Equipment
1 Tractor Model racetracks (perbuah) 376,190,100 buah 2.00 -
2 Mobil tangki 5000 liter (per unit) 275,000,000 unit 3.00 -
3 Arena Surface 135,000,000 ls 1.00 -
4 Riding track drag 57,142,800 ls 1.00 -

B. Competition Equipment
1 Show jumping & Eventing (per buah) 15,000,000 buah 30.00 -
2 Horse truck transport 380,952,000 unit 2.00 -
3 Timer + 2 Scoring board 714,285,000 unit 2.00 -
4 Struktur Covered training area 2,500,000,000 unit 1.00 -
5 Special Footing 8,500,000,000 item 1.00 -
6 Cadangan Genset 1,600,000,000 item 1.00 -

XIV.2 - Dana bersyarat untuk biaya cadangan (Provisional Sum for Contingencies)

Biaya Cadangan sebesar Rp . item 1.00 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VI ( 357 ) SAMEP


DAFTAR NO. XIV - PROVISIONAL SUM, Provisional Sum for Contingencies Rp
and Dayworks Allowances

VI.3 - Pekerjaan Harian (Daywork Allowance)

Tenaga Kerja : ( Rate Only )

Pekerja hari 1.00


Tukang Bobokan (beton/dinding) hari 1.00
Tukang Cor beton hari 1.00
Tukang Besi beton hari 1.00
Tukang Konstruksi Baja hari 1.00
Tukang kayu (acuan/kuda-kuda) hari 1.00
Tukang kayu halus (kusen/pintu) hari 1.00
Tukang batu/bata hari 1.00
Tukang pasang pelapis/tegel hari 1.00
Tukang cat hari 1.00
Tukang kaca hari 1.00
Tukang Aluminium hari 1.00
Tukang las hari 1.00
Tukang listrik hari 1.00
Tukang plumbing hari 1.00
Tukang gali hari 1.00
Juru ukur hari 1.00
Pelaksanaan lapangan hari 1.00
Asisten Pelaksanaan lapangan hari 1.00
Site Engineer hari 1.00
Project Manager hari 1.00
Alat Boring komplit dengan Operator, Bahan Bakar dan Supervisi hari 1.00
Pompa dewatering berikut kelengkapannya (kap …. lt/det) hari 1.00
Pompa air, dengan Operator , bahan bakar (kap = ………lt/det) hari 1.00

Peralatan : ( Rate Only )

Molen (kap. 250 It), dengan operator , bahan bakar , supervisi hari 1.00
Molen (kap. 350 It), dengan operator, bahan bakar , supervisi hari 1.00
Alat Penggetar Beton , dengan operator , bahan bakar hari 1.00
Mesin las dengan operator dan bahan bakar hari 1.00
Mobil pick up dengan open dan bahan bakar hari 1.00
Truk kapasitas 5 ton dengan supir dan bahan bakar hari 1.00
Truk kapasitas 8 ton dengan supir dan bahan bakar hari 1.00
Mesin wales 10 ton, dengan supir dan bahan bakar hari 1.00
Jack hammering dengan operator dan bahan bakar hari 1.00
Stumper dengan operator, bahan bakar , supervisi hari 1.00
Backhoe loader dengan operator , bahan bakar (kap = 0,25 m³) hari 1.00
Dozer (type D6) dengan operator , bahan bakar (kap = …… m³) hari 1.00
Dozer (type D7) dengan operator , bahan bakar (kap = ...… m³) hari 1.00
Tower crane, dengan operator dan bahan bakar hari 1.00
Hoist dengan operator dan bahan bakar (kap = 2 x 1 ton) hari 1.00
Kompressor, dengan operator dan bahan bakar hari 1.00
Generating set kap.100 Kva , dengan operator , bahan bakar hari 1.00
Scaffolding (diluar/pinggir bangunan) untuk setiap 1 M² hari 1.00
Gudang sementara m² 1.00

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VI ( 358 ) SAMEP


DAFTAR NO. XIV - PROVISIONAL SUM, Provisional Sum for Contingencies Rp
and Dayworks Allowances

Bahan atau Material Bangunan :

Pasir m3 1.00
Batu split m3 1.00
Batu kali m3 1.00
Semen @ 50 kg Zak 1.00
Beton fc' 30 MPa m3 1.00
Beton fc' 25 MPa m3 1.00
Batu bata Bh 1.00
Celcon block Bh 1.00
Besi beton ulir Kg 1.00
Besi beton polos Kg 1.00
Baja siku Kg 1.00
Baja Channel Kg 1.00
Baja WF Kg 1.00
Kayu Nyatoh m3 1.00
Kayu Merbau m3 1.00
Multiplek 9 mm Lbr 1.00
Multiplek 12 mm Lbr 1.00

Upah pekerjaan : ( Rate Only )

Bobokan beton bertulang m3


Bobokan dinding bata m2
Perapihan opening dinding bata m2
Pembuangan tanah lumpur m3
Buang puing keluar lokasi proyek m3
Pekerjaan Las Titik
Bobok dan pasang kembali kusen pintu ( di atas 1 m 2 ) Bh
Bobok dan pasang kembali kusen jendela ( di atas 1 m2 ) Bh
Bongkar dan pasang kembali paving blok m2
Bongkar dan pasang kembali plafon gypsum m2
Pelobangan plat beton untuk pipa termasuk perapihan kembali Titik
Bongkar besi tulangan ( plat, balok, kolom, dll ) Kg
Pasang besi tulangan Kg
Bobokan keramik ( lantai dan dinding ) m2
Plamur pada cat tembok m2
Ketrikan pada beton m2
Ketrikan pada plaster + aci m2
Tali air m
Profilan pada dinding bata m

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VI ( 359 ) SAMEP


DAFTAR NO. XIV - PROVISIONAL SUM, Provisional Sum for Contingencies Rp
and Dayworks Allowances

DAFTAR NO. XIV - PROVISIONAL SUM, Provisional Sum for Contingencies and Dayworks Allowances -
Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-VI ( 360 ) SAMEP


PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR BANGUNAN TRIBUN
PROYEK EQUESTRIAN - JAKARTA

DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL


SAT VOLUME
(PRELIMINARIES) SATUAN ( Rp )

Catatan Harga ( Pricing Notes ) :

I
Kontrak ini bersifat Harga Tetap (Lump Sum Fix Price), kecuali dimana
dicantumkan Provisional atau "Provisional Sum". Kontraktor wajib
menghitung kembali volume pekerjaan dan memeriksa satuannya yang dibuat
oleh Quantity Surveyor dan jika menurut perhitungan Kontraktor volume dan
atau satuannya tidak sesuai atau terdapat item pekerjaan yang belum
tercantum, maka Kontraktor dapat merubah atau menambahkan pada
lampiran khusus yang dibuat untuk pekerjaan tambah atau kurang.

II Harga yang tercantum di dalam Pekerjaan Persiapan, Prasarana dan


Penunjang (Preliminaries) sudah mencakup keseluruhan pekerjaan termasuk
pekerjaaan tambahn kurang dan sudah diperhitungkan terhadap :
- Penambahan dan pengurangan volume pada item pekerjaan di dalam
kontrak
- Peniadaan dan penambahan bagian pekerjaan
- Perubahan kwalitas pekerjaan
- Perubahan-perubahan level, garis-garis as, posisi-posisi dan ukuran-
ukuran bagian pekerjaan
- Pekerjaan tambah kurang lainnya
- Perpanjangan waktu pelaksanaan (± 2 bulan)

III
Dalam mengajukan harga pekerjaan ini Pemborong harus sudah
mempertimbangkan untuk memasukkan semua biaya pengeluaran pekerjaan
dan tidak ada tuntutan di kemudian hari terhadap Pemberi tugas, bila daftar
uraian pekerjaan/BQ ini dipandang tidak lengkap.

IV
Semua hal yang tidak tercantum disini dianggap sudah termasuk didalam
penawaran dan semua resiko baik mengenai eskalasi harga, salah hitung
terhadap volume maupun harga yang diajukan dan kekurangan item pekerjaan
dan biaya-biaya lain yang tak terduga adalah tetap menjadi tanggung jawab
Pemborong. Karena BQ sesudah penawaran adalah BQ Pemborong

V
Pemborong sudah harus memperhitungkan/mempertimbangkan semua
kemungkinan-kemungkinan yang terjadi di lapangan dalam pelaksanaan
berhubung adanya Pemborong-Pemborong lain unutk pelaksanaan Proyek
tersebut

576900177.xlsx Daf-1 Persiapan1 Hal.1/390 BUILDING DAN FASILITAS PAKET 2


DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL
SAT VOLUME
(PRELIMINARIES) SATUAN ( Rp )

Proyek Manajemen dan Biaya Administrasi Lapangan


1 Item 1 15,000,000 15,000,000
Pemborong harus menyediakan biaya - biaya yang dikeluarkan untuk
mengadakan tenaga teknis dan tenaga pimpinan proyek di lapangan yang
kompeten, cakap, menguasai bidang pekerjaan dengan baik dan
berpengalaman, yang akan mengelola pelaksanaan pekerjaan, semua biaya
administrasi dan biaya mengurus segala hal yang berhubungan dengan
tanggung jawabnya terhadap kontrak ini .

Peralatan dan Perlengkapan Kerja


2 Item 1 18,750,000 18,750,000
Pengadaan peralatan dan perlengkapan kerja yang lengkap untuk kelancaran
pelaksanaan pekerjaan sebagaimana yang dimaksud didalam Dokumen
Kontrak, termasuk biaya ijin pemasukan peralatan ke dalam lokasi proyek,
pemeliharaan dan pemindahan dari satu tempat ke tempat lainnya di dalam
lokasi pekerjaan serta mengeluarkannya setelah penyelesaian pekerjaan,
misalnya Tower Crane, Alimax, Scaffolding, dan lain-lain, tidak terbatas pada
alat tersebut.

Peralatan dan Perlengkapan Keselamatan Kerja serta P3K


3 Item 1 1,855,000 1,855,000
Pemborong bertanggung jawab atas pengadaan alat-alat keselamatan kerja
seperti helm, sepatu lapangan, jas hujan, sabuk pengaman, handy talky, dan
lain-lain sebanyak yang diperlukan untuk Pekerja dan Staff Pemborong, serta
terhadap pihak lain di dalam lokasi proyek (Pemberi Tugas, QS, Konsultan
Pengawas). Pengadaan pelatihan keselamatan kerja secara berkala untuk
tenaga-tenaga kerja dan pihak-pihak terkait lain, pengadaan peralatan K3 di
lapangan serta penyediaan tenaga-tenaga khusus K3 yang mencukupi selama
pelaksanaan proyek.

Rapat Proyek
4 Item 1 200,000 200,000
Pemborong harus menyediakan fasilitas yang diperlukan termasuk akomodasi
dan konsumsi (snack) untuk pelaksanaan rapat rutin di proyek dengan Pemberi
Tugas, Pimpinan Proyek, para Konsultan dan para Kontraktor paket lain serta
mengkoordinasikannya.

Pengadaan Gambar
5 Pengadaan gambar For Construction untuk pelaksanaan by Perenana, Item 1 300,000 300,000
sedangkan memperbanyak untuk keperluan kerja di lapangan termasuk 2 (dua)
set untuk keperluan pengawasan.

Laporan
6 Pemborong wajib membuat Laporan Harian, Mingguan dan Bulanan, laporan
Item 1 exclude -
progress pekerjaan serta laporan lainnya

Photo - Photo Kemajuan Pekerjaan


7 Item 1 350,000 350,000
Pembuatan photo berwarna atas kemajuan pekerjaan sebanyak 4 (empat) set
untuk diserahkan setiap bulan hingga masa serah terima ke-1 (pertama) serta
setiap tahap pengajuan pembayaran (penagihan) dan diserahkan kepada
Pemberi Tugas.

Kantor Konsultan dan Direksi di Lapangan


8 Pembuatan Kantor Sementara untuk Konsultan dan Konsultan lainnya di Item 1 exclude -
lapangan berikut semua fasilitas yang diperlukan seperti listrik, air, telepon, AC,
toilet, meja, kursi, filling cabinet dan perlengkapan penunjang lainnya dan
bertanggung jawab atas pemeliharaan, kebersihan dan pengadaan peralatan
atau perabotannya selama proyek berlangsung dan memindahkan ke tempat
lainnya di dalam lokasi pekerjaan apabila ada perintah membongkar setelah
pekerjaan selesai.

Kantor Pemborong Lapangan


9 Kantor sementara pemborong di lapangan berikut semua fasilitas yang Item 1 exclude -
diperlukan termasuk toilet untuk para pekerja dan berikut pemeliharaan
selama pelaksanaan pekerjaan dan memindah-mindahkan dalam lokasi
pekerjaan bila ada perintah, Pemborong berkewajiban dalam pemeliharaan
kebersihan didalam lokasi pekerjaan, pembongkaran bila ada perintah
membongkar setelah pekerjaan selesai dan merapihkan bekas lokasinya.

576900177.xlsx Daf-1 Persiapan1 Hal.2/390 BUILDING DAN FASILITAS PAKET 2


DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL
SAT VOLUME
(PRELIMINARIES) SATUAN ( Rp )

Gudang Sementara dan Los Kerja


10 Pengadaan gudang sementara dan los pekerjaan di lapangan berikut Item 1 exclude -
pemeliharaannya dan membongkar setelah pekerjaannya selesai serta
memperbaiki, merapihkan dan membersihkannya

Pagar Sementara Proyek


11 Item 1 exclude -
Pembuatan pagar sementara proyek tidak boleh melewati batas - batas lokasi
tanah proyek (site) termasuk pemeliharaannya dan membongkar setelah
pekerjaan selesai serta memperbaiki, merapihkan dan membersihkan kembali
sesuai ketentuan lingkungan yang ditetapkan oleh Peraturan Pemerintah
Daerah, sedangkan ukuran, bentuk, spesifikasi materialnya sesuai dengan yang
ditetapkan Pemberi Tugas.

Kebersihan dan Kerapihan


12 Item 1 3,000,000 3,000,000
Pemborong harus mengangkut ke luar lokasi proyek semua sampah secara
teratur jika sudah bertumpuk dan pada waktu penyelesaian pekerjaan harus
bersih dan rapih. (Catatan : Dalam pengangkutan keluar proyek tidak boleh
mengotori jalan dan prasarana umum).

Keamanan Proyek
13 Item 1 3,000,000 3,000,000

Pemborong bertanggung jawab atas penjagaan, dan perlindungan terhadap


pekerjaan yang dianggap penting selama masa pelaksanaan kontrak siang dan
malam . Pemberi tugas tidak bertanggung jawab terhadap pemborong dan sub
Pemborong atas kehilangan, kerusakan bahan-bahan bangunan, peralatan atau
pekerjaan yang sedang dalam pelaksanaan. Pemborong wajib menempatkan
tenaga Satpam yang terlatih dan mencukupi selama 24 jam untuk penjagaan
keamanan terhadap pencurian dan oknum-oknum yang mengganggu
ketertiban termasuk kerjasama dengan satuan Polri setempat.

Listrik Kerja dan Penerangan Malam Hari


14 Item 1 3,000,000 3,000,000
Menyediakan pembangkit tenaga listrik sementara atau penerangan buatan
termasuk pemasangan kabel-kabel dan meteran yang dipergunakan untuk
keperluan kerja atau pengambilan daya dari sumber atau PLN yang sudah ada,
maka semua biaya pengadaan dan pemakaian daya selama pelaksanaan proyek
termasuk izin yang diperlukan serta perapihan setelah pekerjaan selesai sudah
harus diperhitungkan oleh pemborong termasuk penerangan malam hari pada
tempat-tempat strategis sepanjang sisi dalam proyek.

Pengukuran dan Bouwplank


15 Item 1 exclude -

Pemborong harus menyediakan peralatan yang diperlukan seperti alat ukur


optik, waterpass, theodlit, dll, dan juru ukur yang berpengalaman. Penentuan
letak titik-titik patok pengukuran dilapangan bersama Pemberi Tugas dan harus
dijaga dari kerusakan-kerusakan. Setiap titik patok pengukuran yang tidak
pada tempatnya lagi atau hilang harus dibuat lagi, penentuan peil-peil
pekerjaan akan diambil dari titik-titik yang teliti. Kesalahan yang timbul dalam
pengambilan ukuran dan perubahan letak atau hilangnya titik-titik patok
pengukuran menjadi tanggung jawab pemborong. Dalam hal ini pemborong
harus mengadakan pegawai sebanyak yang diperlukan untuk membantu
Pemberi Tugas untuk melaksanakan pekerjaan diatas dengan biaya ditanggung
pemborong.

Kerusakan Dan Kerugian terhadap Bangunan Lain


16 Item 1 exclude -
Semua kerusakan atau kerugian terhadap bangunan atau jaringan instalasi di
sekitarnya maupun jaringan instalasi yang sudah ada dari PLN, PAM, Perumgas,
Peumtel, PU, dsb yang berada di lokasi proyek selama waktu pelaksanaan
menjadi tanggung jawab sepenuhnya pemborong. Berikut pemindahan
jaringan-jaringan instalasi tersebut di atas juga menjadi tanggung jawab
pemborong, jika jaringan tersebut mengganggu dalam pelaksanaan proyek,
termasuk pengurusan izin-izin pada instansi yang bersangkutan.

576900177.xlsx Daf-1 Persiapan1 Hal.3/390 BUILDING DAN FASILITAS PAKET 2


DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL
SAT VOLUME
(PRELIMINARIES) SATUAN ( Rp )

DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG ( PRELIMINARIES ) 45,455,000


Dipindahkan ke Penjumlahan Total

576900177.xlsx Daf-1 Persiapan1 Hal.4/390 BUILDING DAN FASILITAS PAKET 2


PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR BANGUNAN TRIBUN
PROYEK EQUESTRIAN - JAKARTA

DAFTAR No. 2 - PEKERJAAN BONGKARAN STRUKTUR HARGA TOTAL TOTAL +/-


SAT VOLUME VOLUME +/-
SATUAN ( Rp ) ( Rp )
DAFTAR NO. 2.1. - PEKERJAAN BONGKARAN STRUKTUR

2.1. Catatan Harga

I Harga satuan bongkaran beton sudah termasuk buangan


keluar site

II Harga satuan bongkaran beton sudah termasuk pembersihan


area site

III Harga Bongkaran Kolom sudah termasuk beton dan besi.

IV Harga Bongkaran Shear Wall sudah termasuk beton dan besi


serta peralatan yang akan digunakan.

V Harga satuan bongkaran plat Lantai sudah termasuk


bongkaran bondek, beton dan besi serta peralatan yang
akan digunakan.

X Harga satuan bongkaran balok baja canopy sudah termasuk


baut-baut, assesoris dan kelengkapan lainnya..

PEKERJAAN BONGKARAN BETON

1 Bongkaran Kolom, pada : (Reff : Gbr. )


- Denah Kolom Elevasi +8.36 m3 0.54 1,068,400 576,936 -

2 Bongkaran Plat inc Screed dan finishing lantai diatasnya, tebal = 15cm, pada : (Reff : Gbr.)
- Denah Pelat Elevasi +4.36 m2 93.93 194,768 18,294,512 -
- Denah Pelat Elevasi +8.36 m2 72.83 194,768 14,184,917 -
- Denah Pelat Elevasi +12.36 m2 49.78 194,768 9,695,526 -

3 Bongkaran Balok, pada : (Reff : Gbr.)


- Denah Balok Elevasi +4.36 m3 12.04 1,068,400 12,866,114 -
- Denah Balok Elevasi +8.36 m3 14.51 1,068,400 15,498,384 -
- Denah Balok Elevasi +12.36 m3 11.37 1,068,400 12,152,957 -

4 Bongkaran Tangga (Plat Miring, Balok Bordes, Plat Bordes, dan Trap tangga), tinggi trap = 17cm pada : (Reff : )
- Denah Balok Elevasi +4.36 m2 81.30 194,768 15,834,598 -
- Denah Balok Elevasi +8.36 m2 81.30 194,768 15,834,598 -

5 Bongkaran Core Lift, pada : (Reff : Gbr.)


- Denah Balok Elevasi +4.36 m3 19.23 1,068,400 20,542,768 -
- Denah Balok Elevasi +8.36 m3 19.23 1,068,400 20,542,768 -
- Denah Balok Elevasi +12.36 m3 19.23 1,068,400 20,542,768 -

6 Bongkaran Tangga, tinggi trap = 20 cm pada :


- Tribune penonton m2 197.95 194,768 38,554,228 -

DAFTAR NO. 2. - PEKERJAAN STRUKTUR 215,121,073 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-2 Str1 Hal.1/390 BUILDING DAN FASILITAS PAKET 2
DAFTAR No. 2 - PEKERJAAN BONGKARAN STRUKTUR HARGA TOTAL TOTAL +/-
SAT VOLUME VOLUME +/-
SATUAN ( Rp ) ( Rp )
DAFTAR NO. 2.1. - PEKERJAAN BONGKARAN STRUKTUR

Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-2 Str1 Hal.2/390 BUILDING DAN FASILITAS PAKET 2
PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR BANGUNAN TRIBUN
PROYEK EQUESTRIAN - JAKARTA

DAFTAR NO. 3 -PEKERJAAN BONGKARAN ARSITEKTUR VOLUME HARGA SATUAN TOTAL HARGA
SAT VOLUME
+/- Rp Rp

Catatan Harga
I
Harga satuan bongkaran sudah termasuk buangan keluar site.

II
Harga satuan bongkaran sudah termasuk pembersihan area site

III
Harga satuan bongkaran dinding kaca dan ralling kaca sudah
termasuk assesoris, kelengkapan lainnya, pembersihan sebelum
dibongkar dan penyimpanan ditempat yang diinstruksikan MK atau
Owner.

IV Harga satuan bongkaran dinding gypsum/partisi sudah termasuk


bongkaran rangka.

V Harga satuan bongkaran pelapis plafond gypsum sudah termasuk


bongkaran rangka hollow dan list plafond.

VI Harga satuan bongkaran rolling door sudah termasuk assesoris dan


kelengkapan lainnya.

VII Harga satuan bongkaran pintu dan jendela sudah termasuk assesoris
dan kelengkapan lainnya.

VIII Harga satuan bongkaran facade sudah termasuk assesoris dan


kelengkapan lainnya.

3.1 PEKERJAAN BONGKARAN DINDING

Bongkaran dinding bata merah/Partisi Gypsum/Dinding Kaca, sesuai


1 lapangan dan gambar pada :

- Lantai Dasar m2 2,114.80 42,290 89,435,078


- Lantai 2 m2 2,801.02 42,290 118,455,136
- Lantai 3 m2 2,136.42 42,290 90,349,075
- Lantai 4 m2 1,469.29 42,290 62,136,274

3.2. BONGKARAN PELAPIS LANTAI


1 Bongkaran Pelapis lantai …… ukuran …..x….. ex . …. ,berikut screed,
sesuai lapangan dan gambar pada :

- Lantai Dasar m2 1,665.00 42,290 70,412,850


- Lantai 2 m2 1,369.00 42,290 57,895,010
- Lantai 3 m2 1,255.00 42,290 53,073,950
- Lantai 4 m2 1,588.00 42,290 67,156,520
- Tribune penonton m2 769.23 42,290 32,530,737

3.3. BONGKARAN PELAPIS PLAFOND

Bongkaran Pelapis Plafond …… ukuran …..x….. ex . …. ,berikut Rangka,


1 sesuai lapangan dan gambar pada :

- Lantai Dasar m2 1,665.00 42,290 70,412,850


- Lantai 2 m2 1,369.00 42,290 57,895,010
- Lantai 3 m2 1,255.00 42,290 53,073,950
- Lantai 4 m2 1,588.00 42,290 67,156,520

DAFTAR NO.3. - PEKERJAAN ARSITEK 889,982,960


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-3 Ars1 Hal.3/390 BUILING DAN FASILITAS PAKET 2
PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR BANGUNAN TRIBUN
PROYEK EQUESTRIAN - JAKARTA

DAFTAR NO. 5 - TOTAL PEKERJAAN BIONGKARAN TRIBUN HARGA SATUAN TOTAL HARGA
SAT VOLUME
Rp. Rp.

