ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter

Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
1 Vadodara Mumbai Expresway Project (Package - I) 1106 days Tue 20-03-18 Tue 30-03-21

2 Pre Construction Works (Development Period) 217 days Tue 20-03-18 Mon 22-10-18

3 Award of the project by Goverment to the Concessionaire 0 days Tue 20-03-18 Tue 20-03-18 20-03

4 LOI issued by IRB to L&T TIIC 0 days Tue 17-04-18 Tue 17-04-18 17-04

5 Signing of CA (between VK1 & NHAI) 0 days Wed 09-05-18 Wed 09-05-18 09-05

6 Signing of EPC Aggrement (between MRMPL & L&T TIIC) 0 days Mon 25-06-18 Mon 25-06-18 25-06

7 Signing of Supplementary Aggrement (Among VK1, IRB, MRM & L&T)0 days Wed 27-06-18 Wed 27-06-18 27-06

8 Appointment of IE 0 days Sat 07-07-18 Sat 07-07-18 5FS+60 days 07-07

9 Appointment of Design Consultants by Contractor 1 day Mon 22-10-18 Mon 22-10-18 Appointment of Design Consultant[1]

10 Concessionaire Obligations 90 days Sun 31-03-19 Sun 02-06-19

11 Conditions precedents - Authority 90 days Sun 31-03-19 Sun 02-06-19

12 Handing over of 80% encumberance free land including Utility 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
Shifting and Tree cutting for Phase 1
13 Handing over of 80% encumberance free land including Utility 90 days Sun 31-03-19 Sun 02-06-19 12
Shifting and Tree cutting for Phase 2
14 Dismantling of Structures 90 days Sun 31-03-19 Sun 02-06-19 12

15 Water Pipe Line Shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

16 ROB GAD approval from Railways 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

17 All Applicable permits relating to Environmental protection & 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
Conservation of the site
18 Conditions precedents-Contractor 0 days Sun 31-03-19 Sun 31-03-19 31-03

19 Permission of the State Government for Extraction of boulders 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
from quarries for and in respect of at least 20% (twenty percent)
of the total length of the Project.
20 Permission from village Panchayat for installation of Crusher 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
Plant.
21 Clearance of Pollution control board for setting up Crusher 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
plant.
22 License for use of Explosives. 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

23 Permission of the State Government for Drawing Water from 0 days Sun 31-03-19 Sun 31-03-19 51 31-03
River / Reservoir
24 Contractor Obligation 74 days Wed 16-01-19 Sun 31-03-19

25 Performance Bank Gurantee 0 days Wed 16-01-19 Wed 16-01-19 16-01

26 Insurance 0 days Wed 16-01-19 Wed 16-01-19 16-01

27 Identification of land, for camps, Quarries, & Plant establishment 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

28 Mobilization of Staff 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

29 Mobilization of plant & Equipments 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

30 Labour License 0 days Wed 16-01-19 Wed 16-01-19 16-01

31 GFC to be approved by MRMPL 180 days Sun 31-03-19 Mon 30-09-19

32 GFC for Plan and Profile 15 days Sun 31-03-19 Wed 10-04-19 51 Horizontal alignment design[23,740],Vertical alignment design[23,740]

33 Appointment of Topo survey agecny 1 day Sun 31-03-19 Sun 31-03-19 51 Appointment of Topo survey agecny[1]

34 Appointment of Geotechnical Investigation Agency 1 day Sun 31-03-19 Sun 31-03-19 51 Appointment of Geotechnical Investigation Agency[1]

35 Approval of Pavement Design 15 days Mon 01-04-19 Thu 11-04-19 51,33,34 Pavement Design[1]

36 GFC of Box Culvert 45 days Sun 31-03-19 Thu 02-05-19 51 BC Design[47]

37 GFC of Pipe Utility Structures 45 days Sun 31-03-19 Thu 02-05-19 51 PC Design[18]

38 GFC of PUP/CUP 15 days Sun 31-03-19 Wed 10-04-19 51 VUP/PUP/CUP Design[11]

39 GFC of LVUP 15 days Sun 31-03-19 Wed 10-04-19 51 VUP/PUP/CUP Design[2]

40 GFC of VUP 45 days Sun 31-03-19 Thu 02-05-19 51 VUP/PUP/CUP Design[5]

41 GFC of Minor Bridge 120 days Sun 31-03-19 Mon 24-06-19 51 Minor Bridge Design[4]

42 GFC of Minor Bridge - Gas /Oil/Water Pipe line 120 days Sun 31-03-19 Mon 24-06-19 51 Minor Bridge Design[4]

43 GFC of Major Bridge 150 days Sun 31-03-19 Fri 30-08-19 51 Major Bridge Design[3]

44 GFC of ROB 60 days Sun 31-03-19 Sun 12-05-19 51 ROB Design[2]

45 Launching Scheme approval of ROB 30 days Sun 31-03-19 Sun 21-04-19 51

46 GFC of Flyover 120 days Sun 31-03-19 Mon 24-06-19 51 FOB Design[6]

47 GFC of Interchange 120 days Sun 31-03-19 Mon 24-06-19 51 Interchange Design[2]

48 RE Wall Design & Drawings 30 days Sun 31-03-19 Sun 21-04-19 51 RE Wall Design[1]

49 Approval of Project Facilities & Drainage Drawings 180 days Sun 31-03-19 Mon 30-09-19 51 Design for ATMS Works[1],Design for Building Works[1],Design for Electrical Works[1],Submission of design for drainage & protective works[23,740],Submission of design for junctions/intersections[23,740],Submission of design for other project facilities[1]

50 Schedule of Eight Laning of Vadodara Mumbai Expressway 730 days Sun 31-03-19 Tue 30-03-21
(Package-01 From CH 355+000 To 378+740)
51 Issue of Notice to Proceed (NTP) 0 days Sun 31-03-19 Sun 31-03-19 31-03

52 Submission of Construction Programme 0 days Sat 20-04-19 Sat 20-04-19 51FS+28 days 20-04

53 Section - I (From 355+000 To 357+000) 571 days Sun 31-03-19 Sat 14-11-20

54 Road Works 510 days Sun 31-03-19 Sun 27-09-20

Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
55 Land Acquisition 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

56 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

57 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,55 31-03

58 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,57 31-03

59 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,58 31-03

60 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

61 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,55 31-03

62 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,61 31-03

63 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,62 31-03

64 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

65 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,55 31-03
Authority
66 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,65 31-03
authority to shifting of utilities
67 Water Pipe Line Shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

68 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,55 31-03
Authority
69 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,68 31-03
authority to shifting of utilities
70 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 51,55 31-03

71 Clearing & Grubbing 50 days Sun 31-03-19 Sun 05-05-19 51,64,56,60,59,63,66,69,70,55


Cleaning & Grubbing[1,918.81]

