Professional Documents
Culture Documents
If production cannot be interrupted for any reason but local isolation can
be achieved and 100% positive isolation at valves with spades installed
then it will be possible to cold cut the pipe. There are a number of actions
that need to be carried out.
Raise permit
Erect scaffold platform
Crane in place to lift up cutting machine
In case of valve let by install spade at tie-in 002B
Set up cutting machine
Gas test area
Perform first cut
Measure and mark up for second cut
Set up machine
Cut and prep pipe
Install inline weld and test plug
Set up rigging gear
Lift up 20” RFWN flg (weight approx 172Kg)
Set up butt for welding
Weld butt
Hydrotest flange
Remove inline weld and test plug and lower to grade
Remove cutting machine from scaffold and lower to grade
Crane lift pre-fabricated spool into place and bolt up.
Retain the spade at tie-in 002B and insert another at tie-in 002A