Construction and Completion of Foundation Work For 46 Units of Small Terrace House (St3) at Parcel C2 - Gamuda Gardens
Construction and Completion of Foundation Work For 46 Units of Small Terrace House (St3) at Parcel C2 - Gamuda Gardens
THE OWNER:
THE CONTRACTOR:
CONTENTS
4. TEST PROCEDURE
6. SAFETY GUIDELINE
Page 2/11
Construction and Completion of Foundation work for 46 Units
Of Small Terrace House (ST3) at Parcel C2 - Gamuda
gardens
Method Statement for Underground Package.
Page 3/11
Construction and Completion of Foundation work for 46 Units
Of Small Terrace House (ST3) at Parcel C2 - Gamuda
gardens
Method Statement for Underground Package.
3.1. Static load test pile conducted using methods of loading previous counterweight
3.2. Testing system
3.2.1. Counterweight system
Counterweight system used in the works is a system comprised of many blocks of pre-
cast reinforced concrete weighing from 2.5 to 5 tons per block that are put together into
huge blocks on a steel beam system. Counterweight system is calculated to match the
testing load (the maximum test load multiplied with 1.2).
Beams system withstanding testing load: a system includes I-shaped steel beams linked
together on bearings system. Beams system is calculated for enough strength and no
deformation when loading as well as during the experiment.
Bearings system: The system includes pre-cast reinforced concrete slabs on the ground
and has effect of supporting beams system. Bearings system must be calculated to
ensure enough cross- section to not be causes of settlement when loading testing loads, not
affect the work of the pile as well as other devices in the course of the experiment.
3.2.2. Loading system
Loading system in the experiment is the hydraulic jack system with a lifting capacity of
50 tons (498.2kN is >1.5 times of the maximum requirement value) and has the
valid certification. This hydraulic jack system is mounted on the tested pile so that
compression jack axis coincides with the axis of the experimented pile. The jack head has
a self-regulation unit that always ensures compression force is transmitted along the pile
shaft.
Force measurement system:
Using hydraulic meters 0 - 400kG/cm2 measuring range. The meters has been tested and
licensed for use by the authority company. Compression force acting on the pile head is
calculated through readings of the meters and hydraulic lift coefficient of the hydraulic
jack.
Hydraulic oil pump system: hydraulic oil pump system is attached to the hydraulic jack
and oil is supplied into the jack in order to adjust the lifting capacity of the jack as desired.
Pumping discharge: 3 litters/minute, maximum pressure: 700 kg/cm2.
3.2.3. Deformation gauge system
Strain measurement system includes 04 settlement meters/gauges with measurement
range 0-50 mm, accuracy of 0.01mm tied up with pile shaft through a fitment system
and steel yokes. The meter has been tested and licensed for use by authority company.
Fitment system of settlement gauges: has magnetic legs by electric magnets fastened to
the steel bondage system mounted on the pile head.
Benchmark system: The benchmark system used in the works is a shape-steel system
with feet buried by concrete. The stiffness of the benchmark system must ensure to not
be distorted during the experiment and not be influenced by external forces.
4. TEST PROCEDURE
1. Static load compression test for reinforced concrete piles used in the project is
conducted in accordance with British standard BS 8004:1986.
2. Piles designed to test with the maximum test load is following designed documents
Page 4/11
Construction and Completion of Foundation work for 46 Units
Of Small Terrace House (ST3) at Parcel C2 - Gamuda
gardens
Method Statement for Underground Package.
3. Loading method
Check the operation of experimental devices and create good contact between the
device and the pile head: before the experiment, the settlement gauges is adjusted to 0,
previous loading is done by acting 5% of the design load on the pile head, holding this
load for 10 minutes and then unload it to 0 without correcting settlement gauges to 0,
the existing values of the meter are recorded as the initial readings corresponding to
when the load is 0 ton.
Loading testing load:
- Testing load is loaded by 2 experimental cycles for preliminary test pile;
- Testing load is loaded by 1 experimental cycles for working test pile;
(a) Preliminary test pile
Loading the pile must be carried out by each level without pulses, pile test by 2 test
cycles:
- Cycle I: load levels respectively increased by 0%, 10%, 20%, 30%, 40%, 50%,
60%,70%, 80%, 90%, 100% of the design load. Each load level must be
maintained and monitored in 10 minutes, but the load level of 100% design load,
must be observed within 60 min (1 hour) or settlement rate less than 0.25mm/h
(whichever is longer). Then load levels are reduced by 70%, 50%, 25%, 0% of
the design load when unloading, observation time for each load level is 10
minutes, except the load level of 0% design load is observed in 30 minutes.
-Cycle II: the level of load in turn increases: 25%, 50%, 75%, 100%,
110%,120%, 130%, 140%, 150%, 160%, 170%, 180%, 190% and 200% of the
design load and are maintained, monitored in 10 minutes. However the load level
of 200% design load is maintained in minimum 60 min and until reaching a
conventional stable settlement (whichever is longer). Then reducing testing load,
the reduced load is conducted in the order of 150%, 100%, 50%, 0% of the
design load. Each load level is monitored for 10 minutes, except the load level
of 0% design load is observed in 30 minutes.
TABLE OF TESTING PROCESS (Preliminary test pile)
Testing load
level Time of maintaining testing load on Time of observation and
the tested pile head record of experimental data
%
Increasing load, cycle I
0 10 minutes Data record at 0’, 5', 10’
10 10 minutes Data record at 0’, 5', 10’
20 10 minutes Data record at 0’, 5', 10’
30 10 minutes Data record at 0’, 5', 10’
40 10 minutes Data record at 0’, 5', 10’
50 10 minutes Data record at 0’, 5', 10’
60 10 minutes Data record at 0’, 5', 10’
70 10 minutes Data record at 0’, 5', 10’
Page 5/11
Construction and Completion of Foundation work for 46 Units
Of Small Terrace House (ST3) at Parcel C2 - Gamuda
gardens
Method Statement for Underground Package.
Testing load
Time of maintaining testing load on Time of observation and
level
the tested pile head record of experimental data
%
Reducing load, cycle I
75 10 minutes Data record at 0’, 5', 10’
50 10 minutes Data record at 0’, 5', 10’
25 10 minutes Data record at 0’, 5', 10’
0 30 minutes Data record at 0’, 10’, 20', 30'
Load increase, cycle II
25 10 minutes Data record at 1’, 5', 10’
50 10 minutes Data record at 1’, 5', 10’
75 10 minutes Data record at 1’, 5', 10’
100 10 minutes Data record at 1’, 5', 10’
110 10 minutes Data record at 1’, 5', 10’
120 10 minutes Data record at 1’, 5', 10’
130 10 minutes Data record at 1’, 5', 10’
140 10 minutes Data record at 1’, 5', 10’
150 10 minutes Data record at 1’, 5', 10’
160 10 minutes Data record at 1’, 5', 10’
170 10 minutes Data record at 1’, 5', 10’
180 10 minutes Data record at 1’, 5', 10’
190 10 minutes Data record at 1’, 5', 10’
Data record at 0’,10’, 20’,
Minimum 60 min and until reaching a
200 30’, 45’, 60’, 120’, 180’, 240’,
conventional stable settlement
300’, 360’ …
Reducing load, cycle II
150 10 minutes Data record at 1’, 5', 10’
100 10 minutes Data record at 1’, 5', 10’
50 10 minutes Data record at 1’, 5', 10’
0 30 minutes Data record at 1’, 5', 10’
Page 6/11
Construction and Completion of Foundation work for 46 Units
Of Small Terrace House (ST3) at Parcel C2 - Gamuda
gardens
Method Statement for Underground Package.
- Load levels respectively increased by 0%, 10%, 20%, 30%, 40%, 50%,
60%,70%, 80%, 90%, 100% of the design load. Each load level must be
maintained and monitored in 10 minutes, but the load level of 100% design load
must be observed within 60 min (1 hour) or settlement rate less than 0.25mm/h
(whichever is longer). Then load levels are reduced by 70%, 50%, 25%, 0% of
the design load when unloading, observation time for each load level is 10
minutes, except the load level of 0% design load is observed in 30 minutes.