72 Earthwork in Embankment 250 days Sun 19-05-19 Mon 17-02-20 32,71FS+20 days Embankment[1,918.9]

73 Earthwork in Subgrade 240 days Fri 20-09-19 Sun 17-05-20 35,72SS+100 days Subgrade[1,918.81]

74 Granular Sub Base 180 days Sun 29-12-19 Fri 26-06-20 73SS+100 days Granular Sub base[1,918.81]

75 DLC 120 days Tue 07-04-20 Sat 12-09-20 74SS+100 days Dry Lean Concrete[1,918.81]

76 Kerb Casting 110 days Thu 07-05-20 Sun 27-09-20 75SS+30 days Road Furniture Kerb[2,000]

77 PQC 100 days Thu 07-05-20 Sun 20-09-20 75SS+30 days Pavement Quality Concrete[1,918.81]

78 Median Filling 30 days Fri 26-06-20 Fri 04-09-20 76SS+50 days

79 Connecting Road 61 days Sun 27-09-20 Sat 14-11-20

80 Earthwork 15 days Sun 27-09-20 Fri 09-10-20 32,78FS+30 days

81 GSB 10 days Tue 13-10-20 Wed 21-10-20 80FS+5 days

82 WMM 10 days Sun 25-10-20 Sun 01-11-20 81FS+5 days

83 DBM 5 days Sat 07-11-20 Wed 11-11-20 82FS+7 days

84 BC 2 days Thu 12-11-20 Sat 14-11-20 83FS+2 days

85 Structure Work 326 days Wed 03-04-19 Fri 28-02-20

86 Pipe Culverts - 3 Nos 50 days Sun 12-05-19 Sun 16-06-19 37,71FS+10 days Finishing[3],Head Wall[3],Pipe Laying including bedding[3]

87 Slab/Box Culverts - 3 Nos 150 days Wed 03-04-19 Thu 05-09-19 36SS+5 days,71SS BC Finishing[3],BC Foundation[3],BC Substructure[3],BC Superstructure[3]

88 CH 355+820 VUP (1 X 12 x 5.5) 197 days Sun 12-05-19 Mon 16-12-19

89 Foundation 35 days Sun 12-05-19 Thu 06-06-19 40,71FS+10 days VUP Foundation[1]

90 Sub Structure 36 days Sun 09-06-19 Fri 19-07-19 89FS+5 days VUP Substructure[1]

91 Super Structure 55 days Sat 03-08-19 Wed 16-10-19 90FS+5 days VUP Superstructure[1]

92 Finishing Works 54 days Wed 23-10-19 Mon 16-12-19 91FS+7 days VUP Finishing[1]

93 CH 356+188 Fly Over (1 X 36.85) 271 days Sun 12-05-19 Fri 28-02-20

94 Foundation 100 days Sun 12-05-19 Tue 10-09-19 46SS+10 days,71FS+10


FOB days
Foundation[1]

95 Sub Structure 94 days Mon 24-06-19 Sun 03-11-19 94SS+60 days FOB Substructure[1]

96 Super Structure 72 days Fri 08-11-19 Sun 19-01-20 95FS+5 days FOB PSC Girder[1],FOB Superstructure[1]

97 Finishing Works 33 days Sun 26-01-20 Fri 28-02-20 96FS+7 days FOB Finishing[1]

98 CH 356+564 Fly Over (1 X 32.20) 271 days Sun 12-05-19 Fri 28-02-20

99 Foundation 100 days Sun 12-05-19 Tue 10-09-19 46SS,71FS+10 daysFOB Foundation[1]

100 Sub Structure 94 days Mon 24-06-19 Sun 03-11-19 99SS+60 days FOB Substructure[1]

101 Super Structure 72 days Fri 08-11-19 Sun 19-01-20 100FS+5 days FOB PSC Girder[1],FOB Superstructure[1]

102 Finishing Works 33 days Sun 26-01-20 Fri 28-02-20 101FS+7 days FOB Finishing[1]

103 Section - II (From 357+000 To 361+000) 640 days Sun 31-03-19 Wed 06-01-21

104 Road Works 580 days Sun 31-03-19 Sat 21-11-20

105 Land Acquisition 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

106 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03

107 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,105 31-03

108 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,107 31-03

Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 2
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
109 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,108 31-03

110 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03

111 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,105 31-03

112 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,111 31-03

113 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,112 31-03

114 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

115 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,105 31-03
Authority
116 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,115 31-03
authority to shifting of utilities
117 Water Utility Shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

118 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,105 31-03
Authority
119 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,118 31-03
authority to shifting of utilities
120 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 105 31-03

121 Clearing & Grubbing 60 days Sun 31-03-19 Sun 12-05-19 51,109,113,116,105,119,120
Cleaning & Grubbing[3,259.55]

122 Earthwork in Embankment 270 days Sun 14-04-19 Sat 18-01-20 32,121SS+20 days Embankment[3,259.55]

123 Earthwork in Subgrade 270 days Fri 20-09-19 Tue 16-06-20 122SS+150 days Subgrade[3,259.55]

124 Granular Sub Base 270 days Sat 09-11-19 Sat 12-09-20 123SS+50 days Granular Sub base[3,259.55]

125 DLC 240 days Wed 08-01-20 Mon 05-10-20 124SS+60 days Dry Lean Concrete[3,259.55]

126 Kerb Casting 240 days Sat 18-01-20 Tue 13-10-20 125SS+10 days Road Furniture Kerb[4,635]

127 PQC 270 days Fri 07-02-20 Sat 21-11-20 125SS+30 days Pavement Quality Concrete[3,259.55]

128 Median Filling 90 days Tue 16-06-20 Tue 13-10-20 126SS+150 days

129 Structure Work 640 days Sun 31-03-19 Wed 06-01-21

130 Pipe Culverts - 4 Nos 60 days Sun 19-05-19 Mon 01-07-19 37,121FS+10 days Finishing[4],Head Wall[4],Pipe Laying including bedding[4]

131 Slab/Box Culverts - 4 Nos 150 days Sun 12-05-19 Wed 30-10-19 36SS+10 days,121 BC Finishing[4],BC Foundation[4],BC Substructure[4],BC Superstructure[4]

132 CH 357+326 CUP (1 X 12 x 3.50) 184 days Sun 12-05-19 Tue 03-12-19

133 Foundation 32 days Sun 12-05-19 Tue 04-06-19 38,121 PUP Foundation[1]

134 Sub Structure 32 days Sun 09-06-19 Thu 04-07-19 133FS+7 days PUP Substructure[1]

135 Super Structure 46 days Thu 25-07-19 Fri 04-10-19 134FS+7 days PUP Superstructure[1]

136 Finishing Works 50 days Mon 14-10-19 Tue 03-12-19 135FS+10 days PUP Finishing[1]

137 CH 357+975 CUP (1 X 12 x 3.5) 184 days Wed 10-04-19 Sat 19-10-19

138 Foundation 32 days Wed 10-04-19 Fri 03-05-19 38,121SS+10 days PUP Foundation[1]

139 Sub Structure 32 days Wed 08-05-19 Fri 31-05-19 138FS+7 days PUP Substructure[1]

140 Super Structure 46 days Tue 04-06-19 Sun 28-07-19 139FS+7 days PUP Superstructure[1]

141 Finishing Works 50 days Tue 27-08-19 Sat 19-10-19 140FS+10 days PUP Finishing[1]

142 CH 358+348 CUP (1 X 12 x 3.5) 181 days Tue 07-05-19 Fri 22-11-19

143 Foundation 32 days Tue 07-05-19 Wed 29-05-19 38,138FS+5 days PUP Foundation[1]

144 Sub Structure 32 days Mon 03-06-19 Wed 26-06-19 143FS+7 days PUP Substructure[1]

145 Super Structure 46 days Mon 01-07-19 Thu 26-09-19 144FS+7 days PUP Superstructure[1]

146 Finishing Works 50 days Thu 03-10-19 Fri 22-11-19 145FS+7 days PUP Finishing[1]

147 CH 358+975 VUP (1 X 12 x 5.5) 204 days Thu 02-05-19 Sun 08-12-19

148 Foundation 35 days Thu 02-05-19 Sun 26-05-19 40,121SS+10 days VUP Foundation[1]

149 Sub Structure 36 days Fri 31-05-19 Wed 26-06-19 148FS+7 days VUP Substructure[1]

150 Super Structure 55 days Mon 01-07-19 Sat 05-10-19 149FS+7 days VUP Superstructure[1]

151 Finishing Works 54 days Tue 15-10-19 Sun 08-12-19 150FS+10 days VUP Finishing[1]

152 CH 359+397 CUP (1 X 12 x 3.5) 184 days Wed 10-04-19 Sat 19-10-19

153 Foundation 32 days Wed 10-04-19 Fri 03-05-19 38 PUP Foundation[1]

154 Sub Structure 32 days Wed 08-05-19 Fri 31-05-19 153FS+7 days PUP Substructure[1]

155 Super Structure 46 days Tue 04-06-19 Sun 28-07-19 154FS+7 days PUP Superstructure[1]

156 Finishing Works 50 days Tue 27-08-19 Sat 19-10-19 155FS+10 days PUP Finishing[1]

157 CH 359+810 MNB (1 X 32.250) 269 days Sun 21-04-19 Mon 27-01-20

158 Foundation 98 days Sun 21-04-19 Sat 29-06-19 42SS+30 days,121SS+20


MNB days
Foundation[1]

159 Sub Structure 74 days Sun 16-06-19 Fri 04-10-19 158SS+80 days MNB Substructure[1]

160 Super Structure 70 days Fri 11-10-19 Fri 20-12-19 159FS+7 days MNB Superstructure[1]

161 Finishing Works 28 days Mon 30-12-19 Mon 27-01-20 160FS+10 days MNB Finishing[1]

162 CH 359+868 CUP (1 X 12 x 3.5) 184 days Sat 04-05-19 Fri 22-11-19

Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 3
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
163 Foundation 32 days Sat 04-05-19 Mon 27-05-19 38,153FS+2 days PUP Foundation[1]

164 Sub Structure 32 days Sat 01-06-19 Mon 24-06-19 163FS+7 days PUP Substructure[1]

165 Super Structure 46 days Fri 28-06-19 Mon 23-09-19 164FS+7 days PUP Superstructure[1]

166 Finishing Works 50 days Thu 03-10-19 Fri 22-11-19 165FS+10 days PUP Finishing[1]

167 CH 360+220 MJB (1 X 77.99m) (Single Span Steel Girder) 302 days Sun 31-03-19 Thu 30-01-20

168 Foundation 120 days Sun 31-03-19 Mon 24-06-19 43SS MJB Foundation[1]

169 Sub Structure 86 days Sun 02-06-19 Thu 26-09-19 168SS+90 days MJB Substructure[1]

170 Steel Girder Erection 90 days Thu 10-10-19 Wed 08-01-20 169FS+14 days MJB PSC Girder[1]

171 Super Structure 74 days Sun 06-10-19 Thu 19-12-19 169FS+10 days MJB Superstructure[1]

172 Finishing Works 28 days Thu 02-01-20 Thu 30-01-20 171FS+14 days MJB Finishing[1]

173 CH 361+034 ROB (1201.487m) 610 days Sun 21-04-19 Wed 06-01-21

174 Foundation 320 days Sun 21-04-19 Wed 18-03-20 44SS+30 days,51FS+15
ROBdays
Foundation[1]

175 Sub Structure 350 days Sun 02-06-19 Tue 16-06-20 174SS+60 days ROB Substructure[1]

176 PSC Girder 230 days Sat 28-03-20 Sat 28-11-20 175SS+270 days ROB PSC Girder[0.5]

177 Steel Girder Erection 60 days Tue 23-06-20 Fri 25-09-20 45FS+1 day,175FS+7
ROB
days
PSC Girder[0.5]

178 Super Structure 143 days Fri 07-08-20 Mon 14-12-20 176SS+30 days,177SS+20
ROB Superstructure[1]
days

179 Finishing Works 140 days Sun 20-09-20 Wed 06-01-21 178SS+33 days ROB Finishing[1]

180 Section - III (From 361+000 To 366+000) 630 days Sun 31-03-19 Tue 29-12-20

181 Road Works 630 days Sun 31-03-19 Tue 29-12-20

182 Land Acquisition 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

183 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03

184 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,182 31-03

185 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,184 31-03

186 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,185 31-03

187 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03

188 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,182 31-03

189 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,188 31-03

190 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,189 31-03

191 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

192 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,182 31-03
Authority
193 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,192 31-03
authority to shifting of utilities
194 Water Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

195 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,182 31-03
Authority
196 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,195 31-03
authority to shifting of utilities
197 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 182 31-03

198 Clearing & Grubbing 60 days Sun 31-03-19 Sun 12-05-19 51,186,190,193,196,182,197
Cleaning & Grubbing[3,840.53]

199 Earthwork in Embankment 300 days Sun 14-04-19 Mon 17-02-20 32,198SS+20 days Embankment[3,840.53]

200 Earthwork in Subgrade 280 days Tue 19-11-19 Sun 27-09-20 199SS+210 days Subgrade[3,840.53]

201 Granular Sub Base 250 days Sat 18-01-20 Wed 21-10-20 200SS+60 days Granular Sub base[3,840.53]

202 DLC 210 days Fri 17-04-20 Sat 28-11-20 201SS+90 days Dry Lean Concrete[3,840.53]

203 Kerb Casting 80 days Fri 17-07-20 Wed 21-10-20 202SS+80 days Road Furniture Kerb[4,397]

204 PQC 210 days Wed 27-05-20 Tue 29-12-20 202SS+40 days Pavement Quality Concrete[3,840.53]

205 Median Filling 30 days Mon 05-10-20 Wed 28-10-20 203SS+60 days

206 Connecting Road 85 days Mon 17-02-20 Tue 12-05-20

207 Earthwork 45 days Mon 17-02-20 Thu 02-04-20 32,198,199

208 GSB 15 days Thu 02-04-20 Fri 17-04-20 207

209 WMM 10 days Fri 17-04-20 Mon 27-04-20 208

210 DBM 10 days Mon 27-04-20 Thu 07-05-20 209

211 BC 5 days Thu 07-05-20 Tue 12-05-20 210

212 Structure Work 562 days Wed 10-04-19 Wed 18-11-20

213 Pipe Culverts - 5 Nos 90 days Thu 02-05-19 Tue 16-07-19 37,198SS+30 days Finishing[5],Head Wall[5],Pipe Laying including bedding[5]

214 Slab/Box Culverts - 5 Nos 200 days Wed 10-04-19 Mon 04-11-19 36SS+15 days BC Finishing[5],BC Foundation[5],BC Substructure[5],BC Superstructure[5]

215 CH 362+160 CUP (1 X 12 x 3.5) 184 days Sat 01-06-19 Tue 31-12-19

216 Foundation 32 days Sat 01-06-19 Mon 24-06-19 38,163FS+7 days PUP Foundation[1]

Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 4
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
217 Sub Structure 32 days Fri 28-06-19 Mon 09-09-19 216FS+7 days PUP Substructure[1]

