B PEKERJAAN FINISHING
C PEKERJAAN JALAN
Pemadatan jalan dengan vibro 2,780.00 / m2 2,500
Tebar sirtu tebal 10 cm 2,230.00 / m2 2,000
Tebar abu batu pengisi tebal 3 cm 3,060.00 / m2 2,750
Pasang macadam tebal 30 cm 5,010.00 / m2 4,500
Aspal hotmix padat (bahan + upah) 1 cm 13,360.00 / m2 12,000
ATB padat (bahan + upah) 1 cm 11,690.00 / m2 10,500
Pemadatan sirtu/ macadam 4,170.00 / m2 3,750
Pemadatan batu pengisi 1,110.00 / m2 1,000
Pasang kanstein beton 6,680.00 / m' 6,000
D LAIN - LAIN
Bongkar dinding, Kusen & Pintu 11,980.00 / m2 10,760
Bongkar keramik lantai 14,970.00 / m2 13,450
Bongkar plafond 11,320.00 / m2 10,170
Bongkar Atap 31,800.00 / m2 28,571
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA
1 M3 PAS Anstamping 1 : 5
Batu belah m³ 1.200 217,030 260,436
Pasir pasang m³ 0.400 233,720 93,488
Upah cor m³ 1.000 44,520 44,520
Sub Jumlah 398,444
Profit -
Jumlah 398,444
Dibulatkan 398,440
1 KG BESI BETON
Besi Beton kg 1.035 7,570 7,835
Kawat Beton kg 0.010 13,360 134
Alat bantu lot 1.000 - -
Upah kg 1.000 890 890
Kaki ayam kg 0.010 - -
Sub Jumlah 8,859
Profit -
Jumlah 8,859
Dibulatkan 8,859
1 M2 BEKISTING BATACO
Batako bh 15.000 3,170 47,550
PC zak 0.175 70,820 12,394
Pasir Pasang m³ 0.023 233,720 5,376
Upah m² 1.000 19,480 19,480
Sub Jumlah 84,799
Profit -
Jumlah 84,799
Dibulatkan 84,790
1 M² BEKISTING KOLOM
Multipleks poly film 1 muka 4' x 8', tebal 18 mm lbr 0.082 328,320 26,800
Minyak bekisting ltr 0.150 16,690 2,504
Hollow 50 x 50 x 600 mm Ls 1.000 26,580 26,580
Stell prop Ls 1.000 3,250 3,250
Waller Beam / klem UNP 100 x 50 ls 1.000 15,790 15,790
Material bantu ls 1.000 - -
Upah m² 1.000 55,000 55,000
Sub Jumlah 129,923
Profit -
Jumlah 129,923
Dibulatkan 129,920
1 M² BEKISTING BALOK
Multipleks poly film 1 muka 4' x 8', tebal 15 mm lb 0.102 278,240 28,390
Minyak bekisting ltr 0.150 16,690 2,504
Hollow 50 x 50 x 2000 mm Ls 1.000 14,960 14,960
Hollow 50 x 100 x 6000 mm Ls 1.000 13,630 13,630
Material bantu ls 1.000 - -
Upah m² 1.000 44,520 44,520
Sub Jumlah 104,003
Profit -
Jumlah 104,003
Dibulatkan 104,000
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA
1 M2 BEKISTING TANGGA
Multipleks poly film 1 muka 4' x 8', tebal 15 mm lb 0.113 245,410 27,822
Minyak bekisting ltr 0.150 16,690 2,504
Rangka Besi Hollow 50 x 50 x 6000 mm Ls 1.000 14,610 14,610.00
Rangka Besi Hollow 50 x 100 x 6000 mm Ls 1.000 18,260 18,260.00
Material bantu Ls 1.000 - -
Upah m² 1.000 100,170 100,170
Sub Jumlah 163,366
Profit -
Jumlah 163,366
Dibulatkan 163,360
1 M² BEKISTING DINDING
Multipleks phenolic 1 sisi 4' x 8', tebal 18 mm lbr 0.102 328,320 33,500
Minyak bekisting ltr 0.150 16,690 2,504
Rangka Besi Hollow 80 x 40 x 3 mm Ls 1.000 19,140 19,140
Stell prop Ls 1.000 3,250 3,250
Waller Beam UNP 100 x 50 Ls 1.000 20,260 20,260
Material bantu Ls 1.000 - -
Upah m² 1.000 33,390 33,390
Sub Jumlah 112,043
Profit -
Jumlah 112,043
Dibulatkan 112,040
1 M2 DINDING KERAMIK 20 x 20 cm
Keramik exMulia m² 1.100 64,550 71,005
PC zak 0.150 70,820 10,623
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 102,470 11,272
Grouting nat kg 0.379 11,130 4,222
Upah m² 1.000 38,950 38,950
Sub Jumlah 139,753
Profit -
Jumlah 139,753
Dibulatkan 139,750
1 M2 DINDING KERAMIK 30 x 30 cm
Keramik ex Mulia m² 1.100 85,140 93,654
PC zak 0.150 75,880 11,382
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.379 11,130 4,222
Upah m² 1.000 38,950 38,950
Sub Jumlah 161,560
Profit -
Jumlah 161,560
Dibulatkan 161,560
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA
1 M2 DINDING KERAMIK 30 x 30 cm
Keramik ex Mulia m² 1.100 65,110 71,621
PC zak 0.150 75,880 11,382
Pasir pasang m³ 0.016 233,720 3,681
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.379 11,130 4,222
Upah m² 1.000 38,950 38,950
Sub Jumlah 139,527
Profit -
Jumlah 139,527
Dibulatkan 139,520
1 M2 LANTAI ANDESIT
Screed lantai m² 1.000 43,380 43,380
Batu alam andesit ukuran 20 x 20 cm m² 0.525 170,280 89,397
Granit 30 x 60 cm m² 0.525 1,193,090 626,372
Pasir Pasang zak 0.131 233,720 30,676
Coating anti jamur m² - - -
Upah m² 1.000 38,950 38,950
Sub Jumlah 828,775
Profit -
Jumlah 828,775
Dibulatkan 828,770
1 M2 LANTAI KERAMIK 30 x 30 cm
Screed lantai m² 1.000 43,380 43,380
Keramik lantai m² 1.100 85,140 93,654
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.386 11,130 4,296
Upah m² 1.000 22,260 22,260
Sub Jumlah 173,261
Profit -
Jumlah 173,261
Dibulatkan 173,260
1 M2 LANTAI KERAMIK 20 x 20 cm
Screed lantai m² 1.000 43,380 43,380
Keramik lantai m² 1.100 64,550 71,005
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.386 11,130 4,296
Upah m² 1.000 22,260 22,260
Sub Jumlah 150,612
Profit -
Jumlah 150,612
Dibulatkan 150,610
1 M2 LANTAI KERAMIK 40 x 40 cm
Screed lantai m² 1.000 43,385 43,385
Keramik lantai m² 1.100 46,190 50,809
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.386 11,130 4,296
Upah m² 1.000 22,260 22,260
Sub Jumlah 130,421
Profit -
Jumlah 130,421
Dibulatkan 130,420
1 M2 koral silikat
koral m² 1.100 43,406 47,747
Perekat keramik zak 0.110 87,920 9,671
Grouting nat kg 0.386 11,130 4,296
PROYEK : JAKARTA INTERNATIONAL EQUASTRIAN PARK
LOKASI : JAKARTA
1 M2 LANTAI KERAMIK 60 x 60 CM
Screed lantai m² 1.000 43,380 43,380
Keramik lantai m² 1.100 141,740 155,914
Perekat keramik zak 0.138 87,920 12,089
Grouting nat kg 0.286 11,130 3,180
Upah m² 1.000 27,820 27,820
Sub Jumlah 242,383
Profit -
Jumlah 242,383
Dibulatkan 242,380
Profit -
Jumlah 528,201
Dibulatkan 528,200
Jumlah 707,875
Dibulatkan 707,870
1 M' STEPNOSING HT
Screed lantai m' 0.100 43,385 4,338
Stepnosing keramik 60 x 20 bh 0.360 252,420 90,871
Perekat keramik lantai zak 0.012 87,920 1,055
Grouting nat kg 0.013 11,130 147
Upah m' 1.000 18,920 18,920
Sub Jumlah 115,332
Profit -
Jumlah 115,332
Dibulatkan 115,330
PEMBULATAN 3,335,100
1 M' TANGGULAN DG PAS. BATA RINGAN LEBAR 60 CM TEBAL 20 CM FIN KERAMIK 400X400 CM EX. PLATINUM
Bata ringan Ex Jaya Celcon 0.126 m3 567,610 71,519
Thinbed 111 (perekat bata ringan t = 3-8 mm) Ex. Drymix 0.100 zak 63,440 6,344
Tile Adhesive Standar (HT, Dinding, Lantai) Ex. Drymix 0.150 zak 82,359 12,354
Tile Grout Ex. Drymix 0.210 kg 7,791 1,636
Lexus Cream, Grey 1.050 m2 68,981 72,430
Keramik mulia 400 x 400 1.100 m2 65,110 71,621
Angkur 1.000 ls 556 556
Alat bantu 1.000 ls 1,669 1,669
Upah Pasang dinding bata ringan dinding dalam 1.000 m2 25,042 25,042
Upah Pasang lantai keramik 1.000 m2 41,736 41,736
SUB TOTAL 238,130 66,777
PROFIT - -
PPH - -
JUMLAH 238,130 66,777
PEMBULATAN 304,910
1 BH CAR STOPPER
Kanstin Car Stopper uk 60 x 30 x 15 cm (K-400) bh 1.000 61,210 61,210
Angkur dia. 12 mm bh 1.000 24,485 24,485
Cat Minyak Ex Gardex Premium Jotun m2 0.284 33,390 9,483
Upah pasang m' 1.000 5,565 5,565
Sub Jumlah 100,743
Profit -
Jumlah 100,743
Dibulatkan 100,740
Rp
1. Kontrak ini bersifat Harga Tetap (Lump Sum Fix Price), kecuali
dimana dicantumkan Provisional atau "Provisional Sum".
Kontraktor wajib menghitung kembali volume pekerjaan dan
memeriksa satuannya yang dibuat oleh Quantity Surveyor dan jika
menurut perhitungan Kontraktor volume dan atau satuannya tidak
sesuai atau terdapat item pekerjaan yang belum tercantum, maka
Kontraktor dapat merubah atau menambahkan pada lampiran
khusus yang dibuat untuk pekerjaan tambah atau kurang.
6 Laporan Bulanan Dan Photo - Photo Kemajuan Pekerjaan ls 1.00 57,000,000 57,000,000
Pemborong wajib membuat Laporan harian, mingguan dan
bulanan, laporan progress pekerjaan serta laporan lainnya.
Pemborong berkewajiban untuk membuat photo- photo atas
kemajuan pekerjaan sebanyak 4 (empat) set untuk
diserahkan setiap bulan hingga masa penyerahan pertama,
serta setiap tahap pengajuan pembayaran (penagihan)
prestasi.
21 Kebersihan
a) Pemborong harus menyediakan fasilitas yang dibutuhkan ls 1.00 200,000,000 200,000,000
untuk memelihara kondisi lapangan serta lingkungan
sekitarnya agar tetap bersih, termasuk pembersihan ban
kendaraan yang keluar masuk proyek.
b) Pemborong harus mengangkut dan membuang keluar proyek ls 1.00 105,000,000 105,000,000
semua sampah, puing-puing, dan bahan-bahan yang tidak
terpakai secara teratur selama pelaksanaan dan pada waktu
penyelesaian pekerjaan keadaan lokasi harus bersih dan
rapih termasuk penyediaan sarana-sarana yang diperlukan
untuk maksud tersebut. (Catatan : sampah dibersihkan setiap
hari dan dalam pengangkutan keluar proyek tidak mengotori
jalan umum).
22 Jalan Masuk Tempat Pekerjaan dan Jalan Sementara ls 1.00 50,000,000 50,000,000
d) Asuransi peralatan yang dimilikinya yang digunakan dalam ls 1.00 545,000,000 545,000,000
proyek ini.
11,647,333,691
II Harga satuan untuk pengeboran ( boring ) dan buang tanah sudah harus
diperhitungkan kemungkinan resiko longsor, pengeboran yang terkena pondasi
dan / atau konstruksi bangunan existing yang masih tertanam pembuangan sisa-
sisa akar tanaman.
III
Harga satuan beton sudah termasukoverbreak beton,semua
yang diperlukan seperti kubus beton, penyiraman, sambungan-
sambungan perhentian beton, pembuatan parit-parit, dsb.
V
Perbedaan yang dikeluarkan oleh suatu pabrik yang lain untuk
diameter yang sama menjadi tanggung jawab kontraktor
1.Contingeous piles :
A Pengeboran Contingeous piles , Ø = 600 mm
Kedalaman pengeboran = …. m, Contingeous pile = …. Unit m' - Exclude - -
3.2 Pekerjaan Buang tanah + lumpur dari pengeboran ke luar lokasi proyek
( Out site ) ( Volume dihitung netto ) pada :
1.Contingeous piles :
E Pengeboran Contingeous piles , Ø = 600 mm
Kedalaman pengeboran = …. m, Contingeous pile = …. Unit m3 - Exclude - -
1.Contingeous piles :
G Contingeous piles , Ø = 600 mm
Kedalaman = …. m, Contingeous pile = ... Unit kg - Exclude - -
3.5 Potong Kepala Tiang borepile termasuk buang puing keluar site
I Contingeous piles , Ø = 600 mm = …. Bh bh - by Others - -
Axial Loading Test (Test Reaksi), 250% x Design Axial Load ( Beban = 250% x
A Bh 1.00 - 37,840,544 37,840,544 -
400 T = 1000 T ) - Diameter 600mm
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja
III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko longsoran,
volume untuk tempat kerja
VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi dan
tidak mengganggu debit air di lingkungan
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan sesuai
gambar spesifikasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan) untuk
urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pile Cap m3 737.78 - 55,640 41,050,301 -
- Pile Cap (area spectator tribune) m3 138.89 - 55,640 7,728,062 -
- Tie beam (area spectator tribune) m3 18.90 - 55,640 1,051,854 -
- Pit lift (area spectator tribune) m3 95.78 - 55,640 5,329,458 -
- Tangga (area spectator tribune) m3 16.88 - 55,640 938,925 -
- Bio Tank Tribun Utara m3 42.70 55,640 2,375,828 -
- Bio Tank Tribun Selatan m3 42.70 55,640 2,375,828 -
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu berikut
peralatan perlengkapan sesuai spesifikasi dan gambar
- Pile Cap m3 35.86 - 272,340 9,766,943 -
- Pile Cap (area spectator tribune) m3 8.67 - 272,340 2,361,392 -
- Tie beam (area spectator tribune) m3 2.93 - 272,340 798,779 -
- Pit lift (area spectator tribune) m3 4.46 - 272,340 1,213,302 -
- Tangga (area spectator tribune) m3 1.13 - 272,340 306,383 -
Bobok kepala Borpile, termasuk buang keluar lokasi proyek sesuai spesifikasi
dan gambar
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Dibawah Tie beam (area spectator tribune) m3 1.47 - 667,780 979,306 -
2) Pile cap m3 358.63 - 667,780 239,486,283 -
3) Pile Cap (area spectator tribune) m3 4.34 - 667,780 2,895,077 -
4) Pit lift (area spectator tribune) m3 2.23 - 667,780 1,487,513 -
5) Pondasi Tangga (area spectator tribune) m3 0.56 - 667,780 375,626 -
6) Bio Tank Tribun Utara m3 1.66 667,780.00 1,108,515 -
7) Bio Tank Tribun Selatan m3 1.66 667,780.00 1,108,515 -
PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M9-150
1) Pelat, pada:
- Lantai 4 m2 189.16 - 66,090 12,501,861 -
6) Kolom, pada:
- Lantai 1 kg 2,012.74 (518.22) 8,859 17,829,841 (4,590,681)
- Lantai 2 kg 1,255.57 (414.20) 8,859 11,122,463 (3,669,174)
- Lantai 3 kg 909.33 (183.39) 8,859 8,055,323 (1,624,519)
2) Kolom, pada:
- Lantai 1 m2 121.37 (5.37) 163,870 19,888,083 (879,163)
- Lantai 2 m2 76.50 (10.90) 163,870 12,536,055 (1,786,183)
- Lantai 3 m2 62.73 (1.07) 163,870 10,279,565 (174,685)
I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-
lubang baut, perapihan dengan gerinda, penyediaan
peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)
I Kolom baja
1) WF 500 x 200 x 12 x 19 Kg 34,006.48 18,364 624,487,969 -
2) WF 400 x 200 x 8 x 13 Kg 22,139.04 18,364 406,556,754 -
3) WF 300 x 300 x 10 x 15 Kg 245,385.12 18,364 4,506,201,619 -
4) WF 300 x 150 x 6,5 x 9 Kg 19,488.80 18,364 357,888,313 -
5) WF 250 x 250 x 9 x 14 Kg 35,910.40 18,364 659,451,162 -
6) WF 250 x 125 x 6 x 9 Kg 8,317.01 18,364 152,731,816 -
7) WF 200 x 200 x 8 x 12 Kg 27,642.60 18,364 507,623,066 -
8) WF 200 x 150 x 6 x 9 Kg 3,938.83 18,364 72,331,897 -
9) WF 200 x 100 x 5,5 x 8 Kg 22,333.12 18,364 410,120,825 -
10) WF 200 x 100 x 5,5 x 8 Kg 22,333.12 18,364 410,120,825 -
11) CNP 150 x 50 x 20 x 2,3 Kg 10,198.00 18,364 187,273,964 -
12) L 150 x 150 x 15 Kg 49,929.51 18,364 916,895,158 -
13) L 120 x 120 x 12 Kg 75,961.15 18,364 1,394,934,893 -
14) L 100 x 100 x 10 Kg 56,158.71 18,364 1,031,286,978 -
15) L 90 x 90 x 10 Kg 10,400.60 18,364 190,994,468 -
16) L 90 x 90 x 7 Kg 2,938.38 18,364 53,959,729 -
17) L 80 x 80 x 6 Kg 22,367.58 18,364 410,753,571 -
18) L 70 x 70 x 6 Kg 5,716.48 18,364 104,976,257 -
19) L 60 x 60 x 6 Kg 20,171.45 18,364 370,424,301 -
20) L 60 x 60 x 5 Kg 9,913.27 18,364 182,045,186 -
21) L 50 x 50 x 5 Kg 17,394.37 18,364 319,426,630 -
22) L 50 x 50 x 4 Kg 1,367.98 18,364 25,121,375 -
23) L 40 x 40 x 4 Kg 1,136.82 18,364 20,876,313 -
24) baut 2 m12 bh 21,320.00 31,163 664,390,912 -
25) baut m12 (provisional) bh 4,040.00 31,163 125,897,715 -
26) plat t=5mm kg 461.45 17,807 8,217,197 -
27) L 40x40x4 @400mm kg 2,968.78 18,364 54,518,036 -
28) plat t=6mm kg 787.74 17,807 14,027,607 -
29) plat t=7mm kg 454.19 17,807 8,087,988 -
30) baut 2 m20 bh 9,520.00 17,807 169,525,636 -
31) plat t=8mm kg 3,095.09 17,807 55,115,160 -
32) plat t=9mm kg 2,543.69 17,807 45,296,257 -
33) baut 2 m16 bh 4,008.00 31,163 124,900,505 -
34) plat t=10mm kg 1,478.94 17,807 26,335,950 -
35) plat t=12mm kg 16,460.16 17,807 293,111,300 -
36) baut 3 m25 bh 2,016.00 31,163 62,824,206 -
37) plat t=15mm kg 8,969.58 17,807 159,724,148 -
38) plat t=16mm kg 8,862.34 17,807 157,814,406 -
39) plat t=18mm kg 7,536.82 17,807 134,210,444 -
40) plat t=5mm (Provisional) kg 2,423.30 17,807 43,152,377 -
41) plat t=8mm (Provisional) kg 2,631.95 17,807 46,867,926 -
42) Stifner t=8mm kg 1,032.43 17,807 18,384,842 -
44) Stifner t=9mm kg 254.34 17,807 4,529,112 -
45) Stifner t=12mm kg 4,755.22 17,807 84,677,628 -
46) Box 400x200x6,3 Kg 32,967.74 18,364 605,412,726 -
45) Box 300x200x6,3 Kg 10,273.83 18,364 188,666,512 -
46) Box 200x100x6,3 Kg 2,515.42 18,364 46,192,701 -
II Kolom baja-Lanjutan
Lantai 3
1) WF 250 x 125 x 6 x 9 Kg 375.92 18,364 6,903,317 -
2) WF 300 x 150 x 6,5 x 9 Kg 1,000.44 18,364 18,371,910 -
3) WF 350 x 175 x 7 x 11 Kg 2,232.00 18,364 40,987,987 -
4) Plate T=10mm Kg 260.33 17,807 4,635,700 -
5) Anchourage M16 Bh 318.00 222,591 70,784,076 -
6) Baut M16 Bh 84.00 31,163 2,617,675 -
7) Shear Connector 2 dia19 - 175mm Kg 99.71 18,364 1,830,968 -
8) Cat Dasar Kg 3,968.39 3,339 13,249,954 -
Lantai 4
1) WF 250 x 125 x 6 x 9 Kg 375.92 18,364 6,903,317 -
2) WF 300 x 150 x 6,5 x 9 Kg 1,307.80 18,364 24,016,251 -
3) WF 350 x 175 x 7 x 11 Kg 2,232.00 18,364 40,987,987 -
4) UNP 200 x 80 x 7,5 Kg 7,291.44 18,364 133,898,497 -
5) UNP 150 x 75 x 6,5 Kg 1,307.12 18,364 24,003,681 -
6) Plate T=10mm Kg 274.85 17,807 4,894,307 -
7) Anchourage M16 Bh 336.00 222,591 74,790,722 -
8) Baut M16 Bh 90.00 31,163 2,804,652 -
9) Shear Connector 2 dia19 - 175mm Kg 110.83 18,364 2,035,317 -
10) Cat Dasar Kg 12,899.97 3,339 43,071,328 -
IV separator beam
1) WF 300 x 150 x 6,5 x 9 Kg 4,903.12 18,364 90,039,882 -
2) Plate T=10mm Kg 489.84 17,807 8,722,735 -
3) Anchourage M16 Bh 624.00 222,591 138,897,055 -
4) Cat Dasar kg 5,392.96 3,339 18,006,400 -
7) Cat Finish kg 5,527.12 3,339 18,454,343 -
II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton maupun
bata , kawat ayam (jika diperlukan) dan semua pekerjaan bantu
yang berhubungan dengan plesteran. Volume plesteran dan
acian sudah ditambahkan 10cm di atas plafond
- Lantai 3
Lobby Lift Service m2 4.07 0.59 348,040 1,415,479 206,388
Male Toilet As. 1-D m2 48.53 8.45 348,040 16,891,773 2,939,546
Female Toilet As. 1-D m2 46.01 8.25 348,040 16,014,713 2,871,330
Janitor As. 1-D m2 20.02 4.90 348,040 6,966,369 1,706,788
Male Toilet As. 8-D m2 37.11 19.87 348,040 12,917,157 6,914,163
Female Toilet As. 8-D m2 26.79 27.48 348,040 9,323,156 9,562,886
Janitor As. 8-D m2 20.02 4.90 348,040 6,966,369 1,706,788
- Lantai 4
Male Toilet As. 1-D m2 55.11 (6.39) 348,040 19,181,877 (2,222,583)
Female Toilet As. 1-D m2 40.17 14.69 348,040 13,979,932 5,113,543
Janitor As. 1-D m2 21.30 (0.18) 348,040 7,413,670 (63,065)
Men Ablution m2 17.88 0.46 348,040 6,222,955 158,706
Women Ablution m2 18.66 0.46 348,040 6,494,844 159,681
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
- Lantai 1
Steward m2 87.90 0.33 18,360 1,613,807 6,096
Office m2 68.76 0.36 18,360 1,262,470 6,573
Secretariat Office m2 119.35 6.32 18,360 2,191,229 116,072
Retail 1 m2 56.86 1.76 18,360 1,044,014 32,282
Retail 2 m2 53.11 (1.73) 18,360 975,026 (31,800)
Retail 3 m2 53.11 (1.73) 18,360 975,026 (31,800)
Retail 4 m2 55.36 (2.32) 18,360 1,016,419 (42,531)
Retail 5 m2 71.64 2.40 18,360 1,315,365 44,152
Lobby As. 3-D m2 50.25 (1.39) 18,360 922,590 (25,520)
Lobby As. 6-D m2 39.53 (3.06) 18,360 725,679 (56,090)
Lobby Lift Service m2 28.21 1.14 18,360 517,899 21,004
Coridor Toilet Athelete Room m2 43.91 (4.49) 18,360 806,243 (82,491)
Athelete Room m2 124.57 1.91 18,360 2,287,078 35,095
Coridor Toilet As. 1-A m2 114.94 (14.29) 18,360 2,110,360 (262,426)
Coridor Toilet Musholla m2 104.03 12.90 18,360 1,910,080 236,791
Male Toilet Musholla m2 7.87 (0.03) 18,360 144,456 (514)
Musholla m2 94.27 (22.62) 18,360 1,730,886 (415,355)
Meeting Room m2 146.50 (146.50) 18,360 2,689,740 (2,689,740)
Lounge Waiting Room m2 81.62 75.19 18,360 1,498,626 1,380,461
Security Office m2 44.19 0.05 18,360 811,417 977
VIP Lobby & Lobby Lift m2 134.17 (61.39) 18,360 2,463,422 (1,127,108)
Public Hall m2 209.44 (111.51) 18,360 3,845,303 (2,047,368)
Stairs As. 3-D m2 50.89 37.12 18,360 934,304 681,523
Stairs As. 5-D m2 56.40 (4.26) 18,360 1,035,504 (78,214)
- Lantai 2
Multipurpose - 1 m2 106.05 10.24 18,360 1,947,078 188,006
Multipurpose - 2 m2 114.69 68.76 18,360 2,105,708 1,262,434
Multipurpose - 3 m2 244.51 18.15 18,360 4,489,240 333,289
Office Room - 1 m2 61.95 1.44 18,360 1,137,402 26,438
Office Room - 2 m2 45.98 0.62 18,360 844,101 11,291
Office Room - 3 m2 45.98 0.62 18,360 844,101 11,291
Control Room /IT Room m2 66.54 157.78 18,360 1,221,674 2,896,841
Coridor Toilet As. 8-D m2 36.00 9.21 18,360 660,960 169,004
Lobby Lift Service m2 23.03 4.15 18,360 422,794 76,139
OB Counter m2 65.22 (8.64) 18,360 1,197,347 (158,539)
Stairs As. 3-D m2 63.80 14.60 18,360 1,171,368 268,093
Stairs As. 5-D m2 56.40 (4.26) 18,360 1,035,504 (78,214)
C Pengecatan dengan fin. cat Acrylic emulsion paint ex.setara ICI /
Jotun tipe ambience majestic, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada : - lanjutan
- Lantai 3
Lobby Lift m2 24.22 0.39 18,360 444,700 7,174
Coridor m2 250.31 4.04 18,360 4,595,609 74,140
Room As. 1-B m2 67.88 0.53 18,360 1,246,185 9,639
Meeting Room As. 1'-B m2 66.74 0.02 18,360 1,225,255 275
Meeting Room As. 3-D m2 66.97 (7.90) 18,360 1,229,551 (145,026)
Meeting Room As. 4-D m2 49.85 9.26 18,360 915,154 169,922
Meeting Room As. 6-D m2 56.83 (6.22) 18,360 1,043,353 (114,153)
Meeting Room As. 7-D m2 35.03 15.17 18,360 643,059 278,429
VIP Room m2 67.68 6.56 18,360 1,242,605 120,350
Office m2 74.52 (0.15) 18,360 1,368,187 (2,754)
Press Conference Room m2 91.72 (0.28) 18,360 1,683,961 (5,122)
Announcer Box m2 32.18 (32.18) 18,360 590,733 (590,733)
Judges Room m2 43.32 2.07 18,360 795,355 38,005
Fei & Aef Room m2 56.61 (17.38) 18,360 1,039,360 (319,078)
Broadcast Room m2 56.61 (35.87) 18,360 1,039,360 (658,536)
Reporter Room m2 74.99 (13.21) 18,360 1,376,725 (242,471)
Lobby Lift Service m2 23.03 1.75 18,360 422,794 32,167
Coridor Toilet As. 1-D m2 36.00 1.32 18,360 660,960 24,235
Coridor Toilet As. 8-D m2 36.00 1.32 18,360 660,960 24,235
Female Toilet As. 8-D m2 5.29 0.65 18,360 97,058 11,927
OB Counter m2 56.64 (0.06) 18,360 1,039,910 (1,102)
Stairs As. 3-D m2 63.80 (3.23) 18,360 1,171,368 (59,266)
Stairs As. 5-D m2 56.40 (4.26) 18,360 1,035,504 (78,214)
- Lantai 4
Pre-Function Room & Lobby Lift m2 381.80 71.21 18,360 7,009,832 1,307,384
Function Room m2 647.71 120.80 18,360 11,891,999 2,217,942
Coridor Function Room m2 344.05 64.17 18,360 6,316,719 1,178,113
Coridor Toilet m2 77.05 14.37 18,360 1,414,702 263,852
Stairs As. 3-D m2 63.80 (3.23) 18,360 1,171,368 (59,266)
Athlete Dining m2 202.26 (56.58) 18,360 3,713,521 (1,038,744)
VIP Room m2 116.75 (48.83) 18,360 2,143,504 (896,493)
Coridor Toilet As. 1-D m2 40.83 8.47 18,360 749,694 155,454
Musholla m2 62.76 (3.12) 18,360 1,152,274 (57,283)
Lobby Lift Service m2 22.07 3.91 18,360 405,168 71,824
Storage As. C-8 m2 47.75 13.16 18,360 876,741 241,566
Storage As. C'-8 m2 68.10 18.58 18,360 1,250,367 341,169
- Lantai 1
Panel Room m2 32.32 (3.72) 18,920 611,494 (70,382)
Fire Stairs As. 1-D m2 97.36 (6.37) 18,920 1,842,051 (120,566)
Fire Stairs As. 9-D m2 71.20 (6.07) 18,920 1,347,028 (114,825)
Male Toilet Athelete Room m2 18.64 0.28 18,920 352,631 5,335
Female Toilet Athelete Room m2 10.42 (0.06) 18,920 197,146 (1,135)
Male Toilet As. 1-A m2 12.02 0.06 18,920 227,335 1,218
Female Toilet As. 1-A m2 13.10 0.22 18,920 247,829 4,185
Male Toilet Musholla m2 21.52 (0.26) 18,920 407,204 (4,965)
- Lantai 2
Smoke Lobby m2 37.88 (9.08) 18,920 716,661 (171,765)
Fire Stairs As. 1-D m2 75.16 (0.79) 18,920 1,422,027 (15,022)
Fire Stairs As. 9-D m2 76.76 (9.05) 18,920 1,452,224 (171,150)
Room As. 1-B m2 47.75 0.41 18,920 903,335 7,663
Room As. 9-B m2 37.02 (0.60) 18,920 700,362 (11,295)
- Lantai 3
Smoke Lobby m2 28.32 0.48 18,920 535,814 9,082
Fire Stairs As. 1-D m2 75.16 (3.65) 18,920 1,422,027 (69,058)
Fire Stairs As. 9-D m2 69.56 3.09 18,920 1,316,075 58,463
- Lantai 4
Smoke Lobby m2 28.29 (2.49) 18,920 535,247 (47,111)
Fire Stairs As. 1-D m2 75.20 (3.69) 18,920 1,422,784 (69,815)
Fire Stairs As. 9-D m2 76.76 (4.11) 18,920 1,452,224 (77,686)
F CAT WEATHERSHIELD
Pengecatan dengan fin. Weathershield ex.setara ICI/ Jotun tipe
Weathershield Jotashield, termasuk peralatan dan perlengkapan
sesuai spesifikasi dan gambar pada :
- Lantai 2
Tribune m2 229.79 503.58 29,490 6,776,521 14,850,502
- Lantai 3
Male Toilet As. 8-D m2 11.42 (11.42) 29,490 336,776 (336,776)
Female Toilet As. 8-D m2 13.94 (13.94) 29,490 411,091 (411,091)
- Lantai 4
Female Toilet As. 1-D m2 8.72 (8.72) 29,490 257,047 (257,047)
III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).
A PINTU BAJA
Pintu Baja SD1 terdiri dari 2 daun pintu, ukuran overall pintu
1500mm lebar x 2400mm , Fire rated 2 hour, kusen steel duco paint
finish termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Lift Lobby
- Lantai 1 unit 1.00 - 10,183,558 10,183,558 -
- Lantai 4 unit 1.00 - 10,183,558 10,183,558 -
Hardware :
Lockset Wilka Art-8379/855 HF BBKSS set 1.00 - Include
- Lockcase Namef art-1769.35/65 SS
- Cylinder Wilka art-1410.40 Nickel
- Panic bar aart-379 /855 BKSS
Hinges Gracia BB 4,5"x4x3 mm SS bh 6.00 - Include
Automatic Flush bolt art-375 MJ SS bh 2.00 - Include
Door selector art-N250 SS bh 1.00 - Include
Door closer dorma TS 300 EN 4 RA silver bh 2.00 - Include
Pintu Baja SD2 terdiri dari 1 daun pintu, ukuran overall pintu
1000mm lebar x 2400mm , Fire rated 2 hour, kusen steel duco paint
finish termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Fire stair
- Lantai 1 unit 2.00 - 6,469,064 12,938,127 -
- Lantai 2 unit 4.00 - 6,469,064 25,876,254 -
- Lantai 3 unit 4.00 - 6,469,064 25,876,254 -
- Lantai 4 unit 3.00 - 6,469,064 19,407,191 -
Hardware :
Lockset Wilka Art-8379/855 HF BBKSS set 1.00 - Include
- Lockcase Namef art-1769.35/65 SS
- Cylinder Wilka art-1410.40 Nickel
- Panic bar aart-379 /855 BKSS
Hinges Gracia BB 4,5"x4x3 mm SS bh 3.00 - Include
Door cleser dorma TS 300 EN 4 RA silver bh 1.00 - Include
Pintu Baja SD3 terdiri dari 1 daun pintu, ukuran overall pintu
1000mm lebar x 2400mm , Fire rated 2 hour, kusen steel duco paint
finish termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Panel room
- Lantai 1 unit 1.00 - 6,302,120 6,302,120 -
Hardware :
Lever handle art-306 SS psg 1.00 - Include
Lockcase Wilka art-1490.55 SS bh 1.00 - Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 - Include
Hinges Gracia B 4"x3"x3 mm SS bh 3.00 - Include
Door cleser dorma TS 300 EN 4 RA silver bh 1.00 - Include
Pintu Baja SD4 terdiri dari 2 pintu dan 4 daun pintu, ukuran overall
pintu 2480mm lebar x 2400mm , Non Fire rated, kusen steel duco
paint finish termasuk hardware dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
Electrical shaft
- Lantai 4 unit 1.00 - 9,474,048 9,474,048 -
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp
B PINTU KAYU
Pintu Kayu WD1 terdiri dari 1 daun pintu ukuran overall pintu
1100mm lebar x 2400mm,solid wood engineering T= 40 mm fin.
