Project EMIRATES FEDERATION OF WRESTLING AND JUDO – PLOT NO: P14 SECTOR BANIYAS NORTH 1 Date 04th OF JULY,2022
Client U.A.E WRESTLING JUDO & JIU JITSU FEDERATION Consultant STH – SOCIETY TECHNOLOGY HOUSE L.L.C
Employer U.A.E WRESTLING JUDO & JIU JITSU FEDERATION Contractor ALLOLOA AL MUTALIQHA CONTRACTING AND GENERAL MAINTENANCE L.L.C
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
1 XLPE and FP400 Cables are missing and not Delivered. CABLES AND CABLES LV ROOM
Below cables as per ADDC Approval to be provided: SUPPORT SYSTEMS (BILL
NO 18.7)
⎯ 2X4C (FP400) Cable from MDB Panel to ATS
Panel is missing.
⎯ 2X4C (FP400) Cable from ATS Panel to SMDB-
E is missing. The Power cables
⎯ 2X4C (FP400) Cable from Generator to ATS in site are
Panel is missing. temporary, final
⎯ 1X4C (XLPE /SWA/LSF) Cable from MDB to cables to approved
SMDB-101 is missing and delivered as
⎯ 3X4C (XLPE /SWA/LSF) Cable from MDB to per ADDC
SMDB-102 is missing Approval.
⎯ 1X4C (XLPE /SWA/LSF) Cable from MDB to
SMDB-103 is missing ADDC
⎯ 2X4C (XLPE /SWA/LSF) Cable from MDB to REQUIREMENT
SMDB-201 is missing
⎯ 1X4C (FP400) Cable from MDB to FIRE PUMP
(200A TP Isolator) is missing
⎯ 1X4C (XLPE /SWA/LSF) Cable to CAPACITOR
BANK PANEL is missing
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 1
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
2 MDB Panel (FORM B - TYPE 6) is missing and not LV SWITCH GEAR AND LV ROOM
installed with all accessories and breakers: DB'S (BILL NO 18.6)
⎯ MCCB BREAKERS
⎯ ACB BREAKER All accessories
⎯ BUSBARS (lugs, glands…) not
⎯ ACCESSORIES provided yet.
ADDC
REQUIREMENT
3 Capacitor Bank (200 KVAR) Panel/Harmonic Filters is CAPACITOR BANKS (BILL LV ROOM
missing and not installed NO 18.4)
ADDC
REQUIREMENT
4 SMDB-E is not installed properly and not fully LV SWITCH GEAR AND LV ROOM
terminated DB'S (BILL NO 18.6)
CABLES AND CABLES SMDB-E should be
SUPPORT SYSTEMS (BILL connected using
NO 18.7) FP400 Cable as per
Approval.
ADDC
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 2
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
5 FDB wire dressing, breakers and labeling are not done LV SWITCH GEAR AND LV ROOM
DB'S (BILL NO 18.6)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIREMENT
7 Fire Alarm Addressable Dual Input Module for FM-200 FIRE ALARM SYSTEM (BILL LV ROOM
Interfacing is not fixed nor terminated. NO 19.1)
CIVIL DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 3
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
8 Power Supply for the split units is missing SMALL POWER WIRING LV ROOM
ACCESSORIES (BILL NO
18.8)
ADDC
REQUIREMENT
9 ⎯ Earthing for all equipment’s inside LV Room is EARTHING SYSTEM (BILL LV ROOM
not done NO 18.11)
⎯ 1XC ECC from MDB to all SMDB’s are missing LV SWITCH GEAR AND
and not provided. DB'S (BILL NO 18.6)
⎯ 1XC ECC from all SMDB to all Connected AUTOMATIC TRANSFER
SMDB’s and FDB’s, Isolators … are missing and SWITCH -ATS (BILL NO
not provided. 18.3)
CAPACITOR BANK (BILL
NO 18.4)
ADDC
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 4
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
10 Fire Addressable Dual Input Module (3Nos) for Fire FIRE ALARM SYSTEM (BILL PUMP ROOM
Pump Interfacing is not fixed nor terminated. NO 19.1)
CIVIL DEFENSE
REQUIREMENT
11 Fire Addressable Input Module not fixed nor FIRE ALARM SYSTEM (BILL PUMP ROOM
terminated. NO 19.1)
CIVIL DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 5
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
12 The Transformer is missing and not installed LV SWITCH GEAR AND TRANSFORMER ROOM
(Transformer Room is Empty). DB'S (BILL NO 18.6)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIREMENT
13 LV Cables from Transformer to the MDB are missing CABLES AND CABLES TRANSFORMER ROOM
and not laid: SUPPORT SYSTEMS (BILL
⎯ 7X1C,630mm2 XLPE/AWA/LSF (AS PER NO 18.7)
ADDC).
ADDC
REQUIREMENT
14 ⎯ Fire Addressable Dual Input Module for Water FIRE ALARM SYSTEM (BILL TRANSFORMER ROOM
Spray System Interfacing is not fixed nor NO 19.1)
terminated.
⎯ Fire Addressable Input Module is not fixed nor
terminated.
CIVIL DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 6
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
15 The TRM is missing and not installed TRM ROOM
ADDC
REQUIREMENT
16 Fire Addressable Dual Input Module for FM-200 FIRE ALARM SYSTEM (BILL TRM ROOM
Interfacing is not fixed nor terminated. NO 19.1)
CIVIL DEFENSE
REQUIREMENT
17 External Fire alarm Sounder and Flasher (WP) are not FIRE ALARM SYSTEM (BILL TRM ROOM – OUTSIDE
installed NO 19.1) WALL
CIVIL DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 7
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
18 ⎯ Generator only placed inside room without DIESEL GENERATOR - GENERATOR ROOM
any assembling nor connecting any parts 400KVA 0.8 P. F-400V
⎯ Fuel Tank to be for 12 hours. (BILL NO 18.2)
ADDC
REQUIREMENT
19 Generator Battery & Battery Chargers are not DIESEL GENERATOR - GENERATOR ROOM
connected 400KVA 0.8 P. F-400V
(BILL NO 18.2)
ADDC
REQUIREMENT
20 ⎯ Breaker is not connected with the cables DIESEL GENERATOR - GENERATOR ROOM
⎯ 2X4C (FP400) Cable from Generator to ATS is 400KVA 0.8 P. F-400V
missing. (BILL NO 18.2)
ADDC
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 8
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
21 Flexible Connection is not connected DIESEL GENERATOR - GENERATOR ROOM
400KVA 0.8 P. F-400V
(BILL NO 18.2)
ADDC
REQUIREMENT
22 Exhaust Pipe and Muffler are not connected DIESEL GENERATOR - GENERATOR ROOM
400KVA 0.8 P. F-400V
(BILL NO 18.2)
ADDC
REQUIREMENT
23 Discharge Louver with GI Duct is not installed DIESEL GENERATOR - GENERATOR ROOM
400KVA 0.8 P. F-400V As per approved
(BILL NO 18.2) material delivery
note Discharge
Louver with
minimum required
free opening area
behind the
Generator.
