The document provides calculations to determine material requirements for different components of a construction project including bored piles, abutments, and the superstructure of a bridge. It calculates the volume of concrete needed for each component based on their dimensions and rebar weight. It then lists the quantity of cement, sand, gravel, and water needed to achieve the required concrete mix design based on industry standards. The quantities are provided in kilograms, cubic meters, liters and bags as appropriate for each material.
The document provides calculations to determine material requirements for different components of a construction project including bored piles, abutments, and the superstructure of a bridge. It calculates the volume of concrete needed for each component based on their dimensions and rebar weight. It then lists the quantity of cement, sand, gravel, and water needed to achieve the required concrete mix design based on industry standards. The quantities are provided in kilograms, cubic meters, liters and bags as appropriate for each material.
The document provides calculations to determine material requirements for different components of a construction project including bored piles, abutments, and the superstructure of a bridge. It calculates the volume of concrete needed for each component based on their dimensions and rebar weight. It then lists the quantity of cement, sand, gravel, and water needed to achieve the required concrete mix design based on industry standards. The quantities are provided in kilograms, cubic meters, liters and bags as appropriate for each material.
Volume beton cair = Volume bored pile – berat besi
24.000 kg – 2.448,192 kg 21.551,808 kg ~ 21,551 m3 Kebutuhan material beton fc’ 24 Mpa per 1 m3 a) Semen = 21.551,808 kg x 406 kg 8.749,706 kg Jumlah zak = 8.749,706 kg 50 kg/ zak 174,9 zak ~ 175 zak b) Pasir = 21.551,808 kg x 684 kg 14.741,436 kg ~ 14,7 m3 c) Kerikil = 21.551,808 kg x 1026 kg 22.112,155 kg ~ 22 m3 d) Air = 21.551,808 kg x 215 l 4.433,638 liter 59
2. Abutment Table 15. Koefisien Material Mutu Beton
Volume beton cair = Volume abutment – berat besi
77.320 kg – 29.285 kg 48.035 kg ~ 48 m3 Kebutuhan material beton fc’ 24 Mpa per 1 m3
a) Semen = 48.035 kg x 406 kg
19.502,210 kg Jumlak zak = 19.502,210 kg 50 kg/ zak 390 zak b) Pasir = 48.035 kg x 684 kg 32.855,940 kg ~ 33 m3 c) Kerikil 48.035 kg x 1026 kg 49.283,910 kg ~ 49,3 m3 d) Air = 48.035 kg x 215 l 10.327,525 liter 60
3. Bangunan Atas Jembatan
Table 16. Koefisien Material Mutu Beton
Volume beton cair = Volume bangunan atas – berat besi
62.400 kg – 16.404,190 kg 45.995 kg ~ 46 m3 Kebutuhan material beton fc’24 Mpa per 1 m3
a) Semen = 45.995 kg x 406 kg
18.673,970 kg Jumlah zak = 18.673 ,970 kg 50 kg / zak 374 zak b) Pasir = 45.995 kg x 684 kg 31.460,580 kg ~ 32 m3 c) Kerikil = 45.995 kg x 1026 kg 47.190,870 kg ~ 47 m3 d) Air = 45.995 kg x 215 l 79.888,925 liter