HPL wood grain finished ,kusen Alumunium 50/100 powder coating
finish termasuk hardware dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Disable toilet
- Lantai 1 unit 2.00 - 3,812,435 7,624,870 -
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - Include
Door Closer DKS DCL 300 NHO NA set 1.00 - Include
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include
Storage
- Lantai 2 unit 1.00 (1.00) 3,546,160 3,546,160 (3,546,160)
Pantry
- Lantai 3 unit 1.00 (1.00) 3,546,160 3,546,160 (3,546,160)
Service corridor
- Lantai 4 unit 1.00 (1.00) 3,546,160 3,546,160 (3,546,160)
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp
Pintu Kayu WD5 terdiri dari 1 pintu dan 2 daun pintu,solid wood
engineering T= 40 mm fin. HPL wood grain finished ukuran overall
pintu 1600mm lebar x 2400mm ,kusen Alumunium 50/100 powder
coating finish termasuk hardware dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
Secretariat office
- Lantai 1 unit 1.00 - 7,935,385 7,935,385 -
Athlete room
- Lantai 1 unit 1.00 - 7,935,385 7,935,385 -
Storage
- Lantai 4 unit 2.00 - 7,935,385 15,870,769 -
Function room
- Lantai 4 unit 3.00 7,935,385 23,806,154 -
VIP room
- Lantai 4 unit 1.00 1.00 7,935,385 7,935,385 7,935,385
Toilet
- Lantai 4 unit 1.00 7,935,385 7,935,385 -
Control room
- Lantai 4 unit 1.00 7,935,385 7,935,385 -
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include
Pintu Kayu WD7 terdiri dari 1 pintu dan 2 daun pintu,solid wood
engineering T= 40 mm fin. HPL wood grain finished ukuran overall
pintu 1600mm lebar x 2400mm ,kusen Alumunium 50/100 powder
coating finish termasuk hardware dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
VIP room
- Lantai 3 unit 1.00 - 7,935,385 7,935,385 -
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include
Pintu Kayu WD8 terdiri dari 1 pintu dan 2 daun pintu,solid wood
engineering T= 40 mm fin. HPL wood grain finished ukuran overall
pintu 2500mm lebar x 3000mm ,kusen Alumunium 50/100 powder
coating finish termasuk hardware dan perlengkapan bantu lainnya
sesuai spesifikasi dan gambar pada :
Function room
- Lantai 4 unit 3.00 - 7,848,296 23,544,887 -
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 - include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 - include
Cylinder DKS CYL DC DL60MM SN bh 1.00 - include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 - include
Door Closer DKS DCL 300 NHO NA set 1.00 - include
C PINTU KACA
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp
Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include
Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.21 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include
Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include
Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include
Meeting room
- Lantai 3 unit 1.00 - 30,598,053 30,598,053 -
Hardware :
Pull handle art-243/600 mm SS psg 1.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 1.00 - include
Patch fitting dorma PT.21 bh 1.00 - include
Floor hinges dorma BTS 84 T/complete SS set 1.00 - include
Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include
Hardware :
Pull handle art-243/600 mm SS psg 2.00 - include
Patch fitting dorma PT.10,PT20, US10 + cylinder set 2.00 - include
Patch fitting dorma PT.40 bh 2.00 - include
Floor hinges dorma BTS 84 T/complete SS set 2.00 - include
Pintu Kaca AD1, ukuran overall 1000x2400 mm dari kaca clear tebal
8mm, kusen Alumunium 50/100 powder coating finish, lengkap
terpasang termasuk hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada:
Security
- Lantai 1 unit 1.00 - 4,826,448 4,826,448 -
Hardware :
Lever handle art-352 SS psg 1.00 - include
Lockcase Wilka art-1438.30 SN + striking plate bh 1.00 - include
Cylinder Wilka art-1400.60 Nickel bh 1.00 - include
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 - include
Door closer dorma TS 68 RA silver bh 1.00 - include
D JENDELA KACA
Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 - include
Rambuncis art - 118 silver bh 1.00 - include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 - include
HOMOGENEOUS TILE
Homogeneous Tile (polished) uk 600 x 600 mm ex. Setara
Niro granite / Essenza, berikut adukan mortar, additiv,
grouting nat termasuk alat-alat bantu lainnya dengan
peralatan perlengkapan sesuai spesifikasi dan gambar pada :
Lantai 1
- Lift Lobby m2 10.87 0.05 377,320 4,102,028 19,551
- Security office m2 15.47 0.00 377,320 5,836,774 706
- Stair #2 m2 45.56 (0.10) 377,320 17,190,699 (38,713)
- Stair #3 m2 25.35 24.19 377,320 9,565,628 9,127,333
- Teras VIP lobby m2 116.31 11.85 377,320 43,884,326 4,470,892
- Teras Public Hall m2 125.52 31.81 377,320 47,360,810 12,002,795
- Ramp Teras lobby m2 20.83 7.47 377,320 7,858,652 2,819,851
Lantai 2
- Lift Lobby m2 9.40 (0.08) 377,320 3,546,808 (31,318)
- Stair #2 m2 18.63 6.44 377,320 7,029,472 2,430,507
- Stair #3 m2 25.35 6.35 377,320 9,565,628 2,396,359
Lantai 3
- Lift Lobby m2 9.52 (0.10) 377,320 3,592,086 (38,864)
- Stair #2 m2 18.63 6.65 377,320 7,029,472 2,510,650
- Stair #3 m2 22.95 2.49 377,320 8,659,494 940,281
Lantai 4
- Lift Lobby m2 9.28 (0.15) 377,320 3,500,747 (55,174)
- Storage 1 m2 14.09 0.00 377,320 5,318,106 1,880
- Storage 2 m2 30.91 0.03 377,320 11,663,729 11,382
Lantai 1
Detail toilet 1
- Toilet Female m2 28.15 7.42 372,180 10,477,555 2,761,669
- Toilet Male m2 30.37 1.71 372,180 11,302,837 636,623
- Janitor m2 2.31 0.01 372,180 860,890 3,684
- Toilet difable m2 4.77 (0.01) 372,180 1,774,516 (3,721)
Detail toilet 2
Toilet Female m2 15.24 (0.12) 372,180 5,673,748 (43,706)
- Toilet Male m2 18.85 (0.06) 372,180 7,014,995 (21,844)
- Janitor m2 2.73 0.01 372,180 1,017,443 4,005
- Toilet difable m2 6.12 (0.03) 372,180 2,276,835 (12,715)
- Ablution m2 9.78 0.02 372,180 3,640,386 8,393
Lantai 2
Detail toilet 3
- Toilet Female m2 12.46 0.02 372,180 4,637,363 8,709
- Toilet Male m2 12.89 (0.01) 372,180 4,797,400 (2,717)
- Janitor m2 3.15 (0.01) 372,180 1,172,367 (4,355)
Lantai 3
Detail toilet 3
- Toilet Female m2 25.06 (0.18) 372,180 9,326,831 (66,174)
- Toilet Male m2 25.93 (0.25) 372,180 9,650,627 (92,003)
- Janitor m2 6.29 (0.01) 372,180 2,339,151 (3,201)
Lantai 4
Detail toilet 4
- Toilet Female m2 13.73 0.01 372,180 5,110,201 3,739
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
CERAMIC TILE
Ceramic Tile uk. 600 x 600 mm ex setara Roman berikut
adukan mortar, additiv, grouting nat termasuk alat-alat bantu
lainnya dengan peralatan perlengkapan sesuai spesifikasi
dan gambar pada :
Lantai 1
- Panel room m2 9.32 0.03 242,380 2,260,193 7,708
Lantai 2
- Panel room m2 7.24 0.75 242,380 1,754,831 181,833
Lantai 3
- Panel room m2 7.44 (0.05) 242,380 1,803,307 (12,652)
Lantai 4
- Panel room m2 7.44 (1.84) 242,380 1,803,307 (445,252)
FLOOR HARDENER
Floor Hardener 5kg/m2, termasuk alat alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :
Lantai 1
- Security office m2 15.48 (15.48) 41,740 646,135 (646,135)
- Stair #1 m2 35.16 0.23 41,740 1,467,578 9,588
- Stair #4 m2 38.50 (0.54) 41,740 1,606,990 (22,702)
- Stair #5 m2 64.97 5.84 41,740 2,711,848 243,795
- Teras samping m2 162.10 5.82 41,740 6,766,054 242,868
- Tangga ke public hall m2 21.18 17.83 41,740 883,845 744,082
- Tangga ke VIP lobby m2 21.18 24.90 41,740 883,845 1,039,380
Lantai 2
- Pedestrian m2 150.42 8.49 41,740 6,278,531 354,498
- Tribune m2 669.28 18.57 41,740 27,935,747 775,229
- Stair #1 m2 25.99 0.79 41,740 1,084,823 33,004
- Stair #4 m2 26.49 0.55 41,740 1,105,693 23,082
- Teras samping m2 39.91 (39.91) 41,740 1,665,843 (1,665,843)
Lantai 3
- Stair #1 m2 25.69 1.09 41,740 1,072,301 45,522
- Stair #4 m2 26.26 0.70 41,740 1,096,092 29,410
Lantai 1
- Lift Lobby m' 12.22 0.02 20,601 251,749 396
- Security office m' 15.64 0.02 20,601 322,226 369
- Teras VIP lobby m' 27.66 2.13 20,601 569,834 43,881
- Teras Public Hall m' 30.06 0.44 20,601 619,277 9,065
Lantai 2
- Lift Lobby m' 11.88 11.86 20,601 244,744 244,283
Lantai 3
- Lift Lobby m' 11.88 (1.41) 20,601 244,744 (29,003)
Lantai 4
- Lift Lobby m' 11.37 (0.88) 20,601 234,155 (18,224)
Lantai 2
- Panel room m' 11.21 0.03 11,358 127,324 310
Lantai 3
- Panel room m' 10.44 (0.24) 11,358 118,578 (2,715)
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
Lantai 4
- Panel room m' 9.09 1.12 11,358 103,245 12,741
SKIRTING
Homogeneous Tile (polished) uk 100 x 600 mm ex.setara
Niro granite / Essenza, berikut adukan mortar, additiv,
grouting nat termasuk alat-alat bantu lainnya dengan
peralatan perlengkapan sesuai spesifikasi dan gambar
pada :-Provisional
Lantai 1
- Stair #2 m' 16.37 - 20,601 337,244 -
- Stair #3 m' 17.48 - 20,601 360,112 -
Lantai 2
- Stair #2 m' 16.37 - 20,601 337,244 -
- Stair #3 m' 17.48 - 20,601 360,112 -
Lantai 3
- Stair #2 m' 16.37 - 20,601 337,244 -
STEP NOSING
Lantai 1
- Stair #1 m' 30.80 (0.00) 80,110 2,467,388 (0)
- Stair #4 m' 31.90 (1.10) 80,110 2,555,509 (88,121)
Lantai 2
- Stair #1 m' 32.20 (1.40) 80,110 2,579,542 (112,154)
- Stair #4 m' 33.35 (2.55) 80,110 2,671,669 (204,281)
Lantai 3
- Stair #1 m' 32.20 (1.40) 80,110 2,579,542 (112,154)
- Stair #4 m' 33.35 (2.55) 80,110 2,671,669 (204,281)
WATERPROOFING
Lantai 2
- Toilet Female m2 12.46 - 44,520 554,719 -
- Toilet Male m2 12.89 - 44,520 573,863 -
- Janitor m2 3.15 - 44,520 140,238 -
Lantai 3
- Toilet Female m2 24.79 - 44,520 1,103,651 -
- Toilet Male m2 25.66 - 44,520 1,142,383 -
- Janitor m2 6.06 - 44,520 269,791 -
Lantai 4
- Toilet Female m2 15.16 - 44,520 674,923 -
- Toilet Male m2 13.73 - 44,520 611,260 -
- Janitor m2 4.19 - 44,520 186,539 -
- Ablution m2 8.15 - 44,520 362,838 -
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
Lantai 1
- Lift Lobby m2 10.65 0.05 124,090 1,321,122 6,430
- Security office m2 15.32 0.00 124,090 1,900,938 232
- Teras VIP lobby m2 116.31 11.85 124,090 14,432,328 1,470,351
- Teras Public Hall m2 125.52 31.81 124,090 15,575,646 3,947,384
Lantai 2
- Lift Lobby m2 8.70 0.47 124,090 1,079,583 57,950
Lantai 3
- Lift Lobby m2 9.37 (0.25) 124,090 1,162,723 (31,395)
Lantai 4
- Lift Lobby m2 9.11 0.02 124,090 1,130,823 2,330
- Storage 1 m2 14.09 0.00 124,090 1,748,976 618
- Storage 2 m2 30.91 0.03 124,090 3,835,874 3,743
Lantai 1
Detail toilet 1
- Toilet Female m2 28.15 7.42 168,610 4,746,683 1,251,129
- Toilet Male m2 30.37 1.71 168,610 5,120,564 288,411
- Janitor m2 2.18 (0.01) 168,610 367,250 (860)
- Toilet difable m2 4.62 (0.01) 168,610 778,624 (1,686)
Detail toilet 2
- Toilet Female m2 15.09 0.03 168,610 2,545,106 5,491
- Toilet Male m2 18.70 0.09 168,610 3,152,736 15,395
- Janitor m2 2.60 (0.00) 168,610 438,173 (715)
- Toilet difable m2 5.97 (0.03) 168,610 1,006,191 (5,760)
- Ablution m2 9.78 (0.20) 168,610 1,649,217 (34,135)
B Plafond Gypsum Water resistant tebal 12 mm rangka metal furing hollow
ex. Jayaboard, finishing cat Acrylic Emulsion paint ex.ICI, termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :-Lanjutan
Lantai 2
Detail toilet 3
- Toilet Female m2 12.30 0.03 168,610 2,073,903 5,632
- Toilet Male m2 12.73 0.00 168,610 2,146,405 455
- Janitor m2 3.01 (0.02) 168,610 507,516 (3,659)
Lantai 3
Detail toilet 3
- Toilet Female m2 24.79 (0.21) 168,610 4,179,842 (35,037)
- Toilet Male m2 25.66 (0.28) 168,610 4,326,533 (46,739)
- Janitor m2 6.06 (0.08) 168,610 1,021,777 (14,096)
Lantai 4
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
C Beton exposed skim coat, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai dengan spesifikasi dan gambar pada :
- Lantai 1
- Ruang panel m2 9.17 1.87 33,950 311,491 63,594
- Stair #1 m2 18.63 (3.83) 33,950 632,422 (130,132)
- Stair #2 m2 15.67 (1.42) 33,950 531,827 (48,209)
- Stair #3 m2 18.72 2.26 33,950 635,595 76,798
- Stair #4 m2 19.98 1.35 33,950 678,197 45,695
- Lantai 2
- Ruang panel m2 7.23 2.00 33,950 245,459 67,840
- Stair #1 m2 18.94 4.26 33,950 642,897 144,585
- Stair #2 m2 16.09 5.12 33,950 546,105 173,739
- Stair #3 m2 18.72 7.95 33,950 635,595 270,040
- Stair #4 m2 10.89 12.59 33,950 369,846 427,432
- Lantai 3
- Ruang panel m2 7.22 1.47 33,950 245,119 49,749
- Stair #1 m2 18.94 6.37 33,950 642,897 216,171
- Stair #2 m2 16.09 7.30 33,950 546,105 247,832
- Stair #3 m2 22.95 (1.36) 33,950 779,153 (46,240)
- Stair #4 m2 10.89 14.63 33,950 369,846 496,718
- Lantai 4
- Ruang panel m2 5.58 1.14 33,950 189,441 38,825
- Stair #1 m2 21.06 0.14 33,950 714,987 4,814
- Stair #2 m2 21.06 (1.57) 33,950 714,987 (53,366)
- Stair #4 m2 21.30 (0.07) 33,950 722,999 (2,329)
D Metal Ceiling type Custom ex. Durlum atau setara, termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
Lantai 2
- Pedestrian m2 150.42 8.49 444,627 66,880,718 3,776,213
- Tribune m2 669.28 18.57 444,627 297,579,624 8,257,959
1 Sanitary by Interior
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
1 Railing
Railing Tangga steel Pipe dia. 50 W/OP dan dia. 38 W/OP with paint
finish welded & grind smooth tinggi 1100 mm, termasuk Hand Railing dan
alat-alat bantu lainnya dengan peralatan perlengkapan terpasang Sesuai
spesifikasi dan gambar pada :
Lantai 1
- Stair #1 m' 16.51 (7.96) 723,422 11,947,011 (5,761,752)
- Stair #2 m' 11.00 (2.27) 723,422 7,954,939 (1,639,463)
- Stair #3 m' 11.39 1.03 723,422 8,236,623 746,833
- Stair #4 m' 21.72 (13.02) 723,422 15,715,454 (9,421,681)
Lantai 2
- Stair #1 m' 22.87 (13.67) 723,422 16,543,500 (9,888,016)
- Stair #2 m' 11.30 (2.35) 723,422 8,171,966 (1,697,337)
- Stair #3 m' 14.79 (1.59) 723,422 10,696,259 (1,147,086)
- Stair #4 m' 22.52 (13.32) 723,422 16,294,192 (9,638,708)
Lantai 3
- Stair #1 m' 26.67 (16.67) 723,422 19,292,504 (12,058,282)
- Stair #2 m' 13.00 (3.11) 723,422 9,401,783 (2,247,138)
- Stair #4 m' 26.22 (16.12) 723,422 18,970,854 (11,664,290)
2 Handrailing
Hand Railing steel Pipe dia.38mm W/OP with paint finish, termasuk alat-
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
Lantai 1
- Stair #1 m' 16.21 (2.91) 278,239 4,510,472 (809,889)
- Stair #2 m' 16.10 (2.52) 278,239 4,478,612 (700,123)
- Stair #3 m' 17.99 (1.51) 278,239 5,004,311 (420,041)
- Stair #4 m' 15.59 (2.02) 278,239 4,338,595 (562,888)
Lantai 2
- Stair #1 m' 16.21 (2.26) 278,239 4,510,472 (629,034)
- Stair #2 m' 16.10 (2.52) 278,239 4,478,612 (700,123)
- Stair #3 m' 17.99 (1.51) 278,239 5,004,311 (420,041)
- Stair #4 m' 15.59 (2.02) 278,239 4,338,595 (562,888)
Lantai 3
- Stair #1 m' 16.21 (2.26) 278,239 4,510,472 (629,034)
- Stair #2 m' 16.10 (2.52) 278,239 4,478,612 (700,123)
- Stair #4 m' 15.59 (2.02) 278,239 4,338,595 (562,888)
3 Railling Kaca
Railling Kaca Tempered 12mm dan Railing stainless steel 20mm x 60mm
(custom) + Hand Railling Stainless Steel 40mm x 80mm with paint finish
welded & grind smooth tinggi 1100 mm , termasuk angkur baut, sealant
dan kelengkapan lainnya sesuai gambar dan spesifikasi pada :
- Lantai 2
- Stair #5 m' 114.17 0.23 3,199,752 365,315,670 735,943
4 Cermin
Kaca cermin tebal 6mm, lengkap dengan bevel bagian pinggir, berikut
lapisan belakang dari multiplek tebal 12 mm, berikut sealant, bracket, dll
termasuk alat-alat bantu lainnya dengan peralatan dan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :
Lantai 1
Detail toilet 1
- Female toilet 1 (uk. 1960x1000 mm) unit 1.00 - 1,590,601 1,590,601 -
- Male toilet 1 (uk. 1960x1000 mm) unit 1.00 - 1,590,601 1,590,601 -
- Female toilet 2 (uk. 2740x1000 mm) unit 1.00 - 2,223,596 2,223,596 -
- Male toilet 2 (uk. 3450x1000 mm) unit 1.00 - 2,799,783 2,799,783 -
Detail toilet 2
- Female toilet (uk. 2740x1000 mm) unit 1.00 - 2,223,596 2,223,596 -
- Male toilet (uk. 2810x1000 mm) unit 1.00 - 2,272,288 2,272,288 -
Lantai 2
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
Lantai 3
Detail toilet 3
- Female toilet (uk. 2690x1000 mm) unit 2.00 - 2,183,019 4,366,038 -
- Male toilet (uk. 2085x1000 mm) unit 2.00 - 1,687,985 3,375,970 -
Lantai 4
Detail toilet 4
- Female toilet (uk. 3590x1000 mm) unit 1.00 - 2,913,397 2,913,397 -
- Male toilet (uk. 1885x1000 mm) unit 1.00 - 1,525,679 1,525,679 -
Lantai 2
Detail toilet 3
- Female toilet (uk. 2690x1000 mm) m' 2.69 - 343,107 922,958 -
- Male toilet (uk. 2085x1000 mm) m' 2.08 - 343,107 713,663 -
Lantai 3
Detail toilet 3
- Female toilet (uk. 2690x1000 mm) m' 2.69 - 343,107 922,958 -
- Male toilet (uk. 2085x1000 mm) m' 2.08 - 343,107 713,663 -
Lantai 4
Detail toilet 4
- Female toilet (uk. 3590x1000 mm) m' 3.59 - 343,107 1,231,755 -
- Male toilet (uk. 1885x1000 mm) m' 1.89 0.00 343,107 646,757 1,716
6 Meja Lavatory
Meja Lavatory granite hitam nero absolute (rangka besi), termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :
Lantai 1
Detail toilet 1
- Female toilet 1 (uk. 1960x1000 mm) unit 1.00 - 2,499,110 2,499,110 -
- Male toilet 1 (uk. 1960x1000 mm) unit 1.00 - 2,499,110 2,499,110 -
- Female toilet 2 (uk. 2740x1000 mm) unit 1.00 - 3,335,100 3,335,100 -
- Male toilet 2 (uk. 3450x1000 mm) unit 1.00 - 4,096,060 4,096,060 -
Meja Lavatory granite hitam nero absolute (rangka besi), termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada :-Lanjutan
Lantai 1
Detail toilet 2
- Female toilet (uk. 2740x1000 mm) unit 1.00 - 3,335,100 3,335,100 -
- Male toilet (uk. 2810x1000 mm) unit 1.00 - 3,335,100 3,335,100 -
Lantai 2
Detail toilet 3
- Female toilet (uk. 2690x1000 mm) unit 1.00 - 3,335,100 3,335,100 -
- Male toilet (uk. 2085x1000 mm) unit 1.00 - 3,335,100 3,335,100 -
Lantai 3
Detail toilet 3
- Female toilet (uk. 2690x1000 mm) unit 2.00 - 3,335,100 6,670,200 -
- Male toilet (uk. 2085x1000 mm) unit 2.00 - 3,335,100 6,670,200 -
Lantai 4
Detail toilet 4
- Female toilet (uk. 3590x1000 mm) unit 1.00 - 4,096,060 4,096,060 -
- Male toilet (uk. 1885x1000 mm) unit 1.00 - 2,499,110 2,499,110 -
Tanggulan tinggi 400 mm, tebal 150 mm lapis keramik ex. Roman
7 termasuk adukan perekat, material bantu dan perlengkapan lainnya sesuai
gambar dan spesifikasi pada : (Provisional)
Lantai 1
Detail toilet 1
- Janitor m' 1.18 - 304,910 358,879 -
Detail toilet 2
- Janitor m' 1.35 - 304,910 411,629 -
Lantai 2
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
Lantai 3
Detail toilet 3
- Janitor m' 1.62 - 304,910 493,954 -
Lantai 4
Detail toilet 4
- Janitor m' 1.65 - 304,910 503,102 -
Tanggulan tinggi 200 mm, tebal 150 mm lapis keramik ex. Roman
8 termasuk adukan perekat, material bantu dan perlengkapan lainnya sesuai
gambar dan spesifikasi pada : (Provisional)
Lantai 1
Detail toilet 1
- Janitor m' 1.18 - 152,455 179,440 -
Detail toilet 2
- Janitor m' 1.35 - 152,455 205,814 -
Lantai 2
Detail toilet 3
- Janitor m' 0.81 - 152,455 123,489 -
Lantai 3
Detail toilet 3
- Janitor m' 1.62 - 152,455 246,977 -
Lantai 4
Detail toilet 4
- Janitor m' 1.65 - 152,455 251,551 -
Tanggulan tinggi 300 mm, tebal 150 mm lapis batu alam termasuk adukan
9 perekat, material bantu dan perlengkapan lainnya sesuai gambar dan
spesifikasi pada : (Provisional)
Lantai 1
Detail toilet 2
- Ablution m' 4.60 - 160,078 736,358 -
Lantai 4
Detail toilet 4
- Ablution m' 3.30 - 160,078 528,257 -
Tanggulan tinggi 150 mm, tebal 300 mm lapis keramik ex. Roman
10 termasuk adukan perekat, material bantu dan perlengkapan lainnya sesuai
gambar dan spesifikasi pada : (Provisional)
Lantai 1
Detail toilet 2
- Ablution m' 4.60 - 152,455 701,293 -
Lantai 4
Detail toilet 4
- Ablution m' 3.30 - 152,455 503,102 -
Tanggulan Urinoir tinggi 1050 mm, tebal 200 mm lapis granit, sesuai
11
gambar dan spesifikasi pada :
Lantai 1
Detail toilet 1
- Male toilet 1 (uk. 1960x1000 mm) m' 2.74 - 457,365 1,253,180 -
Tanggulan Urinoir tinggi 1250 mm, tebal 450 mm lapis granit, sesuai
12
gambar dan spesifikasi pada :
Lantai 1
Detail toilet 2
- Male toilet (uk. 2810x1000 mm) m' 2.14 - 457,365 978,761 -
Tanggulan Urinoir dan closet tinggi 1200 mm, tebal 100 mm lapis granit,
13 sesuai gambar dan spesifikasi pada :
Lantai 4
Detail toilet 4
- Male toilet (uk. 1885x1000 mm) m' 3.59 - 457,365 1,641,940 -
- Female toilet (uk. 3590x1000 mm) m' 3.59 - 457,365 1,641,940 -
15 Grating
Grating ukuran 300 mm (6x25mm stailess steel) termasuk sesuai gambar
dan spesifikasi (Provisional)
Lantai 1
Detail toilet 2
- Ablution m' 4.60 - 560,040 2,576,184 -
Lantai 4
Detail toilet 4
- Ablution m' 3.30 - 560,040 1,848,132 -
16 Planter Box
Planter Box, dari pasangan bata ringan, finish plester+cat, termasuk
material bantu dan perlengkapan lainnya sesuai gambar dan spesifikasi
pada : (PROVISIONAL)
- Lantai 1 m2 195.94 - 149,230 29,240,126 -
18 Groove
Cutter Grove uk. 10x10 mm pada tepi kansteen terpasang sesuai gambar
dan spesifikasi pada :
- Lantai 1 m' 218.02 63.58 26,120 5,694,630 1,660,762
19 Gutter (Provisional)
Gutter with steel grate sesuai spesifikasi dan gambar pada :
Lantai 1
- Outdoor ramp (Gutter uk 400x200mm) m' 14.80 - 340,310 5,036,588 -
- Outdoor stair bawah tribune (Gutter uk 400x200mm) m' 9.20 - 340,310 3,130,852 -
20 Jamb Lift
Wide jamb stainless steel hairline (ex local) sesuai spesifikasi dan gambar
pada :
Lantai 1
- VIP lift m' 12.20 0.40 389,535 4,752,327 155,814
- Public area lift m' 6.00 0.30 389,535 2,337,210 116,861
Lantai 2
- VIP lift m' 12.20 0.40 389,535 4,752,327 155,814
- Public area lift m' 6.00 0.30 389,535 2,337,210 116,861
- Service lift m' 6.00 0.30 389,535 2,337,210 116,861
Lantai 3
- VIP lift m' 12.20 0.40 389,535 4,752,327 155,814
- Public area lift m' 6.00 0.30 389,535 2,337,210 116,861
- Service lift m' 6.00 0.30 389,535 2,337,210 116,861
Lantai 4
- VIP lift m' 12.20 0.40 389,535 4,752,327 155,814
- Service lift m' 6.00 0.30 389,535 2,337,210 116,861
21 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material bantu
dan kelengkapan lainnya, sesuai spesifkasi & gambar pada: (Provisional)
- Lantai Atap m2 1,629.17 - 198,663 323,655,563 -
1 Atap Canopy
Atap Canopy termasuk kaca laminated tebal 10.75mm, rangka
alumunium, metal roof sandwich panel + insulasi berikut alat bantu
dengan peralatan perlengkapan sesuai dengan spesifikasi dan
gambar pada :
Roof top Baja masuk Struktur Pekerjaan Baja
- Tribune m2 634.40 20.79 1,669,436 1,059,090,042 34,712,578
4 Talang air
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci
& alat-alat penggantung, perlengkapan yang dibutuhkan seperti
mur, baut, handle, engsel, kait angin, sealant, dan
kelengkapannya., rubber gasket (sealant), neoprene, penyetelan
dan pemasangan.
A CAT WEATHERSHIELD
Pengecatan dengan fin. Weathershield ex.ICI/ Jotun tipe
Weathershield Jotashield, termasuk peralatan dan perlengkapan
sesuai spesifikasi dan gambar pada :
- Lantai 1
Eksterior m2 576.15 65.50 29,490 16,990,557 1,931,524
- Lantai 2
Eksterior m2 226.76 72.19 29,490 6,687,129 2,128,759
- Lantai 3
Eksterior m2 280.63 4.74 29,490 8,275,767 139,653
- Lantai 4
Eksterior m2 237.13 31.52 29,490 6,992,999 929,478
B CURTAIN WALL
Curtain wall Tinted Tempered Glass 8mm, ex. Asahimas, termasuk
rangka mullion system, plate st.steel 8mm, firestop, transom,
sunshade bracket alumunium extrude, sesuai spesifikasi dan gambar
pada :
TAMPAK UTARA
- Lantai 1 (Provisional) m2 47.55 - 1,391,196 66,151,392 -
- Lantai 3 m2 193.26 170.43 1,391,196 268,857,063 237,102,169
TAMPAK SELATAN
- Lantai 1 (Provisional) m2 101.07 - 1,391,196 140,604,053 -
- Lantai 3 (Provisional) m2 119.36 - 1,391,196 166,053,210 -
- Lantai 4 m2 136.88 85.30 1,391,196 190,431,493 118,673,440
TAMPAK UTARA
- Lantai 4 m2 499.10 60.53 1,391,196 694,346,154 84,205,226
TAMPAK SELATAN
- Lantai 2 (Provisional) m2 119.36 - 1,391,196 166,053,210 -
TAMPAK TIMUR
- Lantai 4 m2 50.05 3.92 1,391,196 69,629,383 5,458,359
TAMPAK BARAT
- Lantai 4 m2 50.05 3.92 1,391,196 69,629,383 5,458,359
C SPANDREL
Spandrel 12 mm calcium cilicate board painted finish, sesuai
spesifikasi dan gambar pada :
TAMPAK UTARA
- Lantai 3 m2 70.23 0.43 180,300 12,662,559 77,439
TAMPAK TIMUR
- Lantai 3 m2 7.04 - 180,300 1,269,808 -
TAMPAK BARAT
- Lantai 3 m2 7.04 - 180,300 1,269,808 -
D RAILING
Tempered Glass Railing h: 900mm and hollow stainless steel
25x50mm hairline finish, Handle stainless steel d. 50mm, 10 mm
temperred glass ex. Asahimas terpasang sesuai dengan gambar dan
spesifikasi pada : (Provisional)
DAFTAR No. II.2 - PEKERJAAN ARSITEKTUR TRIBUNE Vol Vol (+/-) Harsat Rp Rp
TAMPAK SELATAN
- Lantai 1 - Lantai 2 m2 47.34 3.52 1,224,253 57,961,414 4,304,088
TAMPAK TIMUR
- Lantai 1 - Lantai 2 m2 21.35 0.00 1,224,253 26,133,155 4,644
TAMPAK BARAT
- Lantai 1 - Lantai 2 m2 21.35 0.00 1,224,253 26,133,155 4,644
TAMPAK SELATAN
- Lantai 1 - Lantai 4 m2 1,002.01 110.03 2,337,210 2,341,903,804 257,167,266
TAMPAK TIMUR
- Lantai 1 - Lantai 4 m2 394.50 36.15 2,337,210 922,029,365 84,490,145
TAMPAK BARAT
- Lantai 1 - Lantai 4 m2 394.59 36.06 2,337,210 922,240,020 84,279,490
Catwalk Baja , terdiri dari WF, steel angle 50x50x5mm duco finish,
grill strip plate 40x4mm welded system, finish coating termasuk
rangka, perkuatan, pemasangan serta perapihan, sesuai spesifikasi
dan gambar pada :
TAMPAK TIMUR
- Lantai 1 m' 22.65 1.43 946,014 21,425,316 1,354,691
- Lantai 2 m' 22.32 1.76 946,014 21,115,969 1,664,038
- Lantai 3 m' 18.92 0.91 946,014 17,900,469 858,980
- Lantai 4 m' 18.92 0.91 946,014 17,900,469 858,980
TAMPAK BARAT
- Lantai 1 m' 22.65 1.43 946,014 21,425,316 1,354,691
- Lantai 2 m' 22.32 1.76 946,014 21,115,969 1,664,038
- Lantai 3 m' 18.92 0.91 946,014 17,900,469 858,980
- Lantai 4 m' 18.92 0.91 946,014 17,900,469 858,980
- Lantai 1 m2 - by architect
- Lantai 2 m2 - by architect
- Lantai 3 m2 - by architect
- Lantai 4 m2 - by architect
- Lantai 1
Fire Stairs As. 00-01 m2 - by architect
Fire Stairs As. 16-17 m2 - by architect
- Lantai 2
Fire Stairs As. 00-01 m2 - by architect
Fire Stairs As. 16-17 m2 - by architect
- Lantai 3
Fire Stairs As. 00-01 m2 - by architect
Fire Stairs As. 16-17 m2 - by architect
- Lantai 4
Fire Stairs As. 00-01 m2 - by architect
Fire Stairs As. 16-17 m2 - by architect
- Lantai 1
VIP Lobby m2 25.99 (6.09) 500,831 13,014,187 (3,047,655)
- Lantai 2
Multi Purpose 2 m2 23.40 31.85 500,831 11,719,439 15,950,457
- Lantai 3
VIP Room m2 34.53 2.72 500,831 17,293,685 1,362,260
Coridor m2 68.72 (0.55) 500,831 34,417,588 (273,557)
Lobby Lift m2 51.81 (0.41) 500,831 25,948,040 (206,239)
A PINTU KACA
Pintu & Jendela kaca 1 daun Type GD1 ukuran overall 2700 x
3625 mm, terdiri dari tempered clear glass 12 mm thick setara
ex. Asahimas with patch fitting termasuk pemasangan, door seal,
hardware setara ex. Dekkson, kusen plywood fin.HPL dan
aksessories, sesuai dengan gambar dan spesifikasi, pada:
Lantai 1
- Retail 1 unit 1.00 (1.00) 17,038,261 17,038,261 (17,038,261)
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include
Pintu & Jendela kaca 1 daun Type GD1 ukuran overall 2700 x
3850 mm, terdiri dari tempered clear glass 12 mm thick setara
ex. Asahimas with patch fitting termasuk pemasangan, door seal,
hardware setara ex. Dekkson, kusen plywood fin.HPL dan
aksessories, sesuai dengan gambar dan spesifikasi, pada:
Lantai 1
- Retail 2 unit 1.00 17,984,831 17,984,831 -
- Retail 3 unit 1.00 17,984,831 17,984,831 -
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include
-
Pintu & Jendela kaca 1 daun Type GD1 ukuran overall 2700 x
4075 mm, terdiri dari tempered clear glass 12 mm thick setara
ex. Asahimas with patch fitting termasuk pemasangan, door seal,
hardware setara ex. Dekkson, kusen plywood fin.HPL dan
aksessories, sesuai dengan gambar dan spesifikasi, pada:
Lantai 1
- Retail 4 unit 1.00 19,404,686 19,404,686 -
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
Lantai 1
- Retail 5 unit 1.00 31,236,812 31,236,812 -
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include
-
Pintu kaca Frameless 1 daun Type GD2 ukuran overall 2700 x
1400 mm, terdiri dari tempered clear glass 12 mm thick setara
ex. Asahimas with patch fitting termasuk pemasangan, door seal,
hardware setara ex. Dekkson dan aksessories, sesuai dengan
gambar dan spesifikasi, pada:
Lantai 2
- Multi Purpose 2 unit 1.00 6,625,991 6,625,991 -
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include
-
B PINTU KAYU
Lantai 2
- Office Room 1 unit 1.00 2,893,689 2,893,689 -
- Control Room/IT-Room unit 1.00 2,893,689 2,893,689 -
- Office Room 2 unit 1.00 2,893,689 2,893,689 -
- Office Room 3 unit 1.00 2,893,689 2,893,689 -
Hardware :
Handle DKS LHTR 0039 SSS psg 1.00 Include
Mortise Lock DKS MTS IL DL8585 SSS bh 1.00 Include
Cylinder DKS CYL DC DL60MM SN bh 1.00 Include
Hinge DKS ESS DL 4X3X3MM 2BB SSS psg 1.50 Include
Door Closer DKS DCL 300 NHO NA set 1.00 Include
Lantai 3
- FEI & AEF Room unit 1.00 38,953,501 38,953,501 -
- Broadcast Room unit 1.00 38,953,501 38,953,501 -
C JENDELA KACA
Jendela kaca Type PD5 ukuran overall 3000 x 7400 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:
Lantai 2
- Office Room 1 unit 1.00 22,298,653 22,298,653 -
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
Jendela kaca Type PD5 ukuran overall 3000 x 2950 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:
Lantai 2
- Office Room 1 unit 1.00 8,889,328 8,889,328 -
Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 Include
Rambuncis art - 118 silver bh 1.00 Include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 Include
Jendela kaca Type PD5 ukuran overall 3000 x 1000 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:
Lantai 2
- Control Room/IT-Room unit 1.00 3,013,332 3,013,332 -
- Office Room 2 unit 1.00 3,013,332 3,013,332 -
- Office Room 3 unit 1.00 3,013,332 3,013,332 -
Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 Include
Rambuncis art - 118 silver bh 1.00 Include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 Include
Jendela kaca Type PD5 ukuran overall 3000 x 4560 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:
Lantai 2
- Control Room/IT-Room unit 1.00 13,740,792 13,740,792 -
Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 Include
Rambuncis art - 118 silver bh 1.00 Include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 Include
Jendela kaca Type PD5 ukuran overall 3000 x 5960 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:
Lantai 2
- Control Room/IT-Room unit 1.00 17,959,456 17,959,456 -
Hardware :
Hinges gracia BB 4"x3"x2 mm SS bh 3.00 Include
Rambuncis art - 118 silver bh 1.00 Include
Cabin hook gracia art- 50 1/8 " SS bh 1.00 Include
Jendela kaca Type PD5 ukuran overall 3000 x 6000 mm, terdiri
dari tempered clear glass 12 mm thick setara ex. Asahimas with
patch fitting termasuk pemasangan, door seal, Alumunium
Frame powder coating setara ex. Alexindo dan aksessories,
sesuai dengan gambar dan spesifikasi, pada:
Lantai 2
- Office Room 2 unit 1.00 18,079,989 18,079,989 -
- Office Room 3 unit 1.00 18,079,989 18,079,989 -
Hardware :
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
A Homogenous Tile
- Lantai 1
Public Hall m2 398.17 (76) 532,430 211,999,104 (40,681,925)
VIP Lobby m2 145.19 15 532,430 77,301,282 8,242,702
- Lantai 1
Steward m2 4.60 44 1,073,930 4,943,023 47,147,737
Office m2 32.74 0 1,073,930 35,157,774 116,853
Coridor VIP Toilet m2 33.12 22 1,073,930 35,565,035 23,364,297
Athelete Room m2 74.43 1 1,073,930 79,936,408 664,723
Coridor Toilet Athelete Room m2 8.42 0 1,073,930 9,045,242 8,525
Secretariat Office m2 129.06 2 1,073,930 138,601,413 1,947,994
Retail 1 m2 23.53 (0) 1,073,930 25,270,915 (128,496)
Retail 2 m2 22.42 0 1,073,930 24,074,826 16,968
Retail 3 m2 22.42 0 1,073,930 24,074,826 24,593
Retail 4 m2 23.60 0 1,073,930 25,343,406 77,269
Retail 5 m2 51.99 (0) 1,073,930 55,828,373 (133,182)
Coridor Musholla m2 41.24 - 1,073,930 44,285,896 -
Lounge Waiting Room m2 77.45 23 1,073,930 83,173,865 24,353,651
Meeting Room m2 144.18 42 1,073,930 154,844,582 45,339,132
- Lantai 2
Multi Purpose 1 m2 130.11 1 1,073,930 139,734,396 967,652
Multi Purpose 2 m2 134.65 11 1,073,930 144,600,082 11,327,419
Multi Purpose 3 m2 342.44 (3) 1,073,930 367,760,421 (3,683,188)
Coridor toilet m2 9.42 (0) 1,073,930 10,116,421 (56,704)
- Lantai 3
Room As. B1 m2 39.74 1 1,073,930 42,676,636 549,584
Meeting Room 1 m2 50.76 0 1,073,930 54,512,687 192,126
VIP Room m2 43.10 0 1,073,930 46,283,689 151,863
Announcer BOX m2 3.34 1 1,073,930 3,585,473 582,986
Judges Room m2 3.34 1 1,073,930 3,585,210 583,249
FEI & AEF Room m2 5.34 (1) 1,073,930 5,735,011 (633,199)
Broadcast Room m2 5.38 (1) 1,073,930 5,774,913 (642,816)
Reporter Room m2 5.19 (0) 1,073,930 5,574,457 (462,764)
Office m2 46.30 0 1,073,930 49,722,940 508,096
Meeting Room 4 m2 11.04 (1) 1,073,930 11,856,396 (675,389)
Appeal Room m2 11.04 (1) 1,073,930 11,856,397 (675,389)
Lobby Lift m2 44.97 (45) 1,073,930 48,299,062 (48,299,062)
Coridor m2 169.88 (65) 1,073,930 182,444,355 (70,118,580)
Coridor toilet m2 18.84 (19) 1,073,930 20,232,841 (20,232,841)
Homogenous tile (polished) type white onyx setara ex.
Indogress uk. 800 x 800 mm , berikut adukan mortar, additiv,
grouting nat termasuk alat alat bantu lainnya dgn peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar, pada :
(Lanjutan)
- Lantai 4
Athlete Dining m2 194.36 (194) 1,073,930 208,732,061 (208,732,061)
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
Homogenous tile type topaz ex. Indogress atau setara uk. 800
x 800 mm , berikut adukan mortar, additiv, grouting nat
termasuk alat alat bantu lainnya dgn peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar, pada :-Lanjutan
- Lantai 2
Multi Purpose 1 m2 7.62 0 507,040 3,863,645 26,755
Multi Purpose 2 m2 8.38 1 507,040 4,246,967 332,691
Multi Purpose 3 m2 8.88 (0) 507,040 4,502,516 (45,094)
Office Room 1 m2 90.50 1 507,040 45,887,120 428,145
Control Room/IT-Room m2 110.75 (13) 507,040 56,154,680 (6,542,946)
Office Room 2 m2 55.50 1 507,040 28,140,086 266,576
Office Room 3 m2 55.50 1 507,040 28,140,086 266,576
B Carpet
- Lantai 1
Musholla (Provisional) m2 37.89 - 228,156 8,644,908 -
Carpet tile type Abstract series setara ex. Balance ukuran 500
x 500 mm, berikut perekat, termasuk alat alat bantu lainnya
dgn peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar
- Lantai 3
Press Conference Room m2 79.49 1 155,814 12,386,248 165,287
Announcer BOX m2 20.63 (0) 155,814 3,214,264 (16,509)
Judges Room m2 20.04 0 155,814 3,122,567 75,188
Judges Room m2 59.21 - 155,814 9,226,300 -
FEI & AEF Room m2 59.18 1 155,814 9,220,510 129,685
Broadcast Room m2 76.11 (15) 155,814 11,859,478 (2,387,825)
Reporter Room m2 49.56 29 155,814 7,722,662 4,443,622
Meeting Room 2 m2 49.56 1 155,814 7,722,662 177,030
Meeting Room 3 m2 45.05 (0) 155,814 7,019,001 (609)
Meeting Room 4 m2 45.05 (0) 155,814 7,019,001 (608)
- Lantai 4
Function Room (VIP Lounge) m2 795.32 35 155,814 123,921,763 5,531,190
Coridor VIP Lounge m2 69.46 3 155,814 10,823,333 483,094
Musholla m2 29.22 (0) 155,814 4,553,278 (23,235)
Plint Homogenous tile type white onyx setara ex. Indogress uk.
100 x 1200 mm , berikut adukan mortar, additiv, grouting nat
termasuk alat alat bantu lainnya dgn peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar, pada :
- Lantai 1
Public Hall m' 60.06 (23) 73,845 4,435,214 (1,722,837)
VIP Lobby m' 37.40 20 73,845 2,761,661 1,490,852
Plint Homogenous tile type white onyx setara ex. Indogress uk.
100 x 800 mm , berikut adukan mortar, additiv, grouting nat
termasuk alat alat bantu lainnya dgn peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar, pada :
- Lantai 1
Steward m' 29.20 (1) 73,845 2,156,278 (86,879)
Office m' 22.80 0 73,845 1,683,669 864
Coridor VIP Toilet m' 32.23 25 73,845 2,379,734 1,809,457
Athelete Room m' 41.05 0 73,845 3,031,344 9,334
Coridor Toilet Athelete Room m' 12.05 3 73,845 889,834 235,219
Secretariat Office m' 39.60 (1) 73,845 2,924,268 (94,138)
Retail 1 m' 17.03 1 73,845 1,257,214 96,065
Retail 2 m' 15.90 0 73,845 1,174,138 1,086
Retail 3 m' 15.90 (0) 73,845 1,174,138 (650)
Retail 4 m' 16.58 0 73,845 1,223,983 3,611
Retail 5 m' 21.45 1 73,845 1,583,979 58,855
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
- Lantai 3
Room As. B1 m' 22.43 (2) 73,845 1,655,978 (148,252)
Meeting Room 1 m' 21.93 2 73,845 1,619,055 119,134
VIP Room m' 22.04 3 73,845 1,627,547 214,934
Office m' 24.64 4 73,845 1,819,545 324,564
Lobby Lift m' 22.13 31 73,845 1,633,824 2,302,049
Coridor m' 24.64 96 73,845 1,819,545 7,076,603
- Lantai 4
Athlete Dining m' 33.22 (33) 73,845 2,452,914 (2,452,914)
VIP Room m' 19.07 (19) 73,845 1,408,375 (1,408,375)
Pre-Function & Lobby Lift m' 60.91 (61) 73,845 4,498,167 (4,498,167)
Coridor VIP Lounge m' 23.54 1 73,845 1,738,647 88,710
Coridor Toilet m' 23.54 21 73,845 1,738,647 1,527,908
Plint Homogenous tile type topaz ex. Indogress atau setara uk.
100 x 800 mm , berikut adukan mortar, additiv, grouting nat
termasuk alat alat bantu lainnya dgn peralatan perlengkapan
terpasang sesuai spesifikasi dan gambar
- Lantai 2
Office Room 1 m' 20.65 1 292,850 6,047,353 274,635
Control Room/IT-Room m' 22.18 55 292,850 6,495,413 15,971,483
Office Room 2 m' 15.33 0 292,850 4,487,926 47,149
Office Room 3 m' 15.33 0 292,850 4,487,926 35,435
- Lantai 1
Musholla (Provisional) m' 28.23 - 228,156 6,439,937 -
Plint Carpet tile type Abstract series setara ex. Balance ukuran
500 x 500 mm, berikut perekat, termasuk alat alat bantu
lainnya dgn peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar
- Lantai 3
Press Conference Room m' 30.21 5 46,744 1,412,283 224,732
Announcer BOX m' 10.05 - 46,744 469,779 -
Judges Room m' 15.20 - 46,744 710,512 -
Judges Room m' 17.30 - 46,744 808,675 -
FEI & AEF Room m' 17.30 1 46,744 808,675 33,777
Broadcast Room m' 23.43 (6) 46,744 1,094,983 (264,684)
Reporter Room m' 21.96 1 46,744 1,026,643 30,543
Meeting Room 2 m' 16.26 7 46,744 759,827 340,751
Meeting Room 3 m' 18.70 5 46,744 874,117 226,162
Meeting Room 4 m' 11.05 19 46,744 516,523 900,097
- Lantai 4
Function Room (VIP Lounge) m' 110.02 - 46,744 5,142,890 -
Coridor VIP Lounge m' 57.62 - 46,744 2,693,602 -
Musholla m' 20.52 2 46,744 959,191 93,376
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
Lantai 1
- Public Hall m2 263.29 (126.79) 124,090 32,671,342 (15,733,653)
- VIP Lobby m2 100.80 6.37 124,090 12,508,075 790,576
- Steward m2 4.53 43.83 124,090 561,848 5,438,500
- Office m2 32.66 0.03 124,090 4,053,089 4,195
- Coridor VIP Toilet m2 32.54 21.85 124,090 4,038,257 2,711,321
- Athelete Room m2 74.20 0.63 124,090 9,207,607 77,738
- Coridor Toilet Athelete Room m2 8.13 0.15 124,090 1,008,859 18,668
- Secretariat Office m2 128.94 1.71 124,090 16,000,165 212,057
- Retail 1 m2 23.53 (0.12) 124,090 2,919,993 (14,847)
- Retail 2 m2 22.42 0.02 124,090 2,781,788 1,961
- Retail 3 m2 22.42 0.02 124,090 2,781,788 2,842
- Retail 4 m2 23.60 0.07 124,090 2,928,369 8,928
- Retail 5 m2 51.99 (0.12) 124,090 6,450,833 (15,389)
- Coridor Musholla m2 40.53 - 124,090 5,029,412 -
- Lounge Waiting Room m2 76.51 23.07 124,090 9,493,971 2,862,140
- Meeting Room m2 143.65 43.31 124,090 17,825,372 5,373,802
- Musholla m2 37.89 (2.78) 124,090 4,701,807 (344,685)
Lantai 2
- Multi Purpose 1 m2 137.73 0.95 124,090 17,091,535 118,358
- Multi Purpose 2 m2 143.02 11.20 124,090 17,747,566 1,390,277
- Multi Purpose 3 m2 351.19 (3.38) 124,090 43,578,990 (419,867)
- Office Room 1 m2 90.50 0.84 124,090 11,230,145 104,782
- Control Room/IT-Room m2 110.75 (13.65) 124,090 13,742,968 (1,694,350)
- Office Room 2 m2 55.50 0.53 124,090 6,886,840 65,240
- Office Room 3 m2 55.50 0.53 124,090 6,886,840 65,240
Lantai 3
- Room As. B1 m2 39.66 0.44 124,090 4,921,875 54,196
- Meeting Room 1 m2 50.64 0.07 124,090 6,283,918 9,170
- VIP Room m2 42.90 0.19 124,090 5,323,770 23,131
- Press Conference Room m2 79.36 1.20 124,090 9,847,634 148,386
- Announcer BOX m2 23.38 1.03 124,090 2,901,069 127,273
- Judges Room m2 23.38 1.03 124,090 2,901,069 127,273
- FEI & AEF Room m2 63.97 0.79 124,090 7,937,418 98,564
- Broadcast Room m2 63.97 1.60 124,090 7,937,418 198,791
A Plafond Gypsumboard tebal .9 mm setara ex. Jayaboard, finishing cat
interior warna putih setara ex Pentalite, Dulux-ICI , termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :-Lanjutan
Lantai 3
- Reporter Room m2 80.72 2.13 124,090 10,015,924 263,927
- Office m2 46.22 0.55 124,090 5,736,058 68,016
- Meeting Room 2 m2 49.43 1.27 124,090 6,133,563 157,738
- Meeting Room 3 m2 49.43 1.29 124,090 6,133,563 159,525
- Meeting Room 4 m2 51.73 3.72 124,090 6,419,641 461,733
- Appeal Room m2 51.73 3.72 124,090 6,419,641 461,733
- Lobby Lift m2 44.97 41.83 124,090 5,580,839 5,191,116
- Coridor m2 183.80 (42.11) 124,090 22,808,334 (5,225,129)
Lantai 4
- Athlete Dining m2 194.05 (13.31) 124,090 24,079,394 (1,651,938)
- VIP Room m2 52.97 (0.65) 124,090 6,572,905 (80,355)
- Pre-Function & Lobby Lift m2 81.22 (13.85) 124,090 10,078,224 (1,718,827)
- Function Room (VIP Lounge) m2 281.79 (5.73) 124,090 34,967,758 (711,423)
- Coridor VIP Lounge m2 45.09 - 124,090 5,595,088 -
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
B Membrane Ceiling type customized setara ex. Intrino atau setara, black
glossy paint finish termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
Lantai 1
- Public Hall m2 133.78 51.49 1,214,878 162,520,673 62,559,250
- VIP Lobby m2 43.28 10.22 1,214,878 52,576,778 12,416,425
C Metal Ceiling type baffle setara setara ex. Durlum, termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
Lantai 3
- Meeting Room 4 m2 3.77 0.03 458,813 1,727,431 14,177
- Appeal Room m2 3.77 0.03 458,813 1,727,431 14,177
D Metal Ceiling type Custom setara ex. Durlum, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
Lantai 4
- Function Room (VIP Lounge) m2 358.60 (358.60) 444,627 159,443,063 (159,443,063)
- Coridor VIP Lounge m2 18.80 (18.80) 444,627 8,358,978 (8,358,978)
E Metal Ceiling type linear setara ex. Durlum, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
Lantai 4
- Pre-Function & Lobby Lift m2 61.80 (61.80) 425,706 26,308,600 (26,308,600)
- Function Room (VIP Lounge) m2 154.70 (154.70) 425,706 65,856,641 (65,856,641)
- Coridor VIP Lounge m2 30.50 (30.50) 425,706 12,984,018 (12,984,018)
Lantai 1
- Public Hall m' 130.01 (34.20) 44,518 5,787,733 (1,522,352)
- VIP Lobby m' 55.26 21.26 44,518 2,460,170 946,659
- Steward m' 26.40 (0.02) 44,518 1,175,283 (681)
- Office m' 20.80 0.56 44,518 925,980 24,930
Lantai 1
- Coridor VIP Toilet m' 29.10 0.16 44,518 1,295,482 7,123
- Athelete Room m' 37.80 (0.09) 44,518 1,682,791 (4,042)
- Secretariat Office m' 50.10 2.71 44,518 2,230,366 120,645
- Coridor Musholla m' 36.50 - 44,518 1,624,917 -
- Musholla m' 15.85 (15.85) 44,518 705,659 (705,659)
Lantai 2
- Multi Purpose 1 m' 138.90 (11.56) 44,518 6,183,590 (514,631)
- Multi Purpose 2 m' 146.32 (1.74) 44,518 6,513,916 (77,462)
- Multi Purpose 3 m' 337.78 - 44,518 15,037,387 -
Lantai 3
- Meeting Room 1 m' 58.51 6.79 44,518 2,604,745 302,299
- VIP Room m' 47.95 10.28 44,518 2,134,682 457,440
- Press Conference Room m' 97.76 0.50 44,518 4,351,940 22,351
- Announcer Box & Judges Room m' 214.65 1.13 44,518 9,555,850 50,395
- FEI & AEF Room m' 75.33 (0.20) 44,518 3,353,340 (8,764)
- Broadcast Room m' 75.38 (1.46) 44,518 3,355,788 (64,943)
- Reporter Room m' 59.65 14.27 44,518 2,655,737 635,109
- Office m' 39.00 0.18 44,518 1,736,213 8,013
- Meeting Room 2 m' 65.78 0.29 44,518 2,928,206 12,894
- Meeting Room 3 m' 65.78 0.29 44,518 2,928,206 12,894
- Meeting Room 4 m' 46.25 (7.25) 44,518 2,058,971 (322,758)
- Appeal Room m' 46.25 (7.25) 44,518 2,058,971 (322,758)
- Lobby Lift m' 29.96 (0.30) 44,518 1,333,625 (13,212)
- Coridor m' 245.76 3.83 44,518 10,940,694 170,625
Lantai 4
- Athlete Dining m' 44.74 0.22 44,518 1,991,953 9,701
- VIP Room m' 7.74 0.05 44,518 344,623 2,054
- Coridor Toilet m' 33.05 0.01 44,518 1,471,327 625
Lantai 3
- FEI & AEF Room m' 6.40 (0.02) 44,518 284,917 (745)
- Broadcast Room m' 6.40 (0.02) 44,518 284,917 (745)
- Reporter Room m' 6.40 (0.02) 44,518 284,917 (745)
Lantai 1
- Retail 5 m' 7.40 (0.04) 44,518 329,435 (2,003)
1 Lantai 1
Janitor
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 1.00 - 229,660 229,660 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -
Ablution
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 4.00 - 229,660 918,640 -
- Floor Drain setara ex. TOTO TX 1 BN bh 2.00 - 385,700 771,400 -
2 Lantai 2
Janitor
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 1.00 - 229,660 229,660 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -
3 Lantai 3
Janitor As. D9
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 1.00 - 229,660 229,660 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -
Janitor As. D1
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 1.00 - 229,660 229,660 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -
4 Lantai 4
Janitor As. D1
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 1.00 - 229,660 229,660 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -
Male Ablution
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 2.00 - 229,660 459,320 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -
Female Ablution
- Wall Tap setara ex TOTO T23B13 (Provisional) bh 2.00 - 229,660 459,320 -
- Floor Drain setara ex. TOTO TX 1 BN bh 1.00 - 385,700 385,700 -
DAFTAR No. II.3 - PEKERJAAN INTERIOR TRIBUNE Vol Vol (+/-) Harsat Rp Rp (+/-)
A. TRIBUNE
Lantai 1
3 - VIP Male Toilet unit 1.00 (1.00) 3,010,413 3,010,413 (3,010,413)
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja
III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko longsoran,
volume untuk tempat kerja
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 171.86 - 55,640 9,562,513 -
- Pile Cap m3 62.01 (52.61) 55,640 3,450,069 (2,927,332)
- Tie Beam m3 12.87 7.95 55,640 716,270 442,121
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu berikut
peralatan perlengkapan sesuai spesifikasi dan gambar
Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam m3 1.95 - 667,780 1,302,505 -
2) Pile cap m3 1.37 - 667,780 915,526 -
PEKERJAAN PEMBESIAN
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf- III.1.A.3 ( 98 ) BETON
DAFTAR No. III.1.B - PEKERJAAN STRUKTUR CHANGING ROOM Vol Vol (+/-) Harsat Rp Rp (+/-)
I
Harga satuan atap sudah termasuk semua hal yang diperlukan, seperti :
pengelasan, pembuatan lubang-lubang baut, perapihan dengan gerinda,
penyediaan peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)
I Canopy Atap
1) WF 250 x 125 x 6 x 9 Kg 4,475.52 18,364 82,187,524 -
2) HB 200 x 200 x 8 x 12 Kg 359.28 18,364 6,597,744 -
3) Gording CNP 150 x 50 x 20 x 2,3 Kg 3,960.00 18,364 72,720,621 -
4) Plate 6 mm Kg 235.01 18,364 4,315,678 -
5) Plate 12 mm Kg 378.88 18,364 6,957,707 -
6) Stifner 8 mm Kg 105.98 18,364 1,946,103 -
7) Stifner 12 mm Kg 116.06 18,364 2,131,372 -
8) Trekstang dia 10mm Kg 163.50 17,807 2,911,421 -
9) Bracing dia 16mm Kg 358.58 18,920 6,784,358 -
10) Spanskrup Kg 64.00 18,920 1,210,897 -
10) Angkur M20 L = 660mm bh 72.00 222,591 16,026,583 -
11) Baut M12 bh 576.00 31,163 17,949,773 -
12) Baut M 16 bh 360.00 31,163 11,218,608 -
13) Nonshrink Grout, T = 25 mm, Uk 300 x 300mm Kg 18.00 50,083 901,495 -
14) Cat Dasar (Zincromate) bh 10,234.80 3,339 34,172,691 -
15) Cat Finish bh 10,234.80 3,339 34,172,691 -
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.186
32 mm 6.313
Monitoring lapangan :
D PEK. DOLLY
Pekerjaan Dolly tiang pancang ukuran 250 x 250 mm, dengan titik
exclude - -
kedalaman = 2 ~ 3 m'
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja
III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko longsoran,
volume untuk tempat kerja
VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi dan
tidak mengganggu debit air di lingkungan
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan sesuai
gambar spesifikasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 94.73 - 55,640 5,270,777 -
- Pile Cap m3 122.75 - 55,640 6,829,810 -
- Tie Beam m3 93.66 37.88 55,640 5,211,242 2,107,629
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 1 m3 51.60 55,640 2,871,024 -
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 2 m3 51.60 55,640 2,871,024 -
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 3 m3 51.60 55,640 2,871,024 -
- Bio Tank Vol 15 m3 Pada Horse Stable Zone 4 m3 51.60 55,640 2,871,024 -
- Bio Tank Vol 5 m3 Pada Equipment & Equine Clinic m3 28.64 55,640 1,593,619 -
- Bio Tank Vol 5 m3 Pada Pordasi Office m3 28.64 55,640 1,593,619 -
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu berikut
peralatan perlengkapan sesuai spesifikasi dan gambar
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam m3 32.39 - 667,780 21,629,394 -
2) Pile cap m3 3.16 0.10 667,780 2,110,185 69,449
3) Bio Tank Vol 15 m3 Pada Horse Stable Zone 1 m3 1.66 667,780 1,108,448 -
4) Bio Tank Vol 15 m3 Pada Horse Stable Zone 2 m3 1.66 667,780 1,108,448 -
5) Bio Tank Vol 15 m3 Pada Horse Stable Zone 3 m3 1.66 667,780 1,108,448 -
6) Bio Tank Vol 15 m3 Pada Horse Stable Zone 4 m3 1.66 667,780 1,108,448 -
7) Bio Tank Vol 5 m3 Pada Equipment & Equine Clinic m3 1.19 667,780 796,528 -
8) Bio Tank Vol 5 m3 Pada Pordasi Office m3 1.19 667,780 796,528 -
PEKERJAAN PEMBESIAN
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pile cap kg 4,140.21 (1,735.56) 8,859 36,676,050 (15,374,494)
2) Tie beam kg 9,727.33 (218.44) 8,859 86,169,553 (1,935,064)
3) Bio Tank Pada Horse Stable Zone 1 kg 2,480.44 8,859 21,972,942 -
4) Bio Tank Pada Horse Stable Zone 2 kg 2,480.44 8,859 21,972,942 -
5) Bio Tank Pada Horse Stable Zone 3 kg 2,480.44 8,859 21,972,942 -
6) Bio Tank Pada Horse Stable Zone 4 kg 2,480.44 8,859 21,972,942 -
7) Bio Tank Vol 5 m3 Pada Equipment & Equine Clinic kg 1,674.72 8,859 14,835,507 -
8) Bio Tank Vol 5 m3 Pada Pordasi Office kg 1,674.72 8,859 14,835,507 -
Balok, pada:
11) - Lantai 2 kg 9,688.70 1,928.78 8,859 85,827,349 17,086,095
- Ramp kg 5,247.32 63.61 8,859 46,483,384 563,501
Kolom, pada:
12) - Lantai 1 kg 4,853.11 2,034.99 8,859 42,991,275 18,026,987
- Ramp kg 817.32 834.52 8,859 7,240,229 7,392,621
2) Kolom, pada:
- Lantai 1 m2 398.54 152.26 129,920 51,778,317 19,781,619
- Ramp m2 61.06 70.91 129,920 7,932,915 9,212,722
1) lantai atap
- Atap m2 646.04 - 127,690 82,492,848 -
1) Balok
- Balok BP.1 m2 43.20 779,070.02 33,655,825 -
- Balok BP.2 m2 129.60 779,070.02 100,967,474 -
- Balok BP.3 & BP.4 m2 200.64 779,070.02 156,312,608 -
I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-lubang
baut, perapihan dengan gerinda, penyediaan peralatan bantu
untuk pemasangan dan mendirikan atap+rangka serta sisa
terbuang (waste)
II
Harga satuan plesteran biasa atau drymix sudah termasuk acian,
skonengan, tali air , ketrikan atau bobokan beton maupun bata , kawat
ayam (jika diperlukan) dan semua pekerjaan bantu yang berhubungan
dengan plesteran. Volume plesteran dan acian sudah ditambahkan 10cm
di atas plafond
V Harga satuan pekerjaan cat dinding sudah termasuk pengertian cat dasar
(meni, plamur, stained, sealer).
A Pasangan Bata ringan tebal 100 mm, setara ex. Optima/ LeitchBrick,
termasuk dinding penebalan,urinoir, perekat, adukan kering kolom dan
balok praktis
- Lantai 1 sesuai spesifikasi dan gambar : m2 2,589.74 284.87 103,480 267,986,258 29,478,488
- Lantai 2 m2 2,019.40 222.13 103,480 208,967,882 22,986,467
- Lantai 1
Steward Office m2 - by Interior
Dining & Lounge m2 - by Interior
Preparation Pantry m2 - by Interior
Female Shower Room
-Locker Area m2 - by Interior
-Changing Room m2 - by Interior
C Pengecatan dengan fin. cat Interior setara ex.Jotun tipe standar,
termasuk peralatan dan perlengkapan sesuai spesifikasi dan gambar
pada :- Lanjutan
- Lantai 1
Male Shower Room
-Locker Area m2 - by Interior
-Changing Room m2 - by Interior
Security Office m2 48.95 (48.95) 18,920 926,157 (926,157)
Security Bedroom m2 39.50 (39.50) 18,920 747,294 (747,294)
R. Pengelola m2 80.57 (29.39) 18,920 1,524,470 (556,049)
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)
D Pengecatan dengan fin. cat Acrylic Emultion ex setara jotun tipe standar
+ Rubber, termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :
- Lantai 1
Horse Box Type A m2 723.67 (723.67) 18,360 13,286,616 (13,286,616)
Horse Box Type B m2 723.67 (723.67) 18,360 13,286,616 (13,286,616)
Horse Box Type C m2 681.21 (681.21) 18,360 12,506,977 (12,506,977)
Tack Room m2 439.98 (439.98) 18,360 8,078,105 (8,078,105)
Horse Bath/ Cleaning m2 443.41 (443.41) 18,360 8,140,970 (8,140,970)
Female Shower Room m2 27.63 (27.63) 18,360 507,362 (507,362)
Male Shower Room m2 27.63 (27.63) 18,360 507,362 (507,362)
Eksterior Horse Box m2 393.24 (393.24) 18,360 7,219,886 (7,219,886)
- Lantai 2
Horse Box Type A m2 1,709.26 (1,709.26) 18,360 31,382,014 (31,382,014)
Horse Box Type B m2 256.18 (256.18) 18,360 4,703,465 (4,703,465)
Tack Room m2 354.04 (354.04) 18,360 6,500,174 (6,500,174)
Horse Bath/ Cleaning m2 362.06 (362.06) 18,360 6,647,348 (6,647,348)
Stairs m2 53.09 (53.09) 18,360 974,687 (974,687)
Eksterior Stairs m2 56.17 (56.17) 18,360 1,031,281 (1,031,281)
Coridor Horse Box m2 703.86 (703.86) 18,360 12,922,943 (12,922,943)
Eksterior Horse Box m2 1,494.18 (1,494.18) 18,360 27,433,214 (27,433,214)
III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis sekeliling
pintu & jendela, dan peralatan bantu yang diperlukan dan bahan yang
terbuang (waste).