218 Super Structure 46 days Mon 16-09-19 Fri 01-11-19 217FS+7 days PUP Superstructure[1]

219 Finishing Works 50 days Mon 11-11-19 Tue 31-12-19 218FS+10 days PUP Finishing[1]

220 CH 362+350 MJB (142.50m) 427 days Fri 30-08-19 Wed 18-11-20

221 Foundation 130 days Fri 30-08-19 Wed 08-01-20 43,198SS+50 days MJB Foundation[1]

222 Sub Structure 110 days Wed 15-01-20 Mon 04-05-20 221FS+7 days MJB Substructure[1]

223 Super Structure 103 days Mon 11-05-20 Fri 25-09-20 222FS+7 days MJB PSC Girder[1],MJB Superstructure[1]

224 Finishing Works 60 days Sat 03-10-20 Wed 18-11-20 223FS+10 days MJB Finishing[1]

225 CH 362+682 CUP (1 X 12 x 3.5) 184 days Tue 25-06-19 Mon 03-02-20
226 Foundation 32 days Tue 25-06-19 Wed 04-09-19 38,216FS+2 days PUP Foundation[1]

227 Sub Structure 32 days Wed 11-09-19 Sun 13-10-19 226FS+7 days PUP Substructure[1]

228 Super Structure 46 days Sun 20-10-19 Thu 05-12-19 227FS+7 days PUP Superstructure[1]

229 Finishing Works 50 days Sun 15-12-19 Mon 03-02-20 228FS+10 days PUP Finishing[1]

230 CH 363+273 LVUP (1 X 12 X3.5) 184 days Sun 12-05-19 Tue 03-12-19

231 Foundation 32 days Sun 12-05-19 Tue 04-06-19 39,198SS+60 days VUP Foundation[1]

232 Sub Structure 32 days Sun 09-06-19 Thu 04-07-19 231FS+7 days VUP Substructure[1]

233 Super Structure 46 days Thu 25-07-19 Fri 04-10-19 232FS+7 days VUP Superstructure[1]

234 Finishing Works 50 days Mon 14-10-19 Tue 03-12-19 233FS+10 days VUP Finishing[1]

235 CH 363+850 FLY OVER (151m) 398 days Mon 24-06-19 Sun 04-10-20

236 Foundation 137 days Mon 24-06-19 Mon 16-12-19 46,198FS+40 days FOB Foundation[1]

237 Sub Structure 121 days Fri 18-10-19 Sun 16-02-20 233SS+60 days FOB Substructure[1]

238 Super Structure 119 days Wed 26-02-20 Wed 24-06-20 237FS+10 days FOB PSC Girder[1],FOB Superstructure[1]

239 Finishing Works 60 days Sat 11-07-20 Sun 04-10-20 238FS+10 days FOB Finishing[1]

240 CH 364+274 CUP (1 x 12 x3.5) 184 days Fri 06-09-19 Sun 08-03-20

241 Foundation 32 days Fri 06-09-19 Tue 08-10-19 38,226FS+2 days PUP Foundation[1]

242 Sub Structure 32 days Tue 15-10-19 Sat 16-11-19 241FS+7 days PUP Substructure[1]

243 Super Structure 46 days Sat 23-11-19 Wed 08-01-20 242FS+7 days PUP Superstructure[1]

244 Finishing Works 50 days Sat 18-01-20 Sun 08-03-20 243FS+10 days PUP Finishing[1]

245 CH 364+650 MNB (85.936m) 422 days Sun 12-05-19 Sun 06-09-20

246 Foundation 158 days Sun 12-05-19 Thu 07-11-19 42SS,198 MNB Foundation[1]

247 Sub Structure 82 days Sun 17-11-19 Fri 07-02-20 246FS+10 days MNB Substructure[1]

248 Super Structure 97 days Mon 17-02-20 Sun 24-05-20 247FS+10 days MNB Superstructure[1]

249 Finishing Works 50 days Mon 08-06-20 Sun 06-09-20 248FS+15 days MNB Finishing[1]

250 CH 365+165 CUP (1 X 12 x 3.5) 184 days Thu 10-10-19 Sat 11-04-20

251 Foundation 32 days Thu 10-10-19 Mon 11-11-19 38,241FS+2 days PUP Foundation[1]

252 Sub Structure 32 days Mon 18-11-19 Fri 20-12-19 251FS+7 days PUP Substructure[1]

253 Super Structure 46 days Fri 27-12-19 Tue 11-02-20 252FS+7 days PUP Superstructure[1]

254 Finishing Works 50 days Fri 21-02-20 Sat 11-04-20 253FS+10 days PUP Finishing[1]

255 CH 365+976 MJB (1 X 111.65) 444 days Sun 21-04-19 Fri 28-08-20

256 Foundation 130 days Sun 21-04-19 Tue 10-09-19 43SS+30 days,198SS+30
MJB Foundation[1]
days

257 Sub Structure 110 days Tue 17-09-19 Sun 05-01-20 256FS+7 days MJB Substructure[1]

258 Super Structure 130 days Sun 12-01-20 Thu 21-05-20 257FS+7 days MJB PSC Girder[1],MJB Superstructure[1]

259 Finishing Works 50 days Sun 31-05-20 Fri 28-08-20 258FS+10 days MJB Finishing[1]

260 Section - IV (From 366+000 To 371+000) 575 days Sun 31-03-19 Tue 17-11-20

261 Road Works 500 days Sun 31-03-19 Sun 20-09-20

262 Land Acquisition 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

263 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03

264 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,262 31-03
265 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,264 31-03
266 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,265 31-03
267 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03

268 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,262 31-03
269 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,268 31-03
270 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,269 31-03
271 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

272 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,262 31-03
Authority
273 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,272 31-03
authority to shifting of utilities
274 Water Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 5
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
275 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,262 31-03
Authority
276 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,275 31-03
authority to shifting of utilities
277 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 262 31-03

278 Clearing & Grubbing 20 days Sun 31-03-19 Sun 14-04-19 51,266,270,273,276,277
Cleaning & Grubbing[4,823.45]

279 Earthwork in Excavation 30 days Sun 31-03-19 Sun 21-04-19 278SS

280 Earthwork in Embankment 380 days Sun 14-04-19 Thu 07-05-20 32,278 Embankment[4,823.45]

281 Earthwork in Subgrade 250 days Mon 09-12-19 Sun 20-09-20 280SS+230 days Subgrade[4,823.45]

282 Granular Sub Base 150 days Wed 08-01-20 Sat 06-06-20 281SS+30 days Granular Sub base[4,823.45]

283 DLC 130 days Fri 07-02-20 Tue 16-06-20 282SS+30 days Dry Lean Concrete[4,823.45]

284 Kerb Casting 150 days Mon 17-02-20 Sun 16-08-20 283SS+10 days Road Furniture Kerb[4,968]

285 PQC 150 days Sun 08-03-20 Sat 12-09-20 283SS+30 days Pavement Quality Concrete[4,823.45]

286 Median Filling 50 days Fri 17-04-20 Sat 06-06-20 284SS+60 days

287 Connecting Road 85 days Sat 12-09-20 Tue 17-11-20

288 Earthwork 45 days Sat 12-09-20 Sat 17-10-20 285

289 GSB 15 days Sat 17-10-20 Wed 28-10-20 288

290 WMM 10 days Wed 28-10-20 Thu 05-11-20 289

291 DBM 10 days Thu 05-11-20 Fri 13-11-20 290

292 BC 5 days Fri 13-11-20 Tue 17-11-20 291

293 Structure Work 480 days Wed 17-04-19 Thu 24-09-20

294 Pipe Culverts - 4 Nos 100 days Sun 05-05-19 Fri 30-08-19 37,278FS+30 days Finishing[4],Head Wall[4],Pipe Laying including bedding[4]

295 Slab/Box Culverts - 9 Nos 180 days Thu 02-05-19 Thu 14-11-19 36,278 BC Finishing[9],BC Foundation[9],BC Substructure[9],BC Superstructure[9]

