SUPERSTRUCTURE
1 RCC RAILING 2 28.350 0.300 1.250 2.500 KN/M 141.750 1.000 141.75 KN
2 RCC CRASH BARRIER 2 28.350 0.500 0.900 25.000 KN/M^3 510.300 1.000 510.3 KN
3 WEARING COAT 1 28.350 14.500 0.053 22.000 KN/M^3 822.150 1.000 822.15 KN
4 DECK SLAB 1 28.350 14.500 0.220 25.000 KN/M^3 2260.913 1.000 2260.9125 KN
5 LONGI. GIRDER 5 28.350 - - 25.000 KN/M^3 614.000 5.000 3070 KN
TOTAL = 680.51125 T
SUBSTRUCTURE
TOTAL = 358.600 T
DUE TO FORCE LA M
1 RCC RAILING 2 29.300 0.300 1.250 2.500 KN/M 146.500 1.000 146.5 KN
2 RCC CRASH BARRIER 2 29.300 0.500 0.900 25.000 KN/M^3 527.400 1.000 527.4 KN
3 WEARING COAT 1 29.300 14.500 0.065 22.000 KN/M^3 849.700 1.000 849.7 KN
5 DECK SLAB 1 29.300 14.500 0.220 25.000 KN/M^3 2336.675 1.000 2336.675 KN
6 LONGI. GIRDER 4 29.300 - - 25.000 KN/M^3 735.000 5.000 3675 KN
7 END CROSS GIRDER 2 14.500 - - 25.000 KN/M^3 735.000 5.000 3675 KN
8 MIDDLE CROSS GIRDER 1 14.5
TOTAL = 753.5275 T
TOTAL = 792.694 T
183.333333333
MOMENT AT PILE TOP
DUE TO FORCE LA M
8*1*2.5
6.2*1*2.5
MID SUPPORT FLARE
A= 1.08
A1 = 0.135 A1 = 0.135 m^2
A2 = 0.015 A2 = 0.0825 m^2
A3 = 0.015 A3 = 1.14375 m^2
A4 = 0.285 A= 1.36125 m^2
A5 = 0.028125
A6 = 0.028125
A7 = 0.03
A8 = 0.075
A9 = 0.1875
A= 0.79875
L 4.3
B 4.3
A1 = 18.49 m2
A1/4 = 27.735 m3
Pile
A= 0.78 m2
19.11 m3
A1/4-A = 26.955 m2
1010.813 KN