PEKERJAAN PERSIAPAN 45,455,000

PEKERJAAN STRUKTUR 215,121,073

PEKERJAAN ARSITEKTUR 889,982,960

PEKERJAAN TAMBAH KURANG -

DAFTAR No. 5 - REKAPITULASI PEKERJAAN BONGKARAN 1,150,559,032


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf.5 Total1Hal.4/390 BUILDING DAN FASILITAS PAKET 2
PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR HORSE STABLE
PROYEK EQUESTRIAN - JAKARTA

DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL


SAT VOLUME
(PRELIMINARIES) SATUAN ( Rp )

Catatan Harga ( Pricing Notes ) :

I
Kontrak ini bersifat Harga Tetap (Lump Sum Fix Price), kecuali dimana
dicantumkan Provisional atau "Provisional Sum". Kontraktor wajib
menghitung kembali volume pekerjaan dan memeriksa satuannya yang
dibuat oleh Quantity Surveyor dan jika menurut perhitungan Kontraktor
volume dan atau satuannya tidak sesuai atau terdapat item pekerjaan yang
belum tercantum, maka Kontraktor dapat merubah atau menambahkan pada
lampiran khusus yang dibuat untuk pekerjaan tambah atau kurang.

II Harga yang tercantum di dalam Pekerjaan Persiapan, Prasarana dan


Penunjang (Preliminaries) sudah mencakup keseluruhan pekerjaan termasuk
pekerjaaan tambahn kurang dan sudah diperhitungkan terhadap :
- Penambahan dan pengurangan volume pada item pekerjaan di dalam
kontrak
- Peniadaan dan penambahan bagian pekerjaan
- Perubahan kwalitas pekerjaan
- Perubahan-perubahan level, garis-garis as, posisi-posisi dan ukuran-
ukuran bagian pekerjaan
- Pekerjaan tambah kurang lainnya
- Perpanjangan waktu pelaksanaan (± 2 bulan)

III
Dalam mengajukan harga pekerjaan ini Pemborong harus sudah
mempertimbangkan untuk memasukkan semua biaya pengeluaran pekerjaan
dan tidak ada tuntutan di kemudian hari terhadap Pemberi tugas, bila daftar
uraian pekerjaan/BQ ini dipandang tidak lengkap.

IV
Semua hal yang tidak tercantum disini dianggap sudah termasuk didalam
penawaran dan semua resiko baik mengenai eskalasi harga, salah hitung
terhadap volume maupun harga yang diajukan dan kekurangan item
pekerjaan dan biaya-biaya lain yang tak terduga adalah tetap menjadi
tanggung jawab Pemborong. Karena BQ sesudah penawaran adalah BQ
Pemborong

V
Pemborong sudah harus memperhitungkan/mempertimbangkan semua
kemungkinan-kemungkinan yang terjadi di lapangan dalam pelaksanaan
berhubung adanya Pemborong-Pemborong lain unutk pelaksanaan Proyek
tersebut

576900177.xlsx Daf-1 Persiapan2 Hal.1/390 BUILDING DAN FASILITAS PAKET 2


DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL
(PRELIMINARIES) SAT VOLUME
SATUAN ( Rp )

Proyek Manajemen dan Biaya Administrasi Lapangan


1 Item 1 15,000,000 15,000,000
Pemborong harus menyediakan biaya - biaya yang dikeluarkan untuk
mengadakan tenaga teknis dan tenaga pimpinan proyek di lapangan yang
kompeten, cakap, menguasai bidang pekerjaan dengan baik dan
berpengalaman, yang akan mengelola pelaksanaan pekerjaan, semua biaya
administrasi dan biaya mengurus segala hal yang berhubungan dengan
tanggung jawabnya terhadap kontrak ini .

Peralatan dan Perlengkapan Kerja


2 Item 1 18,750,000 18,750,000
Pengadaan peralatan dan perlengkapan kerja yang lengkap untuk kelancaran
pelaksanaan pekerjaan sebagaimana yang dimaksud didalam Dokumen
Kontrak, termasuk biaya ijin pemasukan peralatan ke dalam lokasi proyek,
pemeliharaan dan pemindahan dari satu tempat ke tempat lainnya di dalam
lokasi pekerjaan serta mengeluarkannya setelah penyelesaian pekerjaan,
misalnya Tower Crane, Alimax, Scaffolding, dan lain-lain, tidak terbatas pada
alat tersebut.

Peralatan dan Perlengkapan Keselamatan Kerja serta P3K


3 Item 1 1,855,000 1,855,000
Pemborong bertanggung jawab atas pengadaan alat-alat keselamatan kerja
seperti helm, sepatu lapangan, jas hujan, sabuk pengaman, handy talky, dan
lain-lain sebanyak yang diperlukan untuk Pekerja dan Staff Pemborong, serta
terhadap pihak lain di dalam lokasi proyek (Pemberi Tugas, QS, Konsultan
Pengawas). Pengadaan pelatihan keselamatan kerja secara berkala untuk
tenaga-tenaga kerja dan pihak-pihak terkait lain, pengadaan peralatan K3 di
lapangan serta penyediaan tenaga-tenaga khusus K3 yang mencukupi selama
pelaksanaan proyek.

Rapat Proyek
4 Item 1 200,000 200,000
Pemborong harus menyediakan fasilitas yang diperlukan termasuk akomodasi
dan konsumsi (snack) untuk pelaksanaan rapat rutin di proyek dengan
Pemberi Tugas, Pimpinan Proyek, para Konsultan dan para Kontraktor paket
lain serta mengkoordinasikannya.

Pengadaan Gambar
5 Pengadaan gambar For Construction untuk pelaksanaan by Perenana, Item 1 300,000 300,000
sedangkan memperbanyak untuk keperluan kerja di lapangan termasuk 2
(dua) set untuk keperluan pengawasan.

Laporan
6 Pemborong wajib membuat Laporan Harian, Mingguan dan Bulanan, laporan
progress pekerjaan serta laporan lainnya Item 1 exclude -

Photo - Photo Kemajuan Pekerjaan


7 Item 1 350,000 350,000
Pembuatan photo berwarna atas kemajuan pekerjaan sebanyak 4 (empat) set
untuk diserahkan setiap bulan hingga masa serah terima ke-1 (pertama) serta
setiap tahap pengajuan pembayaran (penagihan) dan diserahkan kepada
Pemberi Tugas.

Kantor Konsultan dan Direksi di Lapangan


8 Pembuatan Kantor Sementara untuk Konsultan dan Konsultan lainnya di Item 1 exclude -
lapangan berikut semua fasilitas yang diperlukan seperti listrik, air, telepon,
AC, toilet, meja, kursi, filling cabinet dan perlengkapan penunjang lainnya dan
bertanggung jawab atas pemeliharaan, kebersihan dan pengadaan peralatan
atau perabotannya selama proyek berlangsung dan memindahkan ke tempat
lainnya di dalam lokasi pekerjaan apabila ada perintah membongkar setelah
pekerjaan selesai.

576900177.xlsx Daf-1 Persiapan2 Hal.2/390 BUILDING DAN FASILITAS PAKET 2


Pembuatan Kantor Sementara untuk Konsultan dan Konsultan lainnya di
lapangan berikut semua fasilitas yang diperlukan seperti listrik, air, telepon,
AC, toilet, meja, kursi, filling cabinet dan perlengkapan penunjang lainnya dan
bertanggung
DAFTAR NO. 1jawab atas pemeliharaan,
- PEKERJAAN PERSIAPAN,kebersihan
PRASARANA danDAN
pengadaan
PENUNJANGperalatan HARGA TOTAL
atau perabotannya selama proyek berlangsung dan memindahkan ke tempat
(PRELIMINARIES) SAT VOLUME
SATUAN ( Rp )
lainnya di dalam lokasi pekerjaan apabila ada perintah membongkar setelah
pekerjaan selesai.

Kantor Pemborong Lapangan


9 Kantor sementara pemborong di lapangan berikut semua fasilitas yang Item 1 exclude -
diperlukan termasuk toilet untuk para pekerja dan berikut pemeliharaan
selama pelaksanaan pekerjaan dan memindah-mindahkan dalam lokasi
pekerjaan bila ada perintah, Pemborong berkewajiban dalam pemeliharaan
kebersihan didalam lokasi pekerjaan, pembongkaran bila ada perintah
membongkar setelah pekerjaan selesai dan merapihkan bekas lokasinya.

Gudang Sementara dan Los Kerja


10 Pengadaan gudang sementara dan los pekerjaan di lapangan berikut Item 1 exclude -
pemeliharaannya dan membongkar setelah pekerjaannya selesai serta
memperbaiki, merapihkan dan membersihkannya

Pagar Sementara Proyek


11 Item 1 exclude -
Pembuatan pagar sementara proyek tidak boleh melewati batas - batas
lokasi tanah proyek (site) termasuk pemeliharaannya dan membongkar
setelah pekerjaan selesai serta memperbaiki, merapihkan dan membersihkan
kembali sesuai ketentuan lingkungan yang ditetapkan oleh Peraturan
Pemerintah Daerah, sedangkan ukuran, bentuk, spesifikasi materialnya sesuai
dengan yang ditetapkan Pemberi Tugas.

Kebersihan dan Kerapihan


12 Item 1 3,000,000 3,000,000
Pemborong harus mengangkut ke luar lokasi proyek semua sampah secara
teratur jika sudah bertumpuk dan pada waktu penyelesaian pekerjaan harus
bersih dan rapih. (Catatan : Dalam pengangkutan keluar proyek tidak boleh
mengotori jalan dan prasarana umum).

Keamanan Proyek
13 Item 1 3,000,000 3,000,000

Pemborong bertanggung jawab atas penjagaan, dan perlindungan terhadap


pekerjaan yang dianggap penting selama masa pelaksanaan kontrak siang dan
malam . Pemberi tugas tidak bertanggung jawab terhadap pemborong dan
sub Pemborong atas kehilangan, kerusakan bahan-bahan bangunan, peralatan
atau pekerjaan yang sedang dalam pelaksanaan. Pemborong wajib
menempatkan tenaga Satpam yang terlatih dan mencukupi selama 24 jam
untuk penjagaan keamanan terhadap pencurian dan oknum-oknum yang
mengganggu ketertiban termasuk kerjasama dengan satuan Polri setempat.

Listrik Kerja dan Penerangan Malam Hari


14 Item 1 3,000,000 3,000,000
Menyediakan pembangkit tenaga listrik sementara atau penerangan buatan
termasuk pemasangan kabel-kabel dan meteran yang dipergunakan untuk
keperluan kerja atau pengambilan daya dari sumber atau PLN yang sudah ada,
maka semua biaya pengadaan dan pemakaian daya selama pelaksanaan
proyek termasuk izin yang diperlukan serta perapihan setelah pekerjaan
selesai sudah harus diperhitungkan oleh pemborong termasuk penerangan
malam hari pada tempat-tempat strategis sepanjang sisi dalam proyek.