296 CH 367+012 CUP (1 X 12 X 3.50) 184 days Wed 17-04-19 Tue 29-10-19
297 Foundation 32 days Wed 17-04-19 Fri 10-05-19 38,278FS+5 days PUP Foundation[1]

298 Sub Structure 32 days Wed 15-05-19 Fri 07-06-19 297FS+7 days PUP Substructure[1]

299 Super Structure 46 days Wed 12-06-19 Tue 27-08-19 298FS+7 days PUP Superstructure[1]

300 Finishing Works 50 days Mon 09-09-19 Tue 29-10-19 299FS+10 days PUP Finishing[1]

301 CH 367+220 MNB GAS (1 X 21.941) 210 days Sun 16-06-19 Mon 17-02-20
302 Foundation 35 days Sun 16-06-19 Thu 15-08-19 42SS+45 days,278FS+90
MNB days
Foundation[1]

303 Sub Structure 36 days Thu 05-09-19 Fri 11-10-19 302FS+10 days MNB Substructure[1]

304 Super Structure 55 days Mon 21-10-19 Sun 15-12-19 303FS+10 days MNB Superstructure[1]

305 Finishing Works 54 days Wed 25-12-19 Mon 17-02-20 304FS+10 days MNB Finishing[1]

306 CH 367+590 CUP (1 X 12 x 3.5) 184 days Tue 14-05-19 Thu 05-12-19

307 Foundation 32 days Tue 14-05-19 Wed 05-06-19 38,297FS+5 days PUP Foundation[1]

308 Sub Structure 32 days Mon 10-06-19 Wed 10-07-19 307FS+7 days PUP Substructure[1]

309 Super Structure 46 days Wed 31-07-19 Sun 06-10-19 308FS+7 days PUP Superstructure[1]

310 Finishing Works 50 days Wed 16-10-19 Thu 05-12-19 309FS+10 days PUP Finishing[1]

311 CH 368+014 FLY OVER (1 X 65m) 248 days Mon 16-12-19 Thu 24-09-20

312 Foundation 100 days Mon 16-12-19 Wed 25-03-20 46,236,278SS+90 days
FOB Foundation[1]

313 Sub Structure 94 days Tue 04-02-20 Fri 08-05-20 312SS+50 days FOB Substructure[1]

314 Super Structure 50 days Fri 15-05-20 Sat 11-07-20 313FS+7 days FOB PSC Girder[1],FOB Superstructure[1]

315 Finishing Works 33 days Sat 22-08-20 Thu 24-09-20 314FS+14 days FOB Finishing[1]

316 CH 369+130 LVUP (1 X 12 X 3.5) 188 days Thu 02-05-19 Fri 22-11-19

317 Foundation 32 days Thu 02-05-19 Fri 24-05-19 39,278SS+45 days VUP Foundation[1]

318 Sub Structure 32 days Wed 29-05-19 Fri 21-06-19 317FS+7 days VUP Substructure[1]

319 Super Structure 46 days Wed 26-06-19 Thu 19-09-19 318FS+7 days VUP Superstructure[1]

320 Finishing Works 50 days Thu 03-10-19 Fri 22-11-19 319FS+14 days VUP Finishing[1]

321 CH 370+024 VUP (1 X 12 X 5.50) 208 days Thu 02-05-19 Thu 12-12-19

322 Foundation 35 days Thu 02-05-19 Sun 26-05-19 40,278SS+45 days VUP Foundation[1]

323 Sub Structure 36 days Fri 31-05-19 Wed 26-06-19 322FS+7 days VUP Substructure[1]

324 Super Structure 55 days Mon 01-07-19 Sat 05-10-19 323FS+7 days VUP Superstructure[1]

325 Finishing Works 54 days Sat 19-10-19 Thu 12-12-19 324FS+14 days VUP Finishing[1]

326 CH 370+580 MNB (1 X 17.03m) 230 days Thu 15-08-19 Sun 12-04-20

327 Foundation 51 days Thu 15-08-19 Wed 16-10-19 41SS+60 days,278FS+90


MNB days,302
Foundation[1]

328 Sub Structure 52 days Wed 25-09-19 Sat 16-11-19 327SS+30 days MNB Substructure[1]

329 Super Structure 72 days Sat 23-11-19 Mon 03-02-20 328FS+7 days MNB Superstructure[1]

Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 6
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
330 Finishing Works 55 days Mon 17-02-20 Sun 12-04-20 329FS+14 days MNB Finishing[1]

331 Section - V (From 371+000 To 374+500) 631 days Sun 31-03-19 Wed 30-12-20

332 Road Works 570 days Sun 31-03-19 Fri 13-11-20

333 Land Acquisition 0 days Sun 31-03-19 Sun 31-03-19 51 31-03


334 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
335 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,333 31-03
336 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,335 31-03
337 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,336 31-03
338 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03
339 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,333 31-03
340 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,339 31-03
341 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,340 31-03
342 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

343 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,333 31-03
Authority
344 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,343 31-03
authority to shifting of utilities
345 Water Pipe Line Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

346 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,333 31-03
Authority
347 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,346 31-03
authority to shifting of utilities
348 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 333 31-03
349 Clearing & Grubbing 40 days Sun 31-03-19 Sun 28-04-19 51,348,333,337,341,344,347
Cleaning & Grubbing[2,615.5]

350 Earthwork in Embankment 450 days Sun 14-04-19 Sun 16-08-20 32,349SS+20 days Embankment[2,615.5]

351 Earthwork in Subgrade 180 days Mon 17-02-20 Sun 20-09-20 350SS+300 days Subgrade[2,615.5]

352 Granular Sub Base 150 days Tue 07-04-20 Mon 05-10-20 351SS+50 days Granular Sub base[2,615.5]

353 DLC 150 days Thu 07-05-20 Wed 28-10-20 352SS+30 days Dry Lean Concrete[2,615.5]

354 Kerb Casting 90 days Sun 17-05-20 Sun 20-09-20 353SS+10 days Road Furniture Kerb[3,500]

355 PQC 150 days Wed 27-05-20 Fri 13-11-20 353SS+20 days Pavement Quality Concrete[2,615.5]

356 Median Filling 50 days Fri 17-07-20 Sun 27-09-20 354SS+50 days

357 Connecting Road 161 days Sun 16-08-20 Wed 30-12-20

358 Earthwork 60 days Sun 16-08-20 Tue 13-10-20 32,349,350

359 GSB 30 days Tue 13-10-20 Thu 05-11-20 358

360 WMM 30 days Fri 06-11-20 Sun 29-11-20 359FS+1 day

361 DBM 25 days Sun 29-11-20 Fri 18-12-20 360

362 BC 15 days Fri 18-12-20 Wed 30-12-20 361

363 Structure Work 575 days Sun 05-05-19 Fri 25-12-20

364 Slab/Box Culverts - 12 Nos 220 days Sun 05-05-19 Sun 29-12-19 36,349FS+10 days BC Finishing[12],BC Foundation[12],BC Substructure[12],BC Superstructure[12]

365 CH 371+720 FLY OVER (1 X 36.90m) 465 days Wed 31-07-19 Thu 10-12-20

366 Foundation 137 days Wed 31-07-19 Sun 05-01-20 46,349FS+100 daysFOB Foundation[1]

367 Sub Structure 121 days Wed 15-01-20 Fri 15-05-20 366FS+10 days FOB Substructure[1]

368 Super Structure 119 days Mon 25-05-20 Sun 18-10-20 367FS+10 days FOB PSC Girder[1],FOB Superstructure[1]

369 Finishing Works 54 days Thu 29-10-20 Thu 10-12-20 368FS+14 days FOB Finishing[1]

370 CH 372+028 MNB (1 X 52.826m) 324 days Thu 10-10-19 Wed 30-09-20

371 Foundation 65 days Thu 10-10-19 Sat 14-12-19 41,349FS+150 daysMNB Foundation[1]

372 Sub Structure 78 days Tue 24-12-19 Wed 11-03-20 371FS+10 days MNB Substructure[1]

373 Super Structure 92 days Sat 21-03-20 Sun 21-06-20 372FS+10 days MNB Superstructure[1]

374 Finishing Works 55 days Tue 14-07-20 Wed 30-09-20 373FS+14 days MNB Finishing[1]

375 CH 373+608 ROB (1 X 186.015m) 560 days Sun 12-05-19 Tue 22-12-20

376 Foundation 130 days Sun 12-05-19 Thu 10-10-19 44,349SS+20 days ROB Foundation[1]

377 Sub Structure 150 days Sun 02-06-19 Fri 29-11-19 376SS+30 days ROB Substructure[1]

378 Launching of Girder 150 days Tue 28-01-20 Fri 26-06-20 377FS+60 days ROB PSC Girder[1]

379 Super Structure 100 days Fri 17-07-20 Thu 05-11-20 378FS+10 days ROB Superstructure[1]

380 Finishing Works 50 days Fri 13-11-20 Tue 22-12-20 379FS+10 days ROB Finishing[1]

381 CH 373+905 MNB GAS (1 X 70.590) 378 days Mon 24-06-19 Fri 18-09-20

382 Foundation 154 days Mon 24-06-19 Thu 02-01-20 42,349FS+60 days MNB Foundation[1]

383 Sub Structure 74 days Sun 12-01-20 Thu 26-03-20 382FS+10 days MNB Substructure[1]

384 Super Structure 62 days Thu 09-04-20 Wed 10-06-20 383FS+14 days MNB Superstructure[1]

385 Finishing Works 50 days Wed 24-06-20 Fri 18-09-20 384FS+14 days MNB Finishing[1]

386 CH 374+355 IC MAIN STRUCTURE (1 X 130.876m) 505 days Mon 24-06-19 Fri 25-12-20

387 Foundation 125 days Mon 24-06-19 Wed 04-12-19 47,349FS+80 days FOB Foundation[1]

388 Sub Structure 120 days Sat 14-12-19 Sun 12-04-20 387FS+10 days FOB Substructure[1]

Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 7
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
389 Super Structure 170 days Wed 22-04-20 Sun 01-11-20 388FS+10 days FOB PSC Girder[1],FOB Superstructure[1]

390 Finishing Works 60 days Mon 09-11-20 Fri 25-12-20 389FS+10 days FOB Finishing[1]

391 CH 374+355 IC VUP RAMP-01 205 days Wed 31-07-19 Fri 13-03-20

392 Foundation 35 days Wed 31-07-19 Wed 25-09-19 47,349FS+100 days

393 Sub Structure 36 days Wed 02-10-19 Thu 07-11-19 392FS+7 days

394 Super Structure 55 days Thu 14-11-19 Wed 08-01-20 393FS+7 days

395 Finishing Works 55 days Sat 18-01-20 Fri 13-03-20 394FS+10 days

396 CH 374+720 IC VUP RAMP-02 216 days Sat 05-10-19 Fri 08-05-20

397 Foundation 35 days Sat 05-10-19 Sat 09-11-19 47,392FS+10 days

398 Sub Structure 36 days Tue 19-11-19 Wed 25-12-19 397FS+10 days

399 Super Structure 55 days Sat 04-01-20 Fri 28-02-20 398FS+10 days

400 Finishing Works 55 days Sat 14-03-20 Fri 08-05-20 399FS+15 days

401 Toll Plaza - Loop-01 170 days Fri 29-11-19 Sun 17-05-20

402 DLC 60 days Fri 29-11-19 Tue 28-01-20 47,349FS+200 days

403 PQC 70 days Mon 09-12-19 Mon 17-02-20 402SS+10 days

404 Toll Booth 50 days Tue 28-01-20 Wed 18-03-20 403SS+50 days

405 Canopy 60 days Wed 18-03-20 Sun 17-05-20 404

406 Lighting & Finishing Works 60 days Thu 27-02-20 Mon 27-04-20 404SS+30 days

407 Toll Plaza - Loop-02 250 days Fri 29-11-19 Sat 12-09-20

408 DLC 60 days Fri 29-11-19 Tue 28-01-20 47,349FS+200 days

409 PQC 180 days Mon 09-12-19 Sat 06-06-20 408SS+10 days

410 Toll Booth 50 days Tue 28-01-20 Wed 18-03-20 409SS+50 days

411 Canopy 60 days Sat 06-06-20 Sat 12-09-20 409

412 Lighting & Finishing Works 60 days Wed 08-01-20 Sun 08-03-20 409SS+30 days

413 Toll Plaza -Ramp-01 200 days Sat 18-01-20 Sat 12-09-20

414 DLC 60 days Sat 18-01-20 Wed 18-03-20 47,349FS+250 days

415 PQC 180 days Tue 28-01-20 Fri 04-09-20 414SS+10 days

416 Toll Booth 50 days Wed 18-03-20 Thu 07-05-20 415SS+50 days

417 Canopy 60 days Thu 07-05-20 Fri 17-07-20 416

418 Lighting & Finishing Works 60 days Sat 06-06-20 Sat 12-09-20 417SS+30 days

419 Toll Plaza - Ramp-02 200 days Sun 08-03-20 Wed 21-10-20

420 DLC 60 days Sun 08-03-20 Thu 07-05-20 47,349FS+300 days

421 PQC 180 days Wed 18-03-20 Tue 13-10-20 420SS+10 days

422 Toll Booth 50 days Thu 07-05-20 Fri 26-06-20 421SS+50 days

423 Canopy 60 days Fri 26-06-20 Sun 27-09-20 422

424 Lighting & Finishing Works 60 days Fri 04-09-20 Wed 21-10-20 423SS+30 days

425 Section - VI (From 374+500 To 377+000) 591 days Sun 31-03-19 Sun 29-11-20

426 Road Works 565 days Sun 31-03-19 Mon 09-11-20

427 Land Acquisition 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

428 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03

429 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,427 31-03

430 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,429 31-03

431 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,430 31-03

432 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03

433 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,427 31-03

434 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,433 31-03

435 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,434 31-03

436 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

437 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,427 31-03
Authority
438 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,437 31-03
authority to shifting of utilities
439 Water Pipe Line Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

440 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,427 31-03
Authority
441 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,440 31-03
authority to shifting of utilities
442 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 427 31-03

Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 8
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
443 Clearing & Grubbing 90 days Sun 31-03-19 Sun 02-06-19 51,442,427,431,435,438,441
Cleaning & Grubbing[2,136.16]

