SUBCONTRACTOR SCOPE & AGREEMENT


Project:
Client Name: LOCATION:
________________________________ _______________________________

Contractor:_________________________________________________________________________
Subcontractor:______________________________________________________________________
Date Start: Target Date of
__________________________________ Accomplishment:_______________________________

ARCHITECTURAL (or insert other subcon awarded scope):


 HOUSE CONSTRUCTION (LIVABLE AND USABLE AREAS)
 LANDSCAPING
 FENCE AND GATE
 OTHERS (PLEASE
SPECIFY):____________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________

GROUND FLOOR

TOTAL SQM
AREA(s) FINISHES AND INCLUSIONS (Measured
wall to wall)
GROUND FLOOR
 LIVING AREA
Flooring
-Use 60 x 60 cm Vitrified Tiles (Color/ Design refer to
swatch(s) given.
-Use Tile adhesive
-Use tile grout

Ceiling:
Cove layout ( see working drawings for details)
Use gypsum board ______ mm THK.
Use metal furring for framing.
Use skim coat for finishing
Use flat white paint.

Walls:
@ Exterior Walls

1
(Note: General Contractor Logo only )
Use 6’’ CHB plastered finish
Use skim coat
Use flat white latex paint primer
Use semi-gloss paint for finishing
Rebars: Specified @ drawings.

Electrical:
Roughing-in based on schedule and lay-out based on
electrical plans,load computation and schedule
shown @ drawings.
Use Royu brand switches and convenience outlet
(No. Will be based on drawings, BOM and BOQ
given.)
-Include panel Board.

 DINING AREA Flooring:


-Use 60 x 60 cm Vitrified Tiles (Color/ Design refer to
swatch(s) given).
-Use Tile adhesive
-Use tile grout

Walls:
@ Exterior Walls
-Use 6’’ CHB plastered finish
-Use skim coat
-Use flat white latex paint primer
-Use semi-gloss paint for finishing
-Rebars: Specified @ drawings.

@Interior Walls
-Use 6 mm HardieFlex or approved as equal drywall
-Use skim coat
-Use flat white latex paint primer
-Use semi-gloss paint for finishing
-Use studs and tracks (see drawings for details)
Note: Except toilet and bath(s) and Powder
Room(s).

Ceiling:
Layout please based on working drawings
-Use gypsum board ______ mm THK.
-Use metal furring for framing.
-Use skim coat for finishing
-Use flat white paint.

Electrical:
Roughing-in based on schedule and lay-out based on
electrical plans,load computation and schedule
shown @ drawings.

2
(Note: General Contractor Logo only )

 KITCHEN AREA FLOORING:


-Use 60 x 60 cm Vitrified Tiles/Non- Slip Tiles (Color/
Design refer to swatch(s) given.
-Use Tile adhesive
-Use tile grout

Walls:
@ Exterior Walls
-Use 6’’ CHB plastered finish
-Use skim coat
-Use flat white latex paint primer
-Use semi-gloss paint for finishing
-Rebars: Specified @ drawings.

@Interior Walls
-Use 6 mm HardieFlex or approved as equal drywall
-Use skim coat
-Use flat white latex paint primer
-Use semi-gloss paint for finishing
-Use studs and tracks (see drawings for details)
Note: Except toilet and bath(s) and Powder
Room(s).

Ceiling:
Flat Ceiling
-Use gypsum board ______ mm THK.
-Use metal furring for framing.
-Use skim coat for finishing
-Use flat white paint.

Electrical:
Roughing-in based on schedule and lay-out based on
electrical plans, load computation and schedule
shown @ drawings.
Use Royu brand switches and convenience outlet.
(No. Will be based on drawings, BOM and BOQ
given.)
Include panel Board.

Plumbing:
-Use specified sanitary pipes and fittings @ BOM,
BOQ and Working Drawings.
-Use specified waterline pipes and fittings @ BOM,
BOQ and Working Drawings.

