Nafhat Al-Eman for trading and general contracting Ltd


Risk Assessment for UXO
WORK AREA: North and South Rumaila DATE OF ASSESSMENT:01/08/2022 Rev.A0

ACTIVITY DESCRIPTION: Civil Work

HAZARDS INITIAL RISK CONTROLS RESIDUAL RISK


Job Steps
Very Mediu
Persons At High Low Very Medi
DESCRIPTION Risk
CONSEQUENCES high m
CONTROLS & RECOVERY MEASURES REQUIRED
High
High
um
Low

• Land Release Certificate obtained


• Toxic Injuries / before work can commence.
death • Safe work area marked out with soft
• Vehicle damage barrier
• Unexploded ordinance • Material damage • Red & White sand bags in place to
ALL
2. UXO • Unidentified mine fields • Collapse of Excavation mark safe locations and unsafe warn
• Undefined roads and tracks of UXO danger zones.
• Harming the
environment • Only safe defined roads and tracks to
• Effect on work site be taken.
area Seek advice from security team if in
doubt

PREPARED BY: Mohammad Ali APPROVED BY: Bilal Abdullah


JOB TITLE: HSE Advisor JOB TITLE: HSE Manager

To Be applied by Site Supervisor:

Name: Ali Abdulzhra Signature: Date: 01/08/2022