444 Earthwork in Excavation 30 days Wed 03-04-19 Thu 25-04-19 443SS+5 days

445 Earthwork in Embankment 400 days Thu 02-05-19 Sun 21-06-20 443SS+45 days,444SS
Embankment[2,136.16]

446 Earthwork in Subgrade 120 days Fri 13-03-20 Sat 01-08-20 32,445SS+300 daysSubgrade[2,136.16]

447 Granular Sub Base 120 days Sat 02-05-20 Thu 01-10-20 446SS+50 days Granular Sub base[2,136.16]

448 DLC 120 days Mon 01-06-20 Sat 24-10-20 447SS+30 days Dry Lean Concrete[2,136.16]

449 Kerb Casting 60 days Tue 16-06-20 Sun 20-09-20 448SS+15 days Road Furniture Kerb[2,500]

450 PQC 120 days Sun 21-06-20 Mon 09-11-20 448SS+20 days Pavement Quality Concrete[2,136.16]

451 Median Filling 30 days Fri 04-09-20 Sun 27-09-20 449SS+40 days

452 Connecting Road 166 days Sat 02-05-20 Fri 06-11-20

453 Earthwork 60 days Sat 02-05-20 Thu 02-07-20 445FF+10 days

454 GSB 30 days Sun 05-07-20 Wed 09-09-20 453FS+1 day

455 WMM 30 days Thu 10-09-20 Sun 04-10-20 454FS+2 days

456 DBM 25 days Mon 05-10-20 Sat 24-10-20 455FS+2 days

457 BC 15 days Sun 25-10-20 Fri 06-11-20 456FS+1 day

458 Structure Work 491 days Sun 09-06-19 Sun 29-11-20

459 Box Culverts - 6 Nos 200 days Sun 09-06-19 Tue 28-01-20 36,443SS+100 daysBC Finishing[6],BC Foundation[6],BC Substructure[6],BC Superstructure[6]

460 CH 375+588 VUP (1 X 12 X 5.5) 199 days Fri 29-11-19 Mon 15-06-20

461 Foundation 35 days Fri 29-11-19 Fri 03-01-20 40,443FS+150 daysVUP Foundation[1]

462 Sub Structure 36 days Wed 08-01-20 Thu 13-02-20 461FS+5 days VUP Substructure[1]

463 Super Structure 55 days Thu 20-02-20 Wed 15-04-20 462FS+7 days VUP Superstructure[1]

464 Finishing Works 54 days Wed 22-04-20 Mon 15-06-20 463FS+7 days VUP Finishing[1]

465 CH 376+867 MNB (1 X 54.45m) 202 days Fri 29-11-19 Thu 18-06-20

466 Foundation 35 days Fri 29-11-19 Fri 03-01-20 41,443FS+150 daysMNB Foundation[1]

467 Sub Structure 36 days Wed 08-01-20 Thu 13-02-20 466FS+5 days MNB Substructure[1]

468 Super Structure 55 days Thu 20-02-20 Wed 15-04-20 467FS+7 days MNB Superstructure[1]

469 Finishing Works 54 days Sat 25-04-20 Thu 18-06-20 468FS+10 days MNB Finishing[1]

470 Toll Plaza (MEW) 401 days Thu 10-10-19 Sun 29-11-20

471 Administration & Office Block 180 days Fri 29-11-19 Wed 27-05-20 443FS+150 days Toll Plaza Building[1]

472 Tunnel 180 days Fri 29-11-19 Wed 27-05-20 471SS Toll Plaza Tunnel[1]

473 Earthwork 90 days Thu 10-10-19 Wed 08-01-20 443FS+100 days Toll Plaza Earthwork[1]

474 GSB 90 days Thu 09-01-20 Wed 08-04-20 473FS+1 day Toll Plaza SubBase[1]

475 DLC 90 days Sat 08-02-20 Fri 08-05-20 474SS+30 days Toll Plaza DLC[1]

476 PQC 120 days Wed 08-04-20 Sun 13-09-20 475SS+60 days Toll Plaza PQC[1]

477 Toll Booth 60 days Thu 28-05-20 Sat 05-09-20 476SS+50 days Toll Plaza Booths[1]

478 Canopy 60 days Thu 28-05-20 Sat 05-09-20 477SS Toll Plaza Space Frame[1]

479 Toll Singages 60 days Sun 07-06-20 Sun 13-09-20 476SS+60 days Toll Singages[1]

480 Traffic & Mediacl Air Post 100 days Sun 13-09-20 Sun 29-11-20 476 Traffic & Mediacl Air Post[1]

481 Lighting & Finishing Works 90 days Thu 28-05-20 Mon 28-09-20 477SS Toll Plaza Electrical - Procurement & Installation[1]

482 Section - VII (From 377+000 To 378+740) 520 days Sun 31-03-19 Mon 05-10-20

483 Road Works 520 days Sun 31-03-19 Mon 05-10-20

484 Land Acquisition 0 days Sun 31-03-19 Sun 31-03-19 51 31-03

485 Tree Cutting-Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03

486 Clearance From MOEF 0 days Sun 31-03-19 Sun 31-03-19 51,484 31-03

487 Tree Cuttinng Permission 0 days Sun 31-03-19 Sun 31-03-19 51,486 31-03

488 Cutting of Trees by State Forest Dept 0 days Sun 31-03-19 Sun 31-03-19 51,487 31-03

489 Tree Cutting - Non Forest Trees 0 days Sun 31-03-19 Sun 31-03-19 31-03

490 Permission for Tree Cutting 0 days Sun 31-03-19 Sun 31-03-19 51,484 31-03

491 Valuation of Trees Identified 0 days Sun 31-03-19 Sun 31-03-19 51,490 31-03

492 Tree Cutting and stacking 0 days Sun 31-03-19 Sun 31-03-19 51,491 31-03

493 Electrical Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

494 Approval of Estimates for shifting electrical utility by 0 days Sun 31-03-19 Sun 31-03-19 51,484 31-03
Authority
495 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,494 31-03
authority to shifting of utilities
496 Water Pipe Line Utility shifting 0 days Sun 31-03-19 Sun 31-03-19 31-03

Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 9
ID Task Task Name Duration Start Finish Predecessors Resource Names 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter
Mode J M M J S N J M M J S N J M M J S N J M M J
497 Approval of Estimates for shifting water pipeline utility by 0 days Sun 31-03-19 Sun 31-03-19 51,484 31-03
Authority
498 Deposit supervision charges to utility owing agency by 0 days Sun 31-03-19 Sun 31-03-19 51,497 31-03
authority to shifting of utilities
499 Structure Dismantling 0 days Sun 31-03-19 Sun 31-03-19 484 31-03

