Professional Documents
Culture Documents
ẢNH HƯỞNG CỦA TCSC ĐẾN PHÍ TRUYỀN TẢI TRONG THỊ TRƯỜNG ĐIỆN BÁN
BUÔN CÓ XÉT GIAO DỊCH SONG PHƯƠNG VÀ DỰ TRỮ CÔNG SUẤT TÁC DỤNG
THE IMPACT OF TCSC ON TRANSMISSION COSTS IN WHOLESALE POWER
MARKETS CONSIDERING BILATERAL TRANSACTIONS AND ACTIVE POWER
RESERVES
Tóm tắt – Trong thị trường điện, xác định phí truyền tải là Abstract – In the electricity market operation, calculating
một vấn đề quan trọng. Tính toán phí truyền tải là xác định transmission charges is a critical issue. Transmission costs relate
đơn vị phải trả phí cũng như số tiền phải trả. Đối với phí to the issue of how much is paid and by whom, for the use of
truyền tải ngắn hạn, chênh lệch giá biên nút (LMP) trên các transmission system. For short-run transmission charges,
nhánh có ảnh hưởng nhiều đến các đơn vị tham gia thị difference of locational marginal prices (LMP) on a network
trường, bao gồm cả các hợp đồng song phương. Khi có branch has much influence on the market participants, including
nghẽn mạch trong hệ thống điện, chênh lệch giá biên nút bilateral transactions. When there is congestion in power
trên các nhánh càng lớn. Một trong các biện pháp để khắc systems, difference of locational marginal prices on the branch
phục nghẽn mạch là sử dụng thiết bị bù dọc có điều khiển becomes bigger. One of the measures to overcome network
(TCSC). Mặt khác, sự có mặt của các phụ tải nhạy theo giá, congestion is using thyristor controlled series capacitor (TCSC).
các giao dịch song phương và yêu cầu dự trữ công suất In addition, the presence of price-sensitive loads, bilateral
trong hệ thống điện làm phức tạp vấn đề xác định phí truyền transactions and requirement of active power reserves in power
tải. Bài báo trình bày cách xác định vị trí đặt tối ưu của TCSC systems complicate matters associated with transmission charges
và phân tích ảnh hưởng dung lượng bù của TCSC đến phí in the wholesale electricity market. In this paper, a method for
truyền tải của hợp đồng song phương trong thị trường điện determining the optimal location of TCSC has been suggested
bán buôn. Các kết quả tính toán được minh họa sử dụng and the impact of TCSC compensation levels to transmission
lưới điện 6 nút. charges of bilateral contracts in the wholesale electricity market is
analyzed. The calculated results are illustrated on a 6-bus
system.
Từ khóa – Giá biên nút, thị trường điện bán buôn, chi phí Key words – Locational marginal prices (LMP), wholesale
truyền tải, dự trữ công suất tác dụng, giao dịch song phương, power markets, transmission costs, active power reserves,
TCSC, ACOPF. bilateral transactions, thyristor controlled series capacitor (TCSC),
AC optimal power flow (ACOPF).
Pij Ui2Gij UiU j Gij cos ij Bij sin ij
(1) NL
w PLm
2n
PI m max (12)
Qij Ui2 Bij Bsh UiU j Gij sin ij Bij cos ij (2) m 1 2n PLm
max
Pij jQij G ij jBij Pji jQ ji where PLm is the active power flow on line m, PLm is
the limit of active power flow on line m.
Uii U j j In this paper, the value of n has been taken as 2 (to
B sh B sh avoid masking effect) and weighting factors wm = 1 (the
importance level of lines is similar).
To decrease congestion level of power transmission
Figure 1. Model of transmission line lines, TCSC should be placed in the line having the most
negative sensitivity index bk which is calculated below
With a TCSC connected between bus i and bus j, the
[7]:
real and reactive power flow from bus i to bus j of a line
are [6]: PI
bk (13)
PijC Ui2Gij' UiU j Gij' cos ij Bij' sin ij (3) X Ck X Ck 0
4
QijC Ui2 Bij' Bsh UiU j Gij' sin ij Bij' cos ij (4) PI NL 1 PLm
wm PLm
3
max (14)
X Ck m 1 PLm X Ck
Gij'
Rij
; Bij'
X ij X C (5) Pi Pi
2 2
Rij2 X ij X C Rij2 X ij X C SFmi SFmj mk
PLm X Ck X Ck
(15)
The change in the line flow due to series capacitance X Ck Pi Pi Pj
can be represented as a line without series capacitance, SFmi X SFmj X X mk
with power injected at the receiving and sending ends of Ck Ck Ck
the line as shown in Figure 2 [6]. where SFmi, SFmj is the sensitivity of branch power
flow m with respect to injected power i and j,
respectively.
3 TẠP CHÍ KHOA HỌC VÀ CÔNG NGHỆ, ĐẠI HỌC ĐÀ NẴNG - SỐ …………..
3. Co-optimization of Energy and active power n
reserves Pi PGi PDi U i U j Gij cos ij Bij sin ij
k 1
3.1 Objective function (17)
n
The objective function of co-optimization problem of Qi QGi QDi U i U j Gij sin ij Bij cos ij
energy and reserves in the wholesale electricity market is k 1
to minimize the total cost to supply minus total consumer 3.2.2 Reserve balance
benefit. This objective function is expressed as Eq. (16).
For each area or zone, the reserve balance is shown
N G N Gi according to the following expressions:
Gib .PGib NG
PGiRR ARR
i 1 b 1
(18)
NG
RR RR RR RR i 1
Gi .PGi Gi .PGi SR SR
Gi .PGi Gi
XR XR
.PGi NG
i 1
N D N Dj N RR N RR
(16) PGiRR ARR (19)
i 1
Djk .PDjk bRR .A bRR bRR .A bRR
PGiSR PGiXR ACR
NG
j1 k 1 b 1 b 1 (20)
N CR N OR i 1
CR
b .A b b .A b
CR OR OR
generating unit i (constant), PGib is power of the energy 3.2.3 Limits on generating active power of block b
RR
block b offered by generating unit i (variable), Gi is 0 PGib PGib
max
i, b (22)
price of Up Regulation Reserve (RR) offered by
3.2.4 Limits on generator power
RR
generating unit i (constant), Gi is price of Down The limits on generator active and reactive power of
Regulation Reserve offered by generating unit i power plants, considering all kinds of reserves are
(constant), SR
Gi is price of Spinning Reserve (SR) offered
expressed as Eq. (23) – (24).
NG NG
PGiSR SR%. PGiSR PGiXR (35) These PTDFs, which are computed at the base load
flow condition, are utilized for computing change in
i 1 i 1
transmission qualities at other operating conditions as
3.2.9 Branch flow limits
well. The transmission costs (TC) paid by bilateral
Branch flow limits are expressed as Eq. (36). transactions are calculated as (42) and (43).
0 Sij Pij2 Qij2 Sijmax (36)
TCijb Pijbmn LMPj LMPi (42)
3.2.10 Voltage Limits TC b TCijb (43)
U imin U i U imax (37) ij
3.2.11 Limits on bilateral contracts where Pijbmn is the change in power flow on line ij
When generating unit i and consumer j have a bilateral when a power transfer of the bilateral transaction is
contract with contract power Pb, this constraint is changed between m and n.
expressed as equations (38)-(39): 5. Calculated results from a 6-bus system
PGi PGib (38) 5.1 Simulation Data
PDj PDj
E
PDj
F
PDj
b
(39) This section presents the calculated results using a 6
bus power system [3]. The energy offer prices of
F
where PDj b
is the constant power of demand j, PGi is the generating units and bid prices of price-sensitive demands
include 5 blocks.
b
amount of power contract of generating unit i, PDj is the In terms of bilateral trade, two different bilateral
amount of power contract of demand j. transactions are carried out: between bus 1 and bus 6 with
The above-mentioned AC-based optimal problem a contractual capacity of 20 MW, denoted as T1 (1, 6,
(ACOPF) be solved using successive linear programming 20); between node 2 and node 5 with a contractual
(SLP) method [3]. capacity of 25 MW, denoted as T2 (2, 5, 25).