576900177.xlsx Daf-1 Persiapan2 Hal.3/390 BUILDING DAN FASILITAS PAKET 2


DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL
(PRELIMINARIES) SAT VOLUME
SATUAN ( Rp )

Pengukuran dan Bouwplank


15 Item 1 exclude -

Pemborong harus menyediakan peralatan yang diperlukan seperti alat ukur


optik, waterpass, theodlit, dll, dan juru ukur yang berpengalaman. Penentuan
letak titik-titik patok pengukuran dilapangan bersama Pemberi Tugas dan
harus dijaga dari kerusakan-kerusakan. Setiap titik patok pengukuran yang
tidak pada tempatnya lagi atau hilang harus dibuat lagi, penentuan peil-peil
pekerjaan akan diambil dari titik-titik yang teliti. Kesalahan yang timbul dalam
pengambilan ukuran dan perubahan letak atau hilangnya titik-titik patok
pengukuran menjadi tanggung jawab pemborong. Dalam hal ini pemborong
harus mengadakan pegawai sebanyak yang diperlukan untuk membantu
Pemberi Tugas untuk melaksanakan pekerjaan diatas dengan biaya
ditanggung pemborong.

Kerusakan Dan Kerugian terhadap Bangunan Lain


16 Item 1 exclude -
Semua kerusakan atau kerugian terhadap bangunan atau jaringan instalasi di
sekitarnya maupun jaringan instalasi yang sudah ada dari PLN, PAM,
Perumgas, Peumtel, PU, dsb yang berada di lokasi proyek selama waktu
pelaksanaan menjadi tanggung jawab sepenuhnya pemborong. Berikut
pemindahan jaringan-jaringan instalasi tersebut di atas juga menjadi tanggung
jawab pemborong, jika jaringan tersebut mengganggu dalam pelaksanaan
proyek, termasuk pengurusan izin-izin pada instansi yang bersangkutan.

DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG ( PRELIMINARIES ) 45,455,000


Dipindahkan ke Penjumlahan Total

576900177.xlsx Daf-1 Persiapan2 Hal.4/390 BUILDING DAN FASILITAS PAKET 2


PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR HORSE STABLE
PROYEK EQUESTRIAN - JAKARTA
DAFTAR No. 2 - PEKERJAAN BONGKARAN STRUKTUR HARGA TOTAL TOTAL +/-
SAT VOLUME VOLUME +/-
SATUAN ( Rp ) ( Rp )
DAFTAR NO. 2.1. - PEKERJAAN BONGKARAN STRUKTUR

2.1. Catatan Harga

I Harga satuan bongkaran beton sudah termasuk buangan


keluar site

II Harga satuan bongkaran beton sudah termasuk pembersihan


area site

III Harga Bongkaran Kolom sudah termasuk beton dan besi.

IV Harga Bongkaran Shear Wall sudah termasuk beton dan besi


serta peralatan yang akan digunakan.

V Harga satuan bongkaran plat Lantai sudah termasuk


bongkaran bondek, beton dan besi serta peralatan yang
akan digunakan.

X Harga satuan bongkaran balok baja canopy sudah termasuk


baut-baut, assesoris dan kelengkapan lainnya..

PEKERJAAN BONGKARAN BETON

1 Bongkaran Kolom, pada : (Reff : Gbr. )


- Denah Kolom Elevasi +8.36 m3 1,068,400 - -

2 Bongkaran Plat inc Screed dan finishing lantai diatasnya, tebal = 15cm, pada : (Reff : Gbr.)
- Denah Pelat Elevasi +4.36 m2 194,768 - -
- Denah Pelat Elevasi +8.36 m2 194,768 - -
- Denah Pelat Elevasi +12.36 m2 194,768 - -

3 Bongkaran Balok, pada : (Reff : Gbr.)


- Denah Balok Elevasi +4.36 m3 1,068,400 - -
- Denah Balok Elevasi +8.36 m3 1,068,400 - -
- Denah Balok Elevasi +12.36 m3 1,068,400 - -

4 Bongkaran Tangga (Plat Miring, Balok Bordes, Plat Bordes, dan Trap tangga), tinggi trap = 17cm pada : (Reff : )
- Denah Balok Elevasi +4.36 m2 194,768 - -
- Denah Balok Elevasi +8.36 m2 194,768 - -

5 Bongkaran Core Lift, pada : (Reff : Gbr.)


- Denah Balok Elevasi +4.36 m3 1,068,400 - -
- Denah Balok Elevasi +8.36 m3 1,068,400 - -
- Denah Balok Elevasi +12.36 m3 1,068,400 - -

DAFTAR NO. 2. - PEKERJAAN STRUKTUR - -


Dipindahkan ke Penjumlahan Total

576900177.xlsx Daf-2 Str2 Hal.1/390 BUILDING DAN FASILITAS PAKET 2


PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR HORSE STABLE
PROYEK EQUESTRIAN - JAKARTA
DAFTAR NO. 3 -PEKERJAAN BONGKARAN ARSITEKTUR HARGA SATUAN TOTAL HARGA
SAT VOLUME VOLUME +/-
Rp Rp
DAFTAR NO. 3.1. - PEKERJAAN BONGKARAN ARSITEKTUR

Catatan Harga
I
Harga satuan bongkaran sudah termasuk buangan keluar site.

II
Harga satuan bongkaran sudah termasuk pembersihan area site

III
Harga satuan bongkaran dinding kaca dan ralling kaca sudah
termasuk assesoris, kelengkapan lainnya, pembersihan sebelum
dibongkar dan penyimpanan ditempat yang diinstruksikan MK atau
Owner.

IV Harga satuan bongkaran dinding gypsum/partisi sudah termasuk


bongkaran rangka.

V Harga satuan bongkaran pelapis plafond gypsum sudah termasuk


bongkaran rangka hollow dan list plafond.

VI Harga satuan bongkaran rolling door sudah termasuk assesoris dan


kelengkapan lainnya.

VII Harga satuan bongkaran pintu dan jendela sudah termasuk assesoris
dan kelengkapan lainnya.

VIII Harga satuan bongkaran facade sudah termasuk assesoris dan


kelengkapan lainnya.

1 Bongkaran dinding bata merah, sesuai lapangan dan gambar pada :

- Lantai Dasar
Farrier m2 274.25 42,292 11,598,683
Horstable blok A,B,C,D m2 1,828.68 42,292 77,339,216

- Lantai 2
Horstable blok A,B,C,D m2 2,016.44 42,292 85,280,031

3.2. BONGKARAN PELAPIS LANTAI


1 Bongkaran Pelapis lantai screed, sesuai lapangan dan gambar pada :

- Lantai 1 m2 2,554.39 42,292 108,031,255


- Lantai 2 m2 2,000.81 42,292 84,619,002

3.3. BONGKARAN ATAP

Bongkaran Pelapis atap UPVC, berikut Rangka, sesuai lapangan dan


1 gambar pada :

- Lantai Atap m2 2,694.24 42,292 113,945,615


- Atap monitor m2 246.00 42,292 10,403,924

DAFTAR NO.3. - PEKERJAAN BONGKARAN ARSITEK 491,217,726


Dipindahkan ke Penjumlahan Total

PEGADAIAN MAKASSAR Daf-3 Ars2 Hal.2/390 BUILDING DAN FASILITAS PAKET 2


PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR HORSE STABLE
PROYEK EQUESTRIAN - JAKARTA
DAFTAR NO. 5 - TOTAL PEKERJAAN BIONGKARAN TRIBUN HARGA SATUAN TOTAL HARGA
SAT VOLUME
Rp. Rp.

PEKERJAAN PERSIAPAN 45,455,000

PEKERJAAN STRUKTUR -

PEKERJAAN ARSITEKTUR 491,217,726

PEKERJAAN TAMBAH KURANG -

DAFTAR No. 5 - PEKERJAAN BONGKARAN HORSE STABLE 536,672,726


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK BUILDING DAN FASILITAS PAKET 2


PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR BANGUNAN COVERED TRAINING AREA
PROYEK EQUESTRIAN - JAKARTA

DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL


SAT VOLUME
(PRELIMINARIES) SATUAN ( Rp )

Catatan Harga ( Pricing Notes ) :

I
Kontrak ini bersifat Harga Tetap (Lump Sum Fix Price), kecuali dimana
dicantumkan Provisional atau "Provisional Sum". Kontraktor wajib
menghitung kembali volume pekerjaan dan memeriksa satuannya yang dibuat
oleh Quantity Surveyor dan jika menurut perhitungan Kontraktor volume dan
atau satuannya tidak sesuai atau terdapat item pekerjaan yang belum
tercantum, maka Kontraktor dapat merubah atau menambahkan pada
lampiran khusus yang dibuat untuk pekerjaan tambah atau kurang.

II Harga yang tercantum di dalam Pekerjaan Persiapan, Prasarana dan


Penunjang (Preliminaries) sudah mencakup keseluruhan pekerjaan termasuk
pekerjaaan tambahn kurang dan sudah diperhitungkan terhadap :
- Penambahan dan pengurangan volume pada item pekerjaan di dalam
kontrak
- Peniadaan dan penambahan bagian pekerjaan
- Perubahan kwalitas pekerjaan
- Perubahan-perubahan level, garis-garis as, posisi-posisi dan ukuran-
ukuran bagian pekerjaan
- Pekerjaan tambah kurang lainnya
- Perpanjangan waktu pelaksanaan (± 2 bulan)

III
Dalam mengajukan harga pekerjaan ini Pemborong harus sudah
mempertimbangkan untuk memasukkan semua biaya pengeluaran pekerjaan
dan tidak ada tuntutan di kemudian hari terhadap Pemberi tugas, bila daftar
uraian pekerjaan/BQ ini dipandang tidak lengkap.

IV
Semua hal yang tidak tercantum disini dianggap sudah termasuk didalam
penawaran dan semua resiko baik mengenai eskalasi harga, salah hitung
terhadap volume maupun harga yang diajukan dan kekurangan item pekerjaan
dan biaya-biaya lain yang tak terduga adalah tetap menjadi tanggung jawab
Pemborong. Karena BQ sesudah penawaran adalah BQ Pemborong

V
Pemborong sudah harus memperhitungkan/mempertimbangkan semua
kemungkinan-kemungkinan yang terjadi di lapangan dalam pelaksanaan
berhubung adanya Pemborong-Pemborong lain unutk pelaksanaan Proyek
tersebut

576900177.xlsx Daf-1 Persiapan3 Hal.1/390 BUILDING DAN FASILITAS PAKET 2


DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL
SAT VOLUME
(PRELIMINARIES) SATUAN ( Rp )

Proyek Manajemen dan Biaya Administrasi Lapangan


1 Item 1 15,000,000 15,000,000
Pemborong harus menyediakan biaya - biaya yang dikeluarkan untuk
mengadakan tenaga teknis dan tenaga pimpinan proyek di lapangan yang
kompeten, cakap, menguasai bidang pekerjaan dengan baik dan
berpengalaman, yang akan mengelola pelaksanaan pekerjaan, semua biaya
administrasi dan biaya mengurus segala hal yang berhubungan dengan
tanggung jawabnya terhadap kontrak ini .

Peralatan dan Perlengkapan Kerja


2 Item 1 18,750,000 18,750,000
Pengadaan peralatan dan perlengkapan kerja yang lengkap untuk kelancaran
pelaksanaan pekerjaan sebagaimana yang dimaksud didalam Dokumen
Kontrak, termasuk biaya ijin pemasukan peralatan ke dalam lokasi proyek,
pemeliharaan dan pemindahan dari satu tempat ke tempat lainnya di dalam
lokasi pekerjaan serta mengeluarkannya setelah penyelesaian pekerjaan,
misalnya Tower Crane, Alimax, Scaffolding, dan lain-lain, tidak terbatas pada
alat tersebut.

Peralatan dan Perlengkapan Keselamatan Kerja serta P3K


3 Item 1 1,855,000 1,855,000
Pemborong bertanggung jawab atas pengadaan alat-alat keselamatan kerja
seperti helm, sepatu lapangan, jas hujan, sabuk pengaman, handy talky, dan
lain-lain sebanyak yang diperlukan untuk Pekerja dan Staff Pemborong, serta
terhadap pihak lain di dalam lokasi proyek (Pemberi Tugas, QS, Konsultan
Pengawas). Pengadaan pelatihan keselamatan kerja secara berkala untuk
tenaga-tenaga kerja dan pihak-pihak terkait lain, pengadaan peralatan K3 di
lapangan serta penyediaan tenaga-tenaga khusus K3 yang mencukupi selama
pelaksanaan proyek.

Rapat Proyek
4 Item 1 200,000 200,000
Pemborong harus menyediakan fasilitas yang diperlukan termasuk akomodasi
dan konsumsi (snack) untuk pelaksanaan rapat rutin di proyek dengan Pemberi
Tugas, Pimpinan Proyek, para Konsultan dan para Kontraktor paket lain serta
mengkoordinasikannya.

Pengadaan Gambar
5 Pengadaan gambar For Construction untuk pelaksanaan by Perenana, Item 1 300,000 300,000
sedangkan memperbanyak untuk keperluan kerja di lapangan termasuk 2 (dua)
set untuk keperluan pengawasan.

Laporan
6 Pemborong wajib membuat Laporan Harian, Mingguan dan Bulanan, laporan
Item 1 exclude -
progress pekerjaan serta laporan lainnya

Photo - Photo Kemajuan Pekerjaan


7 Item 1 350,000 350,000
Pembuatan photo berwarna atas kemajuan pekerjaan sebanyak 4 (empat) set
untuk diserahkan setiap bulan hingga masa serah terima ke-1 (pertama) serta
setiap tahap pengajuan pembayaran (penagihan) dan diserahkan kepada
Pemberi Tugas.

Kantor Konsultan dan Direksi di Lapangan


8 Pembuatan Kantor Sementara untuk Konsultan dan Konsultan lainnya di Item 1 exclude -
lapangan berikut semua fasilitas yang diperlukan seperti listrik, air, telepon, AC,
toilet, meja, kursi, filling cabinet dan perlengkapan penunjang lainnya dan
bertanggung jawab atas pemeliharaan, kebersihan dan pengadaan peralatan
atau perabotannya selama proyek berlangsung dan memindahkan ke tempat
lainnya di dalam lokasi pekerjaan apabila ada perintah membongkar setelah
pekerjaan selesai.

Kantor Pemborong Lapangan


9 Kantor sementara pemborong di lapangan berikut semua fasilitas yang Item 1 exclude -
diperlukan termasuk toilet untuk para pekerja dan berikut pemeliharaan
selama pelaksanaan pekerjaan dan memindah-mindahkan dalam lokasi
pekerjaan bila ada perintah, Pemborong berkewajiban dalam pemeliharaan
kebersihan didalam lokasi pekerjaan, pembongkaran bila ada perintah
membongkar setelah pekerjaan selesai dan merapihkan bekas lokasinya.

576900177.xlsx Daf-1 Persiapan3 Hal.2/390 BUILDING DAN FASILITAS PAKET 2


DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL
SAT VOLUME
(PRELIMINARIES) SATUAN ( Rp )

Gudang Sementara dan Los Kerja


10 Pengadaan gudang sementara dan los pekerjaan di lapangan berikut Item 1 exclude -
pemeliharaannya dan membongkar setelah pekerjaannya selesai serta
memperbaiki, merapihkan dan membersihkannya

Pagar Sementara Proyek


11 Item 1 exclude -
Pembuatan pagar sementara proyek tidak boleh melewati batas - batas lokasi
tanah proyek (site) termasuk pemeliharaannya dan membongkar setelah
pekerjaan selesai serta memperbaiki, merapihkan dan membersihkan kembali
sesuai ketentuan lingkungan yang ditetapkan oleh Peraturan Pemerintah
Daerah, sedangkan ukuran, bentuk, spesifikasi materialnya sesuai dengan yang
ditetapkan Pemberi Tugas.

Kebersihan dan Kerapihan


12 Item 1 3,000,000 3,000,000
Pemborong harus mengangkut ke luar lokasi proyek semua sampah secara
teratur jika sudah bertumpuk dan pada waktu penyelesaian pekerjaan harus
bersih dan rapih. (Catatan : Dalam pengangkutan keluar proyek tidak boleh
mengotori jalan dan prasarana umum).

Keamanan Proyek
13 Item 1 3,000,000 3,000,000

Pemborong bertanggung jawab atas penjagaan, dan perlindungan terhadap


pekerjaan yang dianggap penting selama masa pelaksanaan kontrak siang dan
malam . Pemberi tugas tidak bertanggung jawab terhadap pemborong dan sub
Pemborong atas kehilangan, kerusakan bahan-bahan bangunan, peralatan atau
pekerjaan yang sedang dalam pelaksanaan. Pemborong wajib menempatkan
tenaga Satpam yang terlatih dan mencukupi selama 24 jam untuk penjagaan
keamanan terhadap pencurian dan oknum-oknum yang mengganggu
ketertiban termasuk kerjasama dengan satuan Polri setempat.

Listrik Kerja dan Penerangan Malam Hari


14 Item 1 3,000,000 3,000,000
Menyediakan pembangkit tenaga listrik sementara atau penerangan buatan
termasuk pemasangan kabel-kabel dan meteran yang dipergunakan untuk
keperluan kerja atau pengambilan daya dari sumber atau PLN yang sudah ada,
maka semua biaya pengadaan dan pemakaian daya selama pelaksanaan proyek
termasuk izin yang diperlukan serta perapihan setelah pekerjaan selesai sudah
harus diperhitungkan oleh pemborong termasuk penerangan malam hari pada
tempat-tempat strategis sepanjang sisi dalam proyek.

Pengukuran dan Bouwplank


15 Item 1 exclude -

Pemborong harus menyediakan peralatan yang diperlukan seperti alat ukur


optik, waterpass, theodlit, dll, dan juru ukur yang berpengalaman. Penentuan
letak titik-titik patok pengukuran dilapangan bersama Pemberi Tugas dan harus
dijaga dari kerusakan-kerusakan. Setiap titik patok pengukuran yang tidak
pada tempatnya lagi atau hilang harus dibuat lagi, penentuan peil-peil
pekerjaan akan diambil dari titik-titik yang teliti. Kesalahan yang timbul dalam
pengambilan ukuran dan perubahan letak atau hilangnya titik-titik patok
pengukuran menjadi tanggung jawab pemborong. Dalam hal ini pemborong
harus mengadakan pegawai sebanyak yang diperlukan untuk membantu
Pemberi Tugas untuk melaksanakan pekerjaan diatas dengan biaya ditanggung
pemborong.

Kerusakan Dan Kerugian terhadap Bangunan Lain


16 Item 1 exclude -
Semua kerusakan atau kerugian terhadap bangunan atau jaringan instalasi di
sekitarnya maupun jaringan instalasi yang sudah ada dari PLN, PAM, Perumgas,
Peumtel, PU, dsb yang berada di lokasi proyek selama waktu pelaksanaan
menjadi tanggung jawab sepenuhnya pemborong. Berikut pemindahan
jaringan-jaringan instalasi tersebut di atas juga menjadi tanggung jawab
pemborong, jika jaringan tersebut mengganggu dalam pelaksanaan proyek,
termasuk pengurusan izin-izin pada instansi yang bersangkutan.

576900177.xlsx Daf-1 Persiapan3 Hal.3/390 BUILDING DAN FASILITAS PAKET 2


DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG HARGA TOTAL
SAT VOLUME
(PRELIMINARIES) SATUAN ( Rp )

DAFTAR NO. 1 - PEKERJAAN PERSIAPAN, PRASARANA DAN PENUNJANG ( PRELIMINARIES ) 45,455,000


Dipindahkan ke Penjumlahan Total

576900177.xlsx Daf-1 Persiapan3 Hal.4/390 BUILDING DAN FASILITAS PAKET 2


PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR BANGUNAN COVERED TRAINING AREA
PROYEK EQUESTRIAN - JAKARTA

DAFTAR No. 2 - PEKERJAAN BONGKARAN STRUKTUR HARGA TOTAL


SAT VOLUME VOLUME +/-
SATUAN ( Rp )
DAFTAR NO. 2.1. - PEKERJAAN BONGKARAN STRUKTUR

2.1. Catatan Harga

I Harga satuan bongkaran beton sudah termasuk buangan


keluar site

II Harga satuan bongkaran beton sudah termasuk pembersihan


area site

III Harga Bongkaran Kolom sudah termasuk beton dan besi.

IV Harga Bongkaran Shear Wall sudah termasuk beton dan besi


serta peralatan yang akan digunakan.

V Harga satuan bongkaran plat Lantai sudah termasuk


bongkaran bondek, beton dan besi serta peralatan yang
akan digunakan.

X Harga satuan bongkaran balok baja canopy sudah termasuk


baut-baut, assesoris dan kelengkapan lainnya..

PEKERJAAN BONGKARAN BETON

Bongkaran kolom, Rafter Baja dan atap Metal, sesuai 194,768


1 m2 3,518.32 685,254,406
lapangana :
lapangan pada bangunan existing Covered Training area

DAFTAR NO. 2. - PEKERJAAN STRUKTUR 685,254,406

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-2 Str3 Hal.1/390 BUILDING DAN FASILITAS PAKET 2
DAFTAR No. 2 - PEKERJAAN BONGKARAN STRUKTUR HARGA TOTAL
SAT VOLUME VOLUME +/-
SATUAN ( Rp )
DAFTAR NO. 2.1. - PEKERJAAN BONGKARAN STRUKTUR

Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-2 Str3 Hal.2/390 BUILDING DAN FASILITAS PAKET 2
PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR BANGUNAN COVERED TRAINING AREA
PROYEK EQUESTRIAN - JAKARTA

DAFTAR NO. 4 - TOTAL PEKERJAAN BIONGKARAN TRIBUN HARGA SATUAN TOTAL HARGA
SAT VOLUME
Rp. Rp.

