1.0 SCOPE
This method statement describes the procedures and responsibilities of site personnel which are
involved in the work for assembling reinforcement bar for the ground floor column.
2.0 RESPONSIBILITY
2.1 project manager is responsible for all aspects of the work.
2.2 The project site engineers are responsible for proper execution, arrangement, co-ordination
and supervision for quality, safety, and delivery of work.
2.3 The surveyor shall be responsible for the proper levelling and setting out of the area.
2.4 Safety officer will ensure the work process follows the set down safety standard.
4.0 PREPARATION
The area for the work to be thoroughly cleaned and marked out and all loose sharp reinforcement
be removed prior to start of work. All access and egress should be cleared. All concrete level be
taken according to specifications.
Slab formwork shall be 15mm thick plywood. The slab formwork shall be placed on top of a timber
frame. The levels of slab shall be checked after the reinforcement work.
5.0 PROCEDURE
Seven (7) days early strength grade 25 ready mix concrete with 150mm slump shall be
placed into slab. The poker vibrator shall be inserted to give sound compaction. Top of the
concrete level shall be maintained properly while concreting.
After 24hours of laying concrete, the surface shall be cured by flooding with water.