TABLE OF TESTING PROCESS (Working test pile)
Testing load
level Time of maintaining testing load on Time of observation and
the tested pile head record of experimental data
%
Increasing load
0 10 minutes Data record at 0’, 5', 10’
10 10 minutes Data record at 0’, 5', 10’
20 10 minutes Data record at 0’, 5', 10’
30 10 minutes Data record at 0’, 5', 10’
40 10 minutes Data record at 0’, 5', 10’
50 10 minutes Data record at 0’, 5', 10’
60 10 minutes Data record at 0’, 5', 10’
70 10 minutes Data record at 0’, 5', 10’
80 10 minutes Data record at 0’, 5', 10’
90 10 minutes Data record at 0’, 5', 10’
Data record at 0’,10’, 20’,
60 min (1 hour) or settlement rate less
100 30’, 45’, 60’, 120’, 180’, 240’,
than 0.25mm/h (whichever is longer)
300’, 360’ …
Reducing load
75 10 minutes Data record at 0’, 5', 10’
50 10 minutes Data record at 0’, 5', 10’
25 10 minutes Data record at 0’, 5', 10’
0 30 minutes Data record at 0’, 10’, 20', 30'
NOTE:
1. Settlement of the pile head must be recorded immediately before loading.
2. The following load levels are only issued when further settlement of the pile head at
the previous load level not exceeding 0.25 mm in 1 hour, but the longest duration for each
load level must be less than 2 hours for load levels beyond 100% and 200 %.
3. Fixed time intervals for monitoring, reading and recording data for load levels 100%
and 200%:
- No more than 10 minutes per reading for the first 30 minutes.
- No more than 15 minutes per reading for the next 30 minutes.
- No more than 1h per reading for the next 10 h.
Page 7/11
Construction and Completion of Foundation work for 46 Units
Of Small Terrace House (ST3) at Parcel C2 - Gamuda
gardens
Method Statement for Underground Package.
Page 8/11
Construction and Completion of Foundation work for 46 Units
Of Small Terrace House (ST3) at Parcel C2 - Gamuda
gardens
Method Statement for Underground Package.
Page 9/11
Construction and Completion of Foundation work for 46 Units
Of Small Terrace House (ST3) at Parcel C2 - Gamuda
gardens
Method Statement for Underground Package.
6. SAFETY GUIDELINES
6.1. Safety measures for people and equipment
- Allocate security guards and medical personnel to be on duty 24/24 during the
test.
- All technical staffs and construction workers in the project must be learnt about
safety at work and be assigned for specific tasks before joining the service at work.
Everyone is equipped and forced to use appropriate labor protection such as
gloves, shoes, hard hats and so on.
- There must have rain or shine, wind cover canvas to protect experimental
equipment.
- The construction equipment must be submitted with certifications of quality
control before being put into the construction site.
- The shift leader, drivers must check for safety before performing the work.
- The works of transportation, installed at night must be performed with floodlights
enough light.
- Safety on counterweight system installation and installation of equipment on high.
- Climb on experimental frame by rope ladder, absolutely not up via crane.
- Must have a professional traffic indicator.
6.2. Safety of third parties
- There are signs, restriction and warning of activity areas of the experiment
during the field experiment.
- People who have no duties are not allowed to attend at the experimental
area.
- Coordinate with other units on the working site to implement common safety
measures.
6.3. Environmental sanitation, fire prevention, and so on
- Appoint professional staffs in charge of fire safety, environmental hygiene.
- Training for technicians and workers participating in field experiments to
understand the orders in the fire and explosion protection and use fire-fighting
vehicles proficiently.
- Do not bring flammable or explosive substances into the construction site.
- Equip facilities for fire and explosion prevention such as fire sand tanks,
water tanks, CO2 spray.
- Technicians and workers involved in the experiment must do personal activities
and eat outside of the construction site, only technicians, workers and security
guards who are on duty are allowed to stay in the site at night.
Page 10/11
Construction and Completion of Foundation work for 46 Units
Of Small Terrace House (ST3) at Parcel C2 - Gamuda
gardens
Method Statement for Underground Package.
Page 11/11