Inclusions:
-1.80 li. mts. Cabinets
-Use ¾ “ Marine Plywood

3
(Note: General Contractor Logo only )
- Use Laminate Finish (Color/ Design refer to
swatch(s) given).
-1.80 li. mts. Hanging Cabinets
-Use ¾ “ Marine Plywood
- Use Laminate Finish (Color/ Design refer to
swatch(s) given).
-Fixture Inclusion
1-sink (Single-Tub w/ Drain)
1-Single lever kitchen faucet (gooseneck)

 POWDER ROOM/ Flooring:


T&B Use 30 cm x 30 cm non-slip tiles (Color/ Design refer
to swatch(s) given.)
-Use Tile adhesive
-Use tile grout

Walls:
-Use 4’’ CHB wall
-Use 30 cm x 60 cm glazed tiles (Color/ Design refer
to swatch(s) given.)for Finishing
-Use tile adhesive
-Use tile Grout

Ceiling:
Flat Ceiling
-Use 3.5 mm THK HardieFlex or approved as equal
plaster board.
-Use metal furring for framing.
-Use skim coat for finishing
-Use flat white paint.

Electrical:
Roughing-in based on schedule and lay-out based on
electrical plans, load computation and schedule
Shown @ drawings.
Use Royu brand switches and convenience outlet.
(No. Will be based on drawings, BOM and BOQ
given.)
Include panel Board.

Plumbing:
-Use specified sanitary pipes and fittings @ BOM,
BOQ and Working Drawings.
-Use specified waterline pipes and fittings @ BOM,
BOQ and Working Drawings.

Inclusions: (Cool or Pozzi Brand or Approved as


equal)

4
(Note: General Contractor Logo only )
Fixtures:
Wall hang lavatory
Water Closet
Bidet Spray
Faucet ( Single handle basin mixer faucet) as
indicated number(s)
Telephone Shower (if included @ draings)
Appurtenances:
Soap and Tissue Holder
Fittings

Flooring:
Concrete Pavement
@ Counter top 60 cm X 60 cm tiles
 SERVICE AREA @Depressed at sink area

PLUMBING:
-Hose bibb and roughing-in
 PORCH Concrete pavement
 LANAI Concrete pavement
Flooring:
Concrete Pavement
 CARPORT
PLUMBING:
-Hose bibb and roughing-in
 MAID’S ROOM
Flooring:
- HDF Wood Laminate 194 x 1212 x 8mm
(color/design as per approved swatch of client) -Use
–Use adhesive based on installation process
required.

Walls:
@ Exterior Walls
-Use 6’’ CHB plastered finish
-Use skim coat
-Use flat white latex paint primer
-Use semi-gloss paint for finishing
-Rebars: Specified @ drawings.

@Interior Walls
-Use 6 mm HardieFlex or approved as equal drywall
-Use skim coat
-Use flat white latex paint primer
-Use semi-gloss paint for finishing
-Use studs and tracks (see drawings for details)
Note: Except toilet and bath(s) and Powder
Room(s).

Ceiling:

5
(Note: General Contractor Logo only )
Layout please based on working drawings
-Use gypsum board ______ mm THK.
-Use metal furring for framing.
-Use skim coat for finishing.
-Use flat white paint.

Electrical:
Roughing-in based on schedule and lay-out based on
electrical plans,load computation and schedule
shown @ drawings.

Flooring:
- HDF Wood Laminate 194 x 1212 x 8mm
(color/design as per approved swatch of client) -Use
–Use adhesive based on installation process
required.

Walls:
@ Exterior Walls
-Use 6’’ CHB plastered finish
-Use skim coat
-Use flat white latex paint primer
-Use semi-gloss paint for finishing
-Rebars: Specified @ drawings.

@Interior Walls
-Use 6 mm HardieFlex or approved as equal drywall
-Use skim coat
 MASTER
-Use flat white latex paint primer
BEDROOM
-Use semi-gloss paint for finishing
-Use studs and tracks (see drawings for details)
Note: Except toilet and bath(s) and Powder
Room(s).

Ceiling:
Layout please based on working drawings
-Use gypsum board ______ mm THK.
-Use metal furring for framing.
-Use skim coat for finishing.
-Use flat white paint.