A PINTU KAYU
Pintu Kayu P1 Terdiri dari 1 pintu dan 2 daun pintu dengan kusen/frame
alumunium ukuran 2628x2400 mm, Plywood, kaca 5 mmTHK. lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :
Main Entrance
- Lantai 1 unit 3.00 (1.00) 7,545,850 22,637,549 (7,545,850)
- Lantai 2 unit 8.00 2.00 7,545,850 60,366,797 15,091,699
Pintu Kayu P3 Terdiri dari 1 pintu dan 2 daun pintu dengan kusen/frame
alumunium ukuran 1807x2400 mm, Plywood, kaca 5 mmTHK +
Sunblast. lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 2.00 (2.00) 6,533,059 13,066,117 (13,066,117)
Pintu Kayu P4 Terdiri dari 1 pintu dan 2 daun pintu dengan kusen/frame
alumunium ukuran 1700x2400 mm , Plywood, kaca 5 mmTHK +
Sunblast. lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 1.00 (1.00) 3,584,418 3,584,418 (3,584,418)
B JENDELA
CERAMIC TILE
Lantai 1
- Toilet Pria m2 18.41 (18.41) 173,260 3,188,962 (3,188,962)
- Toilet Wanita m2 16.91 (16.91) 173,260 2,929,938 (2,929,938)
- Toilet Difable m2 3.59 (3.59) 173,260 621,791 (621,791)
- Selasar samping as 20-23/A-L (Provisional) m2 180.23 - 173,260 31,226,650 -
Lantai 2
- Toilet Pria m2 18.41 (18.41) 173,260 3,188,962 (3,188,962)
- Toilet Wanita m2 16.91 (16.91) 173,260 2,929,938 (2,929,938)
- Toilet Difable m2 3.59 (3.59) 173,260 621,791 (621,791)
PAVING BLOCK
Lantai 1
- Koridor m2 3,233.89 499.91 248,600 803,945,054 124,277,626
- Jalur kuda eksternal m2 548.32 720.38 248,600 136,312,352 179,086,468
- Horse box m2 1,027.84 512.96 248,600 255,521,024 127,521,856
- Tack room m2 123.60 68.40 248,600 30,726,960 17,004,240
- Horse bath m2 129.12 66.48 248,600 32,099,232 16,526,928
FLOOR HARDENER
Lantai 1
- Ramp Horse Box m2 172.80 178.32 33,390 5,769,792 5,954,105
- Ramp Horse Bath m2 57.68 31.42 33,390 1,925,935 1,049,114
- Ramp Koridor m2 189.19 751.01 33,390 6,317,196 25,076,082
Lantai 2
- Koridor m2 1,522.01 (601.01) 33,390 50,819,914 (20,067,724)
- Jalur kuda eksternal m2 612.44 1,211.16 33,390 20,449,372 40,440,632
- Horse box m2 998.40 532.80 33,390 33,336,576 17,790,192
- Tack room m2 124.96 65.84 33,390 4,172,414 2,198,398
- Horse bath m2 128.48 67.12 33,390 4,289,947 2,241,137
Lantai 1
- Selasar samping as 20-23/A-L (Provisional) m' 56.20 - 2,843 159,761 -
WATERPROOFING
Lantai 1
- Koridor m2 3,233.89 - 22,259 71,983,621 -
- Jalur kuda eksternal m2 548.32 - 22,259 12,205,133 -
- Horse box m2 1,027.84 - 22,259 22,878,838 -
- Tack room m2 123.60 - 22,259 2,751,230 -
- Horse bath m2 129.12 - 22,259 2,874,101 -
- Ramp Horse Box m2 172.80 - 22,259 3,846,380 -
- Ramp Horse Bath m2 57.68 - 22,259 1,283,907 -
- Ramp Koridor m2 189.19 - 22,259 4,211,302 -
Lantai 2
- Koridor m2 1,522.01 - 22,259 33,878,639 -
- Jalur kuda eksternal m2 612.44 - 22,259 13,632,390 -
- Horse box m2 998.40 - 22,259 22,223,529 -
- Tack room m2 124.96 - 22,259 2,781,503 -
- Horse bath m2 128.48 - 22,259 2,859,855 -
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
Lantai 1
- Toilet Pria m2 18.41 0.29 144,680 2,662,929.09 42,586.91
- Toilet Wanita m2 16.91 (2.01) 144,680 2,446,631.93 (290,899.93)
- Toilet Difable m2 3.59 0.21 144,680 519,223.84 30,560.16
Lantai 2
- Toilet Pria m2 18.41 (11.71) 144,680 2,662,929.09 (1,693,573.09)
- Toilet Wanita m2 16.91 (12.61) 144,680 2,446,631.93 (1,824,507.93)
- Toilet Difable m2 3.59 (3.59) 144,680 519,223.84 (519,223.84)
- Lantai 2
- Koridor m2 1,522.01 (0.01) 52,310 79,616,343.10 (523.10)
- Jalur Kuda Eksternal m2 612.44 (612.44) 52,310 32,036,736.40 (32,036,736.40)
- Horse Box m2 998.40 532.80 52,310 52,226,304.00 27,870,768.00
- Tack Room m2 124.96 65.84 52,310 6,536,657.60 3,444,090.40
- Horse Bath m2 128.48 67.12 52,310 6,720,788.80 3,511,047.20
Lantai 1
Toilet Male
Toilet Female
Toilet Difable
Lantai 2
Toilet Male
- Wastafel Set setara ex TOTO LW549J bh 3.00 (3.00) 3,644,970 10,934,910 (10,934,910)
- Closet Duduk Set setara ex. TOTO bh 3.00 (1.00) 3,385,100 10,155,300 (3,385,100)
- CW860NJ/SW861JP
Floor Drain setara ex. TOTO TX 1 BN bh 4.00 (1.00) 385,700 1,542,800 (385,700)
- Tissue Holder setara ex. TX 720 ACRB bh 3.00 (1.00) 267,820 803,460 (267,820)
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 (1.00) 581,660 1,744,980 (581,660)
- Faucet setara ex. TOTO TX 108LDN bh 3.00 (3.00) 1,301,490 3,904,470 (3,904,470)
- Urinoir setara ex. TOTO UW 930 JM bh 3.00 (1.00) 3,483,960 10,451,880 (3,483,960)
- Urinoir Divider setara ex. TOTO AW 115 J bh 2.00 - 3,483,960 6,967,920 -
Toilet Female
- Wastafel Set setara ex TOTO LW549J bh 3.00 (2.00) 3,644,970 10,934,910 (7,289,940)
- Closet Duduk Set setara ex. TOTO bh 3.00 (2.00) 3,385,100 10,155,300 (6,770,200)
- CW860NJ/SW861JP
Floor Drain setara ex. TOTO TX 1 BN bh 4.00 (2.00) 385,700 1,542,800 (771,400)
- Tissue Holder setara ex. TX 720 ACRB bh 3.00 (2.00) 267,820 803,460 (535,640)
- Jetwasher setara ex. TOTO TB 19 CSN bh 3.00 (2.00) 581,660 1,744,980 (1,163,320)
- Faucet setara ex. TOTO TX 108LDN bh 3.00 (2.00) 1,301,490 3,904,470 (2,602,980)
Lantai 2 (Lanjutan)
Toilet Difable
- Wastafel Set setara ex TOTO LW549J bh 1.00 (1.00) 3,644,970 3,644,970 (3,644,970)
- Closet Duduk Set setara ex. TOTO bh 1.00 (1.00) 3,385,100 3,385,100 (3,385,100)
- CW860NJ/SW861JP
Floor Drain setara ex. TOTO TX 1 BN bh 2.00 (2.00) 385,700 771,400 (771,400)
- Tissue Holder setara ex. TX 720 ACRB bh 1.00 (1.00) 267,820 267,820 (267,820)
- Jetwasher setara ex. TOTO TB 19 CSN bh 1.00 (1.00) 581,660 581,660 (581,660)
- Faucet setara ex. TOTO TX 108LDN bh 1.00 (1.00) 1,301,490 1,301,490 (1,301,490)
- Grab bar (provisional) bh 1.00 - 555,220 555,220 -
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
1 Railing
Railing Tangga steel Pipe dia. 50 W/OP dan dia. 38 W/OP with paint
finish welded & grind smooth tinggi 1100 mm, termasuk Hand Railing dan
alat-alat bantu lainnya dengan peralatan perlengkapan terpasang Sesuai
spesifikasi dan gambar pada :
Lantai 1
- Tangga security (provisional) m' 10.35 - 723,422 7,484,460 -
2 Cermin
Kaca cermin tebal 6mm, lengkap dengan bevel bagian pinggir, berikut
lapisan belakang dari multiplek tebal 12 mm, berikut sealant, bracket, dll
termasuk alat-alat bantu lainnya dengan peralatan dan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :
Lantai 1
- Female toilet (uk. 1850x1000 mm) unit 1.00 - 2,294,894 2,294,894 -
- Male toilet (uk. 2650x1000 mm) unit 1.00 - 3,287,281 3,287,281 -
- Difable toilet (uk. 650 x1000 mm) unit 1.00 - 806,314 806,314 -
Lantai 2
- Female toilet (uk. 1850x1000 mm) unit 1.00 - 2,294,894 2,294,894 -
- Male toilet (uk. 2650x1000 mm) unit 1.00 - 3,287,281 3,287,281 -
- Difable toilet (uk. 650 x1000 mm) unit 1.00 (1.00) 806,314 806,314 (806,314)
3 Meja Lavatory
Meja Lavatory granite hitam nero absolute, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :
Lantai 1
- Female toilet (uk. 1850x1000 mm) unit 1.00 - 5,765,118 5,765,118 -
- Male toilet (uk. 2650x1000 mm) unit 1.00 - 8,258,142 8,258,142 -
Lantai 2
- Female toilet (uk. 1850x1000 mm) unit 1.00 - 5,765,118 5,765,118 -
- Male toilet (uk. 2650x1000 mm) unit 1.00 - 8,258,142 8,258,142 -
4 Parapet
Dinding parapet beton tinggi 1200 mm, finish plester aci dan cat
weathershield,
Lantai 1 termasuk alat bantu lainnya dengan perlengkapan
- Ramp m' 83.13 - 304,910 25,347,168 -
- Bangunan m' 269.90 - 304,910 82,295,209 -
5 Tanggulan
Tanggulan Urinoir tinggi 1200 mm, tebal 115 mm lapis keramik, sesuai
gambar
Lantai 1dan spesifikasi pada :
- Male toilet (uk. 2650x1000 mm) m' 3.38 0.02 304,910 1,030,596 6,098
Lantai 2
- Male toilet (uk. 2650x1000 mm) m' 3.38 0.02 304,910 1,030,596 6,098
Tanggulan Closet tinggi 1200 mm, tebal 115 mm lapis keramik, sesuai
gambar dan spesifikasi pada :
Lantai 1
- Male toilet (uk. 2650x1000 mm) m' 2.38 0.02 304,910 725,991 5,793
- Female toilet (uk. 1850x1000 mm) m' 2.38 0.02 304,910 725,991 5,793
Lantai 2
- Male toilet (uk. 2650x1000 mm) m' 2.38 0.02 304,910 725,991 5,793
- Female toilet (uk. 1850x1000 mm) m' 2.38 0.02 304,910 725,991 5,793
6 Groove (Provisional)
Cutter Grove uk. 10x10 mm termasuk gutter 50x30 mm terpasang sesuai
gambar dan spesifikasi pada :
Lantai 1
- Groove ramp 1 m2 129.95 - 26,120 3,394,294 -
- Groove ramp 2 m2 104.60 - 26,120 2,732,152 -
7 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material bantu
dan kelengkapan lainnya, sesuai spesifkasi & gambar pada: (Provisional)
DAFTAR No. III.2.A - PEKERJAAN ARSITEKTUR HORSE STABLE Vol Vol (+/-) Harsat Rp Rp (+/-)
Lantai 1
- Horse Box m' 220.80 - 333,887 73,722,283 -
9 PERLENGKAPAN
Tempat makan kuda, sesuai gambar dan spesifikasi pada :
Lantai 1
- Horse Box bh 64.00 32.00 237,872 15,223,829 7,611,915
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
Roof top
- Atap bawah m2 2,193.00 2,349.51 300,498 658,993,069 706,024,079
- Atap monitor (Pekerjaan baja masuk struktur baja) m2 983.00 (237.40) 300,498 295,389,962 (71,338,329)
2
Bongkaran atap UPVC Existing, sesuai lapangan dan gambar pada :
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.
IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.
VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail
B GRC
Rib cetak GRC finishing cat Acrylic Emultion berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar pada :
(Provisional)
- Dinding samping m2 990.40 - 686,690 680,097,776 -
II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton maupun
bata , kawat ayam (jika diperlukan) dan semua pekerjaan bantu
yang berhubungan dengan plesteran. Volume plesteran dan
acian sudah ditambahkan 10cm di atas plafond
III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).
A PINTU
HOMOGENEOUS TILE
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
1 Sanitary by Interior
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
1 Cermin
Kaca cermin tebal 8mm, lengkap dengan blocking plywood, berikut lapisan
granit hitam, berikut sealant, bracket, dll termasuk alat-alat bantu lainnya
dengan peralatan dan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
Wastafel
- Changing Room Pria (762 x1142 mm) unit 4.00 - 1,077,583 4,310,333 -
- Changing Room wanita (762 x1142 mm) unit 8.00 - 1,077,583 8,620,666 -
Kaca cermin tebal 6mm, lengkap dengan blocking plywood, berikut sealant,
bracket, dll termasuk alat-alat bantu lainnya dengan peralatan dan
perlengkapan terpasang sesuai spesifikasi dan gambar pada :
- Changing Room Pria (3244 x2000 mm) unit 2.00 - 8,038,333 16,076,666 -
- Changing Room Pria (3069 x2000 mm) unit 1.00 - 7,616,569 7,616,569 -
- Changing Room Wanita (3069 x2000 mm) unit 3.00 - 7,616,569 22,849,706 -
2 Meja Lavatory
Meja Lavatory granite hitam nero absolute tebal 200 mm, termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada :
Lantai 1
- Changing Room Pria (4180 x570 mm) unit 1.00 - 7,335,245 7,335,245 -
- Changing Room wanita (4180x570 mm) unit 1.00 - 7,335,245 7,335,245 -
- Changing Room Pria (2850x570 mm) unit 1.00 - 5,001,303 5,001,303 -
- Changing Room Wanita (2850x570 mm) unit 1.00 - 5,001,303 5,001,303 -
3 Tanggulan
Tanggulan Urinoir tinggi 1000 mm, tebal 175 mm lapis keramik, sesuai
gambar
Lantai 1dan spesifikasi pada :
- Male toilet m' 2.34 - 457,365 1,070,234 -
4 Tanggulan Closet tinggi 1000 mm, tebal 175 mm lapis keramik, sesuai
gambar
Lantai 1dan spesifikasi pada :
- Male toilet m' 3.88 - 457,365 1,774,576 -
- Female toilet m' 3.88 - 457,365 1,774,576 -
5 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material bantu dan
kelengkapan lainnya, sesuai spesifkasi & gambar pada: (Provisional)
- Lantai Atap m2 434.65 - 198,663 86,348,810 -
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
1 Atap
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.
IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.
VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail
A GRC
Rib cetak GRC finishing cat weathershild berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar pada :
Dinding samping
- Changing room m2 97.96 95.90 686,690 67,268,152 65,853,571
HOMOGENEOUS TILE
WATERPROOFING
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
A C1, Gypsum Board, setara ex. Jaya Board , tebal 9mm dengan rangka
hollow 40x40mm tebal 6 mm dan 40x20mm tebal 6 mm termasuk cat finish
Acrylic emulsion brilliant white setara ex pentalite dulux, ICI dan alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : INT-1111 & INT-1112)
C4, Gypsum Water resistant , setara ex. Jaya Board, tinggi plafond h=
2900mm dengan rangka hollow 40x40mm tebal 6 mm dan 40x20mm tebal
6 mm termasuk cat finish Acrylic emulsion brilliant white setara ex pentalite
dulux, ICI dan alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (reff.gbr : INT-1111 & INT-1112)
Drop Panel Ceilling 01, Gypsumboard 9mm setara ex. Jaya Board, tinggi
h= 200 mm dengan rangka hollow galvanis termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (reff.gbr : INT-3201)
- Changing Room Pria m' 8.29 - 83,140 688,815 -
- Changing Room Wanita m' 8.28 - 83,140 687,984 -
- Dinning Room m' 42.60 - 83,140 3,541,764 -
- Steward Office m' 5.50 - 83,140 457,270 -
I
Harga satuan Upah sanitair (sanitary equipment) dengan kelengkapan
material bantu (adukan, plesteran, acian, nad, sealan, grouting, bahan
bantu pengubung (doble niple) yang berhubungan dengan instalasi ME
dan lainnya berikut pemasangan dan perapihannya.
I
Harga satuan pekerjaan sudah termasuk fitting, accessories,
alat bantu, perlengkapan dan peralatan yang diperlukan
Signed 1 & Console, Signed Acrylic uk lebar 800mm x tinggi 1400mm dan
lebar 400mm x tinggi 1400mm, Console plywood fin HPL uk
400mmx1692mmx200mm , termasuk rangka hollow alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (reff.gbr : INT-3401)
- Changing Room Pria unit 1.00 3,739,536 3,739,536 -
- Changing Room Wanita unit 1.00 3,739,536 3,739,536 -
III Harga satuan Backdrop dinding panel HPL sudah termasuk rangka,
penyesuaian pola permukaan, bahan terbuang, biaya pengeringan kayu,
anti rayap, penyambungan dan finishing
IV
Harga satuan pada pekerjaan Movable Partition sudah termasuk biaya
untuk rangka, perkuatan struktur penggantung, sound berrier, siap cat
harus sudah termasuk biaya fabrikasi, handling dan pemasangan, angkur-
angkur, bracket, sealant dan back of rod pada celah-celah horisontal dan
vertikal untuk mencegah kebocoran udara, air dan suara.
C1, Kursi Type C 200 N Black / Lime green, ex. Morelli atau setara, uk
panjang 480mm x lebar 450mm x tinggi 610mm, termasuk mesh back,
foam seat fabric unpholstery setara ex Ateja sesuai spesifikasi dan
gambar pada :
7 - Changing Room unit 2.00 1,869,768 3,739,536 -
8 - Steward Office unit 12.00 1,869,768 22,437,217 -
SF1, Soffa 1 Seat type Maya ex. Vivere atau setara, Mahogany wood
base stain fin, foam rubber seats dan cushion fabric uphoistery sesuai
spesifikasi dan gambar pada :
12 - Dinning Room unit 2.00 4,273,756 8,547,511 -
SF2, Soffa 3 Seat type Maya ex. Vivere atau setara, Mahogany wood
base stain fin, foam rubber seats dan cushion fabric uphoistery sesuai
spesifikasi dan gambar pada :
13 - Dinning Room unit 2.00 7,835,218 15,670,437 -
FL, Filling Type Elite file drawer, uk diameter 465mm x 620mm x tinggi
1300mm, metal file cabinet 4 drawer metal 0.8 mm powder coating finish,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :
C2, Kursi Tamu Single type Savio setara ex. Ikons, Mahogany wood
base stain fin, foam rubber seats dan cushion fabric uphoistery sesuai
spesifikasi dan gambar pada :
24 - Steward Office unit 6.00 1,157,475 6,944,853 -
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 101.94 55,640 5,671,752 -
- Pile Cap m3 17.79 55,640 989,752 -
- Tie Beam m3 15.55 55,640 865,343 -
- Bio Tank Equine Clinic m3 28.64 55,640 1,593,619 -
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai basement inc Tie Beam m3 91.40 272,340 24,892,965 -
- Pondasi Batu kali m3 9.04 272,340 2,462,209 -
- Pile Cap m3 3.01 272,340 820,560 -
- Tie Beam m3 2.36 272,340 641,754 -
- Bio Tank Equine Clinic m3 0.60 272,340 162,424 -
Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai basement incl Tie beam m3 30.79 (14.82) 667,780 20,558,635 (9,893,822)
2) Pondasi batu kali m3 90.49 - 667,780 60,425,362 -
3) Pile cap m3 15.07 (13.56) 667,780 10,060,106 (9,054,095)
4) Bio Tank pada Equine Clinic m3 1.19 667,780 796,528
PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada:
- Lantai dasar m2 304.68 14.73 53,220 16,215,070 783,984
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pile cap kg 1,289.59 (305.06) 8,859 11,423,875 (2,702,343)
2) Tie beam / sloof 200 x 300 kg 1,052.85 (55.88) 8,859 9,326,645 (495,036)
3) Balok, pada:
- Lantai 1 kg 708.06 104.91 8,859 6,272,384 929,343
4) Kolom, pada:
- Lantai dasar kg 764.49 146.79 8,859 6,772,207 1,300,330
5) Bio Tank Equine Clinic kg 1,674.72 8,858.50 14,835,507 -
I
Harga satuan atap sudah termasuk semua hal yang diperlukan,
seperti : pengelasan, pembuatan lubang-lubang baut, perapihan
dengan gerinda, penyediaan peralatan bantu untuk pemasangan
dan mendirikan atap+rangka serta sisa terbuang (waste)
II
Harga satuan plesteran biasa atau drymix sudah termasuk acian,
skonengan, tali air , ketrikan atau bobokan beton maupun bata ,
kawat ayam (jika diperlukan) dan semua pekerjaan bantu yang
berhubungan dengan plesteran. Volume plesteran dan acian sudah
ditambahkan 10cm di atas plafond
A Pasangan Bata ringan tebal 100 mm, setara ex. Primacon, termasuk
dinding penebalan,urinoir, perekat, adukan kering kolom dan balok
praktis
- Lantaisesuai
1 spesifikasi dan gambar : m2 507.14 81.45 103,480 52,478,388 8,428,284
- Lantai 1
Wastafel Room m2 - by interior
Toilet As. 00-01 m2 - by interior
Toilet Vet Room m2 - by interior
- Lantai 1
Vet Room m2 56.63 (56.63) by interior
Medicine Storage m2 24.31 (24.31) by interior
Coridor m2 28.62 15.22 18,360 525,423 279,480
- Lantai 1
Sick Horse Box As. 00-01 m2 37.35 (0.00) 18,360 685,746 (37)
Sick Horse Box As. 01-02 m2 37.35 (0.00) 18,360 685,746 (37)
Treatment Room m2 166.43 (18.42) 18,360 3,055,625 (338,162)
Farrier Quarter/ Sick Horse Box As. 03-04 m2 50.86 1.48 18,360 933,790 27,173
Farrier Quarter/ Sick Horse Box As. 04-05 m2 50.06 1.88 18,360 919,102 34,517
Sick Horse Box As. 05-06 m2 50.86 1.48 18,360 933,790 27,173
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)
III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).
A PINTU KAYU
Pintu Kayu P1 Terdiri dari 1 pintu dan 2 daun pintu dengan
kusen/frame alumunium ukuran 2628x2400 mm, Plywood, kaca 5
mmTHK.
- Lantai 1 lengkap terpasang termasuk, hardware, accesories dan unit 3.00 (2.00) 7,927,037 23,781,112 (15,854,075)
Hardware :
Lever handle art - 306 SS psg 1.00 - Include
Lockcase wilka art-1490.55 SS bh 1.00 - Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 - Include
Hinges Gracia BB 5"x3"x3 mm SS bh 8.00 - Include
Flush bolt Gracia 200/350 mm SS set 1.00 - Include
Door closer Dorma TS 68 RA Silver bh 1.00 - Include
Hardware :
Lever handle art - 306 SS psg 1.00 2.00 Include
Lockcase wilka art-1490.55 SS bh 1.00 2.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 2.00 Include
Hinges Gracia BB 4"x3"x3 mm SS bh 3.00 6.00 Include
Door closer Dorma TS 68 RA Silver bh 1.00 2.00 Include
Hardware :
Lever handle art - 306 SS psg 1.00 1.00 Include
Lockcase wilka art-1490.55 SS bh 1.00 1.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 1.00 Include
Hinges Gracia BB 4"x3"x3 mm SS bh 3.00 3.00 Include
Door closer Dorma TS 68 RA Silver bh 1.00 1.00 Include
B JENDELA
Hardware :
Hinges Gracia BB 4"x3"x3 mm SS bh 4.00 64.00 Include
Rambuncis artt-118 silver bh 2.00 32.00 Include
Cabin hook Gracia art-50 1/8" SS bh 2.00 32.00 Include
Hardware :
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)
Hardware :
Flush handle art-506 SN bh 4.00 24.00 Include
Lockcase Wilka art-1436.30 SN bh 1.00 6.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 6.00 Include
Ring kunci art-901 CK SS bh 2.00 12.00 Include
Track sliding Calfis SD 100/2mtr btg 1.00 6.00 Include
Cannel Sliding Calfis CL 500/2mtr btg 1.00 6.00 Include
Bracket BK 110 btg 6.00 36.00 Include
Roda sliding Calfis pack 120 (100kg)
Terdiri dari :
- Hanger HW111 (2pcs)
- Track buffer with retained ST 112 (1Pcs)
- Floor Guide FG 115 (1Pcs)
Hardware :
Hinges Gracia BB 4"x3"x3 mm SS bh 3.00 9.00 Include
Rambuncis artt-118 silver bh 1.00 3.00 Include
Cabin hook Gracia art-50 1/8" SS bh 1.00 3.00 Include
FLOOR HARDENER
PAVING BLOCK
Lantai 1
- Tangga m' 16.30 - 150,610 2,454,943.00 -
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
B Beton exposed aci halus finish cat interior ex.Jotun tipe standar, termasuk
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
dengan spesifikasi dan gambar pada :
c Listplank GRC Cetak finishing cat Weathershield setara ex. ICI / Jotun,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :
1 Sanitary by Interior
-
DAFTAR No. IV.2 - PEKERJAAN ARSITEKTUR EQUINE CLINIC Vol Vol (+/-) Harsat Rp Rp (+/-)
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
1 Cermin
Kaca cermin tebal 5mm, lengkap lapisan belakang dari multiplek tebal 12
mm, berikut sealant, bracket, dll termasuk alat-alat bantu lainnya dengan
peralatan dan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :
- Toilet dokter 1 (uk. 800x1550 mm) unit 1.00 - 1,590,601 1,590,601 -
2 Meja Beton
Meja Beton tebal 180mm lapis keramik, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :(provisional)
Lantai 1
- Toilet dokter 1 (uk. 1050x500 mm) unit 1.00 - 466,520 466,520 -
- Toilet 2 umum (uk. 1000x470 mm) unit 1.00 - 466,520 466,520 -
3 Tanggulan
Tanggulan Closet tinggi 900 mm, tebal 100 mm lapis keramik, sesuai
gambar
Lantai 1dan spesifikasi pada :
- Toilet dokter 1 m' 1.05 - 457,365 480,233 -
- Toilet 2 umum m' 1.20 - 457,365 548,838 -
4 Groove (Provisional)
Cutter Grove uk. 10x10 mm termasuk gutter 50x30 mm terpasang sesuai
gambar dan spesifikasi pada :
Lantai 1
- Groove ramp m2 16.87 - 26,120 440,644 -
5 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material bantu
dan kelengkapan lainnya, sesuai spesifkasi & gambar pada:
(Provisional)
- Lantai Atap m2 344.44 - 198,663 68,427,434 -
6 PERLENGKAPAN
Tempat minum kuda, sesuai gambar dan spesifikasi pada :
Lantai 1
- Sick Horse bh 5.00 - 237,872 1,189,362 -
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.
IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.
VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail
A GRC
Rib cetak GRC finishing cat Acrylic Emultion berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar pada :
(Provisional)
- Dinding samping m2 150.52 - 686,690 103,360,579 -
B CAT WEATHERSHILED
Finishing cat weathershiled berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :
D CAT KAMPROT
Cat Kamprot berikut alat bantu dengan peralatan perlengkapan sesuai
dengan spesifikasi dan gambar pada :
- Lantai 1
- Vet Room m2 54.20 (2.09) 18,920 1,025,517 (39,634)
- Medicine Storage m2 26.39 (3.09) 18,920 499,337 (58,501)
- Toilet 1 Dokter m2 8.24 (5.15) 18,920 155,901 (97,438)
- Toilet 2 Umum m2 6.52 (2.52) 18,920 123,298 (47,694)
HOMOGENEOUS TILE
WATER PROOFING
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
A G, Gypsum Board, setara ex. Jaya Board, tebal 9mm tinggi plafond h=
2700mm dengan rangka hollow 40x40mm tebal 6 mm dan 40x20mm
tebal 6 mm termasuk cat finish Acrylic emulsion brilliant white setara ex
pentalite dulux, ICI dan alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai spesifikasi dan gambar pada : (reff.gbr :
INT-1101 & INT-2102)
G, Gypsum Water resistant Board tebal 9mm, setara ex. Jaya Board,
tinggi plafond h= 2700mm dengan rangka hollow 40x40mm tebal 6 mm
dan 40x20mm tebal 6 mm termasuk cat finish Acrylic emulsion brilliant
white setara ex pentalite dulux, ICI dan alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1101 & INT-2102)
G, Gypsum Water resistant Board tebal 9mm , setara ex. Jaya Board,
tinggi plafond h= 2550mm dengan rangka hollow 40x40mm tebal 6 mm
dan 40x20mm tebal 6 mm termasuk cat finish Acrylic emulsion brilliant
white setara ex pentalite dulux, ICI dan alat bantu lainnya dengan
peralatan perlengkapan terpasang sesuai spesifikasi dan gambar pada :
(reff.gbr : INT-1101 & INT-2102)
Drop Panel Ceilling 01, Gypsum Water resistant Board 9mm setara ex.