3.3 LMP Calculation and Components 5.2 Optimal location of TCSC
Locational Marginal Price (LMP) is determined The calculated bk indices for the 6 bus system are
according to following equation [3]. shown in Table 1. From these results and the criteria for
optimal location of TCSC expressed in section 2, TCSC is
LMPi LMPE LFi .LMPE SFl i .l (40) placed in line 2-6.
l
Table 1. Sensitivity bk
4. Transmission costs of bilateral transactions
The main objective of any transmission pricing Pi Pj
method is to recover the transmission cost plus some
Line
X Ck X Ck
bk
profit. In order to recover operating costs, short-run
marginal cost pricing (SMRC) based method is used in 1-2 -0.8830 0.8107 0.2679
this paper [4]. SMRC is the difference in locational 1-4 -2.3154 2.2129 -0.8526
marginal costs of supply bus and delivery bus. The 1-5 -1.2294 1.1625 0.0957
locational marginal costs of two buses can be determined
2-3 -0.0432 0.0401 0.0371
from the solution of co-optimization energy and active
power reserves shown in section 3. The transmission cost 2-4 -4.5384 4.2975 1.4579
5 TẠP CHÍ KHOA HỌC VÀ CÔNG NGHỆ, ĐẠI HỌC ĐÀ NẴNG - SỐ …………..
We sincerely thank the reviewers for their valuable comments and suggestions. Based on the reviewer’s comments,
we have made changes to the paper. Some specific responses to the reviewer’s comments are shown below:
1. Reviewer’s comments: The reviewer suppose that the authors try to innovate a new method, therefore in order to
improve the quality of paper, the authors should prove and describe better the new contributions. For example, add
more references and make some comparisons.
Authors’ comments: We have added some new relevant references ([8], [9]) and some comparisons have been
included in the Introduction. Moreover, the figures have been revised and renumbered.
2. Reviewer’s comments: The abstract said that “In this paper, a method for determining the optimal location of
TCSC has been suggested and the impact of TCSC compensation levels to transmission charges of bilateral contracts in
the wholesale electricity market is analysed.” Could the authors please provide the impact of active power reserves on
the main objective of the paper?
Authors’ comments: Generating output and active power reserves of generating units have interaction with each
other. Because of this interaction, when changing one of the following factors: the reserve capacity required in each
area or zone of the electrical systems, the reserve power and the price of reserve power offered by GENCOs, generating
out of power plants and power of the price-sensitive loads can become different (Eq. 16). Additionally, voltage
magnitudes and relative phase at the system nodes can vary widely as well. Because expressions used to determine the
optimal placement of TCSC depends on voltage magnitudes and phase angle (Equations 6-9, 13-15), the optimal
location of TCSC can alter when aspects related to active power reserves change.
In addition, the variation in the generating output of GENCOs and power of elastic demand result in change of loss
factors (LFs) and the branch power flows. This lead to the considerable alteration of locational marginal prices (LMPs)
(Eq. 40), which has a noticeable effect on transmission charges (Equations 42-43).
Consequently, when TCSC is placed on different lines, the compensation level of TCSC can differently influence on
the generation capacity of GENCOs, the power of price-sensitive load and LMPs, which impacts on the transmission
costs of bilateral contracts.
3. Reviewer’s comments: Which software do the authors use to develop the model? For example: MATLAB,
GAMs, PSS/E or Power world.
Authors’ comments: In this paper, we use the MATLAB software to determine the optimal location of Thyristor
controlled series compensator (TCSC). In addition, POWERWORLD software is adopted to solve the co-optimization
problems of energy and active power reserves.
4. Reviewer’s comments: Section 4 provided the equation to take into account transmission costs or congestion
rent, the reviewer suppose that the author run model with AC-Optimal Power Flow (AC-OPF), why do the author want
to use PTDF (Power Transmission Distribution Factor) to calculate congestion rent? (eq. 41)
Authors’ comments: AC-based Optimal Power Flow Algorithm (ACOPF) provides us with locational marginal
prices (LMPs). From these LMPs, the transmission costs of the bilateral contracts can be calculated (Eq. 42). However,
in the electricity market operation, it is necessary to identify the change of power flows and to compute transmission
charges on each branch of transmission network due to each bilateral agreement. To do this, one of methods is to apply
linear Power Transfer Distribution Factor (PTDF), which is simple, speedy and efficient. As shown in Table 2, the
change of power flows and transmission charges on each line due to bilateral transactions T1 (1, 6, 20) and T2 (2, 5, 25)
were determined by using the coefficients PTDF.
Again, we would like to thank the reviewers for their valuable comments and suggestions.
7 TẠP CHÍ KHOA HỌC VÀ CÔNG NGHỆ, ĐẠI HỌC ĐÀ NẴNG - SỐ …………..
The Authors