ADDC
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 9
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
24 Fire Alarm Addressable Dual Input Module for FOAM FIRE ALARM SYSTEM BILL GENERATOR ROOM
Interfacing is not fixed nor terminated. NO 19.1)
CIVIL DEFENSE
REQUIREMENT
ADDC
REQUIREMENT
26 External Fire Alarm Sounder and Flasher (WP) are not FIRE ALARM SYSTEM BILL SERVICE BLOCK - OUT SIDE
installed NO 19.1) PUMP ROOM
CIVIL DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 10
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
27 External earthing/Lighting Protection PITs are not EARTHING SYSTEM (BILL SERVICE BLOCK -EXTERNAL
done NO 18.11)
ADDC
REQUIREMENT
28 Pole foundation cable is not pulled SMALL POWER WIRING SERVICE BLOCK -EXTERNAL
ACCESSORIES (BILL NO
18.8)
ADDC
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 11
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
29 All Incoming cables from MDB to the SMDB’s are CABLES AND CABLES ELE-1
missing SUPPORT SYSTEMS (BILL
All Incoming cables from SMDB’S to the FDB’s are NO 18.7)
missing
ADDC
REQUIREMENT
30 SMDB’s and FDB’s are not fully terminated nor labeled CABLES AND CABLES ELE-1
SUPPORT SYSTEMS (BILL
NO 18.7)
SMALL POWER WIRING
ACCESSORIES (BILL NO
18.8) ADDC
REQUIREMENT
31 Wires are not Fully managed and not terminated and SMALL POWER WIRING ELE-1
not labeled ACCESSORIES (BILL NO
18.8)
ADDC
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 12
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
32 SMDB’s and FDB’s Breakers not Fully terminated CABLES AND CABLES ELE-1
SUPPORT SYSTEMS (BILL
NO 18.7)
SMALL POWER WIRING
ACCESSORIES (BILL NO
18.8) ADDC
REQUIREMENT
33 All Lighting Control Panels (4Nos) Components are LIGHTING CONTROL ELE-1
missing and not provided. SYSTEM (BILL NO 20.6)
All Lighting Control DB’s not terminated.
ADDC
REQUIREMENT
34 All Incoming cables from MDB to the SMDB’s are CABLES AND CABLES ELE-2
missing SUPPORT SYSTEMS (BILL
All Incoming cables from SMDB’S to the FDB’s are NO 18.7)
missing
ADDC
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 13
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
35 SMDB’s and FDB’s are not fully terminated nor labeled CABLES AND CABLES ELE-2
SUPPORT SYSTEMS (BILL
NO 18.7)
SMALL POWER WIRING
ACCESSORIES (BILL NO
18.8)
ADDC
REQUIREMENT
36 Wires are not Fully managed and not terminated and SMALL POWER WIRING ELE-2
not labeled ACCESSORIES (BILL NO
18.8)
ADDC
REQUIREMENT
37 SMDB’s and FDB’s Breakers not Fully terminated CABLES AND CABLES ELE-2
SUPPORT SYSTEMS (BILL
NO 18.7)
SMALL POWER WIRING
ACCESSORIES (BILL NO
18.8) ADDC
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 14
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
38 All Lighting Control Panels (3Nos) Components are LIGHTING CONTROL ELE-2
missing and not provided. SYSTEM (BILL NO 20.6)
All Lighting Control DB’s not terminated.
ADDC
REQUIREMENT
39 All Incoming cables from MDB to the SMDB’s are CABLES AND CABLES ELE-3
missing SUPPORT SYSTEMS (BILL
All Incoming cables from SMDB’S to the FDB’s are NO 18.7)
missing
ADDC
REQUIREMENT
40 SMDB’s and FDB’s are not fully terminated nor labeled CABLES AND CABLES ELE-3
SUPPORT SYSTEMS (BILL
NO 18.7)
SMALL POWER WIRING
ACCESSORIES (BILL NO
18.8)
ADDC
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 15
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
41 Wires are not Fully managed and not terminated and SMALL POWER WIRING ELE-3
not labeled ACCESSORIES (BILL NO
18.8)
ADDC
REQUIREMENT
42 SMDB’s and FDB’s Breakers not Fully terminated CABLES AND CABLES ELE-3
SUPPORT SYSTEMS (BILL
NO 18.7)
SMALL POWER WIRING
ACCESSORIES (BILL NO
18.8) ADDC
REQUIREMENT
43 All Lighting Control Panels (5Nos) Components are LIGHTING CONTROL ELE-3
missing and not provided. SYSTEM (BILL NO 20.6)
All Lighting Control DB’s not terminated.
ADDC
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 16
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
44 All Lighting Control Panels (1No) Components are LIGHTING CONTROL GUARD ROOM N/A - ROOM DOES NOT EXIST
missing and not provided. SYSTEM (BILL NO 20.6) YET
45 42U IDF Rack + 4KVA UPS are missing: STRUCTURE CABLING TEL-1 ROOM
⎯ Rack assembling inside room not done SYSTEM (BILL NO 20.1)
⎯ Horizontal cable managers inside rack to be
installed.
⎯ Fiber Patch Panels are to be installed and
terminated
⎯ UTP Patch Panels to be installed and
terminated
⎯ Patch cords to be provided.
⎯ PDU’s to be provided.
⎯ Cable tray behind the rack not completed.
46 42U IDF Rack + 4KVA UPS are missing: STRUCTURE CABLING TEL-2 ROOM
⎯ Rack assembling inside room not done SYSTEM (BILL NO 20.1)
⎯ Horizontal cable managers inside rack to be
installed.
⎯ Fiber Patch Panels are to be installed and
terminated
⎯ UTP Patch Panels to be installed and
terminated
⎯ Patch cords to be provided.
⎯ PDU’s to be provided.
⎯ Cable tray behind the rack not completed.
47 42U IDF Rack + 4KVA UPS are missing: STRUCTURE CABLING TEL-3 ROOM
⎯ Rack assembling inside room not done SYSTEM (BILL NO 20.1)
⎯ Horizontal cable managers inside rack to be
installed.
⎯ Fiber Patch Panels are to be installed and
terminated
⎯ UTP Patch Panels to be installed and
terminated
⎯ Patch cords to be provided.
⎯ PDU’s to be provided.
⎯ Cable tray behind the rack not installed.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 17
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
48 42U MDF Rack STRUCTURE CABLING MTR ROOM
⎯ Rack assembling inside room not done SYSTEM (BILL NO 20.1)
⎯ Horizontal cable managers inside rack to be
installed.
⎯ Fiber Patch Panels are to be installed and ADDC
terminated REQUIREMENT
⎯ Patch cords to be provided.
⎯ PDU’s to be provided.
