Professional Documents
Culture Documents
NAME IDNO.
1. RIYAD MOHAMMAD KALIFA cesr/0631 /09
Advisor Name:
Signature:
Date:
2021/2013 i
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Acknowledgments
I would like to take this opportunity to thank individuals, groups, and organizations who played
their much appreciated role for my internship. First and foremost, i would like to thank almighty
God for giving me strength and courage in all i went through. I would also like to thank and
appreciate Madda Walabu University for presenting me with this precious opportunity in
developing my practical experience and modify my theoretical knowledge. I would like to thank
Harari Housing Development and Government Construction Agency for positively responding to
my request to host me as an intern and availing this opportunity for me to practice and learn about
the practical world of building construction and project management. I would also like to present
my heartfelt thanks and gratitude specially to my adviser Mohammad Aman and site supervisor
Eng. Ziyad Jemal for invaluable and generous contribution throughout my practical time tirelessly.
From the time i started my internship until i finish they are giving orienting, guiding, supervising,
answering my questions and clearing doubts, and encouraging me to try do the best. Specially his
invaluable sharing of personal experience along with ordinary site works and brotherly advice to
help me cope with what i face.
I would also like to thank Mekasha Ambaw B.C and Importer contractor/company staffs and
employees for their tireless help and guidance at working site guiding and sharing their experience
with me along with the project client Nursing School Teaching Complex Project and Harari Health
Bureau.
Finally, the coordination and combination of our group members in creating team spirit and work
that enabled us to grasp some useful real construction world knowledge was immense. Hence, this
will develop our better understanding of construction industry and help us develop new ideas.
2021/2013 ii
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Executive summary
This report is an outcome of the exercise i conducted during my internship period at Harari
Housing Development and Government Construction Agency. This was an opportunity for me to
apply the knowledge i had acquired for seven semesters of study in the University into practice.
In the first part of my report, i briefly described introduction to the site and the companies
participated on construction and the back ground of my internship hosting company. Including the
history and objective of the company, its main products and services.
The second part of my report briefly explains the overall internship experience i have gained during
my internship. Started by describing how i get into the company, in which section of the company
i have been worked in and the work piece i executed. I also explained clearly what the general
work flow in the site looks like.
In this report i also briefly explain the procedures i have used while performing my tasks. I tried
to explain the step by step procedure for every work, starting from SB+G+3 works through
SB+G+4. Next to this i briefly describe how formworks are prepared for columns, beams and
slabs. After formwork preparation the next step will be filing the concrete, this contains the step
by step procedure i have followed and checked during casting of concrete, including mixing,
conveying, placing, compacting, and curing of concrete.
The challenges i have faced during my internship period, both site challenges and personal
challenges are covered in this report.
I briefly explains about the overall benefits i gained from my internship in terms of improving my
practical skills, interpersonal communication skills, team playing skills, leadership skills,
upgrading my theoretical knowledge and work ethics.
Finally, i covered my conclusions and recommendations for my hosting company and university.
2021/2013 iii
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Table of Contents
Contents Page
Declaration ..................................................................................................................................................... i
Acknowledgments ....................................................................................................................................... ii
Executive summary.................................................................................................................................... iii
List of Tables ............................................................................................................................................... vi
List of figures .............................................................................................................................................. vii
List of Acronyms ....................................................................................................................................... viii
CHAPTER ONE ......................................................................................................................................... 1
1. INTRODUCTION................................................................................................................................... 1
1.1 General Over View ............................................................................................................................... 1
1.2 Background of Hosting Company....................................................................................................... 2
1.2.1 The strategy of Housing Development Project Office encompasses; .......................................... 3
1.2.2 Objective of Housing Development Project Office ..................................................................... 3
1.2.3 Vision of Housing Development Project Office .......................................................................... 4
1.2.4 Goals of Housing Development Project Office ........................................................................... 4
1.2.5 Main products and services of Housing Development Project Office ......................................... 5
1.2.6 Main customers or the end users of its products or services ........................................................ 5
CHAPTER TWO ........................................................................................................................................ 6
2. OVERALL INTERNSHIP ACTIVITIES AND EXPERIENCES ..................................................... 6
2.1 How i get into the company ................................................................................................................ 6
2.2 Section of the company i have been working ..................................................................................... 6
2.2.1 The work flow in the section........................................................................................................ 7
2.3 Work task i have executed .................................................................................................................. 9
2.3.1 Executed work task procedures (main activities)....................................................................... 10
2.3.2 Construction Materials ............................................................................................................... 13
2.3.3 Concrete work ............................................................................................................................ 16
3.3.4 Reinforcement ............................................................................................................................ 19
2.3.5 Formwork ................................................................................................................................... 20
2.4 Super structure work ......................................................................................................................... 22
2.4.1 Beam .......................................................................................................................................... 22
2021/2013 iv
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
2021/2013 v
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
List of Tables
2021/2013 vi
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
List of figures
Figure 1.1 organization flow chart……………………………………………………….….….4
2021/2013 vii
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
List of Acronyms
C-5: - Compressive Strength of 5MPa of concrete
mm: - Millimeter
m: - meter
2021/2013 viii
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
2021/2013 ix
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
2021/2013 x
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
CHAPTER ONE
1. INTRODUCTION
These problem solvers are trained personals with different engineering courses in universities
and colleges. The knowledge and ability of these engineers is more dependent on the theoretical
method of teaching in universities. But the responsibility of engineers is to solve practical
problems. So the new curriculum of Ethiopia for engineering and technology students are
developed to include sufficient practical knowledge together with theoretical knowledge that
learns in the classroom. Due to this, the ministry of education programmed a two-month internship
program for engineering and technology students.
Based on the new curriculum, were i am doing internship for one full semester at Harari
Housing Development and Government construction Agency in Harar on construction of Harari
health colleges teaching complex. I have gained a lot of understanding and experiences on practical
application of construction in a well-organized and effective manner. While were i am there i have
got several opportunities to visit project frequently to observe the progress and to see the related
activities. Besides this, with in a two month stay in this organization, i have spent plenty time with
site engineers, office engineers and Forman’s with sufficient orientation and practical involvement
on the site.
In this report, i have included insights that i have gained during the internship time both site
and office work knowledge. Of course, it is difficult to report all i have seen, though i have tried
to highlight the main points.
2021/2013 1
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Project Name
• Nursing school Teaching Cmplex
Project Location
• Arategna,Harar
Client
• Harari Health Berua
Consultant
• Harari housing development and Government Construction Agency
Contractor
• Mekasha Ambaw BC
In order to construct within the specific period without any problems and waste of materials and
time each of the below should fulfill its requirements
2021/2013 2
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
It provides a variety of safe, sanitary, accessible, decent, and affordable housing for the
community. In carrying out this mission, the housing agency will provide leadership,
maximize resources, and promote partnerships to develop and implement sound housing
policy.
In the delivery of housing and housing services, it works with and support.
Local authorities
Approved housing bodies, and
The department of the Environment, Community and Local Government
Solving the deteriorating accommodation problem in the city and improve the city
residents’ living standard
Assist and facilitate local authorities and approved housing bodies with their housing
functions.
2021/2013 3
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
I will do this by
Promoting good practice in housing management, and
Supporting the delivery of quality housing in well-designed neighborhoods.
2021/2013 4
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
6. Build institution capacity that is able to execute on average the construction of 2035 houses
per year
7. Enable low income residents to become house owner and there by ensure fair distribution
of income and create conducive environment for development
Governmental organization
2021/2013 5
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
CHAPTER TWO
So my first step was observation and introducing my self with the environment i can say that
everyone around was willing enough to accept me as a part of construction crew. They helped me
a lot in building my confidence, and increasing my knowledge by briefing and answering any
unclear aspects toward the project in their respective fields.
Planning and designing phases are responsibly executed by architectural and structural engineers.
From these distinct sections of the company i were assigned on site supervision work. Consulting
engineers or resident engineers remain alert for the quality of all works that are conducted on the
site such as aggregate quality, mix ratio, the way concrete is casted, back fill, soil quality and etc.
Generally, all works conducted on the site are under supervision of the resident engineer for their
quality assurance and conformation with the contract document.
2021/2013 6
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Project coordinator
Resident engineer
1) Project coordinator
2021/2013 7
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Highly experienced and educated architectural designers, structural and civil engineers and other
professionals are a member of this team. Comprehensive design services in the professional
disciplines of planning, architecture, landscape architecture, interior design, and civil, structural,
mechanical, electrical, plumbing, and fire protection engineering are offered within this team.