Electrical:
Roughing-in based on schedule and lay-out based on
electrical plans, load computation and schedule
shown @ drawings.

 MASTER WALK IN Flooring:


CLOSET - HDF Wood Laminate 194 x 1212 x 8mm
(color/design as per approved swatch of client) -Use
–Use adhesive based on installation process

6
(Note: General Contractor Logo only )
required.

Walls:
@ Exterior Walls
-Use 6’’ CHB plastered finish
-Use skim coat
-Use flat white latex paint primer
-Use semi-gloss paint for finishing
-Rebars: Specified @ drawings.

@Interior Walls
-Use 6 mm HardieFlex or approved as equal drywall
-Use skim coat
-Use flat white latex paint primer
-Use semi-gloss paint for finishing
-Use studs and tracks (see drawings for details)
Note: Except toilet and bath(s) and Powder
Room(s).

Ceiling:
Layout please based on working drawings
-Use gypsum board ______ mm THK.
-Use metal furring for framing.
-Use skim coat for finishing.
-Use flat white paint.

Electrical:
Roughing-in based on schedule and lay-out based on
electrical plans,load computation and schedule
shown @ drawings.

INCLUSIONS:

1.2 MTS WIDTH CABINET


-Use ¾” Marine Plywood
-Use Laminate for finish ( Color /Design as approved
swatch)

 MASTER T&B Flooring:


Use 30 cm x 30 cm non-slip tiles (Color/ Design refer
to swatch(s) given.)
-Use Tile adhesive
-Use tile grout
-Use waterproofing

Walls:
-Use 4’’ CHB wall
-Use 30 cm x 60 cm glazed tiles (Color/ Design refer
to swatch(s) given.)for Finishing
-Use tile adhesive

7
(Note: General Contractor Logo only )
-Use tile Grout

Ceiling:
Flat Ceiling
-Use 3.5 mm THK HardieFlex or approved as equal
plaster board.
-Use metal furring for framing.
-Use skim coat for finishing
-Use flat white paint.

Electrical:
Roughing-in based on schedule and lay-out based on
electrical plans,load computation and schedule
Shown @ drawings.
Use Royu brand switches and convenience outlet.
(No. Will be based on drawings, BOM and BOQ
given.)
Include panel Board.

Plumbing:
-Use specified sanitary pipes and fittings @ BOM,
BOQ and Working Drawings.
-Use specified waterline pipes and fittings @ BOM,
BOQ and Working Drawings.

Inclusions: (Cool or Pozzi Brand or Approved as


equal)
Fixtures:
Pedestal type lavatory
Water Closet
Bidet Spray
Faucet ( Single handle basin mixer faucet)
Telephone Shower

Appurtenances:
Soap and Tissue Holder
Fittings

 __ BEDROOM (S) Flooring:


- HDF Wood Laminate 194 x 1212 x 8mm
(color/design as per approved swatch of client) -Use
–Use adhesive based on installation process
required.

Walls:
@ Exterior Walls
-Use 6’’ CHB plastered finish
-Use skim coat
-Use flat white latex paint primer

8
(Note: General Contractor Logo only )
-Use semi-gloss paint for finishing
-Rebars: Specified @ drawings.

@Interior Walls
-Use 6 mm HardieFlex or approved as equal drywall
-Use skim coat
-Use flat white latex paint primer
-Use semi-gloss paint for finishing
-Use studs and tracks (see drawings for details)
Note: Except toilet and bath(s) and Powder
Room(s).

Ceiling:
Flat Ceiling
-Use gypsum board ______ mm THK.
-Use metal furring for framing.
-Use skim coat for finishing.
-Use flat white paint.

Electrical:
Roughing-in based on schedule and lay-out based on
electrical plans, load computation and schedule
shown @ drawings.

INCLUSIONS:

0.80 MTS WIDTH CABINET


-Use ¾” Marine Plywood
-Use Laminate for finish ( Color /Design as approved
swatch)

 COMMON T&B Flooring:


Use 30 cm x 30 cm non-slip tiles (Color/ Design refer
to swatch(s) given.)
-Use Tile adhesive
-Use waterproofing
-Use tile grout

Walls:
-Use 4’’ CHB wall
-Use 30 cm x 60 cm glazed tiles (Color/ Design refer
to swatch(s) given.)for Finishing
-Use tile adhesive
-Use tile Grout

Ceiling:
Flat Ceiling
-Use 3.5 mm THK HardieFlex or approved as equal
plaster board.

9
(Note: General Contractor Logo only )
-Use metal furring for framing.
-Use skim coat for finishing
-Use flat white paint.

Electrical:
Roughing-in based on schedule and lay-out based on
electrical plans,load computation and schedule
Shown @ drawings.
Use Royu brand switches and convenience outlet.
(No. Will be based on drawings, BOM and BOQ
given.)
Include panel Board.

Plumbing:
-Use specified sanitary pipes and fittings @ BOM,
BOQ and Working Drawings.
-Use specified waterline pipes and fittings @ BOM,
BOQ and Working Drawings.

Inclusions: (Cool or Pozzi Brand or Approved as


equal)
Fixtures:
Pedestal type lavatory
Water Closet
Bidet Spray
Faucet ( Single handle basin mixer faucet)
Telephone Shower

Appurtenances:
Soap and Tissue Holder
Fittings

 BALCONY FLOORING:
-Use plain concrete pavement
-Use waterproofing
RAILING
-Use 2” x 2” tubular painted.
 ROOFING -Use gauge 24 pre-painted long span roofing.
-Use reflective bubble insulation.

 WINDOWS -Use 6mm THK. Anneal glass (or shaded) in


Aluminum Frame Powder Coated
- Note: In larger span of glass 6 mm Tempered Glass
must to use.
 STAIRS -Concrete Stairs
-Use Wood Planks on stair treads.
-Use 2”X2” tubular railing or s specified to drawings.
-Use Wooden millwork on handrail top
 EXTERIOR As shown in drawings

10
(Note: General Contractor Logo only )
FINISHING Note: This may include claddings, wood and tiles.
 EAVES -Use 3.5mm THK HARDIEFLEX OR APPROVED AS
EQUAL PLASTER BOARD.
-Use plain White Paint/ Wood Stain if specified.

 DOORS -As reflected to the Schedule of doors and windows.


NOTES:

Construction of _____________________________________________________________________
(Project Nature)
At ________________________________________________________________________________
(Location)

11
(Note: General Contractor Logo only )

SUB-CONTRACTOR AGREEMENT

THIS AGREEMENT is made this 5th of September 2021 between (Insert Name & Address
of General Contractor) (Hereafter, called “GENERAL CONTRACTOR”),

and (Insert Name & Address of Sub-Contractor) (Hereafter, called “SUB-CONTRACTOR”),


of the mentioned part above.

In consideration of payment to be made by the General Contractor to the Sub-Contractor, the Sub-
Contractor hereby covenants with the General Contractor to execute, complete and maintain the
Sub-Contract works in conformity in all respects with the terms and conditions of this Agreement.

In WITNESS thereof the General Contractor and the Sub-Contractor have hereunto set their
respective hands the day and the year first above written.

Authorized Signatory Authorized Signatory


On Behalf of the Sub-Contractor On Behalf of the General Contractor

____________________________ ____________________________
Printed Name and Signature Printed Name and Signature

12
(Note: General Contractor Logo only )

ACKNOWLEDGMENT

REPUBLIC OF THE PHILIPPINES (


__________________ CITY ) SS

BEFORE ME, a Notary Public, on this _______ day of ____________ , personally appeared
the following and exhibited their government-issued identification cards bearing their respective
photographs and signatures.

NAME ID NO.

They are known to me to be the same persons who signed this Sub-Contractor
Agreement consisting of 12 pages including the Annex and this page on which this
acknowledgment is written. They confirmed that the same is their voluntary act and deed
including that of the corporations that they represent.

Doc No. __________


Page No. _________
Book No. ________
Series of 2021.