⎯ Cable tray for the rack not installed.
49 Incoming Power Cables for the isolators are missing ISOLATING SWITCHES GSM ROOM GF
Isolators Termination to be done (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIREMENT
50 Earth Manholes are not done in all site plan areas EARTHING SYSTEM (BILL SITE PLAN
NO 18.11)
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 18
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
51 Lightning Protection Manholes are not done for all site EARTHING SYSTEM (BILL SITE PLAN
plan areas NO 18.11)
52 Etisalat fiber from JRC-12 Manhole to the Main STRUCTURE CABLING JRC-12 TO MTR
Telecom Room is not laid nor terminated SYSTEM (BILL NO 20.1)
53 Lighting Control System PC is not installed LIGHTING CONTROL FIRE COMMAND ROOM
SYSTEM (BILL NO 20.6)
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 19
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
54 Lighting Control RJ-45 single outlet is not done STRUCTURED CABLING FIRE COMMAND ROOM
SYSTEM
55 Lighting Control 2Gang Switch not installed LIGHTING SWITCHES (BILL MEETING ROOM -GF
Lighting Control 2Gang Switch not installed NO 18.10) MEETING ROOM -FF
Lighting Control 1Gang Switch not installed RECEPTION/SETTING AREA
Lighting Control 1 Gang Switch in Setting Area is not SETTING AREA
installed
56 Lighting Control Sensors (Ceiling Mounted) in all LIGHTING CONTROL ALL AREAS (E.G. ALL
locations are not installed. SYSTEM (BILL NO 20.6) CORRIDORS)
None is installed
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 20
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
57 Lighting Control Sensors (Wall Mounted) in all LIGHTING CONTROL ALL AREAS E.G: JUDO HALL
locations are not installed. SYSTEM (BILL NO 20.6) (6NOS)
None is installed
58 Lighting Control Switch interface in electrical rooms LIGHTING CONTROL ELECTRICAL ROOM GF-FF
are not installed SYSTEM (BILL NO 20.6)
59 Lighting Control Switch interface in Stair are not LIGHTING CONTROL STAIR -1
installed SYSTEM (BILL NO 20.6) STAIR-2
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 21
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
60 Lighting Control Switch interface in Male judo Training LIGHTING CONTROL MALE JUDO TRAINING HALL
Hall (2NOS) is not installed SYSTEM (BILL NO 20.6)
61 Lighting Control Switch interface in Female judo LIGHTING CONTROL FEMALE JUDO TRAINING
Training Hall (2NOS) is not installed SYSTEM (BILL NO 20.6) HALL
62 Lighting Control Photo cell in guard room Roof is not LIGHTING CONTROL GUARD ROOM ROOF N/A - ROOM DOES NOT EXIST
installed SYSTEM (BILL NO 20.6) YET
63 Single Data Outlet in LV Room is missing and cable not STRUCTURE CABLING LV ROOM
pulled SYSTEM (BILL NO 20.1)
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 22
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
64 Single Data Outlet in Generator Room is missing and STRUCTURE CABLING GENERATOR ROOM
cable not pulled SYSTEM (BILL NO 20.1) PUMP ROOM
TRANSFORMER ROOM
(SUBJECT TO ADDC
APPROVAL)
65 Earthing for all equipment’s inside All Electrical rooms EARTHING SYSTEM (BILL ELE-1
are not done NO 18.11) ELE-2
ELE-3
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 23
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
66 Clean earthing in all TEL ROOM’s is not done. CLEAN EARTHING SYSTEM TEL-1
(BILL NO 18.11.2) TEL-2
TEL-3
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 24
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
67 Clean Earthing in MTR ROOM is not done. CLEAN EARTHING SYSTEM MTR ROOM
(BILL NO 18.11.2)
ADDC
REQUIRMENT
68 Clean Earthing in SERVER ROOM is not done. CLEAN EARTHING SYSTEM SERVER ROOM
(BILL NO 18.11.2)
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 25
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
69 Clean Earthing in GSM ROOM is not done. CLEAN EARTHING SYSTEM GSM ROOM
(BILL NO 18.11.2)
ADDC
REQUIRMENT
70 Earthing for all Mechanical Exposed equipment’s is EARTHING SYSTEM (BILL ROOF
not done NO 18.11)
ADDC
REQUIRMENT
71 Public Address Rack including all equipment’s: VOICE EVACUATION & FIRE COMMAND ROOM
⎯ Master Panel PUBLIC ADDRESS SYSTEM
⎯ Power Amplifier Modular (BILL NO 19.3)
⎯ battery Backup All Public Address
⎯ AM/FM Tuner Material Not
Delivered including
⎯ Blu Ray Player
All Cables.
⎯ All Cables
are missing and not installed inside Fire Command
CIVIL DEFENSE
Room.
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 26
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
72 Public Address Touch Paging Station is missing and not VOICE EVACUATION & TICKET COUNTER
installed (CAT6 Cables for the paging station is not PUBLIC ADDRESS SYSTEM
pulled nor terminated) (BILL NO 19.3)
All Public Address
Material Not
Delivered including
All Cables.
73 Public Address Touch Paging Station is missing and not VOICE EVACUATION & FEMALE JUDO TRAINING
installed (CAT6 Cables for the paging station is not PUBLIC ADDRESS SYSTEM HALL RECEPTION
pulled nor terminated) (BILL NO 19.3)
All Public Address
Material Not
Delivered including
All Cables.
74 Public Address Touch Paging Station is missing and not VOICE EVACUATION & MALE JUDO TRAINING HALL
installed (CAT6 Cables for the paging station is not PUBLIC ADDRESS SYSTEM RECEPTION
pulled nor terminated) (BILL NO 19.3)
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 27
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
75 Public Address Touch Paging Station is missing and not VOICE EVACUATION & VIP RECEPTION
installed (CAT6 Cables for the paging station is not PUBLIC ADDRESS SYSTEM
pulled nor terminated) (BILL NO 19.3)
All Public Address
Material Not
Delivered including
All Cables.
76 Public Address Touch Paging Station is missing and not VOICE EVACUATION & FIRE COMMAND ROOM
installed (CAT6 Cables for the paging station is not PUBLIC ADDRESS SYSTEM
pulled nor terminated) (BILL NO 19.3)
77 All Public address speakers (Ceiling Mounted) are VOICE EVACUATION & ALL APPLICABLE AREAS
missing and not installed. PUBLIC ADDRESS SYSTEM
(BILL NO 19.3) All Public Address
Material Not
Delivered including
All Cables.
CIVIL DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 28
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
78 All Public address speakers (Wall Mounted) are VOICE EVACUATION & STAIR -1 GF (1NO)
missing and not installed. PUBLIC ADDRESS SYSTEM STAIR -2 GF (1NO)
(BILL NO 19.3) All Public Address
Material Not
Delivered including
All Cables.
CIVIL DEFENSE
REQUIREMENT
79 All Public address speakers (Wall Mounted) are VOICE EVACUATION & JUDO HALL (4NOS)
missing and not installed. PUBLIC ADDRESS SYSTEM
(BILL NO 19.3)
All Public Address
Material Not
Delivered including
All Cables.
CIVIL DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 29
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
80 ⎯ Fire Alarm Control Panel Not terminated, FIRE ALARM SYSTEM (BILL FIRE COMMAND ROOM
cables not fully pulled to the panel and not NO 19.1)
interfaced with all related systems as per Fire Alarm Panel
approved shop drawings. Material Inspection
⎯ Interfacing module is not installed nor not submitted nor
terminated/Connected. approved.
⎯ 4 Loops (IN) not completed
⎯ 4 Loops (OUT) not completed CIVIL DEFENSE
⎯ 3 CRKT OUT for telephone jacks not REQUIREMENT
completed
⎯ 12 V DC Batteries (2Nos) are missing.
81 Smoke Detectors, Heat Detectors, Control Modules, FIRE ALARM SYSTEM (BILL ALL APPLICABLE AREAS
CIVIL DEFENSE
Monitor Modules, Manual Call Points, Smoke Detector NO 19.1)
ALL APPLICABLE AREAS REQUIREMENT
with Remote LED Indicator are all missing and not
installed.
82 Fire Alarm Sounders & Flashers / WP are Missing and FIRE ALARM SYSTEM (BILL ALL APPLICABLE AREAS CIVIL DEFENSE
not Installed NO 19.1) (WALL MOUNTED BUILDING ALL APPLICABLE AREAS REQUIREMENT
Cables for External Sounders & Flashers not pulled. EXTERNAL WALLS)
83 Fire Telephone Jacks are missing and not Installed FIRE TELEPHONE SYSTEM PUMP ROOM
(BILL NO 19.4)
CIVIL DEFENSE
REQUIREMENT
84 Fire Telephone Jacks (2Nos) are missing and not FIRE TELEPHONE SYSTEM STAIR -1
Installed (BILL NO 19.4)
CIVIL DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 30
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
85 Fire Telephone Jacks (2Nos) are missing and not FIRE TELEPHONE SYSTEM STAIR -2
Installed (BILL NO 19.4)
CIVIL DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 31
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
86 Fire Telephone Jacks are missing and not Installed FIRE TELEPHONE SYSTEM FIRE COMMAND ROOM
(BILL NO 19.4)
CIVIL DEFENSE
REQUIREMENT
87 Fire Telephone cabinet and Telephone Handsets are FIRE TELEPHONE SYSTEM FIRE COMMAND ROOM
missing and not installed. (BILL NO 19.4)
CIVIL DEFENSE
REQUIREMENT
88 ⎯ Central Battery Interface Modules are missing FIRE ALARM SYSTEM (BILL FIRE COMMAND ROOM
and interfacing is not done. NO 19.1)
Fire Alarm Panel
⎯ Water Spray System, FM-200, PUMP’s, Zone
Material Inspection
Control Valve Interfacing in not done.
not submitted nor
⎯ Public Address Interfacing not done approved.
CIVIL DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 32
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
89 2x12 core OM4 Fiber cable from Server room to IDF STRUCTURE CABLING SERVER ROOM – TEL-1
room is missing and not laid nor terminated inside SYSTEM (BILL NO 20.1)
Racks.
90 2x12 core OM4 Fiber cable from Server room to IDF STRUCTURE CABLING SERVER ROOM – TEL-2
room is missing and not laid nor terminated inside SYSTEM (BILL NO 20.1)
Racks.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 33
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
91 2x12 core OM4 Fiber cable from Server room to IDF STRUCTURE CABLING SERVER ROOM – TEL-3
room is missing and not laid nor terminated inside SYSTEM (BILL NO 20.1)
Racks.
92 2x24 core Single Mode Fiber cable from MTR Room to STRUCTURE CABLING MTR ROOM – SERVER
Server Room is missing and not laid nor terminated SYSTEM (BILL NO 20.1) ROOM
inside Racks.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 34
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
93 42U Rack (2Nos) + 6KVA UPS are missing: STRUCTURE CABLING SERVER ROOM
⎯ Rack assembling inside room not done SYSTEM (BILL NO 20.1)
⎯ Horizontal cable managers inside rack to be
installed.
⎯ Fiber Patch Panels are to be installed and
terminated
⎯ UTP Patch Panels to be installed and
terminated
⎯ Patch cords to be provided.
⎯ PDU’s to be provided.
⎯ Cable Trays for the rack are not installed.
94 Isolator (3Nos) are not terminated and Power cables ISOLATING SWITCHES SERVER ROOM
are pulled. (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7) ADDC
REQUIRMENT
95 Isolator (2Nos) are not terminated and Power cables ISOLATING SWITCHES MTR ROOM
are pulled. (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 35
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
96 Isolator (2Nos) are not terminated and Power cables ISOLATING SWITCHES GSM ROOM
are pulled. (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL ADDC
NO 18.7) REQUIRMENT
97 Isolator (1No) are not terminated and Power cables ISOLATING SWITCHES TEL -2
are pulled. (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL ADDC
NO 18.7) REQUIRMENT
98 Isolator (1No) are not terminated and Power cables ISOLATING SWITCHES TEL -3
are pulled. (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL ADDC
NO 18.7) REQUIRMENT
99 Fiber Cable to GSM Room is missing and not laid nor STRUCTURE CABLING GSM ROOM
terminated as per Approved Shop Drawings and SYSTEM (BILL NO 20.1)
Service Provider Requirements.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 36
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
100 All Active Components as per contract BOQ and Shop STRUCTURE CABLING SERVER ROOM
Drawings are missing and to be provided. SYSTEM (BILL NO 20.1) TEL-1 ROOM
TEL-2 ROOM
TEL-3 ROOM
MTR ROOM
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 37
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
101 All Ceiling WI-FI Access Points are missing and to be STRUCTURE CABLING ALL APPLICABLE AREAS
installed SYSTEM (BILL NO 20.1)
102 IDF -G03 Rack is missing and to be installed in Guard STRUCTURE CABLING GUARD ROOM N/A - ROOM DOES NOT EXIST
Room SYSTEM (BILL NO 20.1) YET
103 Dual Data Points (2Nos) are missing in guard room STRUCTURE CABLING GUARD ROOM N/A - ROOM DOES NOT EXIST
SYSTEM (BILL NO 20.1) YET
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 38
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
104 Isolators (W/P-IP65) for the SEF Fans on Roof are ISOLATING SWITCHES ROOF All roof activities
missing and to be installed (BILL NO 18.5) not started yet
CABLES AND CABLES First fix, second fix
SUPPORT SYSTEMS (BILL and third fix are all
NO 18.7) balanced.
ADDC
REQUIRMENT
105 Isolators (4NOS) are missing and to be installed ISOLATING SWITCHES FIRE COMMAND ROOM
(BILL NO 18.5)
ADDC
REQUIRMENT
106 All Electrical Containments (Trays/Trunks) for all roof CABLES AND CABLES ROOF
services are missing and to be installed. SUPPORT SYSTEMS (BILL All roof activities
NO 18.7) not started yet
First fix, second fix
and third fix are all
balanced.
107 Isolators (W/P-IP65) for the SPF Fans on Roof are ISOLATING SWITCHES ROOF All roof activities
missing and to be installed (BILL NO 18.5) not started yet
CABLES AND CABLES First fix, second fix
SUPPORT SYSTEMS (BILL and third fix are all
NO 18.7) balanced.
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 39
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
108 ⎯ TP W/P ISOLATOR for Jokey Pump is not ISOLATING SWITCHES PUMP ROOM
terminated (BILL NO 18.5)
⎯ 1X4C (FP400) Cable from MDB to FIRE PUMP CABLES AND CABLES
(200A TP Isolator) is missing SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIRMENT
109 TP W/P ISOLATOR for Diesel Engine Fire Pump is not ISOLATING SWITCHES PUMP ROOM
terminated (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIRMENT
110 DB is not terminated CABLES AND CABLES GUARD ROOM N/A - ROOM DOES NOT EXIST
SUPPORT SYSTEMS (BILL YET
NO 18.7) ADDC
SMALL POWER WIRING REQUIRMENT
ACCESSORIES (BILL NO
18.8)
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 40
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
111 XLPE /SWA/LSF & FP400 Cables from SMDB’s to FDB’s CABLES AND CABLES LV ROOM & ELECTRICAL
are missing. SUPPORT SYSTEMS (BILL ROOMS
⎯ SMDB-E NO 18.7)
• SMDB-E101
• SMDB-E102
• SMDB-E201
⎯ SMDB-101
⎯ SMDB-102
⎯ SMDB-103
⎯ SMDB -201
ADDC
REQUIRMENT
112 Fire Alarm Interfacing with Aspiration Air Sampling FIRE ALARM SYSTEM (BILL FIRE COMMAND ROOM
System is Missing NO 19.1)
Fire Alarm Panel
Material Inspection
not submitted nor
approved.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 41
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
113 IPTV Rack and Included equipment’s are missing and IPTV SYSTEM (BILL NO TEL-2
not Installed 20.2)
⎯ ETH SWITCH
⎯ T.OX SM PSU 120 W
⎯ T.OX DVBS /S2IP CI MUX
⎯ T.OX ENCODER
⎯ ITV MIDDLE WARE
⎯ VPN ROUTER
⎯ UPS UNIT
114 ⎯ Single RJ-45 Socket for IPTV is missing - LIFT STRUCTURE CABLING LIFT LOBBY-GF
LOBBY-GF SYSTEM (BILL NO 20.1) TICKET COUNTER
⎯ Single RJ-45 Socket for IPTV is missing - ENTRANCE LOBBY (LEFT
TICKET COUNTER WALL)
⎯ Single RJ-45 Socket for IPTV is missing - MEETING ROOM-GF
ENTRANCE LOBBY (LEFT WALL) MEETING ROOM-FF
⎯ Single RJ-45 Socket for IPTV is missing - LIFT LOBBY-FF
MEETING ROOM-GF WAITING AREA -FF
⎯ Single RJ-45 Socket for IPTV is missing -
MEETING ROOM-FF
⎯ Single RJ-45 Socket for IPTV is missing - LIFT
LOBBY-FF
⎯ Single RJ-45 Socket (2Nos) for IPTV is missing
- WAITING AREA -FF
115 IPTV Dish Antennas (3Nos) are missing IPTV SYSTEM (BILL NO ROOF
20.2) All roof activities
not started yet
First fix, second fix
and third fix are all
balanced.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 42
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
116 Lightning Protection (LPS) Components are missing: EARTHING SYSTEM (BILL ROOF
⎯ Air Terminals NO 18.11)
⎯ Earth Rods All roof activities
⎯ Cable Clamps not started yet
⎯ CU Copper Tape First fix, second fix
⎯ Square Tape Clamp and third fix are all
⎯ Non-Metallic DC Clip balanced.
⎯ And all Other LPS Components
117 Lighting Protection Test Points (TP) are not terminated EARTHING SYSTEM (BILL TRANSFORMER ROOM
NO 18.11)
118 Lighting Protection Test Points (TP) are not terminated EARTHING SYSTEM (BILL TRM ROOM
NO 18.11)
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 43
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
119 Lighting Protection Test Points (TP)(2Nos) are not EARTHING SYSTEM (BILL PUMP ROOM
terminated NO 18.11)
120 Lighting Protection Test Points (TP)(2Nos) are not EARTHING SYSTEM (BILL WATER TANKS AREA
terminated NO 18.11)
121 Lighting Protection Test Points (TP)(2Nos) cable not EARTHING SYSTEM (BILL WATER TANKS AREA
pulled are not terminated NO 18.11)
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 44
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
123 Cables not pulled/empty boxes SMALL POWER WIRING ALL OFFICES - FF
ACCESSORIES (BILL NO
18.8)
ADDC
REQUIRMENT
124 Power cables for Isolators are missing ISOLATING SWITCHES LIFT LOBBY-FF
Isolators for Low Pressure Fans are not terminated (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
ADDC
NO 18.7)
REQUIRMENT
125 Cables are missing from External Manholes CABLES AND CABLES SITE PLAN
SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 45
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
126 Cables are missing and pulled inside back boxes SMALL POWER WIRING FEMALE TRAINING HALL
ACCESSORIES (BILL NO
18.8)
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 46
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
127 Cables are missing and pulled inside back boxes SMALL POWER WIRING FEMALE TRAINING HALL -
ACCESSORIES (BILL NO TOILETS
18.8)
ADDC
REQUIRMENT
128 Power cables for Isolator are missing ISOLATING SWITCHES FEMALE TRAINING HALL -
Isolator for AC Equipment is not terminated (BILL NO 18.5) OFFICE
CABLES AND CABLES All Power cables
SUPPORT SYSTEMS (BILL for Isolator and the
NO 18.7) Isolators for AC
Equipment inside
Building are all not
pulled nor
terminated.
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 47
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
129 Floor Box Cable termination and covering plate not SMALL POWER WIRING FEMALE TRAINING HALL -
done ACCESSORIES (BILL NO OFFICE All Floor Box Cable
18.8) termination and
STRUCTURE CABLING covering plate are
SYSTEM (BILL NO 20.1) not done for all
project.
ADDC
REQUIRMENT
130 Cables are missing and pulled inside back boxes SMALL POWER WIRING MALE TRAINING HALL -
ACCESSORIES (BILL NO OFFICE
18.8)
ADDC
REQUIRMENT
131 Cables not terminated and managed SMALL POWER WIRING IT AND MEDIA ROOMS
ACCESSORIES (BILL NO
18.8)
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 48
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
133 Cables grouped and not pulled STRUCTURE CABLING SEVERAL AREAS (E.G JUDO
SYSTEM (BILL NO 20.1) HALL CORRIDOR – SERVERS
ROOM)
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 49
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
134 Cables not terminated/socket to be fixed SMALL POWER WIRING ALL OFFICES -GF
ACCESSORIES (BILL NO
18.8)
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 50
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
135 Cables not pulled inside back boxes SMALL POWER WIRING SECURITY ROOM – GF
Cables not terminated ACCESSORIES (BILL NO
18.8)
ADDC
REQUIRMENT
136 Central Battery System main panel is missing and not EMERGENCY LIGHTING FIRE COMMAND ROOM
installed SYSTEM (BILL NO 20.5)
137 Recessed mounted emergency light EMERGENCY LIGHTING ALL APPLICABLE AREAS ALL APPLICABLE AREAS NOT FIXED IN ALL
SYSTEM (BILL NO 20.5) SITE
CIVIL DEFENSE
REQUIREMENT
138 Surface mounted emergency light EMERGENCY LIGHTING ALL APPLICABLE AREAS ALL APPLICABLE AREAS NOT FIXED IN ALL
SYSTEM (BILL NO 20.5) SITE
CIVIL DEFENSE
REQUIREMENT
139 Exit light -above door EMERGENCY LIGHTING ALL APPLICABLE AREAS ALL APPLICABLE AREAS NOT FIXED IN ALL
SYSTEM (BILL NO 20.5) SITE
CIVIL DEFENSE
REQUIREMENT
140 Exit light -double sided EMERGENCY LIGHTING ALL APPLICABLE AREAS ALL APPLICABLE AREAS NOT FIXED IN ALL
SYSTEM (BILL NO 20.5) SITE
CIVIL DEFENSE
REQUIREMENT
141 Exit light -double sided EMERGENCY LIGHTING ALL APPLICABLE AREAS ALL APPLICABLE AREAS NOT FIXED IN ALL
SYSTEM (BILL NO 20.5) SITE
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 51
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
CIVIL DEFENSE
REQUIREMENT
142 Water Meters (as per BOQ NO 20.7) are missing and CENTRAL MONITORING TO BE AS PER MECHANICAL Water Meters
not connected SYSTEM (BILL NO 20.7) APPROVED SHOP (Data Logging Type
DRAWINGS to be confirmed) to
be approved by
REFER TO MECHANICAL Estidama
APPROVED SHOP DRAWING Independent Agent
and the Engineer.
ESTIDAMA
REQUIREMENT
143 Power Meters (as per BOQ NO 20.7) are missing and CENTRAL MONITORING ELECTRICAL ROOMS
Power Meter (Data
not connected SYSTEM (BILL NO 20.7)
Logging Type) to
be approved by
Estidama
Independent Agent
and the Engineer.
ESTIDAMA
REQUIREMENT
ESTIDAMA
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 52
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
145 Earthing cables are not terminated and not connected EARTHING SYSTEM (BILL MEP AREA
NO 18.11)
146 Power cables for Isolator are missing ISOLATING SWITCHES MEP AREA
Isolators for AC Equipment are not terminated (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7) ADDC
REQUIRMENT
147 Power Cables for the chillers and HVAC Equipment are CABLES AND CABLES MEP AREA
not pulled nor terminated SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 53
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
148 Power cables for Isolator are missing ISOLATING SWITCHES MEP AREA
Isolators for AC Equipment are not terminated (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7) ADDC
REQUIRMENT
149 Power cables for Isolator are missing ISOLATING SWITCHES MEP AREA
Isolators for AC Equipment are missing (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIRMENT
150 Power cables for Isolator are missing ISOLATING SWITCHES MEP AREA
Isolators for AC Equipment are missing (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 54
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
151 Power cables for Isolator are missing ISOLATING SWITCHES MEP AREA
Isolators for AC Equipment are missing (BILL NO 18.5)
CABLES AND CABLES
SUPPORT SYSTEMS (BILL
NO 18.7)
ADDC
REQUIRMENT
152 Exposed Mechanical Equipment’s Earthing is not done EARTHING SYSTEM (BILL MEP AREA
NO 18.11)
ADDC
REQUIRMENT
153 Earthing Termination point not done for all Street EARTHING SYSTEM (BILL SITE PLAN
Lights. NO 18.11)
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 55
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
154 Earthing Cable (ECC Cable) with Earth pit outside EARTHING SYSTEM (BILL TRM ROOM
service block not done NO 18.11) TRANSFORMER ROOM
LV ROOM
GENERATOR ROOM
PUMP ROOM
ADDC
REQUIRMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 56
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
155 Connection Cables between Down Conductor and EARTHING SYSTEM (BILL OUTSIDE SERVICE BLOCK
Earth termination network (earth terminals and LPS NO 18.11)
Pits) not completed.
156 Isolators for the following are all pending: ISOLATING SWITCHES MEP AREA
⎯ MEP AREA (BILL NO 18.5) MALE/FEMALE TOILET MEP AREA
MALE/FEMALE TOILET
⎯ MALE /FEMALE TOILET CABLES AND CABLES MALECHANGING AREA
MALECHANGING AREA
⎯ MALE CHANGING AREA SUPPORT SYSTEMS (BILL ROOF (SEP, SPF ….)
ROOF (SEP, SPF ….) ADDC
⎯ ROOF (SEP, SPF ….) NO 18.7) SERVICEBLOCK ROOF
LIFT (1 &2) SERVICEBLOCK ROOF REQUIREMENT
⎯ SERVICE BLOCK ROOF
JUDO HALL LIFT (1 &2)
⎯ LIFT (1 &2) JUDO HALL
⎯ JUDO HALL AND OTHERS AS PER ADDC
AND OTHERS AS PER ADDC
⎯ AND OTHERS AS PER ADDC
157 All Access Control IP Door Control Panels (3Nos) are ACCESS CONTROL SYSTEM TEL-1
missing and not provided nor Installed: (BILL NO 20.4) TEL-2
⎯ ACP – G01 TEL-3 INTERFACING
ACCESS CONTROL
⎯ ACP – G02
SYSTEM WITH THE
⎯ ACP – F01
FIRE ALARM
SYSTEM IS CIVIL
DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 57
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
158 Access Control System Workstation/Monitor not ACCESS CONTROL SYSTEM FIRE COMMAND ROOM
provided nor installed in Fire Command Room (BILL NO 20.4)
INTERFACING
ACCESS CONTROL
SYSTEM WITH THE
FIRE ALARM
SYSTEM IS CIVIL
DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 58
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
159 All Access control Field Equipment’s: ACCESS CONTROL SYSTEM ⎯ ELEC -1 & TEL-1 ROOMS
⎯ Card Readers (BILL NO 20.4) ENTRANCE -GF
⎯ Push Buttons
⎯ Break Glasses
⎯ Magnetic Locks
⎯ Door Contacts
are not provided not terminated nor fixed in ELEC -1 &
TEL-1
INTERFACING
ACCESS CONTROL
SYSTEM WITH THE
FIRE ALARM
SYSTEM IS CIVIL
DEFENSE
REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 59
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
160 All Access control Field Equipment’s: ACCESS CONTROL SYSTEM ⎯ IT ROOM -GF
⎯ Card Readers (BILL NO 20.4) INTERFACING
⎯ Push Buttons ACCESS CONTROL
⎯ Break Glasses SYSTEM WITH THE
⎯ Magnetic Locks FIRE ALARM
⎯ Door Contacts SYSTEM IS CIVIL
are not provided not terminated nor fixed in IT DEFENSE
ROOM -GF REQUIREMENT
161 All Access control Field Equipment’s: ACCESS CONTROL SYSTEM ⎯ MEDIA ROOM
⎯ Card Readers (BILL NO 20.4) INTERNAL ENTRANCE- INTERFACING
⎯ Push Buttons GF ACCESS CONTROL
⎯ Break Glasses SYSTEM WITH THE
⎯ Magnetic Locks FIRE ALARM
⎯ Door Contacts SYSTEM IS CIVIL
are not provided not terminated nor fixed in MEDIA DEFENSE
ROOM INTERNAL ENTRANCE-GF REQUIREMENT
162 All Access control Field Equipment’s: ACCESS CONTROL SYSTEM ⎯ STAIR -2 ENTRANCE -FF
⎯ Card Readers (BILL NO 20.4) INTERFACING
⎯ Push Buttons ACCESS CONTROL
⎯ Break Glasses SYSTEM WITH THE
⎯ Magnetic Locks FIRE ALARM
⎯ Door Contacts SYSTEM IS CIVIL
are not provided not terminated nor fixed in STAIR -2 DEFENSE
ENTRANCE -FF REQUIREMENT
163 All Access control Field Equipment’s: ACCESS CONTROL SYSTEM ⎯ VIP VESTIBULE -GF
⎯ Card Readers (BILL NO 20.4) (2NOS CARD READERS) INTERFACING
⎯ Push Buttons ACCESS CONTROL
⎯ Break Glasses SYSTEM WITH THE
⎯ Magnetic Locks FIRE ALARM
⎯ Door Contacts SYSTEM IS CIVIL
are not provided not terminated nor fixed in VIP DEFENSE
VESTIBULE -GF (2NOS CARD READERS) REQUIREMENT
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 60
LOCATION – AS PER
S. SYSTEM -AS PER PHOTOS – AS PER SITE
OUTSTANDING REMAINING WORK APPROVED SHOP REMARKS
NO. CONTRACT BOQ CONDITION
DRAWINGS
164 All Access control Field Equipment’s: ACCESS CONTROL SYSTEM ⎯ MAIN TELECOM ROOM
⎯ Card Readers (BILL NO 20.4) -GF INTERFACING
⎯ Push Buttons ACCESS CONTROL
⎯ Break Glasses SYSTEM WITH THE
⎯ Magnetic Locks FIRE ALARM
⎯ Door Contacts SYSTEM IS CIVIL
are not provided not terminated nor fixed in MAIN DEFENSE
TELECOM ROOM -GF REQUIREMENT
165 All Access control Field Equipment’s: ACCESS CONTROL SYSTEM ⎯ ELEC -2 & TEL-2 ROOM ⎯ ELEC -2 & TEL-2 ROOM
⎯ Card Readers (BILL NO 20.4) ENTRANCE -GF ENTRANCE -GF
⎯ Push Buttons ⎯ STAIR -2 EXIT DOOR – ⎯ STAIR -2 EXIT DOOR – GF
⎯ Break Glasses GF ⎯ MEETING ROOM
⎯ Magnetic Locks ⎯ MEETING ROOM CORRIDOR EXIT DOOR -GF
⎯ Door Contacts CORRIDOR EXIT DOOR - ⎯ EQUIPMENT STORAGE-GF
are not provided not terminated nor fixed in all GF ⎯ FIRE COMMAND ROOM-GF
building. ⎯ EQUIPMENT STORAGE- ⎯ OFFICES ENTRANCE -GF
GF ⎯ VIP RECEPTION CORRIDOR INTERFACING
⎯ FIRE COMMAND ⎯ SERVER ROOM -GF ACCESS CONTROL
ROOM-GF ⎯ MEDIA ROOM EXTERNAL SYSTEM WITH THE
⎯ OFFICES ENTRANCE -GF ENTRANCE -GF FIRE ALARM
⎯ VIP RECEPTION ⎯ STAIR -1 ENTRANCE -FF SYSTEM IS CIVIL
CORRIDOR ⎯ ELE -3 ROOM -FF DEFENSE
⎯ SERVER ROOM -GF ⎯ WASTE ROOM -FF REQUIREMENT
⎯ MEDIA ROOM ⎯ TEL-3 ROOM -FF
EXTERNAL ENTRANCE -
GF
⎯ STAIR -1 ENTRANCE -FF
⎯ ELE -3 ROOM -FF
⎯ WASTE ROOM -FF
⎯ TEL-3 ROOM -FF
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 61
PART 2. GENERAL NOTES:
• After reviewing Material Inspections & Delivery Notes, the following Materials are not yet delivered to site till date:
• Closeouts Documents (O&MM, Training, Warranties and Spare Parts and Asset Registers) are part of the Engineering Work to be done by Subcontractor.
• All work on site should be inspected officially (through WIR’s) and approved by the Engineer to be accountable.
• All Electrical Works on roof are not started yet.
• Nearly all final fixes and termination for most of the systems are not started yet.
• All NCR’s SOR’s should be cleared and closed by the Engineer for Electrical Works to be accountable.
• All Materials on site should be inspected officially (through MIR’s) and approved by the Engineer to be accountable.
• Electrical Authorities Approval and Authorities handing over are part of the Subcontractor scope of work.
• All Engineering work should be upgraded to status A to complete the Engineering scope of work.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 63
PART 3. ELECTRICAL WORK COMPLETION PERCENTAGE (SYSTEM WISE)
Emirates Federation of Wrestling and Judo BILL OF Bill No.
QUANTITIES
Plot P14, Sector Baniyas North 1 ELECTRICAL WORKS
Abu Dhabi, UAE 2/18
Item Ref. Item Description Quantity Unit Completion
Percentage
18.1.6 New route reservation is to be considered for future LV & HV network expansion 1 ITEM
18.1.7 Paying statutory ADDC charges for acquiring main supply including (Transformer, HV switch gear, Energy 1 ITEM
Meters) Rates and Insurance.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 64
18.2 DISEL GENERATOR
Supply, install, testing and commissioning of 400 KVA (at 50 degree C ambinet) 0.8 P.F., 400 Volts, Diesel 1 NOS 75%
Generators in accordance with technical specification complete with necessary accessories and anxillaries works
such as, but not limited to the following: Silencors, flexible joints, exhaust pipes, fuel tanks, fuel pipes, battery,
battery chargers, canvas make up duct, isolators, cercuit breaker, hand pumps, monitoring and protection
erection materials and special tools.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 65
18.6 Low Voltage Switchgear and Distribution Board
Supply, install, test, commission and maintain low voltage switchgear complete with all components as specified
and as shown on the drawings including all necessary works and fittings required for the complete installation
including all incoming and outgoing feeders and as per the ADDC regulations and requirements.
18.7.2 XLPE Insulated PVC sheathed - Armoured cables from main switch board to sub-main distribution boards as ITEM 10%
shown on the schematic diagram and as per the ADDC regulations and requirements.
18.7.3 XLPE Insulated FP400 Fire Rated Cables - Armoured cables for all life and safety equipments, as specified and ITEM 10%
shown on the electrical schematic diagram and other electrical drawings and as per the ADDC regulations and
requirements.
18.7.4 XLPE Insulated PVC sheathed - Armoured Cables from sub-main distribution boards to final DBs and other ITEM 10%
mechanical plant as specified and shown on drawings and as per the ADDC regulations and requirements.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 66
18.8 Small Power Wiring Accessories
Supply and install conduits, conduit fittings, junction boxes, PVC insuilated Wires, draw boxes from final
distribution board including all wires and connections for the following small power wiring accessories all as per
specfications , shown on drawings and ADDC requirments.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 67
18.9.2 Type - LF2 8 NOS
18.9.3 Type - LF3 15 NOS
18.9.4 Type - LF4 90 NOS
18.9.5 Type - LF5 144 NOS
18.9.6 Type - LF6 159 NOS
18.9.7 Type - LF7 106 NOS
18.9.8 Type - LF8 12 NOS
18.9.9 Type - LF9 31 NOS
18.9.10 Type - LF10 39 NOS
18.9.11 Type - LF11 1 ITEM
18.9.12 Type - LF12 117 NOS
18.9.13 Type - LF13 46 NOS
18.9.14 Type - LF14 244 NOS
Supply, install, test, commission lighting switches including all necessary accessories complete in accordance
with specifications, drawings and ADDC requirements.
18.11.2 allow for a dedicated Clean Earth System including Earthing Terminals, Cables, Rods and Earthing Pit for IT ITEM 10%
Equipment’s all as per drawings and to latest TRA Requirements.
18.12 Sundries
18.14.1 allow for Testing the whole Electrical installation at completion in the presence of the Engineer, repeat test as 50%
may be required and leave in perfect order and to the satisfaction of the engineer and Local Authority.
18.14.3 Allow for all Builder's work in connection with Electrical System's installation. ITEM
18.14.4 Allow for all submittals, samples, shop drawings, As-built Drawings, warranty certificates. ITEM 80%
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 69
The tenderer is required to detail below any additional items with quantities and rates, which he deems
necessary to arrive at the lump sum Tender Sum but the same is not included in this Section of Works. Should
the tenderer fail to provide any additional items herein, it will be considered that his lump sum price include for
all items shown on the Drawing and described in the Specification. Hence no subsequent claim for any
additional item will be accepted.
19.3.1 Voice Evacuation and Public Address master panel 1 ITEM 10%
19.3.2 Intelligent Power Amplifier Modular 1 ITEM 10%
19.3.3 Capacitive touch IP-based desktop voice alarm paging microphone 5 NOS 10%
19.3.4 6 watts Metal ceiling speaker with fire dome and ceramic termination 37 NOS 10%
19.3.5 6 watts Wall mount Cabinet speaker with ceramic termination 6 NOS 10%
19.3.6 Battery Backup 1 ITEM 10%
19.3.7 Equipment rack. 1 NOS 10%
19.3.8 AM/FM Tuner 1 ITEM 10%
19.3.9 Blu ray Player 1 ITEM 10%
Total - BILL No. 2/19:FIRE ALARM , FIRE TELEPHONE & PAVA SYSTEMS
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 71
19.4 FIRE TELEPHONE SYSTEM
Supply & install the following fire telephone system complete including pull boxes, conduit cable address and all
necessary fixing accessories all as shown in the drawings & specification for each.
19.5.1 2Cx1.5 sq.mm for fire alarm & fire telephone circuits 1 ITEM 75%
19.5.2 2Cx2.5 sq.mm for speakers circuits 1 ITEM 75%
19.6 Sundries
19.6.1 allow for Testing the whole installation at completion in the presence of the Engineer, repeat test as may be
required and leave in perfect order and to the satisfaction of the engineer and Local Authority.
19.6.4 Allow for required GI cable trays , GI Trunking and piping. 1 ITEM 85%
19.6.5 Allow for all submittals, samples, shop drawings, As-built Drawings, warranty certificates. 1 ITEM 80%
19.7 Additional Items
The tenderer is required to detail below any additional items with quantities and rates, which he deems
necessary to arrive at the lump sum Tender Sum but the same is not included in this Section of Works. Should
the tenderer fail to provide any additional items herein, it will be considered that his lump sum price include for
all items shown on the Drawing and described in the Specification. Hence no subsequent claim for any
additional item will be accepted.
Total - BILL No. 2/19: FIRE ALARM SYSTEMS
Carried to Summary of BILL No. 2 Bill No.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 72
Emirates Federation of Wrestling and Judo BILL OF 2/20
QUANTITIES
Plot P14, Sector Baniyas North 1 ELV SYSTEM Completion
Abu Dhabi, UAE Percentage
Item Ref. Item Description Quantity Unit
20.1.13 Allow for GSM Service Vertical & Horizontal cable trays as shown on drawings. 1 ITEM 75%
20.1.14 Allow for IT System Active component as per specifications and client requirements. 1 ITEM 0%
20.1.15 Allow for fiber optic cables as shown on drawings and to the latest TRA Requirements. 10%
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 73
Total - BILL No. 2/20: ELV SYSTEM
Carried to Summary of BILL No. 2 Bill No.
OUTSTANDING REMAINING ELECTRICAL WORL LIST EMIRATES FEDERATION OF WRESTLING AND JUDO 75
20.7 CENTRAL MONITORING SYSTEM
Supply, install, test, commission of all CMS system complete with all energy meters , water meters all
accessories , wiring , containment , workstations , etc. as per specification and according to Estidama RE-R2 and
PW-R2 Requirements.
20.7.1 Allow for data logger energy meters 1 ITEM 10%
20.7.2 Allow for data logger water meters 1 ITEM 10%
20.8 Sundries
20.8.1 allow for Testing the whole ELV Systems installation at completion in the presence of the Engineer, repeat test 1 ITEM
as may be required and leave in perfect order and to the satisfaction of the engineer and Local Authority.
END OF REPORT