PEKERJAAN PERSIAPAN 45,455,000

PEKERJAAN STRUKTUR 685,254,406

PEKERJAAN TAMBAH KURANG -

DAFTAR No. 4 - PEKERJAAN BONGKARAN COVERED TRAINING ARENA 730,709,406


Dipindahkan ke Penjumlahan Total

JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf.4 Total3Hal.3/390 BUILDING DAN FASILITAS PAKET 2
REKAPITULASI PENJUMLAHAN TOTAL
PAKET PEKERJAAN BUILDING & FASILITAS ( SAP, ME, LANDSCAPE & INTERIOR) PAKET 2
PROYEK JAKARTA INTERNATIONAL EQUESTRIAN PARK PAKET II

NO URAIAN PEKERJAAN TOTAL BASIC TOTAL ± TOTAL BASIC + TOTAL ±

I DAF - I PEKERJAAN PERSIAPAN Rp 11,647,333,691 Rp 11,647,333,691

II DAF - II BANGUNAN SPECTATOR TRIBUNE Rp 78,737,250,765


II.1 PEKERJAAN STRUKTUR Rp 27,506,278,324
II.1.1 PEKERJAAN PONDASI Rp 1,902,880,498 -
II.1.2 PEKERJAAN TANAH Rp 136,313,053 -
II.1.3 PEKERJAAN STRUKTUR BETON Rp 4,476,038,921 (13,413,845)
II.1.4 PEKERJAAN STRUKTUR BAJA Rp 21,004,459,698 -
II.2 PEKERJAAN ARSITEKTUR Rp 26,640,818,373
II.2.1 PEKERJAAN DINDING Rp 1,855,203,863 (1,185,713)
II.2.2 PEKERJAAN PINTU DAN JENDELA Rp 1,183,302,306 (54,588,708)
II.2.3 PEKERJAAN LANTAI Rp 381,047,859 41,423,819
II.2.4 PEKERJAAN PLAPOND Rp 457,817,424 21,530,514
II.2.5 PEKERJAAN SANITARY Rp by Interior
II.2.6 PEKERJAAN LAIN-LAIN Rp 1,093,761,269 (58,279,214)
II.2.7 PEKERJAAN ATAP TRIBUN Rp 13,837,938,645 330,673,744
II.2.8 PEKERJAAN FAÇADE Rp 6,639,452,519 912,720,046
II.3 PEKERJAAN MEKANIKAL - ELEKTRIKAL Rp 17,004,423,869
II.3.1 PEKERJAAN PLUMBING Rp 185,768,200
II.3.2 PEKERJAAN PEMADAM KEBAKARAN Rp 1,291,404,030
II.3.3 PEKERJAAN TATA UDARA Rp 4,450,888,600
II.3.4 PEKERJAAN ELEKTRIKAL Rp 1,923,712,200
II.3.5 PEKERJAAN ELEKTRONIK
II.3.5.1 FIRE ALARM Rp 314,771,383
II.3.5.2 TATA SUARA Rp 336,524,800
II.3.5.3 TELEPON Rp 506,660,733
II.3.5.4 CCTV Rp 331,950,000
II.3.5.5 DATA Rp 2,525,804,633
II.3.5.6 MATV Rp 159,680,000
II.3.5.7 ACCESS CONTROL Rp 251,534,583
II.3.5.8 LIFT Rp 4,725,724,706
II.4 PEKERJAAN INTERIOR Rp 7,585,730,199
II.4.1 PEKERJAAN DINDING Rp 339,016,464 (5,504,630)
II.4.2 PEKERJAAN PINTU DAN JENDELA Rp 307,845,372 (17,038,261)
II.4.3 PEKERJAAN LANTAI Rp 3,197,376,090 (414,327,276)
II.4.4 PEKERJAAN PLAPOND Rp 1,055,639,965 (199,532,524)
II.4.5 PEKERJAAN SANITARY Rp 521,005,020 1,542,800
II.4.6 PEKERJAAN FIX FURNITURE Rp Incl. loose furniture
II.4.7 PEKERJAAN LOOSE FURNITURE Rp 2,826,125,248 (26,418,068)

III DAF - III BANGUNAN HORSE STABLE & CHANGING ROOM Rp 22,187,227,799
III.1.A PEKERJAAN STRUKTUR HORSE STABLE Rp 3,698,693,468
III.1.A.1 PEKERJAAN PONDASI Rp Tidak ada -
III.1.A.2 PEKERJAAN TANAH Rp 92,581,628 2,164,276
III.1.A.3 PEKERJAAN STRUKTUR BETON Rp 2,190,804,100 156,080,089
III.1.A.4 PEKERJAAN STRUKTUR BAJA Rp 1,257,063,375 -
III.1.B PEKERJAAN STRUKTUR CHANGING ROOM Rp 605,944,301
III.1.B.1 PEKERJAAN TANAH Rp 37,896,707 (2,485,211)
III.1.B.2 PEKERJAAN STRUKTUR BETON Rp 273,297,958 (2,485,211)
III.1.B.3 PEKERJAAN STRUKTUR BAJA Rp 302,205,268 (2,485,211)
III.2.A PEKERJAAN ARSITEKTUR HORSE STABLE Rp 11,410,258,065
III.2.A.1 PEKERJAAN DINDING Rp 1,450,292,318 (47,123,833)
III.2.A.2 PEKERJAAN PINTU DAN JENDELA Rp 1,437,384,943 485,732,459
III.2.A.3 PEKERJAAN LANTAI Rp 2,499,255,342 525,617,670
III.2.A.4 PEKERJAAN PLAPOND Rp 462,655,730 96,255,469
III.2.A.5 PEKERJAAN SANITARY Rp 172,198,600 (52,029,540)
III.2.A.6 PEKERJAAN LAIN-LAIN Rp 902,165,107 14,452,885
III.2.A.7 PEKERJAAN ATAP Rp 1,497,283,538 1,175,384,829
III.2.A.8 PEKERJAAN FAÇADE Rp 782,872,956 7,859,592
III.2.B PEKERJAAN ARSITEKTUR CHANGING ROOM Rp 589,762,830
III.2.B.1 PEKERJAAN DINDING Rp Include horsestable
III.2.B.2 PEKERJAAN PINTU DAN JENDELA Rp Include horsestable
III.2.B.3 PEKERJAAN LANTAI Rp 33,674,061 -
III.2.B.4 PEKERJAAN PLAPOND Rp 9,837,200 -
III.2.B.5 PEKERJAAN SANITARY Rp by Interior
III.2.B.6 PEKERJAAN LAIN-LAIN Rp 175,115,232 -
III.2.B.7 PEKERJAAN ATAP Rp 212,542,544 21,500,062
III.2.B.8 PEKERJAAN FAÇADE Rp 71,240,161 65,853,571
III.3.A PEKERJAAN MEKANIKAL - ELEKTRIKAL HORSE STABLE Rp 3,093,137,017
III.3.A.1 PEKERJAAN PLUMBING Rp 243,789,800
III.3.A.2 PEKERJAAN PEMADAM KEBAKARAN Rp 7,823,200
III.3.A.3 PEKERJAAN TATA UDARA Rp 684,014,400
III.3.A.4 PEKERJAAN ELEKTRIKAL Rp 755,050,100
III.3.A.5 PEKERJAAN ELEKTRONIK
III.3.A.5.1 FIRE ALARM Rp Tidak ada
III.3.A.5.2 TATA SUARA Rp 2,204,200
III.3.A.5.3 TELEPON Rp 2,670,900
III.3.A.5.4 CCTV Rp 1,377,019,550
III.3.A.5.5 DATA Rp 19,229,267
III.3.A.5.6 MATV Rp Tidak ada
III.3.A.5.7 ACCESS CONTROL Rp 1,335,600
III.3.B PEKERJAAN MEKANIKAL - ELEKTRIKAL CHANGING ROOM Rp 1,445,492,367
III.3.B.1 PEKERJAAN PLUMBING Rp 60,865,600
III.3.B.2 PEKERJAAN PEMADAM KEBAKARAN Rp 2,235,200
III.3.B.3 PEKERJAAN TATA UDARA Rp 1,071,807,500
III.3.B.4 PEKERJAAN ELEKTRIKAL Rp 184,504,200
III.3.B.5 PEKERJAAN ELEKTRONIK
III.3.B.5.1 FIRE ALARM Rp 46,231,300
III.3.B.5.2 TATA SUARA Rp 5,567,000
III.3.B.5.3 TELEPON Rp 5,961,600

JAKARTA INTERNATIONAL EQUESTRIAN PARK SAMEP


REKAPITULASI PENJUMLAHAN TOTAL
PAKET PEKERJAAN BUILDING & FASILITAS ( SAP, ME, LANDSCAPE & INTERIOR) PAKET 2
PROYEK JAKARTA INTERNATIONAL EQUESTRIAN PARK PAKET II

NO URAIAN PEKERJAAN TOTAL BASIC TOTAL ± TOTAL BASIC + TOTAL ±

III.3.B.5.4 CCTV Rp 17,664,300


III.3.B.5.5 DATA Rp 50,655,667
III.3.B.5.6 MATV Rp Tidak ada
III.3.B.5.7 ACCESS CONTROL Rp Tidak ada
III.4 PEKERJAAN INTERIOR CHANGING ROOM Rp 1,343,939,750
III.4.1 PEKERJAAN DINDING Rp 308,858,223 -
III.4.2 PEKERJAAN PINTU DAN JENDELA Rp Incl. Arsitektur
III.4.3 PEKERJAAN LANTAI Rp 350,576,055 -
III.4.4 PEKERJAAN PLAPOND Rp 104,926,834 -
III.4.5 PEKERJAAN SANITARY Rp 132,120,920 -
III.4.6 PEKERJAAN FIX FURNITURE Rp 22,069,941 -
III.4.7 PEKERJAAN LOOSE FURNITURE Rp 425,387,777 -

IV DAF - IV BANGUNAN EQUINE CLINIC Rp 1,985,150,635


IV.1 PEKERJAAN STRUKTUR Rp 695,122,049
IV.1.1 PEKERJAAN TANAH Rp 51,058,787 -
IV.1.2 PEKERJAAN STRUKTUR BETON Rp 368,610,109 (11,587,987)
IV.1.3 PEKERJAAN STRUKTUR BAJA Rp 287,041,140 -
IV.2 PEKERJAAN ARSITEKTUR Rp 770,504,585
IV.2.1 PEKERJAAN DINDING Rp 102,605,980 (246,061)
IV.2.2 PEKERJAAN PINTU DAN JENDELA Rp 209,973,890 (15,854,075)
IV.2.3 PEKERJAAN LANTAI Rp 68,569,878 923,643
IV.2.4 PEKERJAAN PLAPOND Rp 44,668,468 670,356
IV.2.5 PEKERJAAN SANITARY Rp by Interior
IV.2.6 PEKERJAAN LAIN-LAIN Rp 74,824,611 -
IV.2.7 PEKERJAAN ATAP CANOPY Rp 133,793,923 (1,117,674)
IV.2.8 PEKERJAAN FAÇADE Rp 135,025,060 16,666,585
IV.3 PEKERJAAN MEKANIKAL - ELEKTRIKAL Rp 394,086,517
IV.3.1 PEKERJAAN PLUMBING Rp 46,572,300
IV.3.2 PEKERJAAN PEMADAM KEBAKARAN Rp 1,117,600
IV.3.3 PEKERJAAN TATA UDARA Rp 218,530,900
IV.3.4 PEKERJAAN ELEKTRIKAL Rp 82,655,450
IV.3.5 PEKERJAAN ELEKTRONIK
IV.3.5.1 FIRE ALARM Rp Tidak ada
IV.3.5.2 TATA SUARA Rp 1,016,800
IV.3.5.3 TELEPON Rp 2,218,033
IV.3.5.4 CCTV Rp 21,957,300
IV.3.5.5 DATA Rp 18,319,133
IV.3.5.6 MATV Rp 1,699,000
IV.3.5.7 ACCESS CONTROL Rp Tidak ada
IV.4 PEKERJAAN INTERIOR Rp 125,437,485
IV.4.1 PEKERJAAN DINDING Rp 31,313,275 (501,817)
IV.4.2 PEKERJAAN PINTU DAN JENDELA Rp Incl. Arsitektur
IV.4.3 PEKERJAAN LANTAI Rp 16,210,751 114,598
IV.4.4 PEKERJAAN PLAPOND Rp 5,535,108 46,106
IV.4.5 PEKERJAAN SANITARY Rp 26,960,890 -
IV.4.6 PEKERJAAN FIX FURNITURE Rp 8,982,190 -
IV.4.7 PEKERJAAN LOOSE FURNITURE Rp 36,776,384 -

V DAF - V BANGUNAN GROOM DORMITORY Rp 31,055,483,048


V.1 PEKERJAAN STRUKTUR Rp 4,482,866,910
V.1.1 PEKERJAAN PONDASI Rp 495,766,771 -
V.1.2 PEKERJAAN TANAH Rp 67,484,713 6,090,985
V.1.3 PEKERJAAN STRUKTUR BETON Rp 3,511,752,041 366,737,441
V.1.4 PEKERJAAN STRUKTUR BAJA Rp 35,034,959 -
V.2 PEKERJAAN ARSITEKTUR Rp 5,457,297,744
V.2.1 PEKERJAAN DINDING Rp 1,321,526,231 190,235,389
V.2.2 PEKERJAAN PINTU DAN JENDELA Rp 3,405,103,437 (368,623,935)
V.2.3 PEKERJAAN LANTAI Rp by Interior
V.2.4 PEKERJAAN PLAPOND Rp by Interior
V.2.5 PEKERJAAN SANITARY Rp by Interior
V.2.6 PEKERJAAN LAIN-LAIN Rp 495,667,960 13,053,288
V.2.7 PEKERJAAN ATAP CANOPY Rp 6,721,463 9,093,745
V.2.8 PEKERJAAN FAÇADE Rp 300,749,126 83,771,041
V.3 PEKERJAAN MEKANIKAL - ELEKTRIKAL Rp 11,864,780,113
V.3.1 PEKERJAAN PLUMBING Rp 672,507,400
V.3.2 PEKERJAAN PEMADAM KEBAKARAN Rp 300,793,400
V.3.3 PEKERJAAN TATA UDARA Rp 1,247,614,800
V.3.4 PEKERJAAN ELEKTRIKAL Rp 1,954,623,680
V.3.5 PEKERJAAN ELEKTRONIK
V.3.6 V.3.5.1 FIRE ALARM Rp 324,346,467
V.3.5.2 TATA SUARA Rp 165,832,100
V.3.5.3 TELEPON Rp 301,909,067
V.3.5.4 CCTV Rp 219,047,600
V.3.5.5 DATA Rp 4,343,340,033
V.3.5.6 MATV Rp 394,107,200
V.3.5.7 ACCESS CONTROL Rp 218,889,567
V.3.6 PEKERJAAN LIFT 1,721,768,800
V.4 PEKERJAAN INTERIOR Rp 9,250,538,281
V.4.1 PEKERJAAN DINDING Rp 1,174,934,679 25,801,205
V.4.2 PEKERJAAN PINTU DAN JENDELA Rp Incl.Arsitektur
V.4.3 PEKERJAAN LANTAI Rp 3,180,103,761 (539,366,720)
V.4.4 PEKERJAAN PLAPOND Rp 560,365,516 (50,612,463)
V.4.5 PEKERJAAN SANITARY Rp 1,269,719,300 305,680
V.4.6 PEKERJAAN FIX FURNITURE Rp 1,642,581,314 -
V.4.7 PEKERJAAN LOOSE FURNITURE Rp 1,987,908,002 (1,201,994)

VI DAF - VI BANGUNAN STORAGE Rp 9,219,337,012


VI.1 PEKERJAAN STRUKTUR Rp 1,664,173,630
VI.1.1 PEKERJAAN PONDASI Rp 193,765,843 -
VI.1.2 PEKERJAAN TANAH Rp 40,365,953 (3,255,069)
VI.1.3 PEKERJAAN STRUKTUR BETON Rp 1,033,560,341 (60,026,205)

JAKARTA INTERNATIONAL EQUESTRIAN PARK SAMEP


REKAPITULASI PENJUMLAHAN TOTAL
PAKET PEKERJAAN BUILDING & FASILITAS ( SAP, ME, LANDSCAPE & INTERIOR) PAKET 2
PROYEK JAKARTA INTERNATIONAL EQUESTRIAN PARK PAKET II

NO URAIAN PEKERJAAN TOTAL BASIC TOTAL ± TOTAL BASIC + TOTAL ±

VI.1.4 PEKERJAAN STRUKTUR BAJA Rp 459,762,768 -

JAKARTA INTERNATIONAL EQUESTRIAN PARK SAMEP


REKAPITULASI PENJUMLAHAN TOTAL
PAKET PEKERJAAN BUILDING & FASILITAS ( SAP, ME, LANDSCAPE & INTERIOR) PAKET 2
PROYEK JAKARTA INTERNATIONAL EQUESTRIAN PARK PAKET II

NO URAIAN PEKERJAAN TOTAL BASIC TOTAL ± TOTAL BASIC + TOTAL ±

VI.2 PEKERJAAN ARSITEKTUR Rp 610,578,682


VI.2.1 PEKERJAAN DINDING Rp 243,101,500 1,633,400
VI.2.2 PEKERJAAN PINTU DAN JENDELA Rp 343,789,760 (343,789,760)
VI.2.3 PEKERJAAN LANTAI Rp 29,557,830 285,685
VI.2.4 PEKERJAAN PLAPOND Rp 38,365,723 292,622
VI.2.5 PEKERJAAN SANITARY Rp Tidak ada
VI.2.6 PEKERJAAN LAIN-LAIN Rp 2,609,766 -
VI.2.7 PEKERJAAN ATAP Rp 279,060,877 1,350,740
VI.2.8 PEKERJAAN FAÇADE Rp 14,320,539 -
VI.3 PEKERJAAN MEKANIKAL - ELEKTRIKAL Rp 6,944,584,700
VI.3.1 PEKERJAAN PLUMBING Rp 6,621,000
VI.3.2 PEKERJAAN PEMADAM KEBAKARAN Rp 16,761,800
VI.3.3 PEKERJAAN TATA UDARA Rp 131,264,400
VI.3.4 PEKERJAAN ELEKTRIKAL Rp 6,758,475,300
VI.3.5 PEKERJAAN ELEKTRONIK
VI.3.5.1 FIRE ALARM Rp 25,242,500
VI.3.5.2 TATA SUARA Rp 2,849,800
VI.3.5.3 TELEPON Rp 3,369,900
VI.3.5.4 CCTV Rp Tidak ada
VI.3.5.5 DATA Rp Tidak ada
VI.3.5.6 MATV Rp Tidak ada
VI.3.5.7 ACCESS CONTROL Rp Tidak ada
VII DAF - VII BANGUNAN ADMINISTRATION OFFICE Rp 1,135,713,851
VII.1 PEKERJAAN STRUKTUR Rp 736,988,083
VII.1.1 PEKERJAAN TANAH Rp 37,163,416 (607,318)
VII.1.2 PEKERJAAN STRUKTUR BETON Rp 405,002,956 (100,132,336)
VII.1.3 PEKERJAAN STRUKTUR BAJA Rp 395,561,365 -
VII.2 PEKERJAAN ARSITEKTUR Rp 213,364,601
VII.2.1 PEKERJAAN DINDING Rp 30,632,676 (426,557)
VII.2.2 PEKERJAAN PINTU DAN JENDELA Rp 47,528,836 -
VII.2.3 PEKERJAAN LANTAI Rp 33,059,213 369,349
VII.2.4 PEKERJAAN PLAPOND Rp 9,757,628 2,262,040
VII.2.5 PEKERJAAN SANITARY Rp 12,074,890 -
VII.2.6 PEKERJAAN LAIN-LAIN Rp 1,208,326 -
VII.2.7 PEKERJAAN ATAP CANOPY Rp 26,675,246 (231,384)
VII.2.8 PEKERJAAN FAÇADE Rp 49,231,343 1,222,994
VII.3 PEKERJAAN MEKANIKAL - ELEKTRIKAL Rp 185,361,167
VII.3.1 PEKERJAAN PLUMBING Rp 2,167,900
VII.3.2 PEKERJAAN PEMADAM KEBAKARAN Rp 558,800
VII.3.3 PEKERJAAN TATA UDARA Rp 139,652,600
VII.3.4 PEKERJAAN ELEKTRIKAL Rp 15,759,700
VII.3.5 PEKERJAAN ELEKTRONIK
VII.3.5.1 FIRE ALARM Rp Tidak ada
VII.3.5.2 TATA SUARA Rp 1,893,000
VII.3.5.3 TELEPON Rp 3,945,833
VII.3.5.4 CCTV Rp Tidak ada
VII.3.5.5 DATA Rp 19,684,333
VII.3.5.6 MATV Rp 1,699,000
VII.3.5.7 ACCESS CONTROL Rp Tidak ada

VIII DAF - VIII BANGUNAN QUARANTINE STABLE Rp 1,104,839,742


VIII.1 PEKERJAAN STRUKTUR Rp 334,396,056
VIII.1.1 PEKERJAAN TANAH Rp 13,764,163 295,448
VIII.1.2 PEKERJAAN STRUKTUR BETON Rp 94,888,330 7,121,639
VIII.1.3 PEKERJAAN STRUKTUR BAJA Rp 218,326,475 -
VIII.2 PEKERJAAN ARSITEKTUR Rp 594,250,187
VIII.2.1 PEKERJAAN DINDING Rp 72,455,387 10,269,820
VIII.2.2 PEKERJAAN PINTU DAN JENDELA Rp 92,495,477 -
VIII.2.3 PEKERJAAN LANTAI Rp 38,903,790 494,337
VIII.2.4 PEKERJAAN PLAPOND Rp 4,722,157 4,063,448
VIII.2.5 PEKERJAAN SANITARY Rp Tidak ada
VIII.2.6 PEKERJAAN LAIN-LAIN Rp 198,003,294 -
VIII.2.7 PEKERJAAN ATAP CANOPY Rp 56,499,716 13,372,180
VIII.2.8 PEKERJAAN FAÇADE Rp 90,059,328 12,911,251
VIII.3 PEKERJAAN MEKANIKAL - ELEKTRIKAL Rp 176,193,500
VIII.3.1 PEKERJAAN PLUMBING Rp 1,285,200
VIII.3.2 PEKERJAAN PEMADAM KEBAKARAN Rp 558,800
VIII.3.3 PEKERJAAN TATA UDARA Rp 38,828,000
VIII.3.4 PEKERJAAN ELEKTRIKAL Rp 121,798,300
VIII.3.5 PEKERJAAN ELEKTRONIK
VIII.3.5.1 FIRE ALARM Rp Tidak ada
VIII.3.5.2 TATA SUARA Rp Tidak ada
VIII.3.5.3 TELEPON Rp Tidak ada
VIII.3.5.4 CCTV Rp 13,723,200
VIII.3.5.5 DATA Rp Tidak ada
VIII.3.5.6 MATV Rp Tidak ada
VIII.3.5.7 ACCESS CONTROL Rp Tidak ada

IX DAF - IX BANGUNAN COVERED TRAINING AREA Rp 8,544,415,692


IX.1 PEKERJAAN STRUKTUR Rp 3,159,778,527
IX.1.1 PEKERJAAN TANAH Rp 20,610,022 (1,018,214)
IX.1.2 PEKERJAAN STRUKTUR BETON Rp 149,941,740 42,442,664
IX.1.3 PEKERJAAN STRUKTUR BAJA Rp 2,947,802,315 -
IX.2 PEKERJAAN ARSITEKTUR Rp 3,552,464,265
IX.2.1 PEKERJAAN DINDING Rp 38,874,451 (3,100,499)
IX.2.2 PEKERJAAN LANTAI Rp 2,031,508,224 40,626,010
IX.2.3 PEKERJAAN ATAP CANOPY Rp 1,190,950,425 253,605,655
IX.3 PEKERJAAN MEKANIKAL - ELEKTRIKAL Rp 1,832,172,900
IX.3.1 PEKERJAAN PLUMBING Rp 1,611,543,500
IX.3.2 PEKERJAAN PEMADAM KEBAKARAN Rp Tidak ada
IX.3.3 PEKERJAAN TATA UDARA Rp Tidak ada
IX.3.4 PEKERJAAN ELEKTRIKAL Rp 175,608,400

JAKARTA INTERNATIONAL EQUESTRIAN PARK SAMEP


REKAPITULASI PENJUMLAHAN TOTAL
PAKET PEKERJAAN BUILDING & FASILITAS ( SAP, ME, LANDSCAPE & INTERIOR) PAKET 2
PROYEK JAKARTA INTERNATIONAL EQUESTRIAN PARK PAKET II

NO URAIAN PEKERJAAN TOTAL BASIC TOTAL ± TOTAL BASIC + TOTAL ±

IX.3.5 PEKERJAAN ELEKTRONIK

JAKARTA INTERNATIONAL EQUESTRIAN PARK SAMEP


REKAPITULASI PENJUMLAHAN TOTAL
PAKET PEKERJAAN BUILDING & FASILITAS ( SAP, ME, LANDSCAPE & INTERIOR) PAKET 2
PROYEK JAKARTA INTERNATIONAL EQUESTRIAN PARK PAKET II

NO URAIAN PEKERJAAN TOTAL BASIC TOTAL ± TOTAL BASIC + TOTAL ±

IX.3.5.1 FIRE ALARM Rp Tidak ada


IX.3.5.2 TATA SUARA Rp 14,125,800
IX.3.5.3 TELEPON Rp Tidak ada
IX.3.5.4 CCTV Rp 30,895,200
IX.3.5.5 DATA Rp Tidak ada
IX.3.5.6 MATV Rp Tidak ada
IX.3.5.7 ACCESS CONTROL Rp Tidak ada

X DAF - X BANGUNAN GUARD POST Rp 847,031,668


X.1 PEKERJAAN STRUKTUR Rp 194,038,806
X.1.1 PEKERJAAN TANAH Rp 17,276,921 (126,692)
X.1.2 PEKERJAAN STRUKTUR BETON Rp 77,627,831 (10,543,280)
X.1.3 PEKERJAAN STRUKTUR BAJA Rp 109,804,026 -

X.2 PEKERJAAN ARSITEKTUR Rp 430,163,029


X.2.1 PEKERJAAN DINDING Rp 132,902,025 911,578
X.2.2 PEKERJAAN PINTU DAN JENDELA Rp 89,269,288 57,371,451
X.2.3 PEKERJAAN LANTAI Rp 9,911,957 (7,818,478)
X.2.4 PEKERJAAN PLAPOND Rp 24,299,314 (20,241,463)
X.2.5 PEKERJAAN SANITARY Rp 29,608,850 -
X.2.6 PEKERJAAN LAIN-LAIN Rp 2,401,166 -
X.2.7 PEKERJAAN ATAP CANOPY Rp 57,446,286 42,673,783
X.2.8 PEKERJAAN FAÇADE Rp 11,326,047 101,224
X.3 PEKERJAAN MEKANIKAL - ELEKTRIKAL Rp 222,829,833
X.3.1 PEKERJAAN PLUMBING Rp 25,031,000
X.3.2 PEKERJAAN PEMADAM KEBAKARAN Rp 4,470,400
X.3.3 PEKERJAAN TATA UDARA Rp 139,652,600
X.3.4 PEKERJAAN ELEKTRIKAL Rp 52,236,000
X.3.5 PEKERJAAN ELEKTRONIK
X.3.5.1 FIRE ALARM Rp Tidak ada
X.3.5.2 TATA SUARA Rp Tidak ada
X.3.5.3 TELEPON Rp 1,439,833
X.3.5.4 CCTV Rp Tidak ada
X.3.5.5 DATA Rp Tidak ada
X.3.5.6 MATV Rp Tidak ada
X.3.5.7 ACCESS CONTROL Rp Tidak ada
XI DAF - XI BANGUNAN FOOD & BEVERAGE Rp 1,156,869,459
XI.1 PEKERJAAN STRUKTUR Rp 604,424,175
XI.1.1 PEKERJAAN TANAH Rp 52,730,369 (37,039,378)
XI.1.2 PEKERJAAN STRUKTUR BETON Rp 136,876,090 (12,887,042)
XI.1.3 PEKERJAAN STRUKTUR BAJA Rp 464,744,136 -
XI.2 PEKERJAAN ARSITEKTUR Rp 233,027,584
XI.2.1 PEKERJAAN DINDING Rp 26,491,627 (3,416,254)
XI.2.2 PEKERJAAN PINTU DAN JENDELA Rp 8,413,956 -
XI.2.3 PEKERJAAN LANTAI Rp 77,016,478 -
XI.2.4 PEKERJAAN PLAPOND Rp 3,831,539 -
XI.2.5 PEKERJAAN SANITARY Rp 45,076,680 -
XI.2.6 PEKERJAAN LAIN-LAIN Rp 1,535,222 -
XI.2.7 PEKERJAAN ATAP CANOPY Rp 74,078,335 -
XI.2.8 PEKERJAAN FAÇADE Rp Tidak ada
XI.3 PEKERJAAN MEKANIKAL - ELEKTRIKAL Rp 319,417,700
XI.3.1 PEKERJAAN PLUMBING Rp 20,603,300
XI.3.2 PEKERJAAN PEMADAM KEBAKARAN Rp 2,794,000
XI.3.3 PEKERJAAN TATA UDARA Rp 8,461,400
XI.3.4 PEKERJAAN ELEKTRIKAL Rp 123,855,100
XI.3.5 PEKERJAAN ELEKTRIKAL
XI.3.5.1 FIRE ALARM Rp Tidak ada
XI.3.5.2 TATA SUARA Rp 5,734,200
XI.3.5.3 TELEPON Rp 3,369,900
XI.3.5.4 CCTV Rp 120,414,600
XI.3.5.5 DATA Rp 25,077,400
XI.3.5.6 MATV Rp 9,107,800
XI.3.5.7 ACCESS CONTROL Rp Tidak ada

XII DAF - XII LANDSCAPE Rp 57,216,256,511


XII.1 ZONA DEPAN Rp 28,611,449,101
XII.1.1 SOFTSCAPE Rp 1,630,175,836 -
XII.1.2 HARDSCAPE Rp 4,912,943,333 -
XII.1.3 MEP Rp 11,187,956,000
XII.1.4 PARKIR Rp 7,224,530,231 -
XII.1.5 LAIN-LAIN (KOLAM) Rp 2,852,919,916 -
XII.1.6 STRUKTUR JEMBATAN Rp 803,499,184 (575,399)

XII.2 ZONA BANGUNAN PENUNJANG Rp 15,854,430,560


XII.2.1 SOFTSCAPE Rp 2,464,378,717 -
XII.2.2 HARDSCAPE Rp 8,981,530,339 -
XII.2.3 MEP Rp 1,516,849,312
XII.2.4 LAIN-LAIN Rp 2,891,672,192 -
XII.3 ZONA CROSS COUNTRY Rp 12,750,376,850
XII.3.1 SOFTSCAPE Rp 5,813,518,795 -
XII.3.2 HARDSCAPE Rp 635,653,650 -
XII.3.3 MEP Rp 2,335,445,073
XII.3.4 STRUKTUR REFEREE TOWER Rp 132,699,920 (112,393)
XII.3.4 LAIN-LAIN Rp 3,833,171,806 -

XIII DAF - XIII OUTDOOR ARENA Rp 18,291,608,880


XIII.1 ARENA FIELD OF PLAY (FOP) Rp 3,984,870,875 7,095,326
XIII.2 ARENA WARMING UP Rp 3,065,807,767 187,604,461
XIII.3 COLLECTING ARENA Rp 896,623,027 -
XIII.4 TRAINING ARENA I Rp 2,559,249,987 205,886,566
XIII.5 LAIN-LAIN Rp 7,384,470,870 -
XIII.6 ME (PLUMBING) Rp COVERED TRAINING AREA

JAKARTA INTERNATIONAL EQUESTRIAN PARK SAMEP


REKAPITULASI PENJUMLAHAN TOTAL
PAKET PEKERJAAN BUILDING & FASILITAS ( SAP, ME, LANDSCAPE & INTERIOR) PAKET 2
PROYEK JAKARTA INTERNATIONAL EQUESTRIAN PARK PAKET II

NO URAIAN PEKERJAAN TOTAL BASIC TOTAL ± TOTAL BASIC + TOTAL ±

XIV DAF - XIV GENSET ROOM & STP Rp 14,263,802,863


XIV.1 PEKERJAAN STRUKTUR GENSET & STP Rp 792,228,443
XIV.1.1 PEKERJAAN PONDASI Rp 122,147,049 -
XIV.1.2 PEKERJAAN TANAH Rp 54,960,679 164,583
XIV.1.3 PEKERJAAN STRUKTUR BETON Rp 676,847,284 (61,891,153)
XIV.2 PEKERJAAN ARSITEKTUR Rp 170,143,053
XIV.2.1 PEKERJAAN DINDING Rp 97,324,059 -
XIV.2.2 PEKERJAAN PINTU DAN JENDELA Rp 20,535,740 (6,789,039)
XIV.2.3 PEKERJAAN LANTAI Rp 12,474,838 -
XIV.2.4 PEKERJAAN PLAPOND Rp 10,171,760 -
XIV.2.5 PEKERJAAN SANITARY Rp Tidak ada
XIV.2.6 PEKERJAAN LAIN-LAIN Rp 2,782,393 -
XIV.2.7 PEKERJAAN ATAP CANOPY Rp Tidak ada
XIV.2.8 PEKERJAAN FAÇADE Rp 33,643,303 -
XIV.3 PEKERJAAN MEKANIKAL - ELEKTRIKAL Rp 13,301,431,367
XIV.3.1 PEKERJAAN PLUMBING Rp 2,993,600
XIV.3.2 PEKERJAAN PEMADAM KEBAKARAN Rp 17,262,000
XIV.3.3 PEKERJAAN TATA UDARA Rp 128,543,200
XIV.3.4 PEKERJAAN ELEKTRIKAL Rp 29,235,933
XI.3.5.1 FIRE ALARM Rp 3,014,200
XI.3.5.2 TATA SUARA Rp 6,300,933
XI.3.5.3 TELEPON Rp 31,952,400
XI.3.5.4 CCTV Rp Tidak ada
XI.3.5.5 DATA Rp Tidak ada
XI.3.5.6 MATV Rp Tidak ada
XI.3.5.7 ACCESS CONTROL Rp
XIV.3.2 PEKERJAAN STP Rp Include MEP Landscape

XV DAF - XV PEKERJAAN ITEM TAMBAH - KURANG Rp 1,104,078,167

XVI DAF - XVI PROVISIONAL SUM (Provisional Sum for Contingencies and Rp Exclude Rp
Daywork Allowances)

XVII DAF - XVIII Biaya Bongkaran Rp 2,417,941,165 Rp 2,417,941,165


Struktur dan Arsitektur Spectator Tribun Rp 1,150,559,032
Struktur dan Arsitektur Horse Stable Rp 536,672,726
Stuktur Existing Covered Training Area Rp 730,709,406

SUB TOTAL Rp 260,914,340,949


PPN 10% Rp 26,091,434,095
NILAI TOTAL Rp 287,005,775,044
PEMBULATAN Rp 287,005,000,000

TERBILANG : _____________________________________________________________________________________.
Dua ratus delapan puluh tujuh milyar lima juta rupiah

JAKARTA INTERNATIONAL EQUESTRIAN PARK SAMEP


LEMBAR PENGESAHAN

Nama Project : JAKARTA INTERNATIONAL EQUESTRIAN PARK

Alamat : Gedung Perkantoran Pulomas Satu Gedung VI lantai 3


Jalan Jendral Ahmad Yani No.2 - Jakarta Timur

Paket Pekerjaan : STRUKTUR, ARSITEKTUR, MEKANIKAL ELEKTRIKAL PLUMBING


BONGKARAN BANGUNAN TRIBUN DAN HORSESTABLE

Anggaran Dana : Rp287,005,000,000 (Include Ppn)


Terbilang : Dua ratus delapan puluh tujuh milyar lima juta rupiah

Jakarta, 24 Januari 2017

PT. QUANTITY SURVEYOR INDONESIA PT. PULOMAS JAYA

HERI DEBIYANTO ...............................


Direktur Direktur