H. Kebutuhan Material

1. Pondasi Bored Pile


Table 14. koefisien Material Mutu Beton

Volume beton cair = Volume bored pile – berat besi


24.000 kg – 2.448,192 kg
21.551,808 kg ~ 21,551 m3
Kebutuhan material beton fc’ 24 Mpa per 1 m3
a) Semen = 21.551,808 kg x 406 kg
8.749,706 kg
Jumlah zak = 8.749,706 kg
50 kg/ zak
174,9 zak ~ 175 zak
b) Pasir = 21.551,808 kg x 684 kg
14.741,436 kg ~ 14,7 m3
c) Kerikil = 21.551,808 kg x 1026 kg
22.112,155 kg ~ 22 m3
d) Air = 21.551,808 kg x 215 l
4.433,638 liter
59

2. Abutment
Table 15. Koefisien Material Mutu Beton

Volume beton cair = Volume abutment – berat besi


77.320 kg – 29.285 kg
48.035 kg ~ 48 m3
Kebutuhan material beton fc’ 24 Mpa per 1 m3

a) Semen = 48.035 kg x 406 kg


19.502,210 kg
Jumlak zak = 19.502,210 kg
50 kg/ zak
390 zak
b) Pasir = 48.035 kg x 684 kg
32.855,940 kg ~ 33 m3
c) Kerikil 48.035 kg x 1026 kg
49.283,910 kg ~ 49,3 m3
d) Air = 48.035 kg x 215 l
10.327,525 liter
60

3. Bangunan Atas Jembatan


Table 16. Koefisien Material Mutu Beton

Volume beton cair = Volume bangunan atas – berat besi


62.400 kg – 16.404,190 kg
45.995 kg ~ 46 m3
Kebutuhan material beton fc’24 Mpa per 1 m3

a) Semen = 45.995 kg x 406 kg


18.673,970 kg
Jumlah zak = 18.673 ,970 kg
50 kg / zak
374 zak
b) Pasir = 45.995 kg x 684 kg
31.460,580 kg ~ 32 m3
c) Kerikil = 45.995 kg x 1026 kg
47.190,870 kg ~ 47 m3
d) Air = 45.995 kg x 215 l
79.888,925 liter