Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
1 Vadodara Mumbai Expresway Project (Package - I) 1106 days Tue 20-03-18 Tue 30-03-21
2 Pre Construction Works (Development Period) 217 days Tue 20-03-18 Mon 22-10-18
3 Award of the project by Goverment to the Concessionaire 0 days Tue 20-03-18 Tue 20-03-18 20-03
4 LOI issued by IRB to L&T TIIC 0 days Tue 17-04-18 Tue 17-04-18 17-04
5 Signing of CA (between VK1 & NHAI) 0 days Wed 09-05-18 Wed 09-05-18 09-05
6 Signing of EPC Aggrement (between MRMPL & L&T TIIC) 0 days Mon 25-06-18 Mon 25-06-18 25-06
7 Signing of Supplementary Aggrement (Among VK1, IRB, MRM & L&T)0 days Wed 27-06-18 Wed 27-06-18 27-06
9 Appointment of Design Consultants by Contractor 1 day Mon 22-10-18 Mon 22-10-18 Appointment of Design Consultant[1]
12 Handing over of 80% encumberance free land including Utility 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
Shifting and Tree cutting for Phase 1
13 Handing over of 80% encumberance free land including Utility 90 days Sun 31-03-19 Sun 02-06-19 12
Shifting and Tree cutting for Phase 2
14 Dismantling of Structures 90 days Sun 31-03-19 Sun 02-06-19 12
15 Water Pipe Line Shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
16 ROB GAD approval from Railways 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
17 All Applicable permits relating to Environmental protection & 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
Conservation of the site
18 Conditions precedents-Contractor 0 days Sun 31-03-19 Sun 31-03-19 31-03
19 Permission of the State Government for Extraction of boulders 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
from quarries for and in respect of at least 20% (twenty percent)
of the total length of the Project.
20 Permission from village Panchayat for installation of Crusher 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
Plant.
21 Clearance of Pollution control board for setting up Crusher 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
plant.
22 License for use of Explosives. 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
23 Permission of the State Government for Drawing Water from 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
River / Reservoir
24 Contractor Obligation 74 days Wed 16-01-19 Sun 31-03-19
27 Identification of land, for camps, Quarries, & Plant establishment 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
29 Mobilization of plant & Equipments 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
32 GFC for Plan and Profile 15 days Sun 31-03-19 Wed 10-04-19 51 Horizontal alignment design[23,740],Vertical alignment design[23,740]
33 Appointment of Topo survey agecny 1 day Sun 31-03-19 Sun 31-03-19 51 Appointment of Topo survey agecny[1]
34 Appointment of Geotechnical Investigation Agency 1 day Sun 31-03-19 Sun 31-03-19 51 Appointment of Geotechnical Investigation Agency[1]
35 Approval of Pavement Design 15 days Mon 01-04-19 Thu 11-04-19 51,33,34 Pavement Design[1]
37 GFC of Pipe Utility Structures 45 days Sun 31-03-19 Thu 02-05-19 51 PC Design[18]
41 GFC of Minor Bridge 120 days Sun 31-03-19 Mon 24-06-19 51 Minor Bridge Design[4]
42 GFC of Minor Bridge - Gas /Oil/Water Pipe line 120 days Sun 31-03-19 Mon 24-06-19 51 Minor Bridge Design[4]
43 GFC of Major Bridge 150 days Sun 31-03-19 Fri 30-08-19 51 Major Bridge Design[3]
46 GFC of Flyover 120 days Sun 31-03-19 Mon 24-06-19 51 FOB Design[6]
47 GFC of Interchange 120 days Sun 31-03-19 Mon 24-06-19 51 Interchange Design[2]
48 RE Wall Design & Drawings 30 days Sun 31-03-19 Sun 21-04-19 51 RE Wall Design[1]
49 Approval of Project Facilities & Drainage Drawings 180 days Sun 31-03-19 Mon 30-09-19 51 Design for ATMS Works[1],Design for Building Works[1],Design for Electrical Works[1],Submission of design for drainage & protective works[23,740],Submission of design for junctions/intersections[23,740],Submission of design for other project facilities[1]
50 Schedule of Eight Laning of Vadodara Mumbai Expressway 730 days Sun 31-03-19 Tue 30-03-21
(Package-01 From CH 355+000 To 378+740)
51 Issue of Notice to Proceed (NTP) 0 days Sun 31-03-19 Sun 31-03-19 31-03
52 Submission of Construction Programme 0 days Sat 20-04-19 Sat 20-04-19 51FS+28 days 20-04
53 Section - I (From 355+000 To 357+000) 571 days Sun 31-03-19 Sat 14-11-20
Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress
Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
55 Land Acquisition 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
57 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,55 31-03
58 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,57 31-03
59 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,58 31-03
60 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
61 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,55 31-03
62 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,61 31-03
63 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,62 31-03
