Weekly Report Feb.14 182022K4 59 Quirangay River Camalig Albay Dredging Project
Weekly Report Feb.14 182022K4 59 Quirangay River Camalig Albay Dredging Project
Location: Brgy. Tagay tay Camalig Albay Dredge Master: EMMANUEL B. BIÑAS
Date Started: Dec.20,2021 Equipment Used: Amphibious Excavator
Total Dredging Hours: 238.00 Estimated Total DOOSAN (K4-59)
Total Dredging Days: 44 Volume
Total Fuel Consumed Fuel: 2671 Accomplished: 8,755 cubic meters
Performed PM1
Refuelled the equipment (__ Liters)
v Security of Equipment
Meter/Gauge Reading
v Dredging Operations
v Adjustment/Repair/Corrective Maintenance
Performed PM1
v Refuelled the equipment (_110___ Liters)
v Security of Equipment
v Dredging Operations
Adjustment/Repair/Corrective Maintenance
Others
Performed PM1
v Refuelled the 100 L
v Security of Equipment
v Dredging Operations
Adjustment/Repair/Corrective Maintenance
Others (Loading of dump truck for hauling)
Performed PM1
v Refuelled the 90 L
v Security of Equipment
v Dredging Operations
Adjustment/Repair/Corrective Maintenance
Date: Feb.18, 2022 (Friday)
Equipment Hourmeter Reading (hrs)
1536 (hours)
v Performed PM1
v Refuelled the equipment (_120____ Liters)
v Security of Equipment
Meter/Gauge Reading v Dredging Operations
Adjustment/Repair/Corrective Maintenance
Total Estimated
342 Liters
Fuel Consumption
Estimated Total Dredged Volume 1,226 cubic meters
Total Dredging
29
Hours hours
REMARKS:
We Do Preventive Maintenance of Amphex(Change oil and replace oil filter,Clean water separator),then coordinate to Engr.Emil Flores on D
and Concerns)
EMMANUEL B. BIÑAS
Dredge Master III