Jaya Board, tinggi h= 150mm dengan rangka hollow termasuk alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (reff.gbr : INT- 1101 & INT-2102)
- Toilet 1 Dokter m' 2.25 (0.88) 116,861 262,936 (102,837)
- Toilet 2 Umum m' 1.17 1.08 116,861 136,727 126,209
Toilet 1 Dokter
Toilet Umum
C1, Kursi Kerja Type S 220 LB slim series black ex. Morelli
atau setara, uk panjang 450mm x lebar 450mm x tinggi 610mm,
Mesh back foam seat fabric upholstery ex Ateja atau setara
terpasang sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-
3102 )
5 - R Kerja unit 1 1,028,372 1,028,372 -
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.186
32 mm 6.313
Monitoring lapangan :
Ukuran 250 x 250 mm, 4D13 U-40, stirup Ø5 -75 pada atas dan
bawah, stirup Ø5 -150 pada tengah
kedalaman pemancangan = 11 m' m' 2,123 155,814 330,793,130 -
Jumlah titik pemancangan = 193 titik
Sambungan tiang pancang ukuran 250 x 250 mm nos 193 Rate only
- -
Note : Kedalaman tiang pancang 11 m'
D PEK. DOLLY
Pekerjaan Dolly tiang pancang ukuran 250 x 250 mm, dengan titik 193 Rate only
kedalaman = 2 ~ 3 m' - -
Test beban pancang + PDA (Pile Driving Analysis) test ttk 2.00 7,790,700
15,581,400 -
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat
kerja
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu
dan kelengkapannya pada:
- Pile Cap m3 123.77 - 55,640 6,886,803 -
- Tie Beam m3 64.32 94.58 55,640 3,578,934 5,262,470
- Bio Tank Pada :
Zoning Dormitory 1 m3 51.60 55,640 2,871,024 -
Zoning Dormitory 2 m3 51.60 55,640 2,871,024 -
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai, Tie Beam m3 7.68 2.22 272,340 2,090,443 604,944
- Pile Cap m3 9.40 0.21 272,340 2,559,940 56,627
- Bio Tank Pada :
Zoning Dormitory 1 m3 1.66 272,340 452,057 -
Zoning Dormitory 2 m3 1.66 272,340 452,057 -
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam m3 76.76 (27.27) 667,780 51,257,841 (18,212,284)
2) Pile cap m3 94.00 (89.19) 667,780 62,769,955 (59,562,032)
8) Bio Tank Pada :
- Zoning Dormitory 1 m3 0.83 667,780 554,224 -
- Zoning Dormitory 2 m3 0.83 667,780 554,224 -
4) Balok, pada:
- Lantai 2 m3 49.69 5.49 782,410 38,876,126 4,291,689
- Lantai 3 m3 49.69 5.49 782,410 38,876,126 4,291,689
- Lantai 4 m3 49.69 5.25 782,410 38,876,126 4,105,468
- Lantai Atap m3 50.11 10.76 782,410 39,203,076 8,415,932
6) Kolom, pada:
- Lantai 1 m3 20.87 (2.63) 782,410 16,331,205 (2,060,046)
- Lantai 2 m3 20.87 (3.21) 782,410 16,331,205 (2,510,715)
- Lantai 3 m3 20.87 (5.09) 782,410 16,331,205 (3,979,142)
- Lantai 4 m3 20.87 (5.09) 782,410 16,331,205 (3,979,142)
PEKERJAAN PEMBESIAN
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pile cap kg 18,974.37 (6,682.08) 8,859 168,084,458 (59,193,235)
2) Tie beam kg 9,270.81 8,959.29 8,859 82,125,454 79,365,900
3) Pelat, pada:
- Lantai 1 kg 13,935.96 2,098.14 8,859 123,451,699 18,586,330
- Lantai 2 kg 8,535.21 (581.59) 8,859 75,609,163 (5,152,034)
- Lantai 3 kg 8,535.21 (581.59) 8,859 75,609,163 (5,152,034)
- Lantai 4 kg 8,535.21 (615.90) 8,859 75,609,163 (5,455,979)
- Lantai Atap kg 11,367.39 (968.69) 8,859 100,698,050 (8,581,161)
4) Balok, pada:
- Lantai 2 kg 14,136.37 4,811.95 8,859 125,227,010 42,626,698
- Lantai 3 kg 14,136.37 4,811.95 8,859 125,227,010 42,626,698
- Lantai 4 kg 14,136.37 4,730.21 8,859 125,227,010 41,902,595
- Lantai Atap kg 14,358.25 6,543.91 8,859 127,192,519 57,969,203
Lantai 1
- Tangga as 16-17 / C-D kg 701.34 - 8,859 6,212,779 -
- Tangga as 0-1 / C-D kg 701.34 - 8,859 6,212,779 -
Lantai 2
- Tangga as 16-17 / C-D kg 701.34 - 8,859 6,212,779 -
- Tangga as 0-1 / C-D kg 701.34 - 8,859 6,212,779 -
6) Kolom, pada:
- Lantai 1 kg 5,102.80 1,857.33 8,859 45,203,140 16,453,181
- Lantai 2 kg 5,102.80 (165.47) 8,859 45,203,140 (1,465,817)
- Lantai 3 kg 5,102.80 (379.82) 8,859 45,203,140 (3,364,607)
- Lantai 4 kg 5,102.80 (979.66) 8,859 45,203,140 (8,678,304)
2) Kolom, pada:
- Lantai 1 m2 208.44 (13.50) 129,920 27,080,525 (1,753,920)
- Lantai 2 m2 208.44 (19.66) 129,920 27,080,525 (2,553,708)
- Lantai 3 m2 208.44 (31.80) 129,920 27,080,525 (4,131,456)
- Lantai 4 m2 208.44 (31.80) 129,920 27,080,525 (4,131,456)
1) lantai atap
- Atap + Atap Tangga m2 950.20 - 160,780 152,773,838 -
I
Harga satuan atap sudah termasuk semua hal yang diperlukan, seperti :
pengelasan, pembuatan lubang-lubang baut, perapihan dengan gerinda,
penyediaan peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)
I Tangga baja
1) WF 250 x 125 x 6 x 9 Kg 284.16 18,364 5,218,256 -
2) HB 150 x 150 x 7 x 10 Kg 78.75 18,364 1,446,149 -
3) Plate 6 mm Kg 49.13 17,807 874,890 -
4) Base Plate 12 mm Kg 12.26 17,807 218,320 -
5) Plate 9 mm Kg 46.73 17,807 832,224 -
6) Stifner 9 mm Kg 14.20 17,807 252,875 -
7) Plate 12 mm Kg 1,133.93 17,807 20,192,293 -
8) Angkur M16 L = 500mm Bh 18.00 222,591 4,006,646 -
9) Baut M16 Bh 18.00 31,163 560,930 -
10) Nonshrink Grout, T = 25 mm, Uk 190 x 190mm titik 1.00 38,954 38,954 -
10) Nonshrink Grout, T = 25 mm, Uk 600 x 200mm titik 1.00 66,777 66,777 -
11) Nonshrink Grout, T = 25 mm, Uk 310 x 200mm titik 1.00 44,518 44,518 -
12) Cat Dasar (Zincromate) Kg 192.00 3,339 641,063 -
13) Cat Finish Kg 192.00 3,339 641,063
II
Harga satuan plesteran biasa atau drymix sudah termasuk acian,
skonengan, tali air , ketrikan atau bobokan beton maupun bata ,
kawat ayam (jika diperlukan) dan semua pekerjaan bantu yang
berhubungan dengan plesteran. Volume plesteran dan acian
sudah ditambahkan 10cm di atas plafond
- Lantai 1
Living room + bedroom
- Room as A-B/0-1 m2 36.77 0.74 18,360 675,015 13,500
- Room as A-B/1-2 m2 35.99 0.72 18,360 660,715 13,214
- Room as A-B/2-3 m2 35.90 0.72 18,360 659,148 13,183
- Room as A-B/3-4 m2 36.05 0.72 18,360 661,957 13,239
- Room as A-B/4-5 m2 35.97 0.72 18,360 660,426 13,209
- Room as A-B/5-6 m2 36.05 0.72 18,360 661,957 13,239
- Room as A-B/6-7 m2 36.49 0.73 18,360 669,932 13,399
- Room as C-D/1-2 m2 36.05 0.72 18,360 661,875 13,238
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
- Lantai 2
Living room + bedroom
- Room as A-B/0-1 m2 36.55 0.73 18,360 671,025 13,421
- Room as A-B/1-2 m2 35.68 37.11 18,360 655,056 681,258
- Room as A-B/2-3 m2 35.67 37.10 18,360 654,970 681,168
- Room as A-B/3-4 m2 35.68 0.71 18,360 655,036 13,101
- Room as A-B/4-5 m2 35.68 0.71 18,360 655,036 13,101
- Room as A-B/5-6 m2 35.68 0.71 18,360 655,032 13,101
- Room as A-B/6-7 m2 36.11 0.72 18,360 662,973 13,259
- Room as A-B/12-13 m2 35.68 0.71 18,360 655,065 13,101
- Room as A-B/13-14 m2 35.68 0.71 18,360 655,022 13,100
- Room as A-B/14-15 m2 35.68 0.71 18,360 655,023 13,100
- Room as A-B/15-16 m2 35.68 0.71 18,360 655,022 13,100
- Room as A-B/16-17 m2 36.55 0.73 18,360 670,968 13,419
- Room as C-D/1-2 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/2-3 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/3-4 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/4-5 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/5-6 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/6-7 m2 36.11 0.72 18,360 663,022 13,260
- Room as C-D/10-11 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/11-12 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/12-13 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/13-14 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/14-15 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/15-16 m2 35.68 0.71 18,360 655,036 13,101
Foyer
- Room as A-B/0-1 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/1-2 m2 12.01 12.49 18,360 220,452 229,270
- Room as A-B/2-3 m2 12.01 12.49 18,360 220,452 229,270
- Room as A-B/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/4-5 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/6-7 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/12-13 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/13-14 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/14-15 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/15-16 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/16-17 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/1-2 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/2-3 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/4-5 m2 12.01 0.24 18,360 220,452 4,409
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
- Lantai 3
Living room + bedroom
- Room as A-B/0-1 m2 36.55 0.73 18,360 671,025 13,421
- Room as A-B/1-2 m2 35.68 37.11 18,360 655,056 681,258
- Room as A-B/2-3 m2 35.67 37.10 18,360 654,970 681,168
- Room as A-B/3-4 m2 35.68 0.71 18,360 655,036 13,101
- Room as A-B/4-5 m2 35.68 0.71 18,360 655,036 13,101
- Room as A-B/5-6 m2 35.68 0.71 18,360 655,032 13,101
- Room as A-B/6-7 m2 36.11 0.72 18,360 662,973 13,259
- Room as A-B/12-13 m2 35.68 0.71 18,360 655,065 13,101
- Room as A-B/13-14 m2 35.68 0.71 18,360 655,022 13,100
- Room as A-B/14-15 m2 35.68 0.71 18,360 655,023 13,100
- Room as A-B/15-16 m2 35.68 0.71 18,360 655,022 13,100
- Room as A-B/16-17 m2 36.55 0.73 18,360 670,968 13,419
- Room as C-D/1-2 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/2-3 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/3-4 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/4-5 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/5-6 m2 35.68 0.71 18,360 655,014 13,100
- Room as C-D/6-7 m2 36.11 0.72 18,360 663,022 13,260
- Room as C-D/10-11 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/11-12 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/12-13 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/13-14 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/14-15 m2 35.68 0.71 18,360 655,036 13,101
- Room as C-D/15-16 m2 35.68 0.71 18,360 655,036 13,101
Foyer
- Room as A-B/0-1 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/1-2 m2 12.01 12.49 18,360 220,452 229,270
- Room as A-B/2-3 m2 12.01 12.49 18,360 220,452 229,270
- Room as A-B/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/4-5 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/6-7 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/12-13 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/13-14 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/14-15 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/15-16 m2 12.01 0.24 18,360 220,452 4,409
- Room as A-B/16-17 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/1-2 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/2-3 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/3-4 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/4-5 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/5-6 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/6-7 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/10-11 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/11-12 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/12-13 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/13-14 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/14-15 m2 12.01 0.24 18,360 220,452 4,409
- Room as C-D/15-16 m2 12.01 0.24 18,360 220,452 4,409
Ruang panel m2 32.86 0.66 18,360 603,339 12,067
Lobby Lift m2 13.46 (13.46) 18,360 247,194 (247,194)
Lounge m2 27.33 (27.33) 18,360 501,724 (501,724)
Koridor m2 214.36 (13.66) 18,360 3,935,599 (250,747)
Void m2 38.49 11.37 18,360 706,633 208,723
- Lantai 4
Living room + bedroom
- Room as A-B/0-1 m2 36.55 0.73 18,360 671,025 13,421
- Room as A-B/1-2 m2 35.68 37.11 18,360 655,056 681,258
- Room as A-B/2-3 m2 35.67 37.10 18,360 654,970 681,168
- Room as A-B/3-4 m2 35.68 0.71 18,360 655,036 13,101
- Room as A-B/4-5 m2 35.68 0.71 18,360 655,036 13,101
- Lantai 1
Fire Stairs As. 00-01 m2 72.73 (12.00) 33,390 2,428,538 (400,767)
Fire Stairs As. 16-17 m2 76.41 (17.31) 33,390 2,551,213 (577,984)
- Lantai 2
Fire Stairs As. 00-01 m2 72.73 (12.00) 33,390 2,428,538 (400,767)
Fire Stairs As. 16-17 m2 76.41 (17.31) 33,390 2,551,213 (577,984)
- Lantai 3
Fire Stairs As. 00-01 m2 72.73 (12.00) 33,390 2,428,538 (400,767)
Fire Stairs As. 16-17 m2 76.41 (17.31) 33,390 2,551,213 (577,984)
- Lantai 4
Fire Stairs As. 00-01 m2 72.73 (12.00) 33,390 2,428,538 (400,767)
Fire Stairs As. 16-17 m2 76.41 (17.31) 33,390 2,551,213 (577,984)
A PINTU BAJA
Pintu Baja P10 terdiri dari 1 daun pintu ukuran 2200x4300mm
kusen besi finish powder coating + kaca tebal kaca 6 mm, fire
rated 2 hours, lengkap terpasang termasuk, hardware,
Fire stair
- Lantai 1 unit 2.00 - 10,127,910 20,255,820 -
Hardware :
Lockset Wilka Art - 8379/855 HF BKSS set 1.00 1.00 Include
Hinges gracia BB 4,5"x4"x3 mm SS bh 3.00 3.00 Include
Door closer dorma TS 300 EN 4 RA silver bh 1.00 1.00 Include
Pintu Baja PS1 terdiri dari 1 daun pintu ukuran 500x1200 mm,
kusen besi finish powder coating, lengkap terpasang termasuk,
hardware,
Shaft accesories dan perlengkapan bantu lainnya sesuai
- Lantai 1 unit 15.00 (15.00) 4,173,589 62,603,841 (62,603,841)
- Lantai 2 unit 15.00 (15.00) 4,173,589 62,603,841 (62,603,841)
- Lantai 3 unit 15.00 (15.00) 4,173,589 62,603,841 (62,603,841)
- Lantai 4 unit 15.00 (15.00) 4,173,589 62,603,841 (62,603,841)
Hardware :
Ring handle art-8-3 SS bh 1.00 (1.00) Include
Shaft door art -542 Nickel bh 1.00 (1.00) Include
Anak kunci shaft door art-543 Nickel bh 1.00 (1.00) Include
Hinges Gracia BB 4"x3"x3 mm SS bh 2.00 (2.00) Include
B PINTU KACA
Pintu Kaca P1 terdiri dari 1 pintu dan 2 daun pintu Stainless
Panel Patch, ukuran 7200x6060, Kaca Tempered 12mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan
Main Entrance
- Lantai 1 unit 1.00 - 34,888,883 34,888,883 -
Hardware :
Pull handle art-243/600 mm SS psg 2.00 - Include
Patch fitting Dorma PT10,PT20 US 10 + Cylinder set 2.00 - Include
Patch fitting Dorma PT40 bh 2.00 - Include
Floor hinges Dorma BTS 84 T/ Complete SS set 2.00 - Include
Main Entrance
- Lantai 1 unit 2.00 - 8,837,002 17,674,005 -
- Lantai 2 unit 2.00 - 8,837,002 17,674,005 -
- Lantai 3 unit 2.00 - 8,837,002 17,674,005 -
- Lantai 4 unit 2.00 - 8,837,002 17,674,005 -
Hardware :
Lever handle art-352 SS psg 1.00 7.00 Include
Lockcase Wilka art-1438.30 SN + striking plate bh 1.00 7.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 7.00 Include
Hinges Gracia BB 4"x3"x2" mm silver bh 6.00 42.00 Include
Flush bolt Rioby 456/250 mm silver set 1.00 7.00 Include
Door closer Dorma TS 68 RA silver bh 1.00 7.00 Include
C PINTU KAYU
Pintu kayu P3 terdiri dari 1 daun pintu Kusen Alumunium 3" finish
powder coating ukuran 1880x4800, plywood + rangka kayu finish
HPL lengkap terpasang termasuk, hardware, accesories dan
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
Hardware :
Lever handle art-306 SS psg 1.00 7.00 Include
Lockcase Wilka art-1490.55 SN bh 1.00 7.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 7.00 Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 21.00 Include
Door closer Dorma TS 68 RA silver bh 1.00 7.00 Include
Hardware :
Lever handle art-306 SS psg 1.00 3.00 Include
Lockcase Wilka art-1490.55 SN bh 1.00 3.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 3.00 Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 9.00 Include
Door closer Dorma TS 68 RA silver bh 1.00 3.00 Include
Pintu Kayu P5 terdiri dari 1 daun pintu kusen Alumunium 3" finish
powder coating ukuran 1780x4800, plywood + rangka kayu +
lubang
kitchen kaca finish Hpl, tebal kaca 6 mm lengkap terpasang
- Lantai 1 unit 1.00 - 3,839,702 3,839,702 -
Hardware :
Lever handle art-306 SS psg 1.00 - Include
Lockcase Wilka art-1490.55 SN bh 1.00 - Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 - Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 - Include
Door closer Dorma TS 68 RA silver bh 1.00 - Include
Hardware :
Lever handle art-306 SS psg 1.00 - Include
Lockcase Wilka art-1490.55 SN bh 1.00 - Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 - Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 - Include
Flush bolt gracia 200/350 mm SS bh 1.00 - Include
Door closer Dorma TS 68 RA silver bh 1.00 - Include
Pintu Kayu P7 terdiri dari 1 daun pintu kusen Alumunium 3" finish
powder coating ukuran 1780x4800, plywood + rangka kayu finish
Hpl lengkap
kitchen, dry &terpasang termasuk, hardware, accesories dan
cold stroge
- Lantai 1 unit 2.00 - 3,477,991 6,955,982 -
Hardware :
Lever handle art-306 SS psg 1.00 1.00 Include
Lockcase Wilka art-1490.55 SN bh 1.00 1.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 1.00 Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 3.00 Include
Door closer Dorma TS 68 RA silver bh 1.00 1.00 Include
Hardware :
Lever handle art-345 SS psg 1.00 90.00 Include
Lockcase Wilka art-1490.55 SN bh 1.00 90.00 Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 90.00 Include
Hinges Gracia BB 4"x3"x3" mm silver bh 3.00 270.00 Include
Door stopper Dorma art-601 SN bh 1.00 90.00 Include
B JENDELA
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
-
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
1 Hand Railing Pipa besi h=1100mmØ2,5" besi Ø2", termasuk hand railing
dan alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (reff.gbr : GD-AR 2201)
Lantai 1
- Tangga darurat 01 m' 12.73 28.37 278,239 3,541,986 7,893,649
- Tangga darurat 02 m' 12.73 28.37 278,239 3,541,986 7,893,649
- Tangga as 7-8/C-D (Provisional) m' 5.95 - 278,239 1,655,524 -
2 Railing besi pipa Ø12 finish cat hitam, termasuk angkur baut dan alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai
spesifikasi dan gambar pada : (reff.gbr : GD-AR 2202)
Lantai 1
- Tangga as 7-8/C-D m' 59.71 (59.71) 311,629 18,607,385 (18,607,385)
3 Railling Kaca
Railling Kaca Tempered 12mm dan Railing stainless steel 20mm x 60mm
(custom) + Hand Railling Stainless Steel 40mm x 80mm with paint finish
welded & grind smooth tinggi 1000 mm , termasuk angkur baut, sealant
dan kelengkapan lainnya sesuai gambar dan spesifikasi pada :
Lantai 2
- Void m' 8.58 - 3,199,752 27,453,871 -
Lantai 3
- Void m' 10.70 - 3,199,752 34,237,345 -
Lantai 4
- Void m' 10.70 - 3,199,752 34,237,345 -
4 Meja Beton
Meja Beton tebal 100mm lapis black granit, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :(provisional)
Lantai 1
- Guest room (uk. 1100x500 mm) unit 13.00 - 466,520 6,064,760 -
Lantai 2
- Guest room (uk. 1100x500 mm) unit 26.00 - 466,520 12,129,520 -
Lantai 3
- Guest room (uk. 1100x500 mm) unit 26.00 - 466,520 12,129,520 -
Lantai 4
- Guest room (uk. 1100x500 mm) unit 26.00 - 466,520 12,129,520 -
5 Meja Lavatory
Meja Lavatory rangka lapis black granit, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :(provisional)
Lantai 1
- Powder room male (uk. 800x665 mm) unit 1.00 - 1,117,760 1,117,760 -
- Powder room female (uk. 1000x665 mm) unit 1.00 - 1,303,820 1,303,820 -
- Locker male (uk. 2250x890 mm) unit 1.00 - 3,127,830 3,127,830 -
- Locker female (uk. 2250x890 mm) unit 1.00 - 3,127,830 3,127,830 -
6 Tanggulan
Tanggulan Janitor tinggi 300 mm, tebal 145 mm lapis keramik, sesuai
gambar
Lantai 1dan spesifikasi pada :
- Locker male m' 1.70 - 304,910 518,347 -
- Locker female m' 1.78 - 304,910 541,215 -
Tanggulan Urinoir tinggi 1070 mm, tebal 150 mm lapis black granit,
sesuai
Lantaigambar
1 dan spesifikasi pada :
- Locker male m' 1.76 - 457,365 804,962 -
7 Groove (Provisional)
Cutter Grove uk. 10x10 mm termasuk gutter 50x30 mm terpasang sesuai
gambar dan spesifikasi pada :
Lantai 1
- Groove ramp m2 8.89 - 26,120 232,207 -
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
9 Fire
FireStop
Stop(Provisional)
termasuk plat untuk dudukan dan glasswool, insulasi, rangka,
angkur, sealant, material bantu dan perlengkapan lainnya sesuai gambar
dan spesifikasi
Area shaft pada:
- Lantai 1 m2 3.75 - 556,479 2,086,795 -
- Lantai 2 m2 4.08 - 556,479 2,270,433 -
- Lantai 3 m2 4.08 - 556,479 2,270,433 -
- Lantai 4 m2 4.08 - 556,479 2,270,433 -
11 Pasangan Dinding
Pasangan bata ringan, tebal 100 mm dan perekat, adukan kering, kolom
dan balok praktis, sesuai spesifikasi dan gambar pada :
- Trap tangga (Provisional) m2 11.60 - 103,480 1,200,368 -
- Tangga darurat 01 m2 8.63 10.32 103,480 893,032 1,068,328
- Tangga darurat 02 m2 8.63 10.32 103,480 893,032 1,068,328
- Parapet Ramp kiri dan kanan m2 16.39 - 103,480 1,696,037 -
12 Finishing Cat
Cat Interior ex.Jotun Tipe standar, termasuk peralatan dan perlengkapan
sesuai spesifikasi dan gambar pada :
- Trap tangga (Provisional) m2 11.60 - 18,360 212,976 -
Lantai 1
Powder room
- Female toilet m' 0.60 - 343,107 205,864 -
- Male toilet m' 0.60 - 343,107 205,864 -
Locker room
- Female toilet m' 2.25 - 343,107 771,991 -
- Male toilet m' 2.25 - 343,107 771,991 -
14 Cove lampu
Cove lampu lebar 200mm termasuk alat-alat bantu lainnya dengan
peralatan dan perlengkapan terpasang sesuai spesifikasi dan gambar
pada :
Lantai 1
- Guest room m' 43.05 5.70 343,107 14,770,764 1,955,711
Lantai 2
- Guest room m' 86.10 11.40 343,107 29,541,528 3,911,422
Lantai 3
- Guest room m' 86.10 11.40 343,107 29,541,528 3,911,422
Lantai 4
- Guest room m' 86.10 11.40 343,107 29,541,528 3,911,422
15 Jamb Lift
Wide jamb stainless steel hairline (ex local) sesuai spesifikasi dan gambar
pada :
Lantai 1
- lift ( 2 unit) m' 11.17 0.03 389,535 4,351,106 11,686
Lantai 2
- lift ( 2 unit) m' 11.17 0.03 389,535 4,351,106 11,686
Lantai 3
- lift ( 2 unit) m' 11.17 0.03 389,535 4,351,106 11,686
Lantai 4
- lift ( 2 unit) m' 11.17 0.03 389,535 4,351,106 11,686
DAFTAR No. V.2 - PEKERJAAN ARSITEKTUR DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
1 Atap
Roof covering metal roof pada atap, sesuai gambar dan spesifikasi
pada :
- Roof m2 9.86 13.34 681,690 6,721,463 9,093,745
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya.,
rubber gasket (sealant), neoprene, penyetelan dan pemasangan.
B CAT WEATHERSHILED
Cat eksterior ex.Jotun Tipe standar, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :
Exterior
- Lantai 1 m2 490.30 20.91 29,490 14,459,065 616,636
- Lantai 2 m2 455.89 51.91 29,490 13,444,285 1,530,855
- Lantai 3 m2 455.89 51.91 29,490 13,444,285 1,530,855
- Lantai 4 m2 455.89 51.91 29,490 13,444,285 1,530,855
C ALUMUNIUM GRILL
Alumunium Grill berikut alat bantu dengan peralatan perlengkapan
sesuai dengan spesifikasi dan gambar pada :
D TERALIS
Teralis Ac out door berikut alat bantu dengan peralatan perlengkapan
sesuai dengan spesifikasi dan gambar pada :
Lantai 1
- Guest Room unit 13.00 - 6,121,264 79,576,438 -
Lantai 2
- Guest Room unit 26.00 - 6,121,264 159,152,875 -
Lantai 3
- Guest Room unit 26.00 - 6,121,264 159,152,875 -
Lantai 4
- Guest Room unit 26.00 - 6,121,264 159,152,875 -
Lantai 1
- Ruang Ganti & Locker Pria unit 1.00 - 16,694,358 16,694,358 -
- Ruang Ganti & Locker Wanita unit 1.00 - 16,694,358 16,694,358 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
HOMOGENEOUS TILE
Lantai 1
- Guest Room m2 216.15 2.90 1,073,930 232,132,207 3,112,160
- Kamar Mandi Guest Room m2 43.03 0.13 1,073,930 46,211,208 139,611
- Koridor m2 111.21 (111.21) 1,073,930 119,428,573 (119,428,573)
- Drugstore m2 10.34 10.27 1,073,930 11,104,436 11,029,261
- Room m2 20.41 2.46 1,073,930 21,918,911 2,641,868
- Time Keeper & Security Office m2 12.82 (0.02) 1,073,930 13,767,783 (21,479)
- Panel Room m2 4.09 0.12 1,073,930 4,392,374 128,872
- Tangga Kebakaran Kiri m2 20.82 (2.37) 1,073,930 22,359,223 (2,545,214)
- Tangga Tengah m2 9.77 (9.77) 1,073,930 10,496,059 (10,496,059)
- Tangga Kebakaran Kanan m2 20.66 (2.21) 1,073,930 22,187,394 (2,373,385)
- Trap tangga (Provisional) m2 11.60 - 1,073,930 12,457,588 -
- Teras entrance & Ramp (Provisional) m2 29.15 - 1,073,930 31,305,060 -
Lantai 2
- Guest Room m2 434.27 3.83 1,073,930 466,380,526 4,108,207
- Kamar Mandi Guest Room m2 86.06 0.26 1,073,930 92,422,416 279,222
- Koridor m2 83.14 (83.14) 1,073,930 89,286,876 (89,286,876)
- Reception area, Dinning Room m2 68.69 (68.69) 1,073,930 73,766,311 (73,766,311)
- Panel Room m2 4.23 (0.02) 1,073,930 4,542,724 (21,479)
- Tangga Kebakaran Kanan m2 20.49 (2.04) 1,073,930 22,004,826 (2,190,817)
- Tangga Tengah m2 13.80 (13.80) 1,073,930 14,820,234 (14,820,234)
- Tangga Kebakaran Kiri m2 20.56 (2.11) 1,073,930 22,080,001 (2,265,992)
Lantai 3
- Guest Room m2 434.27 3.83 1,073,930 466,380,526 4,108,207
- Kamar Mandi Guest Room m2 86.06 0.26 1,073,930 92,422,416 279,222
- Koridor m2 83.14 (83.14) 1,073,930 89,286,876 (89,286,876)
- Reception area, Dinning Room m2 68.69 (68.69) 1,073,930 73,766,311 (73,766,311)
- Panel Room m2 4.23 (0.02) 1,073,930 4,542,724 (21,479)
- Tangga Kebakaran Kanan m2 20.49 (2.04) 1,073,930 22,004,826 (2,190,817)
- Tangga Tengah m2 13.80 (13.80) 1,073,930 14,820,234 (14,820,234)
- Tangga Kebakaran Kiri m2 20.56 (2.11) 1,073,930 22,080,001 (2,265,992)
Lantai 4
- Guest Room m2 434.27 3.83 1,073,930 466,380,526 4,108,207
- Kamar Mandi Guest Room m2 86.06 0.26 1,073,930 92,422,416 279,222
- Koridor m2 46.08 (46.08) 1,073,930 49,488,372 (49,488,372)
- Reception area, Dinning Room m2 68.69 (68.69) 1,073,930 73,766,311 (73,766,311)
- Panel Room m2 4.23 (0.02) 1,073,930 4,542,724 (21,479)
- Tangga Kebakaran Kanan m2 20.49 (2.04) 1,073,930 22,004,826 (2,190,817)
- Tangga Tengah m2 13.80 (13.80) 1,073,930 14,820,234 (14,820,234)
- Tangga Kebakaran Kiri m2 20.56 (2.11) 1,073,930 22,080,001 (2,265,992)
Lantai 1
- Koridor m2 2.51 2.13 707,870 1,777,196 1,509,261
Lantai 2
- Koridor m2 4.63 (4.63) 707,870 3,278,323 (3,278,323)
Lantai 3
- Koridor m2 4.63 (4.63) 707,870 3,278,323 (3,278,323)
Lantai 4
- Koridor m2 4.63 (4.63) 707,870 3,278,323 (3,278,323)
Lantai 1
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
Lantai 1
- Office Management m2 41.69 (0.01) 507,040 21,138,498 (5,070)
- Kitchen m2 31.33 0.36 507,040 15,885,563 182,534
- Dry Storage m2 4.61 0.10 507,040 2,337,454 50,704
- Cold Storage m2 4.45 0.11 507,040 2,256,328 55,774
- Staf Dinning m2 10.26 (10.26) 507,040 5,202,230 (5,202,230)
- Linen Storage m2 10.11 0.13 507,040 5,126,174 65,915
Lantai 1
- Powder Room Pria m2 2.67 0.01 376,210 1,004,481 3,762
- Powder Room Wanita m2 2.16 - 376,210 812,614 -
Lantai 1
- Men's Locker & Toilet m2 19.71 (0.45) 470,030 9,264,291 (211,514)
- Women's Locker & Toilet m2 19.57 (0.37) 470,030 9,198,487 (173,911)
Lantai 1
- Praying Room/Mushola m2 27.84 (27.84) 228,156 6,351,869 (6,351,869)
Lantai 1
- Guest Room m' 98.67 136.11 40,069 3,953,568 5,453,736
- Koridor m' 113.27 (15.81) 40,069 4,538,570 (633,467)
- Drugstore m' 14.07 3.18 40,069 563,765 127,418
- Room m' 19.82 (1.32) 40,069 794,160 (52,891)
- Time Keeper & Security Office m' 16.69 (0.93) 40,069 668,745 (37,264)
- Panel Room m' 8.58 0.17 40,069 343,789 6,812
- Tangga Kebakaran Kanan (Provisional) m' 20.12 - 40,069 806,180 -
- Tangga Kebakaran Kiri (Provisional) m' 20.42 - 40,069 818,201 -
Lantai 2
- Guest Room m' 475.28 (5.72) 40,069 19,043,977 (229,367)
- Koridor m' 70.41 13.66 40,069 2,821,150 547,417
- Tangga Kebakaran Kanan (Provisional) m' 20.43 - 40,069 818,688 -
- Tangga Kebakaran Kiri (Provisional) m' 20.13 - 40,069 806,668 -
Lantai 3
- Guest Room m' 475.28 (5.72) 40,069 19,043,977 (229,367)
- Koridor m' 70.41 13.66 40,069 2,821,150 547,417
- Tangga Kebakaran Kanan (Provisional) m' 20.43 - 40,069 818,688 -
- Tangga Kebakaran Kiri (Provisional) m' 20.13 - 40,069 806,668 -
Lantai 4
- Guest Room m' 475.28 (5.72) 40,069 19,043,977 (229,367)
- Koridor m' 70.41 13.66 40,069 2,821,150 547,417
- Tangga Kebakaran Kanan (Provisional) m' 20.43 - 40,069 818,688 -
- Tangga Kebakaran Kiri (Provisional) m' 20.13 - 40,069 806,668 -
Lantai 1
- Reception area & Elevator Lobby m' 13.56 (1.89) 27,355 371,025 (51,786)
- Dinning Room & Lounge m' 17.53 (2.45) 27,355 479,413 (66,914)
WATER PROOFING
Lantai 1
- Kamar Mandi Guest Room m2 44.32 - 44,520 1,973,166 -
- Powder Room Pria m2 2.75 - 44,520 122,434 -
- Powder Room Wanita m2 2.22 - 44,520 99,048 -
- Men's Locker & Toilet m2 20.30 - 44,520 903,814 -
- Women's Locker & Toilet m2 20.16 - 44,520 897,394 -
Lantai 2
- Kamar Mandi Guest Room m2 88.64 - 44,520 3,946,333 -
Lantai 3
- Kamar Mandi Guest Room m2 88.64 - 44,520 3,946,333 -
Lantai 4
- Kamar Mandi Guest Room m2 88.64 - 44,520 3,946,333 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
I Harga satuan pekerjaan plafond sudah termasuk rangka, extra rangka pada
pertemuannya dengan kolom, balok, dinding dan lubang equipment M/E
(lampu, grill AC, dll.)
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant dan
telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII
Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow Line
C1, Gypsum Board, setara ex. Jaya Board, tebal 9mm dengan rangka
hollow 40x40mm tebal 6 mm dan 40x20mm tebal 6 mm termasuk cat finish
Acrylic emulsion brilliant white setara ex pentalite dulux, ICI dan alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr :AR06)
Lantai 1
- Guest Room m2 215.39 1.45 124,090 26,728,100 179,576
- Koridor m2 111.21 (33.00) 124,090 13,799,681 (4,095,248)
- Drugstore m2 10.34 10.27 124,090 1,283,091 1,274,404
- Room m2 20.41 (5.59) 124,090 2,532,677 (693,663)
- Time Keeper & Security Office m2 12.82 (0.02) 124,090 1,590,834 (2,482)
- Panel Room m2 4.09 (0.01) 124,090 507,528 (1,241)
- Reception area & Elevator Lobby m2 59.60 (11.94) 124,090 7,395,609 (1,482,050)
- Dinning Room & Lounge m2 85.97 (17.23) 124,090 10,668,426 (2,137,909)
- Office Management m2 41.69 (0.15) 124,090 5,173,312 (18,613)
- Kitchen m2 31.33 (0.03) 124,090 3,887,740 (3,723)
- Dry Storage m2 4.61 (0.03) 124,090 572,055 (3,723)
- Cold Storage m2 4.45 (0.02) 124,090 552,201 (2,482)
- Staf Dinning m2 10.26 (3.04) 124,090 1,273,163 (377,829)
- Linen Storage m2 10.11 (0.01) 124,090 1,254,550 (1,241)
- Praying Room/Mushola m2 27.84 (0.24) 124,090 3,454,666 (29,782)
Lantai 2
- Guest Room m2 430.79 2.89 124,090 53,456,200 359,152
- Koridor m2 87.77 0.15 124,090 10,891,573 18,420
- Reception area, Dinning Room m2 116.16 (116.16) 124,090 14,414,288 (14,414,288)
- Panel Room m2 4.23 (0.15) 124,090 524,901 (18,614)
- Tangga Kanan m2 20.49 (20.49) 124,090 2,542,604 (2,542,604)
- Tangga Tengah m2 13.80 (13.80) 124,090 1,712,442 (1,712,442)
- Tangga Kiri m2 20.56 (20.56) 124,090 2,551,290 (2,551,290)
Lantai 3
- Guest Room m2 430.79 2.89 124,090 53,456,200 359,152
- Koridor m2 87.77 0.15 124,090 10,891,573 18,420
- Reception area, Dinning Room m2 116.16 (116.16) 124,090 14,414,288 (14,414,288)
- Panel Room m2 4.23 (0.15) 124,090 524,901 (18,614)
- Tangga Kanan m2 20.49 (20.49) 124,090 2,542,604 (2,542,604)
- Tangga Tengah m2 13.80 (13.80) 124,090 1,712,442 (1,712,442)
- Tangga Kiri m2 20.56 (20.56) 124,090 2,551,290 (2,551,290)
Lantai 4
- Guest Room m2 430.79 2.89 124,090 53,456,200 359,152
- Koridor m2 87.77 0.15 124,090 10,891,573 18,420
C1, Gypsum Board, setara ex. Jaya Board, tebal 9mm dengan rangka
hollow 40x40mm tebal 6 mm dan 40x20mm tebal 6 mm termasuk cat finish
Acrylic emulsion brilliant white setara ex pentalite dulux, ICI dan alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr :AR06)-Lanjutan
Lantai 4
- Reception area, Dinning Room m2 116.16 (116.16) 124,090 14,414,288 (14,414,288)
- Panel Room m2 4.23 (0.15) 124,090 524,901 (18,614)
- Tangga Kanan m2 20.49 (20.49) 124,090 2,542,604 (2,542,604)
- Tangga Tengah m2 13.80 (13.80) 124,090 1,712,442 (1,712,442)
- Tangga Kiri m2 20.56 (20.56) 124,090 2,551,290 (2,551,290)
C4, Gypsum Water resistant , setara ex. Jaya Board, tebal 9mm dengan
rangka hollow 40x40mm tebal 6 mm dan 40x20mm tebal 6 mm termasuk cat
finish Acrylic emulsion brilliant white setara ex pentalite dulux, ICI dan alat
bantu lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada : (reff.gbr : AR06 )
Lantai 1
- Kamar Mandi Guest Room m2 41.37 1.79 150,250 6,216,218 268,572
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
Lantai 2
- Kamar Mandi Guest Room m2 82.75 3.57 150,250 12,432,436 537,144
Lantai 3
- Kamar Mandi Guest Room m2 82.75 3.57 150,250 12,432,436 537,144
Lantai 4
- Kamar Mandi Guest Room m2 82.75 3.57 150,250 12,432,436 537,144
Drop Panel Ceilling 01, Gypsumboard 9mm setara ex. Jaya Board, tinggi
h= 100mm dengan rangka hollow galvanis termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (reff.gbr : AR06)
Lantai 1
- Koridor m' 45.37 0.24 100,166 4,544,738 23,840
- Powder Room m' 1.75 4.65 100,166 175,291 465,773
- Powder Room 1 m' 1.10 5.30 100,166 110,183 530,881
Lantai 2
- Koridor m' 74.03 (19.94) 100,166 7,415,099 (1,997,113)
Lantai 3
- Koridor m' 74.03 (19.94) 100,166 7,415,099 (1,997,113)
Lantai 4
- Koridor m' 74.03 (19.94) 100,166 7,415,099 (1,997,113)
Drop Panel Ceilling 01, Gypsum Water Resistant 9mm setara ex. Jaya
Board, tinggi h= 100mm dengan rangka hollow galvanis termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : AR06)
Lantai 1
- Kamar Mandi Guest Room m' 55.25 47.58 105,731 5,841,634 5,030,678
- Reception area, Dinning Room m' 49.25 (49.25) 105,731 5,207,248 (5,207,248)
Lantai 2
- Kamar Mandi Guest Room m' 110.50 95.16 105,731 11,683,268 10,061,355
- Reception area, Dinning Room m' 35.75 (35.75) 105,731 3,779,352 (3,779,352)
Lantai 3
- Kamar Mandi Guest Room m' 110.50 95.16 105,731 11,683,268 10,061,355
- Reception area, Dinning Room m' 35.75 (35.75) 105,731 3,779,352 (3,779,352)
Lantai 4
- Kamar Mandi Guest Room m' 110.50 95.16 105,731 11,683,268 10,061,355
- Reception area, Dinning Room m' 35.75 (35.75) 105,731 3,779,352 (3,779,352)
Drop Panel Ceilling 01, Gypsumboard 9mm setara ex. Jaya Board, tinggi
h= 200mm dengan rangka hollow galvanis termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan gambar
pada : (reff.gbr : AR06)
Lantai 1
- Guest Room m' 43.05 5.70 100,166 4,312,273 570,827
Lantai 2
- Guest Room m' 86.10 11.40 100,166 8,624,545 1,141,654
Lantai 3
- Guest Room m' 86.10 11.40 100,166 8,624,545 1,141,654
Lantai 4
- Guest Room m' 86.10 11.40 100,166 8,624,545 1,141,654
Drop Panel Ceilling 01, Gypsumboard 9mm setara ex. Jaya Board, tinggi
h= 100mm + 100mm dengan rangka hollow galvanis termasuk alat bantu
lainnya dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (reff.gbr : GD-INT 3102)
Lantai 1
- Guest Room m' 30.55 - 100,166 3,060,076 -
Lantai 2
- Guest Room m' 61.10 - 100,166 6,120,151 -
Lantai 3
- Guest Room m' 61.10 - 100,166 6,120,151 -
Lantai 4
- Guest Room m' 61.10 - 100,166 6,120,151 -
Shadow line, Gypsumboard ex. Jaya Board atau setara, lebar 20mm
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (reff.gbr : GD-INT 3102)-Provisional
Lantai 1
- Guest Room m' 257.79 - 19,480 5,021,749 -
Lantai 2
- Guest Room m' 515.58 - 19,480 10,043,498 -
Lantai 3
- Guest Room m' 515.58 - 19,480 10,043,498 -
Lantai 4
- Guest Room m' 515.58 - 19,480 10,043,498 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY Vol Vol (+/-) Harsat Rp Rp (+/-)
Lantai 1
Guest Room
- Robe Hook ex. TOTO (provisional) bh 3.00 (1.00) 186,400 559,200 (186,400)
- Soap Holder ex. TOTO (provisional) bh 1.00 - 102,210 102,210 -
- Kran wudhu ex. TOTO (provisional) bh 2.00 1.00 492,080 984,160 492,080
Lantai 2
Guest Room
Lantai 3
Guest Room
Lantai 4
Guest Room
WALL DECORATIVE
Lantai 1
- Guest Room unit 13.00 9,603,429 124,844,579 -
Lantai 2
- Guest Room unit 26.00 9,603,429 249,689,158 -
Lantai 3
- Guest Room unit 26.00 9,603,429 249,689,158 -
Lantai 4
- Guest Room unit 26.00 9,603,429 249,689,158 -
III Harga satuan Backdrop dinding panel HPL sudah termasuk rangka,
penyesuaian pola permukaan, bahan terbuang, biaya pengeringan
kayu, anti rayap, penyambungan dan finishing
BED, Kasur ex. Chantique atau setara , termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada : (Reff.Gbr : AR03)
Lantai 1
- Guest Room unit 26.00 - 2,671,097 69,448,527 -
Lantai 2
- Guest Room unit 52.00 - 2,671,097 138,897,055 -
Lantai 3
- Guest Room unit 52.00 - 2,671,097 138,897,055 -
Lantai 4
- Guest Room unit 52.00 - 2,671,097 138,897,055 -
C9, Kursi Single hitam/Lime greenType Slim Aime ex. Ikons atau
setara, dengan peralatan perlengkapan terpasang sesuai spesifikasi
dan gambar pada : (Reff.gbr : AR03)
Lantai 1
- Guest Room unit 13.00 - 1,402,326 18,230,238 -
Lantai 2
- Guest Room unit 26.00 - 1,402,326 36,460,477 -
Lantai 3
- Guest Room unit 26.00 - 1,402,326 36,460,477 -
Lantai 4
- Guest Room unit 26.00 - 1,402,326 36,460,477 -
Lantai 1
- Meja Reception unit 1.00 - 3,305,483 3,305,483 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY sat. volume vol +/- H. Satuan Jumlah Harga Jumlah Harga
Rp. Rp. (+/-)
DAFTAR NO. V.3.7. - PEKERJAAN LOOSE FURNITURE
C1, Kursi Kerja Penerima Type Winona Black / Lime green, ex.
Ikons atau setara, uk panjang 410mm x lebar 510mm x tinggi 690mm,
termasuk Mahogany wood chair stain finish fabric cushions include
sesuai spesifikasi dan gambar pada : (Reff.gbr : INT-1103 )
Lantai 1
- R Penerima Lobby unit 1.00 1.00 734,552 734,552 734,552
T2, Dinning Table, uk. 1200mm x 800mm, Top Table plywood 40mm
finish HPL dan powder coated steel pipe Ø2,5", dan besi Ø3/4"
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR03 & F01)
Lantai 1
- Dinning Table unit 3.00 (1.00) 1,936,545 5,809,636 (1,936,545)
Lantai 1
- Dinning Table unit 8.00 - 1,936,545 15,492,364 -
Lantai 1
- Dinning Room unit 60.00 - 1,402,326 84,139,562 -
Lantai 2
- Lounge unit 6.00 - 1,402,326 8,413,956 -
Lantai 1
- Office Management unit 4.00 - 591,314 2,365,257 -
Lantai 1
- Office Management unit 1.00 - 2,126,861 2,126,861 -
Lantai 1
- Office Management unit 6.00 - 9,025,637 54,153,825 -
- time keeper unit 2.00 - 9,025,637 18,051,275 -
Lantai 1
- Office Management unit 1.00 - 23,238,546 23,238,546 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY sat. volume vol +/- H. Satuan Jumlah Harga Jumlah Harga
Rp. Rp. (+/-)
DAFTAR NO. V.3.7. - PEKERJAAN LOOSE FURNITURE
PR1, Devider, uk 1500mmx200mm x tinggi 2900mm, Portal Devider
Plywood finish HPL dan Jalusi devider Alumunium finish natural,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR03 & F04)
Lantai 1
- Office Management unit 1.00 - 8,714,455 8,714,455 -
Lantai 1
- Office Management unit 1.00 - 771,279 771,279 -
Lantai 1
- Office Management unit 2.00 - 1,355,582 2,711,164 -
Lantai 1
- Office Management unit 1.00 - 590,980 590,980 -
Lantai 1
- Office Management unit 6.00 - 677,791 4,066,745 -
- Security Office & Time keeper unit 3.00 - 677,791 2,033,373 -
CT1
C2, Kursi Single Type Winona, uk diameter 510mm x 410mm x
690mm, Ex Ikons atau setara, Mahogany wood chair stain finish,
Fabric cushins include dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada : (Reff.gbr : AR02 & F02)
Lantai 1
- Dinning Staff unit 6.00 - 1,402,326 8,413,956 -
Lantai 2
- Lounge unit 6.00 - 1,402,326 8,413,956 -
Lantai 2
- Lounge unit 1.00 - 2,136,878 2,136,878 -
Lantai 2
- Lounge unit 1.00 - 3,472,426 3,472,426 -
Lantai 2
- Lounge unit 1.00 - 4,006,646 4,006,646 -
Lantai 1
- Ruang Ganti & Locker wanita unit 1.00 - 4,140,201 4,140,201 -
DAFTAR No. V.4 - PEKERJAAN ARSITEKTUR GROOM DORMITORY sat. volume vol +/- H. Satuan Jumlah Harga Jumlah Harga
Rp. Rp. (+/-)
DAFTAR NO. V.3.7. - PEKERJAAN LOOSE FURNITURE
Lantai 1
- Ruang Ganti & Locker pria unit 1.00 - 4,340,533 4,340,533 -
- Ruang Ganti & Locker wanita unit 1.00 - 4,340,533 4,340,533 -
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.186
32 mm 6.313
Monitoring lapangan :
D PEK. DOLLY
Pekerjaan Dolly tiang pancang ukuran 250 x 250 mm, dengan titik 54 Rate only
kedalaman = 2 ~ 3 m' - -
Test beban pancang + PDA (Pile Driving Analysis) test ttk 1.00 7,790,700
7,790,700 -
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pile Cap m3 25.24 (9.17) 55,640 1,404,628 (510,224)
- Tie Beam m3 74.45 (3.65) 55,640 4,142,612 (203,097)
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai inc Tie Beam m3 8.66 (8.66) 272,340 2,357,239 (2,357,239)
- Pile Cap m3 2.09 (0.37) 272,340 569,191 (101,038)
Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam, termasuk GWT m3 86.56 (49.22) 667,780 57,799,698 (32,865,001)
2) Pile cap m3 1.04 (0.18) 667,780 694,491 (120,534)
4) Balok, pada:
- Lantai 2 m3 22.79 (1.18) 782,410 17,831,124 (919,527)
6) Kolom, pada:
- Lantai 1 m3 12.78 (0.71) 782,410 9,996,383 (553,477)
PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada:
- Lantai 1 m2 788.40 (41.61) 53,220 41,958,648 (2,214,285)
3) Pelat, pada:
- Lantai 1 kg 4,383.39 560.30 8,859 38,830,249 4,963,406
- Lantai atap kg 3,227.53 783.85 8,859 28,591,107 6,943,773
4) Balok, pada:
- Lantai 2 kg 5,485.09 124.62 8,859 48,589,670 1,103,977
6) Kolom, pada:
- Lantai 1 kg 1,954.75 133.61 8,859 17,316,168 1,183,562
2) Kolom, pada:
- Lantai 1 m2 170.35 (9.43) 129,920 22,132,132 (1,225,405)
1) lantai atap
- Atap m2 312.83 - 127,690 39,945,263 -
I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-
lubang baut, perapihan dengan gerinda, penyediaan
peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)
I Canopy Atap
1) WF 250 x 125 x 6 x 9 Kg 87.35 18,364 1,604,070 -
2) WF 200 x 100 x 5,5 x 8 Kg 5,040.90 18,364 92,569,972 -
3) CNP 150 x 50 x 20 x 2,3 Kg 4,291.20 18,364 78,802,710 -
4) L 50 x 50 x 5 Kg 1,503.45 18,364 27,609,045 -
5) HB 200 x 200 x 8 x 12 Kg 1,528.30 18,364 28,065,400 -
6) Plate T = 6 mm Kg 169.73 17,807 3,022,428 -
7) Plate T = 8 mm Kg 80.25 17,807 1,428,963 -
8) Plate T = 10 mm Kg 82.86 17,807 1,475,596 -
9) Plate T = 12 mm Kg 982.77 17,807 17,500,423 -
10) Baut Diameter M 12 mm bh 390.00 31,163 12,153,492 -
11) Baut Diameter M 16 mm bh 542.00 31,163 16,890,238 -
12) Trekstang dia 10mm Kg 142.86 17,807 2,543,871 -
13) Angkur M 16, L=500 mm bh 104.00 222,591 23,149,509 -
14) Roundbar Ø 10 Kg 149.09 18,364 2,737,802 -
15) Cat Dasar (Zincromate) Kg 14,162.74 3,339 47,287,585 -
15) Cat Finish Kg 28,485.28 3,339 95,108,705 -
16) Nonshrink grout t=25 m3 0.59 13,355,486 7,812,959 -
II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton
maupun bata , kawat ayam (jika diperlukan) dan semua
pekerjaan bantu yang berhubungan dengan plesteran. Volume
plesteran dan acian sudah ditambahkan 10cm di atas plafond
- Lantai 1
Horse Food Storage m2 61.92 3.10 18,360 1,136,759 56,838
Bedding Storage 1 m2 216.83 (10.96) 18,360 3,980,966 (201,266)
Bedding Storage 2 m2 219.06 (11.70) 18,360 4,021,909 (214,779)
Equipment Storage m2 323.25 16.16 18,360 5,934,797 296,740
Ruang trafo & Ruang PDTM m2 128.90 6.44 18,360 2,366,531 118,327
Kapasitor bank m2 53.21 2.66 18,360 977,009 48,850
Ruang PDTR m2 77.70 3.88 18,360 1,426,508 71,325
Ruang Genset m2 213.77 10.69 18,360 3,924,821 196,241
Ruang Pompa m2 69.71 3.49 18,360 1,279,894 63,995
Selasar as 2-2'/a-d m2 168.41 8.42 18,360 3,091,984 154,599
Ramp as 2-2'/c'-e m2 107.40 5.37 18,360 1,971,939 98,597
III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).
A PINTU BAJA
Pintu Baja P1 Steel plat tebal 1,5 mm 2 daun pintu ukuran 2230 x
2550 mm lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
Main Entrance unit 10.00 (10.00) 13,745,021 137,450,210 (137,450,210)
- Lantai 1
Hardware :
Lever handle art-306 SS psg 1.00 (1.00) Include
Lockcase Wilka art-1490.55 SS bh 1.00 (1.00) Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 (1.00) Include
Hinges Gracia BB 5" x 3" x 3 mm bh 8.00 (8.00) Include
Flush bolt gracia 200/350 mm SS set 1.00 (1.00) Include
Door closer Dorma TS 68 RA Silver bh 1.00 (1.00) Include
Hardware :
Lever handle art-306 SS psg 1.00 (1.00) Include
Lockcase Wilka art-1490.55 SS bh 1.00 (1.00) Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 (1.00) Include
Floor hinges dorma BTS 80 complete SS bh 2.00 (2.00) Include
Flush bolt gracia 200/350 mm SS set 1.00 (1.00) Include
Pintu Baja P3 Steel plat tebal 1,5 mm 2 daun pintu ukuran 2120 x
2150 mm lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
Main Entrance unit 2.00 (2.00) 10,145,718 20,291,435 (20,291,435)
- Lantai 1
Hardware :
Lever handle art-306 SS psg 1.00 (1.00) Include
Lockcase Wilka art-1490.55 SS bh 1.00 (1.00) Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 (1.00) Include
Hinges Gracia BB 5" x 3" x 3 mm bh 8.00 (8.00) Include
Flush bolt gracia 200/350 mm SS set 1.00 (1.00) Include
Door closer Dorma TS 68 RA Silver bh 1.00 (1.00) Include
Pintu Baja P4 Steel plat tebal 1,5 mm 1 daun pintu ukuran 1120 x
2150 mm lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
Main Entrance unit 2.00 (2.00) 5,360,002 10,720,003 (10,720,003)
- Lantai 1
Hardware :
Lever handle art-306 SS psg 1.00 (1.00) Include
Lockcase Wilka art-1490.55 SS bh 1.00 (1.00) Include
Cylinder Wilka art-1400.60 Nickel bh 1.00 (1.00) Include
Hinges Gracia BB 5" x 3" x 3 mm bh 8.00 (8.00) Include
Flush bolt gracia 200/350 mm SS set 1.00 (1.00) Include
Door closer Dorma TS 68 RA Silver bh 1.00 (1.00) Include
B JENDELA
CONCRETE SLAB
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
A Beton exposed aci halus finish cat interior ex.Jotun tipe standar, termasuk
alat bantu lainnya dengan peralatan perlengkapan terpasang sesuai
dengan spesifikasi dan gambar pada :
-
DAFTAR No. VI.2 - PEKERJAAN ARSITEKTUR STORAGE Vol Vol (+/-) Harsat Rp Rp (+/-)
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
1 Trap tangga
Pasangan bata ringan, tebal 100 mm dan perekat, adukan kering, kolom
dan balok praktis, sesuai spesifikasi dan gambar pada :
- Trap tangga (Provisional) m2 25.22 103,480 2,609,766 -
1 Atap
Roof top
- Storage m2 928.66 4.50 300,498 279,060,877 1,350,740
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.
IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.
VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja
III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko longsoran,
volume untuk tempat kerja
V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah termasuk
kebersihan jalan maupun apabila perlu dibuat cleaning pit
VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi dan tidak
mengganggu debit air di lingkungan
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan sesuai
gambar spesifikasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan) untuk
urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 166.58 - 55,640 9,268,336 -
- Pile Cap m3 15.03 - 55,640 836,380 -
- Tie Beam m3 16.19 - 55,640 900,800 -
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu berikut
peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai inc Tie Beam m3 2.45 - 272,340 668,050 -
- Pondasi Batu kali m3 14.77 - 272,340 4,023,551 -
- Pile Cap m3 2.74 (2.23) 272,340 746,756 (607,318)
Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam m3 24.53 - 667,780 16,380,643 -
2) Pile cap m3 27.42 (27.16) 667,780 18,310,528 (18,139,576)
PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada:
- Lantai 1 m2 546.71 - 53,220 29,095,906 -
I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-
lubang baut, perapihan dengan gerinda, penyediaan
peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)
I
Harga satuan dinding batako, bata, hebel, celcon sudah termasuk adukan biasa
atau drymix, kolom praktis, ringbalk, angkur, sparing dan semua pekerjaan bantu
yang berhubungan dengan pekerjaan dinding tersebut.
II
Harga satuan plesteran biasa atau drymix sudah termasuk acian, skonengan, tali
air , ketrikan atau bobokan beton maupun bata , kawat ayam (jika diperlukan)
dan semua pekerjaan bantu yang berhubungan dengan plesteran. Volume
plesteran dan acian sudah ditambahkan 10cm di atas plafond
III
Harga satuan pekerjaan pelapis dinding (seperti : granit, marmer, keramik,
porselin) sudah termasuk adukan, cor beton,perekat (calbond), angkur, kawat
pengikat alumunium fixing pada dinding dengan ketinggian lebih dari 2m,
pemotongan, pinggulan, adu manis, naad, dan alat bantu lainnya
IV Harga satuan pekerjaan plesteran sudah termasuk untuk dinding kedap air
sesuai gambar dan spesifikasi
V Harga satuan pekerjaan cat dinding sudah termasuk pengertian cat dasar (meni,
plamur, stained, sealer).
VI Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan sesuai
spesifikasi.
A Pasangan Bata ringan tebal 100 mm, setara ex. primacon, termasuk dinding
penebalan,urinoir, perekat, adukan kering kolom dan balok praktis sesuai
spesifikasi
- Lantai 1 dan gambar :
Kantor Administrasi m2 158.63 0.64 103,480 16,415,032 66,363
A Plesteran dan Acian, Plesteran halus berikut acian halus, termasuk peralatan
dan perlengkapan sesuai spesifikasi dan gambar pada :
- Lantai 1
Kantor Administrasi m2 81.77 0.10 61,540 5,031,830 6,388
- Area Exterior
Kantor Administrasi m2 120.04 0.09 61,540 7,387,262 5,600
B Pengecatan dengan fin. cat Acrylic emulsion paint ex.setara ICI / Jotun tipe
ambience majestic, termasuk peralatan dan perlengkapan sesuai spesifikasi dan
gambar pada :
- Kantor Administrasi
Administration Office m2 74.55 (4.09) 18,360 1,368,650 (75,004)
Toilet Room m2 23.42 (23.42) 18,360 429,903 (429,903)
I
Harga satuan pintu dan jendela kayu sudah termasuk angkur, perlengkapan
kaca, pemasangan kolom & ringbalk praktis sekeliling pintu & jendela, dan
peralatan bantu yang diperlukan dan bahan yang terbuang (waste).
II
Harga satuan pintu dan jendela besi sudah termasuk angkur, pengelasan, kaca,
pemasangan kolom & balok praktis sekeliling pintu & jendela , dan peralatan
bantu yang diperlukan dan bahan yang terbuang (waste).
III
Harga satuan pintu dan jendela aluminium sudah termasuk angkur, sealant,
karet, kaca, pengelasan, pemasangan kolom praktis sekeliling pintu & jendela,
dan peralatan bantu yang diperlukan dan bahan yang terbuang (waste).
IV
Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik pembuat.
A PINTU KAYU
Pintu Kayu P1 Terdiri dari 1 pintu dan 2 daun pintu dengan kusen/frame
alumunium ukuran 1790x2400 mm, Plywood, kaca 5 mm THK. lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu lainnya
sesuai
- Lantaispesifikasi
1 dan gambar pada :-Provisional unit 1.00 2,281,562 2,281,562 -
Hardware :
Lever handle art-LH UL306/22 mm SS psg 1.00 Include
Lockcase Calfis art 17180.55 SS bh 1.00 Include
Cylinder Calfis art-17140.62 S. Nickel bh 1.00 Include
Hinges Gracia BB 5"x3"3" mm SS bh 3.00 Include
Door closer Calfis CFS 2002 RA Silver bh 1.00 Include
Friction Stay Top hung Art-12" psg 1.00 Include
Rambuncis art-118 Silver bh 1.00 Include
Hardware :
Lever handle art-LH UL306/22 mm SS psg 1.00 Include
Lockcase Calfis art 17180.55 SS bh 1.00 Include
Cylinder Calfis art-17140.62 S. Nickel bh 1.00 Include
Hinges Gracia BB 5"x3"3" mm SS bh 3.00 Include
Door closer Calfis CFS 2002 RA Silver bh 1.00 Include
Friction Stay Top hung Art-12" psg 1.00 Include
Rambuncis art-118 Silver bh 1.00 Include
Hardware :
Flush handle art- 506 SN bh 4.00 Include
Lockcase Calfis art-17136.30 SS bh 1.00 Include
Ring kunci art-901 CK SS bh 1.00 Include
Track Sliding Calfis SD 100/2 mtr bh 2.00 Include
Cannel Sliding Calfis CL 500/2mtr bh 1.00 Include
Bracket BK110 btg 1.00 Include
Roda sliding Calfis pack 120 (100kg) btg 6.00 Include
Terdiri dari :
- Hanger HW 111 (2pcs)
- Track Buffer with retained ST 112 (1 Pcs)
- Floor Guide FG 115 (1 Pcs)
DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR ADMINISTRASI Vol Vol (+/-) Harsat Rp Rp (+/-)
HOMOGENOUS TILE
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
C Listplank GRC Cetak finishing cat Weathershield setara ex. ICI / Jotun,
termasuk alat bantu lainnya dengan peralatan perlengkapan terpasang
sesuai spesifikasi dan gambar pada :
II
Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik pembuat.
I Lantai 1
12,074,890 -
DAFTAR No. VII.2 - PEKERJAAN ARSITEKTUR KANTOR ADMINISTR Vol Vol (+/-) Harsat Rp Rp (+/-)
1 Cermin
Kaca cermin tebal 6mm, lengkap dengan bevel bagian pinggir, berikut
lapisan belakang dari multiplek tebal 12 mm, berikut sealant, bracket, dll
termasuk alat-alat bantu lainnya dengan peralatan dan perlengkapan
terpasang sesuai spesifikasi dan gambar pada :
Lantai 1
- Toilet (uk. 1000x1000 mm) unit 1.00 800,216.20 800,216 -
2 Meja Lavatory
Meja Lavatory lapis keramik tebal 180 mm, termasuk alat bantu lainnya
dengan peralatan perlengkapan terpasang sesuai spesifikasi dan
gambar pada :
Lantai 1
- Toilet (uk. 1000x478 mm) unit 1.00 408,110 408,110 -
1 Atap
Roof top
- Kantor Administrasi m2 88.77 (0.77) 300,498 26,675,246 (231,384)
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci
& alat-alat penggantung, perlengkapan yang dibutuhkan seperti
mur, baut, handle, engsel, kait angin, sealant, dan
kelengkapannya., rubber gasket (sealant), neoprene, penyetelan
dan pemasangan.
A GRC
Rib cetak GRC finishing cat acrylic emultion berikut alat bantu
dengan peralatan perlengkapan sesuai dengan spesifikasi dan
gambar pada :
Dinding samping
- Kantor administrasi m2 70.10 1.21 686,690 48,136,969 830,895
B Cat Weathershield
Finishing cat weathershiled berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :
Dinding depan dan belakang
- Eksterior m2 37.11 13.30 29,490 1,094,374 392,099
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 59.84 - 55,640 3,329,498 -
- Pile Cap m3 28.51 - 55,640 1,586,408 -
- Tie Beam m3 5.87 5.31 55,640 326,829 295,448
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai inc Tie Beam m3 1.78 - 272,340 484,765 -
- Pondasi Batu kali m3 5.44 - 272,340 1,481,530 -
- Pile Cap m3 1.20 - 272,340 326,808 -
Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam m3 0.89 - 667,780 594,324 -
2) Pile cap m3 0.60 - 667,780 400,668 -
4) Kolom, pada:
- Lantai 1 m3 3.02 1.30 782,410 2,366,008 1,014,003
PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada:
- Lantai 1 m2 147.00 - 53,220 7,823,340 -
3) Balok, pada:
- Lantai 2 kg 549.14 110.14 8,859 4,864,563 975,679
4) Kolom, pada:
- Lantai dasar kg 505.10 189.72 8,859 4,474,449 1,680,642
2) Kolom, pada:
- Lantai dasar m2 40.32 17.28 129,920 5,238,374 2,245,018
I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-
lubang baut, perapihan dengan gerinda, penyediaan
peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)
I Canopy Atap
1) WF 250 x 125 x 6 x 9 Kg 2,237.76 18,364 41,093,762 -
2) WF 200 x 100 x 5,5 x 8 Kg 2,989.60 18,364 54,900,396 -
3) HB 200 x 200 x 8 x 12 Kg 239.52 18,364 4,398,496 -
4) Gording CNP 150 x 50 x 20 x 2,3 Kg 1,050.00 18,364 19,281,983 -
5) Plate 6 mm Kg 130.56 17,807 2,324,944 -
6) Plate 8 mm Kg 50.24 17,807 894,639 -
7) Plate 10 mm Kg 28.26 17,807 503,235 -
8) Plate 12 mm Kg 386.26 17,807 6,878,212 -
9) Stifner 8 mm Kg 77.24 17,807 1,375,508 -
10) Stifner 12 mm Kg 51.58 17,807 918,571 -
11) Trekstang dia 10mm Kg 75.46 17,807 1,343,733 -
12) Bracing dia 16mm Kg 119.95 18,920 2,269,415 -
13) Spanskrup Bh 28.00 18,920 529,768 -
14) Angkur M20 L = 660mm Bh 32.00 222,591 7,122,926 -
15) Baut M12 Bh 432.00 31,163 13,462,330 -
16) Baut M 16 Bh 352.00 31,163 10,969,306 -
17) Nonshrink Grout, T = 25 mm, Uk 300 x 300mm titik 8.00 50,083 400,665 -
18) Cat Dasar (Zincromate) Kg 7,436.43 3,339 24,829,293 -
18) Cat Dasar (Zincromate) Kg 7,436.43 3,339 24,829,293 -
- Lantai 1
Horse Box 1 m2 30.65 0.15 18,360 562,734 2,818
Horse Box 2 m2 28.75 0.15 18,360 527,850 2,681
Horse Box 3 m2 30.65 0.15 18,360 562,734 2,818
Horse Box 4 m2 30.65 0.15 18,360 562,734 2,818
Horse Box 5 m2 28.75 0.15 18,360 527,850 2,681
Horse Box 6 m2 30.65 0.15 18,360 562,734 2,818
Coridor m2 15.29 44.84 18,360 280,644 823,306
III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).
A PINTU KAYU
Pintu Kayu P1 Terdiri dari 1 pintu dan 2 daun pintu, ukuran
2628x2400 wood clear glass lengkap terpasang termasuk,
hardware,
- Lantai 1 accesories dan perlengkapan bantu lainnya sesuai unit 2.00 - 7,456,813 14,913,626 -
Hardware :
Lever handle art-LH UL306/22 mm SS psg 1.00 1.00 Include
Lockcase Calfis art 17180.55 SS bh 1.00 1.00 Include
Cylinder Calfis art-17140.62 S. Nickel bh 1.00 1.00 Include
Hinges Gracia BB 5"x3"3" mm SS bh 8.00 8.00 Include
Flush bolt Calfis 150/350 mm SN set 1.00 1.00 Include
Door closer Calfis CFS 2002 RA Silver bh 1.00 1.00 Include
B JENDELA
C PINTU JENDELA
Jendela PJ1 ukuran 3350x2400, besi hollow Ø20, pipa besi Ø50
lengkap terpasang termasuk, hardware, accesories dan
perlengkapan bantu lainnya sesuai spesifikasi dan gambar pada :
- Lantai 1 unit 6.00 - 8,354,873 50,129,236 -
A PAVING BLOCK
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan luas
kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
A Beton exposed aci halus, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai dengan spesifikasi dan gambar pada :
1 Sanitary -
1 Heat Insulation
Heat Insulation Atap Rockwool density 50kg/m3 termasuk material
bantu dan kelengkapan lainnya, sesuai spesifkasi & gambar pada:
(Provisional)
- Lantai Atap m2 200.70 946,014 189,864,928 -
2 Grill (Provisional)
Grill ukuran 300 mm, sesuai gambar dan spesifikasi, pada :
Lantai 1
- Horse Box m' 20.10 333,887 6,711,132 -
3 PERLENGKAPAN
Tempat minum kuda, sesuai gambar dan spesifikasi pada :
Lantai 1
- Horse Box bh 6.00 237,872 1,427,234 -
1 Atap
Roof top
- Quarantine stable m2 188.02 44.50 300,498 56,499,716 13,372,180
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya.,
rubber gasket (sealant), neoprene, penyetelan dan pemasangan.
A GRC
Rib cetak GRC finishing cat weathershild berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar
pada :
Dinding depan
- Quarantine stable m2 103.08 4.46 686,690 70,784,005 3,062,637
D CAT KAMPROT
Cat Kamprot berikut alat bantu dengan peralatan perlengkapan
sesuai dengan spesifikasi dan gambar pada :
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja
III Harga satuan galian sudah termasuk pekerjaan persiapan, resiko longsoran,
volume untuk tempat kerja
V Buangan tanah keluar proyek / mendatangkan tanah dari luar sudah termasuk
kebersihan jalan maupun apabila perlu dibuat cleaning pit
VI Pekerjaan dewatering sudah termasuk izin pembuangan air keluar lokasi dan
tidak mengganggu debit air di lingkungan
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan sesuai
gambar spesifikasi
A Pembersihan lokasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan) untuk
urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi telapak m3 59.54 (35.73) 55,640 3,312,527 (1,988,017)
- Balok m3 42.48 - 55,640 2,363,587 -
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu berikut
peralatan perlengkapan sesuai spesifikasi dan gambar
- Tangga tribun m3 8.34 - 272,340 2,271,316 -
- Ramp m3 1.78 - 272,340 484,765 -
- Pondasi telapak m3 3.97 3.97 272,340 1,080,917 1,080,917
- Balok m3 5.66 (0.41) 272,340 1,542,534 (111,115)
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pondasi telapak m3 1.98 1.98 667,780 1,325,209 1,325,209
2) Di bawah balok m3 2.83 (0.20) 667,780 1,891,153 (136,227)
PEKERJAAN PEMBESIAN
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pondasi telapak kg 1,164.52 1,173.62 8,859 10,315,893 10,396,501
2) Kolom pedestal kg 2,249.69 (152.12) 8,859 19,928,842 (1,347,573)
3) Balok kg 4,908.69 56.94 8,859 43,483,660 504,443
I
Harga satuan atap sudah termasuk semua hal yang diperlukan,
seperti : pengelasan, pembuatan lubang-lubang baut, perapihan
dengan gerinda, penyediaan peralatan bantu untuk pemasangan
dan mendirikan atap+rangka serta sisa terbuang (waste)
CATATAN
Pekerjaan STRUKTUR COVERED TRAINING ARENA adalah
Pekerjaan STRUKTUR COVERED TRAINING ARENA yang sudah
ada dng ukuran 38 m x 58 m, dipindahkan ketempat lain dan
dimodifikasi menjadi ukuran 48 m x 80 m dengan memanfaatkan
Struktur yang masih dapat dipakai
A CERAMIC TILE
B SPECIAL FOOTING
LAPISAN BAWAH
1 Porous asphalt tebal 50 mm m2 3,518.32 86.68 166,832 586,969,346 14,461,022
2 Geotextile non woven pori maks 180 gr/m2 m2 3,518.32 86.68 22,259 78,314,789 1,929,423
3 Gravel 2/3 tebal 125 mm m2 3,518.32 86.68 52,300 184,008,918 4,533,383
4 Geotextile non woven pori maks 180 gr/m2 m2 3,518.32 86.68 22,259 78,314,789 1,929,423
5 Sub base dia 15-30 cm Tebal 445 mm m2 3,518.32 86.68 168,831 594,002,797 14,634,304
B SPECIAL FOOTING :
1 Pasir dengan campuran serat fibre geotextile dan anti debu m2 3,518.32 BY OTHER
( Material Ex Import )
C PAGAR
4 Railing tinggi 1600mm dengan pipa pembagi co extrude m' 247.60 973,840.00 241,122,784 -
PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght max
4m co extrude PVC/ASA dan kelengkapan lainnya sesuai
gambar dan spesifikasi
Roof top
- Covered Training Arena m2 3,963.25 844 300,498 1,190,950,425 253,605,655
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi
- Lokasi area lahan (Tipe 1A, 1B, dan 1C) m2 58.12 - 11,130 646,806 -
- Lokasi area lahan (Tipe 2) m2 9.92 - 11,130 110,428 -
- Lokasi area lahan (Tipe 3) m2 21.75 - 11,130 242,068 -
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu
dan kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m (Tipe 1A, 1B dan 1C) m3 67.32 - 55,640 3,745,685 -
- Pondasi Batu kali sedalam 1,1 m Tipe 2 (provisional) m3 13.38 - 55,640 744,241 -
- Pondasi Batu kali sedalam 1,1 m Tipe 3 (provisional) m3 16.63 - 55,640 925,404 -
- Pile Cap (Tipe 1A, 1B dan 1C) m3 9.50 - 55,640 528,803 -
- Pile Cap Tipe 2 (provisional) m3 2.11 - 55,640 117,512 -
- Pile Cap Tipe 3 (provisional) m3 2.11 - 55,640 117,512 -
- Tie Beam (Tipe 1A, 1B dan 1C) m3 5.05 (2.28) 55,640 280,926 (126,692)
- Tie Beam Tipe 2 (provisional) m3 1.00 - 55,640 55,818 -
- Tie Beam Tipe 3 (provisional) m3 1.25 - 55,640 69,405 -
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai inc Tie Beam (Tipe 1A, 1B dan 1C) m3 17.73 - 272,340 4,828,588 -
- Dibawah plat lantai inc Tie Beam Tipe 2 (provisional) m3 0.30 - 272,340 82,791 -
- Dibawah plat lantai inc Tie Beam Tipe 3 (provisional) m3 0.38 - 272,340 102,945 -
- Pondasi Batu kali (Tipe 1A, 1B dan 1C) m3 6.12 - 272,340 1,666,721 -
- Pondasi Batu kali Tipe 2 (provisional) m3 1.22 - 272,340 331,165 -
- Pondasi Batu kali Tipe 3 (provisional) m3 1.51 - 272,340 411,778 -
- Pile Cap (Tipe 1A, 1B dan 1C) m3 0.32 - 272,340 88,238 -
- Pile Cap Tipe 2 (provisional) m3 0.07 - 272,340 19,608 -
- Pile Cap Tipe 3 (provisional) m3 0.07 - 272,340 19,608 -
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam (Tipe 1A, 1B dan 1C) m3 3.47 - 667,780 2,313,858 -
2) Di bawah pelat lantai, Tie beam Tipe 2 (provisional) m3 0.99 - 667,780 658,698 -
3) Di bawah pelat lantai, Tie beam Tipe 3 (provisional) m3 1.24 - 667,780 827,780 -
4) Pile cap + kolom pedestal (Tipe 1A, 1B dan 1C) m3 0.16 (0.11) 667,780 108,180 (72,120)
5) Pile cap + kolom pedestal Tipe 2 (provisional) m3 0.04 - 667,780 24,040 -
6) Pile cap + kolom pedestal Tipe 3 (provisional) m3 0.04 - 667,780 24,040 -
PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada: (Tipe 1A, 1B dan 1C)
- Lantai 1 m2 54.00 - 53,220 2,873,880 -
2) Pelat, pada: Tipe 2 (provisional)
- Lantai 1 m2 9.00 - 53,220 478,980 -
3) Pelat, pada: Tipe 3 (provisional)
- Lantai 1 m2 11.40 - 53,220 606,708 -
I
Harga satuan atap sudah termasuk semua hal yang
diperlukan, seperti : pengelasan, pembuatan lubang-
lubang baut, perapihan dengan gerinda, penyediaan
peralatan bantu untuk pemasangan dan mendirikan
atap+rangka serta sisa terbuang (waste)
II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton maupun
bata , kawat ayam (jika diperlukan) dan semua pekerjaan bantu
yang berhubungan dengan plesteran. Volume plesteran dan
acian sudah ditambahkan 10cm di atas plafond
- Lantai 1 (Toilet)
Pos Jaga Type 1A m2 32.97 - 161,560 5,326,633 -
Pos Jaga Type 1B m2 21.98 - 161,560 3,551,089 -
Pos Jaga Type 1C m2 10.99 - 161,560 1,775,544 -
Pos Jaga Type 2 m2 11.95 - 161,560 1,930,642 -
Pos Jaga Type 3 m2 11.47 - 161,560 1,853,093 -
III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan dan
bahan yang terbuang (waste).