65 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,55 31-03
Authority
66 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,65 31-03
authority to shifting of utilities
67 Water Pipe Line Shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
68 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,55 31-03
Authority
69 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,68 31-03
authority to shifting of utilities
70 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 51,55 31-03
72 Earthwork in Embankment 250 days Sun 19-05-19 Mon 17-02-20 32,71FS+20 days Embankment[1,918.9]
73 Earthwork in Subgrade 240 days Fri 20-09-19 Sun 17-05-20 35,72SS+100 days Subgrade[1,918.81]
74 Granular Sub Base 180 days Sun 29-12-19 Fri 26-06-20 73SS+100 days Granular Sub base[1,918.81]
75 DLC 120 days Tue 07-04-20 Sat 12-09-20 74SS+100 days Dry Lean Concrete[1,918.81]
76 Kerb Casting 110 days Thu 07-05-20 Sun 27-09-20 75SS+30 days Road Furniture Kerb[2,000]
77 PQC 100 days Thu 07-05-20 Sun 20-09-20 75SS+30 days Pavement Quality Concrete[1,918.81]
86 Pipe Culverts - 3 Nos 50 days Sun 12-05-19 Sun 16-06-19 37,71FS+10 days Finishing[3],Head Wall[3],Pipe Laying including bedding[3]
87 Slab/Box Culverts - 3 Nos 150 days Wed 03-04-19 Thu 05-09-19 36SS+5 days,71SS BC Finishing[3],BC Foundation[3],BC Substructure[3],BC Superstructure[3]
89 Foundation 35 days Sun 12-05-19 Thu 06-06-19 40,71FS+10 days VUP Foundation[1]
90 Sub Structure 36 days Sun 09-06-19 Fri 19-07-19 89FS+5 days VUP Substructure[1]
91 Super Structure 55 days Sat 03-08-19 Wed 16-10-19 90FS+5 days VUP Superstructure[1]
92 Finishing Works 54 days Wed 23-10-19 Mon 16-12-19 91FS+7 days VUP Finishing[1]
93 CH 356+188 Fly Over (1 X 36.85) 271 days Sun 12-05-19 Fri 28-02-20
95 Sub Structure 94 days Mon 24-06-19 Sun 03-11-19 94SS+60 days FOB Substructure[1]
96 Super Structure 72 days Fri 08-11-19 Sun 19-01-20 95FS+5 days FOB PSC Girder[1],FOB Superstructure[1]
97 Finishing Works 33 days Sun 26-01-20 Fri 28-02-20 96FS+7 days FOB Finishing[1]
98 CH 356+564 Fly Over (1 X 32.20) 271 days Sun 12-05-19 Fri 28-02-20
99 Foundation 100 days Sun 12-05-19 Tue 10-09-19 46SS,71FS+10 daysFOB Foundation[1]
100 Sub Structure 94 days Mon 24-06-19 Sun 03-11-19 99SS+60 days FOB Substructure[1]
101 Super Structure 72 days Fri 08-11-19 Sun 19-01-20 100FS+5 days FOB PSC Girder[1],FOB Superstructure[1]
102 Finishing Works 33 days Sun 26-01-20 Fri 28-02-20 101FS+7 days FOB Finishing[1]
103 Section - II (From 357+000 To 361+000) 640 days Sun 31-03-19 Wed 06-01-21
106 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
107 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,105 31-03
108 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,107 31-03
Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress
Page 2
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
109 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,108 31-03
110 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
111 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,105 31-03
112 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,111 31-03
113 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,112 31-03
114 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
115 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,105 31-03
Authority
116 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,115 31-03
authority to shifting of utilities
117 Water Utility Shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
118 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,105 31-03
Authority
119 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,118 31-03
authority to shifting of utilities
120 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 105 31-03
121 Clearing & Grubbing 60 days Sun 31-03-19 Sun 12-05-19 51,109,113,116,105,119,120
Cleaning & Grubbing[3,259.55]
122 Earthwork in Embankment 270 days Sun 14-04-19 Sat 18-01-20 32,121SS+20 days Embankment[3,259.55]
123 Earthwork in Subgrade 270 days Fri 20-09-19 Tue 16-06-20 122SS+150 days Subgrade[3,259.55]
124 Granular Sub Base 270 days Sat 09-11-19 Sat 12-09-20 123SS+50 days Granular Sub base[3,259.55]
125 DLC 240 days Wed 08-01-20 Mon 05-10-20 124SS+60 days Dry Lean Concrete[3,259.55]
126 Kerb Casting 240 days Sat 18-01-20 Tue 13-10-20 125SS+10 days Road Furniture Kerb[4,635]
127 PQC 270 days Fri 07-02-20 Sat 21-11-20 125SS+30 days Pavement Quality Concrete[3,259.55]
128 Median Filling 90 days Tue 16-06-20 Tue 13-10-20 126SS+150 days
130 Pipe Culverts - 4 Nos 60 days Sun 19-05-19 Mon 01-07-19 37,121FS+10 days Finishing[4],Head Wall[4],Pipe Laying including bedding[4]
131 Slab/Box Culverts - 4 Nos 150 days Sun 12-05-19 Wed 30-10-19 36SS+10 days,121 BC Finishing[4],BC Foundation[4],BC Substructure[4],BC Superstructure[4]
132 CH 357+326 CUP (1 X 12 x 3.50) 184 days Sun 12-05-19 Tue 03-12-19
133 Foundation 32 days Sun 12-05-19 Tue 04-06-19 38,121 PUP Foundation[1]
134 Sub Structure 32 days Sun 09-06-19 Thu 04-07-19 133FS+7 days PUP Substructure[1]
135 Super Structure 46 days Thu 25-07-19 Fri 04-10-19 134FS+7 days PUP Superstructure[1]
136 Finishing Works 50 days Mon 14-10-19 Tue 03-12-19 135FS+10 days PUP Finishing[1]
137 CH 357+975 CUP (1 X 12 x 3.5) 184 days Wed 10-04-19 Sat 19-10-19
138 Foundation 32 days Wed 10-04-19 Fri 03-05-19 38,121SS+10 days PUP Foundation[1]
139 Sub Structure 32 days Wed 08-05-19 Fri 31-05-19 138FS+7 days PUP Substructure[1]
140 Super Structure 46 days Tue 04-06-19 Sun 28-07-19 139FS+7 days PUP Superstructure[1]
141 Finishing Works 50 days Tue 27-08-19 Sat 19-10-19 140FS+10 days PUP Finishing[1]
142 CH 358+348 CUP (1 X 12 x 3.5) 181 days Tue 07-05-19 Fri 22-11-19
143 Foundation 32 days Tue 07-05-19 Wed 29-05-19 38,138FS+5 days PUP Foundation[1]
144 Sub Structure 32 days Mon 03-06-19 Wed 26-06-19 143FS+7 days PUP Substructure[1]
145 Super Structure 46 days Mon 01-07-19 Thu 26-09-19 144FS+7 days PUP Superstructure[1]
146 Finishing Works 50 days Thu 03-10-19 Fri 22-11-19 145FS+7 days PUP Finishing[1]
147 CH 358+975 VUP (1 X 12 x 5.5) 204 days Thu 02-05-19 Sun 08-12-19
148 Foundation 35 days Thu 02-05-19 Sun 26-05-19 40,121SS+10 days VUP Foundation[1]
149 Sub Structure 36 days Fri 31-05-19 Wed 26-06-19 148FS+7 days VUP Substructure[1]
150 Super Structure 55 days Mon 01-07-19 Sat 05-10-19 149FS+7 days VUP Superstructure[1]
151 Finishing Works 54 days Tue 15-10-19 Sun 08-12-19 150FS+10 days VUP Finishing[1]
152 CH 359+397 CUP (1 X 12 x 3.5) 184 days Wed 10-04-19 Sat 19-10-19
154 Sub Structure 32 days Wed 08-05-19 Fri 31-05-19 153FS+7 days PUP Substructure[1]
155 Super Structure 46 days Tue 04-06-19 Sun 28-07-19 154FS+7 days PUP Superstructure[1]
156 Finishing Works 50 days Tue 27-08-19 Sat 19-10-19 155FS+10 days PUP Finishing[1]
157 CH 359+810 MNB (1 X 32.250) 269 days Sun 21-04-19 Mon 27-01-20
159 Sub Structure 74 days Sun 16-06-19 Fri 04-10-19 158SS+80 days MNB Substructure[1]
160 Super Structure 70 days Fri 11-10-19 Fri 20-12-19 159FS+7 days MNB Superstructure[1]
161 Finishing Works 28 days Mon 30-12-19 Mon 27-01-20 160FS+10 days MNB Finishing[1]
162 CH 359+868 CUP (1 X 12 x 3.5) 184 days Sat 04-05-19 Fri 22-11-19
Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress
Page 3
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
163 Foundation 32 days Sat 04-05-19 Mon 27-05-19 38,153FS+2 days PUP Foundation[1]
164 Sub Structure 32 days Sat 01-06-19 Mon 24-06-19 163FS+7 days PUP Substructure[1]
165 Super Structure 46 days Fri 28-06-19 Mon 23-09-19 164FS+7 days PUP Superstructure[1]
166 Finishing Works 50 days Thu 03-10-19 Fri 22-11-19 165FS+10 days PUP Finishing[1]
167 CH 360+220 MJB (1 X 77.99m) (Single Span Steel Girder) 302 days Sun 31-03-19 Thu 30-01-20
168 Foundation 120 days Sun 31-03-19 Mon 24-06-19 43SS MJB Foundation[1]
169 Sub Structure 86 days Sun 02-06-19 Thu 26-09-19 168SS+90 days MJB Substructure[1]
170 Steel Girder Erection 90 days Thu 10-10-19 Wed 08-01-20 169FS+14 days MJB PSC Girder[1]
171 Super Structure 74 days Sun 06-10-19 Thu 19-12-19 169FS+10 days MJB Superstructure[1]
172 Finishing Works 28 days Thu 02-01-20 Thu 30-01-20 171FS+14 days MJB Finishing[1]
173 CH 361+034 ROB (1201.487m) 610 days Sun 21-04-19 Wed 06-01-21
174 Foundation 320 days Sun 21-04-19 Wed 18-03-20 44SS+30 days,51FS+15
ROBdays
Foundation[1]
175 Sub Structure 350 days Sun 02-06-19 Tue 16-06-20 174SS+60 days ROB Substructure[1]
176 PSC Girder 230 days Sat 28-03-20 Sat 28-11-20 175SS+270 days ROB PSC Girder[0.5]
177 Steel Girder Erection 60 days Tue 23-06-20 Fri 25-09-20 45FS+1 day,175FS+7
ROB
days
PSC Girder[0.5]
178 Super Structure 143 days Fri 07-08-20 Mon 14-12-20 176SS+30 days,177SS+20
ROB Superstructure[1]
days
179 Finishing Works 140 days Sun 20-09-20 Wed 06-01-21 178SS+33 days ROB Finishing[1]
180 Section - III (From 361+000 To 366+000) 630 days Sun 31-03-19 Tue 29-12-20
183 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
184 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,182 31-03
185 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,184 31-03
186 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,185 31-03
187 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
188 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,182 31-03
189 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,188 31-03
190 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,189 31-03
191 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
192 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,182 31-03
Authority
193 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,192 31-03
authority to shifting of utilities
194 Water Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
195 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,182 31-03
Authority
196 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,195 31-03
authority to shifting of utilities
197 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 182 31-03
198 Clearing & Grubbing 60 days Sun 31-03-19 Sun 12-05-19 51,186,190,193,196,182,197
Cleaning & Grubbing[3,840.53]
199 Earthwork in Embankment 300 days Sun 14-04-19 Mon 17-02-20 32,198SS+20 days Embankment[3,840.53]
200 Earthwork in Subgrade 280 days Tue 19-11-19 Sun 27-09-20 199SS+210 days Subgrade[3,840.53]
201 Granular Sub Base 250 days Sat 18-01-20 Wed 21-10-20 200SS+60 days Granular Sub base[3,840.53]
202 DLC 210 days Fri 17-04-20 Sat 28-11-20 201SS+90 days Dry Lean Concrete[3,840.53]
203 Kerb Casting 80 days Fri 17-07-20 Wed 21-10-20 202SS+80 days Road Furniture Kerb[4,397]
204 PQC 210 days Wed 27-05-20 Tue 29-12-20 202SS+40 days Pavement Quality Concrete[3,840.53]
205 Median Filling 30 days Mon 05-10-20 Wed 28-10-20 203SS+60 days
213 Pipe Culverts - 5 Nos 90 days Thu 02-05-19 Tue 16-07-19 37,198SS+30 days Finishing[5],Head Wall[5],Pipe Laying including bedding[5]
214 Slab/Box Culverts - 5 Nos 200 days Wed 10-04-19 Mon 04-11-19 36SS+15 days BC Finishing[5],BC Foundation[5],BC Substructure[5],BC Superstructure[5]
215 CH 362+160 CUP (1 X 12 x 3.5) 184 days Sat 01-06-19 Tue 31-12-19
216 Foundation 32 days Sat 01-06-19 Mon 24-06-19 38,163FS+7 days PUP Foundation[1]
Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress
Page 4
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
217 Sub Structure 32 days Fri 28-06-19 Mon 09-09-19 216FS+7 days PUP Substructure[1]
218 Super Structure 46 days Mon 16-09-19 Fri 01-11-19 217FS+7 days PUP Superstructure[1]
219 Finishing Works 50 days Mon 11-11-19 Tue 31-12-19 218FS+10 days PUP Finishing[1]
220 CH 362+350 MJB (142.50m) 427 days Fri 30-08-19 Wed 18-11-20
221 Foundation 130 days Fri 30-08-19 Wed 08-01-20 43,198SS+50 days MJB Foundation[1]
222 Sub Structure 110 days Wed 15-01-20 Mon 04-05-20 221FS+7 days MJB Substructure[1]
223 Super Structure 103 days Mon 11-05-20 Fri 25-09-20 222FS+7 days MJB PSC Girder[1],MJB Superstructure[1]
224 Finishing Works 60 days Sat 03-10-20 Wed 18-11-20 223FS+10 days MJB Finishing[1]
225 CH 362+682 CUP (1 X 12 x 3.5) 184 days Tue 25-06-19 Mon 03-02-20
226 Foundation 32 days Tue 25-06-19 Wed 04-09-19 38,216FS+2 days PUP Foundation[1]
227 Sub Structure 32 days Wed 11-09-19 Sun 13-10-19 226FS+7 days PUP Substructure[1]
228 Super Structure 46 days Sun 20-10-19 Thu 05-12-19 227FS+7 days PUP Superstructure[1]
229 Finishing Works 50 days Sun 15-12-19 Mon 03-02-20 228FS+10 days PUP Finishing[1]
230 CH 363+273 LVUP (1 X 12 X3.5) 184 days Sun 12-05-19 Tue 03-12-19
231 Foundation 32 days Sun 12-05-19 Tue 04-06-19 39,198SS+60 days VUP Foundation[1]
232 Sub Structure 32 days Sun 09-06-19 Thu 04-07-19 231FS+7 days VUP Substructure[1]
233 Super Structure 46 days Thu 25-07-19 Fri 04-10-19 232FS+7 days VUP Superstructure[1]
234 Finishing Works 50 days Mon 14-10-19 Tue 03-12-19 233FS+10 days VUP Finishing[1]
235 CH 363+850 FLY OVER (151m) 398 days Mon 24-06-19 Sun 04-10-20
236 Foundation 137 days Mon 24-06-19 Mon 16-12-19 46,198FS+40 days FOB Foundation[1]
237 Sub Structure 121 days Fri 18-10-19 Sun 16-02-20 233SS+60 days FOB Substructure[1]
238 Super Structure 119 days Wed 26-02-20 Wed 24-06-20 237FS+10 days FOB PSC Girder[1],FOB Superstructure[1]
239 Finishing Works 60 days Sat 11-07-20 Sun 04-10-20 238FS+10 days FOB Finishing[1]
240 CH 364+274 CUP (1 x 12 x3.5) 184 days Fri 06-09-19 Sun 08-03-20
241 Foundation 32 days Fri 06-09-19 Tue 08-10-19 38,226FS+2 days PUP Foundation[1]
242 Sub Structure 32 days Tue 15-10-19 Sat 16-11-19 241FS+7 days PUP Substructure[1]
243 Super Structure 46 days Sat 23-11-19 Wed 08-01-20 242FS+7 days PUP Superstructure[1]
244 Finishing Works 50 days Sat 18-01-20 Sun 08-03-20 243FS+10 days PUP Finishing[1]
245 CH 364+650 MNB (85.936m) 422 days Sun 12-05-19 Sun 06-09-20
246 Foundation 158 days Sun 12-05-19 Thu 07-11-19 42SS,198 MNB Foundation[1]
247 Sub Structure 82 days Sun 17-11-19 Fri 07-02-20 246FS+10 days MNB Substructure[1]
248 Super Structure 97 days Mon 17-02-20 Sun 24-05-20 247FS+10 days MNB Superstructure[1]
249 Finishing Works 50 days Mon 08-06-20 Sun 06-09-20 248FS+15 days MNB Finishing[1]
250 CH 365+165 CUP (1 X 12 x 3.5) 184 days Thu 10-10-19 Sat 11-04-20
251 Foundation 32 days Thu 10-10-19 Mon 11-11-19 38,241FS+2 days PUP Foundation[1]
252 Sub Structure 32 days Mon 18-11-19 Fri 20-12-19 251FS+7 days PUP Substructure[1]
253 Super Structure 46 days Fri 27-12-19 Tue 11-02-20 252FS+7 days PUP Superstructure[1]
254 Finishing Works 50 days Fri 21-02-20 Sat 11-04-20 253FS+10 days PUP Finishing[1]
255 CH 365+976 MJB (1 X 111.65) 444 days Sun 21-04-19 Fri 28-08-20
256 Foundation 130 days Sun 21-04-19 Tue 10-09-19 43SS+30 days,198SS+30
MJB Foundation[1]
days
257 Sub Structure 110 days Tue 17-09-19 Sun 05-01-20 256FS+7 days MJB Substructure[1]
258 Super Structure 130 days Sun 12-01-20 Thu 21-05-20 257FS+7 days MJB PSC Girder[1],MJB Superstructure[1]
259 Finishing Works 50 days Sun 31-05-20 Fri 28-08-20 258FS+10 days MJB Finishing[1]
260 Section - IV (From 366+000 To 371+000) 575 days Sun 31-03-19 Tue 17-11-20
263 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
264 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,262 31-03
265 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,264 31-03
266 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,265 31-03
267 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
268 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,262 31-03
269 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,268 31-03
270 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,269 31-03
271 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
272 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,262 31-03
Authority
273 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,272 31-03
authority to shifting of utilities
274 Water Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress
Page 5
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
275 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,262 31-03
Authority
276 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,275 31-03
authority to shifting of utilities
277 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 262 31-03
278 Clearing & Grubbing 20 days Sun 31-03-19 Sun 14-04-19 51,266,270,273,276,277
Cleaning & Grubbing[4,823.45]
280 Earthwork in Embankment 380 days Sun 14-04-19 Thu 07-05-20 32,278 Embankment[4,823.45]
281 Earthwork in Subgrade 250 days Mon 09-12-19 Sun 20-09-20 280SS+230 days Subgrade[4,823.45]
282 Granular Sub Base 150 days Wed 08-01-20 Sat 06-06-20 281SS+30 days Granular Sub base[4,823.45]
283 DLC 130 days Fri 07-02-20 Tue 16-06-20 282SS+30 days Dry Lean Concrete[4,823.45]
284 Kerb Casting 150 days Mon 17-02-20 Sun 16-08-20 283SS+10 days Road Furniture Kerb[4,968]
285 PQC 150 days Sun 08-03-20 Sat 12-09-20 283SS+30 days Pavement Quality Concrete[4,823.45]
286 Median Filling 50 days Fri 17-04-20 Sat 06-06-20 284SS+60 days
294 Pipe Culverts - 4 Nos 100 days Sun 05-05-19 Fri 30-08-19 37,278FS+30 days Finishing[4],Head Wall[4],Pipe Laying including bedding[4]
295 Slab/Box Culverts - 9 Nos 180 days Thu 02-05-19 Thu 14-11-19 36,278 BC Finishing[9],BC Foundation[9],BC Substructure[9],BC Superstructure[9]
296 CH 367+012 CUP (1 X 12 X 3.50) 184 days Wed 17-04-19 Tue 29-10-19
297 Foundation 32 days Wed 17-04-19 Fri 10-05-19 38,278FS+5 days PUP Foundation[1]
298 Sub Structure 32 days Wed 15-05-19 Fri 07-06-19 297FS+7 days PUP Substructure[1]
299 Super Structure 46 days Wed 12-06-19 Tue 27-08-19 298FS+7 days PUP Superstructure[1]
300 Finishing Works 50 days Mon 09-09-19 Tue 29-10-19 299FS+10 days PUP Finishing[1]
301 CH 367+220 MNB GAS (1 X 21.941) 210 days Sun 16-06-19 Mon 17-02-20
302 Foundation 35 days Sun 16-06-19 Thu 15-08-19 42SS+45 days,278FS+90
MNB days
Foundation[1]
303 Sub Structure 36 days Thu 05-09-19 Fri 11-10-19 302FS+10 days MNB Substructure[1]
304 Super Structure 55 days Mon 21-10-19 Sun 15-12-19 303FS+10 days MNB Superstructure[1]
305 Finishing Works 54 days Wed 25-12-19 Mon 17-02-20 304FS+10 days MNB Finishing[1]
306 CH 367+590 CUP (1 X 12 x 3.5) 184 days Tue 14-05-19 Thu 05-12-19
307 Foundation 32 days Tue 14-05-19 Wed 05-06-19 38,297FS+5 days PUP Foundation[1]
308 Sub Structure 32 days Mon 10-06-19 Wed 10-07-19 307FS+7 days PUP Substructure[1]
309 Super Structure 46 days Wed 31-07-19 Sun 06-10-19 308FS+7 days PUP Superstructure[1]
310 Finishing Works 50 days Wed 16-10-19 Thu 05-12-19 309FS+10 days PUP Finishing[1]
311 CH 368+014 FLY OVER (1 X 65m) 248 days Mon 16-12-19 Thu 24-09-20
312 Foundation 100 days Mon 16-12-19 Wed 25-03-20 46,236,278SS+90 days
FOB Foundation[1]
313 Sub Structure 94 days Tue 04-02-20 Fri 08-05-20 312SS+50 days FOB Substructure[1]
314 Super Structure 50 days Fri 15-05-20 Sat 11-07-20 313FS+7 days FOB PSC Girder[1],FOB Superstructure[1]
315 Finishing Works 33 days Sat 22-08-20 Thu 24-09-20 314FS+14 days FOB Finishing[1]
316 CH 369+130 LVUP (1 X 12 X 3.5) 188 days Thu 02-05-19 Fri 22-11-19
317 Foundation 32 days Thu 02-05-19 Fri 24-05-19 39,278SS+45 days VUP Foundation[1]
318 Sub Structure 32 days Wed 29-05-19 Fri 21-06-19 317FS+7 days VUP Substructure[1]
319 Super Structure 46 days Wed 26-06-19 Thu 19-09-19 318FS+7 days VUP Superstructure[1]
320 Finishing Works 50 days Thu 03-10-19 Fri 22-11-19 319FS+14 days VUP Finishing[1]
321 CH 370+024 VUP (1 X 12 X 5.50) 208 days Thu 02-05-19 Thu 12-12-19
322 Foundation 35 days Thu 02-05-19 Sun 26-05-19 40,278SS+45 days VUP Foundation[1]
323 Sub Structure 36 days Fri 31-05-19 Wed 26-06-19 322FS+7 days VUP Substructure[1]
324 Super Structure 55 days Mon 01-07-19 Sat 05-10-19 323FS+7 days VUP Superstructure[1]
325 Finishing Works 54 days Sat 19-10-19 Thu 12-12-19 324FS+14 days VUP Finishing[1]
326 CH 370+580 MNB (1 X 17.03m) 230 days Thu 15-08-19 Sun 12-04-20
328 Sub Structure 52 days Wed 25-09-19 Sat 16-11-19 327SS+30 days MNB Substructure[1]
329 Super Structure 72 days Sat 23-11-19 Mon 03-02-20 328FS+7 days MNB Superstructure[1]
Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress
Page 6
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
330 Finishing Works 55 days Mon 17-02-20 Sun 12-04-20 329FS+14 days MNB Finishing[1]
331 Section - V (From 371+000 To 374+500) 631 days Sun 31-03-19 Wed 30-12-20
343 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,333 31-03
Authority
344 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,343 31-03
authority to shifting of utilities
345 Water Pipe Line Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
346 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,333 31-03
Authority
347 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,346 31-03
authority to shifting of utilities
348 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 333 31-03
349 Clearing & Grubbing 40 days Sun 31-03-19 Sun 28-04-19 51,348,333,337,341,344,347
Cleaning & Grubbing[2,615.5]
350 Earthwork in Embankment 450 days Sun 14-04-19 Sun 16-08-20 32,349SS+20 days Embankment[2,615.5]
351 Earthwork in Subgrade 180 days Mon 17-02-20 Sun 20-09-20 350SS+300 days Subgrade[2,615.5]
352 Granular Sub Base 150 days Tue 07-04-20 Mon 05-10-20 351SS+50 days Granular Sub base[2,615.5]
353 DLC 150 days Thu 07-05-20 Wed 28-10-20 352SS+30 days Dry Lean Concrete[2,615.5]
354 Kerb Casting 90 days Sun 17-05-20 Sun 20-09-20 353SS+10 days Road Furniture Kerb[3,500]
355 PQC 150 days Wed 27-05-20 Fri 13-11-20 353SS+20 days Pavement Quality Concrete[2,615.5]
356 Median Filling 50 days Fri 17-07-20 Sun 27-09-20 354SS+50 days
364 Slab/Box Culverts - 12 Nos 220 days Sun 05-05-19 Sun 29-12-19 36,349FS+10 days BC Finishing[12],BC Foundation[12],BC Substructure[12],BC Superstructure[12]
365 CH 371+720 FLY OVER (1 X 36.90m) 465 days Wed 31-07-19 Thu 10-12-20
366 Foundation 137 days Wed 31-07-19 Sun 05-01-20 46,349FS+100 daysFOB Foundation[1]
367 Sub Structure 121 days Wed 15-01-20 Fri 15-05-20 366FS+10 days FOB Substructure[1]
368 Super Structure 119 days Mon 25-05-20 Sun 18-10-20 367FS+10 days FOB PSC Girder[1],FOB Superstructure[1]
369 Finishing Works 54 days Thu 29-10-20 Thu 10-12-20 368FS+14 days FOB Finishing[1]
370 CH 372+028 MNB (1 X 52.826m) 324 days Thu 10-10-19 Wed 30-09-20
371 Foundation 65 days Thu 10-10-19 Sat 14-12-19 41,349FS+150 daysMNB Foundation[1]
372 Sub Structure 78 days Tue 24-12-19 Wed 11-03-20 371FS+10 days MNB Substructure[1]
373 Super Structure 92 days Sat 21-03-20 Sun 21-06-20 372FS+10 days MNB Superstructure[1]
374 Finishing Works 55 days Tue 14-07-20 Wed 30-09-20 373FS+14 days MNB Finishing[1]
375 CH 373+608 ROB (1 X 186.015m) 560 days Sun 12-05-19 Tue 22-12-20
376 Foundation 130 days Sun 12-05-19 Thu 10-10-19 44,349SS+20 days ROB Foundation[1]
377 Sub Structure 150 days Sun 02-06-19 Fri 29-11-19 376SS+30 days ROB Substructure[1]
378 Launching of Girder 150 days Tue 28-01-20 Fri 26-06-20 377FS+60 days ROB PSC Girder[1]
379 Super Structure 100 days Fri 17-07-20 Thu 05-11-20 378FS+10 days ROB Superstructure[1]
380 Finishing Works 50 days Fri 13-11-20 Tue 22-12-20 379FS+10 days ROB Finishing[1]
381 CH 373+905 MNB GAS (1 X 70.590) 378 days Mon 24-06-19 Fri 18-09-20
382 Foundation 154 days Mon 24-06-19 Thu 02-01-20 42,349FS+60 days MNB Foundation[1]
383 Sub Structure 74 days Sun 12-01-20 Thu 26-03-20 382FS+10 days MNB Substructure[1]
384 Super Structure 62 days Thu 09-04-20 Wed 10-06-20 383FS+14 days MNB Superstructure[1]
385 Finishing Works 50 days Wed 24-06-20 Fri 18-09-20 384FS+14 days MNB Finishing[1]
386 CH 374+355 IC MAIN STRUCTURE (1 X 130.876m) 505 days Mon 24-06-19 Fri 25-12-20
387 Foundation 125 days Mon 24-06-19 Wed 04-12-19 47,349FS+80 days FOB Foundation[1]
388 Sub Structure 120 days Sat 14-12-19 Sun 12-04-20 387FS+10 days FOB Substructure[1]
Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress
Page 7
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
389 Super Structure 170 days Wed 22-04-20 Sun 01-11-20 388FS+10 days FOB PSC Girder[1],FOB Superstructure[1]
390 Finishing Works 60 days Mon 09-11-20 Fri 25-12-20 389FS+10 days FOB Finishing[1]
391 CH 374+355 IC VUP RAMP-01 205 days Wed 31-07-19 Fri 13-03-20
393 Sub Structure 36 days Wed 02-10-19 Thu 07-11-19 392FS+7 days
394 Super Structure 55 days Thu 14-11-19 Wed 08-01-20 393FS+7 days
395 Finishing Works 55 days Sat 18-01-20 Fri 13-03-20 394FS+10 days
396 CH 374+720 IC VUP RAMP-02 216 days Sat 05-10-19 Fri 08-05-20
398 Sub Structure 36 days Tue 19-11-19 Wed 25-12-19 397FS+10 days
399 Super Structure 55 days Sat 04-01-20 Fri 28-02-20 398FS+10 days
400 Finishing Works 55 days Sat 14-03-20 Fri 08-05-20 399FS+15 days
401 Toll Plaza - Loop-01 170 days Fri 29-11-19 Sun 17-05-20
404 Toll Booth 50 days Tue 28-01-20 Wed 18-03-20 403SS+50 days
406 Lighting & Finishing Works 60 days Thu 27-02-20 Mon 27-04-20 404SS+30 days
407 Toll Plaza - Loop-02 250 days Fri 29-11-19 Sat 12-09-20
409 PQC 180 days Mon 09-12-19 Sat 06-06-20 408SS+10 days
410 Toll Booth 50 days Tue 28-01-20 Wed 18-03-20 409SS+50 days
412 Lighting & Finishing Works 60 days Wed 08-01-20 Sun 08-03-20 409SS+30 days
413 Toll Plaza -Ramp-01 200 days Sat 18-01-20 Sat 12-09-20
415 PQC 180 days Tue 28-01-20 Fri 04-09-20 414SS+10 days
416 Toll Booth 50 days Wed 18-03-20 Thu 07-05-20 415SS+50 days
418 Lighting & Finishing Works 60 days Sat 06-06-20 Sat 12-09-20 417SS+30 days
419 Toll Plaza - Ramp-02 200 days Sun 08-03-20 Wed 21-10-20
421 PQC 180 days Wed 18-03-20 Tue 13-10-20 420SS+10 days
422 Toll Booth 50 days Thu 07-05-20 Fri 26-06-20 421SS+50 days
424 Lighting & Finishing Works 60 days Fri 04-09-20 Wed 21-10-20 423SS+30 days
425 Section - VI (From 374+500 To 377+000) 591 days Sun 31-03-19 Sun 29-11-20
428 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
429 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,427 31-03
430 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,429 31-03
431 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,430 31-03
432 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
433 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,427 31-03
434 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,433 31-03
435 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,434 31-03
436 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
437 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,427 31-03
Authority
438 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,437 31-03
authority to shifting of utilities
439 Water Pipe Line Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
440 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,427 31-03
Authority
441 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,440 31-03
authority to shifting of utilities
442 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 427 31-03
Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress
Page 8
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
443 Clearing & Grubbing 90 days Sun 31-03-19 Sun 02-06-19 51,442,427,431,435,438,441
Cleaning & Grubbing[2,136.16]
444 Earthwork in Excavation 30 days Wed 03-04-19 Thu 25-04-19 443SS+5 days
445 Earthwork in Embankment 400 days Thu 02-05-19 Sun 21-06-20 443SS+45 days,444SS
Embankment[2,136.16]
446 Earthwork in Subgrade 120 days Fri 13-03-20 Sat 01-08-20 32,445SS+300 daysSubgrade[2,136.16]
447 Granular Sub Base 120 days Sat 02-05-20 Thu 01-10-20 446SS+50 days Granular Sub base[2,136.16]
448 DLC 120 days Mon 01-06-20 Sat 24-10-20 447SS+30 days Dry Lean Concrete[2,136.16]
449 Kerb Casting 60 days Tue 16-06-20 Sun 20-09-20 448SS+15 days Road Furniture Kerb[2,500]
450 PQC 120 days Sun 21-06-20 Mon 09-11-20 448SS+20 days Pavement Quality Concrete[2,136.16]
451 Median Filling 30 days Fri 04-09-20 Sun 27-09-20 449SS+40 days
459 Box Culverts - 6 Nos 200 days Sun 09-06-19 Tue 28-01-20 36,443SS+100 daysBC Finishing[6],BC Foundation[6],BC Substructure[6],BC Superstructure[6]
460 CH 375+588 VUP (1 X 12 X 5.5) 199 days Fri 29-11-19 Mon 15-06-20
461 Foundation 35 days Fri 29-11-19 Fri 03-01-20 40,443FS+150 daysVUP Foundation[1]
462 Sub Structure 36 days Wed 08-01-20 Thu 13-02-20 461FS+5 days VUP Substructure[1]
463 Super Structure 55 days Thu 20-02-20 Wed 15-04-20 462FS+7 days VUP Superstructure[1]
464 Finishing Works 54 days Wed 22-04-20 Mon 15-06-20 463FS+7 days VUP Finishing[1]
465 CH 376+867 MNB (1 X 54.45m) 202 days Fri 29-11-19 Thu 18-06-20
466 Foundation 35 days Fri 29-11-19 Fri 03-01-20 41,443FS+150 daysMNB Foundation[1]
467 Sub Structure 36 days Wed 08-01-20 Thu 13-02-20 466FS+5 days MNB Substructure[1]
468 Super Structure 55 days Thu 20-02-20 Wed 15-04-20 467FS+7 days MNB Superstructure[1]
469 Finishing Works 54 days Sat 25-04-20 Thu 18-06-20 468FS+10 days MNB Finishing[1]
470 Toll Plaza (MEW) 401 days Thu 10-10-19 Sun 29-11-20
471 Administration & Office Block 180 days Fri 29-11-19 Wed 27-05-20 443FS+150 days Toll Plaza Building[1]
472 Tunnel 180 days Fri 29-11-19 Wed 27-05-20 471SS Toll Plaza Tunnel[1]
473 Earthwork 90 days Thu 10-10-19 Wed 08-01-20 443FS+100 days Toll Plaza Earthwork[1]
474 GSB 90 days Thu 09-01-20 Wed 08-04-20 473FS+1 day Toll Plaza SubBase[1]
475 DLC 90 days Sat 08-02-20 Fri 08-05-20 474SS+30 days Toll Plaza DLC[1]
476 PQC 120 days Wed 08-04-20 Sun 13-09-20 475SS+60 days Toll Plaza PQC[1]
477 Toll Booth 60 days Thu 28-05-20 Sat 05-09-20 476SS+50 days Toll Plaza Booths[1]
478 Canopy 60 days Thu 28-05-20 Sat 05-09-20 477SS Toll Plaza Space Frame[1]
479 Toll Singages 60 days Sun 07-06-20 Sun 13-09-20 476SS+60 days Toll Singages[1]
480 Traffic & Mediacl Air Post 100 days Sun 13-09-20 Sun 29-11-20 476 Traffic & Mediacl Air Post[1]
481 Lighting & Finishing Works 90 days Thu 28-05-20 Mon 28-09-20 477SS Toll Plaza Electrical - Procurement & Installation[1]
482 Section - VII (From 377+000 To 378+740) 520 days Sun 31-03-19 Mon 05-10-20
485 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
486 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,484 31-03
487 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,486 31-03
488 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,487 31-03
489 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
490 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,484 31-03
491 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,490 31-03
492 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,491 31-03
493 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
494 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,484 31-03
Authority
495 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,494 31-03
authority to shifting of utilities
496 Water Pipe Line Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03
Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress
Page 9
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
497 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,484 31-03
Authority
498 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,497 31-03
authority to shifting of utilities
499 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 484 31-03
500 Clearing & Grubbing 120 days Sun 31-03-19 Mon 24-06-19 51,484,488,492,495,498
Cleaning & Grubbing[1,536.91]
502 Earthwork in Embankment 350 days Sun 21-04-19 Fri 17-04-20 32,500SS+30 days Embankment[1,536.91]
503 Earthwork in Subgrade 180 days Tue 19-11-19 Sun 17-05-20 502SS+200 days Subgrade[1,536.91]
504 Granular Sub Base 120 days Fri 07-02-20 Sat 06-06-20 503SS+80 days Granular Sub base[1,536.91]
505 DLC 100 days Sat 28-03-20 Fri 17-07-20 504SS+50 days Dry Lean Concrete[1,536.91]
506 Kerb Casting 90 days Fri 17-04-20 Sun 16-08-20 505SS+20 days Road Furniture Kerb[1,740]
507 PQC 120 days Thu 07-05-20 Mon 05-10-20 506SS+20 days Pavement Quality Concrete[1,536.91]
508 Median Filling 50 days Sat 06-06-20 Fri 04-09-20 506SS+50 days
538 Longitudinal Drain 220 days Fri 26-06-20 Fri 29-01-21 51FS+450 days Longitudinal Drain[20,130.91]
539 Median Drain 150 days Wed 28-10-20 Sun 28-02-21 51FS+450 days,538FF+30
Media days
Drain[20,130.91]
540 Ravine Area Treatment 270 days Fri 26-06-20 Sat 20-03-21 51FS+450 days Ravine Area Treatment[20,130.91]
541 Slope Protection 150 days Fri 13-11-20 Sat 20-03-21 51FS+400 days,540FF
Drainage - Slope Protection[20,130.91]
542 RE Wall (From 355+000 To 378+740) 310 days Thu 27-02-20 Wed 06-01-21
543 RE Wall Casting 250 days Thu 27-02-20 Sat 21-11-20 51FS+330 days RE Wall Panel Casting[20,130.91]
544 RE Wall Erection 250 days Sat 28-03-20 Mon 14-12-20 51FS+360 days,543FF+30
RE Walldays
Panel Erection[20,130.91]
545 Toe Wall/R Wall 150 days Sat 12-09-20 Wed 06-01-21 51FS+420 days,544FF+30
Toe Wall/Rwall[20,130.91]
days
546 Project Facilities (From 355+000 To 378+740) 510 days Wed 30-10-19 Sat 20-03-21
547 Road Side Furniture 330 days Thu 27-02-20 Fri 22-01-21 32,51SS+330 days,49
548 Signages 210 days Fri 04-09-20 Thu 18-02-21 51FS+480 days Road Furniture Signages[23,740]
549 Road Marking 210 days Mon 31-08-20 Sat 13-02-21 51FS+210 days,77SS+30
Road days,127SS+30
Furniture Road days,204SS+30
Markings[23,740]
days,355SS+30 days,450SS+30 days,285SS+30 days
550 Boundary Wall 180 days Wed 27-05-20 Sun 06-12-20 51FS+420 days Road Furniture Boundary Wall[23,740]
551 Irrigation 280 days Wed 27-05-20 Sun 28-02-21 51FS+420 days Road Furniture Irrigation[23,740]
552 Street Lighting 360 days Wed 30-10-19 Fri 13-11-20 32,51FS+210 days Road Furniture street lightning procurement & installation[23,740]
553 Chain Link Fencing 360 days Wed 30-10-19 Fri 13-11-20 32,51FS+210 days Road Furniture ChainLink Fencing[23,740]
554 Lanscaping and Tree plantation 180 days Tue 13-10-20 Wed 10-03-21 32,51FS+450 days,78SS+10
Road Furniture
days,128SS+10
Plantation[23,740]
days,205SS+10 days,356SS+10 days,451SS+10 days
555 Noise Barrier 510 days Wed 30-10-19 Sat 20-03-21 32,51FS+210 days Road Furniture Noise Barrier Installation[23,740]
556 Metal Beam Crash Barrier 480 days Sat 02-11-19 Sun 21-02-21 32,51FS+213 days Road Furniture Metalbeam procurement & instalation[23,740]
557 Telecom System 210 days Fri 26-06-20 Fri 22-01-21 32,51FS+450 days ATMS[1]
559 Schedule I Test on Completion 30 days Sat 21-11-20 Mon 14-12-20 178FF,508,507,510,511,516,521,526,531,536
560 Issue of Provisional Completion Cerfificate 1 day Sun 13-12-20 Mon 14-12-20 559FF,52,77
561 Completion of Punch List Items as per schedule 90 days Fri 25-12-20 Mon 15-03-21 560FS+15 days,86,87,92,97,102,130,131,136,141,146,151,156,161,166,172,213,214,219,224,229,234,239,244,249,254,259
562 Submission of As-built drawings 60 days Fri 25-12-20 Sat 13-02-21 561SS,294,295,300,305,310,325,330,369,374,380,385,390,395,400,457,459,464,469
563 Issue of Completion Certificate 0 days Tue 30-03-21 Tue 30-03-21 561FS+15 days,541,547,548,549,550,551,552,553,554,555,556,557,559,560,562,538,539,540,543,544,545,507,508,481,479,480,450,451,84,127,128,179,204,205,211,292,315,320,355,356,362,364,406,405,411,412,417,418,423,424,53,103,180,260,331,425,482,537,542,546 30-03