Weekly Accomplishment Report

Dredging Project: Quirangay River


Feb.14-18,2022

Location: Brgy. Tagay tay Camalig Albay Dredge Master: EMMANUEL B. BIÑAS
Date Started: Dec.20,2021 Equipment Used: Amphibious Excavator
Total Dredging Hours: 238.00 Estimated Total DOOSAN (K4-59)
Total Dredging Days: 44 Volume
Total Fuel Consumed Fuel: 2671 Accomplished: 8,755 cubic meters

Date: Feb.14,2022 (Monday)


Equipment Hourmeter Reading
1511.8 hrs

Estimated Fuel Consumption (L) (Balance)


52

Estimated Dredged Volume


185 (cu. meters)
(Insert Pictures/Highlights, may include before and after operations)No Operation(Christmas Party on Naga)
Activities:

Performed PM1
Refuelled the equipment (__ Liters)
v Security of Equipment
Meter/Gauge Reading
v Dredging Operations
v Adjustment/Repair/Corrective Maintenance

Date: Feb.15, 2022 (Tuesday)


Equipment Hourmeter Reading (hrs)
1517.7

Estimated Fuel Consumption (L) (Balance)


71

Estimated Dredged Volume


254 (cu. meters)
(Insert Pictures/Highlights, may include before and after operations)
Activities:

Performed PM1
v Refuelled the equipment (_110___ Liters)
v Security of Equipment
v Dredging Operations
Adjustment/Repair/Corrective Maintenance
Others

Date: Feb.16,2022 (Wednesday)


Equipment Hourmeter Reading (hrs)
1524.6 hrs

Estimated Fuel Consumption (L) (Balance)


83

Estimated Dredged Volume


297 (cu. meters)
(Insert Pictures/Highlights, may include before and after operations)
Activities:

Performed PM1
v Refuelled the 100 L
v Security of Equipment
v Dredging Operations
Adjustment/Repair/Corrective Maintenance
Others (Loading of dump truck for hauling)

Date: Feb.17,2022 (Thursday)


Equipment Hourmeter Reading (hrs)
1531.9 hrs

Estimated Fuel Consumption (L) (Balance)


88

Estimated Dredged Volume


314 (cu. meters)
(Insert Pictures/Highlights, may include before and after operations)No operations
Activities:

Performed PM1
v Refuelled the 90 L
v Security of Equipment
v Dredging Operations
Adjustment/Repair/Corrective Maintenance
Date: Feb.18, 2022 (Friday)
Equipment Hourmeter Reading (hrs)
1536 (hours)

Estimated Fuel Consumption (L) (Balance)


49

Estimated Dredged Volume


176 (cu. meters)
(Insert Pictures/Highlights, may include before and after operations)No Operations
Activities:

v Performed PM1
v Refuelled the equipment (_120____ Liters)
v Security of Equipment
Meter/Gauge Reading v Dredging Operations
Adjustment/Repair/Corrective Maintenance

Summary of Weekly Dredging Accomplishment

Total Estimated
342 Liters
Fuel Consumption
Estimated Total Dredged Volume 1,226 cubic meters
Total Dredging
29
Hours hours

REMARKS:
We Do Preventive Maintenance of Amphex(Change oil and replace oil filter,Clean water separator),then coordinate to Engr.Emil Flores on D
and Concerns)

Prepared By: Checked and Verified By:

RAY O. NIERVA JOHN BERT B. ONRUBIA


ENGINEER 1 Engineer II

EMMANUEL B. BIÑAS
Dredge Master III