A PINTU KAYU
Pintu Kayu P1 Terdiri dari 1 pintu dengan kusen/frame alumunium
ukuran 1000x2400 mm, Plywood lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
Hardware :
Lever handle art-LH UL 306/22 mm SS psg - -
Lockcase Calfis art-17180.55 SS bh - -
Cylinder Calfis art-17140.62 S Nickel bh - -
Hinges gracia BB 5"x3"x3mm SS bh - -
Door closer Calfis CFS 2002 RA silver bh - -
Friction stay Top hung art-12" psg - -
Rambuncis art-118 silver bh - -
Tipe 1A
- Pintu utama unit 1.00 2.00 2,281,562 2,281,562 4,563,124
- Bedroom unit 1.00 2.00 2,281,562 2,281,562 4,563,124
Tipe 1B
- Pintu utama unit 1.00 1.00 2,281,562 2,281,562 2,281,562
- Bedroom unit 1.00 1.00 2,281,562 2,281,562 2,281,562
Tipe 1C
- Pintu utama unit 1.00 - 2,281,562 2,281,562 -
- Bedroom unit 1.00 - 2,281,562 2,281,562 -
Tipe 2
- Pintu utama unit 1.00 - 2,281,562 2,281,562 -
Tipe 3
- Pintu utama unit 2.00 - 2,281,562 4,563,124 -
Hardware :
Lever handle art-LH UL 306/22 mm SS psg - - -
Lockcase Calfis art-17180.55 SS bh - - -
Cylinder Calfis art-17140.62 S Nickel bh - - -
Hinges gracia BB 5"x3"x3mm SS bh - - -
Door closer Calfis CFS 2002 RA silver bh - - -
Friction stay Top hung art-12" psg - - -
Rambuncis art-118 silver bh - - -
Tipe 1A
- Toilet unit 1.00 2.00 2,225,914 2,225,914 4,451,829
Tipe 1B
- Toilet unit 1.00 1.00 2,225,914 2,225,914 2,225,914
Tipe 1C
- Toilet unit 1.00 - 2,225,914 2,225,914 -
Tipe 2
- Toilet unit 1.00 - 2,225,914 2,225,914 -
Tipe 3
- Toilet unit 1.00 - 2,225,914 2,225,914 -
B JENDELA
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)
DAFTAR
Jendela NO.
J1 ukuran
X.2.2 -1000x1500
PEKERJAAN mmPINTU
Kusendan
Alumunium
JENDELA
40 mm Clear
Anodized, Daun Jendela Alumunium, Kaca Clear 5 mm lengkap
terpasang termasuk, hardware, accesories dan perlengkapan bantu
lainnya sesuai spesifikasi dan gambar pada :
Hardware :
Flush handle art-506 SN bh - - -
Lockcase Calfis art-17136.30 SS bh - - -
Cylinder Calfis art-17140.62 S Nickel bh - - -
Ring kunci art-901 CK SS bh - - -
Track sliding Calfis CL 500/2mtr btg - - -
Bracket BK 110 btg - - -
Roda sliding Calfis Pack 120 (100kg) btg - - -
- Hanger HW 111 (2 pcs)
- Track Buffer with Retained ST 112
- Floor guide FG 115
Tipe 1A
- Lantai 1 unit 2.00 4.00 1,558,700 3,117,400 6,234,800
Tipe 1B
- Lantai 1 unit 2.00 2.00 1,558,700 3,117,400 3,117,400
B JENDELA-Lanjutan
Tipe 1C
- Lantai 1 unit 2.00 - 1,558,700 3,117,400 -
Tipe 2
- Lantai 1 unit 1.00 - 1,558,700 1,558,700 -
Tipe 3
- Lantai 1 unit 1.00 - 1,558,700 1,558,700 -
Tipe 1A
- Lantai 1 unit 1.00 2.00 7,559,913 7,559,913 15,119,826
Tipe 1B
- Lantai 1 unit 1.00 1.00 7,559,913 7,559,913 7,559,913
Tipe 1C
- Lantai 1 unit 1.00 - 9,352,469 9,352,469 -
Tipe 2
- Lantai 1 unit 1.00 - 5,689,419 5,689,419 -
Tipe 3
- Lantai 1 unit 1.00 - 4,504,773 4,504,773 -
Tipe 1B
- Lantai 1 unit 1.00 1.00 4,442,423 4,442,423 4,442,423
DAFTAR No. X.2 - PEKERJAAN ARSITEKTUR GUARD POST Vol Vol (+/-) Harsat Rp Rp (+/-)
Tipe 1C
- Lantai 1 unit 1.00 - 2,571,929 2,571,929 -
Tipe 2
- Lantai 1 unit 1.00 - 2,571,929 2,571,929 -
CERAMIC TILE
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
III Harga satuan plafond papan kayu, pergola, lambresiring sudah termasuk
anti rayap, pengecatan (polyurethane) termasuk anti rayap, fire retardant
dan telah dikeringkan (dryclean)
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
### Tanggulan
Tanggulan Closet tinggi 930 mm, tebal 95 mm lapis keramik, sesuai
gambar dan spesifikasi pada :
Pos Jaga 1A
- toilet m' 1.05 457,365 480,233 -
Pos Jaga 1B
- toilet m' 1.05 457,365 480,233 -
Pos Jaga 1C
- toilet m' 1.05 457,365 480,233 -
Pos Jaga 2
- toilet m' 1.05 457,365 480,233 -
Pos Jaga 3
- toilet m' 1.05 457,365 480,233 -
A Atap
- Roof top
Pos Jaga 1A m2 43.54 92.22 300,498 13,083,702 27,710,764
Pos Jaga 1B m2 43.54 46.96 300,498 13,083,702 14,112,609
Pos Jaga 1C m2 43.54 1.71 300,498 13,083,702 514,453
Pos Jaga 2 m2 28.09 0.53 300,498 8,441,001 159,264
Pos Jaga 3 m2 32.46 0.59 300,498 9,754,179 176,693
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.
IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.
VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail
A Cat Weathershield
Cat weathershiled setara ex.Jotun Tipe standar, termasuk peralatan dan
perlengkapan sesuai spesifikasi dan gambar pada :
Eksterior
- Lantai 1
Pos Jaga Type 1A m2 156.71 1.02 29,490 4,621,275 29,962
Pos Jaga Type 1B m2 104.47 1.73 29,490 3,080,850 50,988
Pos Jaga Type 1C m2 47.96 0.80 29,490 1,414,355 23,666
Pos Jaga Type 2 m2 32.14 0.38 29,490 947,676 11,221
Pos Jaga Type 3 m2 42.79 (0.50) 29,490 1,261,892 (14,612)
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat kerja
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu dan
kelengkapannya pada:
- Pondasi Batu kali sedalam 1,1 m m3 30.95 - 55,640 1,722,058 -
- Pile Cap m3 8.27 (2.83) 55,640 460,143 (157,461)
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai inc Tie Beam m3 135.43 (135.43) 272,340 36,883,006 (36,883,006)
- Pondasi Batu kali m3 2.81 - 272,340 765,275 -
- Pile Cap m3 1.22 0.00 272,340 332,255 1,089
Bobok kepala tiang pancang, termasuk buang keluar lokasi proyek sesuai
spesifikasi dan gambar
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai m3 22.57 - 667,780 15,071,795 -
2) Pile cap m3 0.61 0.00 667,780 407,346 1,336
PEKERJAAN PEMBESIAN
A Wiremesh 1 lapis M8-150
1) Pelat, pada:
- Lantai dasar m2 451.45 - 53,220 24,026,169 -
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pile cap kg 1,200.17 (279.00) 8,859 10,631,706 (2,471,539)
2) Balok, pada:
- Lantai 1 kg 1,208.88 (549.60) 8,859 10,708,863 (4,868,622)
2) Balok, pada:
- Lantai 1 m2 59.10 (22.78) 104,000 6,146,400 (2,369,120)
I
Harga satuan atap sudah termasuk semua hal yang diperlukan,
seperti : pengelasan, pembuatan lubang-lubang baut, perapihan
dengan gerinda, penyediaan peralatan bantu untuk pemasangan dan
mendirikan atap+rangka serta sisa terbuang (waste)
I Canopy Atap
1) Pipa Baja Hitam 6", tebal 6mm Kg 9,475.40 23,372 221,460,002
2) Pipa Baja Hitam 4", tebal 4,5mm Kg 3,733.20 23,372 87,252,726
3) Pipa Baja Hitam 3", tebal 4mm Kg 1,501.62 23,372 35,096,014
4) Shear Stud dia 13mm, p = 10 cm bh 204.00 66,777 13,622,596
5) Nonshrink Grout, T = 50 mm, Uk 280 x 280mm titik 204.00 44,518 9,081,730
6) Cat Zinchromate Kg 14,710.22 3,339 49,115,534
7) Cat Finish Kg 14,710.22 3,339 49,115,534
II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton
maupun bata , kawat ayam (jika diperlukan) dan semua
pekerjaan bantu yang berhubungan dengan plesteran. Volume
plesteran dan acian sudah ditambahkan 10cm di atas plafond
- Lantai 1
Mushola m2 54.30 (22.24) 18,360 996,948 (408,337)
Toilet 1 m2 6.29 (6.29) 18,360 115,484 (115,484)
Toilet 2 m2 6.29 (6.29) 18,360 115,484 (115,484)
D CERAMIC TILE
III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).
A PINTU PVC
Pintu PVC P1 Terdiri dari 1 daun pintu dengan kusen/frame
alumunium ukuran 720x2100 mm, lengkap terpasang termasuk,
hardware, accesories dan perlengkapan bantu lainnya sesuai
spesifikasi dan gambar pada :
- Pintu toilet unit 2.00 4,206,978 8,413,956 -
A CERAMIC TILE
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
A Beton exposed aci halus, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai dengan spesifikasi dan gambar pada :
I Lantai 1
Toilet
- Closet Set setara ex.TOTO CW860NJ/SW861JP bh 2.00 3,385,100 6,770,200 -
- Floor Drain ex. TOTO TX133L bh 2.00 385,700 771,400 -
- Jetwasher setara ex. TOTO TB 19 CSN bh 2.00 581,660 1,163,320 -
- Paper Holder setara ex.TOTO TX 720 ACRB bh 2.00 267,820 535,640 -
Tempat Wudhu
- Floor Drain ex. TOTO TX133L bh 2.00 385,700 771,400 -
- Kran air bh 4.00 492,080 1,968,320 -
Area Makan
- Wastafel Set setara ex TOTO LW549J bh 8.00 3,644,970 29,159,760 -
- Kran air bh 8.00 492,080 3,936,640 -
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
1 Penebalan
Penebalan closet tinggi 200 mm, tebal 100 mm lapis keramik, sesuai
gambar dan spesifikasi pada :
Lantai 1
- Toilet 1 m2 0.80 152,455 121,964 -
- Toilet 2 m2 0.80 152,455 121,964 -
2 Tanggulan
Tanggulan wudhu tinggi 340 mm, tebal 100 mm lapis keramik, sesuai
gambar dan spesifikasi pada :
Lantai 1
- Toilet 1 m' 3.85 167,701 645,647 -
- Toilet 2 m' 3.85 167,701 645,647 -
1 Atap
Atap Membran ex Ferari berikut alat bantu dengan peralatan
perlengkapan sesuai dengan spesifikasi dan gambar pada :
- F&B m2 512.02 144,680 74,078,335 -
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.
IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.
VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail
I Semua tanaman harus bebas dari hama, korasil, tegak, segar / tidak
layu berakar baik dengan diameter ketinggian tanaman sesuai yang
dikehendaki
II
Tanaman sudah termasuk pemupukan, penyiraman steiger/
penyangga, pembuangan tanaman / umbi-umbian yang tidak
diperlukan termasuk akarnya, batu-batuan dan perawatan baik
pemupukan, pemangkasan, dan penyemprotan pestisida.
V Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.
VI
Perawatan tanaman selama masa peleksanaan dan pemeliharaan.
I PEKERJAAN TANAH
E Fine Grading yaitu Pembentukan muka tanah untuk menjadi lebih m2 9,934.70 8,904 88,455,165 -
rata permukaannya ( Level tertinggi yang menjadi patokan
permukaannya adalah area ex Green atau Hole Golf
II PEKERJAAN PENANAMAN
1.POHON BARU
A TREMBESI (Samane Saman), Tinggi Overal 4 m daun, Diameter phn 14.00 3,561,463 49,860,481 -
batang 30 - 35 cm, Warna daun hijau, bunga warna Pink, Tertanam
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan (04122015))
B ANGGUR LAUT (Cocoloba spa), Tinggi Overal 3 - 4 m daun, phn 18.00 667,774 12,019,937 -
Diameter batang 8 - 10 cm, Warna daun hijau, bunga warna kuning,
Terpasang Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan
C KETAPANG KENCANA (Bucida Molinety), Tinggi Overal 3 m phn 52.00 712,293 37,039,215 -
daun, Diameter batang 8 - 10 cm, Warna daun hijau, bunga warna
………., Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr
For Tender Softscape Master Plan
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)
E TABEBUYA BUNGA KUNING (Tabebuia Argentea), Tinggi Overal phn 51.00 667,774 34,056,489 -
3 - 4 m daun, Diameter batang 8 - 10 cm, Warna daun hijau, warna
bunga kuning, Tertanam Sesuai Spesifikasi dan Gambar pada:
(Reff. Gbr For Tender Softscape Master Plan.
G KAMBOJA BALI (Plumeria sp), Tinggi Overal 3 m daun, Diameter phn deleted 756,811 - -
batang 8 - 10 cm, Warna daun hijau bunga kuning putih, Tertanam
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan.
I TABEBUYA PINK (Tabebuia Rosea), Tinggi Overal 3 m daun, phn 58.00 712,293 41,312,970 -
Diameter batang 5 - 6 cm, Warna daun hijau, warna bunga Pink,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.
J Bunga Kupu Kupu (Bauhinia Purpurea), Tinggi Overal 3 m daun, phn 114.00 267,110 30,450,508 -
Diameter batang 7 - 8 cm, Warna daun hijau, warna bunga putih,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.
K Pulai (Alstonia Scholaris), Tinggi Overal 6 - 7 m daun, Diameter phn 2.00 890,366 1,780,731 -
batang 30 - 40 cm, Warna daun hijau, warna bunga …………...,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.
2. SEMAK PERDU
3.RUMPUT
A Rumput Gajah Mini (Axonopus compressus Dwarft) Tertanam m2 8,903.15 27,824 247,720,615 -
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan.
II
Tanaman sudah termasuk pemupukan, penyiraman steiger/
penyangga, pembuangan tanaman / umbi-umbian yang tidak
diperlukan termasuk akarnya, batu-batuan dan perawatan baik
pemupukan, pemangkasan, dan penyemprotan pestisida.
V Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.
I PEKERJAAN TANAH
D Fine Grading yaitu Pembentukan muka tanah untuk menjadi m2 16,862.03 8,904 150,133,737 -
lebih rata permukaannya ( Level tertinggi yang menjadi patokan
permukaannya adalah area ex Green atau Hole Golf
II PEKERJAAN PENANAMAN
1.POHON BARU
A Pulai (Alstonia Scholaris), Tinggi Overal 4 m daun, Diameter phn 23.00 1,112,957 25,598,015 -
batang 10 - 12 cm, Warna daun hijau, warna bunga …………...,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.
B TABEBUYA BUNGA KUNING (Tabebuia Argentea), Tinggi phn 60.00 667,774 40,066,458 -
Overal 3 - 4 m daun, Diameter batang 8 - 10 cm, Warna daun
hijau bunga kuning, Tertanam Sesuai Spesifikasi dan Gambar
pada: (Reff. Gbr For Tender Softscape Master Plan.
D MINDI (Melia Azedarach), Tinggi Overal 3 - 4 m daun, phn 30.00 712,293 21,368,778 -
Diameter batang 6-8 cm, Warna daun hijau, Tertanam Sesuai
Spesifikasi dan Gambar pada: (Reff. Gbr For Tender Softscape
Master Plan.
DAFTAR No. XII.2 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
BANGUNAN PENUNJANG
E KAMBOJA BALI (Plumeria sp), Tinggi Overal 3 m daun, phn 36.00 756,811 27,245,191 -
Diameter batang 10 - 12 cm, Warna daun hijau bunga kuning
putih, Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr
For Tender Softscape Master Plan.
F Bunga Kupu Kupu (Bauhinia Purpurea), Tinggi Overal 3 m phn 29.00 267,110 7,746,182 -
daun, Diameter batang 7 - 8 cm, Warna daun hijau, warna
bunga putih, Tertanam Sesuai Spesifikasi dan Gambar pada:
(Reff. Gbr For Tender Softscape Master Plan.
G PUCUK MERAH DIPANGKAS 1,5 M (Syzygium sp), Tinggi phn 16.00 445,183 7,122,926 -
Overal 3-4 m daun, Diameter batang 5 - 6 cm, Warna daun
hijau merah bunga …………..., Tertanam Sesuai Spesifikasi dan
Gambar pada: (Reff. Gbr For Tender Softscape Master Plan.
(Provisional)
H TREMBESI (Samane Saman), Tinggi Overal 3-4 m daun, phn 14.00 1,335,549 18,697,680 -
Diameter batang 4-5 cm, Warna daun hijau,warna bunga Pink,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan (04122015))
I DIOSPYROS (Diospyros buxifolia), Tinggi Overal 3 m daun, phn 70.00 890,366 62,325,601 -
Diameter batang 5-6 cm, Warna daun hijau,warna bunga Pink,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan
2. SEMAK PERDU
A LEE KWAN YU (Vernonia eliptica) tinggi 30-50 cm Tertanam m2 735.00 64,106 47,118,155 -
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan.
4. RUMPUT
II
Tanaman sudah termasuk pemupukan, penyiraman steiger/
penyangga, pembuangan tanaman / umbi-umbian yang tidak
diperlukan termasuk akarnya, batu-batuan dan perawatan baik
pemupukan, pemangkasan, dan penyemprotan pestisida.
V Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.
I PEKERJAAN TANAH
D Pembentukan dan penyesuaian tepi Danau meliputi pengurugan m3 2,593.70 166,944 433,001,551 -
dan penghalusan tepi Danau
E Fine Grading yaitu Pembentukan muka tanah untuk menjadi lebih m2 Exclude 8,904 - -
rata permukaannya ( Level tertinggi yang menjadi patokan
permukaannya adalah area ex Green atau Hole Golf
II PEKERJAAN PENANAMAN
1.POHON BARU
A TREMBESI (Samane Saman), Tinggi Overal 4 m daun, Diameter phn 76.00 3,561,463 270,671,183 -
batang 30 - 35 cm, Warna daun hijau,warna bunga Pink, Tertanam
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan (04122015))
B MAHONI (Switenia Mahagony), Tinggi Overal 3 m daun, phn 105.00 667,774 70,116,302 -
Diameter batang 8 - 10 cm, Warna daun hijau, warna bunga Putih,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan (04122015))
C KETAPANG (Terminalia Cattappa), Tinggi Overal 4 - 5 m daun, phn 46.00 534,219 24,574,094 -
Diameter batang 8 - 10 cm, Warna daun hijau, warna bunga
…………..., Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff.
Gbr For Tender Softscape Master Plan
DAFTAR No. XII.3 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
CROSS COUNTRY
E KETAPANG KENCANA (Bucida Molinety), Tinggi Overal 3 m phn 42.00 712,293 29,916,289 -
daun, Diameter batang 8 - 10 cm, Warna daun hijau, warna bunga
………….., Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff.
Gbr For Tender Softscape Master Plan
F Pulai (Alstonia Scholaris), Tinggi Overal 6 - 7 m daun, Diameter phn 179.00 1,335,549 239,063,200 -
batang 30 - 40 cm, Warna daun hijau, warna bunga …………...,
Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For
Tender Softscape Master Plan.
G KAYU PUTIH BATANG WARNA (Eucaliptus Deglupta), Tinggi phn 15.00 356,146 5,342,194 -
Overal 2 - 2,5 m daun, Diameter batang 2 - 3 cm, Warna daun
hijau, warna bunga …………..., Tertanam Sesuai Spesifikasi dan
Gambar pada: (Reff. Gbr For Tender Softscape Master Plan.
H POHON YANG LIU (Salix Babylonica), Tinggi Overal 3 - 4 m phn 139.00 756,811 105,196,712 -
daun, Diameter batang 6 - 8 cm, Warna daun hijau, warna bunga
…………..., Tertanam Sesuai Spesifikasi dan Gambar pada: (Reff.
Gbr For Tender Softscape Master Plan.
I TABEBUYA BUNGA KUNING (Tabebuia Argentea), Tinggi phn 100.00 667,774 66,777,430 -
Overal 3 - 4 m daun, Diameter batang 8 - 10 cm, Warna daun
hijau bunga kuning, Tertanam Sesuai Spesifikasi dan Gambar
pada: (Reff. Gbr For Tender Softscape Master Plan.
2.RUMPUT
A Rumput Gajah Mini (Axonopus compressus Dwarft) Tertanam m2 Exclude 22,259 -
Sesuai Spesifikasi dan Gambar pada: (Reff. Gbr For Tender
Softscape Master Plan.
VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.
VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead dan
jasa Pemborong.
I PEKERJAAN PERKERASAN
PERKERASAN 7
G Batu koral Tebar / Lepas dia 3 - 5 cm m2 30.10 139,120 4,187,501 -
warna abu abu & warna Hitam
VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.
VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead dan
jasa Pemborong.
I PEKERJAAN PERKERASAN
Kansteen
Kansteen type-1 sleepform ukuran 600x450x210mm
natural colour ex..
- Zona Gallop Track m' 3,415.22 143,310 489,435,178 -
- Zona Asphalt m' 1,971.28 143,310 282,504,137 -
Car Stopper
Car Stopper ukuran 600x150x...mm natural colour ex…
- Area Parkir bh 63.00 57,160 3,601,080 -
Traffic Arrow
Traffic Arrow type-1 Thermoplastic paint finish white colour
- Jalan Area Penunjang bh 22.00 139,120 3,060,640 -
Parking Line
Zebra Cross Thermoplastic paint finish white colour
- Mobil uk. 5000mm bh 47.00 139,120 6,538,640 -
- Bus uk. 12000mm bh 17.00 139,120 2,365,040 -
DAFTAR No. XII.2 - PEKERJAAN LANDSCAPE ZONA Vol Vol (+/-) Harsat Rp Rp (+/-)
BANGUNAN PENUNJANG
VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.
I PEKERJAAN PERKERASAN
B Fine Grading Jalur Cross Country dengan tambahan taburan pasir m2 22,489.36 10,573 237,782,097 -
+ screening 3cm (provisional)
Kansteen
C Kansteen type-1 sleepform ukuran 600x450x210mm m' 2,776.30 143,310 397,871,553 -
natural colour ex..
VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.
Kansteen
Kansteen type-1 sleepform ukuran 600x450x210mm natural
colour ex..
- Jalan & Pedestrian m' 1,299.83 143,310 186,278,637 -
Car Stopper
Car Stopper ukuran 600x150x...mm natural colour ex…
- Area Parkir bh 792.00 100,740 79,786,080 -
Traffic Arrow
Traffic Arrow type-1 Thermoplastic paint finish white colour
- Jalan & Pedestrian bh 70.00 139,120 9,738,400 -
Traffic Arrow type-3 (Bus Sign) Thermoplastic paint finish white colour
- Pedestrian & Rumput bh 8.00 139,120 1,112,960 -
Zebra Cross
Zebra Cross Thermoplastic paint finish white colour
- uk. 10700x4330mm bh 1.00 139,120 139,120 -
- uk. 9900x4330mm bh 1.00 139,120 139,120 -
Parking Line
Zebra Cross Thermoplastic paint finish white colour
- Mobil uk. 5000mm bh 300.00 139,120 41,736,000 -
- Motor uk. 2000mm bh 55.00 139,120 7,651,600 -
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)
VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus dilapisi
core darin.
VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead dan jasa
Pemborong.
Water Feature
Struktur Kolam beton bertulang, termasuk beton besi & bekisting,
perapihan dan alat bantu
- Drop Off m3 26.61 3,338,870 88,839,518 -
Pagar
Pagar Besi (type-1) h:2400mm terdiri dari kombinasi Besi Hollow
Galvanis & plat galvanis uk.150x150mm, 80x80mm, kolom pagar beton
bertulang dan pasangan bata finish expose, sloof beton bertulang dan
pondasi batu kali termasuk perapihan perkuatan sesuai gambar dan
spesifikasi
- Zona Depan m' 31.40 612,126 19,220,770 -
Pagar BRC h:1800mm terdiri dari pagar BRC 1800x2400mm & pipa besi
Ø5cm, pondasi kolom beton 250x250mm dan pasangan bata, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi (Provisional)
Zona Depan m' 169.60 389,535 66,065,138 -
Railling
Railling Pengaman h:1000mm terdiri dari railling pipa besi galvanize
Ø3", pedestal dan kolom beton bertulang finish aci + cat, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi
- Jembatan Pintu Keluar VIP m' 47.94 1,112,957 53,350,715 -
Bangku Taman
Bangku Taman h:450mm terdiri dari beton cor bertulang, plat baja
t:7mm, pasangan bata finish plester aci, buis beton dan capping batu
andesit Diva black polish termasuk perapihan perkuatan sesuai gambar
dan spesifikasi
- Zona Depan m2 42.55 37,562 1,598,276 -
Tempat Sampah
Tempat Sampah Ø350mm h:700mm terdiri dari rangka luar besi plat
perporated, rangka dalam fiber, tutup alumunium, pondasi dudukan,
termasuk perapihan perkuatan sesuai gambar dan spesifikasi
(Provisional)
- Zona Depan bh 36.00 14,050 505,800 -
Treegrids
Treegrids uk. 1200x1200mm terdiri dari besi cor finish zincromate, pasir
urug, rabat beton finish aci, dudukan treegrids besi siku, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi
- Zona Depan bh 8.00 556,480 4,451,840 -
Gate
Ticket Booth uk. 1700x928x2150mm termasuk sloof beton bertulang
dan pondasi batu kali, perapihan perkuatan sesuai gambar dan
spesifikasi
- Main VIP Entrance bh 3.00 4,451,830 13,355,490 -
- Area Spectator Entrance bh 3.00 4,451,830 13,355,490 -
- Area Spectator Exit bh 2.00 4,451,830 8,903,660 -
- Area Parkir VIP Exit bh 3.00 4,451,830 13,355,490 -
Bollard Ø200mm h:900mm terdiri dari beton cor bertulang finish aci
halus termasuk pemasangan, perapihan perkuatan sesuai gambar dan
spesifikasi
- Main Entrance bh 12.00 117,950 1,415,400 -
- Area Spectator Entrance bh deleted - -
- Area Spectator Exit bh deleted - -
- Area Parkir VIP Exit bh deleted - -
Logo
Logo Pulomas Jaya, termasuk perapihan perkuatan sesuai gambar dan
spesifikasi
- Kolom Pagar Type-1 bh 7.00 556,480 3,895,360 -
Ornamen Patung
Ornamen Patung h:7075mm termasuk pedestal beton bertulang dan
pondasi, pasangan bata finish beton exposed, perapihan perkuatan
sesuai gambar dan spesifikasi
- Zona Depan bh 1.00 38,953,500 38,953,500 -
Ticket Box
Ticket Box Counter uk. 7000x3000x….mm termasuk sloof beton
bertulang dan pondasi batu kali, perapihan perkuatan sesuai gambar
dan spesifikasi
- Zona Depan bh deleted - - -
Tiang Bendera
Tiang Bendera h: 7000mm terdiri dari pipa stainless steel Ø4" & Ø3"
pondasi beton bertulang uk. Diameter 600 tinggi 1500mm dan besi
angkur Ø12mm, termasuk perapihan perkuatan sesuai gambar dan
spesifikasi
- Zona Depan bh 23.00 3,756,230 86,393,290 -
Drainase
Drainase tertutup lebar 500mm, terdiri U-ditch beton precast ex.
Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Depan m' 1,629.99 946,010 1,541,986,840 -
Pergola
Pergola h:2700mm terdiri dari struktur Baja H Beam finish cat besi anti
karat, lapisan atap polycarbonate, pondasi kolom beton, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi
- Plaza Utama m2 479.51 278,240 133,418,028 -
Bak Kontrol
Bak Kontrol ukuran 600x600x450mm terdiri dari struktur beton
bertulang, waterproofing integral, n, termasuk perapihan perkuatan
sesuai gambar dan spesifikasi
- Area Drop Off Tribune bh 6.00 333,890 2,003,340 -
2,006.02
DAFTAR No. XII.1 - PEKERJAAN LANDSCAPE ZONA DEPAN Vol Vol (+/-) Harsat Rp Rp (+/-)
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
PEKERJAAN PEMBESIAN
A Mutu baja tulangan < Ø 10 mm = U-24 dan ≥ Ø 10 mm = U-40:
1) Pelat jembatan kg 22,157.69 - 8,859 196,283,897 -
2) Pelat Injak kg 1,468.64 - 8,859 13,009,947 -
3) Capping beam kg 5,864.30 - 8,859 51,948,902 -
PEKERJAAN LAIN-LAIN
B Expansion joint
1) Pelat jembatan m' 28.30 (5) 61,213 1,732,318 (287,699)
2) Pelat jembatan m' 28.30 (5) 61,213 1,732,318 (287,699)
D Grouting
1) Pelat jembatan m' 28.30 1,391,196.46 39,370,860 -
2) Pelat jembatan m' 28.30 1,391,196.46 39,370,860 -
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN TANAH
Pembersihan lokasi
Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan
ditentukan) untuk urugan dan sisanya di buang ke luar site, berikut
alat-alat bantuTapak
- Pondasi dan kelengkapannya pada: m3 4.49 (4.49) 61,213 274,975 (274,975)
Pekerjaan Urugan
PEKERJAAN BETON
PEKERJAAN PEMBESIAN
A Wiremesh M8-150
1) Pelat, pada:
- Lantai 1 m2 28.69 - 53,220 1,526,749 -
B Bekisting bondex
1) Pelat, pada: m2 28.69 - 100,570 2,885,102 -
PEKERJAAN LAIN-LAIN
A Pondasi Tapak
1) Beton tumbuk m3 0.38 - 100,570 38,619 -
PEKERJAAN BAJA
VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus
dilapisi core darin.
VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead dan
jasa Pemborong.
Pagar
Pagar Besi (type-2) h:2400mm terdiri dari Besi Hollow Galvanis
uk.150x150mm, 80x80mm, dan plat galvanis 10x80mm , sloof beton
bertulang dan pondasi batu kali termasuk perapihan perkuatan sesuai
gambar dan spesifikasi
- Zona Penunjang m' 803.61 612,126 491,910,441 -
Railling
Railling Pengaman h:1700mm terdiri dari railling pipa besi galvanize
Ø60mm & Ø50mm, pedestal beton bertulang finish aci, termasuk
perapihan perkuatan sesuai gambar dan spesifikasi
- Zona Penunjang m' 142.33 1,112,957 158,406,081 -
Bangku Taman
Bangku Taman h:450mm terdiri dari beton cor bertulang, plat baja
t:7mm, pasangan bata finish plester aci, buis beton dan capping batu
andesit Diva black polish termasuk perapihan perkuatan sesuai
gambar dan spesifikasi
- Zona Penunjang m2 21.64 37,562 812,886 -
Treegrids
Treegrids uk. 1200x1200mm terdiri dari besi cor finish zincromate,
pasir urug, rabat beton finish aci, dudukan treegrids besi siku,
termasuk perapihan perkuatan sesuai gambar dan spesifikasi
- Parkir Mobil Zona Penunjang bh 10.00 556,480 5,564,800 -
- Smoking Area Zona Penunjang bh 4.00 556,480 2,225,920 -
Drainase
Drainase tertutup lebar 500mm, terdiri U-ditch beton precast ex.
Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Penunjang m' 937.71 946,010 887,083,037 -
VII Bila dasar tempat tanaman dari plat dan bak bunga beton harus dilapisi
core darin.
VIII Untuk harga satuan pekerjaan harus sudah termasuk overhead dan jasa
Pemborong.
I PEKERJAAN PAGAR
Pagar
Pagar Besi (type-2) h:2400mm terdiri dari Besi Hollow Galvanis
uk.150x150mm, 80x80mm, dan plat galvanis 10x80mm , sloof beton
bertulang dan pondasi batu kali termasuk perapihan perkuatan sesuai
gambar dan spesifikasi
Pagar Beton (type-3) h:3000mm terdiri dari precast panel uk. 2400x400
kolom precast panel dan pondasi beton termasuk perapihan perkuatan
sesuai gambar dan spesifikasi
- Zona Cross Country m' 1,865.30 890,370 1,660,807,161 -
Gabion
Gabion h:450mm terdiri dari pasangan batu kali h:700mm, finish caping
…... , kawat ayam, termasuk perapihan perkuatan sesuai gambar dan
spesifikasi
- Zona Cross Country m2 382.30 500,830 191,467,309 -
Signage Board
Gabion Signage board uk. 3500x800mm terdiri strukutr besi hollow anti
karat paint finish, dan acrylic, termasuk perapihan perkuatan sesuai
gambar dan spesifikasi
- Zona Cross Country bh 1.00 5,564,790 5,564,790 -
Drainase
Drainase tertutup lebar 600mm, terdiri U-ditch beton precast ex.
Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Cross Country m' 89.41 946,010 84,582,754 -
Drainase
Drainase tertutup lebar 700mm, terdiri U-ditch beton precast ex.
Dusaspun, cover u-ditch, termasuk galian, pemasangan, perapihan
perkuatan sesuai gambar dan spesifikasi
- Zona Cross Country m' 665.13 946,010 629,219,631 -
Bak Kontrol
Bak Kontrol ukuran 700x700x450mm terdiri dari struktur beton
bertulang, waterproofing integral, n, termasuk perapihan perkuatan
sesuai gambar dan spesifikasi
DAFTAR No. XII.3 - PEKERJAAN LANDSCAPE ZONA CROSS COUNT Vol Vol (+/-) Harsat Rp Rp (+/-)
SPECIAL FOOTING
A LAPISAN BAWAH
1 Geotextile non woven pori maks 180 gr /m2 m2 8,000.00 15.69 22,259 178,073,147 349,246
2 Porous asphalt tebal 6 cm m2 8,000.00 15.69 166,832 1,334,658,237 2,617,598
3 Gravel 2/3, tebal 125 mm m2 8,000.00 15.69 52,300 418,401,779 820,590
4 Geotextile non woven pori maks 75 micron m2 8,000.00 15.69 22,259 178,073,147 349,246
5 Sub base dia 15-30 cm, Tebal 44,5 cm m2 8,000.00 15.69 168,831 1,350,650,986 2,648,964
B SPECIAL FOOTING :
1 Pasir dengan campuran serat fibre geotextile dan anti debu m2 8,000.00 BY OTHER
(Material Ex, Import)
PAGAR
1 Balok beton Ukuran 30x65cm (Provisional) m3 70.21 - 835,830 58,680,482 -
2 Besi Tulangan Rasio 90 kg/m3 kg 6,318.90 8,859 55,975,976
3 Bekisting kayu m2 594.05 100,570 59,743,558
4 Railing tinggi 1600mm dengan pipa pembagi co extrude m' 360.03 0.32 973,840 350,613,563 309,681
PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght
max 4m co extrude PVC/ASA dan kelengkapan lainnya sesuai
gambar dan spesifikasi
DAFTAR NO. XIII.1 - PEKERJAAN LANTAI ARENA FIELD OF PLAY 3,984,870,875 7,095,326
Dipindahkan ke Penjumlahan Total
DAFTAR No. XIII - OUTDOOR ARENA Vol Vol (+/-) Harsat Rp Rp (+/-)
SPECIAL FOOTING
A LAPISAN BAWAH
1 Geotextile non woven pori maks 180 gr /m2 m2 6,000.00 410.66 22,259 133,554,860 9,140,940
2 Porous asphalt tebal 6 cm m2 6,000.00 410.66 166,832 1,000,993,678 68,511,344
3 Gravel 2/3, tebal 125 mm m2 6,000.00 410.66 52,300 313,801,334 21,477,609
4 Geotextile non woven pori maks 75 micron m2 6,000.00 410.66 22,259 133,554,860 9,140,940
5 Sub base dia 15-30 cm, Tebal 44,5 cm m2 6,000.00 410.66 168,831 1,012,988,240 69,332,292
B SPECIAL FOOTING :
1 Pasir dengan campuran serat fibre geotextile dan anti debu m2 6,000.00 BY OTHER
(Material Ex, Import)
C PAGAR
1 Concrete tebal 30x65cm m3 72.00 - 835,830 60,179,760 -
2 Besi Tulangan Rasio 90 kg/m3 kg 6,480.00 8,859 57,403,080 -
3 Bekisting kayu m2 511.50 100,570 51,441,555 -
4 Railing tinggi 1600mm dengan pipa pembagi co extrude
PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght max
4m co extrude PVC/ASA dan kelengkapan lainnya sesuai m' 310.00 10.27 973,840 301,890,400 10,001,337
gambar dan spesifikasi
SPECIAL FOOTING
A LAPISAN BAWAH
1 Geotextile non woven pori maks 180 gr /m2 m2 1,500.00 22,259 33,388,715 -
2 Porous asphalt m2 1,500.00 166,832 250,248,419 -
3 Gravel 2/3 tebal 125 mm m2 1,500.00 52,300 78,450,334 -
4 Geotextile non woven pori maks 75 micron m2 1,500.00 22,259 33,388,715 -
5 Sub base dia 15-30 cm m2 1,500.00 168,831 253,247,060 -
B SPECIAL FOOTING :
1 Pasir dengan campuran serat fibre geotextile dan anti debu m2 1,500.00 BY OTHER
(Material Ex, Import)
C PAGAR
1 Balok beton Ukuran 30x65cm (Provisional) m3 33.15 835,830 27,707,765 -
2 Besi Tulangan Rasio 90 kg/m3 kg 2,983.50 8,859 26,429,335 -
3 Bekisting kayu m2 280.50 100,570 28,209,885 -
4 Railing tinggi 1600mm dengan pipa pembagi co extrude m' 170.00
PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght max
4m co extrude PVC/ASA dan kelengkapan lainnya sesuai 973,840 165,552,800 -
gambar dan spesifikasi
SPECIAL FOOTING
A LAPISAN BAWAH :
1 Geotextile non woven pori maks 180 gr /m2 m2 4,960.00 440.03 22,259 110,405,351 9,794,691
2 Porous asphalt tebal 6 cm m2 4,960.00 440.03 166,832 827,488,107 73,411,208
3 Gravel 2/3, tebal 125 mm m2 4,960.00 440.03 52,300 259,409,103 23,013,667
4 Geotextile non woven pori maks 75 micron m2 4,960.00 440.03 22,259 110,405,351 9,794,691
5 Sub base dia 15-30 cm, Tebal 44,5 cm m2 4,960.00 440.03 168,831 837,403,612 74,290,869
B SPECIAL FOOTING :
1 Pasir dengan campuran serat fibre geotextile dan anti debu m2 4,960.00 BY OTHER
(Material Ex, Import)
C PAGAR :
1 Balok beton Ukuran 30x65cm (Provisional) m3 55.38 - 835,830 46,288,265 -
2 Besi Tulangan Rasio 90 kg/m3 kg 4,984.20 8,859 44,152,536 -
3 Bekisting kayu m2 468.60 100,570 47,127,102 -
4 Railing tinggi 1600mm dengan pipa pembagi co extrude
PVC/ASA dan Hand railing 15x5cm 3(tiga) buah, rail lenght max
4m co extrude PVC/ASA dan kelengkapan lainnya sesuai m' 284.00 16.00 973,840 276,570,560 15,581,440
gambar dan spesifikasi
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.186
32 mm 6.313
Monitoring lapangan :
D PEK. DOLLY
Pekerjaan Dolly tiang pancang ukuran 250 x 250 mm, dengan titik 15 Rate only
kedalaman = 2 ~ 3 m' - -
Test beban pancang + PDA (Pile Driving Analysis) test ttk 1.00 7,790,700
7,790,700 -
II Volume galian, urugan dihitung netto, tidak ada ekstra untuk tempat
kerja
VII Harga satuan pekerjaan sudah termasuk alat-alat yang diperlukan dan
sesuai gambar spesifikasi
B Pekerjaan Galian
Pekerjaan galian tanah, termasuk buang di site (lokasi akan ditentukan)
untuk urugan dan sisanya di buang ke luar site, berikut alat-alat bantu
dan kelengkapannya pada:
- Pondasi batu kali m3 165.23 - 55,640 9,193,397 -
- Pile Cap Genset m3 5.76 (0.00) 55,640 320,486 (0)
- Plat STP m3 92.84 - 55,640 5,165,590 -
- Tie Beam Genset m3 9.72 2.96 55,640 540,821 164,583
C Pekerjaan Urugan
Urugan pasir urug tebal : 10 cm, termasuk pemadatan, alat alat bantu
berikut peralatan perlengkapan sesuai spesifikasi dan gambar
- Dibawah plat lantai inc Tie Beam Genset m3 106.11 - 272,340 28,897,997 -
- Pondasi batu kali m3 11.55 - 272,340 3,145,527 -
- Dibawah plat lantai inc Tie Beam STP m3 2.69 - 272,340 732,867 -
- Pile Cap Genset m3 0.54 (0.00) 272,340 147,064 (0)
VI Diameter Kg/m
6 mm 0.222
8 mm 0.395
10 mm 0.617
12 mm 0.888
13 mm 1.042
16 mm 1.578
19 mm 2.226
22 mm 2.985
25 mm 3.853
29 mm 5.185
32 mm 6.315
PEKERJAAN BETON
A Beton mutu = K-125, lantai kerja tebal = 50 mm, pada:
1) Di bawah pelat lantai, Tie beam Genset m3 18.41 - 667,780 12,293,830 -
2) Di bawah pelat lantai, Tie beam STP m3 1.35 - 667,780 898,498 -
3) Pile cap Genset m3 0.27 (0.00) 667,780 180,301 (0)
PEKERJAAN PEMBESIAN
A Wiremesh 2 lapis M8-150
1) Pelat lantai dasar, pada:
- Genset m2 346.50 (166.73) 124,830 43,253,595 (20,812,282)
- Ramp m2 346.50 - 124,830 43,253,595 -
PEKERJAAN LAIN-LAIN
H Bak kontrol
1) Beton m3 0.16 - 782,410 124,873 -
2) Besi kg 29.89 - 8,859 264,762 -
3) Bekisting m2 2.02 - 129,920 261,919 -
4) Galian Tanah m3 0.28 - 55,640 15,540 -
5) Urugan Pasir 10 cm m3 0.05 - 667,780 32,721 -
6) Lantai kerja 5 cm m3 0.02 - 782,410 19,169 -
7) Waterstop m' 2.80 - 94,600 264,880 -
8) Integral m3 0.16 - 100,170 15,987 -
9) Manhole uk 100 x 60 cm unit 1.00 - 222,591 222,591 -
1) lantai atap
- Atap dak m2 201.47 124.36 127,690 25,725,066 15,879,688
DAFTAR NO. XIV.1.3 - PEKERJAAN STRUKTUR BETON
Dipindahkan ke Penjumlahan Total 676,847,284 (61,891,153)
II
Harga satuan plesteran biasa atau drymix sudah termasuk
acian, skonengan, tali air , ketrikan atau bobokan beton
maupun bata , kawat ayam (jika diperlukan) dan semua
pekerjaan bantu yang berhubungan dengan plesteran. Volume
plesteran dan acian sudah ditambahkan 10cm di atas plafond
- Lantai 1
Baseplate pdtm m2 63.93 18,360 1,173,736 -
Gardu PLN m2 90.64 18,360 1,664,165 -
Genset m2 164.20 18,360 3,014,767 -
Kapasitor bank m2 58.02 18,360 1,065,299 -
Ruang Trafo m2 60.62 18,360 1,112,932 -
Ruang PDTR m2 77.59 18,360 1,424,552 -
III Harga satuan pintu dan jendela aluminium sudah termasuk angkur,
sealant, karet, kaca, pengelasan, pemasangan kolom praktis
sekeliling pintu & jendela, dan peralatan bantu yang diperlukan
dan bahan yang terbuang (waste).
A PINTU BAJA
Pintu Baja P1 terdiri dari 2 daun pintu ukuran 2120x2150mm
kusen besi finish powder coating, lengkap terpasang termasuk,
hardware, accesories
Ruang Kapasitor, danPDTR,
Ruang perlengkapan bantuRuang
Ruang Trafo, lainnyagardu
sesuai
PLN
- Lantai 1 unit 5.00 (2.00) 2,281,562 11,407,811 (4,563,124)
Hardware :
Ring handle art-8-3 SS bh 1.00 2.00 - -
Shaft door art -542 Nickel bh 1.00 2.00 - -
Anak kunci shaft door art-543 Nickel bh 1.00 2.00 - -
Hinges Gracia BB 4"x3"x3 mm SS bh 2.00 4.00 - -
Hardware :
Ring handle art-8-3 SS bh 1.00 (1.00) - -
Shaft door art -542 Nickel bh 1.00 (1.00) - -
Anak kunci shaft door art-543 Nickel bh 1.00 (1.00) - -
Hinges Gracia BB 4"x3"x3 mm SS bh 2.00 (2.00) - -
B JENDELA
FLOOR HARDENER
II Harga satuan sudah termasuk angkur-angkur, mur, baut, skrup, list kayu,
kawat-kawat, penggantung, lubang lampu atau grill AC.
IV Luas plafond dan plafond vertikal (drop ceiling) tidak dikurangi dengan
luas kolom, lampu dan grill A/C
V Harga satuan pekerjaan cat plafond salah termasuk pengertian cat dasar
(plamur, meni, stained, sealer dan bahan bantu lainnya)
VII Harga satuan pekerjaan plafond sudah termasuk corner bead & Shadow
Line
A Beton exposed aci halus, termasuk alat bantu lainnya dengan peralatan
perlengkapan terpasang sesuai dengan spesifikasi dan gambar pada :
III Setiap pekerjaan harus sesuai dengan petunjuk yang disyaratkan pabrik
pembuat.
III Harga satuan jendela kaca dan pintu kaca, sudah termasuk kunci &
alat-alat penggantung, perlengkapan yang dibutuhkan seperti mur,
baut, handle, engsel, kait angin, sealant, dan kelengkapannya., rubber
gasket (sealant), neoprene, penyetelan dan pemasangan.
IV Dimensi (ukuran) daun pintu dan daun jendela yang tercantum di dalam
daftar ini harus disesuaikan dengan gambar.
VI Harus sesuai spesifikasi teknis dan gambar gambar tender dan sketch
detail
A KISI-KISI
Kisi-kisi bata finished cat uk. 500 x 200 mm berikut alat bantu dengan
peralatan perlengkapan sesuai dengan spesifikasi dan gambar pada :
(Provisional)
- Eksterior
Genset m2 245.80 136,870 33,643,303 -
I
Jumlah satuan pekerjaan maupun jumlah biaya cadangan (contingency) dan
Dana Bersyarat (Provisional Sum) yang tercantum dalam daftar ini adalah masih
diperkirakan (belum pasti), tetapi harga satuannya sudah tetap (mengikat),
sedangkan volume maupun biaya yang pasti akan dihitung kemudian.
II Biaya perkiraan dan contingency ini digunakan jika terdapat pekerjaan tambah
atas instruksi tertulis yang diterbitkan oleh Manajemen Konstruksi atau Pemberi
Tugas.
III
Harga satuan yang dicantumkan oleh Pemborong sudah mencakup keuntungan,
biaya tidak terduga seperti : waktu yang tidak produktif, lembur, bahan yang
terbuang, bahan bakar, asuransi, peralatan, biaya kerusakan, transportasi,
administrasi, supervisi, alat
IV 1 ( satu ) hari sama dengan 7 ( tujuh ) jam kerja atau 8 ( delapan ) jam termasuk
1 ( satu ) jam untuk istirahat.
V
Pemborong harus mengisi harga pada semua butir-butir yang terlampir.
Dana bersyarat untuk pekerjaan atau biaya yang belum terdefenisi jelas
pada gambar dan spesifikasi / belum jelas
A. Engineering Equipment
1 Tractor Model racetracks (perbuah) 376,190,100 buah 2.00 -
2 Mobil tangki 5000 liter (per unit) 275,000,000 unit 3.00 -
3 Arena Surface 135,000,000 ls 1.00 -
4 Riding track drag 57,142,800 ls 1.00 -
B. Competition Equipment
1 Show jumping & Eventing (per buah) 15,000,000 buah 30.00 -
2 Horse truck transport 380,952,000 unit 2.00 -
3 Timer + 2 Scoring board 714,285,000 unit 2.00 -
4 Struktur Covered training area 2,500,000,000 unit 1.00 -
5 Special Footing 8,500,000,000 item 1.00 -
6 Cadangan Genset 1,600,000,000 item 1.00 -
XIV.2 - Dana bersyarat untuk biaya cadangan (Provisional Sum for Contingencies)
Molen (kap. 250 It), dengan operator , bahan bakar , supervisi hari 1.00
Molen (kap. 350 It), dengan operator, bahan bakar , supervisi hari 1.00
Alat Penggetar Beton , dengan operator , bahan bakar hari 1.00
Mesin las dengan operator dan bahan bakar hari 1.00
Mobil pick up dengan open dan bahan bakar hari 1.00
Truk kapasitas 5 ton dengan supir dan bahan bakar hari 1.00
Truk kapasitas 8 ton dengan supir dan bahan bakar hari 1.00
Mesin wales 10 ton, dengan supir dan bahan bakar hari 1.00
Jack hammering dengan operator dan bahan bakar hari 1.00
Stumper dengan operator, bahan bakar , supervisi hari 1.00
Backhoe loader dengan operator , bahan bakar (kap = 0,25 m³) hari 1.00
Dozer (type D6) dengan operator , bahan bakar (kap = …… m³) hari 1.00
Dozer (type D7) dengan operator , bahan bakar (kap = ...… m³) hari 1.00
Tower crane, dengan operator dan bahan bakar hari 1.00
Hoist dengan operator dan bahan bakar (kap = 2 x 1 ton) hari 1.00
Kompressor, dengan operator dan bahan bakar hari 1.00
Generating set kap.100 Kva , dengan operator , bahan bakar hari 1.00
Scaffolding (diluar/pinggir bangunan) untuk setiap 1 M² hari 1.00
Gudang sementara m² 1.00
Pasir m3 1.00
Batu split m3 1.00
Batu kali m3 1.00
Semen @ 50 kg Zak 1.00
Beton fc' 30 MPa m3 1.00
Beton fc' 25 MPa m3 1.00
Batu bata Bh 1.00
Celcon block Bh 1.00
Besi beton ulir Kg 1.00
Besi beton polos Kg 1.00
Baja siku Kg 1.00
Baja Channel Kg 1.00
Baja WF Kg 1.00
Kayu Nyatoh m3 1.00
Kayu Merbau m3 1.00
Multiplek 9 mm Lbr 1.00
Multiplek 12 mm Lbr 1.00
DAFTAR NO. XIV - PROVISIONAL SUM, Provisional Sum for Contingencies and Dayworks Allowances -
Dipindahkan ke Penjumlahan Total
I
Kontrak ini bersifat Harga Tetap (Lump Sum Fix Price), kecuali dimana
dicantumkan Provisional atau "Provisional Sum". Kontraktor wajib
menghitung kembali volume pekerjaan dan memeriksa satuannya yang dibuat
oleh Quantity Surveyor dan jika menurut perhitungan Kontraktor volume dan
atau satuannya tidak sesuai atau terdapat item pekerjaan yang belum
tercantum, maka Kontraktor dapat merubah atau menambahkan pada
lampiran khusus yang dibuat untuk pekerjaan tambah atau kurang.
III
Dalam mengajukan harga pekerjaan ini Pemborong harus sudah
mempertimbangkan untuk memasukkan semua biaya pengeluaran pekerjaan
dan tidak ada tuntutan di kemudian hari terhadap Pemberi tugas, bila daftar
uraian pekerjaan/BQ ini dipandang tidak lengkap.
IV
Semua hal yang tidak tercantum disini dianggap sudah termasuk didalam
penawaran dan semua resiko baik mengenai eskalasi harga, salah hitung
terhadap volume maupun harga yang diajukan dan kekurangan item pekerjaan
dan biaya-biaya lain yang tak terduga adalah tetap menjadi tanggung jawab
Pemborong. Karena BQ sesudah penawaran adalah BQ Pemborong
V
Pemborong sudah harus memperhitungkan/mempertimbangkan semua
kemungkinan-kemungkinan yang terjadi di lapangan dalam pelaksanaan
berhubung adanya Pemborong-Pemborong lain unutk pelaksanaan Proyek
tersebut
Rapat Proyek
4 Item 1 200,000 200,000
Pemborong harus menyediakan fasilitas yang diperlukan termasuk akomodasi
dan konsumsi (snack) untuk pelaksanaan rapat rutin di proyek dengan Pemberi
Tugas, Pimpinan Proyek, para Konsultan dan para Kontraktor paket lain serta
mengkoordinasikannya.
Pengadaan Gambar
5 Pengadaan gambar For Construction untuk pelaksanaan by Perenana, Item 1 300,000 300,000
sedangkan memperbanyak untuk keperluan kerja di lapangan termasuk 2 (dua)
set untuk keperluan pengawasan.
Laporan
6 Pemborong wajib membuat Laporan Harian, Mingguan dan Bulanan, laporan
Item 1 exclude -
progress pekerjaan serta laporan lainnya
Keamanan Proyek
13 Item 1 3,000,000 3,000,000
2 Bongkaran Plat inc Screed dan finishing lantai diatasnya, tebal = 15cm, pada : (Reff : Gbr.)
- Denah Pelat Elevasi +4.36 m2 93.93 194,768 18,294,512 -
- Denah Pelat Elevasi +8.36 m2 72.83 194,768 14,184,917 -
- Denah Pelat Elevasi +12.36 m2 49.78 194,768 9,695,526 -
4 Bongkaran Tangga (Plat Miring, Balok Bordes, Plat Bordes, dan Trap tangga), tinggi trap = 17cm pada : (Reff : )
- Denah Balok Elevasi +4.36 m2 81.30 194,768 15,834,598 -
- Denah Balok Elevasi +8.36 m2 81.30 194,768 15,834,598 -
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-2 Str1 Hal.1/390 BUILDING DAN FASILITAS PAKET 2
DAFTAR No. 2 - PEKERJAAN BONGKARAN STRUKTUR HARGA TOTAL TOTAL +/-
SAT VOLUME VOLUME +/-
SATUAN ( Rp ) ( Rp )
DAFTAR NO. 2.1. - PEKERJAAN BONGKARAN STRUKTUR
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-2 Str1 Hal.2/390 BUILDING DAN FASILITAS PAKET 2
PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR BANGUNAN TRIBUN
PROYEK EQUESTRIAN - JAKARTA
DAFTAR NO. 3 -PEKERJAAN BONGKARAN ARSITEKTUR VOLUME HARGA SATUAN TOTAL HARGA
SAT VOLUME
+/- Rp Rp
Catatan Harga
I
Harga satuan bongkaran sudah termasuk buangan keluar site.
II
Harga satuan bongkaran sudah termasuk pembersihan area site
III
Harga satuan bongkaran dinding kaca dan ralling kaca sudah
termasuk assesoris, kelengkapan lainnya, pembersihan sebelum
dibongkar dan penyimpanan ditempat yang diinstruksikan MK atau
Owner.
VII Harga satuan bongkaran pintu dan jendela sudah termasuk assesoris
dan kelengkapan lainnya.
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-3 Ars1 Hal.3/390 BUILING DAN FASILITAS PAKET 2
PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR BANGUNAN TRIBUN
PROYEK EQUESTRIAN - JAKARTA
DAFTAR NO. 5 - TOTAL PEKERJAAN BIONGKARAN TRIBUN HARGA SATUAN TOTAL HARGA
SAT VOLUME
Rp. Rp.
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf.5 Total1Hal.4/390 BUILDING DAN FASILITAS PAKET 2
PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR HORSE STABLE
PROYEK EQUESTRIAN - JAKARTA
I
Kontrak ini bersifat Harga Tetap (Lump Sum Fix Price), kecuali dimana
dicantumkan Provisional atau "Provisional Sum". Kontraktor wajib
menghitung kembali volume pekerjaan dan memeriksa satuannya yang
dibuat oleh Quantity Surveyor dan jika menurut perhitungan Kontraktor
volume dan atau satuannya tidak sesuai atau terdapat item pekerjaan yang
belum tercantum, maka Kontraktor dapat merubah atau menambahkan pada
lampiran khusus yang dibuat untuk pekerjaan tambah atau kurang.
III
Dalam mengajukan harga pekerjaan ini Pemborong harus sudah
mempertimbangkan untuk memasukkan semua biaya pengeluaran pekerjaan
dan tidak ada tuntutan di kemudian hari terhadap Pemberi tugas, bila daftar
uraian pekerjaan/BQ ini dipandang tidak lengkap.
IV
Semua hal yang tidak tercantum disini dianggap sudah termasuk didalam
penawaran dan semua resiko baik mengenai eskalasi harga, salah hitung
terhadap volume maupun harga yang diajukan dan kekurangan item
pekerjaan dan biaya-biaya lain yang tak terduga adalah tetap menjadi
tanggung jawab Pemborong. Karena BQ sesudah penawaran adalah BQ
Pemborong
V
Pemborong sudah harus memperhitungkan/mempertimbangkan semua
kemungkinan-kemungkinan yang terjadi di lapangan dalam pelaksanaan
berhubung adanya Pemborong-Pemborong lain unutk pelaksanaan Proyek
tersebut
Rapat Proyek
4 Item 1 200,000 200,000
Pemborong harus menyediakan fasilitas yang diperlukan termasuk akomodasi
dan konsumsi (snack) untuk pelaksanaan rapat rutin di proyek dengan
Pemberi Tugas, Pimpinan Proyek, para Konsultan dan para Kontraktor paket
lain serta mengkoordinasikannya.
Pengadaan Gambar
5 Pengadaan gambar For Construction untuk pelaksanaan by Perenana, Item 1 300,000 300,000
sedangkan memperbanyak untuk keperluan kerja di lapangan termasuk 2
(dua) set untuk keperluan pengawasan.
Laporan
6 Pemborong wajib membuat Laporan Harian, Mingguan dan Bulanan, laporan
progress pekerjaan serta laporan lainnya Item 1 exclude -
Keamanan Proyek
13 Item 1 3,000,000 3,000,000
2 Bongkaran Plat inc Screed dan finishing lantai diatasnya, tebal = 15cm, pada : (Reff : Gbr.)
- Denah Pelat Elevasi +4.36 m2 194,768 - -
- Denah Pelat Elevasi +8.36 m2 194,768 - -
- Denah Pelat Elevasi +12.36 m2 194,768 - -
4 Bongkaran Tangga (Plat Miring, Balok Bordes, Plat Bordes, dan Trap tangga), tinggi trap = 17cm pada : (Reff : )
- Denah Balok Elevasi +4.36 m2 194,768 - -
- Denah Balok Elevasi +8.36 m2 194,768 - -
Catatan Harga
I
Harga satuan bongkaran sudah termasuk buangan keluar site.
II
Harga satuan bongkaran sudah termasuk pembersihan area site
III
Harga satuan bongkaran dinding kaca dan ralling kaca sudah
termasuk assesoris, kelengkapan lainnya, pembersihan sebelum
dibongkar dan penyimpanan ditempat yang diinstruksikan MK atau
Owner.
VII Harga satuan bongkaran pintu dan jendela sudah termasuk assesoris
dan kelengkapan lainnya.
- Lantai Dasar
Farrier m2 274.25 42,292 11,598,683
Horstable blok A,B,C,D m2 1,828.68 42,292 77,339,216
- Lantai 2
Horstable blok A,B,C,D m2 2,016.44 42,292 85,280,031
PEKERJAAN STRUKTUR -
I
Kontrak ini bersifat Harga Tetap (Lump Sum Fix Price), kecuali dimana
dicantumkan Provisional atau "Provisional Sum". Kontraktor wajib
menghitung kembali volume pekerjaan dan memeriksa satuannya yang dibuat
oleh Quantity Surveyor dan jika menurut perhitungan Kontraktor volume dan
atau satuannya tidak sesuai atau terdapat item pekerjaan yang belum
tercantum, maka Kontraktor dapat merubah atau menambahkan pada
lampiran khusus yang dibuat untuk pekerjaan tambah atau kurang.
III
Dalam mengajukan harga pekerjaan ini Pemborong harus sudah
mempertimbangkan untuk memasukkan semua biaya pengeluaran pekerjaan
dan tidak ada tuntutan di kemudian hari terhadap Pemberi tugas, bila daftar
uraian pekerjaan/BQ ini dipandang tidak lengkap.
IV
Semua hal yang tidak tercantum disini dianggap sudah termasuk didalam
penawaran dan semua resiko baik mengenai eskalasi harga, salah hitung
terhadap volume maupun harga yang diajukan dan kekurangan item pekerjaan
dan biaya-biaya lain yang tak terduga adalah tetap menjadi tanggung jawab
Pemborong. Karena BQ sesudah penawaran adalah BQ Pemborong
V
Pemborong sudah harus memperhitungkan/mempertimbangkan semua
kemungkinan-kemungkinan yang terjadi di lapangan dalam pelaksanaan
berhubung adanya Pemborong-Pemborong lain unutk pelaksanaan Proyek
tersebut
Rapat Proyek
4 Item 1 200,000 200,000
Pemborong harus menyediakan fasilitas yang diperlukan termasuk akomodasi
dan konsumsi (snack) untuk pelaksanaan rapat rutin di proyek dengan Pemberi
Tugas, Pimpinan Proyek, para Konsultan dan para Kontraktor paket lain serta
mengkoordinasikannya.
Pengadaan Gambar
5 Pengadaan gambar For Construction untuk pelaksanaan by Perenana, Item 1 300,000 300,000
sedangkan memperbanyak untuk keperluan kerja di lapangan termasuk 2 (dua)
set untuk keperluan pengawasan.
Laporan
6 Pemborong wajib membuat Laporan Harian, Mingguan dan Bulanan, laporan
Item 1 exclude -
progress pekerjaan serta laporan lainnya
Keamanan Proyek
13 Item 1 3,000,000 3,000,000
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-2 Str3 Hal.1/390 BUILDING DAN FASILITAS PAKET 2
DAFTAR No. 2 - PEKERJAAN BONGKARAN STRUKTUR HARGA TOTAL
SAT VOLUME VOLUME +/-
SATUAN ( Rp )
DAFTAR NO. 2.1. - PEKERJAAN BONGKARAN STRUKTUR
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf-2 Str3 Hal.2/390 BUILDING DAN FASILITAS PAKET 2
PAKET PEKERJAAN BONGKARAN STRUKTUR DAN ARSITEKTUR BANGUNAN COVERED TRAINING AREA
PROYEK EQUESTRIAN - JAKARTA
DAFTAR NO. 4 - TOTAL PEKERJAAN BIONGKARAN TRIBUN HARGA SATUAN TOTAL HARGA
SAT VOLUME
Rp. Rp.
JAKARTA INTERNATIONAL EQUESTRIAN PARK Daf.4 Total3Hal.3/390 BUILDING DAN FASILITAS PAKET 2
REKAPITULASI PENJUMLAHAN TOTAL
PAKET PEKERJAAN BUILDING & FASILITAS ( SAP, ME, LANDSCAPE & INTERIOR) PAKET 2
PROYEK JAKARTA INTERNATIONAL EQUESTRIAN PARK PAKET II
III DAF - III BANGUNAN HORSE STABLE & CHANGING ROOM Rp 22,187,227,799
III.1.A PEKERJAAN STRUKTUR HORSE STABLE Rp 3,698,693,468
III.1.A.1 PEKERJAAN PONDASI Rp Tidak ada -
III.1.A.2 PEKERJAAN TANAH Rp 92,581,628 2,164,276
III.1.A.3 PEKERJAAN STRUKTUR BETON Rp 2,190,804,100 156,080,089
III.1.A.4 PEKERJAAN STRUKTUR BAJA Rp 1,257,063,375 -
III.1.B PEKERJAAN STRUKTUR CHANGING ROOM Rp 605,944,301
III.1.B.1 PEKERJAAN TANAH Rp 37,896,707 (2,485,211)
III.1.B.2 PEKERJAAN STRUKTUR BETON Rp 273,297,958 (2,485,211)
III.1.B.3 PEKERJAAN STRUKTUR BAJA Rp 302,205,268 (2,485,211)
III.2.A PEKERJAAN ARSITEKTUR HORSE STABLE Rp 11,410,258,065
III.2.A.1 PEKERJAAN DINDING Rp 1,450,292,318 (47,123,833)
III.2.A.2 PEKERJAAN PINTU DAN JENDELA Rp 1,437,384,943 485,732,459
III.2.A.3 PEKERJAAN LANTAI Rp 2,499,255,342 525,617,670
III.2.A.4 PEKERJAAN PLAPOND Rp 462,655,730 96,255,469
III.2.A.5 PEKERJAAN SANITARY Rp 172,198,600 (52,029,540)
III.2.A.6 PEKERJAAN LAIN-LAIN Rp 902,165,107 14,452,885
III.2.A.7 PEKERJAAN ATAP Rp 1,497,283,538 1,175,384,829
III.2.A.8 PEKERJAAN FAÇADE Rp 782,872,956 7,859,592
III.2.B PEKERJAAN ARSITEKTUR CHANGING ROOM Rp 589,762,830
III.2.B.1 PEKERJAAN DINDING Rp Include horsestable
III.2.B.2 PEKERJAAN PINTU DAN JENDELA Rp Include horsestable
III.2.B.3 PEKERJAAN LANTAI Rp 33,674,061 -
III.2.B.4 PEKERJAAN PLAPOND Rp 9,837,200 -
III.2.B.5 PEKERJAAN SANITARY Rp by Interior
III.2.B.6 PEKERJAAN LAIN-LAIN Rp 175,115,232 -
III.2.B.7 PEKERJAAN ATAP Rp 212,542,544 21,500,062
III.2.B.8 PEKERJAAN FAÇADE Rp 71,240,161 65,853,571
III.3.A PEKERJAAN MEKANIKAL - ELEKTRIKAL HORSE STABLE Rp 3,093,137,017
III.3.A.1 PEKERJAAN PLUMBING Rp 243,789,800
III.3.A.2 PEKERJAAN PEMADAM KEBAKARAN Rp 7,823,200
III.3.A.3 PEKERJAAN TATA UDARA Rp 684,014,400
III.3.A.4 PEKERJAAN ELEKTRIKAL Rp 755,050,100
III.3.A.5 PEKERJAAN ELEKTRONIK
III.3.A.5.1 FIRE ALARM Rp Tidak ada
III.3.A.5.2 TATA SUARA Rp 2,204,200
III.3.A.5.3 TELEPON Rp 2,670,900
III.3.A.5.4 CCTV Rp 1,377,019,550
III.3.A.5.5 DATA Rp 19,229,267
III.3.A.5.6 MATV Rp Tidak ada
III.3.A.5.7 ACCESS CONTROL Rp 1,335,600
III.3.B PEKERJAAN MEKANIKAL - ELEKTRIKAL CHANGING ROOM Rp 1,445,492,367
III.3.B.1 PEKERJAAN PLUMBING Rp 60,865,600
III.3.B.2 PEKERJAAN PEMADAM KEBAKARAN Rp 2,235,200
III.3.B.3 PEKERJAAN TATA UDARA Rp 1,071,807,500
III.3.B.4 PEKERJAAN ELEKTRIKAL Rp 184,504,200
III.3.B.5 PEKERJAAN ELEKTRONIK
III.3.B.5.1 FIRE ALARM Rp 46,231,300
III.3.B.5.2 TATA SUARA Rp 5,567,000
III.3.B.5.3 TELEPON Rp 5,961,600
XVI DAF - XVI PROVISIONAL SUM (Provisional Sum for Contingencies and Rp Exclude Rp
Daywork Allowances)
TERBILANG : _____________________________________________________________________________________.
Dua ratus delapan puluh tujuh milyar lima juta rupiah