500 Clearing & Grubbing 120 days Sun 31-03-19 Mon 24-06-19 51,484,488,492,495,498
Cleaning & Grubbing[1,536.91]

501 Earthwork in Excavation 30 days Wed 10-04-19 Thu 02-05-19 32

502 Earthwork in Embankment 350 days Sun 21-04-19 Fri 17-04-20 32,500SS+30 days Embankment[1,536.91]

503 Earthwork in Subgrade 180 days Tue 19-11-19 Sun 17-05-20 502SS+200 days Subgrade[1,536.91]

504 Granular Sub Base 120 days Fri 07-02-20 Sat 06-06-20 503SS+80 days Granular Sub base[1,536.91]

505 DLC 100 days Sat 28-03-20 Fri 17-07-20 504SS+50 days Dry Lean Concrete[1,536.91]

506 Kerb Casting 90 days Fri 17-04-20 Sun 16-08-20 505SS+20 days Road Furniture Kerb[1,740]

507 PQC 120 days Thu 07-05-20 Mon 05-10-20 506SS+20 days Pavement Quality Concrete[1,536.91]

508 Median Filling 50 days Sat 06-06-20 Fri 04-09-20 506SS+50 days

509 Structure Work 416 days Thu 02-05-19 Mon 20-07-20


510 Pipe Culverts - 2 Nos 60 days Thu 02-05-19 Thu 13-06-19 37,484SS+30 days Finishing[2],Head Wall[2],Pipe Laying including bedding[2]
511 Slab/Box Culverts - 8 Nos 150 days Sun 29-12-19 Wed 27-05-20 36,500FS+150 daysBC Finishing[8],BC Foundation[8],BC Substructure[8],BC Superstructure[8]
512 CH 377+374 VUP (1 X 12 x 5.5) 181 days Sun 29-12-19 Sat 27-06-20
513 Foundation 35 days Sun 29-12-19 Sun 02-02-20 40,484FS+270 daysVUP Foundation[1]
514 Sub Structure 36 days Sun 02-02-20 Mon 09-03-20 513 VUP Substructure[1]
515 Super Structure 55 days Mon 09-03-20 Sun 03-05-20 514 VUP Superstructure[1]
516 Finishing Works 55 days Sun 03-05-20 Sat 27-06-20 515 VUP Finishing[1]
517 CH 377+920 MNB (1 X 70.590m) 181 days Sun 09-06-19 Thu 09-01-20
518 Foundation 35 days Sun 09-06-19 Tue 16-07-19 41SS+60 days,484FS+100
MNB Foundation[1]
days
519 Sub Structure 36 days Tue 16-07-19 Sat 21-09-19 518 MNB Substructure[1]
520 Super Structure 55 days Sat 21-09-19 Fri 15-11-19 519 MNB Superstructure[1]
521 Finishing Works 55 days Fri 15-11-19 Thu 09-01-20 520 MNB Finishing[1]
522 CH 378+211 Fly Over (1 X 32.411m) 316 days Thu 15-08-19 Mon 20-07-20
523 Foundation 280 days Thu 15-08-19 Mon 01-06-20 46,366SS+5 days FOB Foundation[1]
524 Sub Structure 100 days Tue 15-10-19 Thu 23-01-20 523SS+50 days FOB Substructure[1]
525 Super Structure 94 days Thu 23-01-20 Sun 26-04-20 524 FOB PSC Girder[1],FOB Superstructure[1]
526 Finishing Works 72 days Sun 26-04-20 Mon 20-07-20 525 FOB Finishing[1]
527 CH 378+740 IC Main Structure 335 days Mon 24-06-19 Thu 02-07-20
528 Foundation 110 days Mon 24-06-19 Tue 19-11-19 47,484FS+100 daysFOB Foundation[1]
529 Sub Structure 100 days Fri 20-09-19 Sun 29-12-19 528SS+50 days FOB Substructure[1]
530 Super Structure 125 days Sun 29-12-19 Sat 02-05-20 529 FOB PSC Girder[1],FOB Superstructure[1]
531 Finishing Works 60 days Sat 02-05-20 Thu 02-07-20 530 FOB Finishing[1]
532 CH 378+740 IC VUP 181 days Fri 20-09-19 Thu 19-03-20
533 Foundation 35 days Fri 20-09-19 Fri 25-10-19 47,528SS+50 days
534 Sub Structure 36 days Fri 25-10-19 Sat 30-11-19 533
535 Super Structure 55 days Sat 30-11-19 Fri 24-01-20 534
536 Finishing Works 55 days Fri 24-01-20 Thu 19-03-20 535
537 Drain (From 355+000 To 378+740) 270 days Fri 26-06-20 Sat 20-03-21

538 Longitudinal Drain 220 days Fri 26-06-20 Fri 29-01-21 51FS+450 days Longitudinal Drain[20,130.91]

539 Median Drain 150 days Wed 28-10-20 Sun 28-02-21 51FS+450 days,538FF+30
Media days
Drain[20,130.91]

540 Ravine Area Treatment 270 days Fri 26-06-20 Sat 20-03-21 51FS+450 days Ravine Area Treatment[20,130.91]

541 Slope Protection 150 days Fri 13-11-20 Sat 20-03-21 51FS+400 days,540FF
Drainage - Slope Protection[20,130.91]

542 RE Wall (From 355+000 To 378+740) 310 days Thu 27-02-20 Wed 06-01-21
543 RE Wall Casting 250 days Thu 27-02-20 Sat 21-11-20 51FS+330 days RE Wall Panel Casting[20,130.91]

544 RE Wall Erection 250 days Sat 28-03-20 Mon 14-12-20 51FS+360 days,543FF+30
RE Walldays
Panel Erection[20,130.91]

545 Toe Wall/R Wall 150 days Sat 12-09-20 Wed 06-01-21 51FS+420 days,544FF+30
Toe Wall/Rwall[20,130.91]
days

546 Project Facilities (From 355+000 To 378+740) 510 days Wed 30-10-19 Sat 20-03-21

547 Road Side Furniture 330 days Thu 27-02-20 Fri 22-01-21 32,51SS+330 days,49

548 Signages 210 days Fri 04-09-20 Thu 18-02-21 51FS+480 days Road Furniture Signages[23,740]

549 Road Marking 210 days Mon 31-08-20 Sat 13-02-21 51FS+210 days,77SS+30
Road days,127SS+30
Furniture Road days,204SS+30
Markings[23,740]
days,355SS+30 days,450SS+30 days,285SS+30 days

550 Boundary Wall 180 days Wed 27-05-20 Sun 06-12-20 51FS+420 days Road Furniture Boundary Wall[23,740]

551 Irrigation 280 days Wed 27-05-20 Sun 28-02-21 51FS+420 days Road Furniture Irrigation[23,740]

552 Street Lighting 360 days Wed 30-10-19 Fri 13-11-20 32,51FS+210 days Road Furniture street lightning procurement & installation[23,740]

553 Chain Link Fencing 360 days Wed 30-10-19 Fri 13-11-20 32,51FS+210 days Road Furniture ChainLink Fencing[23,740]

554 Lanscaping and Tree plantation 180 days Tue 13-10-20 Wed 10-03-21 32,51FS+450 days,78SS+10
Road Furniture
days,128SS+10
Plantation[23,740]
days,205SS+10 days,356SS+10 days,451SS+10 days

555 Noise Barrier 510 days Wed 30-10-19 Sat 20-03-21 32,51FS+210 days Road Furniture Noise Barrier Installation[23,740]

556 Metal Beam Crash Barrier 480 days Sat 02-11-19 Sun 21-02-21 32,51FS+213 days Road Furniture Metalbeam procurement & instalation[23,740]

557 Telecom System 210 days Fri 26-06-20 Fri 22-01-21 32,51FS+450 days ATMS[1]

558 Project Completion 150 days Sat 21-11-20 Tue 30-03-21

559 Schedule I Test on Completion 30 days Sat 21-11-20 Mon 14-12-20 178FF,508,507,510,511,516,521,526,531,536

560 Issue of Provisional Completion Cerfificate 1 day Sun 13-12-20 Mon 14-12-20 559FF,52,77

561 Completion of Punch List Items as per schedule 90 days Fri 25-12-20 Mon 15-03-21 560FS+15 days,86,87,92,97,102,130,131,136,141,146,151,156,161,166,172,213,214,219,224,229,234,239,244,249,254,259

562 Submission of As-built drawings 60 days Fri 25-12-20 Sat 13-02-21 561SS,294,295,300,305,310,325,330,369,374,380,385,390,395,400,457,459,464,469

563 Issue of Completion Certificate 0 days Tue 30-03-21 Tue 30-03-21 561FS+15 days,541,547,548,549,550,551,552,553,554,555,556,557,559,560,562,538,539,540,543,544,545,507,508,481,479,480,450,451,84,127,128,179,204,205,211,292,315,320,355,356,362,364,406,405,411,412,417,418,423,424,53,103,180,260,331,425,482,537,542,546 30-03

Project: Vadodara Mumbai Expres Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Tue 05-03-19 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress