You are on page 1of 1

SITE: 242

QUALITY CONTROL
Inspection Checklist

Project Details
Project Name BEACH VILLA (B+G+1+PH) ON BVN 55 to 60 at the Pearl Qatar
Area/Building MV/PA/GH Date
Person doing site inspection: (Print name)
Person doing site inspection: (Signature)

Items for inspection – Concreting of Suspended Slab and Beam.

Item X Item X


or N/A or N/A
A.Formworks C.Pre-concreting checking
Check the if formworks is Check all the required materials
properly aligned. and tools are available on site.
Check if is cleaned. Check all service line (electrical,
sanitary, plumbing., etc) which
go through the RCC member.
Check if is oiled. D.Checking during concreting
Check inner face of the Check the slump. (as per
formwork is smooth. specification)
Check if the formwork is Check concrete cubes/cylinders
watertight. for testing.
Check support are properly Check available carpenters at
placed and fixed. shuttering area to take
immediate action if anything
happens during concrete
pouring.
Check width and depth/height of Check drop height of concrete.
formwork.
Check thin metal sheets are Check vibrating is done properly.
provided along joints of wooden
formworks.
B.Reinforcements checking Check the level of the concrete
surface.
Check steel are placed as per Check the finishing of the
drawing. concrete surface.
Check rebars are straight. E.Post Concreting checking
Check spacing of rebars. Check if curing is done properly.
Check the diameter of the rebar. Check formwork removal
duration is followed properly.
Check hooks and bends are Test the cubes/cylinders. If test
placed as specified. result is not satisfied. AEB should
be notified immediately.
Check the rebars are rust free.
Check the rebars are crack free.
= yes
X = no
N/A = not applicable

Quality Control Site Inspection checklist

Current Version 1 by JML