Professional Documents
Culture Documents
PROJECT:
NC-200 ERAWIN FIELD EPF PHASE- I (PLAN B)
A.Dinesh
Shanmugam
Digitally signed by
Ajaykumar Burade DN: cn=Venkatraman Shanmugam,
A.Dinesh Kumar
n o=Petrofac International,
This document is issued pursuant to an Agreement between Petrofac Facilities Management Limited and Zallaf Libya Exploration and Production Oil & Gas
Company which agreement sets forth the entire rights, obligations and liabilities of those parties with respect to the content and use of the report. Reliance by
any other party on the contents of the document shall be at its own risk. Petrofac makes no warranty or representation, expressed or implied, to any other party
with respect to the accuracy, completeness or usefulness of the information contained in this report and assumes no liabilities with respect to any other party’s
use of or damages resulting from such use of any information, conclusions or recommendations disclosed in this document.
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF JI-2047 ZALLAF ENG052-20ERW-000-
PHASE- I (PLAN B) QA-WQS-0010-000
HOLDS
Hold No. Section Description
ABBREVIATIONS
Abbreviation Description
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF JI-2047 ZALLAF ENG052-20ERW-000-
PHASE- I (PLAN B) QA-WQS-0010-000
CONTENTS
CONTENTS ........................................................................................................................................ 3
PROPOSED WELDING PROCEDURE SPECIFICATION FOR WELDING OF TIE-IN
( PWPS/TI/002)6”x9.525MM ………………………………………………………………………………… 4
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF JI-2047 ZALLAF ENG052-20ERW-000-
PHASE- I (PLAN B) QA-WQS-0010-000
JOINT DESIGN
9.525 mm
9.525mm
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF JI-2047 ZALLAF ENG052-20ERW-000-
PHASE- I (PLAN B) QA-WQS-0010-000
WELDING PARAMETERS
Bead Electrode Voltage Amper Polarity Technique Speed Average Heat input
Number Size and age
mm/min KJ/mm
type
Root E6010 (A 5.1) 17 ~ 34 TBR TBR
61 ~ 109 DCEP Stringer
Ø 2.5/3.2
Hot E7010(A 5.1) 18 ~ 30 74 ~ 103 TBR TBR
DCEP Weaving
Ø 3.2
Fill E7010(A 5.1) 22~32 76 ~ 103 TBR TBR
DCEP Weaving
Ø 3.2
Cap E7010(A 5.1) 22 ~ 32 74 ~ 107 DCEP Weaving TBR TBR
Ø 3.2/4.0
Notes:
1. Weaving shall not exceed 3 times electrode diameter.
2. Ensure machine and tools and tackles are calibrated and record welding machine type and make . The ranges for Arc Energy, Voltage and Amperage shall be
recorded during qualification.
3 Wind speed shelter shall be provided to protect weld area from high winds, rain, sand or dust, airborne moisture.
4 The field beveled surface shall be magnetic particle examined and adjacent material over a distance of at least 50mm shall be smooth, uniform, and free from
laminations, Scale, paint, grease and other foreign material that adversely affect weld quality before commencement of welding.
5. Number of runs on this WPS may vary from actual depending on the material thickness being welded and record during qualification. Wet or contaminated electrodes shall
not be used for welding.
6. External clamp shall not be removed after completion of 50% of root pass which shall be equi-spaced.
7. In case shift ends without joint completion, at least 4 passes must be deposited the joint shall be cooled in a slow and uniform manner and joint shall be preheated to the
required preheat temp on resumption of welding.
8. Cleaning and / or grinding during passes shall be done using Power Brushing, (Pneumatic)/ Grinding/ Chipping Hamer
9. Lowering shall be permitted after completion of joint until then shall be held by side booms and supported on sandbags with sufficient clearance between the pipe
and ground/trench
10. All electrodes batch tests shall be documented by an inspection certificate in accordance with EN 10204 Type 3.1
11. Arc strikes shall not be permitted outside the weld bevel
12.The working clearance around the pipe at the weld shall be as per requirement.
13. Each pipe shall be swabbed prior to alignment with pipeline, all sand, loose scale and foreign substances shall be removed from inside pipes
1. Visual Examination shall be as per ASME Section V, article 9 & Acceptance criteria shall
be as per 6.4 of API1104.
2. Non – Destructive Testing shall be radiography, ultrasonic and magnetic particle
examination on the completed joints only for PQR.
3. Tensile Test shall be as per clause 5.6.2, Figure 3 and Table 2 of API 1104.
4. Nick Break Test shall be as per clause 5.6.3, Figure 3 and Table 2 of API 1104.
5. Bend Test shall be as per clause 5.6.4, Figure 3 and Table 2 of API 1104.
6. Impact Test shall be as per clause 7.4 (d) of ENG052-20ERW-000-QA-SPC-0003-000 at 3
O’ Clock position.
7. Hardness and Macro shall be as clause 7.4 (e) & (f) of ENG052-20ERW-000-QA-SPC-
0003-000 at 6 O’ clock position.