You are on page 1of 5

PACKAGES LTD.

Prepared By: Sheraz

JOB SAFETY ANALYSIS (Demin water line connection)

Date: 28.06.2022

POTENTIAL HAZARD SEVERITY / CONSEQUENCES CONTROL MEASURE


SR. JOB STEPS
(What can cause harm?) (What can go wrong?) (What can be done to prevent it from going wrong?)
#
a. Hot work permit is required before starting the
job outside /inside confined space.
i. Fire Watch required
ii. Fire Extinguisher should be located at
work site.
iii. All hand tools Hammer, chisel, power
tool, welding machine, and grinder
should be in proper and good condition.
b. Crane engine and welding plants shall have
- Electrical shock - Injury Ground Fault Circuit Interrupter (GFCI).
- Fire - Burn i. Fire Blanket should be used for spark
- parts (cutting and grinding m/c) - Explosion protection
01 Hot Work
- Power tools - Property damage ii. Electrical cables, Socket and other
- Smoke - Reparatory disorder gauges should be in good condition and
double cored.
iii. Grinding must be used with guards. Electrical
cables must be secured to avoid tripping hazard.
iv. Safety Glasses, Face shields, Welding
screens, and Hand gloves must be worn
by users
v. Gas cylinders must be secured, on trolley
with chain and cap.
a. Cylinder’s hoses, gauges & regulators must
be in working condition.
02 Work at Height 1. Falling hazards of: - Personal injury and property a. Platform should be erected under supervision.
a. Material damage b. Damaged components of platform should not be
b. Spares used.
c. Platform c. Area should be barricaded while dismantling.
d. Personnel Platform should be free from any loose materials.
d. Guard rails should be erected on platform. Fall
PACKAGES LTD.

Prepared By: Sheraz

JOB SAFETY ANALYSIS (Demin water line connection)

Date: 28.06.2022

protection Equipment Safety Harness,


- Electric shock - Pre-user inspection
- Dust - Wetting area before work
- Noise - Personal injury - Use of air Muff
Digging and filling of - Vibration - Respiratory issues - Job rotation
03
floor - Skin issue - Hearing issue - Skilled persons
- Hand effects - Issue of PTW
- Proper PPE
- Barricades the area.
- Skilled person
- Recommended lifting accessories
- Material falling - Proper barricading and warning signs
- Personnel injury
04 Material lifting - Mechanical failure of lifter - Restriction of unauthorized persons in area.
- property damage
- falling guarder - Proper barricading around the crane along the
length of the boom.

- Area should be clear


- Proper house keeping
- Slipping hazard
- Injury hazard - Keep material at proper place
05 Housekeeping - Tripping hazard
- Avoid the spillage of liquids
- Falling hazard
- Turn off temporary or permanent lighting when
not required
- Prohibition signs
- Warning Signs
06 Safety Signs - - - Mandatory signs
- Safe condition signs
- First aid/ Direction signs
- Air pollution - Proper ventilation of area
- Eye, nose, and throat - Job rotation during task
irritations
Dust, Dirt, smoke, - Air pollution
07 - Difficulty in breathing
odour - Health hazard
- Reduced lung function
- Asthma attacks
- Chest pain
PACKAGES LTD.

Prepared By: Sheraz

JOB SAFETY ANALYSIS (Demin water line connection)

Date: 28.06.2022

- Switch off all electrical equipments when not in


- Environmental pollution due operation.
08 Energy conservation - Depletion of natural resources
to burning of fossils fuels - Switch off all vehicles and plant when not being
used
- Use silencers
Noise produced by - Health hazard - Cause deafness
- Switch off noisy equipment when not in operation
9 vehicles and - Environment hazard - Noise pollution
- Use appropriate route for cranes and fork lifters
operations
- Use air plugs or muffs

- Use of PPE’S
- Fire extinguisher must be placed near the area
- During operation person, may where activity is being carried out
get injure - Area must be barricaded
- Injury
Use of Tools/ - Chances of fire - Only authorized persons will be allowed to enter
11 - Property damage
Equipment’s - Noise pollution - Pre-inspection of tools before use
- Health hazard
- Electric shock - Check electrical wires, insulation, plugs, sockets
before use by authorized skilled person
- Pre-inspection of hand tools e.g pliers, hammer,
grinder etc
Personnel injury due to:

3Being struck by or caught


- Inspectors will check that employers are
between materials or being
providing information and instruction to
caught in pinch points - Personal injury and
12 Material Handing workers to perform assigned tasks.
property damage
resulting in fractures and - Use of inspected and certified lifting equipment
- Ensure proper place is there for free movement
bruises - Area barricading and signage is being ensured.
- Lack of experience and
competence

-
- - -
16 Scaffolding (vehicles, - Unauthorized /untrained - personnel injury - only experienced, skilled and trained person
PACKAGES LTD.

Prepared By: Sheraz

JOB SAFETY ANALYSIS (Demin water line connection)

Date: 28.06.2022

should be allowed
- all hand tools should be inspected prior to start
of job
- scaffolding pipes with corrosion should not be
used
- check the straightness of pipes damaged or faulty
pipes should be separated for not use ground
surface should be leveled
- use wooden planks below base plates red tag
inexperienced personnel on the
must be placed/ hanged at the start of scaffolding
job
- scaffolders must use full body double lanyard
- uninspected tools
safety harness and should be properly hooked
scaffolding, materials, - uneven ground
where possible
pipes, joints, planks, - faulty/ poor condition
- ensure vertical pipes alignment and check it with
base plate, toe board scaffolding material
- property loss hand level
& etc.) Level strip, - improper scaffoldingerection
- - ensure all joints are properly tightened use
hammer, meter tap & - tag system not followed.
bracing pipes and outriggers pipes where
rope.) - fail to comply mandatory and
necessary
additionalppe’s
- ladder should be constructed at suitable place
- wrong material handling/ falling
and use drop bar for in/out point.
object
- all pipes extendedinworkers movement area
-
should be highlighted with barication tape.
- toe board, midtrial and guard rail are necessary
for a proper platform metal planks should be
properly placed on pipes with hooks and use
binding wire for binding where necessary there
should be no space between platform planks
- no person should go in drop zone.
- scaffolding area
-
- - -
- - -
- - -
PACKAGES LTD.

Prepared By: Sheraz

JOB SAFETY ANALYSIS (Demin water line connection)

Date: 28.06.2022

- - -
- Ensure workers are complying PPE’S
- Required.
- extinguisher must be present at all time
- light should be proper prior to start the
- hand injury/eye injury - Work.
Night Working - electric shock / - all power cables should be inspected and
Activities (Lights, electrocution - Insulated.
21 - Improper Illumination
Stands) - personal injury - lights should be installed over head height
- property loss - To avoid glaring to personal.
- - if generator use for electricity should be
- Properly grounded.
- all tower crane lights should be checked
- And use wherever necessary
-