The main objective of this team is to prepare architectural and structural design to client of the
company and of their own. The team works in the owner’s best interests from the beginning of
design to project completion. This team provides continuous service to the project from start to
finish, establishing and maintaining the quality and integrity of each design. The contractual
relationships between the members of the team are intended to minimize adversary relationships
and to contribute to greater responsiveness within the team.
3) Resident engineer
Supervision of the building process is best performed by the individuals educated and trained in
the profession, that is, engineers. Resident engineers are consulting engineers that are assigned on
a specific site to supervise all construction works conducted therein. Their responsibility is towards
ensuring the construction meets the requirements of the contract documents and is performed under
safe conditions. They regularly control the ongoing tasks on the site. As i able to see from the
diagram of work flow they are directly responsible to design and supervision team.
1. Quality control
2021/2013 8
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
My hosting company assigned me to work with resident engineer who works under
consultant to check quality of work, proper implementation of the design, and to report daily,
weekly and monthly progress.
I spent a very good time with team through the period even if the pandemic disease (COVID-19)
made it difficult for us from the first time of starting the internship program period. In site i were
given a task to check the progress of construction and our office work includes preparation of
takeoff sheet and rebar schedule for different structures.
During my first arrival i were getting prepared and making my self-familiar with the overall
construction works, the structural and architectural drawings and staff members and my site
supervisors. And assisting them in all possible ways i can.
After a while were i get a chance to check quality of concrete mix, then i checked reinforcements
on slab and beam to approve the work and proceed to casting concrete the approval under goes
some of the following checks, arrangement and installing proper length recommended on the
design, provision of top bar(negative reinforcements), main bar, number and spacing of stirrups,
length plus section of overlap, provision of spacer (mortar spacer for cover and kebelato to separate
bottom bars from top on slab ) tightness of form work, alignment of beam and provision of
electrical conduits and sewer pipes. For columns, i have checked overlap length (4 times dia.),
center to center span length with the corresponding columns, vertical alignment and deviation
check using tumbi, provision of spacer, number and spacing of stirrup. Tightness of form work is
finally approved.
2021/2013 9
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Office work: are works that are carried in the office mainly by the office engineer. Ongoing
site work reports and problems against execution of works are recorded and reported in the
office. The main tasks conducted in the office includes: -
Preparation of bill of quantity and cost break down
Preparation of takeoff sheet for payment certificate
Quantity calculation for the ongoing works
Writing diary on executed tasks
Reading drawing
Site work: site works include all works that are conducted on the construction site towards
erecting and constructing the building components. It mainly includes the followings and
its details are put forth: -
Earth work
Foundation work
Superstructure work
2021/2013 10
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
It is the format which is used in a bill of quantity to list (include) a short description of the
specification along with its measuring unit, quantity and unit prices to determine the total cost for
each trade of item. There are four clearly defined steps in preparation of Bill of Quantities:
1. Taking off
2. Squaring
3. Abstracting
1 2 3 4 1 2 3 4
2021/2013 11
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
I have been using the above format for recording quantities and for writing descriptions to
accompany the quantities. Accordingly, Column 1 is used for stating the number of times an item
occurs and is called the timising column. Column 2 is called dimension column as it is used to
enter the dimensions of the items of works. The dimensions entered in column2 are squared or
cubed as the case may be, multiplied by the timising factor, and the result entered in column3. This
task is called squaring. The squared dimensions are transferred to abstract sheets and all similar
dimensions are collected in the same category to obtain the total quantity of each item. After the
abstract sheets have been completed and checked, the final bill of quantity is written.
Format used to calculate the quantity of reinforcement bars. In this format the quantity of bar of
each diameter will be calculated.
It. Loca Typ Shape (mm Le No. No. Tot Total length (m)
No tion e ) ngt of of al
h bars me no.
(m per mbe of Ø 8 10 12 14 16 20 24
) me r bars 6
mbe
r
Total length(m)
Total weight(kg)
2021/2013 12
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
In office i also tried to read detail drawings of the building being constructed. It has a paramount
important in improving the skill of understanding the 3D of the structure and helps me to priory
know what to be constructed. This drawing includes architectural, structural, sanitary and electrical
drawings. Every construction activity is undertaken by referring to those drawings and the engineer
executes and controls the whole work based on them.
CEMENT
Ordinary Portland cement is most widely used cement in the construction of my site and it is
suitable hydraulic cement. It is a fine powder used to create bond and strength when used in
concrete or mortar. Mostly it is found in market with a size of 50 kg bag pack and it is a hydrophilic
material which means it attracts water and changes to a hard stone for this reason storing of cement
needs a special care. In my site there is a store house to keep the cement dry. Usually they put flat
wood on the ground in order to avoid the moisture arising from the ground.
2021/2013 13
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Coarse aggregate
Aggregates are important constituents in concrete they generally occupy 65- 75% of the volume
of concrete hence due consideration should be given in their selection and proportion. In choosing
aggregate for in a particular concrete attention should be given to Strength and durability. The
aggregate used on the site is a product of national cement plc. Transported from dire dawa it has
basaltic nature with grain size of 1-4 cm.
Fine aggregate
Shall be of coarse sand consisting of hard, sharp and angular grains and shall pass through a screen
of 5mm square mesh. Sand shall be of standard specifications, clean and free from dust, dirt and
organic matter.
2021/2013 14
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Water
It should be free from impurities such as suspended solids, silt, clay, acids, alkalis,
organic matters and dissolved salts.
Tests by the sense of smell, sight should reveal such impurities; however, water of doubtful quality
should be submitted for laboratory analysis and test.
STONE
There are different kinds of stones in the process of construction in project the most widely used
are
2021/2013 15
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Batching
Prior to the mixing of ingredient, it is essential to measure the materials accurately to ensure the right
proportions. The concrete may be batched either by weight or by volume. Even though batching by
weight is preferable for its simplicity and convenience, volume batching was being used at my
construction site. But cement is always measured by weight; one bag of cement is 50kg and it is taken
as 35lit for relative proportioning.
The following relations show the grade of concrete with their relevant ratios and dimension of the
boxes used for the volume bathing.
Mixing of concrete
During batching it is essential to select suitable ingredients of concrete and proportioning their relative
quantities with the object of getting as economically as possible concrete of certain minimum
properties such as strength, durability and workability.
Variable factors that should be considered in specifying concrete mix are: water cement ratio,
cement aggregate ratio, gradation of aggregate and workability of fresh concrete. One common
2021/2013 16
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
practice of expressing the proportions of the granular materials in concrete mix is by ratio of
cement, fine aggregate and coarse aggregate, with cement considered as unity. Except lean
concrete all of the works on my site have being performed by C-25 quality concrete and the
specified gradients ratio that was intended to produce this grade of concrete is 1:2:3, with minimum
cement content of 360kg per meter cubic of concrete. While for lean concrete(C-5), the ratio is
1:3:6, with minimum cement content of 150kg.
The ingredients of concrete are mixed thoroughly such that they are uniformly distributed in the
concrete mass and shall produce a workable and consistent mix. Since the site constitutes large
construction works and hence it required good quality of concrete, they were using machine mixing
method. All the ingredients including water are put according their ratio in to the mixing drum,
mixer, which is rotating. The drum is rotated for 2 to 3 minutes to mix one batch of concrete and
then the mix is taken out of the drum and immediately transported to the place where it will be
casted. The quick transportation of concrete is essential such that the concrete is placed and
compacted before the initial set of cement starts.
Placing of concrete
It refers to casting of the concrete on its final position and thus ensures proper distribution of
concrete in the structure. Concrete must be placed in position as soon after mixing as possible and
before too stiff to work. The important points to be noted in placing concrete are the following:
Compaction of concrete
In this process effort are only directed to reduce the voids in the compacted concrete. During
vibrator and immediately after, depositing concrete shall be compacted means of mechanical
vibration. Vibrators produce vibrations and transmitted to concrete make it to flow and affect
compaction. Over vibration should not be allowed as otherwise course aggregate particles will
2021/2013 17
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
get concentrated at the lower layer and only mortar will be left at the top surface. Vibrator is also
known as needle pocket or immersion vibrator. It consists of a power unit and a long flexible
tube at the end of which vibrating head is attached whenever compaction is done. The vibrating
head is inserting in concrete. This is very use full for compaction of concrete work
Curing of concrete
After placing concrete in position, it should remain protected for sufficient time to become durable
and strong. Concrete shall be protected from premature drying and excessively hot temperatures
for max. 28 days from the date of casting. The concrete surface shall be kept continuously wet by
application of water for at least 7 days to maintain constant temperature and thus regulate its heat
of hydration. Where the temperature is excessively high the surface of concrete shall be covered
with absorptive mat, fabric or sand continuously kept wet or the application of other moisture
retaining covering as approved by the Engineer. The watering of concrete shall continue until the
concrete has achieved its designed strength. Proper curing of concrete has a prominent use such
as: -
Lean concrete: is a C-5 quality concrete which is laid under footing pads, grade beams and
masonry walls. Lean concrete is mainly laid for the following purposes: -
One should notice that lean concrete has no structural function a part from the above
mentioned uses. Most commonly a lean concrete of 5cm thickness is used for its requirement
2021/2013 18
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
3.3.4 Reinforcement
Setting of reinforcement
Reinforcement steel is buried in concrete to keep them from cracking & breaking this
reinforcing steel must be set in different forms before the concrete is placed.
Reinforcement steel is placed a dry place to prevent steel from rust.
2021/2013 19
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
As per the design, as shown in the plan, the size of bars and spacing of the bars to be placed in the
concrete are known. The supervisor gives a copy of the engineers plans to the bar bender, who
prepare the reinforcement.
When the bar bender receives the plan, the bar schedule showing nothing but lengths, sites and
bending needed for all the reinforcing bars in the construction for a given footing pad, foundation
column, beam column, stair and slab. The bar bender then cut and bend the steel rod as the
requirement.
Placing of reinforcement
As required for the construction of footing pad, foundation column, beams column, stair and slab,
when all of the reinforcing bars have been cut to the right length and have been bent, then the main
beam and column reinforcements tied with stirrups of diameter 6mm bars by tying wire.
2.3.5 Formwork
It is a temporary structural element which supports and molds slabs, beams, footings and other
structural members in casting concrete. It shall be designed and erected to safely support, vertical
and lateral loads that might be applied until such load can be supported by the concrete structure.
One should always remember that these works should be constructed in such a way that removal
of formwork can be done easily as planned. Most common materials used for temporary works,
formworks, are timber, plywood and steel. The period of removal for vertical formworks such as
columns and footings is 16 hrs. Or lesser and for horizontal members such as beams and slabs is
less 21days.
2021/2013 20
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Requirements of formworks: -
formwork should be coated with form oil to prevent adhesion of concrete such that it
allows easy stripping
should be fixed in position and stiff enough to resist the pressure and weight during
casting and in other cases
It should be rigid enough to retain the shape without excessive deformation
Formwork must be easily removable
Stripping time: in normal circumstances (generally where the temperature is above 20 0C) and
where ordinary cement is used, forms may be struck after expiry of the following periods.
2021/2013 21
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
2.4.1 Beam
A building member used to carry and transfer loads to the consecutive columns and used as a
confining element for the slab. As that of grade beams, supper structure beams are subjected to
moments and shear loads. Detail provision and reinforcement are provided as that of grade beams.
But the difference is it does not have contact with the ground and thus the construction needs
bottom formwork (soffit) and props for casting. When the slab and beams are to be made of the
same concrete quality they are casted monolithically and the beams are designed as T-beam and
L-beam. On my site all beams are of a rectangular dimension and fixed ended.
2021/2013 22
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Any building structure loads increase as i go down to the ground and so bottom structural members
are properly configured that they carry all super structural loads above it and transfer safely to the
foundation. Hence the sections of columns in upper stories are reduced as they have to carry lesser
loads. But center lines of columns must coincide accurately for various columns of different stores.
The steel reinforcement from the column in the lower story is bent such that they are
accommodated in the column of the top floor.
Both longitudinal bars and stirrups are provided according to their spacing
Spacers are tied with bars and then formwork is constructed for the member
Its verticality is checked with plumb bob
Concrete is poured into formwork and vibrated around rod reinforcement
Formworks are removed after expiry of their period and the concrete surface is watered
until it sufficiently cures
2.4.3 Slab
Slab is a structural part of the building having plate shape and used to cover the distance between
beams and possibly columns. Generally, slabs are constructed monolithically with beams and
concreted in one operation for the full depth. The top surface of the slab is kept rough to create a
proper bond with any type of floor finish desired. At our project site they used solid slab.
2021/2013 23
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
1) Solid slab: it was constructed from a concrete quality C-25 and its reinforcement details
were the same to those of beams. The bottom reinforcement is continuous over the entire
span and top reinforcement is provided at the support section to take up the tensile forces.
The designed solid slabs were for two panels and they are the panels where toilets and
water closets present. Since solid slabs have a greater concrete depth, they are meant for
their greater prevention of water percolation a part from its structural function.
• Supporting system is constructed and formwork is laid with panels and checked entirely
for not being pierced
• Reinforcements are provided according to their details and spacers are placed between
panels and reinforcement bars
• All fixtures such as sanitary, electrical and water pipes are positioned and installed
according to their drawings
• Concrete is casted properly while fulfilling its requirements
2021/2013 24
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
wall to prevent seepage and to bear lateral loads that comes from backfilled material and for the
corners of the building columns as an additional core. And also used for an aesthetical purpose.
2.4.5 Stairs
Stairs are the commonly used means of vertical transportation in buildings. For building up to three
floors, only stairs are usually provided but for buildings more than three floors, both electrical lifts
and stairs are to be provided. On our project site the building being educational and G+4, it is
provided with stair. The stair case is doglegged type half turn stairs and it is provided with main
longitudinal bars bedded into the slab and transverse reinforcements tied with main bars. The stair
case was made of reinforced concrete quality of C-25. The common terms used in stairs are tread,
riser, flight, pitch or slope and soffit. Generally, it is very important that we should not change the
dimensions of tread and rises from the start to finish of the stairs.
2021/2013 25
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Form works (panels) were constructed. The level, cleanness & smoothness of the form
work were also checked.
The reinforcement was placed & the diameter, number, length shape & bending
dimension of main bars are checked according with the drawing.
The bars & form work is checked before casting.
Both the slab & the stair is casted monolithically.
The form works were removed after 21 days
Note that all supervision works and checks to be done for super structure are the same to sub
structure and all are done according to the quality requirements of each items of work.
Masonry is the building of structures from individual units laid in and bound together by
mortar; the term masonry can also refer to the units themselves. The common materials of masonry
2021/2013 26
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
construction are brick, stone, marble, granite, travertine, limestone, cast stone, concrete block,
glass block, stucco, and tile. Masonry is generally a highly durable form of construction. However,
the materials used, the quality of the mortar and workmanship, and the pattern in which the units
are assembled can significantly affect the durability of the overall masonry construction.
These are:-
The above block are used for main wall, partition wall and toilet and shower respectively. In the
site the ingredient of HCB were cement, sand, zero size aggregate, white soil, komiche and water.
This overall mixing ratio were 1:2:2:2:6 respectively and water is added simply by judgment
means that for 50kg of cement they were used two wooden box of sand, two zero size aggregate
and two white soil with standard box size of 20*40*50cm and six wooden box of 25*25*40cm.
2021/2013 27
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
~ One the site activities I had observed continuously throughout my two month stay is plastering.
~ Plastering is the process of covering various surfaces of structure with plastic materials such as
cement mortar, lime mortar or composite mortar, to obtain an even smooth, regular, clean and
durable surface. Provide base for receiving other decorative finishes like painting.
1. First coat is held on directly on the HBCs or chiseled exposed beam and column to some
millimeter and have a rough surface prepare for the second coat. The mortar to be used for this
first coat has a mix ratio of 1:3.
2. the second coat locally called "mullet" is done by first doing fasha which is two nail is nailed at
the same level and a tread is tied on each nail keeping the same horizontal level and a plum bob is
thrown around 40cm above the ground level another fasha is done from these references the rest
part of the wall is plastered. The mortar to be used this first coat has a mix ratio of 1:2.
3. The third coat is usually done as the finishing work start and is different from the first and second
as it is gypsum used rather than mortar. If done properly it would provide the perfect base for the
finishing paint.
2021/2013 28
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
2021/2013 29
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
forced us to withdraw our internship program for few months and even if i tried to manage starting
it again the working environment were difficult to do given task and moving around as you like.
Footing pad bars... Grilla............. Reinforcement bar mesh under footing pad
Bottom soffit........ Fando ..............Is used as a formwork for beams and slabs at the bottom.
Side board.......... Sponda...........Aims as a formwork for beams and slabs on vertical sides.
2021/2013 30
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Yoke .....................Karabat ............Used to fix the form works together in their position.
Segregation problems: once after the concrete is placed in to the formwork, one cannot easily
detect the occurrence of segregation, instead the happening of segregation is seen after the
formwork is removed off. This is the major and foremost problem that is encountered after the
concrete is placed. It is a separation of coarse aggregates from the concrete mass and is caused by:
Uncontrolled pumping or falling
Placing under waters
Placing concrete in heavily reinforced members
Poor vibration
Precautions to control segregation:
2021/2013 31
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
CHAPTER THREE
Since the field of civil engineering mostly comprises of field activities, the one who take an
internship program on the site is expected to come up with a tremendous practical skill. One thing
that needs to be pointed out when discussing improving practical skills is that i got to learn how to
associate myself with professionals who had a lot to offer in the field. Being able to easily
communicate and understand each other with supervisors greatly improves one’s practical skill.
I would like to list the practical skills i gained from the internship program as the following:
Supervision of construction materials such as cement, aggregate, sand and etc.
The methods and steps of how structural members are erected
Problem solving skills when it encountered
Able to inspect and understand things that remained vague during our theoretical lessons
Improved my ability of understanding and reading working drawings etc.
The methods and steps of how structural members are erected
Problem solving skills when it encountered.
Generally this internship program let us to assume ourselves as a potentially responsible workman
for a particular work that i were assigned whether from the contractor side or consulting company
to charge my responsibility independently and confidently. And it also got me with construction
methodologies and expression of ideas towards problem solving.
2021/2013 32
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
table or in theory; instead it helped in improving the already available ways and ideas of problem
solving skills to a great level.
Generally, an internship program is the system by which the students can observe the practical real
world and relate it with the theoretical lessons. Being attended this program effectively, i made
clear on issues that were remaining unclear and i were vague of. I can also assure internship’s
paramount important in providing a brand new ideas that i were not familiar with before and ideas
that are proven quite helpful when it comes to solving practical problems. But what worth
mentioning is some of the courses have a premier position in contributing for the success of the
internship program and ease in understanding the tasks conducted on the site. Of such courses
include: -construction material, structural courses and foundation courses.
2021/2013 33
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Of course it is not always that such situations arise but since the work is done by professionals
who after all are human beings, it is expected to see some altercations. And as a leader, one needs
to learn how to handle and resolve such cases without too many negative consequences. Plus,
controlling the overall activities taking place on a construction site by itself is a big leadership
quality that needs to be encouraged. Thanks to my supervisor and employers, i were able to observe
and witness a great leadership quality and were able to take some points on how to develop my
own leadership qualities after all and in the near future.
Although i were hosted by the consulting company, the leadership skill i were been developing is
not solely from my supervisor but i had been observing the leading ways from the contractor side.
The site engineers who controls and executes the overall work shall have a good leadership skill
and it has been also an area for us where i were able to see what the leadership is and how it should
be. And accordingly, good leadership greatly contributes for the overall healthy construction
environment and for retaining the workers and employees on their working position and thus for
success of the project while meeting both its quality and completion period.
2021/2013 34
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Punctuality is one of the major issues that could be raised when talking about work ethics and on
my side i tried to meet this criterion by attending to my working station in time so that there will
not be any delay on the activities planned for that day. The behaviour that one shows towards his
peers and colleagues is also one manifestation of the concept of work ethics. Personally, i always
respected and gave priority the employers of the company.
Elements of work ethics that worth mentioning are: -punctuality, honesty, reliability, office
discipline, corporation and responsibility.
Generally, i am student should follow the rules and regulations set by the company and avoid
complaining any work load, activity or assignment that may arise on the site or office. It is a
pleasure of supervisors if i have a good work ethics and i am responsible for any given tasks. Since
the aim of internship is to let students know the outside environment pertinent to their field, which
includes of such the above dealt qualities, i were with the great interest that i tried to meet my
responsibilities and work ethics that i supposed to be based on my wisdom.
2021/2013 35
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
They are varying in educational level, work experience and work position. Since the aim of the
project is to accomplish the work in good way, i just try to have good communicative skills with
people around. As i tried to know some things that are strange to me on the site, i would ask those
nearby to me and whom i supposed they know. In turn, besides understanding the ambiguities and
vague, i were developing the communication ways and interpersonal communications. What i
literally can say is interpersonal communication skills are not so developed intentionally and been
recognizing, but its improvement depends on the student’s or on the ones eagerness and interest to
know things from those experts or any concerned professional. What also i could assure was site
engineers, supervisors and office engineers are easier to ask them than university teachers. As such
the internship program was being an ideal place where i greatly developed my interpersonal
communication skill.
Generally, for any person communication is an important way of learning, which can be defined
formally as the act, process, or experience of gaining knowledge or skills and sharing what i know.
Cool communication is important in the real constructions world and it can appear indifferent
forms as speaking, writing, and listening.
2021/2013 36
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
CHAPTER FOUR
4.1 Conclusion
I am in the position now to attest how the overall internship program has contributed in owing
knowledge and in introducing the students prior in to the outside engineering environment by
which most of the students will be intervened by the near future. It has been an ideal place and
program for us to freshly and keenly grasp site experiences, upgrade theoretical knowledge and to
widen my perspective from many angles when design and construction of structures are issues at
hand. It has been also an exciting event especially for those who had stressed too much during
their university stay, meanwhile here was the place where you recall and relate the theoretical
knowledge that u possess and discuss with many experienced professionals, engineers.
There was a gap between the knowledge which i know in the class with the outside environment
that means the working environment in site know this gap is narrowed in the internship program.
I got practical work experiences and benefits after i attend in to Harari Housing Development and
Government construction Agency office Administration building project.
2021/2013 37
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
4.2 Recommendation
Universities and the company are providing good opportunities for students in this internship
program. But in both side there is problem. So i would like to recommend both of them to do
better.
Since bars are the main input of reinforced concrete i should give great care for the bars
to prevent it from corrosion.
They should organize their construction material in good condition. Sometimes they place
formworks and metal scaffolding in inappropriate area that means exposed to corrosion.
On the mix concrete the ratio of cement, sand, aggregate and addition of water are high
sometimes doesn’t properly done based on the needs design provided. Accordingly, the
consultant and site engineer should test the strength of the mix before cast.
In most concrete work, labors do not give consideration on segregation and mortar laws,
there by the contractor must give grade consideration and control every works.
Most of site worker, particularly site engineers and daily laborers do not have safety closes
like safety shoes, helpmates, etc. to protect them from sudden injuries. Due to this
problem, they are exposed to different injuries while working. Therefore, we recommend
the company to arrange safety tools for site workers.
The company reuses some materials such as wood and nails which have economically
important to the company. However, reuses of such staff have difficulty for workers and
delays the works.
2021/2013 38
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Field trips and Practical observations should be arranged more often in accordance with
the theoretical class. Which is very helpful to easily understanding of the theoretical
courses given in the class and also it makes the teaching learning more practical rather
than theoretical this make the students full confidential and good professional in the field
of study.
The university should have close and strong communication with the hosting
organization to supervise the students on the internship period.
The pocket money given to us is insufficient b/c of the market condition and it not given
for the students by the scheduled period it must be given a care.
2021/2013 39
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Reference
Company brochure and documents containing detailed explanation of the organizational
structure.
Company profile and stuffing documents
Construction management books
Building construction book by P.C. Varghese
Quantity surveying and specification handouts
Building design and construction handbook
2021/2013 40
Department of Civil Engineering
Madda Walabu University Final internship report
2021/2013
Appendix
C-5: a compressive strength of 5MPa for a concrete
Footing pad bars... Grilla............. Reinforcement bar mesh under footing pad
Bottom soffit........ Fando ..............Is used as a formwork for beams and slabs at the bottom.
Side board.......... Sponda...........Aims as a formwork for beams and slabs on vertical sides.
Yoke .....................Karabat ............Used to fix the form works together in their position.
2021/2013 41
Department of Civil Engineering