You are on page 1of 6

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Medium Voltage Switchgear SATIP-P-116-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO

RECEIVING
1.0
INSPECTION

Storage, Handling, & Preservation Weekly inspection by the contractor QC.


Visual Inspection
1.1
Jobsite Acceptance and Space Heater
SATR-P-3806 SATR-P-3806 I S Space heater and/or condensation testing as needed in
Functional Testing accordance with manufacturer's instructions.

Material Receiving
1.2 Visual Inspection SAIC-P-3813 SAIC-P-3813 I W
MV Metal-Clad Switchgear

Material Receiving
1.3 Visual Inspection SAIC-P-3814 SAIC-P-3814 I W
MV SF6 Circuit Breaker

Material Receiving
Visual Inspection
1.4
Manually Operated Pad Mounted SF6
SAIC-P-3815 SAIC-P-3815 I W
Switchgear

Material Receiving
1.5 Visual Inspection SAIC-P-3817 SAIC-P-3817 I W
Vacuum Circuit Breaker - Feeder

Material Receiving
It shall be used in addition to SAIC-P-3817 if motors are
1.6 Visual Inspection SAIC-P-3816 SAIC-P-3816 I W connected directly to switchgear
Vacuum Circuit Breaker - Motor Load

MV Switchgear Accessories Notify SA PID by RFI on initial receipt of each listed


1.7
Visual Inspection
SAIC-P-3818 SAIC-P-3818 I W accessory (by type and/or manufacturer).

2.0 INSTALLATION

Page 1 of 6
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Medium Voltage Switchgear SATIP-P-116-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO

Indoor Pre-Installation
Hold point for substantial completion of building and
Visual Inspection-MV Metal Clad
2.1
Switchgear Installation and
SAIC-P-3003 SAIC-P-3003 H H electrical room civil / structural / architectural finish work
(i.e., no construction dust or fumes).
Precommissioning

SATIP-P-104-07 B/G Conduit


Outdoor Foundation
2.2
Visual Inspection
See Remarks See Remarks H H Hold point for completion of MV Switchgear B/G conduit
and slab/foundation.

MV Metal-Clad Switchgear
2.3 Installation & Identification SAIC-P-3819 SAIC-P-3819 H H Also see SATIP-P-111-01 Grounding and Bonding
Visual Inspection

MV SF6 Switchgear
2.4 Installation & Identification SAIC-P-3820 SAIC-P-3820 H H Also see SATIP-P-111-01 Grounding and Bonding
Visual Inspection

SATIP-P-104-05 A/G Conduit


SATIP-P-104-03 Cable Tray
Conduit, and/or Cable Tray
SATIP-P-104-07 B/G Conduit
2.5 Installation & Identification See Remarks See Remarks
SATIP-P-111-01 Grounding and Bonding
Visual Inspection
SATIP-P-116-10 Medium Voltage Cablebus (Maximum 15
kV)

SATIP-P-104-01 LV Cable and Wire


SATIP-J-902-01 Metallic Instrument Cable
Cable Pulling SATIP-P-116-10 Medium Voltage Cablebus (Maximum 15
2.6
Visual Inspection
SAIC-P-3214 SAIC-P-3214 H W kV) SATIP-
P-104-02 Medium Voltage Cable and Conductors (=35
kV)

SATIP-P-104-01 LV Cable and Wire


SATIP-J-902-01 Metallic Instrument Cable
Cable Gland Installation, SATIP-P-116-10 Medium Voltage Cablebus (Maximum 15
2.7 Cable Dressing, Identification, SAIC-P-3214 SAIC-P-3214 H W kV) SATIP-
& Termination Visual Inspection P-104-02 Medium Voltage Cable and Conductors (=35
kV)
SATIP-P-111-01 Grounding and Bonding

Page 2 of 6
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Medium Voltage Switchgear SATIP-P-116-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO

3.0 PRE-COMMISSIONING

SATIP-J-902-01 Metallic Instrument Cable


Cable Continuity, SATIP-P-116-10 Medium Voltage Cablebus (Maximum 15
Insulation Resistance, and kV)
3.1
Insulation Withstand Testing
SATR-P-3208 SATR-P-3208 I W SATIP-P-104-02 Medium Voltage Cable and Conductors
(Installed Cablebus or Cable) (=35 kV)See SATIP-P-104-01 LV Cable and Wire as
applicable

MV Switchgear
3.2 High-Potential SATR-P-3808 SATR-P-3808 I W In accordance with manufacturer's instructions.
Withstand Testing

SATIP-P-116-10 Medium Voltage Cablebus (Maximum 15


kV) SATIP-
Power Cable / Cablebus
3.3
Termination Torque Testing
SATR-P-3209 SATR-P-3209 I W P-104-02 Medium Voltage Cable and Conductors (=35
kV)See SATIP-P-104-01 LV Cable and Wire as
applicable

SF6 Circuit Breaker


3.4 Testing and Setting SATR-P-3809 SATR-P-3809 I W
for Energization Certificate

Vacuum Circuit Breaker - Motor Load


3.5 Testing and Setting SATR-P-3810 SATR-P-3810 I W
for Energization Certificate

Vacuum Circuit Breaker - Feeder


3.6 Testing and Setting SATR-P-3811 SATR-P-3811 I W
for Energization Certificate

Protection Relays
3.7 Testing and Setting SATR-P-3801 SATR-P-3801 I W
for Energization Certificate

Page 3 of 6
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Medium Voltage Switchgear SATIP-P-116-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO

MV Metal-Clad Switchgear
Pre-energization Functional Testing
3.8
and Visual Inspection
SAIC-P-3819 SAIC-P-3819 I W
for Energization Certificate

MV Metal-Clad Switchgear
Pre-energization Functional Testing
3.9
and Visual Inspection
SATR-P-3807 SATR-P-3807 I W
for Energization Certificate

MV SF6 Switchgear
Pre-energization Functional Testing
3.10
and Visual Inspection
SAIC-P-3820 SAIC-P-3820 I W
for Energization Certificate

MV SF6 Switchgear
Pre-energization Functional Testing
3.11
and Visual Inspection
SATR-P-3808 SATR-P-3808 I W
for Energization Certificate

MV Manual SF6 Circuit Breaker


Pre-energization Functional Testing
3.12
and Visual Inspection
SAIC-P-3821 SAIC-P-3821 I W
for Energization Certificate

MV Manual SF6 Circuit Breaker


Pre-energization Functional Testing
3.13
and Visual Inspection
SATR-P-3809 SATR-P-3809 I W
for Energization Certificate

MV Vacuum Circuit Breaker


Motor Load
3.14 Pre-energization Functional Testing SAIC-P-3822 SAIC-P-3822 I W
and Visual Inspection
for Energization Certificate

MV Vacuum Circuit Breaker


Motor Load
3.15 Pre-energization Functional Testing SATR-P-3810 SATR-P-3810 I W
and Visual Inspection
for Energization Certificate

Page 4 of 6
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Medium Voltage Switchgear SATIP-P-116-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO

MV Vacuum Circuit Breaker - Feeder


Pre-energization Functional Testing
3.16
and Visual Inspection
SAIC-P-3823 SAIC-P-3823 I W
for Energization Certificate

MV Vacuum Circuit Breaker - Feeder


Pre-energization Functional Testing
3.17
and Visual Inspection
SAIC-P-3811 SAIC-P-3811 I W
for Energization Certificate

Quality Document Review Energization


3.18
and Energization Certificate
EIL
Certificate
RH RH Review all Quality documents prior to energization

Energized MV Switchgear
3.19 Remote Control, Indication, See Remarks See Remarks H H See SATIP-J-900-01 Instrument loop checking
and Alarm Testing

Review FEIL and all associated Quality Records.


Energized Quality Document Review
3.20
and Mechanical Completion Certificate
FEIL PMCC/MCC RH RH
Hold point prior to certified completion of the MV system.

Page 5 of 6
03/09/2022 3:38 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - March 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Medium Voltage Switchgear SATIP-P-116-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD
SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

Switchgear accessories include storage cabinets, lifting devices, portable charging motor or hand crank (for stored-energy power C/Bs), test plugs, portable test kits for C/B trip units and protection relays,
6
overload relay heating elements, termination hardware, terminal blocks, cable and wire markers, CT's, PT's, CPT's, fuses, nameplates, and warning labels.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 6 of 6
03/09/2022 3:38 PM

You might also like