SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Pipeline Right of Way (ROW) Inspection SAIC-L-1001 30-Oct-17 CIVIL-


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A PIPELINE ROUTE AND PROFILE

The pipeline route as stipulated on the Issued for Construction (IFC)


drawings shall be surveyed and staked by the Construction Contractor.
SAES-L-450
A1 Changes to original routing may be acceptable with prior approval by
Sec. 7.1.1
Saudi Aramco PMT and the Proponent Representative prior to
implementation in the form of Modified IFC Drawings.

The Construction Contractor shall field verify the original vertical profile of
the pipeline, the amount of cover, the location and degree of elastic and
SAES-L-450
A2 preformed bends, in accordance with the IFC drawings. The change in
Sec. 7.1.2
slope of the pipeline at normal spacing of 30 m., and at intermediate
stations as required, shall be calculated.

Fills and cuts shall be made to reduce the number and/or magnitude of
SAES-L-450
A3 overbends and sagbends in the pipeline. Fills should be avoided in areas
Sec. 7.1.3
where the natural drainage of the surrounding area is affected.

Provisions shall be made to prevent wash-out of the pipeline cover by rain SAES-L-450
A4
storms if the pipeline construction changes the natural drainage pattern. Sec. 7.1.4

B PIPELINE RIGHT OF WAY (ROW)

The construction right-of-way shall be graded to a flat or smooth rolling


SAES-L-450
B1 surface and shall be maintained accessible with standard four-wheel drive
Sec. 7.2.1
vehicles on at least one side of the line during construction period.

In sabkha areas, fill shall be provided to support construction equipment


as required. The width of such fills and cuts shall not be less than the SAES-L-450
B2
area to be stabilized and the adjacent slopes shall not be steeper than Sec. 7.2.2
four to one.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-30-Oct-2017- REV. 2017.06.00 (Standards Cutoff -June 30, 2017) Rev. 2017.06.00 30-Jun-17

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Pipeline Right of Way (ROW) Inspection SAIC-L-1001 30-Oct-17 CIVIL-


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

The final finished right of way shall be at least 5 meters (6 meters in


SAES-L-450
B3 Sabkha areas and 3 meter in sand dune areas) wide from bottom edge of
Sec. 7.2.3
pipeline berm.

Construction waste materials shall be removed from the right-of-way as SAES-L-450


B4
the construction progresses. Sec. 19.1

REMARKS:

REFERENCE DOCUMENTS:
1- SAES-L-450 -- Construction of On-Land and Near Shore Pipelines,12 October 2015
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED