Daerah Pusat Inventory (Lot Size) Lead Time Foreacst

Safety Stock
Distribusi on Hand Order Quantity (Minggu) Units/Minggu
1 Jakarta 225 115 500 1 112
2 Madiun 164 125 200 1 47
3 Semarang 350 47 500 1 127
4 Surabaya 1170 287 2200 2 0
Penyelesaian

1 Lead Time Safety Stock Lot Sizing PERIODE


1 115 500 PD 1 2 3
Gross Requirement 112 112 112
Schedule Receipe 500
Project On Hand 225 613 501 389
Net Requirement
Planned Order Receipt 0 0
Planned Order Release 0 0 0

2 Lead Time Safety Stock Lot Sizing PERIODE


1 125 200 PD 1 2 3
Gross Requirement 47 47 47
Schedule Receipe 200
Project On Hand 164 317 270 223
Net Requirement
Planned Order Receipt 0 0
Planned Order Release 0 0 0

3 Lead Time Safety Stock Lot Sizing PERIODE


1 47 500 PD 1 2 3
Gross Requirement 127 127 127
Schedule Receipe 0
Project On Hand 350 223 96 469
Net Requirement 78
Planned Order Receipt 0 500
Planned Order Release 0 500 0

4 Lead Time Safety Stock Lot Sizing PERIODE


2 287 2200 PD 1 2 3
Gross Requirement 0 500 0
Schedule Receipe 0
Project On Hand 1170 1170 670 670
Net Requirement
Planned Order Receipt 0 0 0
Planned Order Release 0 0 2200
PERIODE
4 5 6 7 8
112 112 112 112 112

277 165 553 441 329


62
0 0 500 0 0
0 500 0 0 0

PERIODE
4 5 6 7 8
47 47 47 47 47

176 129 282 235 188


43
0 0 200 0 0
0 200 0 0 0

PERIODE
4 5 6 7 8
127 127 127 127 127

342 215 88 461 334


86
0 0 0 500 0
0 0 500 0 0

PERIODE
4 5 6 7 8
0 700 500 0 0

670 2170 1670 1670 1670


317
0 2200 0 0 0
0 0 0 0 0
Daerah Pusat Inventory (Lot Size) Lead Time Foreacst
Safety Stock
Distribusi on Hand Order Quantity (Minggu) Units/Minggu
Jakarta 215 115 300 2 140
Madiun 350 125 350 1 170
Semarang 155 45 250 2 100
Surabaya 1000 500 900 1 0
Penyelesaian

Lead Time Safety Stock Lot Sizing PERIODE


2 115 300 PD 1 2 3
Gross Requirement 140 140 140
Schedule Receipe 300
Project On Hand 215 375 235 395
Net Requirement 20
Planned Order Receipt 0 300
Planned Order Release 300 0 0

Lead Time Safety Stock Lot Sizing PERIODE


1 125 350 PD 1 2 3
Gross Requirement 170 170 170
Schedule Receipe 0
Project On Hand 350 180 360 190
Net Requirement 115
Planned Order Receipt 350 0
Planned Order Release 350 0 350

Lead Time Safety Stock Lot Sizing PERIODE


2 45 250 PD 1 2 3
Gross Requirement 100 100 100
Schedule Receipe 0
Project On Hand 155 55 205 105
Net Requirement 90
Planned Order Receipt 250 0
Planned Order Release 0 250 0

Lead Time Safety Stock Lot Sizing PERIODE


1 500 900 PD 1 2 3
Gross Requirement 650 550 350
Schedule Receipe 900
Project On Hand 1000 1250 700 1250
Net Requirement 150
Planned Order Receipt 0 900
Planned Order Release 0 900 0
PERIODE
4 5 6 7 8
140 140 140 140 140

255 115 275 135 295


140 120
0 0 300 0 300
300 0 300 0 0

PERIODE
4 5 6 7 8
170 170 170 170 170

370 200 380 210 390


105 95 85
350 0 350 0 350
0 350 0 350 0

PERIODE
4 5 6 7 8
100 100 100 100 100

255 155 55 205 105


40 90
250 0 0 250 0
0 250 0 0 0

PERIODE
4 5 6 7 8
300 550 350 0 0

950 1300 950 950 950


100
0 900 0 0 0
900 0 0 0 0